TEIAS TURKEY ELECTRICITY TRANSMISSION CORPORATION GENERAL DIRECTORATE 380 kV MALTEPE GIS SUBSTATION- KARTAL GIS SUBSTATION (GAS INSULATED SYSTEM SUBSTATION) UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN (İSTANBUL PROVINCE, MALTEPE, PENDİK & KARTAL COUNTIES) ANKARA – JUNE 2010

Transcript of TEIAS TURKEY ELECTRICITY TRANSMISSION … · 10. teias ... 380 kv maltepe gis -kartal gis...

TEIAS

TURKEY ELECTRICITY TRANSMISSION CORPORATION

GENERAL DIRECTORATE

380 kV MALTEPE GIS SUBSTATION-KARTAL GIS SUBSTATION

(GAS INSULATED SYSTEM SUBSTATION) UNDERGROUND CABLE

ENVIRONMENTAL MANAGEMENT PLAN

(İSTANBUL PROVINCE, MALTEPE, PENDİK & KARTAL COUNTIES)

ANKARA – JUNE 2010

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

380 kV MALTEPE GIS SUBSTATION-KARTAL GIS SUBSTATION

UNDERGROUND CABLE

ENVIRONMENTAL MANAGEMENT PLAN

Project Owner Turkey Electricity Transmission Co. General Directorate

Address Inonu Boulevard No:27 Bahcelievler 06490, Ankara

Telephone +90 (312) 203 86 11

Fax no +90 (312) 203 87 17

Project name 380 kV Maltepe GIS Substation-Kartal GIS Substation Underground Cable

Location of Project Site Istanbul Province, Maltepe, Pendik and Kartal Counties

2

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

TABLE OF CONTENT

Table of Content..................................................................................................................3 Table List.............................................................................................................................4 Figure List ...........................................................................................................................5 Appendix List ......................................................................................................................6

1. PROJECT DESCRIPTION

1.1. General Description......................................................................................................8 1.2. Purpose of Project ........................................................................................................8 1.4. Project Area..................................................................................................................11 2. MITIGATION PLAN ...................................................................................................14 3. MONITORING PLAN .................................................................................................18 4. INSTITUTIONAL ARRANGEMENTS .....................................................................28 5. CONSULTATION WITH PROJECT AFFECTED GROUPS AND NON-GOVERMNENTAL ORGANIZATIONS (NGO’s).......................................................32

APPENDICES

PROJECT TEAM PREPARING THE REPORT

3

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

TABLE LIST

Table 2.1.Mitigation Plan ........................................................................................................ 15

Table3.1.Monitoring Plan........................................................................................................ 19

Table4.1.OrganizationTable .................................................................................................... 30

4

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

FIGURE LIST

Figure 1.1. Underground Cable Installation Section..........................................................10 Figure 1.2. Process Flow and Timing Chart.......................................................................10 Figure 4.1. Environmental Information Flow ....................................................................29

5

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDICES LIST

APPENDIX A Satellite Image of the Project Site

APPENDIX B Map of Cable Route

APPENDIX C Photographs of the Project Site

APPENDIX D Public Consultation Documents

APPENDIX E Correspondences with Institutions/Associations

APPENDIX F “EIA Not Necessary” Certificate

6

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

CHAPTER - I

PROJECT DESCRIPTION

7

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

1. PROJECT DESCRIPTION

1.1. Project Description

This project covers the construction and operation of 380 kV Maltepe Gas Insulated

System (GIS) Substation-Kartal GIS Substation having a length of 8 km within the

boundary of Maltepe, Pendik and Kartal Counties in Istanbul.

1.2. Project Purpose

With the implementation of the proposed substation it is aimed to supply energy to the

area uninterruptedly when there is a power cut, thus not to affect the local people

negatively. Therefore, the bottleneck in energy in the region which is expected in the

future shall be prevented. With the implementation of the project it is anticipated that

the economy of both the region and the country will be influenced for the good.

The satellite view, map of the proposed project cable route and the photographs are

presented in Annex.A, Annex.B and Annex.C, respectively.

Project planned to be completed in 17 months by working 8 hours per day. As the

works of underground cable installation on the course shall be limited in the locations

with heavy traffic; works shall be performed in off-peak hours within shifts.

