Setraco Nig.Ltd.
1st Bi-Monthly Project Report Of
EDO- State ( Auchi )
Prepared By: Checked By: Engr. Amaresh Dhibar Engr. Pedro Chami Technical Office Engineer Project Manager
Approved By:Engr. Zakhia Akl
Regional Manager
PROJECTSEDO- State consist of Three different Project Named-CONSTRUCTION OF JATTU - AFOWA - IYORA - AKPANA - AYOGWIRI ROAD (11+772 KM) INCLUDING ONE BRIDGE OF 1X15 M SPAN IN EDO STATE.
CONSTRUCTION OF AYOGWIRI-APANA-IMIEKBA-IMIEKIBU ROAD (18+730 KM) WITH ONE BRIDGE OF 3X20M SPAN INCLUDING IGBODOR-OKPEKPE-SPUR ROAD (7+56O KM) WITH ONE BRIDGE OF 2X20M SPAN.
CONSTRUCTION OF EKPERI-ANEGBETTE ROAD (30+100 KM) WITH TWO BRIDGES 3X15 M SPAN & 4X15 M SPAN.
Setraco Nig.Ltd.
PROJECT DETAILSPROJECTS LENGTH
OF ROAD
CLIENT CONSULTANT BRIDGES
Jattu Road 11+772 Km
EDO STATE GOVERNMENT OF NIGERIA ,EDO STATE MINISTRY OF WORKS,
BENIN , EDO STATE.
CYPRESS KONSULT LIMITED
1 NBR.1X15 M SPAN
Ayogwiri & okpekpe
Road
18+730 Km&
7+560 Km
CYPRESS KONSULT LIMITED
1 NBR. 3X20M SPAN & 1 NBR. 2X20
M SPAN
Ekperi- Anegbette
Road30+100 KM NOBA NIG. LTD.
1 NBR 3X15M SPAN &
1 NBR 4X15 M SPAN
Setraco Nig.Ltd.
CONTRACT DETAILSSetraco Nig.Ltd.
PROJECT CONTRACT TYPE
DATE OF AWARD
COMMENCEMENT OF
WORK
CONTRACT SUM IN MILLION NAIRA ( N ) DURATION
IN WEEKSORIGINAL REVISED
Jattu Road Item Rate Dec. 2009 12thJan.2010 2717.72 3029.83 72
Ayogwiri &
okpekpe
Road
Item Rate Dec. 2009 28thDec.2009 6162.98 6793.74 72
Ekperi- Anegbett
e RoadItem Rate Dec.2009 14th Jan.2010 7667.71 7927.84 120
Organogram Of EDO ProjectSetraco Nig.Ltd.
Engr. Pedro Chami Project Manager
Engr. Zakhia Akl Regional Manager
Carlos
Haddad
Commerci
al Adm
n.
Engr. Geor
ge Badd
er Site
Engineer
Wiliam Tayar Road-superintendent
K.B.AryaLab S/v
George
nouhiely Snr.
Store Keep
er
Engr. Amaresh
Dhibar
Tech. Offic
e Engineer
Jad Chahada Sr.
Plant Engineer
Yusuf Wetwet Camp Manager
General layout of jattu-apana road projectSetraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
General layout of ayogwiri & okpekpe project
Setraco Nig.Ltd.
JATTU AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROAD
AYOGWIRI-IMIEKIBU
ROAD
OKPEKPE
BRIDGE CH-5+325BRIDGE
CH-11+825
General layout of ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+197
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Progress layout of jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Activity Chainage Color ID
Site Clearing 0+000-11+772
Progress layout of jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Activity Chainage Color ID
Site Clearing 0+000-11+772
Sub- Grade0+000-8+110
8+256 -11+772&
Progress layout of jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Activity Chainage Color ID
Site Clearing 0+000-11+772
Sub- Grade0+000-8+110
8+256 - 11+772&
Sub- Base 0+000-8+110&
8+256 -11+772
Progress layout of jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Activity Chainage Color ID
Site Clearing 0+000-11+772
Sub- Grade0+000-8+110
8+256 - 11+772&
Sub- Base 0+000-8+110&
8+256 - 11+772
Base 0+000-8+110&
8+256 - 11+772
Progress layout of jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Activity Chainage Color ID
Site Clearing 0+000-11+772
Sub- Grade0+000-8+110
8+256 -11+772&
Sub- Base 0+000-8+110&
8+256 - 11+772
Base 0+000-8+110&
8+256 - 11+772
Wearing Course
0+000-8+100
&8+375 -11+772
Progress layout of jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Activity Chainage Color ID
Site Clearing 0+000-11+772
Sub- Grade0+000-8+110
8+256 -11+772&
Sub- Base 0+000-8+110&
8+256 - 11+772
Base 0+000-8+110&
8+256 -11+772
Wearing Course
0+000-8+100&
8+375= 11+772
Surface Dressing
0+000-8+100&
8+375 - 11+772
Progress of Drain jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Description Chainage Color ID
U- drain ( 75x75x10)cm
0+070-0+267,0+269-1+064, 6+797-7+703, 11+138-11+770
Side
LHS
U- drain ( 75x75x10)cm
RHS 5+675-6+198, 6+797-7+702, 11+138-11+378
U- drain ( 75x90x10)cm
LHS & RHS 7+700-8+010
V- drain ( 140x60x50x10)cm LHS & RHS 8+010- 8+105,
8+382-8+600, 9+945-10+370
Progress of Culvert jattu-apana road projectActivity
ChainageColorID
Site Clearing0+000 – 11+772
Sub- Grade0+000 – 8+110
8+256-11+772
Setraco Nig.Ltd.
