TEIAS
TURKISH ELECTRICITY TRANSMISSION CORPORATION
GENERAL MANAGEMENT
380 kV KARTAL GIS SUBSTATION (GAS INSULATED SYSTEM SUBSTATION)
ENVIRONMENTAL MANAGEMENT PLAN
(İSTANBUL PROVINCE, PENDİK COUNTY)
ANKARA – DECEMBER 2010
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
380 kV KARTAL GIS
SUBSTATION
ENVIRONMENTAL MANAGEMENT PLAN
Project Owner Turkish Electricity Transmission Co. General Management
Address Inonu Boulevard No:27 Bahcelievler 06490, Ankara
Telephone +90 (312) 203 86 12
Fax no +90 (312) 203 87 17
Project name 380 kV Kartal GIS Substation Location of Project Site Istanbul Province, Pendik County
2
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
TABLE OF CONTENT
Table of Content..................................................................................................................3 Table List.............................................................................................................................4 Figure List ...........................................................................................................................5 Appendix List ......................................................................................................................6
1. PROJECT DESCRIPTION
1.1. General Description......................................................................................................8 1.2. Purpose of Project ........................................................................................................8 1.3. Scope of Project ...........................................................................................................9 1.4. Project Site ...................................................................................................................9 2. MITIGATION PLAN ...................................................................................................12 3. MONITORING PLAN .................................................................................................21 4. INSTITUTIONAL ARRANGEMENTS .....................................................................31 5. CONSULTATION WITH PROJECT AFFECTED GROUPS AND NON-GOVERMNENTAL ORGANIZATIONS (NGO’s).......................................................34
APPENDICES
PROJECT TEAM PREPARING THE REPORT
3
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
TABLE LIST
Table 2.1.Mitigation Plan ........................................................................................................ 14
Table3.1.Monitoring Plan........................................................................................................ 22
Table4.1.OrganizationTable .................................................................................................... 32
4
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
FIGURE LIST
Figure 1.1. Process Chart ...................................................................................................9 Figure 4.1. Environmental Information Flow Chart...........................................................31
5
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
APPENDICES LIST
APPENDIX A Satellite Image of the Project Site
APPENDIX B General Site Plan of the Project Site
APPENDIX C Photographs of the Project Site
APPENDIX D Public Consultation Documents
APPENDIX E Correspondences with Institutions/Associations
APPENDIX F “EIA Not Necessary” Certificate
6
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
CHAPTER - I
PROJECT DESCRIPTION
7
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
1. PROJECT DESCRIPTION
1.1. Project Description
This project covers the construction and operation of 380 kV Kartal Gas Insulated
System (GIS) Substation within the boundary of Çınardere District, Pendik County in
Istanbul.
380 kV Kartal GIS Substation will be composed of Transformers, GIS building and MC
control buildings. The layout of the buildings within the substation area and their
dimensions will be planned and designed by TEIAS related departments.
After obtaining the necessary certificates and permits for the construction of the 380 kV
Kartal GIS Substation, the excavation borders are applied to the construction area. The
excavation works are done in accordance with the approved general site plan and the
area is leveled off. The drainage system is installed based on the drainage system plan
and the connection to the sewerage system of Istanbul Province is maintained. Steel
works are done and the construction of the substation buildings is completed. Finally,
the electrical works are implemented.
Since 380 kV Kartal GIS Substation is built at the existing 154 kV substation area,
dismantling/demolition of the existing substation will be primarily required. For this
purpose, transformer oil is first extracted and collected. Then, substation is divided into
its components. Buildings and all structural steel can be leveled and removed. All the
redundant equipments and wastes are collected separately and disposed of. If there exist
the materials containing asbestos due to the dismantling of the substation (previous
installation, pipes etc.), special attention will be given for these kinds of waste. In such
cases, components with asbestos will be collected separately as hazardous wastes and
they will be eliminated through the firms having the required license for the disposal of
hazardous wastes such as Izaydaş Corporation. Moreover, it will be avoided for workers
to contact with asbestos containing wastes in such cases.
1.2. Project Purpose
With the implementation of the proposed substation it is aimed to meet the energy
demand of the area in İstanbul and to reduce the likelihood of blackouts and brownouts
in the area. 380 kV Kartal GIS Substation is a part of the loop with 380 kV Maltepe
GIS Substation and the substations will be connected to each other with a 8 km length
8
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
of underground cable. Therefore, the bottleneck in energy in the region which is
expected in the future shall be prevented. With the implementation of the project it is
anticipated that the economy of both the region and the country will be influenced for
the good.
1.3. Project Scope
The work flow chart of the proposed Project is shown in the Figure 1.1.
