UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview:...

35
AFRICAN DEVELOPMENT FUND UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION PROJECT (STWSSP) RDGE/AHWS DEPARTMENTS May 2018 Public Disclosure Authorized Public Disclosure Authorized

Transcript of UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview:...

Page 1: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

AFRICAN DEVELOPMENT FUND

UGANDA

STRATEGIC TOWNS WATER SUPPLY AND SANITATION PROJECT

(STWSSP)

RDGE/AHWS DEPARTMENTS

May 2018

Publi

c D

iscl

osu

re A

uth

ori

zed

P

ubli

c D

iscl

osu

re A

uth

ori

zed

Page 2: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

TABLE OF CONTENTS PROJECT SUMMARY ............................................................................................................ iv Result-Based Logical Framework............................................................................................. vi

I: STRATEGIC THRUST AND RATIONALE ........................................................................ 1 1.1 Project Linkages with Country Strategy and Objectives ............................................ 1 1.2 Rationale for Bank’s Involvement .............................................................................. 2 1.3 Donors Coordination ................................................................................................... 3

II: PROJECT DESCRIPTION ................................................................................................... 4

2.1 Project Components .................................................................................................... 4 2.2 Technical Solution Retained and other Alternatives Explored ................................... 4 2.3 Project Type ................................................................................................................ 5 2.4 Project Cost and Financing Arrangements .................................................................. 5 2.5 Project’s Target Area and Population ......................................................................... 7

2.6 Participatory Process for Project Identification, Design and Implementation ............ 7 2.7 Bank Group Experiences, Lessons Learnt and Reflected in Project Design .............. 7

2.8 Key Performance indicators ........................................................................................ 8 3.1 Economic and Financial Performance......................................................................... 9 3.2 Environmental and Social Impacts ............................................................................ 10 3.2.1 Environment .............................................................................................................. 10

3.2.2 Climate Change 10

3.2.3 Involuntary Resettlement .......................................................................................... 10

3.2.4 Gender ........................................................................................................................ 11 3.2.5 Social ......................................................................................................................... 11

IV: IMPLEMENTATION ....................................................................................................... 12

4.1 Implementation Arrangements .................................................................................. 12 4.1.2 Procurement Arrangements ....................................................................................... 12

4.1.3 Financial Reporting and Audit .................................................................................. 13 4.2 Monitoring ................................................................................................................. 14

4.3 Governance................................................................................................................ 14 4.4 Sustainability ............................................................................................................. 15 4.5 Risk Management ...................................................................................................... 17

4.6 Knowledge Building ................................................................................................. 17

V: LEGAL INSTRUMENTS AND AUTHORITY ................................................................ 18 5.1 Legal Instrument ....................................................................................................... 18 5.2 Conditions Associated with Bank’s Intervention ...................................................... 18 5.3 Compliance with Bank Policies ................................................................................ 18

VI: RECOMMENDATION ..................................................................................................... 18

Appendix I: Comparative Socio-economic Indicators Appendix II: Bank Group Portfolio in Uganda Appendix III: Selected Projects Financed by the Bank and other Development Partners in the

Country

Appendix IV: Government Endorsement Letter for Climate Fund Cofinancing Appendix V: Map of Project Areas

Page 3: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

i

CURRENCY EQUIVALENTS

(As of January 2018)

Currency Unit = Uganda Shillings (UGX)

UA 1 = USD 1.42

UA 1 = EUR 1.19

UA 1 = UGX 5,12452

EUR 1 = USD 1.20 EUR 1 = UGX 4,315.49

USD 1 = UGX 3,598.35

FISCAL YEAR

1st July - 30th June

WEIGHTS AND MEASURES

1 metric tonne = 2204 pounds (lbs).

1 kilogram (kg) = 2.200 lbs.

1 meter (m) = 3.28 feet (ft)

1 millimeter (mm) = 0.3937 inch (“)

1 kilometre (km) = 0.62 mile

1 square kilometre (km2) = 0.386 square mile

1 hectare (ha) = 0.01 km2 = 2.471 acres

Page 4: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

ii

ACRONYMS AND ABBREVIATIONS

AfDB African Development Bank

ADF African Development Fund

CSP Country Strategy Paper

CSI Core Sector Indicator

DPs Development Partners

EA Executing Agency

ESMF Environmental and Social Management Framework

ESMP Environmental and Social Management Plan

FM Financial Management

GoU Government of Uganda

JPF Joint Partnership Fund

JSR Joint Sector Review

JWESSP Joint Water and Environment Sector Support Programme

M&E Monitoring & Evaluation

MWE Ministry of Water and Environment

NWP National Water Policy

O&M Operation & Maintenance

PIT Project Implementation Team

PCR Project Completion Report RBLF Result Based Logical Framework

SDG Sustainable Development Goals

SPS Sector Programme Support

STWSS Strategic Towns Water Supply and Sanitation

SWAp Sector Wide Approach to Planning

UA Unit of Account USD United States Dollars

WSSDPG Water and Sanitation Development Partner Group

WSDF Water and Sanitation Development Facility

WSSWG Water and Sanitation Sub-sector Working Group

Page 5: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

iii

Loan Information

Client’s Information

BORROWER: Republic of Uganda

EXECUTING AGENCY: Ministry of Water and Environment

Financing Plan

Source Amount Instrument

ADF UA 44 million Loan

Government of Uganda UA 4.9million

TOTAL PROJECT

COST

UA 48.9million

ADB’s Key Financing Information

Loan

UA

Interest type* N/A

Interest rate spread* N/A

Service Charge 0.75% per annum

Commitment Fee 0.50% per annum

Tenor 40 years

Grace period 10 years

FIRR , FNPV(base case) (15.52%) UGX 42.29 bn

EIRR , ENPV(base case) (43.49%) UGX 359.83 bn

Timeframe - Main Milestones (expected)

Project Identification July 2017

Preparation Mission Sept 2017

Concept Note Approval Oct 2017

Appraisal Mission Nov 2017

PAR CT Meeting Jan 2018

Project Approval June 2018

Effectiveness Sept 2018

First Disbursement Dec 2018

Closing Date June 2024

Last Repayment Dec 2058

Page 6: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

iv

PROJECT SUMMARY

Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project

(STWSSP) is to support the Government of Uganda’s efforts to achieve sustainable provision

of safe water and hygienic sanitation for the urban population by the year 2030. This in turn

will contribute to improved health and productivity of the population in the targeted towns

across the country. The project is estimated to cost UA 48.89 million, of which UA 44 million

will be funded by an African Development Fund (ADF) loan and UA 4.9 million counterpart

contribution from the Government of Uganda. The project will be implemented over a 5 year

period from September 2018 to June 2024. The project has set aside UA 1.27 million under

which bankable climate change resilient investment projects will be prepared to leverage

approximately USD 83 million financing from the Green Climate Fund identified under the

Uganda Strategic Program for Climate Change Resilience. The Government has also endorsed

USD 2.2 million from the Climate Fund as cofinancing for strengthening climate change

adaptation of the towns.

Project Beneficiaries and Impact: The project is expected to improve the quality of service

and the supply of water and sanitation facilities to towns, including women and children who

bear most of the cost of water scarcity. It will also improve management and functioning of

water supply and sanitation systems. This will be achieved by investing in water supply and

sanitation infrastructure in ten district headquarter towns across the country. At completion,

the project is expected to benefit directly 390,000 people with improved piped water access. A

total of 150 people (of which 20% will be women) will receive training in appropriate urban

sanitation (masonry/mechanic artisans/waste management) while 30 communities will benefit

from sanitation and hygiene promotion, targeting at least 50% women participation. The

project will also support 200 youths and women in skills development for economic

empowerment. About 4,000 temporary jobs and 1,000 permanent jobs will be created from

project activities through stimulation of commercial activities in the services sectors such as

hotels, health and education, and in agro-based industries. The project beneficiaries were

consulted during the design of the project and will be involved during implementation to

enhance social accountability and partnership.

Needs Assessment: Economic growth and urbanization are placing increasing pressure on

Uganda’s water resources and sanitation facilities. Urban services are not keeping pace with

urban population growth, with demand for services far outstripping supply in most urban areas

because of inadequate financing for capital investments and insufficient capacity for planning,

operating, and maintaining urban infrastructure and services. The lack of sanitation facilities

have led to discharge of untreated effluents creating a health hazard for the residents especially

in the main urban centres. Adequate water supply and sanitation infrastructure, remains a

challenge as the country aspires for long term sustainable socio-economic development. The

proposed project will contribute to the goals of the Government’s Vision 2040 and the Second

National Development Plan (NDP II). The Government aims to increase access to clean water

and sanitation services in the major urban centres and their suburbs, expanding access to the

poor in underserved areas and strengthening sector institutions. Access to improved water

supply is currently recorded at 71% for urban areas, while access to sanitation is at 84%, which

falls short of the national goals as outlined in Uganda Vision 2040 (which aims to reach 100%

by 2030). The Government’s new focus for urban sanitation is through improved faecal sludge

management at regional level to ensure safe disposal, and calls for construction of regional

faecal sludge plants. Support from development partners will be required to construct large

core infrastructure for intakes, transmission lines and the treatment plants with capacity to

supply water to additional cluster towns beyond the project towns. Investments in water

infrastructure will act as a catalyst for local development and economic activity by providing

water for agriculture, animal husbandry, food processing, and other businesses. It will bring

higher quantities and more reliable water to households thereby enhancing the quality of their

life by reducing the time and effort to collect water, reducing the incidents of waterborne

Page 7: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

v

diseases, and reducing absence from work and school and the associated costs, including lost

income and opportunities.

Bank Value Addition: The Bank brings a wealth of knowledge and technical experience

directly relevant to the Ugandan urban water supply and situation. The Bank has implemented

a number of urban water projects like the Small Towns Water and Sanitation Project, Kampala

Sanitation Project, Kampala Urban Poor Project, Lake Victoria Water Supply and Sanitation

Program, and Water Supply and Sanitation Program phase I and II. The Project is aligned to

Pillar 1 of the Bank’s Country Strategy Paper (CSP) for Uganda, covering the period 2017-

2021. It will contribute to accelerating implementation of the Bank’s Ten Year Strategy and

contribute to achieving the Banks High 5 priority to ‘improve the quality of life for the people

of Africa’ through eliminating extreme poverty and promoting shared prosperity.

