Hastings Surface Water Management Plan (SWMP)€¦ · AECOM Study Report 2 The Flood Maps for...
Transcript of Hastings Surface Water Management Plan (SWMP)€¦ · AECOM Study Report 2 The Flood Maps for...
Water
Hastings Borough Council March 2011
Hastings Surface Water Management Plan – Study Report Hollington Old Lane flooded in 2009 – Source: EA
Executive Summary ........................................................................................................................................................................ 1
Glossary .......................................................................................................................................................................................... 3
Acronyms ........................................................................................................................................................................................ 8
Introduction and Background........................................................................................................................................................ 9 Introduction ......................................................................................................................................................................... 9 Background ....................................................................................................................................................................... 10
1 Preparation Stage ........................................................................................................................................................... 13 1.1 Identify the need for a SWMP study .................................................................................................................... 13 1.2 Establish Partnership ........................................................................................................................................... 13 1.3 Scope the SWMP ................................................................................................................................................ 14
2 Risk Assessment Stage .................................................................................................................................................. 17 2.1 Strategic Assessment .......................................................................................................................................... 17 2.2 Intermediate Assessment .................................................................................................................................... 18 2.3 Detailed Assessment ........................................................................................................................................... 26 2.4 Map and Communicate Risk ................................................................................................................................ 27
3 Options Stage .................................................................................................................................................................. 33 3.1 Identify Measures ................................................................................................................................................ 33 3.2 Assess Options .................................................................................................................................................... 37
4 Implementation and Review Stage ................................................................................................................................ 48 4.1 Prepare Action Plan ............................................................................................................................................. 48 4.2 Implement and Review Action Plan ..................................................................................................................... 53
General Conclusions and Recommendations............................................................................................................................ 54 Conclusions ....................................................................................................................................................................... 54 Recommendations ............................................................................................................................................................ 54
Table 1.1: Hastings SWMP – Working Group Structure and Representatives ..................................................................... 14 Table 1.2: Partners‟ Programmes linked to the Hastings SWMP ......................................................................................... 15 Table 2.1: Information used to inform the Strategic Assessment .......................................................................................... 17 Table 2.2: Maps produced as part of the Strategic Assessment........................................................................................... 18 Table 2.3: Information used to inform the Intermediate Assessment .................................................................................... 18 Table 2.4: Maps produced to inform the Intermediate Assessment of the flood hotspots ..................................................... 20 Table 2.5: Maps produced to summarise outcome of Site Visits .......................................................................................... 21 Table 2.6: Summary of the findings of the Intermediate Assessment ................................................................................... 22 Table 2.7: Summary of the Conclusions and Recommendations of the Intermediate Assessment ...................................... 24 Table 2.8: Summary of Modelling results in relation to Overtopping of the Dams and Surcharging of Culvert at Upper Glen Road
.......................................................................................................................................................................................... 26 Table 2.9: Differences between AStSWF and FMfSW ......................................................................................................... 27 Table 2.10: EA Surface Water Flood Maps - National and Local (Hastings) Uncertainty Levels ............................................ 29 Table 2.11: List of Maps/Sketches produced to inform the Hastings SWMP .......................................................................... 30 Table 3.1: Summary of Options identified during the Risk Assessment Stage ..................................................................... 33 Table 3.2: Short-listing Criteria Recommended by Defra ..................................................................................................... 34 Table 3.3: Application of Short-listing Criteria to Flood Hotspot 1......................................................................................... 34 Table 3.4: Application of Short-listing Criteria to Flood Hotspot 2......................................................................................... 35 Table 3.5: Application of Short-listing Criteria to Flood Hotspot 3......................................................................................... 36 Table 3.6: Application of Short-listing Criteria to Flood Hotspot 4......................................................................................... 37 Table 3.7: Summary of Assessment of Shortlisted Options for Flood Hotspot 1 .................................................................. 38
Table of Contents
Table 3.8: Summary of Assessment of Shortlisted Options for Flood Hotspot 2 .................................................................. 39 Table 3.9: Summary of Assessment of Shortlisted Options for Flood Hotspot 3 .................................................................. 40 Table 3.10: Summary of Assessment of Shortlisted Options for Flood Hotspot 4 .................................................................. 43 Table 3.11: Summary of Borough-wide studies/investigations ............................................................................................... 44 Table 3.12: Summary of Preferred Options to be taken forward to Implementation Stage ..................................................... 46 Table 3.13: Summary of Agreed Complementary Actions to Improve Surface Water Management across Hastings ............ 47 Table 4.1: Summary of Ranked Options for Implementation ................................................................................................ 49 Table 4.2: Summary of Ranked Complementary Actions for Implementation ...................................................................... 50 Table 4.3: Chronological order of activities required to progress options and complementary actions identified ................. 51 Table 4.4: Additional work identified post completion of Hastings SWMP Study .................................................................. 53 Figure 1: Framework for undertaking a SWMP Study.......................................................................................................................9 Figure 2: Location of Hastings within East Sussex ......................................................................................................................... 10 Figure 3: Overview of Hastings ....................................................................................................................................................... 10
AECOM Study Report 1
Hastings Borough Council appointed AECOM Ltd as consultant for the Hastings Surface Water Management Plan in June 2010.
This appointment followed the initial technical support provided by AECOM to HBC‟s successful bid for DEFRA funding.
The Hastings Surface Water Management Plan has been undertaken following the guidelines set out in the “Surface Water
Management Plan Technical Guidance” published by Defra in March 2010. Four well defined phases are identified in the
guidance and have been followed as part of this study. These stages are: Preparation, Risk Assessment, Options,
Implementation and Review.
The Preparation Stage of the study built on the identification of the need for a Surface Water Management Plan, completed as
part of the original bid for Defra funding, by establishing a robust partnership between all organisations with responsibilities for
flood risk or drainage management across the Borough. The partners for the Hastings Surface Water Management Plan are:
Hastings Borough Council (lead partner), East Sussex County Council (lead local flood authority), Southern Water, Environment
Agency and Rother District Council.
Once the partnership was in place, a working group was formed with representatives of the partners. The group‟s remit was to
contribute effectively to the production of the Surface Water Management Plan by sharing relevant data and attending
meetings/workshops as necessary. The overall aim of the study, as agreed with the partners, was to prepare a robust plan to
reduce the number of properties at risk of surface water flooding in Hastings through the implementation of cost-effective local
solutions. It is envisaged that the partnership formed as part of the Hastings Surface Water Management Plan will remain active
following the completion of this study and will aim to deliver the solutions identified as part of the Surface Water Management
Plan.
A series of objectives that captured the aspirations of the different partners were set out as part of the Preparation Stage. These
objectives, in conjunction with an understanding of the data readily available to inform the study were used to establish the level
of assessment required for the study thus completing the Scoping Phase.
The Risk Assessment Stage of the Hastings Surface Water Management Plan started with the Strategic Assessment Phase
which relied on historical flooding information, the Strategic Flood Risk Assessment for Hastings, LiDAR Data and the Areas
Susceptible to Surface Water Flooding Map produced by the EA. The analysis of this information identified sixteen medium to
large flood hotspots across the Borough which were presented to the working group for review. Upon review of the initial
conclusions it was agreed that further assessment was required but given the budget and time limitations associated with the
study, as per Defra conditions, it was agreed by the working group that four flood hotspots would be looked at in more detail as
part of the Intermediate Assessment Phase.
The Intermediate Assessment started with the identification of the top eight flood hotspots across Hastings by the working group.
A selection criteria based on accepted methods applied for other similar Defra funded studies was then applied to these locations
to identify the top four flood hotspots across the Borough. The selected locations were then subject to more detailed analysis
which included a site visit by the working group aimed at identifying the issues on the ground from the perspective of all partners
as well as establishing any quick solutions to the problems. The output of the intermediate assessment was a series of
conclusions, recommendations and the identification of various options to be investigated further. Among the recommendations
was the need to undertake a detailed assessment of the Upper Hollington Stream aimed at improving the understanding and
management of the existing water retaining structures.
The Risk Assessment Stage was completed with the Map and Communicate Risk phase which involved the production of a
Borough-wide asset register aimed at identifying all flood risk and drainage management assets across Hastings regardless of
ownership. The asset register was the result of a lengthy consultation process with all partners which included attendance at a
workshop aimed at reviewing the information collated, addressing any gaps in the data and agreeing the criticality of the assets
from a surface water flood risk perspective. Details of the maintenance regime of the various assets across the Borough have
also being included. It is envisaged that the asset register will be used by Hastings Borough Council and East Sussex County
Council to inform their flood risk management role and therefore it is essential that any gaps/uncertainties are removed and it is
kept up to date.
Executive Summary
AECOM Study Report 2
The Flood Maps for Surface Water released by the Environment Agency in November 2010 have refined the understanding of
the areas deemed at risk of flooding from surface water across Hastings. It is, however, recognised by all partners that whereas
these revised maps provide a good general representation of the areas at risk, they do not capture all of the known problem
locations. Consequently, it was agreed within the working group that these maps would be used as the best available information
for the area until such time when East Sussex County Council issues the “locally agreed surface water flood risk information”.
The Options Stage included the identification of possible mitigation measures or solutions to the issues identified during the Risk
Assessment Stage. A number of Borough-wide and flood hotspot-specific measures were outlined to provide solutions in the
short, medium and long term. These were short-listed and subsequently assessed through a variety of methods (including
detailed overland flow modelling) and to different levels of detail in order to establish the preferred options for implementation.
The various options selected to be taken forward to the Implementation Stage are outlined below:
- Borough-wide
- Education
- Flood Resistance/Resilience Measures
- Flood Hotspot 1
- Modify Ground Profile around Priory Meadows Shopping Centre
- Flood Hotspot 3
- Install Trash Screen at the culvert entrance at Ashbrook Park, Upper Church Road
- Retrofit SUDS at Hollington Primary School
- Clear debris and improve understanding & use of water management structures
In addition to the above options, a number of complementary actions aimed at improving the management of surface water flood
risk have been identified and progressed in principle as outlined below:
- Seek SUDS Retrofitting Opportunities
- Maintain an up-to-date Borough-wide asset register
- Review maintenance regime for all assets in accordance with their criticality
- Devise a suitable flood response and report procedure
- Seek opportunities to reduce the risk of surface water flooding affecting critical infrastructure
The Implementation and Review Stage contains an action plan which outlines the steps required to deliver and monitor the
implementation of the various options agreed. The action plan included in the final version of this report has being reviewed and
approved by the various partners as well as Hastings Borough Council scrutiny committee.
It is envisaged that the working group formed to inform the production of the Hastings Surface Water Management Plan will
continue to work together post completion of the study to progress the delivery of the various options and complementary
actions. Furthermore, it is foreseen that East Sussex County Council (lead local flood authority) will take a primary role in
managing flood risk across Hastings.