Figure 1.1. 380 kV Kartal GIS Substation Work Flow Chart
1.4. Project Site
1.4.1. Project Site Location
The proposed Kartal GIS Substation Project site locates within the boundary of Pendik
County, Istanbul Province. Settling area constitutes the close environment of the
subjected 380 kV Kartal GIS Substation. There exits Zübeyde Hanım Primary School in
380 kV KARTAL GIS SUBSTATION WORK FLOW CHART
Providing Necessary Permissions from Institution and
Establishments
Excavation, Embankment, Grounding, Drainage, etc.
Preparation for primary equipment and steel construction
Groundwork
Procurement and installation of steel construction materials
Procurement and installation of primary equipment and materials
Control and acceptance
9
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
the Southwest of the project site. The satellite image of the proposed Project site and its
close environment in Appendix.A, the general site plan of the Project site in
Appendix.B and the photographs in Appendix.C are given, respectively.
1.4.2. Project Site Information
The Project site in Çınardere District, Pendik County, İstanbul Province, is owned by
TEIAS General Directorate and 154 kV Kartal Substation presently exist in the area and
is in operation. The proposed 380/33 kV Kartal GIS Substation is planned to be
constructed in the place of exiting 154 kV Substation.
1.4.3. Places with High Landscape Values, Recreation and Protection Areas
By considering the sensitive areas list in EIA Regulation ANNEX-V, proposed project
location and its close environment do not include any wetland, coast, mountainous and
forestland, agricultural field, natural park, special protection area, historical, cultural,
and archaeological and with similar importance and aquifer, potential erosion and
afforestation area subject to protection in accordance with the law regarding
groundwater numbered 167. Additionally, there is no high value rural landscape in or
close environment of the project area.
10
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
CHAPTER - II
MITIGATION PLAN
11
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
12
2. MITIGATION PLAN
This section describes the “Mitigation Plan” prepared to ensure the compliance with the
national environmental regulations and the World Bank Operational Policy (OP/BP/GP
4.01) principles and procedures for the activities to be carried out during the
construction, operation and decommissioning phases of the 380 kV Kartal GIS
Substation.
Mitigation Plan prepared within this scope is presented in Table 2.1.
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
Table 2.1. Mitigation Plan
Phase Subject Mitigation Measures** Cost
Responsible Institution*
Start Date Finish Date
Cultural and Historical Assets
In case of coinciding with any cultural asset, the construction will be stopped immediately and the Cultural and Natural Assets Protection Committee will be informed.
Until the response is taken, any action will not be done at the site.
After taking the positive response (no cultural assets) the construction will continue.
No additional
cost Contractor
Start of Construction Works
Completion of construction works
Dismantling of the existing substation
All redundant equipments and waste will be collected separately and whenever possible, these materials will be recycled by a licensed firm.
Asbestos containing materials will be disposed of by the firms licensed for hazardous waste disposal
Included in the
construction contract
Contractor Start of the dismantling
works Completion of the dismantling works
CONSTRUCTION
Dust – Particulate Matter
The regulated limit value of Dust/Particulate matter emission being 3 mg/Nm3 (Industrial Air Pollution Control Regulation) is not to be exceeded.
Watering will be done in the dry seasons Loading and unloading will be carried out with care
and without scattering. In order not to lead to scattering, loading/unloading works will be performed in an area allocated for loading/unloading and water sprays will be used in loading/unloading area. Moreover, the workers are warned being careful about loading/unloading activities. Windy weathers will not be selected for loading/unloading if it is applicable.
The trucks will be covered with canvas, etc. and speed limitation will be applied. Speed limit on trucks is 30 km/hr (at project site) and 50 km/hr (outer of the project site – within the city)
Only vehicles with emission stickers will be used Tires of the trucks will be cleaned where necessary to
prevent dirt being carried onto the roads
Included in
the construction
contract
Contractor Start of the excavation
work Completion of the excavation works
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
Start Date Finish Date Responsible Subject Mitigation Measures** Cost
Phase Institution*
Noise
All construction works will be done between 7am and 7pm. If it is required to work after 7 pm, local authorities and public will be informed about these working hours.
People, living at the population centers around, will be informed about the working durations
The continuous work-site noise (day times) will be ensured to be under 70 dBA (according to the Turkish Regulation on Assessment and Management of Environmental Noise. To satisfy this;
The construction machines (vehicles) inspection, maintenance and oiling will be done in time and periodically, and the items resulting in noise will be replaced.
No additional
cost
Contractor
Start of Construction Works
Completion of construction works
Wastewater
Wastewaters due to work-site will be given to the
sewerage system of the Istanbul Province by the connection to the sewerage system of Istanbul.
