Local Single Sky ImPlementation (LSSIP) GEORGIA · signature confirms the correctness of the...

59
Year 2015 - Level 1 EUROCONTROL Local Single Sky ImPlementation (LSSIP) GEORGIA

Transcript of Local Single Sky ImPlementation (LSSIP) GEORGIA · signature confirms the correctness of the...

Year 2015 - Level 1

EUROCONTROL

Local Single Sky ImPlementation (LSSIP) GEORGIA

LSSIP Year 2015 Georgia Released Issue

DOCUMENT IDENTIFICATION SHEET

LSSIP for Georgia

Infocentre Reference: 16/01/29-69

Document Identifier Edition: Year 2015

LSSIP Year 2015 Georgia Edition Date: 14/04/2016

LSSIP Focal Point – Vladislav Kuljanishvili E-mail: [email protected] Head of ANS

LSSIP Contact Person – Predrag Vranjkovic E-mail: [email protected]

Unit DPS/PEPR

Status Intended for

Working Draft General Public

Draft Agency Stakeholders

Proposed Issue Restricted Audience

Released Issue

Accessible via: Internet (www.eurocontrol.int)

Path: Y:\03 LSSIP\1. LSSIP States\Georgia (GE) - PV\Year 2015\Released\LSSIP Year 2015_Georgia_Released.docx

LINKS TO REFERENCE DOCUMENTS

1 LSSIP Guidance Material http://www.eurocontrol.int/articles/lssip

2 ESSIP Plan Edition 2015 Working - https://www.eatmportal.eu/working

Public - https://www.atmmasterplan.eu/ 3 European ATM Portal https://www.eatmportal.eu/working

4 ESSIP Report 2014 http://www.eurocontrol.int/pepr

5 STATFOR Forecasts http://www.eurocontrol.int/statfor

6 Acronyms and abbreviations

http://www.eurocontrol.int/articles/glossaries

7 LSSIP Documents http://www.eurocontrol.int/articles/lssip

LSSIP Year 2015 Georgia Released Issue

APPROVAL SHEET

The following authorities have approved all parts of the present issue of the LSSIP document and their signature confirms the correctness of the reported information and reflects their commitment to implement the actions laid down in the European Single Sky ImPlementation (ESSIP) documents.

LSSIP Year 2015 Georgia Released Issue

LSSIP DOCUMENT PRODUCTION

The following table shows the experts who have co-ordinated the different contributions, produced and review this LSSIP Document.

LSSIP Year 2015 Georgia Released Issue

TABLE OF CONTENTS

Executive Summary ................................................................................................................................. 1 

Introduction .............................................................................................................................................. 4 

National ATM Environment ................................................................................................... 5 Chapter 1 -1.1  Geographical Scope ................................................................................................................ 5 

1.1.1  International Membership ......................................................................................................... 5 1.1.2  Geographical description of the FIR(s) ..................................................................................... 5 1.1.3  Airspace Classification and Organisation ................................................................................. 6 

1.2  National Stakeholders .............................................................................................................. 6 1.2.1  Civil Regulator(s) ...................................................................................................................... 7 1.2.2  Georgian ANSP (SAKAERONAVIGATSIA) .............................................................................. 8 1.2.3  Airports ...................................................................................................................................... 9 1.2.4  Military Authorities ................................................................................................................... 10 

Traffic and Capacity ............................................................................................................ 12 Chapter 2 -2.1  Evolution of traffic in Georgia ................................................................................................. 12 2.2  TBILISI ACC .......................................................................................................................... 12 

2.2.1  Summer 2015 performance .................................................................................................... 12 2.2.2  Planning Period 2016-2020 - Summer ................................................................................... 13 

ESSIP Report recommendations ........................................................................................ 15 Chapter 3 -

National Projects ................................................................................................................. 16 Chapter 4 -

Regional Co-ordination ....................................................................................................... 20 Chapter 5 -5.1  FAB Co-ordination ................................................................................................................. 20 5.2  FAB Projects .......................................................................................................................... 20 5.3  Regional cooperation ............................................................................................................. 20 

5.3.1  Regional Cooperation Initiatives ............................................................................................. 20 

ESSIP Objective Implementation ....................................................................................... 21 Chapter 6 -6.1  Conventions ........................................................................................................................... 21 6.2  ESSIP Objectives Implementation progress .......................................................................... 22 

ANNEXES

LSSIP Year 2015 Georgia 1 Released Issue

Executive Summary

National ATM Context

Georgia is committed to implement Single European Sky objectives both from regulatory or technical perspectives. Governmental Decree №2497 of December 26, 2014 defines the roadmap on the implementation of EC regulations stemming from Common Aviation Area Agreement (CAAA). TWINNING project II (Legal approximation of Georgian Civil Aviation Regulations with EU standards) has started in July 2015.

Georgian ANSP (SAKAERONAVIGATSIA) is in the process of upgrading its ATC system which is scheduled to be operational in 2017-2018.

Tbilisi airport operator TAV Urban LCC is running the project on the renovation of current runway in Tbilisi international airport which is scheduled to be finalised by the end of 2016.

Traffic and Capacity

Traffic in Georgia increased by 9.1 % during Summer 2015 (May to October), when compared to the same period during 2014.

The STATFOR medium-term forecast (MTF) predicts an average annual increase between 3.6% and 8.2%, with a baseline growth of 5.9% during the planning 2016-2020 cycle. Overall planned traffic and capacity increase will be mainly handled by means of introduction of Free Route airspace, ATFCM measures, optimisation and implementation of ATS route network, improved manpower utilisation and ongoing national PBN project focused on implementation of RNAV1 and APV LNAV/VNAV procedures.

ESSIP Objective Implementation

LSSIP Year 2015 Georgia 2 Released Issue

Implementation progress shown in 2015 has been achieved by improved coordination between stakeholders. Technical implementation of number of objectives that was carried out in previous years, were now followed by implementation of relevant procedures and training of personnel. This contributed to finalization of the respective objectives.

In addition, it has to be mentioned that after thorough examination and conducted study, some of the objectives proved to lack operational need, whereas another objective, which was initially not applicable for Georgia, had been challenged and respective project initiated by the end of 2015. This resulted in joining the applicability area of number of objectives.

For those objectives, which have the status ‘Late’ i.e. FCM01 and FCM03, challenge remains inability to exchange data with NM due to technical constraints of current ATC system, which is due to resolve by 2016-2017, once the new ATC system is put into operation.

As for the objective INFO04, status ‘Late’ is due to the lack of software upgrade, which is planned for 2016, which will enable full implementation of the integrated briefing.

LSSIP 2015 - Georgia * FOC Date

█ Planned implementation date (see legend at the bottom of the table)

State-related ESSIP Objectives

<=

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

AOM13.1 Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) handling

*

AOM19 Implement Advanced Airspace Management *

AOM21.1 Implementation of Direct Routing [PCP]

[E] *

AOM21.2 Implement Free Route Airspace [PCP]

[E] *

AOP03 Improve runway safety by preventing runway incursions *

ATC02.5 Implement ground based safety nets - Area Proximity Warning - level 2

*

ATC02.6 Implement ground based safety nets - Minimum Safe Altitude Warning - level 2

*

ATC02.7 Implement ground based safety nets - Approach Path Monitor - level 2

ATC12.1 Implement automated support for conflict detection, resolution support information and conformance monitoring

*

ATC15 Implement, in En-Route operations, information exchange mechanisms, tools and procedures in support of Basic AMAN operations

ATC16 Implement ACAS II compliant with TCAS II change 7.1 *

ATC17 Electronic Dialogue as Automated Assistance to Controller during Coordination and Transfer

*

COM10 Migrate from AFTN to AMHS *

COM11 Implementation of Voice over Internet Protocol (VoIP) in ATM

*

FCM01 Implement enhanced tactical flow management services *

FCM03 Implement collaborative flight planning *

FCM04 Implementation of Short Term ATFCM Measures - phase 1

FCM05 Implementation of interactive rolling NOP [PCP]

[E] *

FCM06 Traffic Complexity Assessment [PCP]

[E] *

INF04 Implement integrated briefing *

INF07 Electronic Terrain and Obstacle Data (TOD) *

ITY-ACID Aircraft identification

ITY-ADQ Ensure quality of aeronautical data and aeronautical information

*

LSSIP Year 2015 Georgia 3 Released Issue

LSSIP 2015 - Georgia * FOC Date

█ Planned implementation date (see legend at the bottom of the table)

ITY-AGDL Initial ATC air-ground data link services above FL-285 *

ITY-AGVCS2

Implement air-ground voice channel spacing requirements below FL195

*

ITY-COTR Implementation of ground-ground automated co-ordination processes

*

ITY-FMTP Apply a common flight message transfer protocol (FMTP) *

ITY-SPI Surveillance performance and interoperability *

NAV03 Implementation of P-RNAV

NAV10 Implement APV procedures *

SAF10 Implement measures to reduce the risk to aircraft operations caused by airspace infringements

*

SAF11 Improve runway safety by preventing runway excursions *

Airport-related ESSIP Objectives

<=

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

UGTB-Tbilisi Airport

AOP04.1 Implement Advanced Surface Movement Guidance and Control System (A-SMGCS) Level1

AOP04.2 Implement Advanced Surface Movement Guidance and Control System (A-SMGCS) Level 2

AOP05 Implement Airport Collaborative Decision Making (CDM)

AOP10 Time Based Separation [PCP]

[E] AOP11 Initial Airport Operations Plan

[PCP] [E] *

AOP12 Improve runway and airfield safety with ATC clearances monitoring

[PCP] [E]

ATC07.1 Implement AMAN tools and procedures

ENV01 Implement Continuous Descent Operations (CDO) techniques for environmental improvements

ENV02 Implement Collaborative Environmental Management (CEM) at Airports

Understanding the Table

Objective Completed No Plan

Objective Partly Completed Missing Data

Objective Planned Not Applicable – GE does not participate in this objective

Late

E= Essential – Master Plan Reference PCP = Pilot Common Project

NOTE: The year where the coloured box is placed indicates the ‘Implementation Completion Date’ as stated in the ESSIP for each objective. The colour-code indicates the Local progress with respect to this date.