AECOM Study Report 3
Antecedent Conditions:
The pre-existing condition before a rain event (e.g. waterlogged soil)
Areas Susceptible to Surface Water Flooding
Areas identified by the Environment Agency (in 2008) as susceptible to surface water flooding under extreme events (1 in 200
year return period)
Brownfield site:
Any land or site that has been previously developed
Catchment
The area contributing flow or runoff to a particular point on a watercourse
Catchment Flood Management Plan
Environment Agency produced documents providing an overview of the flood risk across each river catchment and estuary and
recommended ways of managing those risks now and over the next 50-100 years
Chance of Flooding
Describes the frequency of a flood event occurring in any given year. This can also be described as an annual probability
Climate change
A long-term variation in global temperature and weather patterns both natural and as a result of human activity, primarily
greenhouse gas emissions
Combined Sewer Network
A unified sewerage system that combines surface water and foul discharges
Cost Benefit Analysis (CBA)
Analysis which quantifies in monetary terms the costs and benefits of a proposed scheme, including items for which the market
does not provide a readily available monetary value
Critical Infrastructure
Infrastructure which is considered vital or indispensable to society , the economy, public health or the environment, and where its
failure or destruction would have large impact
Culvert
Covered channel or pipe that forms a watercourse below ground level, or through a raised embankment
Deep (as identified on the Flood Maps for Surface Water)
Areas where surface water is expected to flow or pond at a depth greater than 0.3 m, as identified on the Flood Maps for Surface
Water
Defra
UK Government department responsible for policy and regulations on the environment, food and rural affairs
Designing for Exceedance
An engineering approach which aims to plan for and manage flows which are larger than the designed capacity of infrastructure
during rainfall events
Development
The carrying out of building, engineering, mining or other operations in, on, over or under land or the making of any material
change in the use of any buildings or other land
Digital Elevation Model (DEM)
A model of the elevation of the ground surface and includes building, vegetation etc
Glossary
AECOM Study Report 4
Digital Terrain Model (DTM)
A model of the terrain of the earth‟s surface („bare earth‟)
Dry Valleys
A valley originally produced by running water but now waterless
Enmained
Watercourse designated as a Main River
Environment Agency (EA)
Government Agency charged with the protection of the environment
Environmental Agency Flood Zones
They indicate land at risk by referring to the probability of flooding from river and sea, ignoring the presence of defences. Flood
zones are defined in Table D.1 of Planning Policy Statement (PPS) 25: Development and Flood Risk
Escarpment
The long continuous steep face of a ridge or mountain
Exceedance Flows
Excess flow that appears on the surface once the capacity of the underground drainage system is exceeded
Flood defence
Flood defence infrastructure, such as flood walls and embankments, intended to protect an area against flooding, to a specified
standard of protection
Flood Estimation Handbook (FEH)
Software offering guidance on rainfall and river flood frequency estimation in the UK
Flood Hotspots
Locations identified as being prone to flooding
Flood Maps for Surface Water
Areas identified by the Environment Agency (in 2010) as prone to surface water flooding under two scenarios, the 1 in 200 year
and 1 in 30 year return period events. The Flood Maps for Surface Water are a refinement of the Areas Susceptible to Surface
Water Flooding maps produced in 2008
Flood Probability
The estimated likelihood of a flood of a given magnitude occurring or being exceeded in any specified time period
Flood risk
An expression of the combination of the flood probability and the magnitude of the potential consequences of the flood event
Flood Risk Assessment (FRA)
A study to assess the risk of a site or area flooding, and to assess the impact that any changes or development in the site or area
will have on flood risk
Flood Risk Management Plan
A plan for the management of a significant flood risk. The plan must include the objectives of the plan and the method by which
those objectives may be achieved
Floods and Water Management Bill
This Bill, passed in April 2010, aims to clarify the legislative framework for managing surface water flood risk in England
Fluvial Flooding
Flooding caused by rivers
AECOM Study Report 5
Foul Sewer Network
Sewer network collecting any foul discharges
Greenfield
Previously undeveloped land
Ground Contours
Show depression or elevation of ground forms in an area
Groundwater
Water in the ground, usually referring to water in the saturated zone below the water table
Groundwater flooding
Flooding caused by groundwater escaping from the ground when the water table rises to or above ground level
Groundwater Vulnerability
A measure of the vulnerability of groundwater stores to contamination
Highways Agency
The national body responsible for managing, maintaining and improving England‟s motorways and trunk roads
Less Susceptible to Surface Water Flooding
Areas which are susceptible to surface water flooding with a modelled indicative depth of between 0.1 m and 0.3 m, as identified
on the Areas Susceptible to Surface Water Flooding maps
LiDAR
Data set that provides a 3D image of the surface of the earth using a “Light Detection And Ranging” technique
Local Development Documents (LDDs)
Documents that set out the spatial strategy for local planning authorities which comprise development plan documents
Local Development Framework (LDF)
Framework which forms part of the statutory development plan and supplementary planning documents which expand policies in
a development plan document or provide additional detail
Local Planning Authority (LPA)
Body responsible for planning and controlling development, through the planning system
Local Resilience Forums (LRF)
Multi-agency forums, bringing together all organisations who have a duty to co-operate under the Civil Contingencies Act, and
those involved in responding to emergencies
Main River
A watercourse designated on a statutory map of Main rivers, maintained by the Environment Agency
Mitigation measure
A generic term used in this guide to refer to an element of development design which may be used to manage some risk to the
development, or to avoid an increase in risk elsewhere
Moderately Susceptible to Surface Water Flooding
Areas which are susceptible to surface water flooding with a modelled indicative depth of between 0.3 m and 1.0 m as identified
on the Areas Susceptible to Surface Water Flooding maps
More Susceptible to Surface Water Flooding
Areas which are susceptible to surface water flooding with a modelled indicative depth of more than 1.0 m, as identified on the
Areas Susceptible to Surface Water Flooding maps
AECOM Study Report 6
Ordinary watercourse
A watercourse which is not a private drain and is not designated a Main river
Permitted Development Rights
Qualified rights to carry out certain limited forms of development without the need to make an application for planning permission,
as granted under the terms of the Town and Country Planning (General Permitted Development ) Order 1995
Pluvial Flooding (Surface water flooding)
Flooding which occurs due to water pooling on or flowing over the surface before it reaches a drain or watercourse
Resilience Measures
Measures designed to reduce the impact of water that enters property and businesses
Resistance Measures
Measures designed to keep flood water out of properties and businesses
Riparian Owners
Land owners with land or property alongside a river or other watercourse
Risk
The probability of a flood occurring multiplied by the consequence of the flood
Runoff
Water flow over the ground surface to the drainage system
Sewers for adoption
Standard for new drainage systems in England & Wales to be used as a guide to assist developers in preparing their submission
to a sewerage undertaker before they enter into an Adoption Agreement under Section 104 of the Water Industry Act 1991
Shallow (as identified on the Flood Maps for Surface Water)
Areas where surface water is expected to flow or pond at a depth greater than 0.1 m, as identified on the Flood Maps for Surface
Water
Shoreline Management Plan (SMP)
Policy framework that assesses and manages risks to people and to the developed, historic and natural environment associated
with coastal processes, on a large-scale
Sewer Network
Entire sewer network, comprising of combined, foul and surface water sewers
Standard of protection
The estimated probability of an event occurring which is more severe than those against which an area is protected by flood
defences
Strategic Flood Risk Assessment (SFRA)
A study to examine flood risk issues on a sub-regional scale, typically for a river catchment or local authority area during the
preparation of a development plan
Source Protection Zone (SPZ)
Defined areas showing the risk of contamination to selected groundwater sources used for public drinking water supply, from any
activities that might cause pollution in the area
Springs
A small stream of water flowing naturally from the earth
Supplementary Planning Document (SPD)
Local Development Document that provides further detail of policies and proposals in a „parent‟ Development Plan Document
AECOM Study Report 7
Surface Water
Water collected or flowing over the ground not contained within a watercourse. Usually results from heavy rainfall
Sustainable Drainage Systems (SUDS)
A sequence of management practices and control structures, often referred to as SUDS, designed to drain surface water in a
more sustainable manner. Typically, these techniques are used to attenuate rates of runoff from potential development sites
Watercourse
Any natural or artificial channel that conveys surface water
Water Cycle Strategy (WCS)
Provides a plan and programme of Water Services Infrastructure implementation. It is determined through an assessment of the
environment and infrastructure capacity for: water supply; sewage disposal; flood risk management; and surface water drainage
Water Framework Directive
A European Community Directive (2000/60/EC) of the European Parliament and Council designed to integrate the way water
bodies are managed across Europe
Watershed
Line depicting the area within which all surface water will drain into an area of interest, such as a town or village. For the
assessment of surface water this boundary is defined from the topography
AECOM Study Report 8
AStSWF Areas Susceptible to Surface Water Flooding
CA Complementary Action
CFMP Catchment Flood Management Plan
CS Infoworks CS, Sewer Network Model
DEFRA Department for Environment, Flood and Rural Affairs
DTM Digital Terrain Model
EA Environment Agency
ES Emergency Services
ESFP East Sussex Flood Partnership
ESCC East Sussex County Council
FEH Flood Estimation Handbook
FMfSW Flood Maps for Surface Water
GIS Geographical Information System
HA Highways Agency
HBC Hastings Borough Council
LiDAR Light Detection And Ranging
mOD Metres Ordinance Datum
OP Options
PFRA Preliminary Flood Risk Assessment
RA Risk Assessment
RDC Rother District Council
SEA Strategic Environmental Assessment
SMP Shoreline Management Plan
SFRA Strategic Flood Risk Assessment
SSSI Sites of Special Scientific Interest
SUDS Sustainable Drainage Systems
SW Southern Water
SWMP Surface Water Management Plan
WFD Water Framework Directive
Acronyms
AECOM Study Report 9
Introduction
Hastings Borough Council (HBC) was successful in a Defra bid for funding to tackle surface water flooding in the Borough. The
bid was produced by AECOM on behalf of HBC and was based on the Areas Susceptible to Surface Water Flooding Map
(AStSWF) published by the Environment Agency (EA) as well as the Strategic Flood Risk Assessment (SFRA) for the area and
local knowledge shared by HBC, EA and East Sussex County Council.
The funding awarded to Hastings Borough Council has been used to produce a Borough-wide Surface Water Management Plan
(SWMP) as well as funding the delivery of some of the solutions identified on the ground.
The Hastings SWMP was based upon the guidance contained within Defra‟s „Surface Water Management Plan Technical
Guidance‟ (hereafter referred to as „the Defra Guidance‟), dated March 2010.
The Defra guidance includes a framework for undertaking SWMPs illustrated by the wheel diagram below:
Figure 1: Framework for undertaking a SWMP Study
Introduction and Background
Map and
communicate risk
AECOM Study Report 10
Background
Study Area Overview
Hastings Borough is located within East Sussex on the south east coast of England. The Borough has an area of 3,066ha, the
majority of which is used for residential purposes.
Figure 2: Location of Hastings within East Sussex
The main settlements within the Borough include the Town Centre, Old Town, St Leonards, St Helens, Hollington, West Marina
and Bulverhythe.
Figure 3: Overview of Hastings
AECOM Study Report 11
Hastings is located where the sandstone beds, at the heart of the Weald, meet the English Channel, forming tall cliffs to the east
of the town. Hastings Old Town is in a sheltered valley between the East Hill and West Hill. The town spreads westwards and
northwards forming a single urban centre with the more suburban area of St Leonards-on-Sea to the west. Roads from the Old
Town valley lead towards Clive Vale and the former village of Ore, from which "The Ridge", marking the effective boundary
between Hastings and Rother, extends north-westwards towards Battle. Beyond Bulverhythe, the western end of Hastings is
marked by low-lying land known as Glyne Gap, separating it from Bexhill-on-Sea.
The beach is mainly shingle, although wide areas of sand are uncovered at low tide. The town is generally built upon a series of
low hills rising to approximately150 m above sea level at "The Ridge" before falling back in the river valley further to the north.
There are three Sites of Special Scientific Interest (SSSI) within the Borough; Marline Valley Woods (an ancient woodland of
pedunculate oak-hornbeam which is uncommon nationally), Combe Haven (site of biological interest, with alluvial meadows, and
the largest reed bed in the county, providing habitat for breeding birds) and Hastings Cliffs To Pett Beach (The site runs along the
coast and is of both biological and geological interest).
From a socio-economic perspective, the history of Hastings paints it as a thriving seaside town enjoying economic success and a
prosperous society. However, in recent decades, the town has experienced a sustained economic decline, leading to an increase
in social problems and the development of distinct pockets of deprivation. According to the national indicators of deprivation,
Hastings is the most deprived town in the South East and one of the most deprived areas in the country1. Flooding Sources
Experience has shown that the vast majority of flooding problems in Hastings Borough cannot be attributed to a single source but
are largely as a result of a combination of factors such as tide locking, surface water runoff, groundwater, high river flows,
hydraulic overloading of the sewer network, blocked gullies, etc.
The various sources likely to have an impact in terms of flooding within the Borough are summarised below.
Sea: The tidal influence along the Combe Haven extends from just upstream of Filsham Nature Reserve to the river mouth at
Bulverhythe. Along this stretch flooding can be caused by a combination of high tides and significant river flows that, on their
own, may not cause any difficulties to the system.
Rivers: Hydraulically, Hastings forms part of the Cuckmere and Sussex Havens Catchment. However, the only major fluvial
catchment draining the Borough is the Combe Haven. The Combe Haven lies to the north-east of Bexhill and to the west of
Hastings. Its catchment is predominantly rural in nature and covers an area of 5,150ha extending over Rother and Hastings.
The main rivers identified within the Borough are Combe Haven, Spring Ditch, Decoy Pond, Pebsham Stream, Hollington
Stream, South Saxons Sewer and Bexhill Road Sewer. From these the Hollington Stream, directly linked to surface water
flooding, is known to have produced significant flooding in the recent past.
Some minor watercourses also exist in the Borough; however, these are reported not to have caused any flooding problems in
the past.
Sewers: Flooding can occur when the flow entering a sewer exceeds its hydraulic capacity thus surcharging the system. The
sewer network draining Hastings is largely combined along the low lying stretches (coastal area) which has historically
manifested in flooding occurring in these areas. Problems with capacity can be further compounded by high tides preventing
outfalls from discharging treated effluent effectively. Groundwater: High groundwater levels and resultant spring flows are
recognised as a source of flooding along the coastal strip of Hastings. This high water table in the gravel beds can be pushed
higher still by the tide, resulting in complex and difficult to predict flooding where no obvious watercourse or source is identified.
This is the case in low lying parts of St Leonards and Bulverhythe.
1 Safer Hastings Partnership (2008) Hastings Community Safety Plan 2008-11. Available at
http://www.saferhastings.co.uk/CSPlan_cropped%20to%20size%20smaller_file.pdf
AECOM Study Report 12
Overland Flow: Due to its topography (surrounded by hills), overland flow is a well recognised problem across the Borough, as
recognised by the AStSWF maps. The impact of overland flow can be compounded by high river flows, blockages, high tides and
groundwater emergence as has been recognised to be the case across Hastings.
Artificial Sources: There are a number of artificial sources across the Borough; however, these do not have a history of flooding
and under normal working conditions are unlikely to contribute to flooding from any other sources.
AECOM Study Report 13
The preparation stage was the first and arguably the most important step in the preparation of the SWMP as it established the
foundations over which the SWMP was undertaken.
This stage was divided in three well defined parts:
- Identify the need for a SWMP study
- Establish Partnership
- Scope the SWMP
1.1 Identify the need for a SWMP study
The objective of this initial step was to identify whether there was a need for a SWMP taking into consideration flooding history,
existing modelling information, anecdotal evidence, etc.
In the case of Hastings Borough this need had already being recognised by Defra and the EA by the award of funding for the
production of a Borough-wide SWMP following the successful submission of a bid to tackle surface water flooding.
1.2 Establish Partnership
The objective of this part of the SWMP was to identify the organisations that should be involved in the study as well as clarify
their roles and responsibilities.
1.2.1 Partners
Partners are organisations with responsibilities for decisions and actions to be taken. For the development of the Hastings
SWMP they were:
- Hastings Borough Council (HBC) – lead organisation
- Environment Agency (EA)
- Southern Water (SW)
- East Sussex County Council (ESCC)
- Rother District Council (RDC)
The level of involvement of RDC was limited as it was established early in the process that there was little correlation between
surface water flood risk in Hastings and Rother. This conclusion was reached following a review of the catchment extents which
suggested that the political borders presented a good correlation to the catchment boundaries and therefore any surface water
problems in one area could not be attributed to what happens in the other.
1.2.2 Stakeholders
A stakeholder is anyone affected by or interested in the problem or solution. Therefore anybody reading this report would fall into
this category. There are a number of organisations that could be regarded as key stakeholders due to their direct involvement in
the prevention, response or management of surface water flooding across the Borough. These include:
- Emergency Services (ES)
- Highways Agency (HA)
- Statutory Undertakers (apart from Southern Water – partner)
- East Sussex Flood Partnership (ESFP)
1.2.3 SWMP Working Group
A working group was formed with representatives of the partners to steer/assist the SWMP study. In order to ensure the SWMP
would complement the existing local processes/structures, representatives from a number of associated disciplines were
identified and invited to form part of the working group. The following table provides a summary of the members of the working
group as well as the various disciplines/sectors represented:
1 Preparation Stage
AECOM Study Report 14
Table 1.1: Hastings SWMP – Working Group Structure and Representatives
Organisation Representatives Discipline/Sector
Hastings Borough Council Virginia Gilbert / Nick Sangster Natalie Bumpus Brian Williamson/ Charles Sharrod
Amenities, Waste & Leisure (Project Lead) Spatial Planning Emergency Planning
Environment Agency Ian Nunn Les Norman
Asset Management Flood Risk Management
Southern Water John Challoner Sewerage
East Sussex County Council Nick Claxton Mark Andrew Derek Ireland
Flood Risk (Lead Local Flood Authority) Structures Highways
Rother District Council Alan Dodge Civil Engineering – General
AECOM David Pope / Galo Pinto Flood Risk Management (Project Consultant)
The group met periodically (approximately once a month) to review progress and agree the way forward for the study. In addition
to the regular progress meetings, a series of special events (workshops, site visits, etc) were undertaken during the study with
active participation from all members of the working group.