Included in the
construction contract
Contractor
Start of Construction Works
Completion of construction works
CONSTRUCTION
Excavation, solid and hazardous wastes due to construction
Excavation wastes will be deposited to the excavation waste disposal area in the Anatolian side of Istanbul having the license taken by Istanbul Great Municipality.
Solid wastes (construction materials such as metal, wood) and packaging wastes (plastic, paper, glass etc.) will be systematically and separately collected and it will be ensured to be taken by Pendik Municipality or a licensed recycle firm.
Organic domestic wastes due to worker/personnel will be collected separately and it will be ensured to be taken by Pendik Municipality and disposed to Kömürcüoda Solid Waste Disposal Area locating near Karakiraz Village.
Hazardous wastes such as oil, dye etc. will be collected separately in leak proof, metal and labeled containers and it will be ensured to be taken by a licensed firm ensured by the Contractor
Not high (changing
by depending
on municipalitie
s and/or licensed recovery
plant)
Contractor Start of Construction
Works Completion of construction works
14
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
Start Date Finish Date Responsible Subject Mitigation Measures** Cost
Phase Institution*
Wastes due to vehicle parking
Maintenance of the vehicles will not be done at the project site unless there is an emergency situation
Waste oil due to construction machines and vehicles will be collected in rustless barrels and will be sent to a licensed firm by the contractor.
The barrels will be placed onto an impermeable ground to protect them from rain and sun and all necessary precautions against fire will be taken. The area where the barrels are placed will be surrounded with the warning sign. Fire fighting set (bucket, axe, shovel, pickaxe, and anchor) will be at that area.
Batteries, tires and similar items due to construction machines and vehicles will be sent to a licensed firm for final disposal.
Not High Contractor Start of Construction
Works Completion of construction works
Health and Safety
All necessary protective equipments (hard hat, safety belt, protective clothes, gloves, glasses etc.) will be provided to the workers
Proper notification signs will be placed to maintain the security of the public and local people
The personnel will be trained on “labor health and occupational safety” issues. Information about the safety rules that must be obeyed within the work-site area during the construction works, risks and related regulations will be provided to all workers before the construction works start.
Within project budget
Contractor Start of Construction
Works Completion of construction works
CONSTRUCTION
Landscape
The work-site will be restored.
No hazardous, solid, liquid, construction wastes will be
left at the site.
Within project budget
Contractor Completion of
construction works Taking the substation into operation
15
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
Start Date Finish Date Responsible Subject Mitigation Measures** Cost
Phase Institution*
OPERATION Noise
The limit values (Ldaytime:65 dBA, Lnightime:55 dBA) regulated in Turkish Enivronmental Noise Evaluation and Control Regulation will not be exceeded. To satisfy this limits;
Equipments forming the substation shall be specified in the bid documents and supplied in accordance with the International Electrotechnical Comission (IEC) 60076-10 and other international standards (For 154 kV transformers≤60 dBA at source/For 380 kV transformers≤70 dBA at source).
Within the operation budget
TEIAS
Transmission Network Operation
Maintenance Department
Taking the substation into operation
Completion of the economic life of the substation
Operation Electro-Magnetic
Field (EMF)
The limit values (5 kV/m for electric field/for public, 1000 mG for magnetic field (24 hours/day); 10 kV for electric field/for labors, 5000 mG for magnetic field (8 hours/day)) mentioned in International Commission on Non-Ionizing Radiation Protection (ICNIRP) will be complied with. In order to satisfy this limits the following will be conducted;
As specified in the bid documents, all the equipments of the substation (transformer, disconnector, circuit breaker, surge-arrester, current transformer, voltage transformer etc.) will be taken according to the International Electrotechnical Commission (IEC) and other international standards and the controls and maintainance (strengthening by renewal) will be done in accordance with IEC.
The substation will be surrounded by the wall and fence. Therefore, enterance, approach, and settlement would be avoided.
The substation building, equipments, wall and fence will be grounded. In any case of sign of a failure (such as failure in the operation of an equipment, increasing the contact current, electrical arc, local warming etc.) the grounding resistance will be measured and according to the measurment results the grounding of the ones having the problem will be strengthened by local rehabilitation, maintaning the continuity of the connections etc.
Within the operation budget
TEIAS
Taking the substation into operation
Completion of the economic life of the substation
16
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
Start Date Finish Date Responsible Subject Mitigation Measures** Cost
Phase Institution*
Health and Safety
The personnell will be selected from the people having trained in first aid, electric safety, working at high levels for the maintanace of the substation
The warning signs and climbing barriers will be placed around the substation.
Not high (as a part of operation budget)
TEİAS
4. TEIAS District
Office
Taking the substation into operation
After the completion of the economic life of the substation
SF6
SF6 gas will be monitored continously with presure measurement and gas leakages will be controlled. In the case of gas leakge (before SF6 gas density drops below the critic level), the bay will be shut down (closed) and that part will be out-of service until the problem is solved.
