Prepared By
SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS)
MONTHLY PROGRESS REPORT
JULY, 2018
RAS OFFICERS’ INSTITUTE (CLUB HOUSE)
(2, institutional Area, Near Dainik Bhaskar, Jaipur)
Developers: M/S RAS Officers’ Institute
2, institutional Area, Near Dainik Bhaskar-Jaipur
Project Highlights
Total Built up Area: - 1, 20,000Sq.ft
Total Floor of Project: -2 Basement + 6 Floors
(Gym, Swimming pool, Banquet hall, Conference hall, Bar, Tennis& Squash)
Builders & Developers
M/S RAS Officers’ Institute,
Registered office at 2, institutional Area,
Near Dainik Bhaskar- Jaipur (Raj.)
Consultants & Management Team
Architectural Consultant Project Management Consultants
Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40, 4th Floor, Trinity Mall,
New Sanganer Road Sodala- Jaipur New Sanganer Road, Jaipur
Mr. Lokesh JoshiMob: 91-9680282624. Phone: 91-9314932438, 0141 5106606
Mr. Kulvinder Singh Mob: 91-9314480610
Structural Consultant MEP Consultant M/S SANRACHNA M/S Cube Consultant
S-41, AMBA BARI, JAIPUR A-8, Jamna Nagar Sodala- Jaipur
Mr. Sandeep Garg Mob: 91-9799496696 Mr. Sanjay Vajpayee Mob: 91-9214308430
Interior Designer Consultant M/S Sthapatya Architects A-58 Shanti path, Tilak Nagar, JAIPUR
Ms. Ritu Khandelwal Mob: 91-9829016773
Contractor Agencies
Civil Contractor Electrical Work Contractor
M/S H. R. Gwala M/S Vijay Electric service
F9/465, Chitrakoot, Vaishali Nagar-Jaipur VivekVihar, New Sanganer Road, Sodala.
Mr. H.R. Gwala Mob: 91-9783940001 Mr. Shyam Vijay Mob: 91-9783300501
Plumbing Contractor Waterproofing Contractor M/S Gayatri Plumbing M/S NS Solutions
B-50, Jawahar Nagar, Jaipur 3/77, Agarwal Farm, Mansarovar, Jaipur
Mr. Jeet Ram Mob: 91-9829008082 Mr. Shrikant Dandia Mob: 91-9214529486
Fire Fighting Contractor False Ceiling Contractor
M/S Men At Work M/s Shakuntalam Interiors Pvt. Ltd.
S-3, CD 304, Dadudayal Residency, 100-A, Civil Lines, Ajmer Road, Jaipur
Dadudayal Nagar, Mansarover, Jaipur. Mr. Sandeep Tholiya Mob: 91-9829059622
Mr. Ravi Kumawat Mob: 91-9928084922
Heating, ventilation, and air conditioning (HVAC)
Daikin Air conditioning India Pvt. Ltd (Higher Side)
S-10-11-12, Second Floor, Geejgarh Tower, Hawa Sadak
Jaipur,302006
M/s K.P. Airtech (Lower Side)
Yashoda Nikunj,BB-51, Jai Ambey Nagar, Tonk Road,
Jaipur – 203018, Rajasthan.
Mr. K.K. Sharma Mob: 91-9829063283
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
4 | P a g e
INDEX
S. No. Content Page. No.
(i) Executive Summary 5
(ii) Project View 5
(iii) Milestone Achieved: At Execution Level 6
(iv) Manpower & Material Status 6-8
(v) Proposed Schedule & Material Procurement Details 8-11
(vi) Drawing Status 12
(vii) Progress Photographs 13-16
(viii) Cube Test Report 17
(ix) Checklist & Pour Card 18-21
(x) Consultant Checking Record 22
(xi) Pending Decisions & Requirements 23
Distribution to:-
(i) RASO’I Members
(ii) Architect Design & Services (ADS)-Architectural Consultant
(iii) Sthapatya- Interior Designer
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
5 | P a g e
EXECUTIVE SUMMARY
Fifth floor roof slab shuttering,bar binding & casting completed.
Lower basement ramp slab casting completed.
Lower Basement Ramp R/W steel binding, shuttering & casting completed.
First Floor brick masonry work completed as per revision.
Fourth floor brick masonry work in progress.
Upper basement ramp slab 1st
lift casting completed.
Ground floor electrical wall conducting work in progress.
Sprinkler Line laying of First Floor.(scope of fire fighting work)
White Wash of second floor ceiling.
Fire Staircase Second Floor LVL. BB, Shuttring & Casting in progress.
PROJECT VIEW as on 31th
July’18
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
6 | P a g e
MILESTONES ACHIEVED
(i) At Execution Level:-
(i) Casting of Fifth Floor Roof Slab concreting (casting) completed.