Links between the Hastings SWMP working group and the East Sussex Flood Risk Group (led by ESCC) were maintained
through HBC and ESCC representatives sitting on both committees. This approach ensured consistency on the work undertaken
across East Sussex and aimed to facilitate the fulfilment of the responsibilities of ESCC as lead local flood authority.
1.2.4 Partner‟s Commitments
All partners expressed their intention of working together to contribute to the production of a robust Surface Water Management
Plan for Hastings. Furthermore, they indicated their willingness to share information as well as attend working group meetings
and other associated events when requested. A data sharing protocol was agreed and signed by all the partners to facilitate the
release of information for the study.
The production of a memorandum of understanding was also discussed within the working group but deemed unnecessary as all
partners were committed to contribute effectively to the delivery of the SWMP.
It was agreed by all partners that in order to deliver the project in the required timeframe, decisions would be taken within the
working group whenever possible. It was, however, recognised that higher level discussions might be required within the
partners‟ organisations at times.
1.3 Scope the SWMP
The objective of this part of the Surface Water Management Plan (SWMP) was to clarify what approach the study should take
based on the available information and the objectives set by all partners involved.
1.3.1 Aim
The overall aim of the SWMP was to prepare a robust plan to reduce the number of properties at risk of surface water flooding in
Hastings through the implementation of cost-effective local solutions.
1.3.2 Objectives
The following general objectives were identified by the working group:
- Produce a robust SWMP following the guidelines set out in Defra‟s „Surface Water Management Plan Technical Guidance‟
(herein referred to as „the Defra Guidance‟), dated March 2010.
- Determine the locations of the main flood risk management and drainage assets as well as identify their ownership and
condition by producing a borough-wide asset register in GIS format.
- Develop an asset maintenance/action plan with the aim of ensuring all main flood risk management and drainage assets are
adequately maintained by the relevant organisation.
AECOM Study Report 15
- Map current and potential surface water flood risk areas, irrespective of source, and engage the community and all
stakeholders to share this knowledge.
- Determine the potential consequences of surface water flooding, now and in the future, so that priorities can be established
with regards to the merits of different mitigation strategies. The outcome of the SWMP should inform any further bidding
process for flood protection funding.
- Identify effective, affordable, achievable and cost-beneficial measures to mitigate surface water flood risk which achieve
multiple benefits where possible. Emphasis should be made on finding suitable local solutions that could be implemented with
the collaboration of the community.
- Work with the EA to improve the flood warning service in light of the outcome of the study.
- Inform the strategic and emergency planning across Hastings to reduce the risk posed by surface water flood risk to members
of the public now and in the future.
- Link the SWMP with other schemes being managed/promoted by partners and other stakeholders with the aim of maximising
the opportunities to deliver solutions on the ground.
- Develop an implementation plan showing how partners and stakeholders will work together to finance and implement the
preferred strategy.
- Tie-in the SWMP with other EA/Defra studies as well as other SWMPs being undertaken across the country to ensure best
practice is observed.
- Periodically review the plan and monitor the effectiveness of chosen solutions.
1.3.3 Links to Partners Programmes
The following existing programmes were identified by the partners as having links to the SWMP:
Table 1.2: Partners‟ Programmes linked to the Hastings SWMP
Organisation Existing Programmes
Hastings Borough Council EA sponsored Coastal Pathfinder (Climate Change) Climate Change Adaptation Study Bulverhythe Flood Defences – Emergency Planning
Environment Agency Catchment Flood Management Plan SUDS Retrofitting Pilot Project Hollington Stream Rapid Response Catchment Action Plan
Southern Water Flood Relief Scheme at Collier Road Pollution Reduction Scheme at Old Roar Gill Bathing Water Risk Study
East Sussex County Council ESCC Preliminary Flood Risk Assessment
Rother District Council None
In addition to the above partners programmes, East Sussex County Council established East Sussex Flood Partnership (ESFP)
in January 2010. This group which includes all the partners of the Hastings SWMP was created in response to the Pitt Review
recommendations and government requests to upper tier authorities to develop strategic level partnerships with key stakeholders
to develop and integrate flood risk management within their areas..
Although not governed by formal agreement, the ESFP‟s terms of reference focus on the delivery of the requirements of the
Flood and Water Management Act and the County Council‟s statutory duty as a Lead Local Flood Authority.
1.3.4 Engagement Plan
It was agreed that Hastings Borough Council would lead the stakeholder engagement, which would comprise the following tasks:
- Internal liaison with Councillors (HBC)
- A briefing to Councillors/HBC Officers to present the study
- A workshop with residents and relevant stakeholders in areas where recommendations are being made
AECOM Study Report 16
- An event for the general public
It is envisaged that any comments made by residents will be considered by the working group and will inform the continuous
revision of the SWMP. It is important to note that the SWMP should be a live document and that the working group created will
continue working together post-completion of the study with the aim of delivering the objectives set out as part of the Hastings
SWMP.
1.3.5 Data Availability
All partners were consulted with regards to the data available to inform the production of Hastings SWMP. A data register
capturing the information available to inform the study from all partners was compiled and is included as Appendix 1A.
1.3.6 Level of Assessment
The Hastings SWMP was based on the Defra Guidance which identifies three levels of assessment as potentially required to
inform the SWMP. The study followed a sequential approach which started by the application of the Strategic Assessment at
Borough-wide level and included the detailed assessment of specific locations within Hastings.
AECOM Study Report 17
The Risk Assessment Stage aims to identify the reasons behind surface water flooding problems across the Borough with the
intention of mapping and communicating the risk and therefore is a vital part of the SWMP process.
During the scoping of the SWMP, it was recognised that in order to maximise efficiency in terms of the financial and time
constraints for the study the Risk Assessment Stage for the Hastings SWMP should be undertaken in phases:
- Strategic Assessment
- Intermediate Assessment
- Detailed Assessment
The final phase of the Risk Assessment Stage involves mapping and communicating the risk identified throughout the different
phases of this Stage of the SWMP.
2.1 Strategic Assessment
The objective of this phase was to identify broad locations which are considered to be more vulnerable to surface water flooding
with the aim of implementing a risk based approach to the assessment of flood risk and options for implementation.
The Strategic Assessment phase involved the following steps:
- Collate information for the Strategic Assessment
- Undertake Strategic Assessment
2.1.1 Collate information for the Strategic Assessment
The strategic assessment was based on existing information, as outlined by the Defra guidance. The principal sources of data
and information considered as part of the Hastings SWMP Strategic Assessment are summarised below:
Table 2.1: Information used to inform the Strategic Assessment
Data Source Coverage Comments
Historical Flooding
HBC 1969/85; 1993/2003;
2006/2009 Periods missing. No detailed information available
ES 1997/2010 (May) Inconsistent level of detail
EA Main Rivers Flooding Extents only
SW 1988/2010 (March)
AStSWF EA National FMfSW were released at the end of November 2010 and therefore were not available to inform this phase of the
assessment
LiDAR Data EA Borough-wide Some small areas around the Borough boundary missing
Hastings Strategic Flood Risk Assessment
(SFRA) HBC Borough-wide Completed in April 2008
2.1.2 Undertake Strategic Assessment
The strategic assessment made use of the information listed above which was entered into a Geographical Information System
(GIS) to facilitate the overlying of the different layers of information.
2 Risk Assessment Stage
AECOM Study Report 18
As part of the Strategic Assessment stage the following Borough-wide maps were created:
Table 2.2: Maps produced as part of the Strategic Assessment
Drawing Number Title
60156460/RA/001 Hastings Flooding History
60156460/RA/002 AStSWF + Hastings Flooding History
60156460/RA/003 Factors Influencing Flood Risk
60156460/RA/004 LiDAR Topographic Information
By bringing together the information collated for the assessment, it was possible to identify surface water flood hotspots across
the Borough. A total of 16No. medium to large flood hotspots areas were identified during this initial assessment. These areas
are shown in Sketch 001 (Maps section).
The flood hotspots areas identified were discussed during a progress meeting of the working group and a consensus reached in
terms of the top eight priority areas. It was agreed by the working group that to ensure transparency these eight areas would be
subject to a priority scoring system to establish the top four areas to be looked at in more detail as part of the intermediate stage.
It is important to recognise the perceived lack of detail/consistency of the historical records provided by the different partners. As
a result of these inconsistencies and despite efforts to select only the relevant records for this study, some level of inaccuracy
might remain in this stage of the assessment.
2.2 Intermediate Assessment
The objective of this phase was to gain an improved understanding of surface water flooding, identify localised flood hotspots and
associated suitable mitigation measures as well as inform the decision making process with regards to the need for further
assessment.
The Intermediate Assessment phase involved the following steps:
- Collate information for Intermediate Assessment
- Undertake Intermediate Assessment
- Determine whether more detail assessment is required
2.2.1 Collate information for Intermediate Assessment
The intermediate assessment was informed by the output of the strategic assessment and by the following information made
available by partners and key stakeholders:
Table 2.3: Information used to inform the Intermediate Assessment
Data Source Coverage Comments
Extent of Sewer Network SW Borough-wide GIS layer provided
Location of Pumping Stations SW Borough-wide Only pumping stations operated by SW
included
Flood Hotspot Locations as identified by sewer modelling
SW Borough-wide GIS layer provided
Schematic of Pumping Arrangements SW Borough-wide
Alignment of Main Rivers EA Borough-wide
Alignment of Ordinary Watercourses EA/HBC (SFRA)
Borough-wide
Hydraulic modelling results and reports EA Combe Haven
including Hollington Stream
1-D ISIS and 2-D Tuflow model
AECOM Study Report 19
Table 2.3: Information used to inform the Intermediate Assessment (continued)
Data Source Coverage Comments
NFCDD Information EA Borough-wide Coastal assets not included
Location of Gullies ESCC Borough-wide GIS layer provided
Location of Culverts ESCC Borough-wide
Location of Highway Structures >1m diam ESCC Borough-wide
Location of Reservoirs in Operation HBC Borough-wide
Areas subject to Escarpment HBC/EA (SFRA)
Borough-wide
Location of Existing Ponds HBC
(SFRA) Borough-wide
Location of Dry Valleys HBC/EA (SFRA)
Borough-wide
Location of Springs HBC/EA (SFRA)
Borough-wide
Maintenance Records and Regimes
EA Borough-wide NFCDD and general information only
SW Borough-wide General information only
ESCC Borough-wide General information only
HBC Borough-wide General information only
Site Specific Flood Risk Assessments HBC Flood hotspots No recent FRAs submitted for development
within these areas
Locations of proposed new residential and employment development
HBC Borough-wide
Aerial Photography HBC Borough-wide
Contour lines HBC Borough-wide 5 metre contours
Location of critical infrastructure HBC Borough-wide
Cuckmere and Sussex Havens Catchment Flood Management Plan
EA Catchment-wide Brief mention of surface water flood risk but
number of people deemed to be affected during an extreme event seems low (70)
Rother District Council (RDC) SFRA RDC District-wide No relevant information for Hastings found
East Sussex Local Flood Warning Plan EA County-wide
Emergency Plan 2010 HBC Borough-wide
Bulverhythe 2007 flood response document HBC Bulverhythe and
surrounding areas
Bulverhythe Flood Evacuation Plan Oct 2009
HBC Bulverhythe and
surrounding areas
Multi Agency Flood Plan for Sussex (Part 1) ESCC Sussex
Site visits to the top four flood hotspots Working
group Flood hotspots one
to four Undertaken by representatives of the various partners on 18
th August 2010
Discussions held with representatives of SW, EA, ESCC, RDC and HBC
Working group
Borough-wide Aimed at gaining a better understanding of
flooding issues across Hastings
It must be noted that whereas additional items of data might have been provided by the various partners, the use and reference
of the information used for this stage of the assessment followed the guidelines set out by Defra. Therefore there might be some
data/information that was made available but was not deemed directly relevant for this particular phase of the SWMP.
AECOM Study Report 20
2.2.2 Undertake Intermediate Assessment
The intermediate assessment started by using the output of the strategic assessment stage (top eight flood hotspots - as agreed
by the working group) and applying a priority scoring system to establish the top four flood hotspots which were the focus of the
intermediate assessment stage.
The priority scoring system used for this study was based on scoring systems used for other SWMPs and adjusted/modified to
reflect the type/quality of data available for this study. Among the factors considered for the scoring system were:
- Flooding History (number of incidents/internal/external)
- Number of properties within AStSWF (FMfSW were not available to inform this process)
- Location of critical infrastructure
- Flood Hotspots areas identified by sewer modelling
- Consequences of flooding (businesses/residences)
A detailed description of the scoring system adopted as well as a summary of the scoring itself is included as Appendix 2A.
Following the application of the priority scoring system, the top four flood hotspots were found to be:
- Town Centre (flood hotspot 1)
- Old Town (flood hotspot 2)
- Hollington Stream (flood hotspot 3)
- Warrior Square (flood hotspot 4)
The assessment undertaken for the above flood hotspots as part of this phase included a review of the data/information listed
above (Table 2.3) as well as the preparation of a series of maps/sketches.
As part of the Intermediate Assessment phase the following maps were created for the top four flood hotspots:
Table 2.4: Maps produced to inform the Intermediate Assessment of the flood hotspots
Drawing Number Title
60156460/RA/1X0 Hastings Flood Hotspot X (AStSWF + Hastings Flooding History)
60156460/RA/1X1 Hastings Flood Hotspot X (Factors Influencing Flood Risk+ Hastings Flooding History)
60156460/RA/1X2 Hastings Flood Hotspot X (Sewer Network + Ground Contours)
60156460/RA/1X3 Hastings Flood Hotspot X (Aerial Photograph)
60156460/RA/1X4 Hastings Flood Hotspot X (Gullies)
X denotes the number assigned to the flood hotspot (1 to 4)
The above maps were used to inform a site visit carried out by the working group and aimed at sharing knowledge as well as
identifying reasons behind flooding at these locations. The site visits were undertaken on 18th
August 2010 and represented a
very important step in understanding the issues associated with these areas. The site visit briefing note (included as Appendix
2B) provides more details on the way the site visits were undertaken.
A site visit report was prepared for each of the top four flood hotspots. These reports summarise the findings of the intermediate
assessment carried out for each of these sites and are complemented by additional maps (see Table 2.5). The site visit reports
are also included as Appendix 2B.