JATTUCH0+000
APANACH11+772
AFOWA
IYORA
BRIDGE CH 8+232
IMIEKEBU
JATTU-APANA ROAD
AYOGWIRI
AYO
GWIR
I-IM
IEKI
BU R
OAD
Description Chainage Color ID
Ring Culvert
Size
1X.9 m
4+592, 9+900, 10+700
10+150, 3+315, 2+425
Ring Culvert 2X.9 m 7+700
Ring Culvert
1X1.2 mRing Culvert
2X1.2 m
6+175, 9+000, 11+150, 5+475, 3+814, 1+343, 1+200, 0+265
Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROAD
AYOGWIRI-IMIEKIBU
ROAD
OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Activity Chainage Color ID
Site Clearing
Ayogwiri-: 0+000-18+725&
Okpekpe:- 0+000-4+350
Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROAD
AYOGWIRI-IMIEKIBU
ROAD
OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Activity Chainage Color ID
Site Clearing
Ayogwiri-: 0+000-18+725&
Okpekpe:- 0+000-4+350
Sub-Grade0+000-11+750
& 12+175-12+975
Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROAD
AYOGWIRI-IMIEKIBU
ROAD
OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Activity Chainage Color ID
Site Clearing
Ayogwiri-: 0+000-18+725&
Okpekpe:- 0+000-4+350
Sub-Grade0+000-11+750
& 12+175-12+975
Sub-Base 0+000-10+500
Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROAD
AYOGWIRI-IMIEKIBU
ROAD
OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Activity Chainage Color ID
Site Clearing
Ayogwiri-: 0+000-18+725&
Okpekpe:- 0+000-4+350
Sub-Grade0+000-11+750
& 12+175-12+975
Sub-Base 0+000-10+500
Base 0+000-9+700
Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROAD
AYOGWIRI-IMIEKIBU
ROAD
OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Activity Chainage Color ID
Site Clearing
Ayogwiri-: 0+000-18+725&
Okpekpe:- 0+000-4+350
Sub-Grade0+000-11+750
& 12+175-12+975
Sub-Base 0+000-10+500
Base 0+000-9+700
Wearing Course 0+000-9+680
Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROAD
AYOGWIRI-IMIEKIBU
ROAD
OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Activity Chainage Color ID
Site Clearing
Ayogwiri-: 0+000-18+725&
Okpekpe:- 0+000-4+350
Sub-Grade0+000-11+750
& 12+175-12+975
Sub-Base 0+000-10+500
Base 0+000-9+700
Wearing Course 0+000-9+680
Surface Dressing
0+000-9+680
Progress of Drain ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROADAY
OGW
IRI-I
MIE
KIBU
RO
AD OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Description Side Chainage Color ID
U- drain ( 75x75x10)cm
LHS 0+025-0+118, 2+843-3+174, 3+203-3+323, 3+343- 3+653
U- drain ( 75x75x10)cm
RHS 0+025-0+114, 2+795-3+321, 3+345-3+681
V- drain ( 140x60x50x10)cm LHS 1+188- 1+448, 1+758-
2+089, 4+547- 4+643, 5+488- 5+735
V- drain ( 140x60x50x10)cm
RHS 1+260- 1+465, 1+758- 2+031, 2+580- 2+683, 4+548- 4+641, 5+488- 5+749, 4+510- 4+539, 9+095- 9+185.
U- drain ( 75x90x10)cm
1+448- 1+752LHS
Progress of Culvert ayogwiri & okpekpe projectSetraco Nig.Ltd.
