Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT JULY, 2018 RAS OFFICERS’ INSTITUTE (CLUB HOUSE) (2, institutional Area, Near Dainik Bhaskar, Jaipur) Developers: M/S RAS Officers’ Institute 2, institutional Area, Near Dainik Bhaskar-Jaipur

Transcript of MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix)...

Page 1: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

Prepared By

SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS)

MONTHLY PROGRESS REPORT

JULY, 2018

RAS OFFICERS’ INSTITUTE (CLUB HOUSE)

(2, institutional Area, Near Dainik Bhaskar, Jaipur)

Developers: M/S RAS Officers’ Institute

2, institutional Area, Near Dainik Bhaskar-Jaipur

Page 2: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

Project Highlights

Total Built up Area: - 1, 20,000Sq.ft

Total Floor of Project: -2 Basement + 6 Floors

(Gym, Swimming pool, Banquet hall, Conference hall, Bar, Tennis& Squash)

Builders & Developers

M/S RAS Officers’ Institute,

Registered office at 2, institutional Area,

Near Dainik Bhaskar- Jaipur (Raj.)

Consultants & Management Team

Architectural Consultant Project Management Consultants

Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40, 4th Floor, Trinity Mall,

New Sanganer Road Sodala- Jaipur New Sanganer Road, Jaipur

Mr. Lokesh JoshiMob: 91-9680282624. Phone: 91-9314932438, 0141 5106606

Mr. Kulvinder Singh Mob: 91-9314480610

Structural Consultant MEP Consultant M/S SANRACHNA M/S Cube Consultant

S-41, AMBA BARI, JAIPUR A-8, Jamna Nagar Sodala- Jaipur

Mr. Sandeep Garg Mob: 91-9799496696 Mr. Sanjay Vajpayee Mob: 91-9214308430

Interior Designer Consultant M/S Sthapatya Architects A-58 Shanti path, Tilak Nagar, JAIPUR

Ms. Ritu Khandelwal Mob: 91-9829016773

Page 3: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

Contractor Agencies

Civil Contractor Electrical Work Contractor

M/S H. R. Gwala M/S Vijay Electric service

F9/465, Chitrakoot, Vaishali Nagar-Jaipur VivekVihar, New Sanganer Road, Sodala.

Mr. H.R. Gwala Mob: 91-9783940001 Mr. Shyam Vijay Mob: 91-9783300501

Plumbing Contractor Waterproofing Contractor M/S Gayatri Plumbing M/S NS Solutions

B-50, Jawahar Nagar, Jaipur 3/77, Agarwal Farm, Mansarovar, Jaipur

Mr. Jeet Ram Mob: 91-9829008082 Mr. Shrikant Dandia Mob: 91-9214529486

Fire Fighting Contractor False Ceiling Contractor

M/S Men At Work M/s Shakuntalam Interiors Pvt. Ltd.

S-3, CD 304, Dadudayal Residency, 100-A, Civil Lines, Ajmer Road, Jaipur

Dadudayal Nagar, Mansarover, Jaipur. Mr. Sandeep Tholiya Mob: 91-9829059622

Mr. Ravi Kumawat Mob: 91-9928084922

Heating, ventilation, and air conditioning (HVAC)

Daikin Air conditioning India Pvt. Ltd (Higher Side)

S-10-11-12, Second Floor, Geejgarh Tower, Hawa Sadak

Jaipur,302006

M/s K.P. Airtech (Lower Side)

Yashoda Nikunj,BB-51, Jai Ambey Nagar, Tonk Road,

Jaipur – 203018, Rajasthan.