Knowledge Management: Lessons from implementing the project will continuously be

captured and documented throughout the project implementation period as part of knowledge

generation and sector monitoring framework. The lessons will be reflected in the quarterly

progress reports and annual sector performance reports. The lessons will ensure improvement

in project implementation and water management and will also inform design and

implementation of future projects. The Ministry of Water & Environment (MWE) will also

ensure that the urban data base captures access and related information on all new and

rehabilitated facilities under the project to facilitate assessment of progress and input in the

Banks Implementation Performance Result (IPR) report and the next Water Atlas.

Page 8: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

vi

Result-Based Logical Framework

Country and Project Name: Uganda - Strategic Towns Water Supply and Sanitation Project (STWSSP)

Purpose of the Project: To support the Government of Uganda’s efforts to achieve sustainable provision of safe water and hygienic sanitation for the urban population with improved

resilience to climate change effects by the year 2030. RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/ MITIGATION MEASURES

Indicators

Baseline

(2017)

Target

(2023)

IMP

AC

T

1. Contribute to improved health

and productivity of the population

through use of safe water and

sanitation services.

1.1 Percentage of incidence of diarrhea

morbidity among children under five.

1.2 Percentage of pupils completing

primary level of education (with a

gender parity index of 1.0).

3.5%

61.6%

2.5%

72%

Health sector

performance

Report;

Education and

Sports sector

performance

report;

UBOS Report

(UNHHS)

Risk: Delays in setting up effective and efficient

regulatory policies and strategies may affect

service delivery.

Mitigation: The Utility Regulation Department

will be strengthened to achieve its mandate

including tariff setting and compliance

monitoring of utilities that will manage the

completed water supply schemes.

Risk: Exchange rate volatility and cost overruns

may affect funds availability, and timely

completion especially where there are delays in

implementation of projects and in

disbursements.

Mitigation: The Bank and GoU will promptly

track all payments requests to ensure timely

disbursement of funds. Adequate price

contingence shall be provided for to guard

against the exchange rate volatility and MWE

shall be supported with contract management.

Risk: Access to any additional land and required

environmental approvals may delay timely

completion of the sub-projects.

Mitigation: The EA will commence additional

land identification and acquisition before project

effectiveness and ensure timely approval of the

Environmental and Social Monitoring Plan.

Risk: Delay in project effectiveness due to

delays in Parliamentary approval.

Mitigation: The EA is already engaging with

the parliamentary committee and the Ministry

Ou

tco

mes

2. Improved access and quality of

service to a sustainable safe water

supply and sanitation facilities.

2.1 Percentage of urban population

with access to safe drinking water

(CSI).

2.2 Number of urban people served

with improved access to safe water

within 200m.

2.3 Percentage of urban people with

access to improved sanitation (CSI).

71%

0

84%

90%

390,000

95%

Annual Sector

Performance

Report

Signed minutes of

Joint Sector

Review

Quarterly progress

reports

JPF quarterly

progress report

Quarterly and

annual component

progress

reporting;

Water atlas

3. Improved management and

functionality of water supply.

3.1 Functionality rate of urban water

supplies systems (%).

94%

96%

Ou

tpu

ts

Component 1: Urban Water Supply

1.1 Urban water supply schemes

constructed.

1.1.1 No. of town water supply

schemes constructed/rehabilitated.

1.1.2 Detailed engineering designs

done.

1.1.3 Total water production capacity

(m3/day).

1.1.4 Total kms of pipelines

constructed (transmission &

distribution).

0

0

0

0

10

10

37,500

1,300

1.2 Support for O&M 1.2.1 No. of regional umbrella of water

and sanitation authorities supported for

effective utility management.

0 6

Page 9: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

vii

Component 2: Improved Urban Sanitation and Environmental

Management

of Finance, Planning and Economic

Development to expedite the approval process

2.1 Sanitation Facilities

constructed.

2.1.1 No. of regional faecal sludge

treatment facilities constructed.

2.1.2 No. of cesspool emptiers

procured.

2.1.3 No. of gender-segregated and

disabled-friendly public sanitation

facilities constructed including in

schools/ institutions.

0

0

0

3

6

40

2.2 Improved sanitation services

and hygiene promotion.

2.2.1 No. of people trained in

appropriate urban sanitation

(masonry/mechanic artisans/waste

management), targeting at least 20%

women.

2.2.2 No. of community trainings on

sanitation and hygiene promotion

conducted (targeting at least 50 %

women participation).

0

0

150

30

2.3 Environmental management

and climate change resilience.

2.3.1 No. of water sources with

protected catchments (including

ESMP).

2.3.2 No. of project feasibility designs

for Uganda strategic program for

climate change resilience.

0

0

8

10

Component 3: Sector Program Support

3.1 Support establishment of water

services regulatory framework.

3.1.1 Water and sanitation services

tariff regime reviewed and tariff policy

updated.

3.1.2 Water and sanitation services

regulation tools developed (technical

and commercial).

0

0

1

1

3.2 Skills development for women

and youth for economic

empowerment.

3.2.1 No. of women and youth trained

in water and sanitation services as a

business.

0

200

3.3 Strengthening sector co-

ordination.

3.3.1 Strategy and framework for

implementation of bulk water supply

developed.

3.3.2 Uganda water and sanitation

atlas updated.

3.3.3 Water and environment sector

0

0

0

1

1

1

Page 10: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

viii

co-ordination and monitoring systems

strengthened.

Activities: Component 1: Urban Water Supply Construction of urban water supply systems covering 10 strategic towns; Engineering Services (Design and construction

supervision); detailed engineering designs, production capacity; transmission & distribution lines and reservoirs; Equipment for the wider O&M and extension through Umbrella utilities.

Component 2: Improved Urban Sanitation and Environmental Management Construction of 3 regional feacal sludge treatment facilities; procurement of 6 cesspool trucks, 40 gender-segregated &

disabled-friendly public sanitation facilities constructed including in schools/ institutions, implementation of environmental management and climate change resilience measures within urban water and sanitation sub-sector.

Component 3: Sector Programme Support Support the regulatory framework through developing of regulation tools and tariff regime reviews; skill development for

women and youth, framework for bulk water; water and sanitation Atlas and sector coordination and M&E.

Input Component 1: UA 41.62m Component 2: UA 4.89m Component 3: UA 2.38m Total ADF: UA 44m Total incl. GoU: UA 48.89m

Page 11: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

ix

Project Time Frame

Project 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6

Loan Negotiations

Loan Approval

Sign Loan Protocol Agreements

Launching Mission

Community planning, mobilsation, hygine

promotion & baseline studies

Design/design review of WATSAN infrastructure

Construction of town water supply systems

Construction of regional faecal sludge management

facilities

Procurement of desludging, O&M and IT

equipment

Climate change resilience measures and feasibility

studies for climate change resilience under SPR

Development of water services regulatory tools

Review of water servives and sanitation tariff

policy

Skills development fo women and youth for

ecomonic empowerment

Development of bulkwater transfer strategy

Updated of the Uganda water and sanitation atlas

First Disbursement

Second Disbursement

Third Disbursement

Fourth Disbursement

Fifth Disbursement

Program mgt, M&E

Supervision Mission

Mid Term Review

JSR and JTR (Joint Sector/Technical Reviews)

Project Completion Report

Q1 2024 Q2 2024

UGANDA - STRATEGIC TOWNS WATER SUPPLY AND SANITATION PROJECT 2018/19 TO 2023/24

PROGRAM IMPLEMENTATION SCHEDULEQ4 2022Q3 2022Q4 2021Q3 2021 Q2 2022Q1 2022Q4 2019Q3 2019 Q2 2020Q1 2020 Q4 2020Q2 2018 Q4 2018Q3 2018 Q2 2019Q1 2019 Q1 2023 Q2 2023 Q3 2023 Q4 2023Q3 2020 Q2 2021Q1 2021

Page 12: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT TO THE BOARD OF

DIRECTORS ON A PROPOSED LOAN TO UGANDA FOR THE STRATEGIC TOWNS

WATER SUPPLY AND SANITATION PROJECT

Management submits the following Report and Recommendation for a proposed ADF loan of UA

44.00 million to the Government of Uganda to finance the Strategic Towns Water Supply and

Sanitation Project (STWSSP). The proposed Bank group financing of the STWSSP is the Bank’s

response to a formal request by the Government of Uganda to support Government efforts to

achieve sustainable provision of safe water and hygienic sanitation for the urban population with

improved resilience to climate change effects by the year 2030.

I STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.1.1 The proposed project will contribute to achieving Government priorities as outlined in the

second National Development Plan (NDP-II) covering the period 2015-2020 which aims to propel

Uganda to middle income status by 2020. The NDP-II’s strategic focus is to ‘Strengthen Uganda’s

Competitiveness for Sustainable Wealth Creation, Inclusive Growth and Employment’ through

four objectives: (i) increasing sustainable production, productivity and value addition in key

growth opportunities; (ii) increasing the stock and quality of strategic infrastructure to accelerate

the country’s competitiveness; (iii) enhancing human capital development; and, (iv) strengthening

mechanisms for quality, effective and efficient service delivery.

1.1.2 The project is aligned to Pillar 1 of the Bank’s Country Strategy Paper (CSP) 2017–2021,

“Infrastructure Development for Industrialization”. The key objective of the interventions in

‘Water Supply and Sanitation’ is to improve access to clean and safe water and sanitation facilities

of agri-business centres/zones, industrial parks, business centres and underserved households. The

Bank will support the Government’s goal to ensure availability and sustainable management of

water and sanitation for all (Sustainable Development Goal 6). By providing sustainable and

affordable water and sanitation services, the project will lay foundations for industrialization and

food security, enhance the sources of economic and social resilience, and contribute to improved

quality of life for the people. The project supports achievement of two of the Bank’s High-5; it

will improve the quality of life for Ugandans, and contribute to country’s industrialization.

1.1.3 The proposed project is also in line with the Bank’s Integrated Water Resource

Management Policy (2000) and is consistent with the Bank’s Climate Change Action Plan (2016-

2020) and Uganda Climate Change policy by supporting improved resilience of communities

against climate variability and change resilience through restoration and source protection of the

water intake areas for the urban water treatment plants. The project also supports the Urban

Development Strategy (2011) through providing strategic infrastructure for economic growth. Its

support to provision of improved water and sanitation services and capacity building with focus

on women and youth are aligned to Pillars II and III of the Bank’s Gender Strategy (2014-2018)

and Bank Group Strategy for Jobs for Youth in Africa (2016-2025).