Installation section of underground cable is shown in Figure 1.1 and Process Flow and

Time Chart in 1.2

8

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Fig 1.1. Underground Cable Installation Section

9

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Figure 1.2. Process Flow and Timing Chart

10

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

1.3. Project Area

The route of 380 kV Maltepe GIS Substation-Kartal GIS Substation Underground

Cable Project starts from 3801 kV Maltepe GIS Substation which will be installed on

the plot no. 1684, 5725 m2 parcel no. 28 of Istanbul Province, Maltepe County, Cevizli

District and ends at 380 kV Kartal GIS Substation in Çınardere District, Pendik County.

The proposed cable route follows the main roads and streets in parallel. Therefore, there

are no procedures to be subject to expropriation. The line will be connected to 380 kV

Kartal GIS Substation from 380 kV Maltepe GIS Substation. The cable route between

the substations will be as follows: After crossing Tugay Yolu Road, the line will

follows in the direction of D-100 North Side Way from Cevizli Crossing (passing

Soğanlı Crossing) to Kartal Crossing. After Kartal Crossing, the line continues until

Altan Street entrance in the direction of D-100 Yakacık Road. Finally, the line follows

Altan Street, Meşe Street and is connected to 380 kV Kartal GIS Substation passing

through Işık Street. Along the cable route, some of the places being considered as

environmentally important are İller Bank 1. District Office, military public housing,

rural services, İSKİ Kartal Office, subway construction and Kartal Law Court

Construction, Titanic Hotel, Dumankaya Residence, and Zübeyde Hanım Primary

School. The photographs of the cable right of way are presented in Annex-C.

1.3.1. Project Location

The Project area of 380 kV Maltepe GIS Substation – Kartal GIS Substation

Underground Cable locates within the boundaries of Maltepe, Pendik and Kartal

Counties. Cevizli District, Soğanlık Yeni District, Soğanlık Orta District, Cumhuriyet

District, Hürriyet District and Çınardere District are within the extent of cable right of

way. The photographs of the proposed 380 kV Maltepe GIS Substation – Kartal GIS

Substation Underground Cable are given in Annex-C.

1.3.2. Places with High Landscape Values, Recreation and Protection Areas

By considering the sensitive districts list in EIA Regulation Appendix-V, the proposed

project location within its total 500 meters course which is 250 meters from left and 250

meters from right do not include any wetland, coast, mountainous and forestland,

agricultural field, natural park, special protection area, historical, cultural,

archaeological and with similar importance and aquifer, potential erosion and

11

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

afforestation area subject to protection in accordance with the law regarding

Groundwater numbered 167.

Additionally, there is no high value rural landscape in or close environment of the

project area.

12

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

CHAPTER - II

MITIGATION PLAN

13

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

14

2. MITIGATION PLAN

This section describes the “Mitigation Plan” prepared to ensure the compliance with the

national environmental regulations and the World Bank Operational Policy (OP/BP/GP

4.01) principles and procedures for the activities to be carried out during the

construction, operation and decommissioning phases of the 380 kV Kartal GIS

Substation - Maltepe GIS Substation Underground Cable.

Mitigation Plan prepared within this scope is presented in Table 2.1.

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Tablo 2.1. Mitigation Plan

Phase Subject Mitigation Measures*** Cost

Responsible Institution**

Start Date Finish Date

Cultural and Historical Assets

In case of coinciding with any cultural asset, the construction will be stopped immediately and the Cultural and Natural Assets Protection Committee will be informed.

Until the response is taken, any action will not be done at the site.

After taking the positive response (no cultural assets), the construction will continue.

No additional

cost Contractor

Start of Construction Works

Completion of construction works

CONSTRUCTION Dust – Particulate

Matter (Due to the

movement of construction machines,

excavation works etc.)

The regulated limit value of Dust/Particulate matter emission being 3 mg/Nm3 (Industrial Air Pollution Control Regulation) is not to be exceeded.

Watering will be done in the dry seasons Loading and unloading will be carried out with care

and without scattering. In order not to lead to scattering, loading/unloading works will be performed in an area allocated for loading/unloading and water sprays will be used in loading/unloading area. Moreover, the workers are warned being careful. While loading/unloading, a limit drop height will be applied for the dusty materials. In addition, wind direction and strength will be taken into account while loading and unloading. Windy weathers will not be selected for loading/unloading if it is applicable.

The trucks will be covered and speed limitation will be applied. Speed limit on trucks is 30 km/hr (at project site) and 50 km/hr (outer of the project site – within the city)

Vehicles with emission stickers will be used

Not High

Contractor Start of the

excavation work Completion of the excavation works

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Start Date Finish Date Responsible Subject Mitigation Measures*** Cost

Phase Institution**

Noise

All construction works will be done between 7am and 7pm. If it is required to work after 7 pm, local authorities and public will be informed about these working hours.

