REPLY TO PRE-BID QUERIES RFP Ref: BOI:HO:IT:RFP:CBS:SI ...
Transcript of REPLY TO PRE-BID QUERIES RFP Ref: BOI:HO:IT:RFP:CBS:SI ...
Serial No RFP Page
No
RFP Clause
No
RFP Clause Clarification BOI COMMENTS
1 16 3.2 Bank intends to select a System Integrator for Management, Monitoring and
Maintenance of Universal Banking Solution (Finacle Core, CRM, SVS, SSO, Config
Editor and Finacle Integrator etc.), Fircosoft, Allied Applications, Delivery Channels, FMS
and other Services at Central Locations, Branches/Subsidiaries and Offices for Bank’s
Overseas Setup at DC and NR located in Mumbai and DR located in Bangalure along
with local DC-DR setup in some overseas centres, based on the Bank's requirement as
stated in the RFP.
Please share what is expected from the bidder
for Local DC-DR setup overseas centres. Our
understanding is that any support that will be
required if any will be done form central site at
Mumbai
Yes . The Local DC and DR should
be in sync with production and any
support which is required to be
extended from central site ,
Mumbai.
2 18 3.2 ii. Finacle e-Banking Application- The bidder shall provide and install all kind of
patches, upgrades, and hotfixes on proactive basis as soon it released by OEM of
Solutions.
Our understanding is Any upgrade of
applications that requires OEM involvement or
requires architectural/technology changes will be
done on a change request/project basis. Please
confirm
As per RFP
3 17 3.2 i. Finacle Universal Banking Solution – The bidder shall provide and install all kind of
patches, upgrades, and hotfixes on proactive basis as soon it released by OEM of
Solutions.
Our understanding is Any upgrade of
applications that involves OEM involvement,
additional costs from OEM or change in
architecture will be done on a change request
basis. Please confirm
As per RFP
4 18 3.2 ii. Finacle e-Banking Application- The bidder shall proactively inform the projections to
Bank regarding upgradation requirement of Hardware with sizing plan and
reasonableness and monitor the same for the entire period of contract.
The sizing for e-Banking is only provided by
Edgeverve and No SI/bidder currently has
capability to do the same. The bidder can
coordinate with Bank's OEM for the same.
As per RFP
5 21 3.2 iv. Universal Banking Solution(UBS), FEBA , Fircosoft , Mobile Banking Hardware –
Bidder has to fulfil the necessary requirement for running all solution / entire setup along
with Hardware.
The necessary Hardware along with AMC is being procured separately and handed over
to CBS SI for further migration, support and management.
Our understanding is that The Hardware will be
procured, Installed, configured and will then be
handed over to the bidder. The bidder's scope
will be restricted to ongoing management of the
system. Please confirm
As per RFP
6 21 3.2 The Bidder shall be responsible for end to end migration of UBS, FEBA, Fircosoft and
allied applications from existing hardware to new hardware setup.
Bidder responsibiliy will be coordinating,
providing inputs to the hardware OEM and
escalting to Bank for any issues. Please confirm
As per RFP
7 21 3.2 Bank may opt for version migration of Finacle to the next higher version (Latest version
to be released by M/s Infosys) . Bidder shall provide the necessary solution design of the
latest version and perform the version migration Bidder shall quote the price in the
relevant section of the price schedule (6.3 part 1 3). The version migration would be done
as per discretion of Bank.
Any version migration of Finacle to newer
version has to be planned and provided in
consultation with OEM only . All solution
design/architecture/new technology decisions of
new versions will be sole discretion of the OEM.
We cannot ascertain this price at the moment as
OEM cannot provide the same. Request you to
remove this clause
As per RFP
8 22 3.2 v. UAT Setup for Universal banking, e-banking, Fircosoft and other allied applications-
The bidder shall implement the new UAT setup of all Universal Banking, e-banking,
Fircosoft and other applications as mentioned above. UAT Servers shall be segregated
and should be in different Network VLAN Segment. Post implementation, bidder shall
manage and maintain the same for entire period of contract.
