Water presentation port of corpus christi
Transcript of Water presentation port of corpus christi
City of Corpus Christi Water Resource Management
April 8, 2014
Overview
• Corpus Christi Regional Water System Overview
• Water Management Strategies• Future Water Supply-Demand
2
Current Water Supply System
• Corpus Christi provides water to 18 cities and communities in the Coastal Bend
• Customers include nearly 500,000 residents, as well as diverse businesses and industries
• In FY, 2013 annual consumption of region was 39,907,000,000 gallons (122,469 acre-feet)
3
4
Corpus Christi Regional Water Supply System
Corpus Christi
Choke Canyon Reservoir
Lake Texana
Lake Corpus Christi
San Antonio
Capacity of ReservoirsIn Nueces Basin: 952,531 ac-ftLake Texana: 161,085 ac-ft
How much can we use?In Nueces Basin (consumptive rights): 443,898 ac-ft / yearLake Texana (contract): 41,840 ac-ft / year
5
Safe Yield 206,000 Ac-ftAverage Annual Demand 120,000 Ac-ftSurplus 86,000 Ac-ftGarwood rights Add- 35,000 Ac-ft
6
Water Supplies in the System
Communities Relying
On Regional Surface
Water System
ALICE
BEEVILLETHREERIVER
S
PORTLAND
KINGSVILLE
PORTARANSAS
FULTONROCKPORT
INGLESIDE
CORPUSCHRISTI
ARANSASPASS
BISHOP
DRISCOLL
ROBSTOWN
MATHIS
Regional Water Planning
• Regional water planning process mandated by state in 1997
• 16 regions• Coastal Bend is Region
“N”• Has 11 Counties
• Involves multiple stakeholders
9
Recommended Water Management Strategies (WMS) in the 2011 Region N
Plan• Mary Rhodes Ph II -Construction to start
April 2014• Water Conservation• Reclaimed Wastewater Supplies• Variable Salinity Desalinization
10
Potential Industrial Demands
12
County Industry Maximum Usage (ac-ft/year)
First Year of Delivery
San Patricio Tianjin Pipe 2,200 2014
San Patricio Cheniere Gas 3,900 2017
San Patricio Hot Iron Steel 3,900 2016
San Patricio Occidental Fractionator 1,100 2015
San Patricio Occidental Ethylene 3,900 2016
San Patricio Ingleside X 6,700 2017
San Patricio Ingleside Y 2,200 2016
San Patricio Occidental Port 1,700 2016
Nueces LyondellBasell – Project X 900 2014
Nueces LyondellBasell – Plant Expansion 2,200 2016
Nueces M&G Industries – PET Plant 8,200
Total 36,900
13
Project Goals and Objectives• Feasibility and cost estimate for desalination in
region• Testing of emerging technologies • Determine basis for design of full scale facility• Be prepared to start full scale facility
Variable Salinity Desalination Project
Overview of Variable Salinity Demonstration
Project•Goals of Project:•Develop a drought resistant “alternative” water supply capable of providing continuous source water to the City’s water supply and distribution system
•Determine the basis for design of a full-scale facility, operating parameters, costing information and product water quality to assess the feasibility of a seawater and/or brackish groundwater supply, including ASR
14
Benefits of Desalination/Pilot Project
• Initiate pilot study to continue desalination initiative,
including:• Determine the “Design Criteria” by which we could
go to a full scale plant if this drought continues.• Determine the rate impact of a full scale plant• Take advantage of any state or federal grants and
loans• Seawater sources would be closer than existing
remote water supplies• Reliability of water supply• Economic development opportunities• Pilot studies would provide a focal point for public
attention and education
Overview of Pilot Project
• Project phases• Phase 1 Conceptual Plan
Define potential areas for pilot facilities, considering environmental and technical constraints
• Phase 2 Site Selection/Scoping of Pilot StudyDriven by environmental, land use, technical and financial considerations, all of which will have an impact on the scope and budget of the eventual Phase 3 Project
• Phase 3 Demonstration ProjectAt selected site, water production tests to be conducted in accordance with TCEQ membrane protocol
Next Steps
• Finalize grant award and details• Application for Emerging Technology funds
from state completed
• Seek City Council Approval April 2014 for Phase 2 Site Selection/Scoping of Pilot • Final Phase 3 –Demonstration Pilot to
produce an industrial water • Anticipated time to complete is November
2017
17
Desalination - Program Schedule
18
Current Contract Estimate: 180 Calendar Days 6 Months
Projected Schedule reflects City Council award in May 2014 with anticipated completion in October 2014.
2014 2015
Q1 Q3 Q4
Next Steps
Equipment Acquisition and Installation
Operating Desalination Demonstration Plant, Technology Testing, and Data Collection
2016
Q4Q3Q2 Q1 Q2 Q3 Q4 Q1 Q2
TM #1
TM #2
TMs #3 & #4
Current Contract Amendment No.1
2014Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Plant Siting and VSD Protocol Development
19
• Completed work: $101,932• Site selection and pilot protocol (item going
to City Council on April 22): $1,032,085• Pilot installation and testing: $1,772,700• Funding to come from USBR grant and
water supply development fund
Program Budget
Variable Salinity Desalination Project
20
QUESTIONS?
Variable Salinity Demonstration Phase 2 Funding
• US Bureau of Reclamation• $400,000
•City of Corpus Christi
• $ 1.2M
•Total Study Cost $1.6 Million plus in-kind services
•Securing additional funding through state
21
Residential - Single Family
31%
Residential - Multi-family
7%Industrial40%
Commercial15%
Institutional5%
Wholesale9%
Customer Demand by Class