1.1.4 The policy framework for the management and development of water resources in Uganda

is based on the National Water Policy (NWP) of 1999.1 The NWP promotes an integrated

approach to the management of water resources to ensure sustainability and optimal benefit to the

country. The NWP promotes the participation of all stakeholders in all stages of water supply and

sanitation and confirms the right of all Ugandans to safe water. Between 1998 and 2005 the

1 Other policy documents which complement the NWP include: the National Environment Management Policy

(1994); the Wetlands Policy (1995), the upcoming Land Use Policy; National Health Policy and Health Sector

Strategic Plan (1999); National Environmental Health Policy (2005); the School Health Policy (2006); and, the

National Gender Policy (1997).

Page 13: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

2

Government of Uganda (GoU) in collaboration with the Development Partners (DP), implemented

reforms in the water sector, in particular, urban water supply, rural water and sanitation, water for

production and water resources management. The consultations and studies recommended more

decentralized delivery of services, increased private-sector participation, and the need for a

programmatic sector-wide approach. It also became apparent that the strategies and investment

plans needed to be reviewed in order to harmonise them to minimise duplication and

contradictions, and bring on board emerging issues such as population growth, internal

movements of people, creation of new districts and town boards; and increased incidences of

climatic variability.

1.1.5 Achieving universal access to safe water and sanitation requires significant capital

expenditure. The sector investment plan (SIP) estimated that UGX 2,517 billion (USD 700

million) was required to achieve a safe water supply and sanitation services target of 77% by 2020.

Sector funding has been short of this expectation; the sector needs to explore more funding sources

to achieve this target. Achieving the Sustainable Development Goal (SDG) of universal access to

water and sanitation will therefore require strong institutions, huge investments (tapping different

sources of financing, including commercial financing), much improved operational efficiencies,

and innovative technologies.

1.2 Rationale for Bank’s Involvement

1.2.1 Economic growth and urbanization are placing increasing pressure on Uganda’s water

resources. It is forecast that by 2040, the population of Uganda will have reached about 61 million

people, of which 30% will reside in cities. However, urban services are not keeping pace with

urban population growth, with demand for services far outstripping supply in most urban areas.

Authorities are unable to keep pace with the growing demand for services because of inadequate

financing for capital investments and insufficient capacity for planning, operating, and

maintaining urban infrastructure and services. Existing wastewater treatment facilities are few and

far from the towns leading to discharge of untreated effluents. The wastewater in the informal

settlements is often discharged through inadequate systems, resulting in septic water and sludge

spilling into the environment.

1.2.2 In line with the SDG-6 target for Uganda, the Government has set to increase access to

water supply and sanitation services from an average of 65% in 2010 to 100% by 2030. The 2017

‘Water and Environment Sector Report’ reported that as at June 2017 access to improved water

supply was 71% for urban areas and 70% for rural areas, while access to improved sanitation was

at 86% for urban areas and 80% for rural areas. The achievements are still short of the national

goals as outlined in Uganda’s Vision 2040. Adequate water supply and sanitation infrastructure

remains a challenge as the country aspires for the long term sustainable socio-economic

development. The Government’s new focus for urban sanitation is through improved feacal sludge

management at regional level and adoption of the Improved Sanitation and Hygiene (ISH)

strategy. The GoU’s proposal to the Bank is to address the necessary urban infrastructure for these

approaches which is in line with the Bank’s strategic focus.

1.2.3 The 10 strategic towns to be covered by the project are located at district headquarters

which have strategic socio-economic importance to the districts. These are areas of high

population growth and significant potential for industrial development. The provision of piped

water and improved sanitation will enhance the competitiveness of Uganda’s important cities by

eliminating water shortages and addressing the problems with the discharge of untreated septic

sludge and sewage, both of which discourage investment and tourism.

1.2.4 The expected reduction in water collection distances and times will be particularly

beneficial to women and children, especially girls, who bear the burden of fetching water and have

to walk long distances or queue for long periods. The interventions through the project will result

in more opportunities for girls to attend school and more time for women to engage in other

Page 14: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

3

economically beneficial activities. The increased population exerts additional stress on the natural

resources of the country in general and on the towns in particular and increases vulnerability to

climate change effects. The project will therefore address environmental issues and catchment

protects particularly at the water source intakes.

1.2.5 The Bank has successfully implemented large urban water and sanitation projects over the

year in regions of Africa similar to Uganda. The Bank has also implemented a number of urban

water projects in Uganda with similar technology options and with the same executing agency,

like the Small Towns Water and Sanitation Project, Kampala Sanitation Project, Kampala Urban

Poor Project, Lake Victoria Water Supply and Sanitation Program, and Water Supply and

Sanitation Program phase I and II. Lessons from these intervention will help improve the quality

of the Bank’s involvements in urban water and sanitation sub-sector.

1.3 Donors Coordination

1.3.1 The Bank is supporting the development of water and sanitation services in Uganda in

partnership with other Development Partners (DPs). At sector level, DPs active in water and

sanitation (including the Bank) are members of the Water Supply and Sanitation Development

Partners Group (WSSDPG).2 The WSSDPG is currently co-chaired by Austria and the World

Bank. The Bank chaired the WSSDPG in 2008/9 and 2011/12. The WSSDPG meets monthly to

discuss sector issues related to water and sanitation interventions within the framework of the

Joint Water and Environment Sector Support Programme (JWESSP). The proposed project has

been discussed in the WSSDPG and the Group had endorsed it.

1.3.2 The DPs are also members of the Water and Environment Sector Working Group

(WESWG) Other membership besides MWE are line ministries, Water and Environment

Authorities and parastatals, and representatives of the WASH NGO, which provides policy and

technical guidance for the sector on all water supply and sanitation and environment related issues.

The working group meets at least four times a year and is supported by two sub-sector working

groups: (i) the Water and Sanitation Sub-Sector Working Group (WSSWG); and, (ii) the

Environment and Natural Resources Sub-Sector Working Group (ENRSWG). The sub-sector

working groups meet quarterly. Table 1 below provides a summary of recent sector funding by

the different sources and level of coordination.

Table 1: WSS Donor Coordination

*Appropriation In Aid which are internally generated funds by parastatals and agencies

Sector or subsector GDP % Budget

Water and Environment N/A

Sector Budget 2016/17 UA %

GoU UGX 331.55 Bn

Donor UGX 357.13 Bn

AIA* UGX 355.05 Bn

Off Budget UGX 54.93 Bn

UA 64.86m

UA 69.86m

UA 69.45m

UA 10.75m

30

33

32

5

Level of Donor Coordination

Existence of Thematic Working Groups Y

Existence of SWAPs or Integrated Sector Approaches Y

AfDB's involvement in donors coordination Chair (2008/09 and in 2011/12)

1.3.3 Since July 2013 the ministry of Water and Environment and its Development Partners

(DPs) have been implementing a Joint Water and Environment Sector Support Programme

(JWESSP). The Programme is expected to end in June 2019. The programme is a successor to the

Joint Water and Sanitation Sector Programme Support (JWSSPS) which ended in June 2013.

Arrangements are under way to prepare the JWESSP II 2018-2023. The JWESSP is an integral

part of the national sector framework, as the core instrument for joint support in the context of a

2 Members of the WSSDPG include AfDB, Danida, World Bank, AfDB, Germany, France, EU, UNICEF, USAID,

Austria, Water Aid, KfW, GIZ, UWASNET, IRC and JICA

Page 15: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

4

Sector-Wide Approach (SWAp) for the Water and Environment Sector. It allows for harmonised

mechanisms for coordination, financial management, performance review, joint decision making,

technical support and, to the extent possible, alignment to government systems.

1.3.4 The Bank has partnered with DPs under the JWESSP to undertake development

interventions in a programmatic approach for some of its previous and ongoing support.

Implementation of the Rural Water Supply and Sanitation Program (RWSSP) and the WSSP I &

II through sector budget support, and co-financing rural water supply in districts together with

Danida and Austria. The Kampala Sanitation Program (KSP) is being co-financed with KfW and

the EU. The STWSSP activities are part of the wider JWESSP co-financed by other DP’s.

II PROJECT DESCRIPTION

2.1 Project Components

2.1.1 The proposed STWSSP will comprise three components as presented in Table 2 below.

Annex B3 presents detailed description.

Table 2: Project Components

No. Component Est. cost

(UA)

Component Description

1 Urban Water

Supply 41.62m (37.46m)

1. Construction of urban water supply systems covering 10

strategic towns.

2. Engineering Services (Design and construction supervision).

3. Detailed engineering designs.

4. Production capacity; transmission & distribution lines and

reservoirs.

5. Equipment for the wider O&M and extension through

Umbrella utilities.

2 Improved

Urban

Sanitation and

Environmental

Management

4.89m

(4.40m)

1. Construction of 3 regional feacal sludge treatment facilities.

2. Procurement of 6 cesspool trucks.

3. 40 gender-segregated & disabled-friendly public sanitation

facilities constructed including in schools/ institutions.

4. Implementation of environmental management and climate

change resilience measures within urban water and sanitation

sub-sector.

3 Sector

Program

Support

(SPS)

2.38m

(2.14m)

1. Support the regulatory framework through developing of

regulation tools and tariff regime reviews.

2. Skills development for women and youth. (Water and

sanitation as a business).

3. Framework for bulk water.

4. Water and sanitation Atlas.

5. Sector coordination and M&E.

*Amounts in brackets depict the Bank’s contribution

2.2 Technical Solution Retained and other Alternatives Explored

2.2.1 The Project has retained expansion and construction of new surface water source intakes

and treatment plants as the best way to address the present water shortfall for an increasing

population in the targeted towns. Use of surface water (as opposed to production wells) is in line

with the sector medium to long term objective of supplying other cluster towns from the same

intake and treatment plant. The project shall prepare detailed engineering designs for multipurpose

water uses including water for production. These will guide future investment projects.

2.2.2 The sector has for the last two years focused on improving faecal sludge management

services across the country. The sector has put in place a strategy of clustering small towns into

50 clusters to guide sector investment in cost-effective shared faecal sludge treatment/disposal

facilities and better engagement of the private sector and local authorities in service delivery. Out

of 50 identified clusters, 13 have Feacal Sludge Plants (FSP) and an additional seven FSP are

Page 16: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

5

nearing completion. The project will support the regional FSP strategy. The alternatives

considered and reasons for rejection are captured in Table 3 below.

Table 3: Project Alternatives Considered and Reasons for Rejection

Alternative Brief Description Reasons for Rejection

Production

wells water

source

Town water supply could be

drawn from production

boreholes

Use of surface water is preferable to address the

medium to longer term objective of supplying

other cluster towns from the same intake and

treatment plant

Sewerage

systems

Construction of sewerage

systems in the towns

Very high investment costs and most towns

predominately have on-site sanitation.

