Status Workshop 08.07.2005 FZJ Prof. Singheiser 1 Linde AG Business Unit Linde Engineering...
-
Upload
cheyenne-presgraves -
Category
Documents
-
view
213 -
download
0
Transcript of Status Workshop 08.07.2005 FZJ Prof. Singheiser 1 Linde AG Business Unit Linde Engineering...
Status Workshop 08.07.2005 FZJ Prof. Singheiser
1Linde AG Business Unit Linde Engineering
“ENCAP”
Enhanced Capture of CO2
Status: July 2005 Dr. Ciattaglia
Status Workshop 08.07.2005 FZJ Prof. Singheiser
2Linde AG Business Unit Linde Engineering
Project costs : 22,2 Mio Euro (EC Contribution: 10,7 Mio Euro)
Start : March 2004
Duration : 5 years
Some partners:
for power station operation: Vattenfall, RWE
for power station construction/turbines: SIEMENS, Alstom
for oxygen generation/supply: Air Liquide, BOC, Linde
for processing/engineering: Lurgi, Mitsui Babcock, Statoil, Linde
for material testing/developing: SINTEF, TNO, Uni Twente, IFP
Status Workshop 08.07.2005 FZJ Prof. Singheiser
3Linde AG Business Unit Linde Engineering
•Project Overview
•Progresses
Status Workshop 08.07.2005 FZJ Prof. Singheiser
4Linde AG Business Unit Linde Engineering
Project goals
Development and optimisation of emerging CO2-capture technologies and processes for power generation based on fossil fuels meeting the following targets:
at least 90% CO2-capture rate
50% CO2-capture-cost reduction Reference: 50-60 Euro/t captured CO2.
ENCAP targets are the enhacement of CO2-capture efficiency and the reduction of CO2-capture costs.
Status Workshop 08.07.2005 FZJ Prof. Singheiser
5Linde AG Business Unit Linde Engineering
Project timing and structure
• Timing: five years (2004-2008), 2 phases, start of project: March 2004
Phase I: research and basic experimental activities on candidate technology concepts (months 1-30).
Phase II: research and large scale verification of one/two candidate technology concepts selected on the basis of Phase I results.
ENCAP timing consists of two main phases.
Status Workshop 08.07.2005 FZJ Prof. Singheiser
6Linde AG Business Unit Linde Engineering
ENCAP is structured in six sub-projects, SP.
• StructureRTD activities structured in 6 sub-projects (important participants):
SP1 Process and Power Systems (Vattenfall, RWE,Siemens, Alstom, Linde LE)(definition of power plant processes, reference plants, bench marks)SP2 Pre-Combustion Decarbonisation Techn. (RWE, Lurgi, Siemens, AirL)(IGCC, IRCC, oxygen from an cryo ASU)SP3 OxyFuel Boiler Technologies (Vattenfall, AirL., Mitsui Babcock Energy)(coal, natural gas with oxygen from an cryo ASU)SP4 Chemical Looping Combustion (Alstom, SINTEF, IFP,TNO)(oxygen transport by metal oxides)SP5 High-Temperature Oxygen Generation for Power Cycles (BOC, Statoil, SINTEF, TNO, Univ. Twente, Linde LE), SP Leader: LINDE LE.(membrane developments)SP6 Novel Pre-Combustion Capture Concepts (Alstom, Siemens, AirL)
Status Workshop 08.07.2005 FZJ Prof. Singheiser
7Linde AG Business Unit Linde Engineering
SP5 is focussed on the development of high-temperature oxygen generation systems.
SP5: High Temp. Oxygen Generation for Power Cycles
Goals: identification, evaluation and ranking of promising high temperature oxygen generation process options, to be effectively integrated in power plant cycles with CO2 capture.
Organisation: 2 phases
phase I: development of three promising high temperature oxygen generation routes, based on ceramic materials and either O2-transport or O2-storage, to enable economic comparison and selection of the most promising option (first 18-months)
phase II: further validation of the selected option
Status Workshop 08.07.2005 FZJ Prof. Singheiser
8Linde AG Business Unit Linde Engineering
WP5.5Stability
definition of materials
WP5.1Oxygen process
selection and integration
WP5.4Oxygen transport
membrane
WP5.3
CAR process
WP5.2Oxygen
separator membrane
Statoil
TNOSINTEFUTwente
SINTEF TNO UTwente
LindeSiemens
RWEBOCAP
SP5 is structured into five interacting work packages
Status Workshop 08.07.2005 FZJ Prof. Singheiser
9Linde AG Business Unit Linde Engineering
•Project Overview
•Progress
Status Workshop 08.07.2005 FZJ Prof. Singheiser
10Linde AG Business Unit Linde Engineering
WP5.1 Oxygen process selection and integration
Definition of a stepwise procedure for the selection of one most promising power plant with integrated high T oxygen generation system (Milestone month 18).
First economic evaluation of preselected, most promising scenarios with integrated oxygen generation systems.
A selection procedure for the identification of the most promising integration power plant scenario was defined
Status Workshop 08.07.2005 FZJ Prof. Singheiser
11Linde AG Business Unit Linde Engineering
WP5.2 Development and validation of oxygen separator membrane for power plant cycle applications
Selection of the basis composition CaTiFeO for the development of a membrane system dense layer + porous support.
Identification of the methodologies for membrane system manufacture.
WP5.3 Development of CAR process
Identification of new materials with oxygen recovery capacity exceeding by a factor 3-6 the standard CAR materials and allowing a decrease in the process temperature by about 200 °C.
Found the phenomenon of “restoration” of perovskite structures enabling thus extended material life time.
Material screening, testing and characterisation were focused by WP5.2 and WP5.3.
Status Workshop 08.07.2005 FZJ Prof. Singheiser
12Linde AG Business Unit Linde Engineering
Principle of the CAR Process(Ceramic Autothermal Recovery)
air
steam/CO2N2
steam/CO2 and O2
regenerator layer
regenerator layer
perowskite pelletslayer
Status Workshop 08.07.2005 FZJ Prof. Singheiser
13Linde AG Business Unit Linde Engineering
WP5.4 Reactive oxygen transport membrane system
Calculation and upgrading of a power plant concept with integrated OTM-reformer reactor or OTM separator
Feasibility study on OTM + reformer reactor
Data on material and on long term stability tests were collected before ENCAP
WP5.5 Stability evaluation of high temperature oxygen generation methods
Intensive work on WP5.3 materialsExperimental confirmation of the “restoration” phenomenon (SINTEF)Stability tests (“accelerated life-time tests”, Twente)
The integration of the OTM unit in power plan was the main issue of WP5.4
Status Workshop 08.07.2005 FZJ Prof. Singheiser
14Linde AG Business Unit Linde Engineering
Month 30
WP5.1 Process integration
WP5.2 Oxygen separator
WP5.3 CAR process
WP5.4 Oxygen reactor
WP5.5 Stability issues
Month 18
Key Milestone: Selection process option
Phase 2: Validation of the selected
processDesign concept
of a scaled-up test unitfor this process
Next steps for SP5
Month 18 is SP5 next critical milestone.
Status Workshop 08.07.2005 FZJ Prof. Singheiser
15Linde AG Business Unit Linde Engineering
thank you
for your attention