(ii) Casting of Terrace Floor columns concreting (casting) 20% completed.
(iii) Brick Masonry of First Floor Completed as per revisions.
(iv) Casting of Ramp R/W & slab Completed up to upper basement.
(v) fire fighting (Sprinkler Line laying) work Started.
(Vi) Lower Basement Soling/Earth Filling Completed.
At Decision Level:-
(i) M/s Shakuntalam Interiors Pvt. Ltd. finalized for False Ceiling works.
MANPOWER DEPLOYED AT SITE STATUS
Total Manpower Deployed at Site by different Agencies / Vendors
Manpower Details Till 31st
July‘18
S. No. Name of Contractor Work Skilled Unskilled Total
1.0 H.R. Gwala Civil Work 62 340 402
1.1 SK Burman/ (H.R. Gwala) Shuttering 120 170 290
1.2 Govind/(H.R. Gwala) Bar Binding 180 250 430
1.3 Ashok/ (H.R. Gwala) Brick Work 140 197 337
1.4 Bharosi/ (H.R. Gwala) Plaster Work 8 16 24
2.0 Vijay Electrical Service Electrical 10 20 30
3.0 Gayatri Plumbing Plumbing 16 0 16
4.0 NS Solutions Waterproofing 0 0 0
5.0 Man At Work Fire Fighting 59 32 91
6.0 WhiteWash White Wash 45 55 100
Total 640 1080 1720
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
7 | P a g e
MATERIAL STATUS
A. Steel Received & Consumed Details in July ‘18
Diameter of Bar Received Till
Date (MT)
Received in
July 18 (MT)
Consumed in
July ’18 (MT)
Total
Consumed
till Date
(MT)
Balance at
Site as on
31.07.18 (MT)
8mm 85.68 - 3.64 80.48 5.20
10mm 206.97 5.457 12.95 196.97 10.00
12mm 94.43 11.61 8.60 88.43 6.00
16mm 50.89 - - 47.40 3.49
20mm 73.59 5.718 1.41 68.09 5.50
25mm 177.43 6.225 2.07 172.93 4.50
32mm 132.21 - - 132.21 0.00
Total (MT) 821.23 29.01 28.67 786.51 34.69
B. Cement Consumed & Received Details in month of July ’18
Location Received
Till Date
(Bags)
Received in
July ’18
(Bags)
Consumed
Till Date
(Bags)
Consumed
in July ’18
(Bags)
Balance at Site
as on 31.07.18
(Bags)
Remarks
At Site 31437 2460 30946 3309 491
At RMC
Plant
5792-
372=5420
0 5420 0 0 372 Bags Amount
adjusted in Vendor’s
Bill
Total (Bags) 36857 2460 36366 3309 491
C. Aggregate Consumed & Received Details in month of July’18
(i) 10mm Aggregate
Location Received
Till Date
(C.Ft)
Received
in July ’18
(C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
July ’18 (C.Ft) Balance at Site
as on 31.07.18
(C.Ft)
Remarks
At Site 46779 1520 45379 5684 1400
At RMC
Plant
11506 - 12271 - 0 Excess 765 C.ft Amount
adjusted in Vendor’s Bill
Total (C.Ft) 58285 1520 57650 5684 1400
(i) 20mm Aggregate
Location Received
Till Date
(C.Ft)
Received
in July ’18
(C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
July ’18 (C.Ft) Balance at Site
as on 31.07.18
(C.Ft)
Remarks
At Site 72970 2280 72070 9408 900
At RMC
Plant
17911 - 18130 - 0 Excess 219 C.ft Amount
adjusted in Vendor’s Bill
Total (C.Ft) 90881 2280 90200 9408 681
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
8 | P a g e
D. Sand Consumed & Received Details in month of July ’18
Location Received
Till Date
(C.Ft)
Received
in July ’18
(C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
July ’18 (C.Ft) Balance at Site
as on31.07.18
(C.Ft)
Remarks
At Site 90675 1968 89475 6987 1200
At RMC
Plant
18112 - 18100 - 0 12 C.ft Amount adjusted
in Vendor’s Bill
Total (C.Ft) 108787 1968 107575 6987 1200
E. Bricks Consumed & Received Details in month of July ’18
Location Received
Till Date
(Nos.)
Received in
July ’18 (Nos.) Consumed Till
Date (Nos.)
Consumed in
July (Nos.) Balance at Site
as on 31.07.18
(Nos.)
At Site 339000 75000 319000 68200 20000
Total (Nos.) 339000 75000 319000 68200 20000
PROPOSED SCHEDULES FOR THE MONTH OF AUGUST ‘18
Following activities are planned for the Month of August ‘18
(i) Completion of Terrace Floor Columns & Parapet wall shuttering, bar binding & concreting
(casting) work.