People, living at the population centers around, will be informed about the working durations

The continuous work-site noise (day times) will be ensured to be under 70 dBA (according to the Turkish Evaluation of Environmental Noise Regulation. To satisfy this;

In the case of working all the construction machines at the same time, the noise level produced from these machines is 100 dB in average (at the origin). Not to exceed the regulated limit value the mitigation measures will be taken such as that the construction machines will not be worked together at the same time (If it is not possible to reduce the number of working machine at the site temporarily, sound absorbing barriers will be used.), new machines and equipments will be used as much as possible because of resulting higher level of noise of vehicles with age. However, the cable route background noise level is expected to be lower than the noise level due to the construction activities of the cable because the cable follows the route as parallel to D-100 Highway having high level of traffic.

No additional

cost

Contractor

Start of Construction Works

Completion of construction works CONSTRUCTION

Wastewater

Wastewater generated at the central construction site

will be discharged to the sewerage system of the Istanbul Province.

Not High

Contractor

Start of Construction Works

Completion of construction works

14

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Start Date Finish Date Responsible Subject Mitigation Measures*** Cost

Phase Institution**

Excavation, solid and hazardous wastes due to construction

Excavation wastes will be deposited at the nearest deposition area having the license taken by Istanbul Great Municipality.

Solid wastes (construction materials such as metal, wood) and packaging wastes (plastic, paper, glass etc.) will be systematically and separately collected and it will be ensured to be taken by Pendik Municipality or a licensed recycle firm.

Organic domestic wastes due to worker/personnel will be collected separately and it will be ensured to be taken by Pendik Municipality and disposed to the Kömürcüoda Solid Waste Landfill locating in Karakiraz Village.

Not high (changing

by depending

on municipalitie

s and/or licensed recovery

plant)

Contractor Start of Construction

Works Completion of construction works

Wastes due to vehicle parking

Maintenance of the vehicles will not be done at the project site as much as possible.

Waste oil due to construction machines and vehicles will be collected in rustles barrels and will be sent to a licensed firm by the contractor.

The barrels will be placed onto an impermeable ground to protect rain and sun and all necessary precautions against fire will be taken (Impermeable barrels will be used and covered. The around of the area where the barrels are placed will be surrounded with the warning sign. Fire apparatus will be at that area).

Batteries, tires and similar items due to construction machines and vehicles will be sent to a licensed firm and will be ensured to be disposed

Not High Contractor Start of Construction

Works Completion of construction works

CONSTRUCTION Health and Safety

All necessary protective equipments (hard hat, safety belt, protective clothes, gloves, glasses etc.) will be provided to the workers

Proper notification signs will be placed to maintain the security of the public and local people

The personal will be trained in “labor health and occupational safety” issues

Within project budget

Contractor Start of Construction

Works Completion of construction works

15

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

16

Phase Subject Mitigation Measures*** Cost

Responsible Institution**

Start Date Finish Date

Landscape

The work-site will be reassembled

No hazardous, solid, liquid, construction wastes will be

left at the site.

Within project budget

Contractor Completion of

construction works Taking the substation into operation

OPERATION Electro-Magnetic

Field (EMF)

Electric and magnetic fields are expected to comply with the international limit values (5 kV/m for electric field/for public, 1000 mG for magnetic field; 10 kV for electric field/for labors, 5000 mG for magnetic field) mentioned in International Commission on Non-Ionizing Radiation Protection (ICNIRP) because of the materials used for the production of the cable and the structure of the channel which the cable is laid (Figure.1.1).

Within the operation budget

TEIAS Taking the substation

into operation Completion of the economic life of the

substation

Health and Safety

The personal who will be responsible for the maintainance, control, repairs and operation of the cable will be selected from the people having trained in first aid, electric safety and fire.

The warning signs will be placed along the cable route.

Not high (as a part of operation budget)

TEİAS

Taking the substation into operation

After the completion of the economic life of the substation

OPERATION

Solid-Liquid and Hazardous Wastes

Solid wastes generated during the maintainance of the cable will be ensured to be collected by the Kagıthane Municipality.

Hazardous wastes are produced during the maintenance of the cable (the materials (cable wastes) due to the connection points, due to changing the cable ends etc.) and when there is a failure (perforation, deformation etc.). These wastes will be collected seperatedly and taken by the lisenced firm to be disposed.