AECOM Study Report 21
Table 2.5: Maps produced to summarise outcome of Site Visits
Drawing Number Title
60156460/RA/2X0 Historical Flooding Issues
60156460/RA/2X1 Potential Mitigation Measures
(X denotes the number assigned to the flood hotspot (1 to 4))
The intermediate assessment undertaken for the four flood hotspots is summarised in the table below.
AECOM Study Report 22
Table 2.6: Summary of the findings of the Intermediate Assessment
Flood Hotspot
Reasons behind Historical Flooding
Predominant Flooding
Mechanisms
Likely Implications of Surface Water Flooding
Possible mitigation measures Comments
1. Town
Centre - Infrastructure failure/
capacity exceeded
- Natural valley
location
- Ground profile
- Overland flooding
(thresholds lower
than road – Town
Centre)
Significant duration/depth of flooding at Town Centre. Significant disruption caused to businesses and residents
Short Term: Flood resistance / resilience; education Medium Term: Modify ground profile; increase capacity of storm outfall Long Term: Replace the combined sewer system; increase number of surface water outfalls.
Further investigation required to improve understanding of links between pumping station and existing outfalls.
2. Old Town - Infrastructure
blockages/capacity
exceeded
- Natural valley
location
- Ground profile
- Overland flooding
(thresholds lower
than road –
George Street)
- Sewer capacity
exceeded /
blockages
Significant duration/depth of flooding at junction between The Bourne and Rock-a-Nore Road. Significant disruption caused to businesses
Short Term: Flood resistance / resilience; education Medium Term: Improve SUDS; increase capacity of storm outfall Long Term: Replace the combined sewer system;
make use of disconnected section of storm sewer; increase number of surface water outfalls.
3. Hollington
Stream - Channel blockages
- Sewer/culvert
capacity exceeded
- Inadequate use of
existing water
management
structures
- Nature of catchment
(Rapid Response)
- Sewer/culvert
capacity
exceeded as
outfalls unable to
discharge into
Hollington Stream
Significant duration/depth of flooding at junction between Battle Road and Upper Church Road as well as the southern edge of Hollington Old Lane. Significant disruption caused to residents
Short Term: Flood resistance / resilience; education; install trash screen; clear debris and improve understanding & use of water management structures Medium Term: Implementation of SUDS; increase
capacity of river channel Long Term: Additional storm water attenuation
Further investigation required to improve understanding of water management structures at upstream end of the catchment.
4. Warrior
Square - Infrastructure failure/
capacity exceeded
- Natural valley
location
- Sewer capacity
exceeded/failures
Isolated locations likely to experience significant depth/duration due to local topography (basements). Potential significant disruption to some businesses and residents
Short Term: Flood resistance / resilience; education Medium Term: Improve SUDS Long Term: Replace the combined sewer system; increase number of surface water outfalls
AECOM Study Report 23
2.2.3 Determine whether more detailed assessment is required
This part of the intermediate assessment was informed by the review of the information made available by different sources and
the output of the site visits undertaken with representatives of the different partners.
The intermediate assessment concluded that there was a need to undertake detailed assessment for flood hotspot 3 – Hollington
Stream in order to gain a better understanding of the water management structures located at the upstream end of this
catchment. No other areas were found likely to benefit significantly from further assessment at this stage of the process.
The following table has been created to facilitate the presentation of the conclusions reached and recommendations made
following completion of the Intermediate Assessment.
AECOM Study Report 24
Table 2.7: Summary of the Conclusions and Recommendations of the Intermediate Assessment
Flood Hotspot
Level of Understanding of
flooding mechanisms
Data available to facilitate improved understanding of flooding mechanisms
Possible Detailed Assessment Techniques (Benefits and Constraints)
Conclusions Recommendations
1. Town
Centre
Generally good
understanding of
flooding mechanisms
and areas at risk
- Sewer Network Models
(Infoworks CS)
An Infoworks 2-D model could be built combining the existing sewer network model with a digital terrain model. Benefits: Improved understanding of likely flood pathways and receptors as well as indication of depth, velocity, rate of onset and duration of flooding Constraints: Potentially costly and time consuming. Unlikely to inform any short term solutions.
Whereas an Infoworks 2-D model would be desirable, it is unlikely to provide any real value to the identified short term solutions. Additionally, the FMfSW provide some of the details that could be obtained from the Infoworks 2-D model.
- Do not undertake any
additional modelling at this
stage.
- Review FMfSW and continue
with Options Stage
2. Old Town Generally good understanding of flooding mechanisms and areas at risk
- Sewer Network Models
(Infoworks CS)
An Infoworks 2-D model could be built combining the existing sewer network model with a digital terrain model. Benefits: Improved understanding of likely flood pathways and receptors as well as indication of depth, velocity, rate of onset and duration of flooding Constraints: Potentially costly and time consuming. Unlikely to inform any short term solutions.
Whereas an Infoworks 2-D model would be desirable, it is unlikely to provide any real value to the identified short term solutions. Additionally, the FMfSW provide some of the details that could be obtained from the Infoworks 2-D model.
- Do not undertake any
additional modelling at this
stage.
- Review FMfSW and continue
with Options Stage
3. Hollington
Stream
Reasonable understanding of flooding mechanisms and areas at risk. However, this could be improved by establishing condition and operation regime of water management structures at upstream end.
- ISIS/Tuflow (1-D/2-D)
model of Hollington
Stream (recently
completed by EA)
- MIKE 11 (1-D) model of
Hollington Stream (built
by Faber Maunsell in
2008 to inform the
Hastings SFRA)
Refinement of the recently completed ISIS/Tuflow model to identify the most appropriate operation regime for the water management structures at the upstream end of Hollington Stream Benefits: Identification of optimum operation regime for water management structures and potential for increased channel capacity. Constraints: To be effective needs to be accompanied by maintenance/operation plan which will depend on human intervention.
The refinement of the model will improve significantly the understanding of the operation of the water management structures. This will in turn enable the implementation of action plans aimed at reducing flood risk downstream by maximising storage upstream. The cost of this work is likely to be relatively low due to the amount of information readily available and the timeframe for completion should be relatively short.
- Proceed with the refinement
of the existing ISIS/Tuflow
model (detailed
assessment)
- Seek to improve emergency
response by contributing
effectively to the Hollington
Stream Rapid Response
Catchment Action Plan
AECOM Study Report 25
Table 2.7: Summary of the Conclusions and Recommendations of the Intermediate Assessment (continued)
Flood Hotspot
Level of Understanding of
flooding mechanisms
Data available to facilitate improved understanding of flooding mechanisms
Possible Detailed Assessment Techniques (Benefits and Constraints)
Conclusions Recommendations
4. Warrior
Square
Generally good understanding of flooding mechanisms and areas at risk
- Sewer Network Models
(Infoworks CS)
An Infoworks 2-D model could be built combining the existing sewer network model with a digital terrain model. Benefits: Improved understanding of likely flood pathways and receptors as well as indication of depth, velocity, rate of onset and duration of flooding Constraints: Potentially costly and time consuming. Unlikely to inform any short term solutions.
Whereas an Infoworks 2-D model would be desirable, it is unlikely to provide any real value to the identified short term solutions. Additionally, the FMfSW provide some of the details that could be obtained from the Infoworks 2-D model.
- Do not undertake any
additional modelling at this
stage.
- Review FMfSW and continue
with Options Stage
AECOM Study Report 26
2.3 Detailed Assessment
The intermediate assessment concluded that there was potential for significant benefits arising from a better understanding of the
water management structures at the upstream end of the Hollington Stream catchment and the role they have on flood risk
(fluvial/surface water) in the area. A detailed assessment was therefore undertaken to complement the knowledge of this section
of the stream directly linked to flood hotspot 3.
The Detailed Assessment phase involved the following steps:
- Select modelling approach
- Develop modelling approach
- Quantify current and future flood risk
2.3.1 Select modelling approach
It was discussed and agreed within the working group that the modelling work should use as basis the hydraulic model for the
Combe Haven catchment (including Hollington Stream) completed in January 2010 by the Environment Agency. The modelling
work was therefore undertaken using a combination of ISIS (1-D) and Tuflow (2-D). This was deemed to be the most appropriate
tool to achieve the objectives set out above as in this area the risk of surface water flooding is directly related to fluvial flooding.
2.3.2 Develop modelling approach
The base model was reviewed and refined locally using historical information on the dams. No significant changes to the base
model were, however, undertaken.
2.3.3 Quantify current and future flood risk
The refined model enabled the formulation of a recommended operation regime aimed at maximising the storage volume
upstream of the dams thus reducing the surcharging of the culverts further downstream and making space for surface water to
enter the river network.
Additionally, the various scenarios run as part of the modelling process facilitated the identification of capacity limits for the dams
under low and high return period events. The modelling work undertaken as part of the detailed assessment phase is
summarised in Table 2.8 and described in detail in Appendix 2C.
Table 2.8: Summary of Modelling results in relation to Overtopping of the Dams and Surcharging of Culvert at Upper Glen Road
Return Period (Years)
Settings Overtopping Culvert Surcharge
Dam 1 Dam 2 Channel Section
Dam 1 Dam 2 Upper Glen
Rd Gardens
100
Fully Open Original Original No (Fb 2.9m) No (Fb 1.3m) Yes Yes
Original Fully Open Original No (Fb 1.4m) No (Fb 2.1m) Yes Yes
Fully Open Fully Open Original No (Fb 2.9m) No (Fb 2.1m) Yes Yes
¼ Opening ¼ Opening Original No (Fb 1.1m) Yes (nominal)
(0.01 m) Yes Yes
¼ Opening ¼ Opening Modified No (Fb 1.1m) No (at risk) (Fb <0.1m)
Yes Yes
5 ¼ Opening ¼ Opening Original No (Fb 2.5m) No (Fb 1.9m) No (at risk) Yes (nominal)
⅛ Opening ⅛ Opening Original No (Fb 1.1m) No (Fb 0.1m) No No (at risk)
20 ¼ Opening ¼ Opening Original No (Fb 1.6m) No (Fb 1.2m) Yes Yes
⅛ Opening ⅛Opening Original No (Fb 1.1m) Yes (0.6 m) No (at risk) No (at risk)
(Fb= Freeboard; Original= set up as per Original model; Dam 1= northern dam; Dam 2= southern dam)
AECOM Study Report 27
2.4 Map and Communicate Risk
The final phase of the risk assessment stage involves mapping the areas identified as likely to be at risk of surface water flooding
and communicating this risk to the spatial and emergency planning teams of Hastings Borough Council as well as the relevant
stakeholders.
2.4.1 Map Surface Water Flooding
Mapping of the areas deemed susceptible to surface water flooding across Hastings was undertaken to:
- Help engage stakeholders on surface water flood risks
- Inform the spatial planning process
- Inform emergency planning functions
- Identify whether critical infrastructure is at risk from surface water flooding The information used to map surface water flood risk was refined throughout the production of the study as described below:
2.4.2 Areas Susceptible to Surface Water Flooding (AStSWF)
These are the first generation of EA Surface Water Flood Maps which were used as the basis for the ranking of settlements
deemed to be at risk of flooding from surface water by Defra as part of their initial funding allocation to tackle surface water flood
risk.
As far as the Hastings SWMP is concerned, these maps were the basis for the Preparation and Risk Assessment Stages of the
study. Furthermore, they were referred to when outlining potential solutions as part of the Options Stage of the study.
2.4.3 Flood Maps for Surface Water (FMfSW)
These are the second generation of EA Surface Water Flood Maps which were officially released at the end of November 2010.
These maps are generally deemed to provide a better representation (in comparison to the first generation) of surface water flood
risk as a result of significant refinement in the modelling process undertaken. It is important to note, however, that the FMfSW do
not supersede the AStSWF which should still be referred to as these maps represent a valid starting point, particularly in areas
where drainage networks are liable to blockage or are tide-locked.
As far as the Hastings SWMP is concerned, due to amount of work already undertaken using the AStSWF as basis, the use of
these refined maps was focused towards informing the mapping and communicating phase rather than revisiting the assessment
previously undertaken. In the absence of the locally agreed surface water information, to be confirmed by the lead local flood
authority (ESCC) as part of the Preliminary Flood Risk Assessment (PFRA), these maps should be referred to as they represent
the primary source of national derived information.
The AStSWF and the FMfSW were reviewed and discussed by the working group and found to provide a good representation of
the areas deemed to be at risk of surface water flooding across Hastings. It is accepted, however, that there are some areas with
a flooding history which are not shown as “at risk” and therefore, it is expected that these will be captured as part of the locally
agreed surface water information for the area.
The differences between the AStSWF and the FMfSW are summarised in Table 2.9.
Table 2.9: Differences between AStSWF and FMfSW
Properties AStSWF FMfSW Why different/same?
Annual Probability
Rainfall
1 in 200
chance
1 in 30 and 1 in
200 chance
1 in 30 added to allow a better understanding of lower
consequence, more frequent events such as the onset of sewer
flooding.
Storm Duration 6.5 hrs 1.1 hr profile 1.1 hr produced on average higher results than other durations
piloted
Rainfall Profile 50% summer 50% summer Recommended profile from the Flood Estimation Handbook (FEH)
AECOM Study Report 28
Table 2.9: Differences between AStSWF and FMfSW (continued)
Properties AStSWF FMfSW Why different/same?
Reduction to
rainfall amount to
represent
infiltration
0
Reduction to
39% in rural
areas and 70%
in urban areas
AStSWF did not consider infiltration
Reduction to
rainfall amount to
represent sewer
flow
0
Reduction of
0mm/hr rural,
12mm/hr urban
AStSWF did not consider effects of sewers
Manning‟s „n‟ 0.1 0.1 rural, 0.03
urban
Urban value reduces now as buildings are included in DTM.
Previously n was increased to account for lack of building
representation
DTM
Infoterra bare
earth LIDAR
and Geo
Perspectives
EA 2010
Composite
(SAR, EA
LIDAR and
PGA2 LIDAR)
with OS 2009
Mastermap
Buildings (DTM
raised by 5m)
Access to EA LIDAR available
Model Resolution 5m 5m Modelling at smaller resolution (for example 2m) was impracticable
at a national scale with the model used due to processing demands.