Not high (as a part of operation budget)
TEİAS
Transmission
Network Operation Maintenance Department
Taking the substation into operation
After the completion of the economic life of the substation
Fire Risk
The substation which will be established as to the fire safety elements in the “Electric Intensive Current Plant Regulation” shall be controlled regularly and all equipments shall be controlled, maintained, tested, rehabilitated and renewed (in terms of the parameters like bushing, SF6, isolation oil, cable ends and gas leakage).
All eqipments will be tested according to the national and international standarts againts arc and sparks.
Not high (as a part of operation budget)
TEIAS
4. TEIAS District
Office
Transmission Network Operation
Maintenance Department
Taking the substation into operation
After the completion of the economic life of the substation
OPERATION
Substation oil
Substation oil will be analyzed physically and chemically (density, acidity, viscosity, corrosive sulfide, flash point, PCB, color).
When the oil completes its economic life, it will be replaced with new one and disposal of it will be ensured by conducting required tests (to determine the category of the oil) and applying proper disposal method as to the category test results
PCBs will never be used as replacement oils.
Not high (as a part of operation budget)
TEIAS
4. TEIAS District
Office
Transmission Network Operation
Maintenance Department
Taking the substation into operation
After the completion of the economic life of the substation
17
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
18
Phase Subject Mitigation Measures** Cost
Responsible Institution*
Start Date Finish Date
Solid-Liquid and Hazardous Wastes
Solid wastes, junk materials and construction wastes will be collected seperately and they will be ensured to be taken by the Pendik Municipality or a licenced firm
Wastes such as oil, dye will be collected in separate, impermeable, metal and labeled conteyners and will be ensured to be taken by a licenced recycle firm
Not High (changing
by depending
on municipalitie
s and/or licensed recovery
plant)
TEIAS
4. TEIAS District
Office
Taking the substation into operation
After the completion of the economic life of the substation
* Valid in the case of handing over of the proposed works to subcontractors. Otherwise, responsibilities defined for contractor will belong to TEIAS ** While taking the proposed measures, compliance with all related regulations (Air Quality Evaluation and Control Regulation, Water Pollution Control Regulation, Environmental Noise Evaluation and Control Regulation, Solid Waste Control Regulation, Soil Pollution Control Excavation, Construction and Demolition Wastes Control Regulation, Hazardous Waste Control Regulation, Package and Packaging Waste Control Regulation, Grounding in Power Installations Regulation, Work Health and Safety Regulation, Health and Safety Conditions on Usage of Work Equipments Regulation) will be complied
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
CHAPTER - III
MONITORING PLANS
19
TEIAS 380 kV KARTAL GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
20
3. MONITORING PLANS
This section describes the “Monitoring Plan” prepared for checking the compliance of the
activities to be carried out during the planning/design, construction, operational and
decommissioning phases of 380 kV Kartal GIS Substation with the national environmental
regulations and the World Bank Operational Policy (OP/BP/GP 4.01) principles and
procedures. Reports in 3 months period concerning the construction activities carried out in
accordance with Mitigation and Monitoring Plans will be prepared and submitted to
TEIAS.
Monitoring Plan prepared within this scope is presented in Table 3.1.
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
Phase Subject
What are the parameters, which
would be monitored?
Where would the
parameters be monitored?
How would the parameters be monitored/typ
es of the monitoring equipment
When would the
parameters be monitored - frequency of
the measurements
/ continuous measurement?
Why would the parameters be
monitored? Cost
The Institute that controls – frequency of the control
Start Date Finish Date
Cultural and Historical Assets
Cultural assets at the site
Construction site
Visual
In case of coinciding a
cultural asset ,continuously
by an archeologist
Compliance with the Cultural and Natural Assets Protection
Law
Not high if no cultural assets are damaged
Provincial Culture and
Museum Directorate
Start of the cunstruction
works
Completion of construction
works
Dismantling of the existing substation
Substation components &
installation
Redundant equipments and
wastes
Construction site
Visual During the dismantling
activity
Related Environmental Laws
and Regulations
No additional cost (within the project budget)
TEİAS
4. TEIAS District Office
Start of the demolishmen
t activities
Complition of the
demolishment activities Constructi
on
Dust – Particulate
Matter
Dust Formation due to the
Movement and Exhaust of the Construction Machinery (mg/Nm3)
Complaints from
public
Construction site
Visual
inspection
Interviews with the local
people near the site
During the excavation
period / intense
construction works, weekly/ in the case of
complaint
Industrial Air Pollution Control
Regulation
No additional cost (within the project budget)
TEİAS
4. TEIAS District Office
Start of construction
works
Completion of construction
works
Construction
Noise
Complaints from
public
Noise Level (dBA)
Construction site
Interviews to be
conducted in near residential
areas
Noise level measurement
with noise meter (sound level meter)
Observation (weekly)
In the case of complaint from
public
Environmental Noise Evaluation and
Control Regulation Not High
TEİAS
4. TEIAS District Office
Start of the cunstruction
works
Completion of construction
works
21
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
When would the
How would the parameters be
What are the Where would
Phase Subject parameters, which
would be monitored?