Not High (changing

by depending

on municipalitie

s and/or licensed recovery

plant)

TEIAS Taking the substation

into operation After the completion of the economic

life of the substation

** Valid in the case of handing over of the proposed works to subcontractors. Otherwise, responsibilities defined for contractor will belong to TEIAS *** While taking the proposed measures, compliance with all related regulations (Air Quality Evaluation and Control Regulation, Water Pollution Control Regulation, Environmental Noise Evaluation and Control Regulation, Solid Waste Control Regulation, Soil Pollution Control Excavation, Construction and Demolition Wastes Control Regulation, Hazardous Waste Control Regulation, Package and Packaging Waste Control Regulation, Grounding in Power Installations Regulation, Work Health and Safety Regulation, Health and Safety Conditions on Usage of Work Equipments Regulation) will be complied

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

CHAPTER - III

MONITORING PLANS

17

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

18

3. MONITORING PLANS

This section describes the “Monitoring Plan” prepared for checking the compliance of the

activities to be carried out during the planning/design, construction, operational and

decommissioning phases of 380 kV Kartal GIS Substation - Maltepe GIS Substation

Underground Cable with the national environmental regulations and the World Bank

Operational Policy (OP/BP/GP 4.01) principles and procedures. Reports in 3 months

period concerning the construction activities carried out in accordance with Mitigation and

Monitoring Plans will be prepared and submitted to TEIAS.

Monitoring Plan prepared within this scope is presented in Table 3.1.

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Table 3.1

Phase

Subject

What are the parameters,

which would be monitored?

Where would the

parameters be

monitored?

How would the

parameters be

monitored/types of the monitoring equipment

When would the

parameters be

monitored - frequency of

the measuremen

ts / continuous

measurement?

Why would the parameters be

monitored? Cost

The Institute that controls – frequency

of the control

Start Date Finish Date

Cultural and

Historical Assets

Cultural assets at the site

Along the cable route

Visual

In case of coinciding a

cultural asset

continuously by an

archeologist

Obeying the Cultural and

Natural Assets Protection Law

Not high if no cultural assets are damaged

Provincial Culture and

Museum Directorate

Start of the cunstruction

works

Completion of

construction works

Construction

Dust – Particulate

Matter

Dust Formation due to the

Movement and Exhaust of the Construction Machinery (mg/Nm3)

Complaints from

public

Along the cable route

Visual

inspection

Interviews with the local people near

the site

During the excavation

period / intense

construction works,

weekly/ in the case of complaint

Industrial Air Pollution Control

Regulation

No additional cost (within the project

budget)

TEİAS

4. TEIAS District Office

Start of construction

works

Completion of

construction works

19

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

When would Table 3.1 the

How would parameters

Phase

Subject

What are the parameters,

which would be monitored?

Where would the

parameters be

monitored?

the be The Institute

parameters monitored - Why would the that controls

be frequency of monitored/ty

pes of the monitoring equipment

the measuremen

ts / continuous

measurement?

parameters be Cost monitored?

– frequency Start Date Finish Date of the

control

Construction

Noise

Complaints from

public

Noise Level (dBA)

Along the cable route

Interviews to be conducted

in near residential

areas

Noise level measurement

with noise meter (sound level meter)

Observation (weekly)

In the case of complaint

from public

Environmental Noise Evaluation

and Control Regulation

Not High

TEİAS

4. TEIAS District Office

Start of the cunstruction

works

Completion of

construction works

20

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

When would Table 3.1 the

How would parameters

Phase

Subject

What are the parameters,

which would be monitored?

Where would the

parameters be

monitored?

the be The Institute

parameters monitored - Why would the that controls

be frequency of monitored/ty

pes of the monitoring equipment

the measuremen

ts / continuous

measurement?

parameters be Cost monitored?

– frequency Start Date Finish Date of the

control

Construction Wastewate

r

Connection to the sewerage

system

Contamination, odor along the

cable route

Connection to the sewerage

system

The cable route

Visual (Wastewater generated by the workers will be given to the sewer system of the

city. The connection to

the sewer system and whether any wastewater

is discharged to soil, water

or to any receiving

body expect the permitted one will be

observed and controlled)

Weekly (irregular controls)

In accordance with the Water Pollution Control Regulation and Soil Pollution

Control Regulation

No additional cost (within the project

budget)

TEİAS

4. TEIAS

District Office

Municipality

Start of the cunstruction

works

Completion of

construction works

21

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Phase Subject

What are the parameters, which would

be monitored?