LSSIP Year 2015 Georgia 4 Released Issue

Introduction

The Local Single Sky ImPlementation documents (LSSIPs), as an integral part of the ESSIP/LSSIP mechanism, constitute a short/medium term implementation plan containing ECAC States’ actions to achieve the Implementation Objectives as set out by the ESSIP and to improve the performance of their national ATM System. The LSSIP document – Year 2015 describes the situation in the State at the end of December 2015.

The LSSIP documents are structured into 6 chapters to better differentiate the Stakeholder(s) accountable for the information contained in each of them:

Chapter 1 provides an overview of the ATM institutional arrangements within the State, the membership of the State in various international organizations, the organizational structure of the main ATM players - civil and military - and their responsibilities under the national legislation. In addition, an overview of the Airspace Organization and Classification, the ATC Units, the ATM systems operated by the main ANSP are also provided in this chapter.

Chapter 2 provides a comprehensive picture of the situation of Air Traffic, Capacity and ATFM Delay per each ACC in the State. It shows the evolution of Air Traffic and Delay in the last five years and the forecast for the next five years. It gives also the achieved performance in terms of delay during the summer season period and the planned projects assumed to offer the required capacity which will match the foreseen traffic increase and keep the delay at the agreed performance level;

Chapter 3 provides a set of recommendations extracted from the ESSIP Report which are relevant to the state/stakeholders concerned. The state reports how they have handled those recommendations and the actions taken during the year to address the concerns expressed by those recommendations;

Chapter 4 provides a set of the main ATM national projects which contribute directly to the implementation of the ATM MP OIs and/or Enablers and ESSIP related Objectives. The description, timescale, progress made and expected contribution to the ATM Key Performance Areas are provided by the states per each project included in this chapter;

Chapter 5 deals with the ATM Regional Coordination. It provides an overview of the FAB cooperation and Projects and also all other regional initiatives and Projects which are out of the FAB scope. The content of this chapter generally is developed and agreed in close cooperation between the states concerned;

Chapter 6 contains high-level information on progress and plans of each ESSIP Objective. The information for each ESSIP Objective is presented in boxes giving a summary of the progress and plans of implementation for each Stakeholder. The conventions used are presented at the beginning of the section.

Note: Chapter 6 is completed with a separate document called LSSIP Level 2. This document consists of a set of tables organised in line with the list of ESSIP Objectives. Each table contains all the actions planned by the four national stakeholders to achieve their respective Stakeholder Lines of Action (SLoAs) as established in the ESSIP.

Note: The information contained in Chapter 6 is deemed sufficient to satisfy State reporting requirements towards ICAO in relation to ASBU (Aviation System Block Upgrades) monitoring.

LSSIP Year 2015 Georgia 5 Released Issue

National ATM Environment Chapter 1 -

1.1 Geographical Scope

1.1.1 International Membership

Georgia is a Member of the following international organisations in the field of ATM:

Organisation Since

ECAC 2005

EUROCONTROL

January 1st 2014

European Union N/A

EASA Working Agreement (signed 2009)

ICAO 1994

NATO N/A

ITU 1993

1.1.2 Geographical description of the FIR(s)

The geographical scope of this document addresses the Tbilisi FIR.

Tbilisi FIR is surrounded by the following 4 State FIRs: Rostov FIR (Russia), Baku FIR (Azerbaijan), Yerevan FIR (Armenia), Ankara FIR (Turkey). This is graphically presented on the figure below.

LSSIP Year 2015 Georgia 6 Released Issue

1.1.3 Airspace Classification and Organisation

Classification of Georgian Airspace is presented on the picture below.

1.2 National Stakeholders

The main National Stakeholders involved in ATM in Georgia are:

- Ministry of Economy and Sustainable Development of Georgia; Transport policy department is body integrated within the Ministry;

- Aircraft Accident and Incident Investigation Bureau (AAIB) is under Ministry of Economy and Sustainable Development of Georgia

- Ministry of Defence

o Land Forces Command;

- Georgian Civil Aviation Agency (GCAA) is a Legal Entity of Public Law (LEPL) is under the state control of the Ministry of Economy and Sustainable Development;

- Sakaeronavigatisa LTD (SAN) the only Air Navigation Service Provider in Georgia (ANSP is organised under private law, responsible for the provision of ANS in Georgia);

- United Georgian Airports

o TAV URBAN Georgia LLC (Airport Operator);

- National Airlines;

- Training Institutions/Organisations.

LSSIP Year 2015 Georgia 7 Released Issue

The activities of stakeholders are detailed in the following subchapters and their relationships are shown in figure below:

1.2.1 Civil Regulator(s)

1.2.1.1 General information

Different national entities having regulatory responsibilities in ATM in Georgia are summarised in the table below.

Activity in ATM: Organisation responsible

Legal Basis

Rule-making GCAA Air Code 29.10.1996 Article 9

Law on Governance and Regulation of Transport Field N 4593 –Iს (S) of 30.03. Article 7 (G), Article 8

Safety Oversight GCAA Law on Governance and Regulation of Transport Field N 4593 –Iს (S) of 30.03. Article 7 (D)

Air Code 29.10.1996 Article 8

Enforcement actions in case of non-compliance with safety regulatory requirements

GCAA Law on Administrative Violation Articles 111 - 1115

Airspace President of Georgia

GCAA /MOD

Air code 29.10.1996 Article 11

Parliamentary decree N363on Airspace structure and classification 24.12.2013.

Presidential decree N253 on distribution of responsibilities and roles between state agency regarding civil and state aviation oversight and control 09.06.2003.

Environment GCAA

Ministry of environment

Air Code 29.10.1996 Article 47

Security GCAA MIA Air Code 29.10.1996 Chapter V

Accident Investigation AAIB Ministerial Order №1-1/242 on Incident and accident investigation rules in civil aviation of 4 September 2014.

LSSIP Year 2015 Georgia 8 Released Issue

1.2.1.2 The Georgian Civil Aviation Agency (GCAA)

The Georgian Civil Aviation Agency is a Legal Entity of Public Law (LEPL), established by Article 7 of Transport Law. The Agency is under the state control of the Minister of Economy and Sustainable Development of Georgia. GCAA has its own operating budget and is functionally separated from the Service Provider. Ministerial Order on Statute of the Agency establishes its internal structure and main functions.

The main functions of the Agency are to develop regulations, supervise their implementation and application and enforce the compliance with the requirements as necessary. The figure in the Annex B indicates the organisational structure of the Agency.

Complimentary information could be found on www.gcaa.ge.

Annual Report published: Under ongoing implementation of occurrence reporting system and continuous maturing the oversight system in Georgia GCAA has produced second safety report. The report is currently under internal review and is planned to be addressed under national SSP committee to improve the overall reporting, analysis and safety improvement.

1.2.2 Georgian ANSP (SAKAERONAVIGATSIA)

Name of the ANSP: SAKAERONAVIGATSIA

Governance: Limited Liability Company

Ownership: 100% State owned

Services provided Y/N Comment

ATC en-route Y

ATC approach Y

ATC Airport(s) Y

AIS Y

CNS Y

MET Y

ATCO training Y Basic training is outsourced. Other kind of trainings are provided in-house.

Others AFIS

Additional information: None

Provision of services in other State(s):

N

Number of air traffic controllers

Supervisors 7

Senior Controller 13

ACC 36

APP 26

TWR 31

SAKAERONAVIGATSIA organisational chart is presented in Annex B.

ANSP web site: www.airnav.ge

LSSIP Year 2015 Georgia 9 Released Issue

1.2.2.1 ATC systems in use

FDPS

Specify the manufacturer of the ATC system currently in use: SELEX SI

Upgrade1 of the ATC system is performed or planned? Upgrade of the system is ongoing

Replacement of the ATC system by the new one is planned? 2017

ATC Unit The ATS services are provided from main centre in Tbilisi ACC

SDPS

Specify the manufacturer of the ATC system currently in use: SELEX Si

Upgrade1 of the ATC system is performed or planned? Upgrade of the system is ongoing

Replacement of the ATC system by the new one is planned? 2017

ATC Unit The ATS services are provided from main centre in Tbilisi ACC

1.2.2.2 ATC units

The ATC units in the Georgian airspace which are of concern to this LSSIP are the following:

ATC Unit Number of sectors Associated FIR(s) Remarks

En-route TMA

Tbilisi ACC 1 Tbilisi FIR 2 sectors

Tbilisi TMA 1 Tbilisi FIR

Batumi TMA 1 Tbilisi FIR

Kutaisi TMA 1 Tbilisi FIR

1.2.3 Airports

The main international Airports in Georgia are:

Tbilisi International Airport

Batumi International Airport,

Kutaisi International Airport

Tbilisi International Airport is owned by United Airports Georgia LLC but is operated by TAV Urban Georgia LLC. Batumi International Airport is owned by the Ministry of Economy and Sustainable Development of Georgia but is operated by TAV Batumi Operations.

Georgia has some airfields for general aviation as well.

1.2.3.1 Airport(s) covered by the LSSIP

The airport covered by this edition of LSSIP document is TBILISI International Airport (TIA) as a main international airport in Georgia.

1 Upgrade is defined as any modification that changes the operational characteristics of the system (SES Framework Regulation 549/2004, Article 2 (40))

LSSIP Year 2015 Georgia 10 Released Issue

1.2.4 Military Authorities

1.2.4.1 Regulatory role

Regulatory framework and rule-making

Oversight

1.2.4.2 Service Provision role

OAT GAT

OAT and provision of service for OAT governed by national legal provisions?

Y Provision of service for GAT by the Military governed by national legal provisions?

N

Level of such legal provision: Air Code. Presidential Decree 253, on distribution of responsibilities between civil and military aviation authorities.