Low willingness to connect to sewers networks.

GoU strategy is to focus on feacal sludge plants

with desludging trucks in the short to medium term

while sewerage systems may be considered for big

towns, in future projects.

Ecological

sanitation

Ecological sanitation demo

facilities in towns to entice

town occupants to upscale

using own resources

Other Bank supported projects have not realised

the anticipated replication within towns.

Preference is for more public facilities and the

ordinary on site facilities.

2.3 Project Type

2.3.1 The proposed project (STWSSP) is an investment project aligned to Uganda’s Joint Water

and Environment Sector Support Program (JWESSP 2018-2023) under the SWAp framework and

implemented by sector departments. The project will use the existing GoU and DPs’ agreed

funding modalities channelling funds through the Joint Partnership Fund (JPF). Monitoring and

evaluation will be aligned to the sector joint monitoring framework while reporting will be through

the joint JPF quarterly reporting agreed upon with other joint partners. The assessment of the

overall governance of the water and sanitation sector and the country’s fiduciary and financial

management environment concluded that country conditions are conducive for the use of national

rules and regulations.

2.4 Project Cost and Financing Arrangements

2.4.1 The total cost of the project including GoU contribution is UA 48.89 million net of taxes

and duties. The project costs are based on feasibility studies conducted on the targeted towns. A

summary of project cost estimates by components, expenditure categories, and schedule are

presented in Tables 4 below. Details are provided in the Technical Annexes B2.

Table 4: Project Cost Estimates by Component (in UA million)

Components Foreign

currency costs

Local currency

costs

Total

Costs

%

Foreign

1. Urban water supply

2. Improved urban sanitation

and environmental management

3. Sector Programme Support

14.67

2.16

0.43

23.17

2.28

1.73

37.84

4.44

2.16

38.8%

48.7%

19.9%

Total base cost 17.26 27.18 44.44 38.8%

Physical contingency 5%

Price Contingency 5%

0.86

0.87

1.36

1.36

2.22

2.23

Total project cost 18.99 29.90 48.89

2.4.2 Financing Arrangement: The Bank is using Uganda’s ADF 14 allocation to finance part

of the project cost not exceeding UA 44 million (90% of the overall project cost). The Government

will add UA 4.89 million (10% of the project cost before taxes) as counterpart financing. A

summary of the project cost by sources of finance is provided in Table 5 below. Detailed

information is provided in the financial tables of the Technical Annex B2.

Page 17: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

6

Table 5: Sources of financing (in UA million)

Sources of

Financing

Foreign Currency

Costs

Local Currency

Costs Total Costs % Total

ADF Group

GoU

18.52

0.49

25.48

4.40

44.00

4.89

90.0%

10.0%

Total Project Cost 19.01 29.88 48.89

Table 6: Project cost by category of expenditure (in UA million)

Categories of

Expenditure

Foreign Currency

Costs

Local Currency

Costs

Total Costs % Foreign

Goods

Works

Services

Operating Costs

1.53

11.70

4.03

0.00

0.45

17.55

6.82

2.36

1.99

29.24

10.85

2.36

77.2%

40.0%

37.1%

0.0%

Total base cost 17.26 27.18 44.44 38.8%

Physical contingency5%

Price contingency 5%

0.86

0.86

1.36

1.36

2.22

2.22

Total project cost 18.99 29.90 48.89

Table 7: Expenditure schedule by component (in UA million)

Components 2018/19 2019/20 2020/21 2021/22 2022/23 Total

1. Urban water supply

2. Improved urban sanitation and

environmental management

3. Sector Programme Support

5.08

0.09

0.42

12.85

0.60

0.54

11.08

0.87

0.66

6.13

2.60

0.40

2.69

0.29

0.15

37.84

4.44

2.16

Total base cost 5.58 13.99 12.61 9.13 3.13 44.44

Physical contingency

Price contingency

0.28

0.28

0.70

0.70

0.63

0.63

0.46

0.46

0.16

0.16

2.22

2.22

Total project cost 6.14 15.39 13.87 10.05 3.44 48.89

2.4.3 Co-financing: Co-financing was discussed with the key DPs in the water sector (KfW,

Austria, World Bank and Danida). Though not able to co-finance in the project, they have

complementary activities in the same regions. Urban water supply in Uganda is implemented

mainly through 4 regional Water and Sanitation Development Facilities (WSDF) coving the

North, East Central and South West region.

KfW will be developing town water supply for refugees in the Northern WSDF through a new

3 year Euro 8 million programme. KFW is currently supporting the WSDF North and East

with a Euro 23 million which ends this year.

World Bank is supporting town’s water development in the East with USD 47 million funding

for the next 3 years and concluding support for towns in the North and West for USD 55

million.

Austria will provide a 2 year bridging financing to towns in the South West, mainly to work

with the sector on Governance.

2.4.4 Other Sources of Financing: The Bank secured a Government endorsement letter for

additional USD 2.2 million to STWSSP from the climate fund (Appendix IV).The additional

funding for making STWSSP more climate change resilient will be appraised after clearance by

the Adaptation Fund Board Secretariat A budget of UA 1.27 million under STWSSP will be

dedicated to preparation of climate resilient projects to leverage approximately USD 83 million

from the Green Climate Fund.

Page 18: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

7

2.5 Project’s Target Area and Population

2.5.1 The primary beneficiaries of the project will be residents of ten towns spread across the

country. The identified towns are Kyenjojo-Katooke (Kyenjojo District), Nakasongola

(Nakasongola District), Kayunga-Busana (Kayunga District), Kamuli (Kamuli District),

Kapchworwa (Kapchorwa District), Dokolo (Dokolo District), Bundibugyo (Bundibugyo

District) and Buikwe (Buikwe District). The project will provide additional access to water and

sanitation to 390,000 people by 2023. The residents of the towns will benefit from a much more

regular supply of water and from improved wastewater and septic sludge collection and treatment

services. The project will train 150 people in appropriate urban sanitation (masonry/mechanic

artisans/waste management), targeting at least 20% women. The project will also conduct

sanitation and hygiene promotion in 30 communities (targeting at least 50 % women participation)

and support skills development for economic empowerment of 200 youth and women.

2.6 Participatory Process for Project Identification, Design and Implementation

2.6.1 Stakeholder engagements by the executing agency were held at different levels

(community, local government, and national). Consultations were held at town and district levels

with the technical staff who were involved in planning and provided the necessary data on the

existing town water and sanitation systems. They also shared investment/development plans for

each district and relevant towns which generated data that guided the feasibility studies and

designs.

2.6.2 The water sector has a fully developed consultative process with documented manuals

outlining several guidelines followed in all phases of a projects. The phases are, advocacy and

preplanning; pre-construction mobilization and training; during construction and post construction

phase. The guidelines are used together with the sector gender strategies in preparation and

implementation of programs/projects.

2.6.3 During preparation and appraisal missions, further consultations were held with the

Permanent Secretary for the MWE, together with the Commissioners of the relevant departments

(urban water supply and sewerage services; water and environment sector liaison, and water

supply regulation) and the technical staff who will implement the project. Further discussions

were held with senior officers of the Ministry of Finance Planning and Economic Development.

The proposed components and outputs were presented and discussed with the Development

Partners Group supporting the water and sanitation subsector in the country. Field visits to the

proposed project sites were conducted to engage with local governments and beneficiaries’ to

establish their level of involvement in the planning process and to appreciate the environmental

issues at the proposed intakes and water sources.

2.7 Bank Group Experiences, Lessons Learnt and Reflected in Project Design

2.7.1 The Bank’s ongoing portfolio in Uganda has a total commitment of UA 840.98 million

financing 18 operations. The portfolio includes 5 water and sanitation projects/programs with total

commitment of approximately UA 163.89 million (60% disbursed). Implementation experiences

of implementing operations in Uganda, especially the five operations in water and sanitation

provided valuable lessons to the design of the proposed project. Below is a summary of the lessons

(detailed information of lessons are provided in Annex B1).

Small Towns Water Supply and Sanitation Project: (i) the need to pay greater attention to

project design to ensure effective project implementation; (ii) timely execution and ownership

for sustainability depends on effective involvement and contribution of local governments and

beneficiaries; (iii) requirement for large Government contributions delays projects. In

designing the STWSSP, the local stake holders have been brought on board right from

the planning stage. Feasibility studies for the targeted sites and 50% of the designs are

ready which will minimise the project lead time.

Page 19: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

8

Water Supply and Sanitation Project Phase I (WSSP I): (i) the use of existing institutional

arrangements and country systems speeds up implementation; and, (ii) a stronger sense of

ownership and institutional memory. Investments in massive core infrastructure during

the projects life time allow for additional clusters of towns to be served using the meagre

government resources and other donor agencies long after the main project has closed.

STWSSP is designed to set in place the massive core infrastructure in the targeted towns.

Lake Victoria Water Supply and Sanitation Program: (i) Funding detailed and

comprehensive feasibility studies for the project towns before commencement of the

investment program improves disbursement rates; (ii) establishment of a fully-fledged and

dedicated Program Management Unit (PMU) to handle all project components including

capacity building and monitoring and evaluation ensures timely implementation; (iii)

utilization of fiduciary staff of the Executing Agency (IA), such as Accountants and

Procurement Officers, who also carry out other duties of the EA affect program

implementation and timely accountability; and, (iv) advance procurement of the design and

supervision consultant should start soon after project appraisal to ensure early engagement of

the Consultant for the project. STWSSP has established a full project team with a dedicated

senior accountant and senior procurement officer. The project is to apply for advance

procurement.

Rural Water Supply and Sanitation Programme: (i) use of common sector monitoring

frameworks allows for synergies and cross benefit from other agencies; and, (ii) decentralized

approach promotes private sector participation and growth as well as increased ownership by

local governments and communities and promotes bottom up planning. STWSSP will use the

common sector monitoring framework and will be implemented through the

decentralised water and sanitation development facilities.

2.8 Key Performance indicators

2.8.1 The Results Based Logical Framework (RBLF) has captured the project indicators for

impact, outcomes and outputs. During implementation of the project, the experienced M&E

experts assigned to the project will verify and analyse project data and submit it for central

amalgamation together with data from the regional and central structures monitoring and

evaluating outputs. The pooled quarterly data will be collected into the central data base for

analysis and computation of outcomes at national level. The outputs and outcomes will feed into

the annual sector performance report to be discussed during the Annual Joint Sector Review for

strategic decisions and sector direction in the following year. Additional monitoring of physical

infrastructure will be conducted annually during the Joint Technical Reviews with full field

participation of supporting DPs, civil; society and local governments. Value for Money studies

will be conducted at sector and Ministry of Finance, Planning and Economic Development level.

