Guidance on IFMS Implementation May 2007 ICGFM Miami Implementing an IFMS.
-
Upload
cassandra-horn -
Category
Documents
-
view
215 -
download
0
Transcript of Guidance on IFMS Implementation May 2007 ICGFM Miami Implementing an IFMS.
ICGFM – IFMS Implementation - 2 May 2007imcl
Setting the scene • You are the Secretary, Department of Finance in
Country X
• You have just signed a multi million dollar contract with a Supplier to implement the IFMS across the whole of Government
• You are happy!
• But now what do you do?
ICGFM – IFMS Implementation - 3 May 2007imcl
You start worrying!• Why?
– Because most IFMS projects to some extent fail
• And– Because you should already have made a series of
preparations
• But mainly– Because this is where the work really begins!
ICGFM – IFMS Implementation - 4 May 2007imcl
Major stages of an IFMS implementation
Build & test live systemBuild & test
model system
Detailconfiguration design
01/01/2008 31/12/2009
2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Train users
Migrate data & balances
Organisational changes at pilot sites
Set up hardware & networks
Go live at pilot sites
Phased rollout to other sites(several years)
Financial year
Contractor mobilises
ICGFM – IFMS Implementation - 5 May 2007imcl
Configuration design• Vendor has to configure their package to meet specification
– Configuration must be within system options– Hence carried through to system upgrades
• Budget classification/chart of accounts– Most critical and most difficult aspect of configuration– This establishes the accounting and reporting structure
• A task for accountants not IT specialists
– Each package has own constraints and terminology
• Workflow– Defined in most packages– Changes to package workflow may cause major problems– Balance against need to adhere to government procedures and practice– Ensure Financial Rules/Regulations are either complied with or amended
ICGFM – IFMS Implementation - 6 May 2007imcl
System architecture• Central database or• Distributed databases
Central database
Central general ledger
Ministry A
Ministry B
Ministry C
Ministries & other agencies enter data locally but all processed on single database
Distributed databases
Ministry A ledger
Ministry B ledger
Ministry C ledger
Central consolidation & management
Ministries & other agencies have own ledgers and databases but managed centrally
ICGFM – IFMS Implementation - 7 May 2007imcl
Hardware & network requirements• Development site
– For vendor to develop & test systems
• Training site• Production servers
– Depends on system architecture– Likely to be multiple servers for different functions– If distributed databases replication at each site
• Backup & disaster recovery arrangements– Balance of cost and risk
• Networks linking sites– Wide area and metropolitan area networks– Technology options
• E.g. fibre optic, wireless, satellite
• Networks at individual sites– Whose responsibility?
ICGFM – IFMS Implementation - 8 May 2007imcl
Testing• Testing
– Extensive testing of live data– Likely to be a series of modules which will developed and
tested separately, e.g.• Budget, commitment, general ledger, revenue, reporting, payroll, etc
• Requires– Test scripts– Development of output formats– Compliance with IPSAS
• Must be project structure for testing– User teams to carry out tests– Sign off required at series of stages
• Configuration design, pilot system tested, live system(s)
ICGFM – IFMS Implementation - 9 May 2007imcl
Organisational changes• Implementation IFMS typically requires organisational
change– Often ignored or underestimated
• Typical changes– Business rules enforced by system– New workflows– Electronic authorisation– Must be consistent management structures
• IFMS changes across government requires whole of government “ownership”– Other Ministries, Departments and Agencies must be involved
as early as possible– An exercise in change management
ICGFM – IFMS Implementation - 10 May 2007imcl
Training of users• Can only start when system configured• Training laboratory with copy of system• Training for:
– Users– Managers– Technical support
• Capacity for ongoing training– Needs of new/transferred staff– Training management structure– Training of trainers– Permanent training unit
ICGFM – IFMS Implementation - 11 May 2007imcl
Migration of data and balances• Simpler under cash accounting
– Only bank and cash balances - must be reconciled
• If moving to modified or full accrual– Loan balances, advances and prepayments - reconcile– Other assets & liabilities balances under full accrual
• Map budget to new coding structure– Budget will have been prepared under old codes
• Consider creating a Statement of Affairs– If no reliable brought forward balance
• Will previous years’ data be entered for comparison?
ICGFM – IFMS Implementation - 12 May 2007imcl
Merits of different architectures• Central databases typical of IFMS
– Ensures common coding and standards– Easier to manage– Data automatically consolidated for analysis
• But– Bigger = more complex– Expensive software & hardware– Critically depends on network linking sites– Difficult to cater for sector specific requirements in a
centralised system• e.g. public works, health care, education each have unique information
requirements
ICGFM – IFMS Implementation - 13 May 2007imcl
Go live• Critical stage when system “goes live” - beginning of
operational use of system• Go live likely to be phased, e.g.