JATTU
AYOGWIRICH0+000
IMIEKIEBUCH0+18+786
IGODOR CH-0+000
SPOURCH-7+563
APANA
IMIEKBA
OKPEKPE-SPOUR
ROADAY
OGW
IRI-I
MIE
KIBU
RO
AD OKPEKPE
BRIDGE CH-5+325
BRIDGE
CH-11+825
Description Size Chainage Color ID
Ring Culvert 1x.9 m 0+975, 1+760, 4+950, 7+640, 8+100, 3+185
Ring Culvert 2x.9 m 3+075
Ring Culvert 1x1.2 m 1+200, 5+325
Ring Culvert 2x1.2 m 2+175, 8+380, 3+328
Box Culvert 1x2x2 m 4+548, 5+475
Progress layout of ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+167
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Activity
Chainage
Color ID
Site Clearing
0+750-19+159
Progress layout of ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+167
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Activity
Chainage
Color ID
Site Clearing
0+750-19+159
Sub-grade
0+800-18+175 &
18+220- 19+025
Progress layout of ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+167
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Activity
Chainage
Color ID
Site Clearing
0+750-19+159
Sub-grade
0+800-18+175 &
18+220- 19+025
Sub-Base
0+800-7+950
Progress layout of ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+167
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Activity
Chainage
Color ID
Site Clearing
0+750-19+159
Sub-grade
0+800-18+175 &
18+220- 19+025
Sub-Base
0+800-7+950
Base
0+800-5+925
Progress layout of ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+167
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Activity
Chainage
Color ID
Site Clearing
0+750-19+159
Sub-grade
0+800-18+175 &
18+220- 19+025
Sub-Base
0+800-7+950
Base
0+800-5+925
Wearing Course
0+800-5+403
Progress layout of ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+167
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Activity
Chainage
Color ID
Site Clearing
0+750-19+159
Sub-grade
0+800-18+175 &
18+220- 19+025
Sub-Base
0+800-7+950
Base
0+800-5+925
Wearing Course
0+800-5+403
Surface Dressing
0+800-5+403
Progress of Culvert ekperi-anegbette road project
Setraco Nig.Ltd.
EKPERI CH 0+000
ANEGBETTE CH-30+100
BRIDGE CH18+167
BRIDGE CH19+100
EKPERI-ANEGBETTE ROAD
Description
Chainage
Color ID
Ring Culvert
8+063, 14+840
Size 1X.9m
Ring Culvert
1X.9/2m
12+910
Ring Culvert
1X1.2m
6+513, 9+710, 13+425, 15+400, 15+825, 16+175
Ring Culvert
1/2X1.2m
2+475
Ring Culvert
2X1.2m
11+500, 14+175
Box Culvert
2X2X2m
7+400
Box Culvert
2X2.4X2.4m
3+500, 18+500, 18+675, 18+850
Jattu Bridge @ch- 8+232 Progress detailsSetraco Nig.Ltd.
Date as on 1st sep’11
Ekperi Bridge @ch-18+197 Progress detailsSetraco Nig.Ltd.
Date as on 1st sep’11
Ekperi Bridge @ch-19+099 Progress detailsSetraco Nig.Ltd.
Date as on 1st sep’11
SummAry of % of Progress Setraco Nig.Ltd.
0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00%
79.89%
31.07%
34.14%
Ekperi Ayogwiri Jattu
% OF COMPLETION
PROJECT
Detailed % of ProgressSetraco Nig.Ltd.
Side Drain
Site Clearing
Sub-Grade
Sub-Base
Base
Surface Dressing
Wearing Coarse
48%
100%
100%
100%
98%
96%
98%
41.25%
71.10%
49.40%
41.17%
36.45%
35.70%
36.81%
0.00%
71.73%
63.30%
24.49%
23.32%
15.34%
15.10%
Ekperi Ayogwiri Jattu
% OF COMPLETION
ACTIVITY
Forcasted vs. executed cumulative turnoverSetraco Nig.Ltd.
Feb'10
March'10
April"10
May'10
June'10
July'10
Aug'10Se
p'10Oct'
10
Nov'10Dec'1
0Jan
'11Fe
b'11
March'11
April"11
May'11
June'11
July'11
Aug'11
0500000000
10000000001500000000200000000025000000003000000000
JATTU- AKPANA ROAD PROJECTCum. Forcasted Turnover Cum. Executed Turnover
Month of Progress
Turnover
Million
Forcasted vs. executed cumulative turnoverSetraco Nig.Ltd.
Feb'10
March'10
April"10
May'10
June'10
July'10
Aug'10Se
p'10Oct'
10
Nov'10Dec'1
0Jan
'11Fe
b'11
March'11
April"11
May'11
June'11
July'11
Aug'11
0
500000000
1000000000
1500000000
2000000000
2500000000
AYOGWIRI-OKPEKPE- IMIEKIBU ROAD PROJECTCum. Forcasted Turnover Cum. Executed Turnover
Month of Progress
Turnover
Million
Forcasted vs. executed cumulative turnoverSetraco Nig.Ltd.