The sector has mainstreamed gender and a lot of emphasis is placed on disaggregation of data to

capture benefits from the projects to gender and youth. Baseline data was collected as part of the

feasibility study and used in the RBLF. The baseline data will be further strengthened and gaps

filled including collection of specific gender disaggregated data. Various supervision missions

and periodic progress reports will reflect the level of achievement under the indicators and will be

captured in the IPR which will guide managers in decision making.

2.8.2 The impact indicators include: (i) percentage incidence of diarrhea morbidity among

children under five reduced; and, (iii) percentage of pupils completing primary level of education.

The outcome indicators include: (i) percentage urban population with access to safe drinking

water; (ii) number of urban people served with improved access to safe water; and, (iii) percentage

of urban people with access to improved sanitation.

Page 20: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

9

2.8.3 The water sector in Uganda publishes the Uganda Water Atlas every 5 years providing

updated baseline data on water supply, functionality, and distribution as captured in the water atlas

up-date project (WATSUP) database. The latest Water Atlas was published in 2017. The project

will contribute to the next Water Atlas. The M& E expert attached to WSDF will make use of the

fully developed MIS system at the facility for data collection and analysis. The revised ESMF and

the accruing ESMPs will be used to monitor compliance in mainstreaming environment and

climate change resilience (see Technical Annex B8).

III PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 The financial and economic analysis (Table 8) has taken into account the assumptions

contained in the subsequent paragraphs. The program will be implemented over a 5 year period

and will have a life span of 20 years following completion of implementation in 2023.

Table 8: Key Economic and Financial Figures

FIRR 15.52% and FNPV UGX 42,268 million (at 10% base case)

EIRR 43.49% and ENPV UGX 359,834 million (at 10% base case)

Note: FIRR: Financial Internal Rate of Return, FNPV: Financial Net Present Value

3.1.2 The estimated target population for access to water supply under the project on completion

is estimated at 450,000 people (from 390,000 in 2017 and growing at 2.4% per annum). Service

assumptions are that proportion of beneficiary population will increase from 30% in 2019,

reaching 60% in 2021 and 100% in 2023.

3.1.3 Tariff setting remains an area of focus requiring support on an ongoing basis. With the

planned faecal sludge treatment plants, the cost of exhausting household and institutional liquid

waste will contribute to the revenue of the relevant operating entities. The financial and economic

assessment assumes a minimal contribution from the operations of the liquid waste infrastructure,

considering that the intervention envisages standalone regional wastewater treatment

infrastructure which relies a lot on use of cesspool emptiers.

3.1.4 Operating and maintenance costs, including administration overheads, are estimated to be

65% of the revenue generated. With the performance contracts to be signed with the utilities or

umbrella bodies, this high level of costs will become a performance target thus enhancing the

viability of the utility and sustainability of the infrastructure.

3.1.5 The EIRR considers the incremental benefits arising from reduction in health costs due to

reduction in waterborne infections. It also considers the time saving benefit, as women and

children spend less time fetching water. This will lead to an increase in their focus on other income

generating activities, thus improving the livelihoods of the communities. It will also contribute to

the ease of doing business, as enterprises will be attracted to set up shop in the target towns, thus

creating employment.

3.1.6 Sensitivity analysis was undertaken to assess the impact on the FIRR and EIRR of

increases in the capital costs and tariff reductions, and concluded that the reductions in tariffs,

have a more accelerated impact on the viability of the project than the measured increases in

capital costs. This will buttress the need to support the regulatory department to build capacity to

provide regular cost recovery tariff reviews in order to enhance the financial health of the utilities

which leads to sustainability. The conclusion of the sensitivity analysis is that both increases in

capital costs and reductions in tariffs of up to 20% will not result in the interventions becoming

unviable.

3.1.7 The Small Town’s Water Supply and Sanitation Project and the Rural Water Supply and

Sanitation Program were satisfactorily completed and PCRs prepared. The PCR process for the

Page 21: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

10

Water Supply and Sanitation Program Phase I is ongoing and the IPR is rated satisfactory. The

WSSP II is one year into implementation and ahead of schedule with a satisfactory rating.

3.2 Environmental and Social Impacts

3.2.1 Environment

The project is aligned to the Bank’s Integrated Safeguards System and is in line with the Bank’s

Environmental and Social Management Procedures. The project was categorized as Category 2

on 12th September 2017. The justification for categorization and application of the Environmental

and Social Management Framework (ESMF) is that most systems are existing and will only be

expanded to meet the needs of existing and growing towns. The project activities will include

undertaking of design reviews on the 10 water supply systems and 3 faecal sludge management

facilities. It is mandatory that the EIA process for any applicable water resources related

development project conforms to the provisions of the National Environment Act, Cap 153 and

the accompanying Regulations.

STWSSP will manage its environmental and social risks through the Project Implementation Unit

(PIU) that is mandated to safeguard the environment and social plight of affected communities.

Using the ESMF the project will apply the EIA process for water resources related projects that is

structured into six steps: (i) screening phase (planning/project conception); (ii) scoping stage (pre-

feasibility study); (iii) EIA study phase (feasibility study); (iv) contract procurement

(compensation and resettlement); (v) defects liability period (environment monitoring); and, (vi)

operation and maintenance phase (compliance audit). The framework provides guidance on the

roles and responsibilities of STWSSP Implementation Staff, communities, and others stakeholders

participating in the STWSSP regarding the sustainable environmental and social management of

sub-programs. This is online with the Bank’s ISS policies and procedures that underscore the need

for effective stakeholder engagement in management of environmental and social risks.

3.2.2 Climate Change

GoU is committed to the achievement of SDGs. According to the Climate Safeguards Screening,

STWSSP is categorized as 2 on climate risk. Under the project, water source and catchment

protection activities and climate safeguards shall be undertaken for all sub-projects. Additionally,

during the preparation of ESMP for each sub-project, an assessment of the climate change impacts

shall be evaluated using the Bank’s Adaptation Review and Evaluation Procedures (AREP) under

the Bank’s Climate Safeguards System (CSS). This will help identify an appropriate adaptation

action including relevant activities for each sub-project as well as capacity building needs for the

Executing Agency. Through the catchment planning activities and water source protection, the

project will contribute to the national climate change adaptation strategies

3.2.3 Involuntary Resettlement

No project intervention will require significant land acquisition, which would result in involuntary

resettlement of the project affected persons (PAPs). However, during the design review, additional

reservoirs may be required to be installed whose area coverage is estimate at 50 sq. metres each.

Such land will be procured in accordance with the Bank’s ISS policy and GoU’s land acquisition

policy and framework, with funds from GoU under counterpart funding which is part of the annual

budget of the sector. The resources will be available starting 2018-2019 financial year. Through

effective stakeholder and community engagement, land for installation of transmission and

distribution pipes for water will be voluntarily provided by beneficiary districts, local

governments and beneficiary communities. The PIU shall undertake all necessary efforts to ensure

that leaders of districts, local governments, town councils, beneficiary communities, the general

public and any other stakeholders are mobilized and sensitized about the project and related land

requirements or arrangements. In the past local governments and beneficiary communities have

always provided land for water and sanitation projects and this has created a sense of ownership

Page 22: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

11

for commissioned water supply and sanitation systems besides enhancement of social cohesion,

community structures, and the social inter-linkages that common property provides.

3.2.4 Gender

The traditional role of women and girls primarily are water collectors, water users and the main

promoters of sanitation and hygiene. The average distance travelled by urban households to collect

water is about 200 metres, compared to 800 metres in rural areas. Women and girls spend about

55% of their time travelling to collect water daily. Consequently, females bear the brunt of

walking long distances to fetch water for domestic use hence trading off productive time used for

other economic activities. Furthermore, the time walked to fetch water deprives girls of school

going age from attending school full time. The gender gap in the water sub-sector is caused by

inadequate access to safe drinking water and sanitation facilities and inequitable control of water

resources. Other challenges relating to inequitable access and control of water resources, supply

and sanitation are reflected in Annex B8. STWSSP has been designed to promote institutional

involvement of women in water management ensuring a minimum of 30% of women are

represented in the leadership role in water user associations.

The project emphasizes community trainings on sanitation and hygiene promotion targeting at

least 50% women participation. Group trainings in water and sanitation related economic activities

like soap making, water vending, and others will be allocated to women and youth.3 A needs

analysis will be undertaken to identify specific gender economic activities for the different regions

and their implementation modalities. The project has been designed to enhance the capacity of

women and youth groups through trainings in economic skills focused on employment generation

to ensure both the women and youth participate in and benefit from inclusive affirmative

opportunities. Annex B8 provides detailed information.

3.2.5 Social

The project will put in place pro-active business startup measures and build capacity of 200

women and youth in the targeted 10 towns. The provision of piped water supply and sanitation

will trigger economic growth through stimulation of commercial activities such as hotels, and it

will provide end user social services to education and health institutions. About 4,000 temporary

jobs and 1,000 permanent jobs will be realized from project activities and stimulation of

commercial activities benefitting a minimum of 30% of women. The project will lead to reduction

of incidences of water borne diseases especially in children and foster development by increased

productivity of the population especially women. Reduced expenditure on health makes more

finances and time available for women to engage in economic activities.

Youth unemployment: Ugandan youths continue to face challenges of limited job opportunities,

inadequate employable skills, lack of access to productive assets, and early marriages hence

forcing the youth into informal sector. While the overall unemployment rate marginally declined

by 0.4 percentage points to 9% (UNHS 2016/17) from 2012/13, the youth unemployment remains

high estimated at 11%. The majority of the youth live in rural areas engaging in agriculture and

urban areas. STWSSP will train the youth and women groups on to how to set up their own

business activities especially in income generating projects. Of the targeted 150 people, at least

20% youth and 20% women will be engaged in the appropriate urban sanitation skilling

(masonry/mechanic artisans/waste management).

HIV/AIDS: An estimated 1.2 million Ugandans are living with HIV/AIDS. HIV prevalence is

four times higher in females aged 15-19 than males and three times higher in females aged 20-24

years of age than males. HIV/AIDS awareness will be undertaken in the context of water

3 Annex 8 of the Technical Annex provides detailed information of how the project support gender economic

empowerment activities related to water and sanitation.