Level of such legal provision: N/A

Authority signing such legal provision: President/Parliament/ MOD

Authority signing such legal provision:

These provisions cover: These provisions cover:

Rules of the Air for OAT Y

Organisation of military ATS for OAT N Organisation of military ATS for GAT N/A

OAT/GAT Coordination Y OAT/GAT Coordination N/A

ATCO Training Y ATCO Training N/A

ATCO Licensing N ATCO Licensing N/A

ANSP Certification N ANSP Certification N/A

ANSP Supervision Y ANSP Supervision N/A

Aircrew Training N ESARR applicability N/A

Aircrew Licensing N

Additional Information: There are no military ATS provided on [civilian airdromes/for GAT traffic].

Additional Information: There are no military ATS provided on [civilian airdromes/for GAT traffic, civilian airspace users].

Means used to inform airspace users (other than military) about these provisions:

Means used to inform airspace users (other than military) about these provisions:

National AIP Y National AIP N/A

National Military AIP N National Military AIP N/A

EUROCONTROL eAIP Y EUROCONTROL eAIP N/A

Other: Other: N/A

OAT GAT

National oversight body for OAT: MoD N/A

Additional information: Nil Additional information: Nil

OAT GAT

Services Provided: Services Provided:

En-Route N En-Route N/A

Approach/TMA N Approach/TMA N/A

Airfield/TWR/GND N Airfield/TWR/GND N/A

AIS N AIS N/A

MET N Provided by civil MET N/A

LSSIP Year 2015 Georgia 11 Released Issue

Military ANSP providing GAT services SES certified?

N/A If YES, since: N/A Duration of the Certificate:

N/A

Certificate issued by: N/A If NO, is this fact reported to the EC in accordance with SES regulations?

N/A

Additional Information:

1.2.4.3 User role

1.2.4.4 Flexible Use of Airspace (FUA)

Note: FUA concept is implemented under ICAO standards and adopted to national environment. Under ongoing regulatory activity EU FUA Concept is planned to be implemented 2016 – 2017.

SAR Y GCAA in collaboration with MIA and MOD

SAR N/A

TSA/TRA monitoring Y SAN FIS N/A

Other: <Specify> Other: <Specify>

Additional Information: Additional Information: Nil

IFR inside controlled airspace, Military aircraft can fly?

OAT only GAT only Both OAT and GAT Y

If Military fly OAT-IFR inside controlled airspace, specify the available options:

Free Routing Y Within specific corridors only Nil

Within the regular (GAT) national route network Y Under radar control Y

Within a special OAT route system Nil Under radar advisory service Nil

If Military fly GAT-IFR inside controlled airspace, specify existing special arrangements:

No special arrangements N Exemption from Route Charges Y

Exemption from flow and capacity (ATFCM) measures N Provision of ATC in UHF Nil

CNS exemptions: RVSM N 8.33 N/A Mode S N ACAS N

Others:

Military in Georgia applies FUA requirements as specified in the Regulation No 2150/2005: The implementation of requirements under Regulation No 2150/2005 are underway in the frames of ongoing ERCTL support project.

FUA Level 1 implemented: N

FUA Level 2 implemented: N

FUA Level 3 implemented: N

LSSIP Year 2015 Georgia 12 Released Issue

Traffic and Capacity Chapter 2 -

2.1 Evolution of traffic in Georgia

2015

Traffic in Georgia increased by 9.1 % during Summer 2015 (May to October), when compared to the same period during 2014.

2016-2020

The STATFOR medium-term forecast (MTF) predicts an average annual increase between 3.6% and 8.2%, with a baseline growth of 5.9% during the planning cycle.

2.2 TBILISI ACC

2.2.1 Summer 2015 performance

Traffic Evolution 2015 Capacity Baseline En-route Delay (min/flight) - Summer Capacity

gap Ref value Actual

+ 9.1% 40 (0%) 0.01 0.0 No

The average en-route delay per flight remained at zero in Summer 2015.

Capacity Plan: Sufficient Capacity to meet demand Comments

Summer 2014 performance assessment

The ACC capacity baseline was estimated to be 40. During the measured period, the average peak 1 hour demand was 39 and the average peak 3 hour demand was 23.

0

50.000

100.000

150.000

200.000

250.000

2011 A 2012 A 2013 A 2014 A 2015 F 2016 F 2017 F 2018 F 2019 F 2020 F 2021 F

IFR

flig

hts

Georgia - Annual IFR Movements

IFR movements - Actuals

IFR movements - Baseline forecast

IFR movements - High forecast

IFR movements - Low forecast A = ActualF = Forecast

2012 A 2013 A 2014 A 2015 F 2016 F 2017 F 2018 F 2019 F 2020 F 2021 F

H 9.4% 10.8% 8.1% 7.2% 7.1% 7.5% 6.6%

B -1.7% 2.1% 5.2% 8.7% 7.9% 5.4% 5.7% 5.4% 5.4% 4.8%

L 7.8% 3.8% 2.9% 3.9% 3.7% 3.7% 3.0%

ESRA08 B -2.4% -1.1% 1.7% 1.6% 2.3% 2.3% 2.3% 2.2% 2.7% 1.8%

EUROCONTROL Seven-Year Forecast (September 2015)IFR flights yearly growth

Georgia

LSSIP Year 2015 Georgia 13 Released Issue

2.2.2 Planning Period 2016-2020 - Summer

The planning focuses on the Summer season to reflect the most demanding period of the year from a capacity perspective. This approach ensures consistency with the previous planning cycles.

Capacity Plan

2016 2017 2018 2019 2020

Free Route Airspace

FRAG concept approval

Further implementation of FRAG

Airspace Management Advanced FUA

Implementing and rational use of ASM CDM MIL

Airport & TMA Network Integration

Cooperative Traffic Management

Implement ATFCM measures and improve FMP issues

Improved ATFCM

Enhanced ATFM techniques through

cooperative traffic management

Airspace

Further optimisation and implementation of ATS route network

Reorganisation of lower and upper

airspace

Implementation of 3rd lateral sector

Procedures

finalization OLDI connection with adjacent units

ATS contingency plan approval

Conversion of lower airspace to RNAV5

Implementation of RNAV1 (GNSS) for SID/STAR’s

Implementation of APV LNAV/VNAV (including LNAV-only minima) at all

instrument runway ends as a backup for ILS precision approaches

Staffing

Optimization of manpower planning

Additional Staff recruitment to cope

demand

Technical Technical implementation of new ATS

system

Transfer to new ATS system

Capacity Traffic Management Improvements

Significant Events

Max sectors 2 2 3 3 3

Capacity increase p.a. Sufficient capacity to meet expected demand

Reference profile 15% 7% 6% 8% N/A

2016 2017 2018 20190.01 0.01 0.01 0.010.01 0.01 0.01 0.01

En-route ATFM delay breakdown - Reference ValuesUGGGCTA

AnnualSummer

H 50 25% 54 8% 58 7% 62 7%

Ref. 46 15% 49 7% 52 6% 56 8%

L 42 5% 44 5% 47 7% 50 6%

Open 40 0% 40 0% 40 0% 40 0%

C/R 45 13% 48 7% 51 6% 55 8%

UGGG 40

ACC2015

baseline 2016 2017 2018 2019

Capacity ProfilesProfiles (hourly movements and % increase over previous year)

LSSIP Year 2015 Georgia 14 Released Issue

 

2014 2015 2016 2017 2018 2019 2020

2016‐2019 Reference Capacity Profile 46 49 52 56

Capacity Profile ‐ Current Routes 45 48 51 55

Capacity Profile ‐ High 50 54 58 62

Capacity Profile ‐ Low 42 44 47 50

Capacity Baseline 40 40

2016 ‐ 2020 Plan 50 54 58 62 62

Capacity Profile ‐ Shortest Routes (Open) 40 40 40 40

0

10

20

30

40

50

60

70

Cap

acity profile (movements per hour)

UGGGCTA - Reference capacity profile and alternative scenarios

2016-2020 Planning Period Outlook

No problems are foreseen for Tbilisi ACC in the coming planning cycle.

LSSIP Year 2015 Georgia 15 Released Issue

ESSIP Report recommendations Chapter 3 -

Recommendations issued from the ESSIP Report for 2014 applicable to Georgia for all items that require corrective actions and improvements.

Reference

number Recommendation 2014 Ownership

REC-2014-1 To increase implementation activities related to SES and SESAR improvements with support of EUROCONTROL.

BA, GE

Corrective actions taken:

YES

Description:

National high level meeting was held to address implementation activities related to SES and SESAR. Transport policy department is monitoring the progress related to issues identified and agreed corrective actions.

REC-2014-2 Local Stakeholders that declared delays in implementation of FCM01, NAV03, AOP03, COM10, ITY-FMTP and ITY-COTR, to take corrective measures to reduce the implementation delays.

Local Stakeholders

Corrective actions taken:

YES

Description:

ESSIP objectives AOP03, COM10, FMTP and COTR have been completed in 2015. Objectives FCM01 and NAV03 are being implemented with support from EUROCONTROL and in the framework of integration to the network.

LSSIP Year 2015 Georgia 16 Released Issue

National Projects Chapter 4 -

Name / Code Description - Scope Schedule Status Link with ATM Master Plan / Other references

Expected Contribution to the Key Performance Areas

GCAA (GE)

Transition from AIS to AIM

Establishment of necessary regulatory framework ensures improvement national AIS products and services. Enables TOD implementation.

2015-2019 National legal system is established. TOD plan will be established during 2016. Formal agreements between originators are being negotiated.

ESSIP:INF07, NAV03, NAV10

OI-Steps: AOM-0601, AOM-0602, AOM-0604

Other: -

Capacity: Efficient and reliable obstacle data collection processes will enhance the overall situational awareness in respect of terrain or obstacle hazards and separation assurance, thereby contributing to or enabling informed decisions, and facilitating better use of available capacity (e.g. improved flight procedure design).

Safety: The availability of quality-assured electronic terrain and obstacle data will contribute to increased safety levels and performance in airborne and ground-based systems (e.g. EGPWS, MSAW, APM, SVS, A-SMGCS and Instrument Procedure Design).

Environment: The availability of more accurate digital terrain and obstacle data would potentially enable the design of more fuel effective and noise-reduced performance based approach procedures.