Where would the

parameters be

monitored?

How would the

parameters be

monitored/types of the monitoring equipment

When would the

parameters be

monitored - frequency of

the measuremen

ts / continuous

measurement?

Why would the parameters be

monitored? Cost

The Institute that controls – frequency

of the control

Start Date Finish Date

Construction

Excavation, Solid and

Hazardous Wastes

Odor

Visual contamination

Along the cable route

(construction site)

Visual

Weekly (irregular controls)

Compliance with Conservation of

Habitat Regulation, Solid Waste

Control Regulation and Soil Pollution

Control Regulation, Hazardous Wastes Control and Waste

Oil Control Regulation

Not High (changing by depending on municipalities

and/or licensed recovery

plant)

Not High (changing by depending on

licensed recovery

plant)

TEİAŞ

4. TEIAS District Office

Contractor

Municipality

Provincial

Directorate of Environment and Forestry

Start of the cunstruction

works

Completion of

construction works

22

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

When would the

How would parameters

Phase Subject

What are the parameters, which would

be monitored?

Where would the

parameters be

monitored?

the be The Institute

parameters monitored - Why would the that controls

be frequency of monitored/ty

pes of the monitoring equipment

the measuremen

ts / continuous

measurement?

parameters be Cost monitored?

– frequency Start Date Finish Date of the

control

Wastes due to Vehicle Parking

Waste oils, automobile

batteries, used tires and junk

electronic materials

At the vehicle

parking area

Inspection and control of

vehicle maintenance documents

During the failure / periodic

maintenance (half yearly)

Achievement of the

disposal of the wastes compliance

with Waste Oil Control Regulation, Waste Battery and

Accumulators Control Regulation, End-of-tires Control

Regulation

Not High (changing by depending on

licensed recovery

plant)

Contractor Start of the cunstruction

works

Completion of

construction works

23

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

When would the

How would parameters

Phase Subject

What are the parameters, which would

be monitored?

Where would the

parameters be

monitored?

the be The Institute

parameters monitored - Why would the that controls

be frequency of monitored/ty

pes of the monitoring equipment

the measuremen

ts / continuous

measurement?

parameters be Cost monitored?

– frequency Start Date Finish Date of the

control

Health and Safety

Documents related to

workers health and safety

training

Equipments used by the

worker during working for construction (hard hat,

gloves, safety belt etc.)

Warning signs,

band

Construction sites (cable construction

line)

Visual

Beginning of

the each work stage

Daily

In accordance with Labor Health and

Occupational Safety Regulation

No additional cost (within the project

budget)

TEİAS

4. TEIAS

District Office

Start of the cunstruction

works

Completion of

construction works

Construction

Landscape

Wastes (solid, liquid,

hazardous, construction

etc.)

Soil / service roads

Along the cable route

Visual

During closing the

construction site

Compliance with Environmental Law

and Regulations

No additional cost (within the project

budget)

TEIAS

4. TEIAS District Office

Completion of construction

works

Taking the cable into operation

24

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

When would the

How would parameters

Phase Subject

What are the parameters, which would

be monitored?

Where would the

parameters be

monitored?

the be The Institute

parameters monitored - Why would the that controls

be frequency of monitored/ty

pes of the monitoring equipment

the measuremen

ts / continuous

measurement?

parameters be Cost monitored?

– frequency Start Date Finish Date of the

control

Operation Electromagn

etic Field Complaints from public

Along the cable route

Interviews with the

people at the near

residential areas

In the case of complaints

Control of satisfying the national and international

referance values

Not High

TEAİS

4. TEIAS District Office

Taking the cable into operation

Completion of the economic

life of the cable

Operation Health and

Safety

Technical training in terms of

operation and maintenance

Protective

equipments and clothes

(whether usage or not)

Warning

beams/signs

Along the cable

route/cable connection

points

Visual

Before the operation

In the case of

failure (During

maintenance – repair)

Once, before

taking the cable into operation

Compliance with related health and safety regulations

No additional cost (within

the operation budget)

TEİAS

4. TEIAS District Office

Taking the cable into operation

Completion of the economic

life of the cable

25

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

26

Phase Subject

What are the parameters, which would

be monitored?

Where would the

parameters be

monitored?