Mr. K.K. Sharma Mob: 91-9829063283

Page 4: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

4 | P a g e

INDEX

S. No. Content Page. No.

(i) Executive Summary 5

(ii) Project View 5

(iii) Milestone Achieved: At Execution Level 6

(iv) Manpower & Material Status 6-8

(v) Proposed Schedule & Material Procurement Details 8-11

(vi) Drawing Status 12

(vii) Progress Photographs 13-16

(viii) Cube Test Report 17

(ix) Checklist & Pour Card 18-21

(x) Consultant Checking Record 22

(xi) Pending Decisions & Requirements 23

Distribution to:-

(i) RASO’I Members

(ii) Architect Design & Services (ADS)-Architectural Consultant

(iii) Sthapatya- Interior Designer

Page 5: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

5 | P a g e

EXECUTIVE SUMMARY

Fifth floor roof slab shuttering,bar binding & casting completed.

Lower basement ramp slab casting completed.

Lower Basement Ramp R/W steel binding, shuttering & casting completed.

First Floor brick masonry work completed as per revision.

Fourth floor brick masonry work in progress.

Upper basement ramp slab 1st

lift casting completed.

Ground floor electrical wall conducting work in progress.

Sprinkler Line laying of First Floor.(scope of fire fighting work)

White Wash of second floor ceiling.

Fire Staircase Second Floor LVL. BB, Shuttring & Casting in progress.

PROJECT VIEW as on 31th

July’18

Page 6: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

6 | P a g e

MILESTONES ACHIEVED

(i) At Execution Level:-

(i) Casting of Fifth Floor Roof Slab concreting (casting) completed.

(ii) Casting of Terrace Floor columns concreting (casting) 20% completed.

(iii) Brick Masonry of First Floor Completed as per revisions.

(iv) Casting of Ramp R/W & slab Completed up to upper basement.

(v) fire fighting (Sprinkler Line laying) work Started.

(Vi) Lower Basement Soling/Earth Filling Completed.

At Decision Level:-

(i) M/s Shakuntalam Interiors Pvt. Ltd. finalized for False Ceiling works.

MANPOWER DEPLOYED AT SITE STATUS

Total Manpower Deployed at Site by different Agencies / Vendors

Manpower Details Till 31st

July‘18

S. No. Name of Contractor Work Skilled Unskilled Total

1.0 H.R. Gwala Civil Work 62 340 402

1.1 SK Burman/ (H.R. Gwala) Shuttering 120 170 290

1.2 Govind/(H.R. Gwala) Bar Binding 180 250 430

1.3 Ashok/ (H.R. Gwala) Brick Work 140 197 337

1.4 Bharosi/ (H.R. Gwala) Plaster Work 8 16 24

2.0 Vijay Electrical Service Electrical 10 20 30

3.0 Gayatri Plumbing Plumbing 16 0 16

4.0 NS Solutions Waterproofing 0 0 0

5.0 Man At Work Fire Fighting 59 32 91

6.0 WhiteWash White Wash 45 55 100

Total 640 1080 1720

Page 7: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

7 | P a g e

MATERIAL STATUS

A. Steel Received & Consumed Details in July ‘18

Diameter of Bar Received Till

Date (MT)

Received in

July 18 (MT)

Consumed in

July ’18 (MT)

Total

Consumed

till Date

(MT)

Balance at

Site as on

31.07.18 (MT)

8mm 85.68 - 3.64 80.48 5.20

10mm 206.97 5.457 12.95 196.97 10.00

12mm 94.43 11.61 8.60 88.43 6.00

16mm 50.89 - - 47.40 3.49

20mm 73.59 5.718 1.41 68.09 5.50

25mm 177.43 6.225 2.07 172.93 4.50

32mm 132.21 - - 132.21 0.00

Total (MT) 821.23 29.01 28.67 786.51 34.69

B. Cement Consumed & Received Details in month of July ’18

Location Received

Till Date

(Bags)

Received in

July ’18

(Bags)

Consumed

Till Date

(Bags)

Consumed

in July ’18

(Bags)

Balance at Site

as on 31.07.18

(Bags)

Remarks

At Site 31437 2460 30946 3309 491

At RMC

Plant

5792-

372=5420

0 5420 0 0 372 Bags Amount

adjusted in Vendor’s

Bill

Total (Bags) 36857 2460 36366 3309 491

C. Aggregate Consumed & Received Details in month of July’18

(i) 10mm Aggregate

Location Received

Till Date

(C.Ft)

