Download - Ground Floor Works

Transcript

RR THULASI BUILDERS (I) PVT. LTD.Site: Bedford AcademyDate: 25.10.2014Ground floor Works1) West wing boys toilet tiles closet area and change of broken tiles.2) Primer coat for doors3) Providing thick silver hook instead of L clamp to lock door when it is open.( Remove L clamp)4) Polishing granite.5) Skirting work.6) Doors. Windows, ventilators fixing for east wing.7) Below centre block staircase cable trench work.8) East wing girls toilet- wall tile laying near lintel.