How would the

parameters be

monitored/types of the monitoring equipment

When would the

parameters be

monitored - frequency of

the measuremen

ts / continuous

measurement?

Why would the parameters be

monitored? Cost

The Institute that controls – frequency

of the control

Start Date Finish Date

Operation

Solid-Liquid and

Hazardous Wastes

(automobile accumulator)

Contamination along the cable

route

Along the cable route

Visual

At the time of failure/maintenance of the

cable

Compliance with Conservation of

Habitat Regulation, Solid Waste

Control Regulation and Soil Pollution

Control Regulation, Hazardous Waste Control Regulation

Compliance with Waste Oil Control

Regulation

Not high

(changing by depending on municipalities

and/or licensed recovery

plant)

Not high (depending

on the firm/laboratory conducting the analysis)

TEIAS

4. TEIAS District Office

Municipality

Taking the cable into operation

Completion of the economic

life of the cable

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

CHAPTER - IV

INSTITUTIONAL ARRANGEMENTS

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

4. INSTITUTIONAL ARRANGEMENTS In this chapter, information about the responsibilities and procedures related to mitigation

measures and monitoring, environmental information flow chart, decision making hierarchy

on environmental management will be given and how the data gathered from the monitoring

is analyzed and used in an efficient way to maintain a sustainable environmental performance

will be mentioned.

4.1 Liabilities and Procedures related to the mitigation measures and monitoring

“Mitigation Plan” which covers the mitigation measures to be taken to minimize the negative

possible environmental effects due to the planning/design, construction and operation

activities is presented in chapter-II. “Monitoring Plan” which aims to control the

implementation clauses of the procedures and measures mentioned in the “mitigation plan” is

provided in chapter-III. “Mitigation and monitoring plans” are the basic elements forming the

“Environmental Management Plan” prepared within the content of “Political, Forensic and

Administrative Framework” section in environmental impact assessment reports.

4.2 Environmental Information Flow (Reporting and the frequency of the report

submission)

In order to devise and implement a successful environmental management plan, the elements

which are supposed to be obeyed should be determined carefully. Within this scope, it is

abided by the subjects mentioned in the international regulations and communiqués.

Environmental issues in Turkey Clauses predicates on the clauses of “Environmental

Assessment Regulation” published in official gazette on 17 July 2008 with no.26939.

According to this regulation, in accordance with Article 32, List.2, energy transmission plants

(transmission lines, substation, switchyard) having 154 kV or above voltage and length of 5

km or longer are supposed to be obtained “EIA Not Necessary Certificate”. Therefore, “EIA

Not Necessary Certificate” (Appendix.F) has been obtained from Turkish MoEF for the 380

kV Maltepe GIS Substation – Kartal GIS Substation Underground Cable Project, due to the

fact that the length of 380 kV Maltepe GIS Substation – Kartal GIS Substation Underground

Cable is around 8 km.

28

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

4.3 380 kV Maltepe GIS Substation-Kartal GIS Substation Underground Cable Project

Environmental Information Flow:

Environmental information flow chart (Figure 4.1) for the proposed 380 kV Maltepe GIS

Substation – Kartal GIS Substation Underground Cable project based on the mentioned

regulation above and the table describing the organization are presented below (Table 4.1).

EIA Certificate and required permits are obtained

Environment Management Plan (EMP) is prepared in answer to the request from World Bank

The prepared EMP is submitted by TEIAS to the World Bank

EMP Application Report (Monitoring Report), which is prepared/had made by the Contractor based on the EMP and Monitoring Program, is submitted to TEIAS

The EMP Application Reports approved by TEIAS is submitted to the World Bank (*)

The submitted report is controlled and approved by the World Bank (**)

Figure 4.1 Environmental Information Flow

(*): TEIAS (as the project owner) with the help of TEIAS’s district offices shall audit the

environmental performance of the contractor and controls whether the contractor obeys to the

issues determined in the EMP. Within this scope, the contractor is liable to meet the

environmental requirements and to submit the reports (in quarterly period) covering the

construction activities and their corresponding mitigation measures to TEIAS.

(**): In the case of necessity, the project site is audited checking in place and approved by the

World Bank representatives.

29

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Table 4.1 Organization Table

Action  Institutional Responsibility Monitoring Data Collection  Construction

Monitoring will be performed by the contractor or consultancy firm hired by the contractor. The report (monitoring) prepared by collecting monitoring data will be submitted to the TEIAS in a quarterly basis.