Model Domain
Size 5 km x 5 km 5 km x 5 km
5km x 5 km provides a reasonable balance between high intensity
local storms and larger less intense events
Buildings Not
represented
Represented in
the DTM using
the 2009 OS
Mastermap
Buildings layer
Earlier work identified that the presence of buildings improved the
routing of flow in urban areas. Use high buildings based upon the
DTM elevation plus 5m. Building outlines are best represented by
OS Mastermap polygons
Flood Depth
Threshold Bands
- 0.1 to 0.3m
(less)
- 0.3 to 1m
(intermediate)
- >1m (more)
- >0.1m
- >0.3m Consultation with partners resulted in 2 bands being produced
The guidance provided to accompany the FMfSW highlighted the importance of establishing the levels of confidence associated
with the EA Surface Water Flood Maps in relation to the local conditions. This exercise was undertaken with the working group
and the results are included in Table 2.10.
AECOM Study Report 29
Table 2.10: EA Surface Water Flood Maps - National and Local (Hastings) Uncertainty Levels
FMfSW AStSWF
Topic Source of Uncertainty
Confidence
Level National
Confidence
Level Local
(Hastings)
Source of Uncertainty Confidence
Level National
Confidence
Level Local
(Hastings)
Data
DTM accuracy Data ground level compared to real
ground level High High
Data ground level compared to real ground level
Medium Medium
DTM
resolution
Average ground level applied to 5m x 5m grid compared to real ground level
Medium - High Medium - High Average ground level applied to 5m x 5m grid compared to real ground level
Medium Medium
Consideration
of Buildings
MasterMap building position in degraded DTM compared to reality
Medium Medium N/A N/A N/A
Hydrology
How realistic is rainfall profile Medium Medium How realistic is rainfall profile Medium Medium
How well storm duration reflects worst case
Medium - High Medium - High How well storm duration reflects worst
case Medium - Low Medium - Low
Other main
data Inputs The EA intends to continue to build up their understanding of uncertainty of other inputs
Mo
de
l
Type How well does JFLOW route the water High High How well does JFLOW route the
water High High
Urban or Rural
Area
Are all urban areas in reality represented as urban in the model
High High N/A N/A N/A
Infiltration
Assumptions
How representative Urban and rural factors are compared to reality
Medium Medium How representative is no infiltration Very Low Very Low
Drainage
Assumptions
How representative 12mm/hr is compared to reality
Medium - Low Medium - Low How representative is 0mm/hr
compared to reality Very Low Very Low
Other major
model variable
assumptions
The EA intends to continue to build up their understanding of uncertainty of other variables / assumptions
Roughness How representative is the global use of
Mannings n values of 0.1 (rural) and 0.03 (urban)
Medium Medium How representative is the blanket use
use of Mannings n value of 0.1 Low Low
AECOM Study Report 30
The local assessment of uncertainty associated with the EA surface water flood maps was found to be very similar to the national
assessment undertaken by the EA. It was concluded therefore that the FMfSW provide a refined understanding of surface water
flooding issues across Hastings and therefore should be used as the primary point of reference in the absence of locally agreed
surface water flood risk information.
2.4.4 Other Sources of Flood Mapping Information
In addition to the EA Surface Water Flood Maps, other hydraulic models were used/developed during the preparation of the
Hastings SWMP and to inform relevant maps. These are summarised below:
- Overland flow model for Hollington Primary School which provides a better understanding of the overland flow paths and flood
receptors around flood hotspot 3
- Hydraulic modelling of Upper Hollington Stream which assisted the understanding of the water management structures (dams)
in the area but was not used to inform the mapping process as this was not the purpose of this model.
The various maps and sketches produced as part of the study are summarised below and included in the mapping section. All
maps are supported by a GIS database system which is available to Hastings Borough Council.
Table 2.11: List of Maps/Sketches produced to inform the Hastings SWMP
Drawing No. Title
001 Hastings Flooding History
002 AStSWF + Hastings Flooding History
003 Factors Influencing Flood Risk
004 LiDAR Topographic Information
005 Potential areas for SUDS (Borough wide)
006(A) FMfSW (1 in 200) + Hastings Flooding History
006(B) FMfSW (1 in 30) + Hastings Flooding History
007(A) Critical Infrastructure + FMfSW (1 in 200)
007(B) Critical Infrastructure + FMfSW (1 in 30)
110 - 114 Flood Hotspot 1 covering (AStSWF, flooding history, factors influencing flood risk, sewer network, ground contours, aerial photography and gullies)
115(A) and (B) Flood Hotspot 1 FMfSW (1 in 200) and (1 in 30) respectively including flooding history
120 - 124 Flood Hotspot 2 covering (AStSWF, flooding history, factors influencing flood risk, sewer network, ground contours, aerial photography and gullies)
125(A) and (B) Flood Hotspot 2 FMfSW (1 in 200) and (1 in 30) respectively including flooding history
130 - 134 Flood Hotspot 3 covering (AStSWF, flooding history, factors influencing flood risk, sewer network, ground contours, aerial photography and gullies)
135(A) and (B) Flood Hotspot 3 FMfSW (1 in 200) and (1 in 30) respectively including flooding history
140 - 144 Flood Hotspot 4 covering (AStSWF, flooding history, factors influencing flood risk, sewer network, ground contours, aerial photography and gullies)
145(A) and (B) Flood Hotspot 4 FMfSW (1 in 200) and (1 in 30) respectively including flooding history
210 and 211 Flood Hotspot 1 covering (historical flooding issues and potential mitigation measures respectively, as identified during the walkover survey with the working group)
220 and 221 Flood Hotspot 2 covering (historical flooding issues and potential mitigation measures respectively, as identified during the walkover survey with the working group)
230 and 231 Flood Hotspot 3 covering (historical flooding issues and potential mitigation measures respectively, as identified during the walkover survey with the working group)
AECOM Study Report 31
Table 2.11: List of Maps/Sketches produced to inform the Hastings SWMP (continued)
Drawing No. Title
240 and 241 Flood Hotspot 4 covering (historical flooding issues and potential mitigation measures respectively, as identified during the walkover survey with the working group)
SKETCH 001 Flood Hotspots
SKETCH 025 FHS 1 Medium Term Solutions
SKETCH 026 Upper Hollington Stream Maintenance (with annotation)
SKETCH 027 Flood Resistance Recommendations - Example Properties
Note: It is important to note that whereas more drawings/sketches were produced throughout the study to inform discussion, the ones listed above summarise the process.
2.4.4.1 Borough-wide Asset Register
During initial discussions with Hastings Borough Council and the working group, it became apparent that in order to improve the
understanding of the existing flood risk management and drainage infrastructure across Hastings, a Borough-wide asset register
needed to be created.
The reasoning behind this requirement was the perceived lack of information as to the ownership and maintenance regimes
associated with the various assets across the Borough.
The asset register was produced using a GIS system and was informed by significant amount of data provided by the various
partners. Due to the nature of the information included in the asset register, the use of GIS software (ArcView) is required to
interrogate the asset register. The asset register includes a criticality rating for all assets aimed at providing an indication as to
their importance from a surface water flood risk point of view. Also included is an indication of the current maintenance regime for
all assets, as advised by the relevant partners. Appendix 2D includes summaries on how the asset register was put together from
a technical perspective and how to interrogate it from a user point of view.
The main constraint in producing the asset register was the lack of detail/consistency of the asset records provided by the
different partners. As a result of these inconsistencies and despite efforts to provide a standard minimum level of information for
every asset, a few gaps remain for certain assets.
To complement the asset register, the production of a Borough-wide asset maintenance plan was originally discussed with the
working group. Unfortunately due to the number of assets identified across the Borough and the varying quality/level of detail of
the records available for the different assets, it was deemed impractical to obtain maintenance information for all assets. A
generic summary of typical maintenance periods for the assets in Hastings has been produced and is included in Appendix 2E.
2.4.5 Communicate Risk
One of the most important parts of the process is communicating the risk identified during the various stages of assessment. For
the Hastings SWMP, the following steps were identified as part of this phase of the study:
- Communicate risk to spatial planning
- Communicate risk to emergency planning
- Communicate risk to other stakeholders
2.4.5.1 Communicate risk to spatial planning
The findings of the Hastings SWMP are being communicated to the spatial planning team by:
- Supplementary Planning Note on Surface Water Flood Risk: this was produced in coordination with the working group to
provide additional guidance to the planning team of Hastings Borough Council on how to deal with planning applications in
areas deemed susceptible to surface water flooding. The Supplementary Planning Note on Surface Water Flood Risk is
included as Appendix 2F
AECOM Study Report 32
- Mapping of Surface Water Flood Risk: the various maps produced as part of the Hastings SWMP should inform the spatial
planning process and eventually be incorporated in a revised version of the Strategic Flood Risk Assessment (SFRA). Refer to
the mapping section for a full description of the maps and copies of them.
- Involvement in the working group: the spatial planning team are represented in the working group and given the commitment
of all partners to maintain the group beyond the completion of the Hastings SWMP study, it is envisaged that they will continue
to play an important role in shaping how surface water flood risk is managed across Hastings.
- Workshop for Hastings Borough Council Officers: it is envisaged that as part of the communications strategy for the Hastings
SWMP, a workshop/presentation will be given to councillors and Hastings Borough Council officers. The key messages for the
spatial planning team will be reiterated during this event.
2.4.5.2 Communicate risk to emergency planning
The findings of the Hastings SWMP are being communicated to the emergency planning team by:
- Mapping of Surface Water Flood Risk: the various maps produced as part of the Hastings SWMP should inform the
emergency planning process and any emergency action plans for the Borough. Refer to the mapping section for a full
description of the maps and copies of them.
- Involvement in the working group: the emergency planning team are represented in the working group and given the
commitment of all partners to maintain the group beyond the completion of the Hastings SWMP study, it is envisaged that they
will continue to play an important role in shaping how surface water flood risk is managed across Hastings.
- Workshop for Hastings Borough Council Officers: it is envisaged that as part of the communications strategy for the Hastings
SWMP, a workshop/presentation will be given to councillors and Hastings Borough Council officers. The key messages for the
emergency planning team will be reiterated during this event.
In addition to the above, a review of the procedures in place to deal with flood reports was carried out in close liaison with the
emergency planning team. As a result of this review the following documents, included as Appendix 2G, were produced:
- Procedure “to answer“ flood incident reports
- Flood Response Plan
- Flood Incident Report Form
2.4.5.3 Communicate risk to other stakeholders
The findings of the Hastings SWMP are being communicated to other stakeholders by:
- Mapping Critical Infrastructure likely to be affected by Surface Water Flooding: two maps and associated summary tables
were produced to identify critical infrastructure likely to be affected by surface water flooding during the 1 in 30yr and the 1 in
200 yr return period events. The tables are included as Appendix 2H and the maps in the mapping section.
In addition to the above, the following documents were drafted with the aim of informing the understanding of the general public
to flood risk and actions they should consider to minimise the impacts of flooding events.
- Flood Information Pack
- Flood Resistance/Resilience Measures These are discussed in more detail in the Options Stage of this report.
AECOM Study Report 33
The Stage of the SWMP aims to identify and assess the options to mitigate/reduce the risk of surface water flooding across the
Borough with the intention of finding the most appropriate mitigation measures which can be agreed and taken forward to the
Implementation Stage. To achieve this objective the Options Stage was divided in two phases:
- Identify measures
- Assess Options
3.1 Identify Measures
The purpose of this phase is to formulate and short-list the various options to be assessed. The Identify Measures Phase
involved the following steps:
- Identify measures
- Short-list measures
3.1.1 Identify Measures
As part of the risk assessment stage, a number of measures were identified as possible mitigation to the risk of surface water
flooding in the short, medium and long term for the top four flood hotspots. These are summarised below:
Table 3.1: Summary of Options identified during the Risk Assessment Stage
Flood Hotspot Possible mitigation measures
Short Term Medium Term Long Term
1. Town Centre - Flood resistance / resilience
- Education
- Modify ground profile
- Increase capacity of storm
outfall
- Replace the combined sewer
system
- Increase number of surface
water outfalls
2. Old Town - Flood resistance / resilience
- Education
- Improve SUDS
- Increase capacity of storm
outfall
- Replace the combined sewer
system
- Make use of disconnected
section of storm sewer
- Increase number of surface
water outfalls.
3. Hollington
Stream - Flood resistance / resilience
- Education
- Install trash screen
- Clear debris and Improve
understanding & use of
water management
structures
- Improve maintenance of
sewer/culvert system along
Hollington Old Lane
- Implementation of SUDS
- Increase capacity of river
channel
- Additional storm water
attenuation
4. Warrior
Square - Flood resistance / resilience
- Education
- Improve SUDS - Replace the combined sewer
system
- Increase number of surface
water outfalls
3 Options Stage
AECOM Study Report 34
3.1.2 Short-list measures
In order to establish what options should be taken forward to the next stage of the Options Appraisal process, the Defra
Guidance recommends a short listing criteria which is summarised below.
Table 3.2: Short-listing Criteria Recommended by Defra
Criteria Description Score
Technical Is it technically possible and buildable?
Will it be robust and reliable? U (unacceptable) – measure eliminated from
further consideration
-2 severe negative outcome
-1 moderate negative outcome
+1 moderate positive outcome
+2 highly positive outcome
Economic Will benefits exceed costs?
Social Will the community benefit or suffer from
implementation of the measure?
Environmental Will the environment benefit or suffer from the
implementation of the measure?
Objectives Will it help achieve the objectives of the SWMP
partnership?
The Defra guidance also recommends that the “Do nothing” and “Do minimum” options are taken forward to the next stage and
that the reasons for short-listing or rejecting any measures should be documented as part of the assessment.
The application of the above short-listing criteria on the top four flood hotspots was undertaken as summarised in the following
tables.
Table 3.3: Application of Short-listing Criteria to Flood Hotspot 1
Option
Te
ch
nic
al
Ec
on
om
ic
So
cia
l
En
vir
on
men
tal
Ob
jec
tiv
es
Ov
era
ll S
co
re
Taken to detailed
analysis? Comments
Do Nothing 2 -1 -2 0 -2 -3 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Do Minimum 1 -1 -1 0 -1 -2 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Flood resistance / resilience
2 1 1 1 2 7 Yes Technically feasible and financially viable
option that could provide significant improvements
Education 2 1 1 1 1 6 Yes Feasible and potentially inexpensive. The major problem will be public willingness to
implement advice
Modify ground profile 2 -1 1 1 2 5 Yes Technically can be implemented and would
benefit the area
Increase capacity of storm outfall
1 -2 1 1 1 2 No Viable from a technical point but unlikely to
be feasible from a financial perspective
Replace the combined sewer system
2 U 1 1 0 U No Although technically feasible the cost is not
viable.