Our understanding is that The Hardware will be
procured, Installed, configured and will then be
handed over to the bidder. The bidder's scope
will be restricted to ongoing management of the
system. Please confirm
As per RFP
REPLY TO PRE-BID QUERIES
RFP Ref: BOI:HO:IT:RFP:CBS:SI:1684 dated 07/05/2021
9 General 3.2 Implementation of Hardware The hardware deployment requires involvement
of OEM and cannot be done by the bidder alone.
The bidder can assist to share the information
required basis inputs from application OEM. The
technology/solution that bank is going to procure
is also unknown at this time. Request Bank to
remove the installation scope of hardware from
bidder's scope
As per RFP
10 General 3.2 vi. Sizing/ Growth Projections of Universal Banking Solution, FEBA, Fircosoft and other
allied Solutions -
The bidder shall submit projections on sizing (and Growth in terms of organic, inorganic
and number of transactions as per defined frequency (quarterly and yearly) over the
period of 7 years for the bank.
The sizing for Universal Banking, FEBA,
Fircosoft can be provided by OEM only basis the
growth projection of Bank. Bidder can coordinate
with OEM to get the sizing basis the ATS
agreement between Bank and OEM. Please
confirm if the bank is okay with the approach
As per RFP
11 23 3.2 The bidder should also provide alert/update immediately on requirement in advance
apart from defined frequency in case there is a spur in the transactions volume, i.e.
increase in transaction growth, over and above the projections. The bidder shall do
proactive monitoring and responsible for any outage in applications due to high surge
and for such non-informing to Bank well in time.
Our understanding is that all the Applications are
being monitored in Bank's ITSM tool. Bidder will
be using the tool to monitor and report any
exception. Please confirm
As per RFP. Understanding is
correct. Bidder has to use the tools
provided by the Bank to monitor
and provide the projections.
12 26 3.2 xvi. The bidder shall supply, install, configure, re-configure, manage and support a
solution, along with integration with existing applications (CBS, Fircosoft, FEBA and
Allied Applications) /setup and new applications/setup having following functionalities -
a. End-to-End encryption at application level and for data at rest, data-in-transit from one
application to another application i.e. from Finacle setup to any other application should
be implemented.
b. The bidder should provide necessary encryption and decryption utility/licenses
(perpetual) for the same which should support latest encryption algorithms.
Our understanding is that Bank has all the
licesnes for encryption/decryption of database
and bidder needs to implement the same.
Please confirm
Understanding is correct
13 28 3.2 D. The bidder shall be responsible for resolutions/closing of incidents/service calls
/tickets/alerts reported in various medium/tools. Implementation of Oracle Advance
Security and Active Data Guard Services-
The bidder shall implement the Oracle Advance Security i.e. Oracle Transparent Data
Encryption(TDE), Oracle Data redaction & Oracle Data Masking and Active Data Guard
in Universal Banking Solution, FEBA, Fircosoft and Allied Applications by deputing the
subject matter expert and professionals of modules with robust planning and zero
downtime as per intimation and concurrence from the Bank. The bidder shall ensure no
impact on services during and post implementation of the modules.
The implementation of Oracle Advance Security
i.e. Oracle Transparent Data Encryption(TDE),
Oracle Data redaction & Oracle Data Masking
and Active Data Guard will be subjected to
supportability from the Application OEM.
As per RFP
14 28 3.2 E. Application Services, Support, Administration and Management ii. The
bidder shall install and provide to the Bank all new applications, databases, operating
systems and other software versions, updates and patches as released by the OEM or
its licensors under whatever terminology so long as it relates to the Deliverables and
Services at no additional cost to the Bank. The bidder has to provide all the changes /
modifications / update/enhancement and customizations to the Deliverables required to
comply with any statutory/business/ regulatory requirement or any industry-wide changes
at no additional cost to the Bank.