Page 23: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

12

management committee groups as well as the related economic empowerment activities to

enhance prevention, treatment and to improve the welfare of persons living with AIDS. The

training coordinator from the projects training activities will collaborate with the existing national

HIV/AIDS control programmes and CSOs to effect sensitization in the women and youth groups.

It is mandatory for water supply and sanitation contractors to have an active HIV and AIDS

workplace policy for their staff intended to raise awareness and prevention, stigma and

discrimination, treatment and positive living. Partnerships between the Project, Health Ministry,

and contractors will be leveraged to increase HIV/AIDS awareness among beneficiary community

and will be incorporated as part of the training modules. The project will use existing structures

like referrals to hospitals (for prevention and treatment purposes); and existing healthcare

structures such as village treatment teams to effect HIV/AIDS related tasks. Detailed information

is provided in Annex B8).

IV IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 The STWSSP will be implemented using existing GoU structures. The GoU will be the

borrower, and the Ministry of Water and Environment will be the executing agency responsible

for overall coordination of planning, implementation and monitoring of the project.

The overall Project Coordinator will be the Commissioner for Urban Water and Sewerage Services

Department assisted by a Project Manager for routine co-ordination of project activities. A

technical advisory team composed of commissioner for water and environment sector liaison;

assistant commissioners for urban water and sewerage services; commissioner for utility

regulation and commissioner for climate change, shall provide technical guidance to the project

implementation team. The Project Implementation Team (PIT) will have an Environment and

Sanitation Officer, Sociologist, Senior Accountant, Senior Procurement Officer, M& E Officer, 3

Engineers, Climate Change Officer, Regulation Officer and a Water Sector Liaison Officer. The

Water and sanitation sub-sector working group shall be the Steering Committee. The organogram

is provided in Annex B3

4.1.2 Procurement Arrangements

Procurement of goods, works and the acquisition of consulting services, financed by the Bank will

be carried out in accordance with the October 2015 “Procurement Policy and Methodology for

Bank Group Funded Operations” (BPM), and following the provisions stated in the Financing

Agreement. Specifically, procurement will be carried out following:

• Borrower Procurement System (BPS): Specific Procurement Methods and Procedures

(PMPs) under BPS comprising Public Procurement and Disposal of Public Assets Act No.1

of 2003; and, Public Procurement and Disposal of Public Assets Regulations 2014, using the

national Standard Solicitation Documents (NSSDs) or other Solicitation Documents agreed

during project negotiations for various group of transactions to be entailed under the project.

• Bank Procurement Policy and Methodology (BPM): Bank standard PMPs, using the

relevant Bank Standard Solicitation Documents SDDs, for contracts that are either (i) above

the thresholds indicated in Technical Annex B5, Paragraph B.5.6.1 or (ii) in case BPS is not

relied upon for a specific transaction or group of transactions; and, (iii) in case BPM have been

found to be the best fit for purpose for a specific transaction or group of transactions.

Procurement Risks and Capacity Assessment (PRCA): The assessment of procurement risks at the

country, sector, and project levels and of procurement capacity at the Executing Agency (EA)

were undertaken for the project and the output have informed the decisions on the procurement

regimes to be used for specific transactions or groups of similar transactions under the project.

Page 24: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

13

The appropriate risks mitigation measures have been included in the Section 5.2.5 of the Technical

Annex.

4.1.3 Financial Reporting and Audit

Consistent with the Paris Declaration on Aid Effectiveness and the Accra Agenda for Action, the

project will make use of the country’s PFM systems. The Assistant Commissioner for Finance in

MWE will be responsible for the Financial Management (FM) of the program while the Permanent

Secretary MWE will be the Accounting Officer.

MWE’s FM is led by an Assistant Commissioner Accounts who has appointed accountants to

manage the day to day financial operations of all donor funded projects guided by the GoU

financial regulations and procedures. Recently because of the new project, a new accountant has

been appointed to assist with the new project financial transactions. The project will use the

Microsoft Dynamics Navision 2013 R2 accounting software to capture and report on all of its

financial transactions based on the International public Sector Accounting Standards (IPSAS).

The Finance Department is adequately staffed. It has over twenty accountants with some of them

assisting project accountants in projects authorization and approval process.

Budgeting for the project will follow the GoU rules and procedures on budgeting. The total project

budget will be included in the MWE annual budget and included in the GoU’s National budget.

The project will follow the GoU financial year of 1st July to 30th June. The project’s financial

statements which will be prepared within three months of the end of the financial year, will be

audited by the Office of the Auditor General (OAG). The audit terms of reference will be agreed

between GoU and the Bank. The audit report, complete with a management letter and responses,

will be submitted to the Bank within six months of the end of the financial year. The Ministry will

also be required to submit to the Bank quarterly Financial Reports together with the project’s

progress report no later than 45 days after the end of each quarter.

The following internal control procedures among others are in place and will be used by the new

project. The procedures include: Approval of Bank accounts opening, proper authorization and

approval of Bank reconciliations, segregation of duties in payments and cash management,

monthly Bank reconciliations and timely banking of receipts.

To provide oversight and assist in strengthening the Project’s internal control mechanism, MWE’s

internal audit section will include the project in its annual audit planning and the audit reports will

be shared with the Bank as needed.

For the Bank financed projects being implemented by the MWE, the internal audit department

clears and approves project transactions before being submitted to the Bank for justifications.

The results of the assessment indicate that the financial management of the MWE risk rating for

the project was substantial because of the following:

(i) Direct method payments not captured in the project’s accounting system;

(ii) Financial transactions mispostings in the accounting system as a result of improper coding of

expenditures from project component managers;

(iii)Long outstanding staff advances; and,

(iv) Delayed monthly bank reconciliations with a backlog of three years being cleared in 2017.

The MWE has put corrective measures in place including appointing an additional accountant and

also creating separate company codes in the accounting system to separate the financial

transactions of the projects under implementation. It is expected that with all these measures the

project will be able to (1) use the funds for the intended purposes in an efficient and economical

way, (2) ensure funds are properly managed and flow smoothly, adequately, regularly and

predictably, (3) prepare accurate, reliable and timely periodic financial reports, (4) monitor the

efficient implementation of the Program, and (5) safeguard the entities’ assets. Detailed information

Page 25: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

14

is provided in Annex B4.

Audit Arrangements: OAG will audit the project financial statements annually and at the end of

the project in line with the terms of reference agreed with the Bank. An audit report, complete

with a management letter and management responses, will be presented annually to the Bank,

within six (6) months following the end of each financial year. The annual audit will be done in

accordance with the International Standards on Auditing. Details are provided in annex B6.

Disbursement Arrangements: Disbursements under the ADF loan will be made in accordance

with the Bank’s rules and procedures as laid out in the Disbursement Handbook. In addition, the

Bank shall issue a Disbursement Letter of which the contents will be discussed and agreed during

negotiations. The disbursement methods that will be used for the Project include the: Direct

Payment and the Special Account methods. The MWE shall show evidence of having opened one

Special Account in foreign currency and one local currency Project account. The two accounts

shall be opened at the Bank of Uganda. The MWE shall process all transactions relating to these

bank accounts and separate cash books shall be maintained for each account within the existing

accounting system. Disbursements to the special account will be made following approved work

plans and satisfactory justifications and not in tranches. The opening of a special account shall be

a condition for first disbursement and should be done after the project is approved.

4.2 Monitoring

4.2.1 The project’s monitoring will fit into the wider sector monitoring and evaluation

framework. Overall monitoring setup will includes Joint Sector Reviews (JSRs) are held twice a

year (Technical Reviews in April and Joint Sector Reviews in October). The sector further

conducts VFM technical audits and tracking studies which are deliberated upon in the sub sector

working group meeting. The Ministry of Finance, Planning and Economic Development also

conducts independent monitoring of the sectors and documents findings for engagement with the

sectors. At the implementation level, the comprehensive Results Based Monitoring (RBM)

Manual to monitor implementation and impact of WSDF interventions will be applied. MWE will

also ensure that the Urban Data base annually captures the access and related information on all

new and rehabilitated facilities under the project to facilitate assessment of progress and input in

the Banks Implementation Performance Result Report and the next Water Atlas.

4.2.2 The Bank will follow up the implementation of the project through active participation in

the periodic technical and sector reviews, regular supervision mission during project

implementation, and ex-post evaluations. In line with use of country systems, MWE will compile

and submit to the Bank the JPF quarterly progress reports and annual progress reports that reflects

all project activities for all funding agencies. A midterm review will be conducted jointly by the

MWE and the Bank in Oct 2021. Upon completion of the project, MWE will prepare and submit

to the Bank a project completion report (PCR). The milestones for monitoring are summarized in

Table 9 below.

Table 9: Milestones

Timeframe Milestone Monitoring process / feedback loop

June 2018

Sept 2018

Sept 2018

Dec 2018

October 2021

June 2024

Loan Approval

Loan Signature

Loan Effectiveness

First Disbursement

Mid Term Review

Closing date

ADF Board

COUG to follow up

Launching Mission – TM follow up

ADF – COUG to monitor closely

COUG/ MWE – Follow-up

ADB/COUG to monitor closely

4.3 Governance

4.3.1 The Water and Sanitation Subsector Working Group, shall be the Project Steering

Committee. It has representatives from the Directorate of Water Development (DWD) and the

Page 26: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

15

Directorate of Water Resources Management (DWRM); National Water and Sewerage

Corporation (NWSC); Selected Line Ministries – Finance, Health, Gender, Local Government

and Agriculture; Development partners, including NGOs represented by UWASNET. It shall

review and approve the joint JPF annual workplans and quarter JPF reports.

4.3.2 The Water sector established a Good Governance Working Group (GGWG) tasked to

identify and recommend measures to promote and monitor transparency, accountability and good

governance. It conducts value for money audits and GG workshops. The GGWG monitoring shall

include project activities.

4.3.3 The current internal controls at sector level require all payment requests initiated by

contractors and consultants to be reviewed and cleared by the implementing departments, the

office of the Director, Internal Audit and Accounts department in the sector before clearance by

the Permanent Secretary who will then submission the verified requests to the office of the

Accountant General in the ministry of Finance, Planning and Economic Development for final

review and clearance before submission to the Bank for payment.

4.3.4 The STWSSP has proposed measures for strengthening financial Governance including:

(i) provision of project financial management manuals; (ii) ensuring internal audit identifies pre-

audit transaction challenges; and, (iii) timely submission of progress reports, and follow up

actions.