Received

in July ’18

(C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

July ’18 (C.Ft) Balance at Site

as on 31.07.18

(C.Ft)

Remarks

At Site 46779 1520 45379 5684 1400

At RMC

Plant

11506 - 12271 - 0 Excess 765 C.ft Amount

adjusted in Vendor’s Bill

Total (C.Ft) 58285 1520 57650 5684 1400

(i) 20mm Aggregate

Location Received

Till Date

(C.Ft)

Received

in July ’18

(C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

July ’18 (C.Ft) Balance at Site

as on 31.07.18

(C.Ft)

Remarks

At Site 72970 2280 72070 9408 900

At RMC

Plant

17911 - 18130 - 0 Excess 219 C.ft Amount

adjusted in Vendor’s Bill

Total (C.Ft) 90881 2280 90200 9408 681

Page 8: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

8 | P a g e

D. Sand Consumed & Received Details in month of July ’18

Location Received

Till Date

(C.Ft)

Received

in July ’18

(C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

July ’18 (C.Ft) Balance at Site

as on31.07.18

(C.Ft)

Remarks

At Site 90675 1968 89475 6987 1200

At RMC

Plant

18112 - 18100 - 0 12 C.ft Amount adjusted

in Vendor’s Bill

Total (C.Ft) 108787 1968 107575 6987 1200

E. Bricks Consumed & Received Details in month of July ’18

Location Received

Till Date

(Nos.)

Received in

July ’18 (Nos.) Consumed Till

Date (Nos.)

Consumed in

July (Nos.) Balance at Site

as on 31.07.18

(Nos.)

At Site 339000 75000 319000 68200 20000

Total (Nos.) 339000 75000 319000 68200 20000

PROPOSED SCHEDULES FOR THE MONTH OF AUGUST ‘18

Following activities are planned for the Month of August ‘18

(i) Completion of Terrace Floor Columns & Parapet wall shuttering, bar binding & concreting

(casting) work.

(ii) Completion of Mumty & O.H. Tank Slab shuttering, bar binding & casting work.

(iii) Fire Staircase up-to Fourth Floor Level bar binding, shuttering & Casting work.

(iv) Fourth & Fifth Floor brick work.

(v) Ramp (up to ground LVL.) shuttering, bar binding & concreting (casting) work.

(vi) Earth filling in surrounding areas of building.

(vii) Lower Basement & Ground Floor Plumbing Drainage & Toilets Internal Works.

(viii) Lower Basement PCC & Trimix Flooring Works.

(ix) Upper Basement to Second Floor Electrical Works.

(x) Ground & First Floor Sprinkler line laying (Fire Fighting).

(xi) Ground Floor HVAC Duct making & Installation.

(xii) Plantation of front side boundary wall.

(xiii) Boundary wall foundation & brick work.

Page 9: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

9 | P a g e

STEEL & CEMENT REQUIREMENT FOR THE MONTH OF AUGUST ‘18

A. Steel Requirement Detail for the Month of August‘18

S. No. Location of Use Dia. Of Bars # Required

Quantity (MT)

Available at

Site (MT)

Net Required

Quantity (MT)

1.

O.H & U.G. water tanks &

Ramp Slab.

8mm 5.20 5.20 -

10mm 12.00 10.00 2.00

12mm 8.50 6.00 2.50

16mm 4.99 3.49 1.50

20mm 8.50 5.50 3.00

25mm 7.50 4.50 3.00

32mm - - -

Total Qty Required (MT) 46.69 MT 34.69 MT 12.00 MT

Note :- Requirement of Steel is based on approximation because reinforcement drawing of Ramp top slab & Tanks is not

available.