We will provide all OS only for the new
applications that bidder has to deploy as part of
this RFP. The OS, DB of existing applications is
already available with the Bank and bidder need
not provide the same. Please confirm
As per RFP
15 32 3.2 The Bidder should extend assistance in testing process as and when required by the
Bank. Other types of testing like Integration (System), Unit (program), interface with other
systems, stress, security testing etc. shall be carried out by Bidder. Any necessary
hardware, software, configuration or any other item required to conduct/perform these
testing will be provided by the bidder without any additional cost to bank Bidder shall
implement required quality control measures to ensure that the code is error free before
the programs are moved into production environment. The programs / application should
be optimized for the performance metrics and availability metrics pertaining to various
Applications as stipulated in SLA clause.
Our understanding is that this will be restricted
to customisations that will be done during the
contract. Please confirm
As per RFP
16 36 3.2 The helpdesk should have capacity to handle average 200 (average) tickets logged per
day in Service Manager which may change due to modification as per UBS Support
requirement for end users. The link and router related calls pertaining to the branches
need to be addressed by the help desk in coordination with the Banks’s 3rd party service
providers as Bidder is responsible for monitoring and providing facilities management
services for the same.
Our understanding is that if any
links/routers/other TP related calls land in
helpdesk , then the helpdesk has to route the
calls to the Bank SPOC. Please confirm
As per RFP
17 43 3.3 Bidder shall co-ordinate and schedule all CBS and allied applications maintenance
activities at DC, DRC , Near DR, Local DC DR ( any location outside India)..
Our understanding is that the bidder will provide
support from Central location at Mumbai. Please
confirm
As per RFP
18 43 3.3 Bidder shall ensure permanent removal of any data in any faulty storage media, during
movement outside DC/DR/NR, through techniques like degaussing or any other method
as per Bank’s policy.
Our understanding is that bidder will handover
the media to Bank SPOC for degaussing.
Please confirm
As per RFP
19 43 3.3 The Bidder should ensure that any future upgrades, modifications or enhancements shall
not affect the current working of the licensed software and all current functionality shall
be migrated to the new / enhanced version.
The Applications are already deployed in the
Bank and bidder is not supplying these core
accplications. This cannot be ascertained by
bidder for the existing applications and subject
to OEM policy & approach
As per RFP
20 45 3.3 The Bank will provide the logistic of seating place, IT Service Management Solution, Call
Manager Solution, emails and PSTN landlines.
Our understanding is that Bank will provide the
necessary desktop and headphones for the
helpdesk. Please confirm
As per RFP
21 58 3.3 Media management including, but not limited to, tagging, cross-referencing, storing (both
on-site and off-site), logging, testing, and vaulting in fire proof cabinets.
Maintaining inventory of offsite tapes (at Bengaluru and Mumbai), on requirement.
q. Tape/ LTO library management loading and unloading tapes, etc. as per the scope.
This requires dedicated Backup team at both DC
& DR. Request you to modify the resource
requirement table
As per RFP
22 60 3.3 The service covers all the applications that run on Banks’ servers at DC, DRC and NDR,
Local DC/DR facilities designated by the Bank
Does bank has a NDR setup for the existing
applications. Please confirm
Currently No NDR setup is
available. But, In future Bank may
consider the same.
23 67 3.3 Indicative Structure of Governance Set-up
The bidder shall deploy Incident/Change/ BCP Manager for managing the incidents and
managing the changes as per laid down process.
Incident/Change/BCP manager are separate
skillsets and cannot be clubbed. Request Bank
to ask for a separate resources for this
requirement
As per RFP
24 81 3.3 L1 Helpdesk - 8 FTE The Bank is asking for round the clock helpdesk
and 8 FTE will be less. Request bank to relook
at the resource count
As per RFP
25 82 3.3 Database L1 - 4 The Bank is asking for round the clock Database
L1 and we will need 5 FTE for coverage.
Request bank to relook at the resource count
As per RFP
26 82 3.3 Database L3/Oracle ACS -1 There will be a requirement of Oracle L3
resource from bidder. If the Bank wants a Oracle
ACS resource from OEM request to include the
same additionally
Please Refer Corrigendum-1
27 107 3.3 Operating System Management Team , L1 -3, L2 -1 There are multiple OS that bidder has to support
Windows/UNIX and requires separate skillset.