Data Analysis  Construction

TEIAS related district office (TEIAS 4. District Office) will control the accuracy of the data in the reports (by examining the data validity in place). Then, the district office will send the report to the TEIAS General Directorate (Ankara) for control. After the control of the report by TEIAS (Environment, Estate and Expropriation Department), the report is sent to the World Bank for approval.

Management Action  Construction

The ministry has the authority to shutdown, change the operations etc. if any illegal or unregulated situation is observed. 

30

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

CHAPTER - V

PUBLIC CONSULTATION WITH PROJECT

AFFECTED GROUPS and NON-GOVERNMENTAL

ORGANIZATIONS (NGO)

31

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

5. GROUPS WHICH WILL BE AFFECTED BY THE PROJECT AND DISCUSSIONS WITH VOLUNTARY AGENCIES (NGO)

For inspection area of the proposed project, 380 kV Maltepe GIS Substation – Kartal

GIS Substation Underground Cable Cevizli, Soğanlık Yeni, Soğanlık Orta, Cumhuriyet,

Hürriyet ve Çınardere districts has been taken as a base and those communities who may be

affected environmentally were determined.

For the aforesaid project; a meeting of Public Participation has been realized in the

meeting hall of Kartal County, Soğanlık Orta District, Öğretmen Salih Nafiz Tüzün Primary

School on January 14 2010, 11 a.m. Announcement of the aforesaid meeting has been

published in national VATAN and local ORTADOĞU newspapers on the date of 02.01.2010.

Locals, related institutions and associations, village headmen etc. who reside in sites that are

involved in the project’s inspection area has been invited to the subject meeting. Detailed

information relevant to subject meetings shall be given below.

Meeting Place and Date:

The meeting was held on the date of 14 January 2010 at 11 a.m. in the meeting room of

Öğretmen Salih Nafiz Tüzün Primary School within the boundary of Soğanlık Orta District in

Istanbul.

Evaluation of the Meeting:

The photographs relating to the meeting, the participation list and the information

brochures distributed to the participants are present in the Appendix.D.

Dates of Interviews/Pre-Preparations

The headmen of Cevizli, Soğanlık Yeni, Soğanlık Orta, Cumhuriyet, Hürriyet and

Çınardere Districts were interviewed with on the dates of 18 November 2009 and 12 January

2010.

After the mentioned meetings, the public participation meeting was held in the meeting

room of Öğretmen Salih Nafiz Tüzün Primary School in Soğanlık Orta District, Kartal

County, Istanbul Province on 14 January 2010 at 11 a.m.

32

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

‐ Places which discussions were implemented:

Discussions/interviews were implemented with the headmen of Cevizli, Soğanlık Yeni,

Soğanlık Orta, Cumhuriyet, Hürriyet and Çınardere Districts via both telephone and visit in

place.

‐ Who were invited to discussion(s):

The public to be possibly affected from the project and who were living within the borders

of the proposed cable investigation area has been invited to the subject meeting. Relevant

people were invited to the meeting by means of correspondences with headman of related

districts (Photo.25/Appendix.D) and local and national newspaper announcements (Vatan

Newspaper Turkey Edition and Ortadoğu Local Newspaper of İstanbul Province on January 1

2010, Appendix.D).

‐ Who were participated in discussions:

Owner of the project (TEİAŞ) and above mentioned community dwellers and headmen

were involved in discussions and relevant photographs are presented in Appendix.D.

‐ Program and Calendar of the Meeting:

First, information about the project site location, possible environmental impacts and

mitigations of the impacts was given to the participants. Then, the questions of the

participants were answered by the TEIAS personals. Furthermore, informative brochures

about the proposed project and electromagnetic field were distributed to the participants and

the contact information of TEIAS General Directorate and TEIAS Related District Offices

was given to the participants to reach if they had any question or problem.

‐ Minutes of Meeting:

The questions raised by the participants and the answers given to these questions are

presented below:

Question: What are the districts within the coverage area of the 380 kV Maltepe GIS

Substation-Kartal GIS Substation Underground Cable Project?

Answer: 380 kV Maltepe GIS Substation-Kartal GIS Substation Underground Cable

connects from 380 kV Maltepe GIS Substation in Cevizli District to 380 kV Kartal GIS

Substation in Çınardere District following Soğanlık Yeni Distirct, Soğanlık Orta District,

Cumhuriyet District, and Hürriyet District. Therefore, the project will embrace six districts.

33

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

34

Question: What is the reason of selecting this area for the proposed project?