Increase number of surface water outfalls
1 -2 1 1 1 2 No There could be implications on the
environment (water quality) but the main problem is the financial aspect
AECOM Study Report 35
Table 3.4: Application of Short-listing Criteria to Flood Hotspot 2
Option
Te
ch
nic
al
Ec
on
om
ic
So
cia
l
En
vir
on
men
tal
Ob
jec
tiv
es
Ov
era
ll S
co
re
Taken to detailed
analysis? Comments
Do Nothing 2 -1 -2 0 -2 -3 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Do Minimum 1 -1 -1 0 -1 -2 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Flood resistance / resilience
2 1 1 1 2 7 Yes Technically feasible and financially viable
option that could provide significant improvements
Education 2 1 1 1 1 6 Yes Feasible and potentially inexpensive. The major problem will be public willingness to
implement advice
Improve SUDS 2 -1 1 1 1 4 No Technically can be implemented but would
bring very limited benefits to the area as suggested by revised flood mapping
Increase capacity of storm outfall
1 -2 1 1 1 2 No Viable from a technical point but unlikely to
be feasible from a financial perspective
Replace the combined sewer system
2 U 1 1 0 U No Although technically feasible the cost is not
viable.
Make use of disconnected section of
storm sewer 1 -2 1 1 1 2 No
Technically feasible but will need to be undertaken as part of a wider scheme to
make it workable.
Increase number of surface water outfalls
1 -2 1 1 1 2 No There could be implications on the
environment (water quality) but the main problem is the financial aspect
AECOM Study Report 36
Table 3.5: Application of Short-listing Criteria to Flood Hotspot 3
Option
Te
ch
nic
al
Ec
on
om
ic
So
cia
l
En
vir
on
men
tal
Ob
jec
tiv
es
Ov
era
ll S
co
re
Taken to detailed
analysis? Comments
Do Nothing 2 -1 -2 0 -2 -3 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Do Minimum 1 -1 -1 0 -1 -2 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Flood resistance / resilience
2 1 1 1 2 7 Yes Technically feasible and financially viable
option that could provide significant improvements
Education 2 1 1 1 1 6 Yes Feasible and potentially inexpensive. The major problem will be public willingness to
implement advice
Install trash screen 2 1 1 1 1 6 Yes Simple and economical to implement
provided the community is prepared to support the option
Clear debris and improve understanding
& use of water management structures
1 1 1 2 1 6 Yes
Technically possible but management of the structures will depend on human
resources available to facilitate manual operation
Improve maintenance of sewer/culvert system along Hollington Old
Lane
1 -1 1 1 1 3 No
Viable from a technical point of view but likely to bring very limited benefits as there
is an issue with capacity of the system during significant storm events which would
be better addressed by exploring other options
Implementation of SUDS
2 -1 2 2 2 7 Yes Technically can be implemented and could bring about significant benefits to the area.
Increase capacity of river channel
2 -1 1 1 1 5 Yes
Feasible from a technical perspective but option limited to locations upstream of
water management structures due to river channel profile.
Additional storm water attenuation
1 -2 1 1 1 2 No
Likely to be financially unviable due to presence of other underground services and lack of space to accommodate it in
areas susceptible to surface water flooding
AECOM Study Report 37
Table 3.6: Application of Short-listing Criteria to Flood Hotspot 4
Option
Te
ch
nic
al
Ec
on
om
ic
So
cia
l
En
vir
on
men
tal
Ob
jec
tiv
es
Ov
era
ll S
co
re
Taken to detailed
analysis? Comments
Do Nothing 2 -1 -2 0 -2 -3 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Do Minimum 1 -1 -1 0 -1 -2 Yes Taken forward to option appraisal stage as
recommended by Defra Guidance
Flood resistance / resilience
2 1 1 1 2 7 Yes Technically feasible and financially viable
option that could provide significant improvements
Education 2 1 1 1 1 6 Yes Feasible and potentially inexpensive. The major problem will be public willingness to
implement advice
Improve SUDS 2 -1 1 1 1 4 No Technically can be implemented but would
bring very limited benefits to the area as suggested by revised flood mapping
Replace the combined sewer system
2 U 1 1 0 U No Although technically feasible the cost is not
viable.
Increase number of surface water outfalls
1 -2 1 1 1 2 No There could be implications on the
environment (water quality) but the main problem is the financial aspect
3.2 Assess Options
The purpose of this phase is to carry out the necessary assessment of the shot-listed options in order to define the preferred
options to be taken forward to the implementation and review stage. The Assess options Phase involved the following steps:
Identify assessment to be carried out
Undertake assessment of options
Agree preferred options
3.2.1 Identify assessment to be carried out
Following the short-listing process, the various options identified as suitable to be taken forward to the next stage were discussed
in principle by the working group with a view to identify the level of assessment required.
The nature of the options taken forward was such that the need for a detailed cost/benefit analysis was deemed unnecessary
and therefore the assessment of the options was based on engineering judgement, local knowledge and experience of all the
members of the working group. Furthermore, no significant investment warranting the application of such assessment methods is
envisaged by any of the partners in the near future following completion of the study.
3.2.2 Undertake assessment of Options
The assessment of Options was undertaken in close liaison with the working group to ensure all relevant local knowledge from
the partners was taken into consideration. The following tables summarise the process followed to assess the shortlisted options
and the conclusions reached.
AECOM Study Report 38
Table 3.7: Summary of Assessment of Shortlisted Options for Flood Hotspot 1
Option Further Assessment Undertaken Assessment Conclusions Option Recommendations
Do Nothing - Working group discussions - Likely to have significant financial and personal implications
for Hastings residents as flood risk will increase - Unacceptable
Do Minimum - Working group discussions - Will not bring any benefits to Hastings residents as flooding
will increase with time due to climate change
- Maintaining the current maintenance regime
is deemed inadequate taking into
consideration the problems identified in the
area as well as the likely increase of
flooding in the future due to climate change.
Flood resistance / resilience
- Working group discussions
- Flood Resistance/Resilience
Measures – Summary Table (see
Appendix 3A)
- Flood Resistance/Resilience
Measures for individual properties
(see Appendix 3A)
- This option would be beneficial to a significant number of
residential and commercial properties in this flood hotspot.
The only drawback is the limited funding available for
delivering solutions on the ground and therefore the
implementation of this type of measures would have to be
financed by the residents benefiting from them or through
EA/DEFRA grants for property level flood protection.
- Promote actively as part of an education
campaign.
- Deliver a sample solution on the ground, as
per the recommendations made for
individual properties.
- Seek funding through applications for
EA/DEFRA grants for property level flood
protection.
Education
- Working group discussions
- Flood Resistance/Resilience
Measures – Summary Table (see
Appendix 3A)
- Flood Advice Pack (see Appendix 3B)
- An education campaign is considered essential to reduce
the risk of surface water flooding across the Borough.
- Carry out a series of public events aimed at
educating local residents on flood risk and
engaging them to contribute to the
successful implementation of solutions on
the ground.
Modify ground profile
- Working group discussions
- Medium term solutions (see Appendix
3C)
- This option could help mitigate the impact of surface water
flooding to commercial properties around Priory Meadows
shopping centre; in particular those surrounding the square
(i.e. Old cricket ground). Flooding problems in the area are
unlikely to disappear, however, unless there is a significant
change to the ground profiles which could be compromised
by the large amount of underground services present.
- Engage the management company
responsible for the Priory Meadows area
with a view to seek the delivery on the
ground of the suggestions made for the
area. This could be a planning condition for
any further works proposed in the area.
AECOM Study Report 39
Table 3.8: Summary of Assessment of Shortlisted Options for Flood Hotspot 2
Option Further Assessment Undertaken Assessment Conclusions Option Recommendations
Do Nothing - Working group discussions - Likely to have significant financial and personal implications
for Hastings residents as flood risk will increase - Unacceptable
Do Minimum - Working group discussions - Will not bring any benefits to Hastings residents as flooding
will increase with time due to climate change
- Maintaining the current maintenance regime
is deemed inadequate taking into
consideration the problems identified in the
area as well as the likely increase of
flooding in the future due to climate change.
Flood resistance / resilience
- Working group discussions
- Flood Resistance/Resilience
Measures – Summary Table (see
Appendix 3A)
- Flood Resistance/Resilience
Measures for individual properties
(see Appendix 3A)
- This option would be beneficial to a various commercial and
potentially some residential properties in this flood hotspot.
The main drawback is the limited funding available for
delivering solutions on the ground and therefore the
implementation of this type of measures would have to be
financed by the residents benefiting from them or through
EA/DEFRA grants for property level flood protection.
- Promote actively as part of an education
campaign.
- Deliver a sample solution on the ground, as
per the recommendations made for
individual properties.
- Seek funding through applications for
EA/DEFRA grants for property level flood
protection.
Education
- Working group discussions
- Flood Resistance/Resilience
Measures – Summary Table (see
Appendix 3A)
- Flood Advice Pack (see Appendix 3B)
- An education campaign is considered essential to reduce
the risk of surface water flooding across the Borough.
- Carry out a series of public events aimed at
educating local residents on flood risk and
engaging them to contribute to the
successful implementation of solutions on
the ground.
AECOM Study Report 40
Table 3.9: Summary of Assessment of Shortlisted Options for Flood Hotspot 3
Option Further Assessment Undertaken Assessment Conclusions Option Recommendations
Do Nothing - Working group discussions - Likely to have significant financial and personal implications
for Hastings residents as flood risk will increase - Unacceptable
Do Minimum - Working group discussions - Will not bring any benefits to Hastings residents as flooding
will increase with time due to climate change
- Maintaining the current maintenance regime is
deemed inadequate taking into consideration the
problems identified in the area as well as the likely
increase of flooding in the future due to climate
change.
Flood resistance / resilience
- Working group discussions
- Flood Resistance/Resilience Measures –
Summary Table (see Appendix 3A)
- Flood Resistance/Resilience Measures for
individual properties (see Appendix 3A)
- This option would be beneficial to a limited number of
residential properties that have been severely affected by
surface water flooding in the past. The only drawback is the
limited funding available for delivering solutions on the ground
and therefore the implementation of this type of measures
would have to be financed by the residents benefiting from
them or through EA/DEFRA grants for property level flood
protection.
- Promote actively as part of an education campaign.
- Deliver a sample solution on the ground, as per the
recommendations made for individual properties.
- Seek funding through applications for EA/DEFRA
grants for property level flood protection.
Education
- Working group discussions
- Flood Resistance/Resilience Measures –
Summary Table (see Appendix 3A)
- Flood Advice Pack (see Appendix 3B)
- Upper Hollington Stream Maintenance
(see Appendix 3D)
- An education campaign is considered essential to reduce the
risk of surface water flooding across the Borough.
Furthermore, this flood hotspot would benefit from active
monitoring of the stream which could be done by local
residents provided the necessary training is made available.
- Carry out a series of public events aimed at
educating local residents on flood risk and engaging
them to contribute to the successful implementation
of solutions on the ground.
Install trash screen
- Working group discussions
- Upper Hollington Stream Maintenance
(see Appendix 3D)
- The installation of a trash screen at the culvert entrance at
Ashbrook Park, Upper Church Road could provide some
benefits if properly maintained.
- This option is generally deemed unacceptable by local
residents who are of the opinion that previous flooding
incidents have been exacerbated by trash screens being
blocked.
- Consideration could be given to containment of the stream
under surcharge conditions, but has not been taken forward
as an option due to the likely cost of containment required
immediately upstream.
- Engage local residents to seek their support and
reach an agreement on the type of trash screen that
could be implemented and its location with a view to
reduce the risk of blockages affecting this culvert.
AECOM Study Report 41
Table 3.9: Summary of Assessment of Shortlisted Options for Flood Hotspot 3 (continued)
Option Further Assessment Undertaken Assessment Conclusions Option Recommendations
Clear debris and improve
understanding & use of water management
structures
- Working group discussions
- Upper Hollington Stream Maintenance
(see Appendix 3D)
- Hydraulic Modelling of Upper Hollington
Stream (see Appendix 2C)
- An improved maintenance regime of the Upper Hollington
Stream would provide hydraulic and environmental benefits to
the stream and the surrounding area.
- The water management structures (dams) can store
significant volumes of water behind them and should be
operated in a way that maximises the benefits for the
properties downstream (see technical note – Appendix 3E).
- The culverts downstream of the dams present significant
constrictions to the flow as they are either surcharged or at
risk of surcharging during most return period events.
Therefore it is important to reduce as much as possible the
amount of flow reaching these culverts by capturing and
storing river flows using the dams. In addition, consideration
could be given to the introduction of sluices at culvert
entrances to reduce surcharge within the culverted sections,
but this has not been taken forward as an option
recommendation due to the likely cost of containment
required immediately upstream.
- Engage local residents to gain their support in the
effective monitoring and clearance of the stream
under the necessary amount of guidance and
supervision from the relevant authority.
- Inform the operations team responsible for the
dams the recommendations made with regards to
their operation following the hydraulic modelling
work undertaken.
- Improve maintenance of the penstocks and
undertake regular tests to ensure they are fully
operational and ready to come into action when
required (under storm conditions)
- Reinforce the message “less debris on the stream =
less flooding” between local residents as part of an
education campaign.
Implementation of SUDS
- Working group discussions
- SUDS Strategy for Hollington Primary
School (see Appendix 3E). This included
an overland flow model of the school and
its vicinity.
- Medium Term Solutions (see Appendix
3C)
- The implementation of SUDS techniques (retrofitting) at
Hollington Primary School would bring potentially significant
benefits not only for the school but also for the surrounding
area from a surface water flooding perspective.
- Three potential solutions have been recommended from a
technical perspective for pricing and potential implementation
depending on funding availability.
- The risk of surface water flooding in the area will not be
eliminated following the retrofitting of SUDS at the school site
due to the significant rainfall runoff generated in other parts of
the catchment.
- Implement at least one of the three recommended
options for retrofitting of SUDS at Hollington
Primary School as part of the SUDS retrofitting
programme of the EA and the Implementation
Stage of the SWMP.
- Promote and implement the remaining two
recommended options for the school at the earliest
possible opportunity.
- Seek future opportunities to retrofit SUDS at the
school site and/or the surrounding area.
AECOM Study Report 42
Table 3.9: Summary of Assessment of Shortlisted Options for Flood Hotspot 3 (continued)
Option Further Assessment Undertaken Assessment Conclusions Option Recommendations
Increase capacity of river
channel
- Working group discussions
- Upper Hollington Stream Maintenance
(see Appendix 3D)
- Hydraulic Modelling of Upper Hollington
Stream (see Appendix 2C)
- This could be done at the upstream end where residential
properties are not in close proximity to the watercourse.