Request Bank to mention additional resources
for both technologies. T
Please Refer Corrigendum-1
28 107 3.3 Operating System Management Team , L1 -3, L2 -1 Bank is not asked for any L3 resources and will
be required to support other than L2 . Request
you to please add the same
Please Refer Corrigendum-1
29 107 3.3 Middleware Support The Bank is not asked for any Midleware
Support resources if this has to be supported.
Request you to please add the same if support
is required
Please Refer Corrigendum-1
30 146 4.10.8 The maximum response time for a maintenance complaint from the site of installation
(i.e. time required for Supplier’s maintenance engineers to report to the installations after
a request call / fax /e-mail is made or letter is written) shall not exceed 2 (two) hours.
Request this to be changed to 8 hours. This is
the best that is available from any hardware
OEM
As per RFP
31 147 4.11.2 The above technical training has to be conducted within 3 months of signoff and is
exclusive of OEM training that is to be provided every year to the Bank team.
Can you please elaborate the requirement and
signoff of what component.
As per RFP
32 147 4.11.2 The above technical training has to be conducted within 3 months of signoff and is
exclusive of OEM training that is to be provided every year to the Bank team.
Our understanding is that OEM training required
by Bank is for Finacle only. Please confirm
As per RFP
33 151 4.18 Post warranty period, the penalty will be deducted in quarterly FMS/AMC/ATS payment.
In case, the Bank is unable to adjust penalty in FMS/AMC/ATS payment, the Bank at its
discretion may invoke the Performance Bank Guarantee (PBG) to deduct the penalty
amount.
Request you to modify the clause as " Post
warranty period, the penalty will be deducted in
quarterly FMS/AMC/ATS payment. In case, the
Bank is unable to adjust penalty in
FMS/AMC/ATS payment, the Bank at its
discretion may invoke the Performance Bank
Guarantee (PBG) to deduct the penalty amount."
As per RFP
34 152 4.18 xiv. If any critical component of the entire configuration setup is out of service , then the
Bidder & OEM shall either immediately replace the defective unit (with new one) or
replace it at its own cost or provide a standby , on immediate basis, not more than 2
hours , the Bidder should maintain proper inventory of standby components for early
resolution of issues.
Request this to be changed to 8 hours. This is
the best that is available from any hardware
OEM. THe hardware that bidder will supply as
part of this RFP is for non-critical solutions so
this will not impact the overall business
As per RFP
35 154 4.18.2.1 Availability Management of Solutions /Appliance/Products
1 % deduction of monthly contract value for the respective solution/ appliance/ software
for every reduction in uptime by 0.01 % in monthly uptime. Uptime shall be calculated
monthly
Request the penalty to be changed as "1 0.1
% deduction of monthly contract value for the
respective solution/ appliance/ software for
every reduction in uptime by 0.01 % in monthly
uptime. Uptime shall be calculated monthly
As per RFP
36 155 4.18.2.1 Manpower Management
Penalty of Rs. 300 per day & Rs 400 for absence per day for each L1 and L2 resources
respectively in addition to deduction of relevant day’s unit cost of the resource.
● Penalty of Rs. 500 per day for absence per day for L3. resource in addition to
deduction of relevant day’s unit cost of the resource.
Request you to allow 12 days casual leave & 12
days of sick leave in a year for all L1, L2 & L3
resource and no money be detectd in this
scenario
As per RFP
37 156 4.18.2.1 Patching / Security Vulnerability Compliance Management
Penalty of Rs.500 per day for delay in version upgrade of (OS, Server, Solution, protocol
etc.) per day.
Request the penalty to be changed to from per
day to per week for all the SLA under this
heading
As per RFP
38 158 4.18.2.1 Knowledge Management
OEM Health Check
Our understanding is that OEM healt check is
required for data base only. Please confirm
Your understanding is correct
39 162 4.18.2.1 4.18.3.1 Level Classification ; Critical Response and Resolution
(a) Within 10 Minutes in case wherein UBS/CBS/any business applications Database and
services restart is required &
(b) Within 15 minutes for all other cases
The stringent resolution ask is possible only for
database that is in Active- Active RAC cluster.