Cost-Efficiency: Operating costs will decrease with the "paperless cockpit" trend, leading to a reduction in printing costs and weight, A more accurate obstacle and terrain dataset will enable more plausible aircraft operating limitation analysis allowing the design of fuel-effective performance based navigation procedures as well as optimized engine maintenance cycles through more accurate take-off performance calculations.

LSSIP Year 2015 Georgia 17 Released Issue

Name / Code Description - Scope Schedule Status Link with ATM Master Plan / Other references

Expected Contribution to the Key Performance Areas

GCAA (GE), SAKAERONAVIGATSIA (GE)

EUROCONTROL Support to GCAA/NSA/ANSP (SUPP-GCAA)

Improve the quality of oversight and address issues related alignment with SES legislation. Improve the performance of ANSP

2016-2018 Ongoing ESSIP:AOM13.1, AOM21.2, FCM05, FCM06, INF07, NAV03, NAV10

OI-Steps: AOM-0202, AOM-0205, AOM-0301, AOM-0401, AOM-0402, AOM-0501, AOM-0502, AOM-0601, AOM-0602, AOM-0604, CM-0101, CM-0102-A, CM-0103-A, DCB-0102, DCB-0103-A, IS-0102, IS-0901-A

Other: -

Safety: Improved safety by ensuring a more streamlined set of regulations and oversight activities

FRA implementation (FRAG)

- 2016-2017 Ongoing ESSIP:AOM21.2

OI-Steps: AOM-0401, AOM-0402, AOM-0501, AOM-0502, CM-0102-A

Other: -

Capacity: Will increase by reduction of flight time, since most flights will be using the shortest routes possible

Safety: Fewer conflicts – since the same number of aircrafts are spread among more routes

Environment: -Reduced CO2 emission, as a consequence of the reduced flight time

Cost-Efficiency: -Low implementation costs b/c implementation of FRA will be supported by the existing ACC equipment

Reduced fuel waste, also a consequence of the reduced flight time and more optimal flight profiles

PBN Implementation (PBN)

Implementation of PBN concept in Georgia in accordance Assembly resolution A37-11.

2016-2019 Ongoing ESSIP:NAV03, NAV10

OI-Steps: AOM-0601, AOM-0602, AOM-0604

Capacity: Reduced aircraft flight time due to the implementation of optimal flight paths

Safety: - Increased airspace safety through the implementation of continuous and stabilized descent procedures using vertical guidance

LSSIP Year 2015 Georgia 18 Released Issue

Name / Code Description - Scope Schedule Status Link with ATM Master Plan / Other references

Expected Contribution to the Key Performance Areas

Other: - Environment: Savings in fuel, reduction in noise and carbon emission, and enhanced environmental protection

Cost-Efficiency: Reduction of costs through implementation of better flight profiles.

GCAA (GE), SAKAERONAVIGATSIA (GE), TBILISI Airport (GE)

Safety Management System (SMS)/ State Safety Plan (SSP) (SMS-SSP)

Streamlining current nation framework related to SMS requirements and establishing new safety regime through SSP.

2014-2016 Ongoing ESSIP:-

OI-Steps: -

Other: -

Safety: Improved overall safety.

SAKAERONAVIGATSIA (GE)

ADS-B implementation (ADS-B)

ADS-B stations installation to provide better coverage in the lower level airspace

2016 Ongoing ESSIP:ITY-SPI

OI-Steps: -

Other: -

Safety: Increase of controller's situational awareness, particularly in areas where there is no surveillance today.

New automated management system for ATS (NEWATC)

Upgrade of current ATC system will replace current operational one.

2017 Ongoing ESSIP:ATC12.1, ATC17, COM10, FCM01, FCM03, ITY-ACID, ITY-SPI

OI-Steps: CM-0201, CM-0202, CM-0203, CM-0205, CM-0207-A, IS-0102

Other: -

Capacity: - New ATC system will allow to introduce new vertical sectors. To connect with NM and exchange data for better planning and airspace utilization

Safety: - New safety nets options and other tools that were developed by industry recently

Cost-Efficiency: Low maintenance cost

The Surveillance Data Distribution System Implementation (SDDS)

Surveillance Data Distribution System implementation

2016-2017 Ongoing ESSIP:ITY-SPI

OI-Steps: -

Other: -

Capacity: -The Surveillance Data Distribution System (SDDS) is a part of the AMS (Airspace Management system) and allows the surveillance data from the various surveillance sensors to be received on the network providing continuous aircraft radar data to the ATC units and other systems (e.g. terminal areas, military, flow management units, etc.) which are connected to the network.

Cost-Efficiency: - Low cost implementation and maintenance.

LSSIP Year 2015 Georgia 19 Released Issue

Name / Code Description - Scope Schedule Status Link with ATM Master Plan / Other references

Expected Contribution to the Key Performance Areas

SAKAERONAVIGATSIA (GE), TBILISI Airport (GE)

Runway rehabilitation (RWYR)

Rehabilitation current RWY and taxiways end 2016 Ongoing ESSIP:-

OI-Steps: -

Other: National

Capacity: Increased capacity

Safety: Improved safety

LSSIP Year 2015 Georgia 20 Released Issue

Regional Co-ordination Chapter 5 -

5.1 FAB Co-ordination

Georgia is currently not participating in any of the FAB initiatives.

5.2 FAB Projects

N/A

5.3 Regional cooperation

5.3.1 Regional Cooperation Initiatives

Currently there are no regional coordination projects on-going in Georgia.

LSSIP Year 2015 Georgia 21 Released Issue

ESSIP Objective Implementation Chapter 6 -

6.1 Conventions

Two colour codes are used for each ESSIP Objective ‘box’:

o a colour code is used to show the Objective Scope in the Objective ID cell, and

o another colour code is used to show the Objective Progress in the State and for each national stakeholder.

Obj. ID (*) Obj. Title (By mm/yyyy of overall objective, inc non-State SloAs) Obj. Progress (**) 

State’s high level progress statement  State Impl. Date

REG (By:mm-yyyy) REG high level progress statement 

REG Progress (**) 

REG Impl. Date ASP (By:mm-yyyy) ASP high level progress statement 

ASP. Progress (**) 

ASP Impl. Date MIL (By:mm-yyyy) MIL high level progress statement 

MIL. Progress (**) 

MIL Impl. Date APO (By:mm-yyyy) APO high level progress statement 

APO. Progress (**) 

APO Impl. Date

(*) Objective Scope Code: (**) Objective/Stakeholder Progress Code:

ECAC Completed No Plan

EU+ Partly Completed Not Applicable

Multi-N Planned Missing Data

APT Late

LSSIP Year 2015 Georgia 22 Released Issue

6.2 ESSIP Objectives Implementation progress

AOM13.1 

Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) handling 

Timescales: 

Initial  operational  capability:  01/01/2012 Full operational capability: 31/12/2018 

 

  Planned 

AAMS‐10a(EN), AIMS‐19b(EN), AOM‐0301(OI) 

 ‐  

This objective will be addressed  in  the  frames of national  FUA and ASM optimisation project. However initial  analysis  shows  that  due  to  limited  operation  of OAT  in Georgia  there  is  no  operational  need  to implement EUROAT specification.   

31/12/2017 

REG (By:12/2018) 

GCAA This objective will be addressed  in  the  frames of national FUA project and ASM optimisation project. 

EUROCONTROL Support to 

GCAA/NSA/ANSP 

Planned 

31/12/2017 

ASP (By:12/2018) 

SAKAERONAVIGATSIA This objective will be addressed  in  the  frames of national FUA project ASM optimisation project 

EUROCONTROL Support to 

GCAA/NSA/ANSP 

Planned 

31/12/2017 

MIL (By:12/2018) 

Mil. Authority Militaries  are  operating  in  uncontrolled  airspace  90%  of  time. No significant operational impact therefore.  

‐ 

Not Applicable 

‐ 

 

AOM19 

Implement Advanced Airspace Management 

Timescales: 

Initial  operational  capability:  01/01/2011 Full operational capability: 31/12/2016 

 

  Planned 

AAMS‐11(EN), AOM‐0201(OI), AOM‐0202(OI), AOM‐0205(OI), AOM‐0401(OI), DCB‐0203(OI) 

 ‐  

Under ongoing  national EU regulations establishment project FUA specification and related processes are planned to be addressed. 

31/12/2016 

ASP (By:12/2016) 

SAKAERONAVIGATSIA Under  ongoing    national  EU  regulations  establishment  project  FUA specification and related processes are planned to be addressed. This SLoA is planned to be addressed accordingly 

‐ Planned 

31/12/2016 

 

AOM21.1 

Implementation of Direct Routing 

Timescales: 

Initial  Operational  Capability:  01/01/2015 Full Operational Capability: 31/12/2017 

[PCP] 

[Essential]  

Not Applicable 

AOM‐0401(OI), AOM‐0402(OI), AOM‐0500(OI) [E] 

 ‐  

Georgia plans to implement FRA, therefore direct routing is considered as not necessary.    ‐ 

ASP (By:12/2017) 

SAKAERONAVIGATSIA Georgia  plans  to  implement  FRA,  therefore  direct  routing  is considered as not necessary.   

‐ 

Not Applicable 

‐ 

 

LSSIP Year 2015 Georgia 23 Released Issue

AOM21.2 

Implement Free Route Airspace 

Timescales: 

Initial  operational  capability:  01/01/2015 Full operational capability: 31/12/2021 

[PCP] 

[Essential]  Planned 

AOM‐0401(OI), AOM‐0402(OI), AOM‐0501(OI) [E], AOM‐0502(OI) [E], CM‐0102‐A(OI) [E] 

 ‐  

FRA implementation plan is under development in cooperation with NM.   31/12/2017 

ASP (By:12/2021) 

SAKAERONAVIGATSIA FRA  implementation plan  is under development  in cooperation with NM.  

EUROCONTROL Support to 

GCAA/NSA/ANSP / FRA 

implementation 

Planned 

31/12/2017 

 

AOP03 

Improve runway safety by preventing runway incursions 

Timescales: 

Initial  operational  capability:  01/04/2003 Full operational capability: 31/12/2013 

 

  Completed 

AO‐0101(OI) 

 ‐  

RST has been established and  regular  formal meetings addressing EAPPRI  recommendations are  taking place under supervision of GCAA.    

