ENVS10003 - A01 Final Logbook Submission
description
Transcript of ENVS10003 - A01 Final Logbook Submission
WEEK 1 – INTRODUCTION TO CONSTRUCTION
This week’s activity was primarily focused on the force of compression. To experiment with this force, towers were to be made out of timber blocks with the following limitations/challenges:
The tower was to be built as high as possible without collapsing. The number of timber blocks used was to be kept to a minimum. The tower had to be able to house a small plastic dog inside. This plastic dog was to be
placed inside AFTER the structure was finished. As part of the deconstruction process, timber blocks were to be removed from parts of the
structure without allowing it to fall. To address each of the limitations and challenges the tower had to have the following:
Sloping walls (To minimise usage of timber blocks) Gaps between block placement (To minimise usage of timber blocks and to allow blocks to
be removed at the end of the construction process) Accurate spacing between blocks (To prevent collapse) A wide opening (To accommodate the plastic dog)
STRUCTURE PLANNING:
Since the room floor acted as the base of the structure, the construction of the wall commenced immediately using the block placement planned earlier. It was decided that a gap large enough to fit the plastic dog would be on the side of the tower rather than the top to avoid the risk of knocking the tower over when placing the plastic dog inside. At first, the tower walls were constructed without a slope to make the lower portion as sturdy as possible. When the tower reached an approximate height of 20-30cm, the structure was made to slope in a fraction; about 1mm each level. This was done in an effort to reduce the number of blocks used. Unfortunately it was later observed that the slope strategy in fact did not reduce the number of blocks used. Furthermore, whilst constructing the tower it was found that the gaps between blocks towards the ends of the wall had to be closer together otherwise it was not possible to continue building the tower.
Adequate spacing between the placement of blocks to minimise block usage. If the spacing was too big, the blocks would fall through and if the spacing was too small then more blocks would have to be used. Also if the spacing was too small it would be harder to remove blocks later on.
No slopes currently in structure in order to create a stable lower wall.
Sloping initially put in place to reduce blocks used but as shown, there is no comparable difference to if it had non-sloping walls.
As the building got higher and the walls became more slanted, it was acknowledged that if the walls
were to continue to be built in the same manner, eventually the top of it would collapse due to the
gravitational force acting on it. Thus, it was decided that the building would start to slant the other
way to balance out the gravitational forces. Towards the end of the tutorial session, height became
the primary objective and since the tower seemed stable at the time, a vertically straight column of
blocks was added to address the challenge given at the beginning (Tower to be built as high as
possible without collapsing). As with all the other timber blocks, this vertical column is classified as a
live load (a load that is movable and typically acts downwards). In this structure, the vertical column
acts as the point load (A concentrated weight on a structural member).
Walls form a wave-like pattern to balance out the gravitational forces and prevent the tower from collapsing.
Live load: Forces
are acting
downw ards and
the load is able
to be removed.
Stable
Unstable
Once the tower was completed the plastic dog was placed inside easily. As for removing the blocks, it sounded like a difficult task but in fact was simple. At first, the blocks were removed carefully one by one and the structure did not collapse. To take it further, a person suggested taking ‘chunks’ of blocks out at a time and to the amazement of the surrounding people, the tower was still standing. This is due to the compression forces throughout the tower holding all the blocks together as if it were the work of masonry (Units such as bricks bound together to form a building).
Compression forces between blocks above and below keep the structure sturdy.
The blocks hanging out work on the same principle as the blocks at the edge of the walls previously addressed.
Key Terms: Load Path – The direction in which each consecutive load will pass through connected members. Masonry – Building blocks bounded together by mortar to form a structure. Compression – A flattening force. Reaction Force – A force that acts in the opposite direction to the action force. Point Load – A concentrated load on a structural member. Beam – A horizontal structural support member. Sources: FREE STANDING WALLS. Brick Development Association. (n.d.) Retrieved from http://www.brick.org.uk/resources/brick-industry/freestanding-walls/
Sticky tape made the balsa wood ‘column’ more rigid than if PVA glue was to be used.
Square base allows 4 balsa wood columns in each corner which will maximise the stability of the tower further up.
WEEK 2 – STRUCTURAL LOADS AND FORCES
This week’s activity was primarily focused on the structural frame of buildings. To analyse the nature and behaviour of frame construction as well as the structural joint, towers were to be made from balsa wood with the following limitations/challenges:
The tower was to be built high enough to reach the ceiling. There was a limited supply of balsa wood.