(ii) Completion of Mumty & O.H. Tank Slab shuttering, bar binding & casting work.
(iii) Fire Staircase up-to Fourth Floor Level bar binding, shuttering & Casting work.
(iv) Fourth & Fifth Floor brick work.
(v) Ramp (up to ground LVL.) shuttering, bar binding & concreting (casting) work.
(vi) Earth filling in surrounding areas of building.
(vii) Lower Basement & Ground Floor Plumbing Drainage & Toilets Internal Works.
(viii) Lower Basement PCC & Trimix Flooring Works.
(ix) Upper Basement to Second Floor Electrical Works.
(x) Ground & First Floor Sprinkler line laying (Fire Fighting).
(xi) Ground Floor HVAC Duct making & Installation.
(xii) Plantation of front side boundary wall.
(xiii) Boundary wall foundation & brick work.
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
9 | P a g e
STEEL & CEMENT REQUIREMENT FOR THE MONTH OF AUGUST ‘18
A. Steel Requirement Detail for the Month of August‘18
S. No. Location of Use Dia. Of Bars # Required
Quantity (MT)
Available at
Site (MT)
Net Required
Quantity (MT)
1.
O.H & U.G. water tanks &
Ramp Slab.
8mm 5.20 5.20 -
10mm 12.00 10.00 2.00
12mm 8.50 6.00 2.50
16mm 4.99 3.49 1.50
20mm 8.50 5.50 3.00
25mm 7.50 4.50 3.00
32mm - - -
Total Qty Required (MT) 46.69 MT 34.69 MT 12.00 MT
Note :- Requirement of Steel is based on approximation because reinforcement drawing of Ramp top slab & Tanks is not
available.
B. Cement Requirement Detail for the Month of August ‘18
(i) Cement (PPC) At site
S. No. Description of Work Qty. Unit Coefficient Quantity Reqd. (Bags)
1 PCC & RCC Work
(i) Ramp Slab Casting
(up to ground LVL.) 90 Cum 7.08 637
(ii) Terrace Floor Columns & O.H
Water Tanks & Mumti Slab 140 Cum 7.08 991
(iii) Brickwork of Fourth & Fifth Floor 180 cum 1.41 253
Total Required Bags of Cement for the Month of August’18 1881
Total Available Bags of Cement at Site 491
Net Required Bags of Cement for the Month of August’18 1390
Say 1800
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
10 | P a g e
C. Aggregate Requirement Detail for the Month of August ‘18
(i) 10mm Aggregate
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) Ramp Slab Casting
(up to ground LVL.) 90 Cum
11.515 1036
(ii) Terrace Floor Columns & O.H
Water Tanks & Mumti Slab 140 Cum
11.515 1612
(iii) Brickwork of Fourth & Fifth Floor 180 -
Total Required Qty of 10mm Aggregates for the Month of August’18 2648
Total Available Qty of 10mm Aggregate at Site 1400
Net Required Qty of 10mm Aggregate for the Month of August’18 1248
Say 2000
(ii) 20mm Aggregate
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) Ramp Slab Casting
(up to ground LVL.) 90 Cum
16.8 1512
(ii) Terrace Floor Columns & O.H
Water Tanks & Mumty Slab 140 Cum
16.8 2352
(iii) Brickwork of Fourth & Fifth Floor 180 - -
Total Required Qty of 20mm Aggregates for the Month of August’18 3864
Total Available Qty of 20mm Aggregate at Site 900
Net Required Qty of 20mm Aggregate for the Month of August’18 2964
Say 3000
A. Sand Requirement Detail for the Month of August ‘18
(i) Sand
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) Ramp Slab Casting
(up to ground LVL.) 90 Cum
17.30 1557
(ii) Terrace Floor Columns & O.H
Water Tanks & Mumty Slab 140 Cum
17.30 2422
(iii) Brickwork of Fourth & Fifth Floor 180 Cum 8.46 1522
Total Required Qty of Sand for the Month of August’18 5501
Total Available Qty of Sand at Site 1200
Net Required Qty of Sand for the Month of August’18 4301
Say 4500
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
11 | P a g e
A. Bricks Requirement Detail for the Month of August ‘18
S.No Description of Work Unit Qty Reqd.
(i) Fourth &Fifth Floor Brickwork. Nos. 90000
(ii) Boundary Wall Brickwork.(front Side) Nos. 22500
Total Required Qty. of Bricks for the Month of July ‘18 112500
Total Available Qty of Bricks at Site 20000
Net Required Qty of Bricks for the Month of July ‘18 92500
Say 100000
A. Weekly Material Procurement Schedule month of August’18
WEEKLY MATERIAL REQUIREMENT SCHEDULE FOR THE MONTH OF JULY ‘18
S.