31/12/2015 

REG (By:12/2013) 

GCAA RST  has  been  established  and  regular  formal meetings  addressing EAPPRI  recommendations  are  taking  place  under  supervision  of GCAA.    

‐ Completed 

31/12/2015 

ASP (By:12/2013) 

SAKAERONAVIGATSIA RST  has  been  established  and  regular  formal meetings  addressing EAPPRI  recommendations  are  taking  place  under  supervision  of GCAA.    

‐ Completed 

31/12/2015 

APO (By:12/2013) 

TBILISI  Airport RST  has  been  established  and  regular  formal meetings  addressing EAPPRI  recommendations  are  taking  place  under  supervision  of GCAA.    

‐ Completed 

31/12/2015 

 

AOP04.1 

Implement  Advanced  Surface  Movement  Guidance  and Control System (A‐SMGCS) Level1 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

AO‐0201(OI), CTE‐S02b(EN), CTE‐S03b(EN), CTE‐S04b(EN) 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

Georgia is not within the area of applicability of this airport objective.  ‐ 

REG (By:12/2010) 

GCAA  Georgia is not within the area of applicability of this airport objective.  ‐ 

Not Applicable 

‐ 

ASP (By:12/2011) 

SAKAERONAVIGATSIA  Georgia is not within the area of applicability of this airport objective.  ‐ 

Not Applicable 

‐ 

APO (By:12/2010) 

TBILISI  Airport  Georgia is not within the area of applicability of this airport objective.  ‐ Not 

Applicable 

LSSIP Year 2015 Georgia 24 Released Issue

 

AOP04.2 

Implement  Advanced  Surface  Movement  Guidance  and Control System (A‐SMGCS) Level 2 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

AO‐0102(OI), AO‐0201(OI), CTE‐S02b(EN), CTE‐S03b(EN), CTE‐S04b(EN) 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

Georgia is not within the area of applicability of this airport objective.  ‐ 

ASP (By:12/2017) 

SAKAERONAVIGATSIA  Georgia is not within the area of applicability of this airport objective.  ‐ 

Not Applicable 

‐ 

APO (By:12/2017) 

TBILISI  Airport  Georgia is not within the area of applicability of this airport objective.  ‐ 

Not Applicable 

‐ 

 

AOP05 

Implement Airport Collaborative Decision Making (CDM) 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

AO‐0501(OI), AO‐0601(OI), AO‐0602(OI), AO‐0603(OI) 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

Georgia is not within the area of applicability of this airport objective.  ‐ 

ASP (By:12/2016) 

SAKAERONAVIGATSIA  Georgia is not within the area of applicability of this airport objective.  ‐ 

Not Applicable 

‐ 

APO (By:12/2016) 

TBILISI  Airport  Georgia is not within the area of applicability of this airport objective.  ‐ 

Not Applicable 

‐ 

 

AOP10 

Time Based Separation 

Timescales: 

‐ not applicable ‐ 

[PCP] 

[Essential]  

Not Applicable 

AO‐0303(OI) [E] 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

‐  ‐ 

REG (By:12/2023) 

ASP (By:12/2023) 

    

LSSIP Year 2015 Georgia 25 Released Issue

 

AOP11 

Initial Airport Operations Plan 

Timescales: 

Initial  Operational  Capability:  01/01/2015 Full Operational Capability: 31/12/2021 

[PCP] 

[Essential]  

Not Applicable 

AO‐0801‐A(OI) [E] 

UGTB ‐ Tbilisi Airport 

Tbilisi Airport is not in the applicability area of this objective.  ‐ 

ASP (By:12/2021) 

SAKAERONAVIGATSIA  ‐  ‐ 

Not Applicable 

‐ 

APO (By:12/2021) 

TBILISI  Airport  ‐  ‐ 

Not Applicable 

‐ 

 

AOP12 

Improve  runway  and  airfield  safety  with  ATC  clearances monitoring 

Timescales: 

‐ not applicable ‐ 

[PCP] 

[Essential]  

Not Applicable 

AERODROME‐ATC‐36(EN), AO‐0104‐A(OI) [E] 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

‐  ‐ 

ASP (By:12/2020) 

APO (By:12/2020) 

 

ATC02.5 

Implement  ground  based  safety  nets  ‐  Area  Proximity Warning ‐ level 2 

Timescales: 

Initial  operational  capability:  01/01/2009 Full operational capability: 31/12/2016 

 

  Completed 

CM‐0801(OI) 

 ‐  

APW function exists and is optimised to the local environment.  The training plans have been updated and a training package has been developed by the ANSP for the use of APW functions. 

31/12/2015 

ASP (By:12/2016) 

SAKAERONAVIGATSIA Ground  systems  supports  the APW  function which  is  in operational use.  

‐ Completed 

31/12/2015 

    

LSSIP Year 2015 Georgia 26 Released Issue

 

ATC02.6 

Implement  ground  based    safety  nets  ‐  Minimum  Safe Altitude Warning ‐ level 2 

Timescales: 

Initial  operational  capability:  01/01/2009 Full operational capability: 31/12/2016 

 

  Completed 

CM‐0801(OI) 

 ‐  

The training plans have been updated and a training package has been developed by the ANSP for the use of MSAW functions. Ground systems supports the MSAW function which is in operational use.   

31/12/2015 

ASP (By:12/2016) 

SAKAERONAVIGATSIA The  training  plans  have  been  updated  and  a  training  package  has been developed by the ANSP for the use of MSAW functions. Ground systems supports the MSAW function which is in operational use.  

‐ Completed 

31/12/2015 

 

ATC02.7 

Implement  ground  based  safety  nets  ‐  Approach  Path Monitor ‐ level 2 

(Outside Applicability Area) 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

CM‐0801(OI) 

 ‐  

Following a cost benefit analysis SAN considers this objective as not applicable.  ‐ 

ASP (By:12/2016) 

SAKAERONAVIGATSIA Following a cost benefit analysis SAN has no plan  to  implement  this objective. 

‐ 

Not Applicable 

‐ 

 

ATC07.1 

Implement AMAN tools and procedures 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

TS‐0102(OI) 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

There are no  capacity problems  in  the TMA and on  the airport. Georgia  considers  this objective as not applicable. 

‐ 

ASP (By:12/2015) 

SAKAERONAVIGATSIA  There are no capacity problems in the TMA and on the airport.  ‐ 

Not Applicable 

‐ 

    

LSSIP Year 2015 Georgia 27 Released Issue

 

ATC12.1 

Implement  automated  support  for  conflict  detection, resolution  support  information  and  conformance monitoring 

Timescales: 

Initial  operational  capability:  01/01/2015 Full operational capability: 31/12/2021 

 

  

Partly Completed 

CM‐0202(OI), CM‐0203(OI), CM‐0205(OI), CM‐0207‐A(OI) 

 ‐  

MTCD and  resolution  support  functions have been  implemented documented and  is  in operational use. Under ongoing ground system upgrade process MONA functions is planned to be implemented. 

30/06/2019 

ASP (By:12/2021) 

SAKAERONAVIGATSIA 

MTCD  and  resolution  support  functions  have  been  implemented documented  and  is  in  operational  use.  Under  ongoing  ground system  upgrade  process  MONA  functions  is  planned  to  be implemented. 

New automated management system for 

ATS  

Partly Completed 

30/06/2019 

 

ATC15 

Implement,  in  En‐Route  operations,  information  exchange mechanisms, tools and procedures in support of Basic AMAN operations 

(Outside Applicability Area) 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

TS‐0305(OI) 

 ‐  

Georgia is not in the applicability area of this objective.  ‐ 

ASP (By:12/2017) 

SAKAERONAVIGATSIA  Georgia is not in the applicability area of this objective.  ‐ 

Not Applicable 

‐ 

    

LSSIP Year 2015 Georgia 28 Released Issue

 

ATC16 

Implement ACAS II compliant with TCAS II change 7.1   

Timescales: 

Initial  operational  capability:  01/03/2012 Full operational capability: 31/12/2015 

 

  Completed 

PRO‐AC‐21(EN) 

 ‐  

Operational  approval  to  aircraft  operators  having  submitted  an  application  has  been  delivered. Airworthiness certification for ACAS  II (TCAS 7.1) aircraft  in the State of Registry under  its responsibility has been provided. Evidence on the status of compliance with regulatory provisions for ACAS II (TCAS 7.1) for  aircraft  and  aircraft  operators  in  the  State  of  Registry  under  the  CAA/NSA  oversight  has  been provided. The training plan and package has been developed by the ANSP.  

31/12/2015 

REG (By:12/2015) 

GCAA 

Operational  approval  to  aircraft  operators  having  submitted  an application has been delivered. Airworthiness certification for ACAS II (TCAS 7.1) aircraft in the State of Registry under its responsibility has been provided.  Evidence  on  the  status  of  compliance  with  regulatory provisions for ACAS II (TCAS 7.1) for aircraft and aircraft operators in the  State  of  Registry  under  the  CAA/NSA  oversight  has  been provided. The training plan and package has been developed by the ANSP.  

‐ 

Completed 

31/12/2015 

ASP (By:03/2012) 

SAKAERONAVIGATSIA A  monitoring  system  of  the  performance  of  ACAS  in  the  ATC environment,  by  means  of  regular  incident  occurrence  reporting, investigation and analysis, has been put in place. 

‐ Completed 

30/12/2015 

MIL (By:12/2015) 

Mil. Authority  MIL has no ATS role.  ‐ 

Not Applicable 

‐ 

 

ATC17 

Electronic Dialogue as Automated Assistance  to Controller during Coordination and Transfer 

Timescales: 

Initial  operational  capability:  01/01/2013 Full operational capability: 31/12/2018 

 

  Planned 

CM‐0201(OI) 

 ‐  

Current ATC operational system has been updated to support basic OLDI functions. Safety assessement of changes generated by upgrade of current ATC system is under development. New ATC system is planned to be put into operation by 2017. The system will have extended OLDI functions.  