4.4 Sustainability

4.4.1 The 1999 National Water Policy (NWP) addressed key recommendations of the reforms,

promoting an integrated approach to the sustainable management of the water resources with

participation of all stakeholders, including women and the poor. The policy objective mandates

and commits the water sector to manage and develop the water resources of Uganda in an

integrated and sustainable manner, so as to secure and provide water of adequate quantity and

quality for all social and economic needs of the present and future generations with the full

participation of all stakeholders. It also defines sustainability strategies to ensure that no new

installations or schemes should be established without, establishing ownership of the facility

strengthen the system for operation and maintenance, including methods of recovering recurrent

cost to ensure sustainability.” The country will be committed to the project in line with the national

policy.

4.4.2 The project will adopt a demand responsive approach, which is well defined in the guiding

implementation manuals used at entry while engaging with beneficiaries to ensure a sense of

ownership and commitment as well as sustainability of the water supply and sanitation facilities.

The proposed institutional arrangement involves a transfer of the water supply schemes from

MWE to either the established water utilities or the Water Authorities (WAs), and the operation

of the facilities by Private Operators (POs) through management contracts. These arrangements

which have been used in small towns across Uganda, enhance efficiency in the management of

the project’s facilities and in revenue collection to ensure the sustainability of the facilities.

4.4.3 For the case of POs, revenues from water in each town will be deposited in an escrow

account, which will be operated by both the POs and WAs to cover recurrent expenditures related

to water services. The funds will be ring- fenced to minimize the possibility of diversion of water

revenues to fund other activities. Creation of WAs and the signing of the Performance contract

between the MWE and the newly created WAs and subsequent establishment of management

contracts between WAs and the POs coupled with operationalization of the Umbrella

Organizations (UOs) for operation and maintenance will ensure sustainability of the created

facilities. The sector will also hand over viable town water systems to the national utility (NWSC)

for further expansion and management. The utility uses a standardized tariff for all the water

supply service areas through a cross-subsidy process. Box 1 provides the highlights of the tariff

Page 27: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

16

regimes and the prevailing tariff levels in the country for areas that are under the jurisdiction of

National Water and Sewerage Corporation (NWSC), Private Operators, small towns and rural

areas.

Box 1: Tariff Regimes

Tariff Regimes in Small Towns, RGCs and NWSC

The information provided below highlights the tariff regimes and the prevailing tariff levels in the country for areas

that are under the jurisdiction of National Water and Sewerage Corporation (NWSC), Private Operators, small towns

and rural areas.

NWSC tariff regime: The National Water and Sewerage Corporation (NWSC) tariff structure has a uniform tariff

across all its towns and service areas (large urban centres, small towns, rural growth centres and urban areas with

gravity schemes), but differentiated by customer groups. The sewerage tariff is based on the volume of water

consumed. The NWSC adopted an indexation policy in 2002 aimed at protecting the tariff from further erosion and

thus enabling the NWSC cover its operational costs, thereby ensuring sustainability of service provision. NWSC

Water and Sewerage rates are subject to annual indexation effective to protect it against the inflation, exchange rate

movements and electricity tariff. The latest tariff approval was done in 2006. The specific tariff rates are in Annex

B3

NWSC Tariff in Rural Areas: The uniform tariff across all towns and service areas still applies in rural areas served

by NWSC. The tariff structure is skewed with the domestic customers paying less than the institutional and

commercial customers. The tariff therefore has an implicit cross subsidy across towns and within customer categories.

NWSC Tariff public institutions: The uniform tariff for ‘Institutions/Government’ which covers also public

institutions is significantly higher than the domestic tariff.

Tariff water vending: The uniform tariff provides for a ‘Public Standpipe’ tariff at lower costs as compared to a

domestic connection, which ‘is applicable to individuals who strictly sell water to the community or rather the public’

(NWSC definition). This public standpipe tariff and their management by the above mentioned individuals refers to

the definition of ‘water vendors’ used for this issues paper. This is a tariff with pro-poor provisions as it should make

the water more affordable to the end user as it is supposed to lower the retail price from the operators / individuals

how sell the water.

Tariff Regimes in Towns Outside Small Towns and Rural Growth Centres

According to the Water Act, Cap. 152 (1997), the tariff policy provides that every water authority can fix tariffs with

the approval of the Minister. This is based on the developed business plans as stipulated in the Tariff Policy (2009)

which reflects the uniqueness of the water infrastructure and hence the associated Operation and Maintenance (O&M)

costs. The policy further requires the tariffs to be simple and uniform which should enable recovery of actual O&M

costs. The uniform tariff in each service area does not provide a separate tariff for Institutions/Government, Public

Standpipes. However, the average tariffs and the tariffs charged at Public Standpipes and Kiosks do differ. Some

smaller and community-managed schemes work with monthly fees which can be defined as pro-poor as these fees

are derived from the willingness and ability to pay rather than cost coverage.

The national average for domestic tariffs throughout the year based on the business plans stands at 2,463 shillings per

unit. Based previous statistics 60% of the small towns were meeting O&M cost recovery while the 40% were

subsidized by the Ministry Urban water supply.

Future Plans

Tariff indexation to avoid tariff erosion based on the prevailing level of inflation.

Introduction of the increasing block tariff to be piloted under regional water utilities (Umbrella Organization)

setting a minimum beyond which the consumer incurs more with increasing volume of water consumed.

Clustering to provide for cross subsidization to optimize the economies of scale.

Development, application and implementation of a comprehensive National tariff Policy covering NWSC, small

towns, Private Operators and Regional water Utilities (Umbrella Organizations) and rural areas.

Improve on the tariff monitoring and approval process by strengthening the existing data management platforms

like UPMIS.

4.4.4 The constructed water systems will adopt the tariffs above pending approval and adoption

of the revised tariff regime that the project will support. The project will also provide support to

build capacity of the regulation department, UOs, WAs and POs to enable them to meet their

obligations and to enhance the institutional sustainability arrangements. Critical to the

sustainability of the project’s benefits is the involvement of women in the planning and

Page 28: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

17

management of the facilities. The project will adhere to the sector gender strategy promoting

affirmative action for women involvement and will monitor the gender indicators as outlined in

the RBLF.

4.5 Risk Management

4.5.1 The project faces the following potential risks as identified in the Result Based Logical

frame with the proposed mitigation measures as in Table 10 below.

Table 10: Risk Mitigation Measures

Risk Probability/

Impact

Mitigation Measures

Policy and regulatory framework

– The regulatory department is still

young. Delays in setting up

effective and efficient regulatory

policies and strategies may affect

service delivery.

Low to medium

probability/

high impact

The Ministry of Water and Environment

continues to regulate the urban water and

sewerage services sub-sector through the

Utility Regulation Department. The Utility

Regulation Department will be strengthened to

achieve its mandate including tariff setting and

compliance monitoring of Utilities that will

manage the completed water supply schemes

Financial and economic:

Exchange rate volatility has

affected funds availability,

especially where there is delay in

implementation of projects and

delay in disbursements.

Low to medium

probability/

medium impact

The AfDB and GoU will ensure timely

disbursement of funds. Adequate price

contingence shall be provided for to guard

against the exchange rate volatility.

Project design and effectiveness:

Access to land and required

environmental approvals may delay

timely completion of the sub-

projects.

Low to medium

probability/

high impact

The EA will start commence land

identification and acquisition before

effectiveness and ensure timely approval of the

Environmental and Social Monitoring Plan

Effectiveness: Possible delay in

project effectiveness due to delays

in parliamentary and government

approvals.

Low to medium

probability/high

impact

The EA will commence engage with the

parliamentary committee and ministry of

Finance, Planning and Economic Development

during the appraisal process

Project implementation: Sub-

project scope, time and cost

overruns may impact on timely

delivery of the project.

Medium to high

probability/

medium impact

The EA shall be supported to strengthen

contract monitoring in order to timely respond

to scenarios that may lead to scope, cost and

time over runs.

4.6 Knowledge Building

4.6.1 STWSSP will generate knowledge owing to its new focus on massive core infrastructure

for urban water supply with potential of supplying town clusters and activities on the new thinking

for urban sanitation through regional plants. The project has also lined up activities on climate

change resilience, women and youth employment and empowerment. The interventions will

generate lessons for the sector. Component 3 of the project will address knowledge gathering

through monitoring reports and analytical studies to capture key lessons from the implementation

and also track the performance against the sector golden indicators.

4.6.2 The WSDF Results Based Monitoring framework sets ground for improved data

collection, processing and dissemination to a wide range of stakeholders on urban water supply

and sanitation. This ensures that all stakeholders at various levels are informed on the progress of

the Project activities, it contributes to improvement measures and share the lessons learnt in

implementation.

Page 29: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

18

V LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instruments

5.1.1 The financing instrument to be used for this project is an ADF loan of UA 44 million. The

loan will be governed by a Loan Agreement to be signed between the African Development Fund

(the “Fund”) and the Republic of Uganda

5.2 Conditions associated with Bank’s intervention

5.2.1. Conditions Precedent to the Entry into Force of the Loan Agreement: The entry into

force of the Loan Agreement shall be subject to the fulfilment by the Borrower of the provisions

of Section 12.01 of the General Conditions Applicable to Loan and Guarantee Agreements of the

Fund (Sovereign Entities).

5.2.2. Conditions Precedent to First Disbursement of the Loan: The obligation of the Fund to

make the first disbursement of the Loan shall be conditional upon the entry into force of the Loan

Agreement.

5.2.3. Other Loan Condition: The Borrower shall open a foreign currency denominated Special

Account to receive the proceeds of the Loan and a local currency denominated account

5.2.4. Undertakings: The Borrower undertakes to:

(i) comply with the national environmental and waste management guidelines and procedures

applicable in Uganda from time to time, and all applicable national environmental

management and coordination laws and biomedical procedures;

(ii) Fully implement the Environmental and Social Management Plan (ESMP); and

comprehensively report on the implementation of the ESMP on a semi-annual basis.

.

5.3 Compliance with Bank Policies

5.3.1 This project complies with all applicable Bank policies.

VI RECOMMENDATION

6.1 Management recommends that the ADF Board of Directors approves the proposed ADF

loan of UA 44.00 million to the Republic of Uganda for the purposes and subject to the conditions

stipulated in this report.