the parameters be
monitored?
parameters be The Institute monitored/typ
es of the monitoring equipment
monitored - Why would the that controls –
frequency of the
measurements / continuous
measurement?
parameters be Cost Start Date Finish Date frequency of
monitored? the control
Construction
Wastewater
Connection to the sewerage system,
Contamination in the water and/or
soil in the substation area
Connection to the sewerage
system
Substation area
Visual (Wastewater generated by
the workers will be given to the sewer system of the city. The connection to
the sewer system and whether any
wastewater is discharged to
soil, water or to any receiving
body expect the permitted one
will be observed and
controlled)
Weekly (irregular controls)
In accordance with the Water Pollution Control Regulation,
Soil Pollution Control and Contaminated
Sites by Point-Source Regulation
No additional cost (within the project budget)
TEİAS
4. TEIAS District Office
Municipality
Start of the cunstruction
works
Completion of construction
works
22
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
Phase Subject
What are the parameters,
which would be monitored?
Where would the
parameters be monitored?
How would the parameters be monitored/typ
es of the monitoring equipment
When would the
parameters be monitored - frequency of
the measurements
/ continuous measurement?
Why would the parameters be
monitored? Cost
The Institute that controls – frequency of the control
Start Date Finish Date
Excavation, Solid and Hazardous
Wastes
Storage and disposal
conditions Construction
site and disposal site
Visual
Weekly (irregular controls)
Compliance with Solid Waste Control
Regulation, Soil Pollution Control and Contaminated Sites
by Point-Source, Hazardous Wastes Control, Excavation
wastes, Construction and Debris Wastes Control Regulation
and Waste Oil Control Regulation
No additional cost
TEİAŞ
4. TEIAS District Office
Contractor
Municipality
Start of the cunstruction
works
Completion of construction
works
Construction
Wastes due to Vehicle Parking
Waste oils, automobile
batteries, used tires and junk
electronic materials
At the vehicle parking area
Visual Inspection and
control of vehicle
maintenance documents
During the failure and
regular maintenance
Achievement of the
disposal of the wastes compliance with
Waste Oil Control Regulation, Waste
Battery and Accumulators Control Regulation, End-of-
tires Control Regulation
No additional cost
Contractor Start of the cunstruction
works
Completion of construction
works
23
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
When would the
How would the parameters be
What are the Where would
Phase Subject parameters,
which would be monitored?
the parameters be
monitored?
parameters be The Institute monitored/typ
es of the monitoring equipment
monitored - Why would the that controls –
frequency of the
measurements / continuous
measurement?
parameters be Cost Start Date Finish Date frequency of
monitored? the control
Health and Safety
Documents related to
workers health and safety
training
Equipments used by the
worker during working for construction
(hard hat, gloves, safety belt etc.)
Work practices
Construction sites
Visual
Beginning of
the each work stage
Daily
In accordance with Labour Health and Safety Regulation
No additional cost (within the project budget)
TEİAS
4. TEIAS
District Office
Start of the cunstruction
works
Completion of construction
works
Construction
Landscape
Wastes (construction,
solid, hazardous, liquid) are left at
the site, the excavated areas
soil, service
roads
The substation area
Visual During closing
the construction site
Compliance with Environmental Law
and Regulations
No additional cost (within the project budget)
TEIAS
4. TEIAS District Office
Start of Operational Acceptance
Completion of Operational Acceptance
Operation Noise Noise level (dBA)
Public complaint
At the border (wall) of the substation
Near residential
areas
Interviews with the local people
In the case of complaint
Control of the limit values determined in the related regulation
Not High
TEİAS
4. TEIAS District Office
Taking the substation into
operation
Completion of the economic
life of the substation
24
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
When would the
How would the parameters be
What are the Where would
Phase Subject parameters,
which would be monitored?
the parameters be
monitored?
parameters be The Institute monitored/typ
es of the monitoring equipment
monitored - Why would the that controls –
frequency of the
measurements / continuous
measurement?