1. By module
2. By phasing
• Ideally go live at start of financial year– Whole years transactions processed on one system– Same coding structure for whole year– No need to transfer balances part way through year
ICGFM – IFMS Implementation - 14 May 2007imcl
Need to plan for overlapping operation of IFMS and legacy systems
• Inevitable situation:– IFMS at some sites– Old (legacy) systems at other sites
• Legacy systems may be manual or computer based
• Legacy systems must be operated and maintained for several years:– As IFMS is rolled out– To provide access to historic data
• Problems with maintaining legacy systems:– May use old technology– May use different chart of accounts– How to consolidate data for reporting
ICGFM – IFMS Implementation - 15 May 2007imcl
IFMS rollout• IFMS will be progressively rolled out across government• Horizontal or vertical slicing?
Ministry A
Dep’t 1 Dep’t 2
Project Agency
Ministry B
Dep’t 1 Dep’t 2
Project Agency
Horizontal slicing
Phase 1: all Ministries
Phase 2: Departments
Phase 3: Projects & agencies
Vertical slicing
Phase 1: whole of Ministry A
Phase 2: whole of Ministry A
ICGFM – IFMS Implementation - 16 May 2007imcl
Rollout Plan – for each group of sites
2. Organisational Change
3. Hardware networksAt each site & network
4. Training
5. Data migrationReconcile balances
6. Go live
7. SupportOngoing support and
help desk
1. PlanChangeover plan
Identify Sites
Repeat process for every group, e.g. Ministries, and for each
phase
ICGFM – IFMS Implementation - 17 May 2007imcl
Other issues• Security
– Who owns the information and controls security?• Should be users, e.g. Ministry of Finance, not IT Department
– Access rights• Levels of access and controls
– Physical security– Backup and disaster recovery
• Records management– Will records on legacy system remain accessible?– Retention and control over records
• Electronic and paper
ICGFM – IFMS Implementation - 18 May 2007imcl
Project Management• IFMS implementation is a major project
– Needs structured project management– Preferably use a standard project management methodology
• E.g. PRINCE (Projects IN a Controlled Environment) developed for UK government
• IFMS implementation managed by government not supplier– Major contract management exercise– Project management may be sub-contracted
ICGFM – IFMS Implementation - 19 May 2007imcl
The PRINCE II Project Components
Organisation
Planning
Controls
StagesRisk
management
Quality management
Configuration management
Change control
Directing a projectStart up
Initi-ating
Start/end
stages
Stage control
Managing products
Project closing
ICGFM – IFMS Implementation - 20 May 2007imcl
Project organisation
Project BoardSenior user
Executive Supplier
Project Manager
Team 1
Team Leader
Team members
Team 2
Team Leader
Team members
Project assurance
Project support
ICGFM – IFMS Implementation - 21 May 2007imcl
Balance between supplier & government roles
· Increased cost may become prohibitive
· If risk too high no firms may be willing to accept contract
· Gov’t minimises risk· Overcomes lack of
Gov’t capacity· More rapid
implementation
Increased role and risk borne
by Government
Increased role and risk borne by IFMS supplier
ICGFM – IFMS Implementation - 22 May 2007imcl
Matrix of rolesRole Gov’t Supplier Comment
1. Project management May be sub-contracted
2. Legal and regulatory framework
3. Software delivery & configuration
4. Hardware and networks May be separate contracts or combined with software - turnkey
5. Initial user training Should be training of trainers
6. Ongoing training Could be continued by supplier or outsourced
7. Preparing data for migration to IFMS
8. Organisational changes and change management
9. Ongoing system operation Could be operated by supplier or other contractor – out-sourcing
10. Ongoing support Could be outsourced
ICGFM – IFMS Implementation - 23 May 2007imcl
Ongoing sustainability of IFMS• Many IFMS are proving:
– Difficult to sustain and/or– Only cover part of government
• Major problems– Cost
• Ongoing operational costs• Maintenance costs• Software licenses
– Organisational• Inadequate technical support structure• Inadequate training resources• Shortage/turnover of skilled staff
– System design• System design inadequacies become increasingly apparent over time
ICGFM – IFMS Implementation - 24 May 2007imcl
Realising the benefits of an IFMS• Better fiscal management
– Only if information is utilised
• More optimal resource allocation– Only if budget system is linked to strategic objectives
• Improved management of resources (value for money)– Only if managers utilise financial information
• Reduced fraud and corruption– If system is designed and used to improve controls
• Improved transparency and accountability– If system information is published in a useful format, e.g.
• IPSAS compliant financial statements on Government we site
ICGFM – IFMS Implementation - 25 May 2007imcl
Conclusions• An IFMS can lead to real benefits• Implementation is challenging
– Must be recognised as a major project impacting across government
– Requires substantial resources– Do not underestimate time
• Sustainability issues must be addressed from the start• IFMS benefits are not automatic
– Must be a strategy to realise the benefits