B. Cement Requirement Detail for the Month of August ‘18

(i) Cement (PPC) At site

S. No. Description of Work Qty. Unit Coefficient Quantity Reqd. (Bags)

1 PCC & RCC Work

(i) Ramp Slab Casting

(up to ground LVL.) 90 Cum 7.08 637

(ii) Terrace Floor Columns & O.H

Water Tanks & Mumti Slab 140 Cum 7.08 991

(iii) Brickwork of Fourth & Fifth Floor 180 cum 1.41 253

Total Required Bags of Cement for the Month of August’18 1881

Total Available Bags of Cement at Site 491

Net Required Bags of Cement for the Month of August’18 1390

Say 1800

Page 10: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

10 | P a g e

C. Aggregate Requirement Detail for the Month of August ‘18

(i) 10mm Aggregate

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) Ramp Slab Casting

(up to ground LVL.) 90 Cum

11.515 1036

(ii) Terrace Floor Columns & O.H

Water Tanks & Mumti Slab 140 Cum

11.515 1612

(iii) Brickwork of Fourth & Fifth Floor 180 -

Total Required Qty of 10mm Aggregates for the Month of August’18 2648

Total Available Qty of 10mm Aggregate at Site 1400

Net Required Qty of 10mm Aggregate for the Month of August’18 1248

Say 2000

(ii) 20mm Aggregate

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) Ramp Slab Casting

(up to ground LVL.) 90 Cum

16.8 1512

(ii) Terrace Floor Columns & O.H

Water Tanks & Mumty Slab 140 Cum

16.8 2352

(iii) Brickwork of Fourth & Fifth Floor 180 - -

Total Required Qty of 20mm Aggregates for the Month of August’18 3864

Total Available Qty of 20mm Aggregate at Site 900

Net Required Qty of 20mm Aggregate for the Month of August’18 2964

Say 3000

A. Sand Requirement Detail for the Month of August ‘18

(i) Sand

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) Ramp Slab Casting

(up to ground LVL.) 90 Cum

17.30 1557

(ii) Terrace Floor Columns & O.H

Water Tanks & Mumty Slab 140 Cum

17.30 2422

(iii) Brickwork of Fourth & Fifth Floor 180 Cum 8.46 1522

Total Required Qty of Sand for the Month of August’18 5501

Total Available Qty of Sand at Site 1200

Net Required Qty of Sand for the Month of August’18 4301

Say 4500

Page 11: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

11 | P a g e

A. Bricks Requirement Detail for the Month of August ‘18

S.No Description of Work Unit Qty Reqd.

(i) Fourth &Fifth Floor Brickwork. Nos. 90000

(ii) Boundary Wall Brickwork.(front Side) Nos. 22500

Total Required Qty. of Bricks for the Month of July ‘18 112500

Total Available Qty of Bricks at Site 20000

Net Required Qty of Bricks for the Month of July ‘18 92500

Say 100000

A. Weekly Material Procurement Schedule month of August’18

WEEKLY MATERIAL REQUIREMENT SCHEDULE FOR THE MONTH OF JULY ‘18

S.

NO.

MATERIAL

DESCRIPTION 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK

TOTAL

QUANTITY

Remarks

(if any)

1 Steel - - - 12.00 12 MT

2 Cement(PPC) - 900 900 - 1800 Bags

3 10mm Aggregate - 1400 600 - 2000 C.Ft

4 20mm Aggregate 1400 800 800 - 3000C.Ft

5 Sand 1000 1000 1500 1000 4500C.Ft

6 Bricks 20000 20000 20000 20000 100000 Nos.

Page 12: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

12 | P a g e

DRAWING STATUS

Status of Drawings in the Month of July‘18

Following is the status of drawings in month of June from Architect Design & Services (ADS) by PMC

Engineer and issued to concerning Contractors at site.

S.No Date of

Received Drawing Title Drawing No.

Rev.