parameters be Cost Start Date Finish Date frequency of
monitored? the control
Electromagnetic Field Strengths
Distance between the
substation and the wall/fence
Documents
related to the equipment
procurement
Grounding resistance (ohm)
Within the substation and substation area
Visual observation
Interviews with the people at
the near residential
areas
Grounding measurement
Taking the substation into the operation
Any problem, failure in the grounding
Compliance with Regulation on the
precautions regarding the protection of environment and
public health from the negative effects of
non-ionizing radiation
Not High
TEIAS
4. TEIAS District Office
Taking the substation into
operation
Completion of the economic
life of the substation
Operation Health and
Safety
Technical training
in terms of operation and maintenance
Protective
equipments and clothes (whether
usage or not)
The substation area
Visual Maintenance works (proper
periods)
Compliance with related labour health
and safety regulations
No additional cost (within the
operation budget)
TEİAS
4. TEIAS District Office
Taking the substation into
operation
Completion of the economic
life of the substation
Operation SF6 SF6 gas pressure
All bays With pressure
meter
During the operation
(continuously)
Compliance with the Environmental Law
and Regulations
In necessaty of operation
No additional cost (within the
operation budget)
TEİAS
4. TEIAS District Office
Taking the substation into
operation
Completion of the economic
life of the substation
25
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
When would the
How would the parameters be
What are the Where would
Phase Subject parameters,
which would be monitored?
the parameters be
monitored?
parameters be The Institute monitored/typ
es of the monitoring equipment
monitored - Why would the that controls –
frequency of the
measurements / continuous
measurement?
parameters be Cost Start Date Finish Date frequency of
monitored? the control
Operation
Fire Risk
SF6 gas pressure
cable ends
isolators
cable connection
points
Primary and secondary controllers
Substation area
Technical tests and standard maintenance
tests performed by the
controllers
Semi-annually / in the case of maintenance, control and
failure
Due to fire risk
To comply Electric Intense Current Plants
Regulation requirements related
to fire safety, to repair the worn, broken
parts, to minimize the risk of accident and to
prevent the outage
No additional cost (within the
operation budget)
TEİAS
4. TEIAS District Office
Taking the substation into
operation
Completion of the economic
life of the substation
Operation Substation Oil
Oil characteristic parameters
(density, acidity, viscosity,
corrosive sulfide, flash point, PCB,
color)
Transformers
Physical, chemical
analyses done by TEIAS Test Laboratories
Bi yearly/daily, weekly, monthly
in the case of failure
Quality control of the substation oil
Not high (within operation budget)
TEIAS
4. TEIAS District Office
Taking the substation into
operation
Completion of the economic
life of the substation
26
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
27
Phase Subject
What are the parameters,
which would be monitored?
Where would the
parameters be monitored?
How would the parameters be monitored/typ
es of the monitoring equipment
When would the
parameters be monitored - frequency of
the measurements
/ continuous measurement?
Why would the parameters be
monitored? Cost
The Institute that controls – frequency of the control
Start Date Finish Date
Solid-Liquid and Hazardous
Wastes (automobile accumulator, substation oil)
Contamination within the area of
substation (wastes, smell
etc.)
Defective equipment
wastes
Contaminants in the waste
substation oil (Arsenic,
Cadmium, Lead, Total Halogens, PCBs, Flashing
point)
Substation area
Visual
Analyses
During the operation
period
In the case of defection,
failure, completion of the economic
life of the equipments
Completion of the economic
life of the substation oil
Compliance with, Solid Waste Control Regulation and Soil
Pollution Control Soil Pollution Control and Contaminated Sites
by Point-Source Regulation,
Hazardous Waste Control Regulation
Compliance with Waste Oil Control
Regulation
Not high
(changing by depending on municipalities
and/or licensed recovery plant)
Not high (depending on
the firm/laboratory conducting the
analysis)
TEIAS
4. TEIAS District Office
Municipality
Provincial Directorate of Environment and Forestry
Taking the substation into
operation
Completion of the economic
life of the substation
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
28
CHAPTER - IV
INSTITUTIONAL ARRANGEMENTS
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
29
4. INSTITUTIONAL ARRANGEMENTS In this chapter, information about the responsibilities and procedures related to mitigation
measures and monitoring, environmental information flow chart, decision making hierarchy
on environmental management will be given and how the data gathered from the monitoring
is analyzed and used in an efficient way to maintain a sustainable environmental performance
will be mentioned.
4.1 Liabilities and Procedures related to the Mitigation Measures and Monitoring
“Mitigation Plan” which covers the mitigation measures to be taken to minimize the negative
possible environmental effects due to the planning/design, construction and operation
activities is presented in chapter-II. “Monitoring Plan” which aims to control the
implementation clauses of the procedures and measures mentioned in the “mitigation plan” is
provided in chapter-III. “Mitigation and monitoring plans” are the basic elements forming the
“Environmental Management Plan” prepared within the content of “Political, Forensic and
Administrative Framework” section in environmental impact assessment reports.