To save time, it was decided that a solid base would be made to hold long upright pieces of balsa wood acting as the columns of the tower. The base could be treated as a brace to the structure. Throughout the construction process uses of glue compared to masking tape were also taken into account. Once the tower was completed, the stresses of the building would be tested by attempting to make it collapse. STRUCTURE PLANNING:
Once the base and columns of the tower were placed together, a problem arose. Due to the length of the balsa wood column, the brace created earlier was not high enough to support it. Also, as the PVA glue was not strong enough to cement the column to the base, the columns would either fall inward or outward. With the time remaining it was decided that the tower would now form the shape of a pyramid and more balsa wood would be attached the top with sticky tape. It is evident from this experience that structural joints formed with sticky tape were much more firm than other parts that utilised PVA glue. Adding more bracing would have also allowed the balsa wood ‘columns’ to stand upright.
Bracing was not strong enough to hold the balsa wood in a vertical position and thus caused the ‘columns’ to tilt inwards or outwards (We decided to tilt it inwards for the purposes of adding more balsa wood on top).
Point Load
Load Path
The structural joints at the base, being mounted together by PVA glue meant that the tower collapsed immediately. The balsa wood ‘columns’ popped out of the ‘pockets’ in the bracing when pressure was applied to the top. The components on structures held by sticky tape did not break; instead they deformed through bending. However, as more and more pressure was applied from the top of the structure, the tower gave in and the structural joints broke because the material could not handle the load and stress applied.
‘Pockets’
Structural joints
bounded by sticky
tape allow more
stress to be
applied before
collapsing
compared to if PVA
glue was used.
Compression and tension forces
No deformation present as the bracing made this section of the tower rigid.
Key Terms: Structural Joint – Junction where building elements meet (no static load applied).2 Stability – The quality/ability of something to stay firmly fixed. Tension – A tight stretching force. Frame – Different structural members pieced together to form the support and shape. Bracing – Strengthening parts of structures with diagonal supporting member(s). Column – A rigid vertical support.
WEEK 3 – FOOTINGS AND FOUNDATIONS
During this week’s tutorial, we went on a tour of the University of Melbourne to identify the various structural systems and materials that we had learnt during the past few weeks. This tour allowed us to touch and see the physical aspects of structures that we had simply seen on paper and screen and thus, we were able to gain a deeper understanding of these parts. The areas we visited include:
- Lot 6 Café - Underground Car Park + South Lawn - Arts West Student Centre - Stairs on West end of Union House - North Court Union House - Beaurepaire Centre Pool - Oval Pavilion (under construction) - New Melbourne School of Design (under construction) - Old Geology South Lecture Theatre Entry Structure - Frank Tate Pavilion
LOT 6 CAFÉ:
Expansion joints are
utilised to allow
expansion and
contraction within the
wall due to
weathering/temperature
without cracking.
Perpend
Bed joint
Column
Despite the length of
the I-Beam that is
unsupported, the
flanges of it reduce
bending whilst the
webs prevent shearing.
Stretcher
OUTSIDE SIDNEY MYER ASIA CENTRE:
Beam used to
support roof
Structural
member acts as
column to
direct the load
from the beam
to the ground.
Strip footing
made of
concrete and
reinforced steel
supports load
of wall.
Timber beams
are used to
support the
timber decking
and load from
above.
OLD GEOLOGY SOUTH ENTRY:
Aluminium windows frames
The windows at the Old
Geology South Entrance are
fixed windows which consist
of frames and stationary
sashes.
Choice of aluminium frames
here could be due to the low
cost, light weight and
corrosion resistant feature.
MELBOURNE SCHOOL OF DESIGN:
Several columns can be
seen that support the
structure above and direct
loads to the ground
Small Cantilever
This section of the
structure work in
the same way as a
cantilever
Beams used to
support
‘cantilever’ section
of the building
Bracing strengthens
the beams and
assists them with
resisting
compression and
tension forces.
BEAUREPAIRE CENTRE POOL:
Although raked mortar
joints are aesthetically
pleasing, it makes bricks
more prone to damage
and water/moisture can
become stuck between
the bricks.
Mortar joints are
recessed (Raked joints).
Strip Footing
supports load of
wall and beam
Aluminium
windows frames
Oval Pavilion:
Cantilever
Aluminium windows
framesTimber door frames
ARTS WEST STUDENT CENTRE:
Column supporting beam
and structural members
above.
Beams used as part of
the design.Bracing used as part of
the design.