However, due to the nature of the catchment (rapid response)
and the apparent lack of capacity of the culverts downstream
of the dams, there is little point in trying to get more flow
through the culverts. One possible alternative could be to
increase channel capacity immediately upstream of the dams
with the intention of storing more water behind them. This
scenario was modelled and found to have very limited benefit
for the residential area downstream as the culverts become
surcharged even under relatively low return period events. A
more effective and less expensive solution would be to
manage effectively the penstock systems of the dams to
constrict the flow at the upstream end of the catchment
without increasing the channel capacity (see Appendix 3E).
- DO NOT PURSUE. Concentrate on optimising the
use of existing dams/penstock rather than
increasing the capacity of the river channel.
AECOM Study Report 43
Table 3.10: Summary of Assessment of Shortlisted Options for Flood Hotspot 4
Option Further Assessment Undertaken Assessment Conclusions Option Recommendations
Do Nothing - Working group discussions - Likely to have significant financial and personal implications
for Hastings residents as flood risk will increase - Unacceptable
Do Minimum - Working group discussions - Will not bring any benefits to Hastings residents as flooding
will increase with time due to climate change
- Maintaining the current maintenance
regime is deemed inadequate taking
into consideration the problems
identified in the area as well as the
likely increase of flooding in the future
due to climate change.
Flood resistance / resilience
- Working group discussions
- Flood Resistance/Resilience Measures –
Summary Table (see Appendix3A)
- Flood Resistance/Resilience Measures for
individual properties (see Appendix 3A)
- This option would be beneficial to a various commercial and
potentially some residential properties in this flood hotspot.
The main drawback is the limited funding available for
delivering solutions on the ground and therefore the
implementation of this type of measures would have to be
financed by the residents benefiting from them or through
EA/DEFRA grants for property level flood protection.
- Promote actively as part of an
education campaign.
- Deliver a sample solution on the
ground, as per the recommendations
made for individual properties.
- Seek funding through applications for
EA/DEFRA grants for property level
flood protection.
Education
- Working group discussions
- Flood Resistance/Resilience Measures –
Summary Table (see Appendix 3A)
- Flood Advice Pack (see Appendix 3B)
- An education campaign is considered essential to reduce the
risk of surface water flooding across the Borough.
- Carry out a series of public events
aimed at educating local residents on
flood risk and engaging them to
contribute to the successful
implementation of solutions on the
ground.
AECOM Study Report 44
In addition to the assessment of shortlisted options for the top four flood hotspots, a series of Borough-wide studies/investigations
were undertaken with the aim of improving the management of surface water flood risk. These are summarised below:
Table 3.11: Summary of Borough-wide studies/investigations
Title Topics Covered Recommendations
Medium Term Solutions
(see Appendix C)
- Possible improvements to the
drainage arrangements at the Town
Centre
- Potential locations for retrofitting of
SUDS across the Borough.
- Engage the management company responsible for the
Priory Meadows area with a view to seek the delivery on
the ground of the suggestions made for the location.
- Seek future opportunities to retrofit SUDS across the
Borough as per but not limited to the suggestions made.
Asset Register (see Appendix 2D)
- Compilation of flood risk and
drainage management assets across
the Borough (main focus = surface
water flood risk)
- Identification of criticality of assets
from a surface water flood risk
perspective
- Gathering of details on maintenance
regimes for assets across the
Borough
- Ownership and responsibility for keeping the asset
register up to date needs to be established between HBC
and ESCC.
- A system needs to be put in place for communicating any
updates/changes to the asset register between all
partners
- Identify gaps in information and complete them at the
earliest possible opportunity
- Review maintenance regimes to ensure adequate
attention is given to the assets according to their criticality.
- Update the asset register regularly to ensure it remains fit
for purpose.
Flood Advice Pack (see Appendix 3B)
- General and Hastings specific
information/advice with regards to
flooding and what to do before,
during and after a flood event
- Distribute to residents as part of a Borough-wide
education campaign.
- Undertake regular reviews to ensure advice remains
current.
Procedure “to answer“ flood
incident reports (see Appendix 2G)
- Guidelines for call handlers as to
how to take reports of flooding from
members of the public.
- Contact details for key stakeholders
- Inform/train the team responsible for taking these calls to
ensure a consistent and suitable approach.
- Undertake regular reviews to ensure procedures remain
current.
Flood Response Plan (see Appendix 2G)
- Guidelines for call handlers as to
how to direct/action reports of
flooding from members of the public.
This form complements the
procedure “to answer” flood incident
report
- Inform/train the team responsible for taking these calls to
ensure a consistent and suitable approach.
- Undertake regular reviews to ensure procedures remain
current.
Flood Incident Report Form
(see Appendix 2G)
- Single form to capture details of the
flooding experienced at property
level. This form complements the
procedure “to answer” flood incident
report and the flood response plan.
- Inform/train the team responsible for carrying out post-
flood events interviews to ensure a consistent approach.
- Keep records of flooding incidents in a central location (to
be agreed between ESCC and HBC) to ensure important
reference data is not lost.
- Undertake regular reviews to ensure procedures remain
current.
AECOM Study Report 45
Table 3.11: Summary of Borough-wide studies/investigations (continued)
Title Topics Covered Recommendations
Critical Infrastructure likely to be affected by Surface Water
Flooding (see Appendix 2H)
- Critical infrastructure located within
or in close proximity to areas at risk
as identified by the FMfSW.
- Raise awareness between the various stakeholders
responsible for these assets of the risk to surface water
flooding and what could be done to mitigate it.
- Review relevant information when updates on areas at
risk of surface water flooding are issued.
Advisory Planning Note
- Guidelines for the spatial planning
team to ensure surface water flood
risk is considered when assessing
planning applications
- Inform/train the spatial planning team to ensure a
consistent and suitable approach when assessing
planning applications.
- Undertake regular reviews to ensure advice remains
current and fit for purpose.
3.2.3 Agree Preferred Options
Following the short listing and assessment of the various options formulated, a number of preferred options for implementation
were identified by the working group as summarised in Table 3.12.
The preferred options will be complemented by a number of actions aimed at improving the management of surface water flood
risk across the Borough as summarised in Table 3.13.
AECOM Study Report 46
Table 3.12: Summary of Preferred Options to be taken forward to Implementation Stage
Option Beneficiaries Possible Constraints Possible Solutions
Flood Resistance / Resilience
- All residential / commercial
properties that incorporate these
systems
- Lack of funding to implement these
techniques.
- Unwillingness of residents to incorporate
these systems due to aesthetic or operation
concerns.
- Bid for EA/DEFRA grants for property level flood
protection.
- Promote actively as part of an education campaign.
Education - Borough-wide benefits - Lack of interest
- Start with areas affected in the past where there is
likely to be interest and then try to make it
Borough–wide by engaging community groups and
schools.
Modify ground profile
- Flood Hotspot 1 (Town Centre) but
similar criteria could potentially be
applied elsewhere
- Lack of funding to implement recommended
improvements
- Unwillingness of management company to
get involved and contribute
- Bid for EA/DEFRA grants for property level flood
protection (where possible).
- Engage Management Company to ensure key
benefits are highlighted.
- Create a planning condition to be met by anyone
proposing future works in the area affected.
Install trash screen - Flood Hotspot 3 (Hollington Stream) - Unwillingness of residents to accept the
installation of this type of asset.
- Engage local residents to seek their support and
reach an agreement.
Clear debris and improve understanding
& use of water management
structures
- Flood Hotspot 3 (Hollington Stream)
- Insufficient human resources to monitor
regularly the watercourse and associated
structures.
- Mechanical problems with penstocks
- Insufficient notice ahead of a storm event to
allow calibration of penstocks as required
- Engage local community to get their support
- More strict/regular maintenance applied to these
key elements of the dams.
- Set the penstocks to the recommended opening to
maximise storage as default and only change it
when necessary.
Implementation of SUDS
- Hollington Primary School and
immediate vicinity (Blackman
Avenue, Hollington Old Lane)
- Lack of funding to retrofit SUDS - Contributions from EA SUDS Retrofitting Project,
HBC and any other partners able to do so.
AECOM Study Report 47
Table 3.13: Summary of Agreed Complementary Actions to Improve Surface Water Management across Hastings
Complementary Action
Beneficiaries Possible Constraints Possible Solutions
Seek Opportunities to Retrofit SUDS
- Areas where retrofitting is
implemented
- Lack of funding to implement these
techniques.
- Unwillingness of residents to incorporate
these systems.
- Bid for EA/DEFRA grants.
- Promote actively as part of an education campaign.
Maintain an up to date Borough – wide asset
register - Borough-wide benefits
- Gaps in information
- Asset register not kept up to date
- Each partner responsible for filling the gaps
associated with their assets.
- Partner in charge of keeping the asset register
current to outline system for regular information
updates to be circulated and incorporated to the
system.
Review maintenance regime for all assets in accordance with their
criticality
- Borough-wide benefits
- Insufficient information on maintenance of
assets
- Lack of human/financial resources to improve
maintenance regime of critical assets
- Partners to be responsible for identifying the
maintenance associated with their assets (if not
done already)
- Seek opportunities for community involvement in
monitoring/maintenance activities.
Device a suitable flood response and report
procedure - Borough-wide benefits
- Call handlers unfamiliar with procedure and
therefore unable to provide consistent advice
- Provide necessary training and background
information to call handlers to facilitate their work.
Seek Opportunities to reduce the risk of
surface water flooding affecting critical infrastructure
- Borough-wide benefits
- Lack of understanding of the risk from key
stakeholders owners of these critical assets.
- Lack of funding for the implementation of
suitable solutions.
- Engage asset owners to raise their awareness
- Seek the incorporation of flood protection schemes
to the capital programmes for asset management
of the relevant organisations.
Follow the Advisory Planning Note on
Surface Water Flood Risk
- Borough-wide benefits
- Spatial Planning team unfamiliar with SWMP
and therefore unable to provide consistent
advice
- Provide necessary training and background
information to spatial planning team to facilitate
their work
Explore opportunities to enmain the upper
part of Hollington Stream
- Residents in the Hollington Stream
Catchment
- Lack of human/financial resources to facilitate
this process
- Seek opportunities for community involvement in
monitoring/maintenance activities as this would
reduce costs and time required to deal with issues.
AECOM Study Report 48
This final stage of the study is about preparing an implementation strategy (i.e. an action plan), delivering the agreed actions and
monitoring implementation of these actions. This stage was undertaken in two phases:
- Prepare Action Plan
- Implement and Review Action Plan
4.1 Prepare Action Plan
The objective of this phase was to prioritise the options to be implemented and schedule the delivery of the various agreed
mitigation measures in coordination with the various partners and other stakeholders. This phase involved the following steps:
- Prepare Action Plan
- Review and publish the Action Plan
4.1.1 Prepare Action Plan
The action plan was prepared using the output of the Options Stage of the study and was informed by discussions with the
working group with regards to possibilities and constraints to fund the identified solutions in the short, medium and long term.
Tables 4.1 and 4.2 summarise the plan of action to deliver the options and associated complementary actions identified as part of
the Hastings SWMP. A number of terms introduced as part of these tables are summarised below:
Priority Ranking: The priority assigned to the option (O) /complementary action (CA) based on the likely benefits on the ground
(number of properties benefiting directly)
Option / Complementary Action: Provides a description of the option/complementary action.
Delivery Responsibility: The organisation(s) identified as directly responsible for organising/supporting the delivery of the option
or complementary action. A lead organisation was identified when more than one organisation were likely to contribute to the
implementation of the action. It is the lead organisation who is ultimately responsible for coordinating the support from others and
delivering on the ground.
Financial Responsibility: The organisation(s) identified as directly responsible for funding the delivery of the option or
complementary action. A lead organisation was identified when more than one organisation were likely to contribute to the
implementation of the action. It is the lead organisation who is ultimately responsible for coordinating the support from others and
delivering on the ground.
Comments: Describes the plan/opportunities for delivery of the option or complementary action.
Timeframe for Delivery: Provides a target date for delivery of the option or complementary action.
4 Implementation and Review Stage
AECOM Study Report 49
Table 4.1: Summary of Ranked Options for Implementation
Priority Ranking
Option Delivery
Responsibility Financial
Responsibility Comments Timeframe for Delivery
O1
Implementation of SUDS at Hollington Primary School
- EA SUDS
Retrofitting Project
Team (lead)
- HBC
- Hollington Primary
School
- ESCC
- EA SUDS
Retrofitting Project
Team (lead)
- HBC
- It is envisaged that at least one of the recommended SUDS options
will be incorporated in the short term as part of the SUDS
Retrofitting Pilot scheme from the EA
- The working group should seek opportunities to deliver the other
SUDS Options recommended for the area when funding becomes
available.
March 2012
(EA Retrofitting SUDS pilot
scheme)
Review Annually
(other SUDS options)
O2
Flood Resistance / Resilience Measures to be applied across the Borough
- HBC (lead)
- EA
- Residents benefiting
from these
measures
- HBC (lead)
- EA/DEFRA grants
- It is envisaged that some flood resistance / resilience measures at
property level would be installed at pilot locations across Hastings
as part of the delivery stage of the SWMP. However, this depends
on funding being available.
- HBC could apply for EA/DEFRA properly level flood protection
funding which, if successful, would enable the implementation of
these measures at key locations.
March 2012
(pilot locations)
March 2013
(other key locations)
O3
Clear debris and improve understanding & use of water management structures along the Upper Hollington Stream Catchment
- HBC (lead)
- ESCC
- EA
- Local Residents
- HBC (lead)
- EA
- ESCC
- Recent inspections suggest that the penstocks of the dams are not
fully functional and therefore some effort will be required to repair
them.
- Routine clearance operations should ideally be supported by the
local community wherever possible (Localism bill)
June 2011
(restore functionality of
penstocks
August 2011
(review maintenance
arrangements)
O4
Education on Flood Risk to residents across the Borough
- HBC (lead)
- EA
- ESCC
- HBC (lead)
- An education campaign involving workshops / presentations to
residents in the areas affected in the past and the general public
was identified as needed to pass on the messages from the study.