4.2 Environmental Information Flow (Reporting and the frequency of the report
submission)
In order to devise and implement a successful environmental management plan, the elements
which are supposed to be obeyed should be determined carefully. Within this scope, it is
abided by the subjects mentioned in the international regulations and communiqués.
Environmental issues in Turkey Clauses predicates on the clauses of “Environmental
Assessment Regulation” published in official gazette on 17 July 2008 with no.26939.
According to the regulation, Article.32 Appendix-2 List of Projects, the energy transmission
plants (transmission lines, substations, switchyards) having 154 kV or above voltage and a
length of 15 km or longer, are within the coverage of the Turkish EIA Regulation and “EIA
Not Necessary Certificate” must be obtained for these Appendix-2 List of Project. Since 380
kV Kartal GIS Substation will be connected with 380 kV Maltepe GIS Substation-Kartal GIS
Substation Underground Cable having a length of 8 km, “EIA Not Necessary Certificate”
must be obtained for the proposed Kartal substation project. The obtained certificate (dated
May 04, 2010) for the project is presented in Appendix-F.
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
30
4.3 Kartal GIS Substation Environmental Information Flow:
Environmental information flow chart (Figure 4.1) for the proposed Kartal GIS Substation
project based on the mentioned regulation above and the table describing the organization are
presented below (Table 4.1).
Figure 4.1. Environmental Information Flow
(*): TEIAS (as the project owner) with the help of TEIAS’s district offices shall audit the
environmental performance of the contractor and controls whether the contractor obeys to the
issues determined in the EMP. Within this scope, the contractor is liable to meet the
environmental requirements and to submit the reports (in quarterly period) covering the
construction activities and their corresponding mitigation measures to TEIAS.
(**): In the case of necessity, the project site is audited checking in place and approved by the
World Bank representatives.
Environment Management Plan (EMP) is prepared in answer to the request from World Bank
EIA and Required permits are obtained
The prepared EMP is submitted by the Project Owner (TEIAS) to the World Bank
EMP Application Report (Monitoring Report), which is prepared/had made by the Contractor based on the EMP and Monitoring Program, is submitted to the Project
Owner (TEIAS)
The EMP Application Reports approved by the Project Owner (TEIAS) is submitted to the World Bank (*)
T he submitted report is controlled and approved bythe World Bank (**)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
31
Table 4.1 Organization Table
Action Institutional Responsibility Monitoring Data Collection Construction
Monitoring will be performed by the contractor or consultancy firm hired by the contractor. The report (monitoring) prepared by collecting monitoring data will be submitted to the Project Owner (TEIAS) in a quarterly basis.
Data Analysis Construction
TEIAS related district office (4. TEIAS District Office) will control the accuracy of the data in the reports (by examining the data validity in place). Then, the district office will send the report to the TEIAS General Directorate (Ankara) for control and approval. If TEIAS (Environment, Estate and Expropriation Department) approve the report, the report is sent to the World Bank.
Management Action Construction
Ministry of Environment and Forestry has the authority to shutdown, change the operations etc. if any illegal or unregulated situation is observed.
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
32
CHAPTER - V
PUBLIC CONSULTATION WITH PROJECT AFFECTED GROUPS and NON-
GOVERNMENTAL ORGANIZATIONS (NGO)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
33
5. GROUPS WHICH WILL BE AFFECTED BY THE PROJECT AND DISCUSSIONS WITH VOLUNTARY AGENCIES (NGO)
Likely affected local people by GIS Substation was determined by considering the area
of inspection and public participation meeting was held in Zübeyde Hanım Primary School
Meeting Room in Çınardere District, Pendik County on 14 January 2010 at 2 p.m. The
announcement of the meeting was published in the national “Güneş” Gazette and in the local
“Bizim Anadolu” Gazette on 01 January 2010. All local people, related authorities,
institutions/associations, headmen were invited to the meeting. The detailed information
regarding the meeting is presented below.
Meeting Place and Date:
The meeting was held on the date of 14 January 2010 at 2 p.m. in the meeting room of
Zübeyde Hanım Primary School within the boundary of Çınardere District in İstanbul.
Evaluation of the Meeting:
The photographs relating to the meeting, the participation list and the information
brochures distributed to the participants are present in the Appendix.D.
Dates of Interviews/Pre-Preparations
The headman of Çınardere District where the project site locates within Pendik County
was interviewed with on the dates of 18 November 2009 and 12 January 2010. Moreover,
before the date of the meeting, the administration of Zübeyde Hanım Primary School where
the meeting was held was interviewed with on 12 January 2010.