NO.
MATERIAL
DESCRIPTION 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK
TOTAL
QUANTITY
Remarks
(if any)
1 Steel - - - 12.00 12 MT
2 Cement(PPC) - 900 900 - 1800 Bags
3 10mm Aggregate - 1400 600 - 2000 C.Ft
4 20mm Aggregate 1400 800 800 - 3000C.Ft
5 Sand 1000 1000 1500 1000 4500C.Ft
6 Bricks 20000 20000 20000 20000 100000 Nos.
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
12 | P a g e
DRAWING STATUS
Status of Drawings in the Month of July‘18
Following is the status of drawings in month of June from Architect Design & Services (ADS) by PMC
Engineer and issued to concerning Contractors at site.
S.No Date of
Received Drawing Title Drawing No.
Rev.
No. Remark
1 - Fifth Floor Working Plan - - Not Received
2 - Terrace Floor Working Plan - - Not Received
3 02.07.2018 Boundary wall Detail 176/RASC/GPP/09/BW 01 Received
4 12.07.2018 Internal Plumbing Layout
(Ground Floor to Fifth Floor) - -
Received
5 14.07.2018 Boundary wall Detail 176/RASC/GPP/09/BW 02 Received
6 28.07.2018 Boundary wall Detail
D/Exterior/RASCLUB/
Ground Floor Plan -
Received
7 28.07.2018 O.H. Water Tank Section Details - - Received
8 28.07.2018 O.H. Water Tank Section Details - - Received
9 28.07.2018 Ground First &Fourth Floor Shaft and
Trap door location - -
Received
10 - Revised plumbing SLD - - Not Received
11 - Revised drainage SLD - - Not Received
12 -
Electrical working plan (Third to Fifth Floor)
- - Not Received
13 - Building Elevation Plans (Final) - - Not Received
14 -
False Ceiling Plans (Lower to Fifth Floor) with Section & Sectional Details.
- - Not Received
15 - Landscaping Final Layout - - Not Received
16 - Revised Door-Window Schedule - - Not Received
17 -
Revised MEP Plan (HVAC,Fire Fighting System)
- - Not Received
List of Drawings Required in August ’18
Following Drawings are required at site in the Month of August ’18
S. No. Drawing Title Date of Requirement
on OR Before
1 Fifth Floor Working Plan 01.07.2018
2 Terrace Floor Working Plan 01.07.2018
3 O.H. Water Tank Top Slab Shuttering plans 10.07.2018
4 O.H. Water Tank Top Slab Roof & Beam detail 01.07.2018
5 Revised plumbing SLD 01.07.2018
6 Revised drainage SLD 01.07.2018
7 Electrical working plan (Third to Fifth Floor) 05.07.2018
8 Building Elevation Plans (Final) 10.07.2018
9 Revised Door-Window Schedule 04.07.2018
10 Revised MEP Plan (HVAC, Fire Fighting System) 14.07.2018
11 False Ceiling Plans (Lower to Fifth Floor) with Section & Sectional Details.
10.07.2018
12 Landscaping Final Layout 10.07.2018
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
13 | P a g e
PROGRESS PHOTOGRAPHS
Site View 31th
July’18
Fifth Floor Roof Slab Checking on 04 July’18,
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
14 | P a g e
False Ceiling Pre-bid at site 20.07.2018
Site Meeting for discussion and selection of Sanitary,CP Fittings, Toilet wall tiles and Flooring material.
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
15 | P a g e
Project Review meeting at Site on every Thursday with all vendors and consultants.
26.07.2018
Meeting at DLB on 27.07.2018
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
16 | P a g e
Slump Test at Site
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
17 | P a g e
Cube Test Report for the month of July, 2018
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
18 | P a g e
Check List Month of July-2018
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
19 | P a g e
Check List Month of July-2018
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
20 | P a g e
Pour Card for the month of July, 2018
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
21 | P a g e
Pour Card for the month of July, 2018
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
22 | P a g e
Checking Record by Architect & Structure Consultants
RAS Officers Institute (Club House) Monthly Progress Report July ‘18
23 | P a g e
MAJOR PENDING DECISIONS & REQUIREMENTS AT SITE
Some other decisions pending at site are as follows:-
(i) Plumbing Material Vendors to be finalized for procurement.
(ii) Elevator (Lift) Vendor to be finalized.
(iii) Swimming pool Vendor to be finalized.
(iv) Flooring & Wall Tiles Make & Pattern to be finalized.
(v) Cp & Ceramic fittings to be finalized for Toilets.
Signature Signature
Mr. Vipin Pachlangia Mr. Kulvinder Singh
(Project Head) (PMC Head)