No. Remark

1 - Fifth Floor Working Plan - - Not Received

2 - Terrace Floor Working Plan - - Not Received

3 02.07.2018 Boundary wall Detail 176/RASC/GPP/09/BW 01 Received

4 12.07.2018 Internal Plumbing Layout

(Ground Floor to Fifth Floor) - -

Received

5 14.07.2018 Boundary wall Detail 176/RASC/GPP/09/BW 02 Received

6 28.07.2018 Boundary wall Detail

D/Exterior/RASCLUB/

Ground Floor Plan -

Received

7 28.07.2018 O.H. Water Tank Section Details - - Received

8 28.07.2018 O.H. Water Tank Section Details - - Received

9 28.07.2018 Ground First &Fourth Floor Shaft and

Trap door location - -

Received

10 - Revised plumbing SLD - - Not Received

11 - Revised drainage SLD - - Not Received

12 -

Electrical working plan (Third to Fifth Floor)

- - Not Received

13 - Building Elevation Plans (Final) - - Not Received

14 -

False Ceiling Plans (Lower to Fifth Floor) with Section & Sectional Details.

- - Not Received

15 - Landscaping Final Layout - - Not Received

16 - Revised Door-Window Schedule - - Not Received

17 -

Revised MEP Plan (HVAC,Fire Fighting System)

- - Not Received

List of Drawings Required in August ’18

Following Drawings are required at site in the Month of August ’18

S. No. Drawing Title Date of Requirement

on OR Before

1 Fifth Floor Working Plan 01.07.2018

2 Terrace Floor Working Plan 01.07.2018

3 O.H. Water Tank Top Slab Shuttering plans 10.07.2018

4 O.H. Water Tank Top Slab Roof & Beam detail 01.07.2018

5 Revised plumbing SLD 01.07.2018

6 Revised drainage SLD 01.07.2018

7 Electrical working plan (Third to Fifth Floor) 05.07.2018

8 Building Elevation Plans (Final) 10.07.2018

9 Revised Door-Window Schedule 04.07.2018

10 Revised MEP Plan (HVAC, Fire Fighting System) 14.07.2018

11 False Ceiling Plans (Lower to Fifth Floor) with Section & Sectional Details.

10.07.2018

12 Landscaping Final Layout 10.07.2018

Page 13: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

13 | P a g e

PROGRESS PHOTOGRAPHS

Site View 31th

July’18

Fifth Floor Roof Slab Checking on 04 July’18,

Page 14: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

14 | P a g e

False Ceiling Pre-bid at site 20.07.2018

Site Meeting for discussion and selection of Sanitary,CP Fittings, Toilet wall tiles and Flooring material.

Page 15: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

15 | P a g e

Project Review meeting at Site on every Thursday with all vendors and consultants.

26.07.2018

Meeting at DLB on 27.07.2018

Page 16: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

16 | P a g e

Slump Test at Site

Page 17: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

17 | P a g e

Cube Test Report for the month of July, 2018

Page 18: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

18 | P a g e

Check List Month of July-2018

Page 19: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

19 | P a g e

Check List Month of July-2018

Page 20: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

20 | P a g e

Pour Card for the month of July, 2018

Page 21: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

21 | P a g e

Pour Card for the month of July, 2018

Page 22: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

22 | P a g e

Checking Record by Architect & Structure Consultants

Page 23: MONTHLY PROGRESS REPORT JULY, 2018 - … · (viii) Lower Basement PCC & Trimix Flooring Works. (ix) Upper Basement to Second Floor Electrical Works. (x) Ground & First Floor Sprinkler

RAS Officers Institute (Club House) Monthly Progress Report July ‘18

23 | P a g e

MAJOR PENDING DECISIONS & REQUIREMENTS AT SITE

Some other decisions pending at site are as follows:-

(i) Plumbing Material Vendors to be finalized for procurement.

(ii) Elevator (Lift) Vendor to be finalized.

(iii) Swimming pool Vendor to be finalized.

(iv) Flooring & Wall Tiles Make & Pattern to be finalized.

(v) Cp & Ceramic fittings to be finalized for Toilets.

Signature Signature

Mr. Vipin Pachlangia Mr. Kulvinder Singh

(Project Head) (PMC Head)

Mobile: 91-9929312666 Mobile: 91-9314480610