Feb'10
March'10
April"10
May'10
June'10
July'10
Aug'10Se
p'10Oct'
10
Nov'10Dec'1
0Jan
'11Fe
b'11
March'11
April"11
May'11
June'11
July'11
Aug'11
0500000000
100000000015000000002000000000250000000030000000003500000000
EKPERI-ANEGBETTE ROAD PROJECTCum. Forcasted Turnover Cum. Executed Turnover
Month of Progress
Turnover
Million
Executed Turnover vs.Certified AmountSetraco Nig.Ltd.
Jattu Ayogwiri Ekperi0.00
500.00
1000.00
1500.00
2000.00
2500.00
3000.00
3500.00
4000.00
4500.00
Million
Jattu Ayogwiri Ekperi
Adv. Payment in
MN647.076 856.45 1825.65
Previously Certified
in MN
2386.19 2321.54 3856.38
Retention Money
in MN
144.28 212.32 330.25
Contract Sum in
MN3029.83 6793.74 7927.84
Progress photograph Of
jattu-akpana road project
Setraco Nig.Ltd.
Setraco Nig.Ltd.
Cut to fill @ 9+950- 10+075
Site clearance and earth work
Borrow to fill @ Ch- 10+375-11+050
Setraco Nig.Ltd.
Site clearance and earth work
Remove Unsuitable @ Ch- 7+900-8+025 Cut to spoil @ 8+000 – 8+225
Setraco Nig.Ltd.
Pavement and surfacing work
Stone Base laying @ 9+187 – 11+200Sub-Base Base laid @6+450 – 8+150
Setraco Nig.Ltd.
Pavement and surfacing work
Laying Mc1 @ Ch- 6+910-8+110 laying Mc1 at shoulder @ 8+375 – 11+200
Setraco Nig.Ltd.
Pavement and surfacing work
Laying S-125 at shoulder @ 8+375 – 11+200 Surface dressing @ 8+375 – 11+200
Setraco Nig.Ltd.
Pavement and surfacing work
Finish Road SurfaceLaying of Asphalt @ 8+375 – 11+200
Setraco Nig.Ltd.
Concrete work
U- drain ( 75x75x10) cm and Precast slab Precast Kerb wall fixing
Setraco Nig.Ltd.
Concrete work
Pile cap & abutment with wing wall casting @ Bride 8+232
Cyclopean Concrete below pile cap @ Bridge 8+232
Setraco Nig.Ltd.
Concrete work
Deck slab Concreting @ Bridge 8+232
Head wall with wing wall casting @ Bride 8+232
Progress photograph Of
Ayogwiri-Imiekibu road project
Setraco Nig.Ltd.
Setraco Nig.Ltd.
Massive Earth cutting @ Ch- 11+300- 12+577
Setraco Nig.Ltd.
Casting of Ring culvert @ Ch- 1+200
Setraco Nig.Ltd.
Compaction of subgrade Ch-0+350 -1+650 Remove unsuitable.
Setraco Nig.Ltd.
Sub-base Ch-0+000 -0+825 Laying of asphalt @ ch- 0+000- 1+370.
Setraco Nig.Ltd.
U-drain (75x90x10) @ ch- 1+580- 1+760 Stone pitching @ch-3+075
Setraco Nig.Ltd.
Precast kerb fixing @ ch- 0+500- 0+783 Culvert 2X2 m @ch-4+547.7
Setraco Nig.Ltd.
Casting of V-drain (140x60x50x10) cm Stone Base laying @ ch-7+000- 8+400
Progress photograph Of
Ekperi-Anegbette road project
Setraco Nig.Ltd.
Setraco Nig.Ltd.
Subgrade preparationSite clearing @ ch- 0+750 – 8+475
Setraco Nig.Ltd.
Lateritic Base Laying of MC1 & surface dressing.
Setraco Nig.Ltd.
Casting of Precast Beam Laying of Asphalt.
Setraco Nig.Ltd.
Pile cap in progress.Drilled Piling @Ch 18+197 Bridge
Setraco Nig.Ltd.
Construction of Cross beam Abutment and retaining wall at Bridge
Setraco Nig.Ltd.
Launching of precast Beam at Bridge@ Ch-18+197 & 19+099
Setraco Nig.Ltd.
Fixing of precast slab and casting of Deck slab at Bridge@ Ch-18+197 & 19+099
Setraco Nig.Ltd.
Box and Ring culvert
Setraco Nig.Ltd.
Dredged Sand filling from Ch-18+220 – 19+025
Progress photograph Other than
project
Setraco Nig.Ltd.
Setraco Nig.Ltd.
Bush-Bar Under construction at Life camp Emulsion plant under construction
Thank You
Setraco Nig.Ltd.