October 2011
(residents in areas affected)
November 2011
(general public)
O5
Modify the ground profile of the pedestrian area surrounding Priory Meadow shopping centre
- HBC (lead)
- ESCC
- EA
- Management
Company
- HBC (lead)
- Management
Company
- Modifications to the existing ground profile at this location could
bring about significant benefits to shops which are significantly
affected by flooding. However, the delivery of this option is
dependent on the support from the Management Company for the
area
Review
(following discussion with
Management Company)
O6
Install trash screen at the culvert entrance at Ashbrook Park, Upper Church Road
- HBC (lead)
- EA
- ESCC
- HBC (lead)
- EA
- ESCC
- The installation of a trash screen at this location could provide
benefits for the area. However, discussions with local residents will
be required to gain their support to this initiative.
- Estimate cost £1,500-2,500 for a trash screen to cover 1350mm
culvert entrance (supply only)
Review
(following discussion with
local residents)
AECOM Study Report 50
Table 4.2: Summary of Ranked Complementary Actions for Implementation
Priority Ranking
Complementary Action
Delivery Responsibility
Financial Responsibility
Comments Timeframe for Delivery
CA1
Seek opportunities to reduce the risk of surface water flooding affecting critical infrastructure
- HBC(lead)
- ESCC
- SW
- EA
- Stakeholders
affected
- Stakeholders
affected
- Protecting critical infrastructure will enable continuous operations
of key services thus minimising the chances of flooding occurring
as a result of infrastructure failure.
Review
(following discussion with
stakeholders affected)
CA2
Review maintenance regime for all assets in accordance with their criticality
- ESCC (lead)
- HBC
- EA
- SW*
- Other stakeholders
- All partners and
stakeholders with
responsibility for
maintaining flood
risk and drainage
assets
- A review of the maintenance programmes is essential in light of the
findings of the study and the criticality assigned to assets. This will
ensure the right level of attention is given to assets depending on
their perceived role on flood risk and drainage.
- * It must be noted that the water industry does not have a set
standard for determining the criticality of its assets in respect of surface water flooding.
October 2011
CA3 Seek opportunities to Retrofit SUDS
- HBC (lead)
- ESCC
- EA
- Other stakeholders
- Will vary depending
on nature of the
scheme and
beneficiaries
- Retrofitting SUDS in certain areas across the Borough could
reduce significantly the impact of surface water flood risk.
Therefore the incorporation of these techniques should be actively
encouraged.
Ongoing
CA4
Maintain an up to date Borough – wide asset register
- ESCC (lead)
- HBC
- SW
- EA
- Other stakeholders
- ESCC (lead)
- HBC
- An up to date asset register would facilitate the role of the lead
local flood authority and all partners by removing uncertainty with
regards to the presence, ownership, maintenance regime and
criticality of assets.
Ongoing
(periodical reviews to be
defined by ESCC)
CA5
Devise a suitable flood response and report procedure
- HBC (lead)
- ESCC
- EA
- SW
- HBC (lead)
- A standardised process that enables a consistent response and
reporting of flooding incidents would provide benefits to residents
whilst facilitating the compilation of suitable detailed information to
support future reviews of the SWMP, SFRA and other studies.
September 2011
(regular reviews required)
CA6
Follow the Advisory Planning Note on Surface Water Flood Risk
- HBC (lead) - HBC (lead)
- A consistent approach when assessing planning applications
across Hastings is essential and the Advisory Planning Note, if
followed correctly, should ensure this occurs.
Ongoing
(following publication of the
Hastings SWMP)
CA7
Explore opportunities to enmain the upper part of Hollington Stream
- EA (lead)
- HBC - EA (lead)
- Assigning this responsibility to the EA would streamline response
when issues are identified. This is particularly important given the
rapid response nature of the catchment and the likelihood of
property flooding during significant events.
Ongoing
AECOM Study Report 51
Table 4.3 was produced to facilitate the understanding of the actions to be undertaken in chronological order when delivering the
options and associated complementary actions identified above. A number of new terms introduced as part of this table are
summarised below:
Task: Numbered to represent the order in which they need to be undertaken (based on estimated completion date)
Completed by: Provides a estimated completion date
Associated with: Links the task with the option or complementary action listed on Tables 4.1 and 4.2
Description: Provides a description of the tasks to be undertaken by the completed by date
Follow up Actions: Describes the actions likely to follow the task as well as an indicative completion date for these actions
Table 4.3: Chronological order of activities required to progress options and complementary actions identified
Task Completed
by Associated
with Description Follow Up Actions
1 Ongoing CA3 Actively promote the retrofitting
of SUDS [HBC, EA, ESCC] - Changes/revisions to SUDS legislation to be
communicated to relevant parties (Ongoing)
2 April 2011 O3 Restore full functionality to
penstocks [EA]
- Raise awareness among operatives with regards
to suggested operation regime (July 2011)
- Seek support from local residents for keeping
clear the stream and its banks (October 2011)
3 June 2011 O1
Define SUDS Option(s) to be
retrofitted [EA SUDS
Retrofitting Project Team, HBC]
- Finalise detailed design of selected option(s) with
preferred contractor and attain any necessary
licences / permits. (September 2011)
- Liaise with Hollington Primary School and
preferred contractor to define timing of works
(October 2011)
- Progress with works (December 2011)
4 July 2011 CA4 Define ownership of the asset
register [HBC, ESCC] - Set up a review programme and communicate it to
relevant parties (Ongoing)
5 July 2011 O5
Discuss benefits and
opportunities for ground
reprofiling with Management
Company [HBC]
- Follow up on initial discussions and if necessary
set the delivery of this option as a planning
condition for any future development in the area.
(October 2011)
6 August 2011
CA7
Hold discussions with the
relevant department within the
EA with regards to enmaining
this section of the stream
- Follow it up depending on outcome on discussions
and continue to pursue it on a regular basis if
necessary
7 September
2011 CA5
Circulate documents to relevant
teams and explain processes
[HBC] - Roll out use of new procedures(October 2011)
8 September
2011 CA6
Circulate documents to
members of the Spatial
Planning team
- Roll out use of the Advisory Planning Note
following publication of the Hastings SWMP
(October 2011)
9 September
2011 CA1
Communicate risk to owners of
critical infrastructure [HBC,
ESCC]
- Discuss opportunities to mitigate the risk and seek
commitment from relevant stakeholders (October
2011)
AECOM Study Report 52
Table 4.3: Chronological order of activities required to progress options and complementary actions identified (continued)
Task Completed
by Associated
with Description Follow Up Actions
10 September
2011 O6
Discuss opportunities for
installation of trash screen with
local residents [EA, ESCC,
HBC]
- Follow up on discussions with residents and if
outcome is positive seek opportunities to finance
and deliver the trash screen (to be revised
following discussions)
11 September
2011 O4
Carry out event to present
results of the SWMP to the
residents of areas affected and
promote flood risk awareness /
education [HBC]
- Organise a subsequent event for the general
public (October 2011)
- Distribute flood pack to residents (October 2011)
12 October
2011 CA2
Review maintenance
arrangements for all assets
[HBC, ESCC, EA, SW]
- Implement changes to maintenance regimes as
identified during the review (Ongoing)
13 April 2012 O2 Apply for EA/Defra property
level flood protection [HBC] - If successful, progress as per guidance circulated
with application
4.1.1.1 Advice and information to local authority planners
One of the objectives of the Hastings SWMP was to provide valuable information to the spatial planning and development
process. This was achieved by involving a representative of the spatial planning team in the working group and producing the
following outputs that will inform their work:
Advisory Planning Note on Surface Water Flood Risk (see Appendix 2F)
Various Maps showing the areas deemed to be at risk of flooding from this source (see Mapping section)
Identification of areas where SUDS Retrofitting could provide some benefits (see Appendix 3C)
A workshop for HBC officers aimed at describing the study and how it could inform their work
4.1.1.2 Advice and information on emergency planning
Another objective of the Hastings SWMP was to provide valuable information to support emergency planning across the
Borough. This was achieved by involving a representative of the emergency planning team in the working group and producing
the following outputs that will inform their work:
Producing a revised procedure “to answer“ flood incident reports aimed at improving the management of flooding calls (see
Appendix 2G)
Various Maps showing the areas deemed to be at risk of flooding from this source (see Mapping section)
Identification of critical infrastructure deemed susceptible to surface water flood risk (see Appendix 2H)
A workshop for HBC officers aimed at describing the study and how it could inform their work
4.1.1.3 Programme of Further Work and Follow up Actions
Tables 4.1 to 4.3 above provide a summary of the work already identified as required to deliver the options / complementary
actions associated with the Hastings SWMP. It is however, recognised that further work will be required in the future to ensure
the actions identified are delivered and the objectives set out at the beginning of the project are fulfilled. Table 4.4 provides a
summary of the further work likely to be required from the working group post completion of the study.
AECOM Study Report 53
Table 4.4: Additional work identified post completion of Hastings SWMP Study
Description Responsibility Completed by
Establish whether the Hastings SWMP requires a Strategic Environmental
Assessment (SEA), an Appropriate Assessment (required by the Habitats
Directive), or an Article 4.7 Water Framework Directive (WFD) assessment
- HBC (lead)
- ESCC
- EA
July 2011
Seek to eliminate the gaps in the asset register - ESCC (lead)
- All working group March 2012
Organise regular meetings of the working group (or similar) post completion of the
SWMP Study to continue the partnership and seek solutions to the issues affecting
Hastings Borough
- ESCC (lead)
- All working group Ongoing
Identify opportunities to engage local residents in areas deemed at risk of surface
water flooding to provide support with routine maintenance (Localism bill) - EA (lead)
- All working group Ongoing
Seek opportunities to obtain funding through grants for the implementation of
solutions on the ground using the assessment carried out as part of the SWMP - HBC (lead)
- All working group Ongoing
Seek opportunities to eliminate the use of combined sewers where possible.
Whereas this is unlikely to be feasible in many areas across Hastings, any
reduction to surface water discharges into the sea will have a positive impact on
water quality.
- SW (lead)
Ongoing
Review effectiveness of solutions implemented as part of the Hastings SWMP - ESCC (lead)
- All working group Ongoing
Undertake regular reviews of the SWMP Study and supporting information; in
particular the surface water flood maps from the EA and update any maps/advice
when required.
- ESCC (lead)
- All working group
Annual
Reviews
(May 2012 for
first review)
4.1.2 Review and publish the Action Plan
The action plan identified above has been reviewed and approved for publication by a number of parties including:
- HBC Scrutiny committees
- HBC (lead partner)
- East Sussex County Council (lead local flood authority)
- Environment Agency
- Southern Water
4.2 Implement and Review Action Plan
The objective of this phase is to ensure that the signed off action plan is being delivered by the different partners or other
stakeholders. The main responsibility for this phase falls on the working group created to steer the production of the Hastings
SWMP and which includes representatives from all partners.
It is envisaged that the partnership formed to deliver the Hastings SWMP will continue to work together post completion of the
study to progress and implement the actions identified as well as undertake any further work required. Additionally, it is important
to note that the action plan should be reviewed and updated at least once every six years but there could be circumstances
under which an interim review might be required. These could include:
- A significant flooding incident
- Updated modelling/mapping information becoming available
- Changes to the investment plans for the partners which might have a direct impact on the implementation of options
- Additional Development or other changes in the catchment which might have an influence in surface water flood risk.
AECOM Study Report
As part of the Hastings SWMP a number of general conclusions and recommendations were reached in consultation with the
working group. These are summarised below and do not include those reached as a result of specific assessments carried out to
inform the study.
Conclusions
i. It is recognised by all partners that localised areas across Hastings are at risk of surface water flooding.
ii. The risk of flooding posed by surface water was found to be closely linked to other sources of flooding (rivers, sea, sewers,
groundwater) and to problems with the operation of flood risk and drainage management assets (blockages of gullies,
penstocks, etc).
iii. Despite showing fewer areas across Hastings as likely to be affected by surface water flooding, the FMfSW were found to be
more representative of reality than the AStSWF and therefore are deemed to be the primary source of surface water flood risk
information in the absence of locally agreed surface water information.
iv. Whereas the AStSWF maps and the FMfSW provide useful indication of the areas likely to be affected by surface water
flooding, there are some parts of the Borough that are known to suffer flooding from this source and have not been adequately
represented.
v. It is recognised by all partners that the level of detail and extent of the Hastings SWMP study was limited by financial, time and
information constraints. Furthermore, it is accepted that this study represents the initial stage of an ongoing process aimed at
reducing the risk of surface water flooding affecting Hastings.
vi. The Hastings SWMP identified a lack of consistency in the level of flooding history details provided by different partner
organisations. Whereas efforts were made to overcome this issue by working closely with the working group, some level of
inaccuracy could have remained, in particular when identifying the flood hotspots for assessment.
vii. Despite significant efforts to eliminate any gaps in information associated with the Borough-wide asset register created for
Hastings, there are a number of assets for which data has not been available.
viii. The nature of the potential mitigation measures identified and taken forward for assessment has been somewhat limited by
the financial constraints associated with the partners programmes.
Recommendations
i. It is recommended that the locally agreed surface water information is used to replace the FMfSW as the main reference for
this type of flooding in the area at the earliest possible opportunity. This should ensure that areas not included in the FMfSW
are recognised and added to the relevant mapping which will inform the spatial and emergency planning.
ii. It is recommended that all partners look to promote a “design for exceedence” culture aimed at ensuring that any flows in
excess of the nominal capacity of the different assets are managed in a controlled way and do not put life or properties at risk.
iii. It is recommended that the outputs of the study are circulated to the relevant team of the EA to inform and contribute to the
flood warning service in Hastings. This is particularly important but perhaps a bit complex in the Hollington Stream area due to
the rapid response nature of the catchment and the significant consequences of flooding in the vicinity of Hollington Stream.
iv. It is recommended that any feedback obtained from liaison with the public is taken into consideration by the working group and
appropriate action taken at the earliest possible opportunity with a view to resolving the issue raised.
v. It is recommended that an agreed common level of flood risk record is captured and stored by all partners in their systems as
this would facilitate any future studies across the Borough.
vi. It is recommended that any missing asset data is compiled at the earliest possible opportunity and added to the asset register.
vii. It is recommended that an update of the Hastings SFRA (completed in April 2008) is undertaken at the earliest possible
opportunity in order to incorporate the recent changes to the EA flood zone maps as well as the relevant information on flood
risk posed by surface water as identified by the SWMP.
viii. It is recommended that a review of the capacity of ponds/reservoirs across the Borough is undertaken with the aim of
identifying opportunities to maximise use of this assets to store additional flow when needed thus reducing the amount of flow
reaching the sewer network/watercourses, etc and reducing surface water flooding.
ix. It is recommended that the working group continue to work together following the completion of the SWMP
General Conclusions and Recommendations