Page 30: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

I

Appendix I: Comparative Socio-economic Indicators

Year Uganda Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2016 242 30,067 97,418 36,907Total Population (millions) 2016 40.3 1,214.4 6,159.6 1,187.1Urban Population (% of Total) 2016 16.9 40.1 48.7 81.1Population Density (per Km²) 2016 201.8 41.3 65.1 33.8GNI per Capita (US $) 2015 670 2 153 4 509 41 932Labor Force Participation *- Total (%) 2016 85.0 65.7 63.5 60.0Labor Force Participation **- Female (%) 2016 82.3 55.7 48.9 52.1Sex Ratio (per 100 female) 2016 99.9 100.1 106.0 105.0Human Dev elop. Index (Rank among 187 countries) 2015 163 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2012 34.6 ... 14.6 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2016 3.3 2.5 1.3 0.6Population Grow th Rate - Urban (%) 2016 5.5 3.6 2.4 0.8Population < 15 y ears (%) 2016 47.8 40.9 27.9 16.8Population 15-24 y ears (%) 2016 20.3 19.3 16.9 12.1Population >= 65 y ears (%) 2016 2.5 3.5 6.6 17.2Dependency Ratio (%) 2016 101.3 79.9 54.3 52.0Female Population 15-49 y ears (% of total population) 2016 22.4 24.0 25.7 22.8Life Ex pectancy at Birth - Total (y ears) 2016 59.9 61.5 69.9 80.8Life Ex pectancy at Birth - Female (y ears) 2016 61.9 63.0 72.0 83.5Crude Birth Rate (per 1,000) 2016 42.1 34.4 20.7 10.9Crude Death Rate (per 1,000) 2016 9.0 9.1 7.6 8.6Infant Mortality Rate (per 1,000) 2015 37.7 52.2 34.6 4.6Child Mortality Rate (per 1,000) 2015 54.6 75.5 46.4 5.5Total Fertility Rate (per w oman) 2016 5.6 4.5 2.6 1.7Maternal Mortality Rate (per 100,000) 2015 343.0 476.0 237.0 10.0Women Using Contraception (%) 2016 34.6 31.0 62.2 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2005-2015 12.0 41.6 125.7 292.2Nurses and midw iv es (per 100,000 people) 2005-2015 134.2 120.9 220.0 859.4Births attended by Trained Health Personnel (%) 2010-2015 58.0 53.2 69.1 ...Access to Safe Water (% of Population) 2015 79.0 71.6 89.4 99.5Access to Sanitation (% of Population) 2015 19.1 39.4 61.5 99.4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2015 7.1 3.4 ... ...Incidence of Tuberculosis (per 100,000) 2015 202.0 240.6 166.0 12.0Child Immunization Against Tuberculosis (%) 2015 93.0 81.8 ... ...Child Immunization Against Measles (%) 2015 82.0 75.7 83.9 93.9Underw eight Children (% of children under 5 y ears) 2010-2015 14.1 18.1 15.3 0.9Prev alence of stunding 2010-2014 33.7 33.3 25.0 2.5Prev alence of undernourishment (% of pop.) 2015-2016 25.5 16.2 12.7 ...Public Ex penditure on Health (as % of GDP) 2014 1.8 2.6 3.0 7.7

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2016 101.1 101.2 104.9 102.4 Primary School - Female 2010-2016 102.1 98.4 104.4 102.2 Secondary School - Total 2010-2016 26.1 52.6 71.1 106.3 Secondary School - Female 2010-2016 24.6 50.2 70.5 106.1Primary School Female Teaching Staff (% of Total) 2010-2016 42.3 47.1 59.8 81.0Adult literacy Rate - Total (%) 2010-2015 73.8 66.8 82.3 ...Adult literacy Rate - Male (%) 2010-2015 81.0 74.3 87.1 ...Adult literacy Rate - Female (%) 2010-2015 66.8 59.4 77.6 ...Percentage of GDP Spent on Education 2010-2015 1.7 5.0 4.0 5.0

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2014 34.4 8.7 11.2 10.3Agricultural Land (as % of land area) 2014 71.9 41.7 37.9 36.4Forest (As % of Land Area) 2014 11.0 23.2 31.4 28.8Per Capita CO2 Emissions (metric tons) 2014 0.1 1.1 3.5 11.0

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Uganda

June 2017

0

10

20

30

40

50

60

70

80

90

100

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

U ganda Af r ica

0

500

1000

1500

2000

2500

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

GNI Per Capita US $

U ganda Af r ica

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

Ug anda Af r ica

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

U ganda Af r ica

Page 31: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

II

Appendix II: Bank Group Portfolio in Uganda

Date of Update: 31st DECEMBER 2017

Serial No.

Project Description Approval

Date Signature

Date

Disbursement Effectiveness

Date

Approved Amount UA million Net Commitments

(UA million)

Amount Disbursed (UA million)

Disbursed (%)

Deadline for Last

Disbursement

Project Task Manager Status (not

effective & on-going/effective

, etc)

1st Date of Disbursemen

t ADB

ADF Loan

ADF Gran

t

A. AGRICULTURE

1 Community Agricultural Infrastructure Improvement Programme III

03/05/2011 10/06/2011 22/02/12 21/03/2012 nil 40.00 nil nil 40.00 38.37 95.9% 31/12/2017 Niwagira Asaph Closed

2 Markets and Agricultural Trade Improvement II (MATIIPII)

10.12.2014 28.07.2015 02.10.2015 16.11.2015 58.78 nill nil nil 60.14 0.60 1.0% 30.06.2020 Niwagira Asaph on going

3 Preparation for Strategic Plan for Climate Resilience

17.03.2016 14.07.2016 14.07.2016 17.10.2016 1.11 nill nil nil 1.11 0.20 18.0% 30.04.2018 Shiam Muhamed on going

4 Farm Income Enhancement and Forestry Conservation Project II

20.01.2016 17.02.2016 12.04.2016 31.05.2016 53.40 nill nil nil 54.79 6.09 11.1% 30.06.2021 Makonnen on going

Agriculture - Sub Total 156.04 45.26 29.0%

B. TRANSPORT

5 Road Sector Project 4 ( Kigumbba Masindi Rd) 135 KM

13/03/2013 11/12/2013 08/08/2014 21.10.2015 nil 72.94 nil nil 72.94

13.89 19.0% 30/06/2018 Katala Jumbe ongoing

6 Road Sector Project V 28/05/2014 03/02/2015 26/08/2015 19.05.2016 nil 70.00 nil nil 70.00

4.28 6.1% 31/12/2020 Katala Jumbe ongoing

Transport - Sub Total 142.94 18.17 12.7%

C. WATER

7 Kampala Sanitation Project 16/12/2008 11/05/2009 18/02/10 16/07/10 nil 35.00 nil nil 35.00 32.93 94.1% 31/12/2018 Mbiro Andrew ongoing

8 Water Supply and sanitation program Phase 1

5/10/2011 11/01/2012 26/09/2012 19/10/2015 nil 40.00 nil 3.59 43.59 42.64 97.8% 31/12/2017 Mbiro Andrew Closed

9 Water Supply and sanitation program Phase 2

3/2/2016 03-Mar-16 11/05/2016 19/07/2016 nil 65.80 nil nil 65.80 25.86 39.3% 30/06/2021 Mbiro Andrew ongoing

Page 32: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

III

10 Additional Funds to Water Supply and Sanitation Program

4/3/2015 30/04/2015 30/04/2015 18/10/2015 nil nill nil 8.37 8.37 4.77 57.0% 30/06/2019 Mbiro Andrew ongoing

Water and Sanitation - Sub total 152.76 106.20 69.5%

D. SOCIAL

11 Rehabilitation of Mulago and KCC Clinics

06/07/2011 11/01/2012 02/07/2012 28/08/2012 nil 46.00 10.00 nil 56.00 42.52 75.9% 30.09.2018 Ogwang Peter on going

12 Education V Project (HEST) 21/11/2012 05/07/2013 18/11/2013 19.02.2014 nil 67.00 nil nil 67.00 28.87 43.1% 30.06.2018 Ogwang Peter On going

Social - Sub Total 123.00 71.39 58.0%

E. ENERGY

13 Rural Electricity Access 16.09.2015 04.11.2015 12.02.2016 25.05.2016 70.92 nil nil 0.00 70.92 0.53 0.7% 31.12.2020 Alemayehu Wubushet

on going

14 Mbarara-Nkenda/Tororo-LiraTransmission Lines Project

16/12/08 26/03/2010 18.02..2011 20/04/11 nil 52.50 nil nil 52.50 42.53 81.0% 28/02/2018 Alemayehu Wubushet

ongoing

Energy - Sub total 123.42 42.53 34.5%

GRAND TOTAL FOR PUBLIC SECTOR OPERATIONS 698.16 283.55 40.6%

Page 33: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

IV

Appendix III: Selected Projects Financed by the Bank and other Development

Partners in the Country

DPs Programme / Project

Location

Project

Implementation

Period

Amount in

million

AfDB

Additional funds to

WSSP for climate

change resilience

Eastern Districts

2015-2018 UA 5.4

AfDB Water Supply and

Sanitation Program II

Country wide 2016-2020 UA 65.8

AfDB

Regional

LVWATSAN Program

Ph II

5 towns around

Lake Victoria 2011-2018 UA 11.13

AfDB Kampala Sanitation

Program

Kampala 2009-2018 UA 35.00

AfDB

Supplementary Loan

to Kampala Sanitation

Program

Kampala

2018-2019 UA 19.00

AFD KW-LVWATSAN Kampala 2012-2018 EURO 75

Denmark Sector Budget Support

Rural WASH

countrywide 2013-2018 DKK 290.5

Denmark Support JWESSP countrywide 2013-2018 DKK 137.5

EU Piped Water Supply Southwest &

East/Northeast

2012-2018 EUR 30.5

Germany/KfW KW-LVWATSAN Kampala 2012-2018 EUR 20

Germany/KfW Urban wash Gulu 2013-2018 EUR23

UNICEF Rural WASH Central, Western,

Acholi and

Karamoja Region

2016-2020 EUE 10

World Bank Urban Wash Arua, Gulu,

Mbale,Ishaka-

Busheny

(2012-2018) USD 55

World Bank Urban Wash Butaleja-Busolwe,

Budaka-Kadama-

Tirinyi, Kumi-

Nyero-Ngora,

Rukungiri, Busia,

Pallisa, Katwe-

Kabatoro and

Koboko

(2012-2018) USD 43

Page 34: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

V

Appendix IV; Government Endorsement Letter for Climate Fund Cofinancing

Page 35: UGANDA STRATEGIC TOWNS WATER SUPPLY AND SANITATION …€¦ · iv PROJECT SUMMARY Project Overview: The objective of the Strategic Towns Water Supply and Sanitation Project (STWSSP)

VI

Appendix V: Map of Project Areas

Source: Ministry of Water and Environment