31/12/2017 

ASP (By:12/2018) 

SAKAERONAVIGATSIA 

Current ATC operational system has been updated to support basic OLDI  functions.  Safety  assessement  of  changes  generated  by upgrade  of  current  ATC  system  is  under  development.  New  ATC system is planned to be put into operation by 2017. The system will have extended OLDI functions.  

New automated management system for 

ATS  

Planned 

31/12/2017 

    

LSSIP Year 2015 Georgia 29 Released Issue

 

COM10 

Migrate from AFTN  to AMHS  

Timescales: 

Initial  operational  capability:  01/12/2011 Full operational capability: 31/12/2014 

 

  

Partly Completed 

CTE‐C06c(EN) 

 ‐  

AMHS system has been installed. ANSP relevant personnel are adequately trained. AMHS system operation is subject to further cross‐boarder agreements.  

31/12/2016 

ASP (By:12/2014) 

SAKAERONAVIGATSIA 

AMHS  system  has  been  installed  and  its  basic  functionalities  are ready  to be  in operation. ANSP  relevant personnel are adequately trained.  Implementation of  regional boundary  gateways  is  subject to further cross‐boarder agreements.  

New automated management system for 

ATS  

Partly Completed 

31/12/2016 

 

COM11 

Implementation  of  Voice  over  Internet  Protocol  (VoIP)  in ATM 

Timescales: 

Initial  operational  capability:  01/01/2013 Full operational capability: 31/12/2020 

 

  

Partly Completed 

CTE‐C05a(EN) 

 ‐  

NSA has been    informed on  the planned  changes of  voice Communication  Systems. Notification on  full operational capability will be addresses accordingly. 

31/12/2017 

ASP (By:12/2020) 

SAKAERONAVIGATSIA Upgrade  of  voice  communications  systems  is  planned  inline  with procurement and putting  into operation of new ATC  system.  Safety assessment for the planned changes will take place in due time.  

‐ 

Partly Completed 

31/12/2017 

 

ENV01 

Implement Continuous Descent Operations (CDO) techniques for environmental improvements 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

AOM‐0701(OI) 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

Georgia is not in the area of applicability of this multi‐national objective.  ‐ 

ASP (By:12/2013) 

SAKAERONAVIGATSIA Georgia  is  not  in  the  area  of  applicability  of  this  multi‐national objective. 

‐ 

Not Applicable 

‐ 

APO (By:12/2013) 

TBILISI  Airport Georgia  is  not  in  the  area  of  applicability  of  this  multi‐national objective. 

‐ 

Not Applicable 

‐ 

    

LSSIP Year 2015 Georgia 30 Released Issue

 

ENV02 

Implement Collaborative Environmental Management  (CEM) at Airports 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

AO‐0703(OI), AO‐0705(OI), AO‐0706(OI) 

UGTB ‐ Tbilisi Airport 

(Outside Applicability Area) 

Georgia is not in the area of applicability of this multi‐national objective.  ‐ 

ASP (By:12/2016) 

SAKAERONAVIGATSIA Georgia  is  not  in  the  area  of  applicability  of  this  multi‐national objective. 

‐ 

Not Applicable 

‐ 

APO (By:12/2016) 

TBILISI  Airport Georgia  is  not  in  the  area  of  applicability  of  this  multi‐national objective. 

‐ 

Not Applicable 

‐ 

 

FCM01 

Implement enhanced tactical flow management services 

Timescales: 

Initial  operational  capability:  01/08/2001 Full operational capability: 31/12/2006 

 

  Late 

IS‐0102(OI) 

 ‐  

This objective  is subject to procurement and operation of new ATC system. Current ATC system does not support automated massege exchange functions.   

31/12/2017 

ASP (By:07/2014) 

SAKAERONAVIGATSIA This objective  is subject to procurement and operation of new ATC system. Current ATC system does not support automated massege exchange functions.   

New automated management system for 

ATS  

Late 

31/12/2017 

 

FCM03 

Implement collaborative flight planning 

Timescales: 

Initial  operational  capability:  01/01/2000 Full operational capability: 31/12/2017 

 

  Late 

IS‐0102(OI) 

 ‐  

With the accetion to the ERCTL some NM masseges due to  limited capabilities of current ATC system are generated and transferred manually. Automatic generation and distribution will take place with the new ATC system by 2017.  

31/12/2017 

ASP (By:12/2017) 

SAKAERONAVIGATSIA 

With the accetion to the ERCTL some NM massegfes due to limited cabalilities  of  current  ATC  system  are  generated  and  trsansfred manually.  Automatic  generation  and  distribution  will  take  place with the new ATC system by 2017.  

New automated management system for 

ATS  

Late 

31/12/2017 

    

LSSIP Year 2015 Georgia 31 Released Issue

 

FCM04 

Implementation of Short Term ATFCM Measures ‐ phase 1 

(Outside Applicability Area) 

Timescales: 

‐ not applicable ‐ 

 

  

Not Applicable 

DCB‐0205(OI) 

 ‐  

Georgia is not in the applicability area of this objective.  ‐ 

ASP (By:12/2015) 

SAKAERONAVIGATSIA  Georgia is not in the applicability area of this objective.  ‐ 

Not Applicable 

‐ 

 

FCM05 

Implementation of interactive rolling NOP 

Timescales: 

Initial  operational  capability:  01/09/2013 Full operational capability: 31/12/2021 

[PCP] 

[Essential]  Planned 

AOM‐0202(OI), AOM‐0205(OI), DCB‐0102(OI), DCB‐0103‐A(OI) [E], IS‐0901‐A(OI) [E] 

 ‐  

SAKAERO is planning integration into NOP.  31/12/2017 

ASP (By:12/2017) 

SAKAERONAVIGATSIA  SAKAERO plans to integrate into NOP. EUROCONTROL Support to 

GCAA/NSA/ANSP 

Planned 

31/12/2017 

APO (By:12/2021) 

TBILISI  Airport Tbilisi  Airport  has  no  operational  need  to  implement  this objective, 

‐ 

Not Applicable 

‐ 

 

FCM06 

Traffic Complexity Assessment 

Timescales: 

Initial  operational  capability:  01/01/2015 Full operational capability: 31/12/2021 

[PCP] 

[Essential]  Planned 

CM‐0101(OI), CM‐0103‐A(OI) [E], IS‐0102(OI) 

 ‐  

Under ongoing process related to NM integration this objective is planned to be implemented.  30/06/2019 

ASP (By:12/2021) 

SAKAERONAVIGATSIA Under ongoing process related to NM integration this objective is planned to be implemented. 

EUROCONTROL Support to 

GCAA/NSA/ANSP 

Planned 

30/06/2019 

    

LSSIP Year 2015 Georgia 32 Released Issue

 

INF04 

Implement integrated briefing 

Timescales: 

Initial  operational  capability:  01/07/2002 Full operational capability: 31/12/2012 

 

  Late 

IS‐0201(OI) 

 ‐  

Integrated  Briefing  function  is  planed  to  be  implemented mid  Summer  2015,  Subject  to  putting  into operation of Information Management System (COMSOFT). At the moment dedicated technical facilities are  in place. Relevant operational and  technical personnel  is  trained. Operational procedure has been developed. There is technical constrains related with software which is under evaluation and testing.   

04/04/2016 

ASP (By:12/2012) 

SAKAERONAVIGATSIA 

Integrated  Briefing  function  is  planed  to  be  implemented  mid Summer  2015,  Subject  to  putting  into  operation  of  Information Management  System  (COMSOFT).  At  the  moment  dedicated technical  facilities  are  in  place.  Relevant  operational  and  technical personnel  is  trained.  Operational  procedure  has  been  developed. There  is  technical  constrains  related with  software which  is  under evaluation and testing.   

‐ 

Late 

04/04/2016 

 

INF07 

Electronic Terrain and Obstacle Data (TOD) 

Timescales: 

Initial  operational  capability:  01/11/2014 Full operational capability: 31/05/2018 

 

  Planned 

AIMS‐16(EN) 

 ‐  

Implementation of eTOD is foreseen in the framework of ongoing  process focused on the aligning current legislation with the latest amendment of Annex 15 of CC.  

31/12/2017 

REG (By:05/2018) 

GCAA 

The  national  TOD  policy  and  implementation  programme  is planned  to  be  established  in  the  framework  of  ongoing regulatory  process  focused  on  the  aligning  current  legislation with the latest amendment of Annex 15 of CC.  

EUROCONTROL Support to 

GCAA/NSA/ANSP / Transition from 

AIS to AIM 

Planned 

31/12/2017 

ASP (By:05/2018) 

SAKAERONAVIGATSIA Currently  ANSP  has  no  operation  plan  to  implement  this objective. This  is subject  to national  regulatory  framework and its implementation.  

EUROCONTROL Support to 

GCAA/NSA/ANSP 

No Plan 

‐ 

APO (By:05/2018) 

TBILISI  Airport  No plan yet  ‐ No Plan 

‐ 

    

LSSIP Year 2015 Georgia 33 Released Issue

 

ITY‐ACID 

Aircraft identification 

Timescales: 

Entry  into  force  of  the  Regulation:  13/12/2011 System  capability:  02/01/2020 Possible deferred  compliance, only  for  services provided by military  units  or  under  military  supervision,  subject  to conditions:: 02/01/2025 

 

  Planned 

GSURV‐0101(EN) 

 ‐  

Surveillance  infrustructure  has  been  updated  to  ensure  unambiguous  and  continuous  identification  of individual aircraft. Current ATC system  is not able to process this  information. New ATC system will have such capability by 2017.  

31/12/2018 

ASP (By:01/2020) 

SAKAERONAVIGATSIA 

Surveillance  infrustructure  has  been  updated  to  ensure unambiguous  and  continuous  identification  of  individual  aircraft. Current ATC system is not able to process this information. New ATC system will have such capability by 2017.  