Request you to confirm whether RAC is
implemented , else request you to change this to
45 minutes as per the Industry standard
As per RFP
40 162 4.18.2.1 Critical - Fircosoft Request you to put this under Key As per RFP
41 162 4.18.2.1 Response time should be 5 Minutes during business and non-business hours
o Within 20 minutes
This is very strigent and request you to relax the
response and resolution timelines
As per RFP
42 170 4.18.3.3
Service Levels
For every deduction of 0.01 % in monthly SLA/ uptime as prescribed below , 1 % of
monthly charges of applicable heads will be deducted for the respective
application/solution/product as mentioned below-
This is very strigent, request you to relax the
same" For every deduction of 0.01 % in monthly
SLA/ uptime as prescribed below , 0.1 % of
monthly charges of applicable heads will be
deducted for the respective
application/solution/product
As per RFP
43 171, 174 4.18.3.3 Critical , Key
Business /Core Banking Application & Systems / Allied Services and Hence the cost of
the Quarter for the below heads divided by 3.
Affected application specific cost heads:
This is a duplication as this is covered in Section
4.18.3 for Allied applications that bidder has to
supply as part of this RFP. Request you to
remove the same
Please Refer corrigendum-1
44 172 4.18.3.3 AVAILABILITY MEASUREMENT TABLE
Following cost heads to be considered:
Our understanding is that in cost reference by "
Application" Bank means "Affected Application
FMS" reference will be taken only. Please
confirm
Please Refer corrigendum-1
45 172 4.18.3.3 AVAILABILITY MEASUREMENT TABLE
Following cost heads to be considered:
Request you to remove PMO Costs from the
cost reference and it be restricted to "
Respective Application + Database + Helpdesk"
only for Finacle
Please Refer corrigendum-1
46 172 4.18.3.3 AVAILABILITY MEASUREMENT TABLE
Following cost heads to be considered:
Request you to remove PMO Costs from the
cost reference and it be restricted to "
Respective Application + Database + Helpdesk"
only for UBS/CBS Components
Please Refer corrigendum-1
47 172 4.18.3.3 Finacle e-Banking Solution (FEBA)
Monthly FMS Charges for Database, Application, FEBA, PMO and Helpdesk
Request you to change this to " Monthly FMS
Charges for Database, Application, FEBA
Support , PMO and Helpdesk
Please Refer corrigendum-1
48 172 4.18.3.3 Online Interface
Following cost heads to be considered:
and Application and PMO
Request you to change this to "Monthly FMS
Charges for Customization/ development team,
Delivery Chanel Team and Application and PMO
Please Refer corrigendum-1
49 173 4.18.3.3 Menus (System / Customized), Reports (System / Customized), Batch Jobs,
Customizations functioning at DC,DR and local DC/DR
Following cost heads to be considered:
Monthly FMS Charges for Database Team, Application Team ,
Customization/Development Team and PMO shall be considered for deduction
Request you to modify the clause as "Following
cost heads to be considered:
Monthly FMS Charges for Database Team,
Application Team , Customization/Development
Team and PMO shall be considered for
deduction"
Please Refer corrigendum-1
50 174 4.18.3.3 Business System & Solutions/Services
All Key Solutions, Setup, Applications as mentioned above
Following cost heads of the specific application to be considered:
o Monthly Cost of Application, Database, PMO and Customisation Team
Request you to remove this as all Availability is
covered in the above section
As per RFP
51 175 4.18.3.4 Performance Measurement - Day - end, month – end, year – end
For default of every 15 minutes i.e. exceeding the defined time window will attract penalty
of:
INR 20,000 for EOD
INR 50,000 for EOM
INR of 10,00,000 for EOQ/EOY.
The penalty is very strigent and request you to
relax the same
As per RFP
52 176 4.18.3.4 System Response Time - End to End response time within the DC (from the Core
Banking Application Servers to the Database Servers and back) should be < 10 ms (milli
seconds) during business hours for OLTP transactions.