After the mentioned meetings, the public participation meeting was held in the meeting
room of Zübeyde Hanım Primary School in Çınardere District, Pendik County, Istanbul
Province on 14 January 2010 at 2 p.m.
‐ Places which discussions were implemented:
Discussions/interviews were implemented with the headman of Çınardere District via both
telephone and visit in place.
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
34
‐ Who were invited to discussion(s):
The public to be possibly affected from the project and who were living within the borders
of the proposed GIS Substation investigation area has been invited to the subject meeting.
Relevant people were invited to the meeting by means of correspondences with headman of
related districts (Photo.12/Appendix.D) and local and national newspaper announcements
(Güneş Newspaper Turkey Edition and Bizim Anadolu Local Newspaper of İstanbul Province
on January 1 2010, Appendix.D).
‐ Who were participated in discussions:
Owner of the project (TEİAŞ) and above mentioned community dwellers and headmen
were involved in discussions and relevant photographs are presented in Appendix.D.
‐ Program and Calendar of the Meeting:
First, information about the project site location, possible environmental impacts and
mitigations of the impacts was given to the participants. Then, the questions of the
participants were answered by the TEIAS personals. Furthermore, informative brochures
about the proposed project and electromagnetic field were distributed to the participants and
the contact information of TEIAS General Directorate and TEIAS Related District Offices
was given to the participants to reach if they had any question or problem.
‐ Minutes of Meeting:
The questions raised by the participants and the answers given to these questions are
presented below:
Question (by school director): During the construction of the substation will there be
any noise affecting the students, especially during lecture hours?
Answer: The permissible noise level during construction phase will not be exceeded; the
necessary precautions will be taken and so school and neighboring community will not be
disturbed during this phase.
Question: Is it correct that energy transmission lines lead to the health problems such as
headache, weakness, and even cancer?
Answer: Electromagnetic Area formation, effects and international values of limit has
been expressed. Measurement samples which TEİAŞ implemented with TÜBİTAK have been
given. Other electromagnetic interactions exposed have been mentioned also. The information
about radiation kinds has been given.
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
35
Question: Is the underground cable laying in Meşe Street, which is very close to the
project site, done by TEIAS?
Answer: The questioned construction activity has been performing by Anatolian
Electricity Distribution Corporation (AYEDAS), not by TEIAS, and the mentioned cable is
medium-voltage distribution cable.
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
36
APPENDICES
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
37
APPENDIX-A
Satellite Image of the Project Site
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
38
Satellite Image
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
39
APPENDIX-B
General Site Plan
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
40
APPENDIX-C
Photos of the Project Site
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
41
Photo.1 (Project Site)
Photo.2 (Project Site/ exiting 154 kV Kartal Substation)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
42
Photo.3 (Project Site/ exiting 154 kV Kartal Substation)
Photo.4 (Project Site/ exiting 154 kV Kartal Substation)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
43
Photo.5 (Project Site/ exiting 154 kV Kartal Substation)
Photo.6 (Project Site/ exiting 154 kV Kartal Substation)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
44
APPENDIX-D
Public Consultation Gazette Announcement
Brochure Participation List
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
45
Gazette Announcement (1) – Local Newspaper
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
46
Gazette Announcement (2) – National Newspaper
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
47
Brochure (1-a)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
48
Brochure (1-b)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
49
Brochure (2-a)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
50
Brochure (2-b)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
51
Public Consultation Participation List (1)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
52
380 kV KARTAL GIS SUBSTATION
PUBLIC CONSULTATION MEETING PHOTOS
14 January 2010 / 14.00 Zübeyde Hanım Primary School Meeting Room / İSTANBUL
Photo 7.
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
53
Photo 8.
Photo 9. (Interview with the Headman)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
54
Photo 10. (Interview with the Headman)
Photo 11. (Meeting Announcement/Announcement Clipboard of Headman)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
55
Photo 12. (Meeting Announcement)
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
56
APPENDIX-E
Associations/Institutions Correspondences
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
57
APPENDIX-F
“EIA Not Necessary” Certificate
TEIAS 380 kV KARTALGIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN
58
Project Team Preparing 380 kV Kartal GIS Substation Environmental Management Plan
Project Owner: TEIAS (Turkey Electricity Transmission Corporation) General Directorate
Project Location: İstanbul Province, Pendik County
Project Name: 380 kV Kartal GIS Substation
Name&Surname Occupation Signature
Gul MISIRLI Architect
Dilek KESKIN
Geological Engineer
(Environmental Sciences
Master Degree)
Mustafa GOKHARMAN Electrical Engineer
Burcu BARUT Agricultural Engineer, M.S.
Murat GURSOY Chemical Engineer
Gozde TEZCE Environmental Engineer,
M.S.