New automated management system for 

ATS  

Planned 

31/12/2018 

 

ITY‐ADQ 

Ensure  quality  of  aeronautical  data  and  aeronautical information 

Timescales: 

Entry  into  force  of  the  regulation:  16/02/2010 Article  5(4)(a),  Article  5(4)(b)  and  Article  6  to  13  to  be implemented  by:  30/06/2013 Article  4, Article5(1)  and Article  5(2), Article  5(3)  and Article 5(4)(c)  to  be  implemented  by:  30/06/2014 All data requirements implemented by: 30/06/2017 

 

  

Not Applicable 

IS‐0202(OI), IS‐0204(OI) 

 ‐  

Georgia is not in the applicability area of this objective. This regulation is not in the Common Aviation Area Agreement (CAAA) between Georgia and EU.  

‐ 

REG (By:06/2017) 

GCAA  Georgia is not in the applicability area of this objective.  ‐ 

Not Applicable 

‐ 

ASP (By:06/2017) 

SAKAERONAVIGATSIA  Georgia is not in the applicability area of this objective.  ‐ 

Not Applicable 

‐ 

APO (By:06/2017) 

TBILISI  Airport  Georgia is not in the applicability area of this objective.  ‐ 

Not Applicable 

‐ 

    

LSSIP Year 2015 Georgia 34 Released Issue

 

ITY‐AGDL 

Initial ATC air‐ground data link services above FL‐285 

Timescales: 

ATS  unit  operational  capability:  05/02/2018 Aircraft capability: 05/02/2020 

 

  

Not Applicable 

AUO‐0301(OI), CTE‐C02b(EN) 

 ‐  

The is no operational need to implement this objective.   ‐ 

REG (By:02/2018) 

GCAA  The is no operational need to implement this objective.   ‐ 

Not Applicable 

‐ 

ASP (By:02/2018) 

SAKAERONAVIGATSIA  The is no operational need to implement this objective.   ‐ 

Not Applicable 

‐ 

MIL (By:01/2019) 

Mil. Authority MIL does not provide ATC service  in Georgia. Very  low  levels of MIL traffic. 

‐ 

Not Applicable 

‐ 

 

ITY‐AGVCS2 

Implement 8,33 kHz air‐ground voice channel spacing below FL195 

Timescales: 

Entry  into  force:  07/12/2012 New  and  upgraded  radio  equipment:  17/11/2013 New  or  upgraded  radios  on  State  aircraft:  01/01/2014 Interim  target  for  freq.  conversions:  31/12/2014 All  radio  equipment:  31/12/2017 All  frequencies  converted:  31/12/2018 State  aircraft  equipped,  except  those  notified  to  EC: 31/12/2018 State  aircraft  equipped,  except  those  exempted  [Art  9(11)]: 31/12/2020 

 

  Planned 

CTE‐C01a(EN) 

 ‐  

Technically SAN  is ready, however currently there  is no operational need to apply 8,33 kHz  in Georgian airspace.   

31/12/2018 

REG (By:12/2018) 

GCAA Technically SAN  is  ready, however currently  there  is no operational need to apply 8,33 kHz in Georgian airspace.   

‐ Planned 

31/12/2018 

ASP (By:12/2018) 

SAKAERONAVIGATSIA Technically SAN  is  ready, however currently  there  is no operational need to apply 8,33 kHz in Georgian airspace.   

‐ Planned 

31/12/2018 

MIL (By:12/2020) 

Mil. Authority  Not providing ATC services.  ‐ 

Not Applicable 

‐ 

APO (By:12/2018) 

TBILISI  Airport Implementation  of  present  objective  is  not  applicable  to  Tbilisi Airport.  

‐ 

Not Applicable 

‐ 

 

LSSIP Year 2015 Georgia 35 Released Issue

ITY‐COTR 

Implementation  of  ground‐ground  automated  co‐ordination processes 

Timescales: 

Entry  into  force  of  Regulation:  27/07/2006 For  putting  into  service  of  EATMN  systems  in  respect  of notification  and  initial  coordination  processes:  27/07/2006 For  putting  into  service  of  EATMN  systems  in  respect  of Revision  of  Coordination,  Abrogation  of  Coordination,  Basic Flight  Data  and  Change  to  Basic  Flight  Data:  01/01/2009 To  all  EATMN  systems  in  operation  by  12/2012:  31/12/2012 Systems  serving  ACCs  providing  services  above  FL285  in  the airspace defined in Regulation (EU) 2015/310: 05/02/2018 

 

  Completed 

CM‐0201(OI) 

 ‐  

Flight data processing and exchange systems have been upgraded and put into service.  10/01/2016 

ASP (By:02/2018) 

SAKAERONAVIGATSIA Flight data processing and exchange systems have been upgraded and put into service. 

‐ Completed 

10/01/2016 

MIL (By:12/2012) 

Mil. Authority  ‐  ‐ 

Not Applicable 

‐ 

 

ITY‐FMTP 

Apply a common flight message transfer protocol (FMTP) 

Timescales: 

Entry  into  force  of  regulation:  28/06/2007 All  EATMN  systems  put  into  service  after  01/01/09: 01/01/2009 All  EATMN  systems  in  operation  by  20/04/11:  20/04/2011 Transitional  arrangements:  31/12/2012 Transitional  arrangements  when  bilaterally  agreed  between ANSPs: 31/12/2014 

 

  Completed 

CTE‐C06(EN) 

 ‐  

Communications systems have been upgraded and in operational use.  31/12/2014 

ASP (By:12/2014) 

SAKAERONAVIGATSIA  Communications systems have been upgraded and in operational use.  ‐ Completed 

31/12/2014 

MIL (By:12/2014) 

Mil. Authority  MIL does not provide ATC service in Georgia.  ‐ 

Not Applicable 

‐ 

    

LSSIP Year 2015 Georgia 36 Released Issue

 

ITY‐SPI 

Surveillance performance and interoperability 

Timescales: 

Entry  intro  force  of  regulation:  13/12/2011 ATS  unit  operational  capability:  12/12/2013 New  aircraft  capability:  08/06/2016 ELS  in  transport‐type  State  aircraft  :  07/12/2017 EHS  and  ADS‐B  Out    in  transport‐type  State  aircraft  : 07/06/2020 Ensure  training  of  MIL  personnel:  07/06/2020 Retrofit aircraft capability: 07/06/2020 

 

  Planned 

GSURV‐0101(EN) 

 ‐  

SAN is running the project focused on the improvement of surveillance performance are ongoing.   30/12/2017 

REG (By:02/2015) 

GCAA SAN  is  running  the  project  focused  on  the  improvement  of surveillance performance are ongoing.  

‐ Planned 

30/12/2017 

ASP (By:02/2015) 

SAKAERONAVIGATSIA SAN  is  running  the  project  focused  on  the  improvement  of surveillance performance are ongoing.  

ADS‐B implementation 

/ New automated management system for ATS  

/ The Surveillance 

Data Distribution System 

Implementation 

Planned 

30/12/2017 

MIL (By:06/2020) 

Mil. Authority  ‐  ‐ 

Not Applicable 

‐ 

 

NAV03 

Implementation of P‐RNAV 

Timescales: 

Initial  operational  capability:  01/01/2001 Full operational capability: 31/12/2023 

 

  

Partly Completed 

AOM‐0601(OI), AOM‐0602(OI), CTE‐N08(EN) 

 ‐  

Terrestrial navigation  infrastructure to support RNAV operations has been conducted. Current DME/DME infrastructure  is  being  expanded.  Local  P‐RNAV  Safety  Case  is  planned  to  be  developed under  ongoing national PBN implementation project to address appropriate SLoA of this objective.   

31/12/2017 

ASP (By:12/2023) 

SAKAERONAVIGATSIA 

Terrestrial navigation infrastructure to support RNAV operations has been conducted. Current DME/DME  infrastructure  is being expanded.  Procedure  designers  responsible  for  the  design  of RNAV  terminal  procedures  have  been  trained.  All  other  SLoA will  be  addressed  accordingly  under  ongoing  national  PBN implementation project.  

EUROCONTROL Support to 

GCAA/NSA/ANSP / PBN 

Implementation 

Partly Completed 

31/12/2017 

    

LSSIP Year 2015 Georgia 37 Released Issue

 

NAV10 

Implement APV procedures 

Timescales: 

Initial  operational  capability:  01/06/2011 Full operational capability: 31/12/2016 

 

  Planned 

AOM‐0602(OI), AOM‐0604(OI), CTE‐N06a(EN), CTE‐N06b(EN) 

 ‐  

Under ongoing national PBN implementation project development APV/Baro procedures will be ensured.    31/12/2016 

REG (By:04/2016) 

GCAA Under  ongoing  national  PBN  implementation  project  EASA material and ofher SLoA under this objective will be addressed.   

EUROCONTROL Support to 

GCAA/NSA/ANSP / PBN 

Implementation / Transition from 

AIS to AIM 

Planned 

30/04/2016 

ASP (By:12/2016) 

SAKAERONAVIGATSIA APV/Baro operations  will be developed under ongoing national PBN implementation project.  

EUROCONTROL Support to 

GCAA/NSA/ANSP / PBN 

Implementation 

Planned 

31/12/2016 

 

SAF10 

Implement measures to reduce the risk to aircraft operations caused by airspace infringements 

Timescales: 

Initial  operational  capability:  01/06/2008 Full operational capability: 31/12/2011 

 

  Completed 

CM‐0801(OI) 

 ‐  

Coordination  procedures  have  been  established  between military  and  civil  ATC  units.  Due  to  limited operations by general aviation and military ACFT the risk of airspace Infringement is negligible.  

31/12/2012 

REG (By:12/2011) 

GCAA GCAA  considered  the  recommendations.  No  need  for  national regulatory material.  

‐ Completed 

31/12/2012 

ASP (By:12/2011) 

SAKAERONAVIGATSIA Coordination  procedures  have  been  established  between  military and civil ATC units. Due to limited operations by general aviation and military ACFT the risk of airspace Infringement is negligible.  

‐ Completed 

30/11/2010 

MIL (By:12/2011) 

Mil. Authority Coordination  procedures  have  been  established  between  military and civil ATC units. Due to limited operations by general aviation and military ACFT the risk of airspace Infringement is negligible.  