Key Terms: Moment – The tendency to make an object or a point rotate. Retaining Wall – A wall that resists pressure from soil and groundwater. Pad Footing – Type of footing that spreads a point load/vertical load over a wider area of ground (Also called Isolated Footing). Strip Footing – Type of footing (sometimes with reinforced steel) that spreads walls or a series of columns in a linear manner. Slab on ground – Concrete slab surface. Substructure – The foundation of the building which supports the superstructure. Bibliography: BORAL. (n.d.). Bricks and Pavers Technical Manual. Retrieved from http://www.boral.com.au/Images/common/clay_bricks_pavers/pdfs/1_209.pdf Old Virginia Brick (n.d.). Weatherproofing. Retrieved from http://www.oldvirginiabrick.com/technical/weatherproofing.html
WEEK 4 – FLOOR SYSTEMS AND HORIZONTAL ELEMENTS
Key Terms: Joist – Horizontal member that helps support the floor or ceiling. Steel Decking – Self-supporting flooring or roofing units consisting of steel. Span – The distance between 2 structural points. Girder – Iron or steel support beam Concrete Plank – Precast slab of concrete used in construction of floors of multi-level buildings. Spacing – The distance between repeating series of similar elements.
WEEK 5 – COLUMNS, GRIDS AND WALL SYSTEMS This week’s tutorial proved to be a more hands on task and it tested our understanding how different structural members worked. Each group was assgned a certain section of the Oval Pavilion to build to a smaller scale using balsa wood. To do this, we had to utilise the plans, sections details etc. in the Oval Pavilion construction documentation set in order to correctly resize the structure as well as have the right structural features so that it would hold.
Key Terms: Stud – The vertical framing member of a building’s wall. Nogging – Horizontal bracing members between wall studs or floor joists that make the wall or floor frame more rigid. Lintel – Horizontal structural member across top of door or window which supports weight of structure. Axial Load – A load that acts along the vertical axis of a member (straight down the middle). Buckling – Bending Seasoned Timber – Timber that is dried out which makes it more rigid/stable.
WEEK 6 – SPANNING AND ENCLOSING SPACE During this week’s tutorial, we had to listen to the Full Size presentations of other sites whilst taking note of details relevant to what we have been studying. The sites that were being presented include Kensington, Brunswick and Brunswick East.
Key Terms: Rafter – A sloping beam that supports the roof. Purlin – Horizontal member in roof that supports load from roof deck. Cantilever – A structure or structural member that is only supported at one end. Portal frame – Structures primarily made out of steel or steel-reinforced precast concrete where the columns and rafters are connected by moment-resisting connections (resistant to bending). Eave – Part of roof that overhangs wall of building. Alloy – A combination of 2 or more metals. Soffit – Underside of a structural component such as an eave. Top chord – Top beams in a truss.
WEEK 7 – DETAILING STRATEGIES 1
Key Terms: Drip – A strategy used to break surface tension by direction water away from underside of surface in window sills etc. Vapour Barrier – Material used to prevent steam from getting through walls. Gutter – The trough found under eaves that drain water from the roof. Parapet – A low protective wall at the edge of roof or an extension of it. Down Pipe – A pipe that caries rainwater from roof to a drain in the ground. Flashing – Impervious material that prevents passage of water into structure. Insulation – Material that reduces transfer of heat, electricity and sound. Sealant – Material used for sealing something to make it airtight or watertight.
WEEK 8 – STRATEGIES FOR OPENINGS
Key Terms: Windows Sash – Framed part of window that holds glass in place (Commonly: Part of window that moves). Deflection – Perpendicular distance a member deviates from its true course under transverse loading. Moment of Inertia – Geometric property that shows how the cross-sectional area of structural member is distributed and does not reflect physical properties of material. Door Furniture – Hand items affixed to a door (e.g. locks, handles etc.). Stress – A force that causes the structural member to bend and deform. Shear Force – A Force that causes structural members to deform in a sliding or skewing manner.
WEEK 9 – DETAILING STRATEGIES
Key Terms: Sandwich Panel – Type of flat panel that consists of 2 aluminium sheets bonded to a non-aluminium core (laminar material). Bending – Causing to curve/deform into an angular shape. Skirting – Covers joints between wall and floor. Composite Beam – Beams made of more than one material. Cornice – Decorative feature round the ceiling/wall of a room.
WEEK 10 – WHEN THINGS GO WRONG
Key Terms: Shear wall – Structural system composed of braced panels to resist lateral loads acting on structure. Soft Storey – Buildings that have openings wear a shear wall should be in place. Braced Frame – Structural frame designed to resist wind and earthquake (dynamic) loads Lifecycle – The extraction and processing of materials, manufacturing, recycling, final disposal etc. Defect – Flaw. Fascia – Flat piece of material covering ends of rafters or other fittings. Corrosion – Gradual destruction of material due to chemical reaction with environment. IEQ – Indoor Environmental Quality.
CONSTRUCTION WORKSHOP