Answer: The most suitable cable route in terms of technical and energy supply aspects

has been determined for 380 kV Maltepe GIS Substation-Kartal GIS Substation Underground

Cable Project. Any expropriation problem does not also exist. Moreover, the cable right-of-

way mostly follows D-100 highway as in parallel so that the local people will be affected by

the construction of the proposed project at minimal level.

Question: Will any negative effect of 380 kV Maltepe GIS Substation-Kartal GIS

Substation Underground Cable Project on the health of people considering the

electromagnetic field effects of the project?

Answer: Electromagnetic Area formation, effects and international values of limit has

been expressed. Measurement samples which TEİAŞ implemented with TÜBİTAK have been

given. Other electromagnetic interactions exposed have been mentioned also. The information

about radiation kinds has been given.

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDICES

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDIX-A

Satellite Image of the Project Site

- 2 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Satellite Image

- 3 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDIX-B

Map of Cable Route

- 4 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDIX-C

Photos of the Project Site

- 5 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.1 (Maltepe GIS Substation Exit/ Tugay Yolu Road)

Photo.2 (Cable Right-of-way/Tugay Yolu Road)

- 6 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.3 (Cable Right-of-way/Cevizli Crossing)

Photo.4 (Cable Right-of-way/Cevizli Crossing D-100 exit)

- 7 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.5 (Cable Right-of-way / D-100 North Parallel Road)

Photo.6 (Cable Right-of-way /Soğanlık Crossing)

- 8 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.7 (Cable Right-of-way/ ISKI Kartal District Office)

Photo.8 (Cable Right-of-way)

- 9 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.9 (Cable Right-of-way/Court of Law in Construction)

Photo.10 (Cable Right-of-way/ Kartal Crossing)

- 10 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.11 (Cable Right-of-way/ D-100 Yakacık Road)

Photo.12 (Cable Right-of-way/ D-100 Yakacık Road)

- 11 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.13 (Cable Right-of-way /Altan Street Entrance)

Photo.14 (Cable Right-of-way/Altan Street)

- 12 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.15 (Cable Right-of-way/Zübeyde Hanım Primary School)

Photo.16 (Cable Right-of-way/Meşe Street)

- 13 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.17 (Cable Right-of-way /Işık Street)

Photo.18 (Cable Right-of-way/Işık Street)

- 14 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.19 (Cable Right-of-way/Trafo Street Entrance)

Photo.20 (Cable Right-of-way/380 kV Kartal Substation)

- 15 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDIX-D

Public Consultation Gazette Announcement

Brochure Participation List

- 16 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Gazette Announcement (1) – Local Newspaper

- 17 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Gazette Announcement (2) – National Newspaper

- 18 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Brochure (1-a)

- 19 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Brochure (1-b)

- 20 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Brochure (2-a)

- 21 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Brochure (2-b)

- 22 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Public Consultation Participation List (1)

- 23 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Public Consultation Participation List (2)

- 24 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

380 kV MALTEPE GIS SUBSTATION-KARTAL GIS SUBSTATION UNDERGROUND CABLE PROJECT

PUBLIC CONSULTATION MEETING PHOTOS

14 January 2010 / 11 a.m. Öğretmen Salih Nafiz Tüzün Primary School Meeting Room / ISTANBUL

Photo.21

Photo.22

- 25 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.23

Photo.24

- 26 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

Photo.25

Photo.26

- 27 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDIX-E

Associations/Institutions Correspondences

- 28 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

APPENDIX-F

“EIA Not Necessary” Certificate

- 29 -

TEIAS 380 kV MALTEPE GIS -KARTAL GIS UNDERGROUND CABLE ENVIRONMENTAL MANAGEMENT PLAN

- 30 -

Project Team Preparing 380 kV Maltepe GIS Substation-Kartal GIS Substation Underground Cable Project Environmental Management Plan

Project Owner: TEIAS (Turkey Electricity Transmission Corporation) General Directorate

Project Location: İstanbul Province, Maltepe, Kartal and Pendik Counties

Project Name: 380 kV Maltepe GIS Substation-Kartal GIS Substation Underground Cable

Name&Surname Occupation Signature

Gul MISIRLI Architect

Dilek KESKIN

Geological Engineer

(Environmental Sciences

Master Degree)

Mustafa GOKHARMAN Electrical Engineer

Murat GURSOY Chemical Engineer

Gozde TEZCE Environmental Engineer