‐ Completed 

30/11/2010 

    

LSSIP Year 2015 Georgia 38 Released Issue

 

SAF11 

Improve runway safety by preventing runway excursions 

Timescales: 

Initial  operational  capability:  01/09/2013 Full operational capability: 31/01/2018 

 

  Completed 

PRO‐006a(EN) 

 ‐  

GCAA has approved national regulation on the establishment on RWY Safety Teams on each international aerodrome. Regulation enforces recommendations contained in European Action Plan for the Prevention of Runway  Incursions. All  stakeholders operating at  international aerodromes are planning  to  conduct forums and  regular meetings  to  implement  the national  requirements.  Implementation of  regulation  is part of GCAA's supervision.   

31/12/2015 

REG (By:01/2018) 

GCAA 

GCAA has approved national regulation on the establishment on RWY Safety Teams on each  international aerodrome. Regulation enforces recommendations  contained  in  European  Action  Plan  for  the Prevention  of  Runway  Excursions.  Implementation  of  regulation  is part of GCAA's supervision.  

‐ 

Completed 

31/12/2015 

ASP (By:12/2014) 

SAKAERONAVIGATSIA 

In the frames of national improvement process Runway Safety Teams will  be  collaborated  with  aerodrome  RWY  Safety  Teams  at international  aerodrome.    In  addition  following  national  regulation on  the  establishment  of  RWY  safety  teams  recommendations contained in the European Action Plan for the Prevention of Runway Excursions  will  be  addressed  through  continuous  improvement process. 

‐ 

Completed 

30/12/2015 

APO (By:12/2014) 

TBILISI  Airport 

Relevant parts of Action plan has been taken  into account based on the  local  conditions  and  environment.    Appropriate  parts  of  the European Action Plan for the Prevention of Runway Excursions will be addressed following the national regulation on the establishments of RWY Safety Teams.  

‐ 

Completed 

30/12/2015 

    

LSSIP Year 2015 Georgia 39 Released Issue

 

Annexes

Annex A – Specialists involved in the LSSIP Process

LSSIP Co-ordination

LSSIP Focal Points Organisation Name

LSSIP Focal Point for Georgia GCAA Vladislav Kuljanishvili

LSSIP Focal Point for NSA/CAA GCAA Vladislav Kuljanishvili

LSSIP Focal Point for ANSP Sakaeronavigatsia Darius Vala, Samvel Karagulyan

LSSIP Focal Point for Airport TAV URBAN Georgia LLC Mzia Londaridze

LSSIP Focal Point for Military Ministry of Defence Kakhaber Kharhiladze

EUROCONTROL LSSIP Support

Function Directorate Name

LSSIP Contact Person for Georgia DPS/PEPR Predrag Vranjkovic

ESSIP Objective Implementation

ESSIP Objective

EUROCONTROL Objective Owners EUROCONTROL PEPR Objective Coordinator

National Stakeholder Specialist(s)

AOM13.1 R. BUCUROIU, O. MROWICKI, C. LUCCIOLI, E. REUBER

A. DYBOWSKA Vladislav Kuljanishvili (GCAA)

AOM19 G. ACAMPORA, O. MROWICKI

A. DYBOWSKA Vladislav Kuljanishvili (GCAA)

D. Kadzanaia (SAKA)

AOM21.1 R. BUCUROIU A. DYBOWSKA N/A

AOM21.2 R. BUCUROIU

A. DYBOWSKA Vladislav Kuljanishvili (GCAA)

E. Tavadze

AOP03 T. LICU

P. VRANJKOVIC Vladislav Kuljanishvili (GCAA)

S.Kuparadze

AOP04.1 P. ADAMSON P. VRANJKOVIC N/A

AOP04.2 P. ADAMSON P. VRANJKOVIC N/A

AOP05 P. ADAMSON P. VRANJKOVIC N/A

AOP10 M. BIRENHEIDE B. HILL N/A

AOP11 M. BIRENHEIDE B. HILL N/A

AOP12 M. BIRENHEIDE P. VRANJKOVIC N/A

ATC02.5 B. BAKKER, S. DROZDOWSKI I. FEIJT Completed

ATC02.6 B. BAKKER, S. DROZDOWSKI I. FEIJT Completed

ATC02.7 B. BAKKER, S. DROZDOWSKI I. FEIJT N/A

ATC07.1 P. CONROY, P. TERZIOSKI L. DELL’ORTO N/A

ATC12.1 P. TERZIOSKI

L. DELL’ORTO A. Trubitsin

D.kadzanaia

ATC15 P. CONROY, P. TERZIOSKI L. DELL’ORTO N/A

ATC16 S. DROZDOWSKI L. DELL’ORTO Completed

ATC17 S. MORTON

L. DELL’ORTO A.Trubitsin

D.Oniani

COM10 Y. EYUBOGLU A. KOKONA G. KOCHLASHVILI

LSSIP Year 2015 Georgia 40 Released Issue

ESSIP Objective

EUROCONTROL Objective Owners EUROCONTROL PEPR Objective Coordinator

National Stakeholder Specialist(s)

COM11 L. POPESCU

A. KOKONA G. KOCHLASHVILI

A.TRUBITSIN

ENV01 C. FABER B. HILL N/A

ENV02 S. MAHONY, A. WATT B. HILL N/A

FCM01 H. KOOLEN

O. CIOARA D. Kadzanaia

D. Oniani

FCM03 TBD

O. CIOARA D. Kadzanaia

D. Oniani

FCM04 P. HOP O. CIOARA N/A

FCM05 I. MENDES

O. CIOARA A.TRUBITSIN

D. kadzanaia

FCM06 P. HOP O. ALFARO D.Kadzanaia

INF04 P. MATERN A-P. FRANGOLHO M. GAPRINDASHVILI

INF07 A. PETROVSKY

A-P. FRANGOLHO Vladislav Kuljanishvili (GCAA) / M. Gaprindashvili

ITY-ACID A. DESMOND-KENNEDY

O. CIOARA A. TRUBITSIN

D.Kadzanaia

ITY-ADQ M. UNTERREINER A-P. FRANGOLHO N/A

ITY-AGDL S. DISSING A. KOKONA N/A

ITY-AGVCS2 J POUZET O. ALFARO G. KOCHLASHVILI

ITY-COTR S. MORTON L. DELL’ORTO Completed

ITY-FMTP L. POPESCU O. ALFARO Completed

ITY-SPI M. BORELY, R. STEWART O. CIOARA Y. Trubitsin

NAV03

F. PAVLICEVIC

A. KOKONA Levan Karanadze (GCAA)

E. Tavadze

M.Gaprindashvili

NAV10 R. FARNWORTH

A. KOKONA Levan Karanadze(GCAA)

Z.Khitarishvili

SAF10

T. LICU I. FEIJT Levan Moseshvili (GCAA)

David Cheishvili (GCAA) / L. Meseridze

SAF11

S. LAWRENCE I. FEIJT Levan Moseshvili (GCAA)

David Cheishvili (GCAA) / L. Meseridze

LSSIP Year 2015 Georgia 41 Released Issue

Annex B – National Stakeholders Organisation Charts

Organisational structure of the Georgian Civil Aviation Agency (GCAA)

LSSIP Year 2015 Georgia 42 Released Issue

Organisational structure of the Georgian ANSP: SAKAERONAVIGATSIA

Organisational structure of the TAV URBAN Georgia LLC

LSSIP Year 2015 Georgia 43 Released Issue

Annex C – Glossary of Abbreviations

AAIB Aircraft Accident and Incident Investigation Bureau

ACAS Airborne Collision Avoidance System

ACC Area Control Centre

AIS Aeronautical Information Services

AMC Acceptable means of Compliance

ANS Air Navigation Services

ANSP ANS Provider

AOP Airports Operations (Domain)

APV Approach with Vertical Guidance

ARN ATS Route Network

ATC Air Traffic Control

ATCO Air Traffic Controller

ATFM Air Traffic Flow Management

ATM Air Traffic Management

ATS Air Traffic Services

CAD Civil Aviation Department

CDM Collaborative Decision Making

CEATS Central European Air Traffic Services

CFMU Central Flow Management Unit

CNS Communications, Navigation and Surveillance

COM Communications

CTR Control Zone

DFL Division Flight Level

EAD European AIS Database

eAIP European Aeronautical Information Publication

EATM European Air Traffic Management

ECAC European Civil Aviation Conference

ESP European Safety Programme

FDP Flight Data Processing

LSSIP Year 2015 Georgia 44 Released Issue

FIR Flight Information Region

FL Flight Level

FSQA Flight Safety and Quality Assurance

FUA Flexible Use of Airspace

GBAS Ground Based Augmentation System

GCAA Georgian Civil Aviation Authority

GCAD Georgian Civil Aviation Department

GNSS Global Navigation Satellite System

HRS Human Resources

HUM Human (Domain)

ICAO International Civil Aviation Organisation

IFPS Initial Flight-plan Processing System

IFR Instrument Flight Rules

ISO International Standards Organisation

JAA Joint Aviation Authorities

kHz Kilohertz

LoA Letters of Agreement

MIL Military

NAV Navigation

NM Nautical Mile

NOTAM Notice To Airmen

OLDI On Line Data Interchange

OPS Operations

TIIAB Aircraft Accident and Incident Investigation Bureau

PSR Primary Surveillance Radar

QMS Quality Management System

REG Regulatory Authorities

RNP Required Navigation Performance

RVSM Reduced Vertical Separation Minimum

SAN Sakaeronavigatsia Ltd (ATM of Georgia)

SBAS Satellite-Based augmentation systems (SBAS)

SLOA Stakeholder Line of Action

LSSIP Year 2015 Georgia 45 Released Issue

SMQS Safety Management and Quality System

SMS Safety Management System

SRC Safety Regulation Commission

SSR Secondary Surveillance Radar

STCA Short Term Conflict Alert

SUR Surveillance (Domain)

TIATC Tbilisi International Training School

TAV Tepe Akfen Urben Airport Georgia

TMA Terminal Manoeuvring Area; Terminal Control Area