Bidder is not sized and supplying the
hardware/Storage/Network, the same is being
procured directly by Bank and request you to
remove this clause
As per RFP
53 176 4.18.3.4 System Utilization – Peak Business Window & System Utilization – Non Peak Business
Window
Bidder is not sized and supplying the
hardware/Storage/Network, the same is being
procured directly by Bank and request you to
remove this clause
As per RFP
54 176 4.18.3.4 Down time for servicing of applications
Following cost heads of the specific application to be considered:
o Monthly Cost of Application, Database and Customisation/ Development Team
Request to change this to " Following cost heads
of the specific application to be considered:
o Monthly Cost of Impacted Application,
Database and Customisation/ Development
Team
As per RFP
55 194 4.18.5 4.18.5 Resource Replacement
If the SI has to replace the resource working on the Bank of India project for any reason,
the SI should make necessary provision to provide the new resource of equivalent or
higher skillset.
If SI fails to make provision or replace, the service credit would be computed at the rate
of 0.5% of the total monthly cost for all the resources of that support category to which
that resource belongs to L1, L2, L3, and Management, for every day of delay/absence.
Total penalty imposed by the Bank under this contract shall not exceed 10% of the order
value (TCO), upon which Bank reserves the right to terminate the Contract within 90 days
from notice to the Vendor.
Request the clause be removed as the Bank will
impose penalty for Absentiesm mentioned in
Section 4.18.2.1 Manpower Management
As per RFP
56 195 4.18.7 4.18.7 On delay in Deployment of FMS
The Bidder shall deploy the required resources as per scope under FMS at Bank
centralized locations within 6 weeks from the date of Purchase order. If the Supplier fails
to deploy the resources within the time period specified in the Contract, the Bank shall,
without prejudice to its other remedies under the Contract, deduct a sum equivalent to
0.5% per week of the total FMS cost for each week or part thereof of delay, until actual
delivery subject to maximum deduction of 10% of the total price of the Facility
Management Support.
Request the clause to be changed to " 4.18.7
On delay in Deployment of FMS
The Bidder shall deploy the required resources
as per scope under FMS at Bank centralized
locations within 6 12 weeks from the date of
Purchase order contract. If the Supplier fails to
deploy the resources within the time period
specified in the Contract, the Bank shall, without
prejudice to its other remedies under the
Contract, deduct a sum equivalent to 0.5% per
week of the total FMS cost for each week or part
thereof of delay, until actual delivery subject to
maximum deduction of 10% of the total price of
the Facility Management Support.
As per RFP
57 232 FORMAT 6.3:
PRICE
SCHEDULE
DRM Solution Please share the Applications for which DRM
solution has to be proposed. Also share
Application wise ( WEB/App/DB/Middleware)
instance details
A per RFP
58 240 FORMAT 6.3:
PRICE
SCHEDULE
Part III
No mention of Middleware Resources in Commercial Format Request you to add the requirement Please Refer Corrigendum-1
59 240 FORMAT 6.3:
PRICE
SCHEDULE
Part III
Finacle OEM Training for Bank users -10 Request you to add the requirement in
Commercial template
As per RFP
60 16 63 172 4.18.3.3
61 18 ii. Finacle e-
Banking
Application-
The bank is also having StarToken NG Solution/Product for domestic and International
Internet Banking Users. The bidder shall do integration of Star Token NG with FEBA and
Universal Banking Solution along with all required interfacing and maintain and monitor
the same time to time so that Internet Banking and other functionalities/modules should
be seamlessly available via StarToken NG Solution.
Please confirm that maintenance and monitoring
of Star Toek NG solution will be limited to
integration from UBS,FEBA only.
Bidder need not provide ATS, L1,L2 support for
Star Token is outside the scope of SI.
Bidders responsibility is restricted
upto integration part only for
startoken solution.
62 20 viii. Fircosoft
Applications :
The Bidder has to develop interfaces (in co-ordination with OEM Support) to integrate
with other Applications. The Bidder shall also require to maintain, support and customize
applications, interfaces as per the bank’s requirement over the period of the contract
Please confirm the SI scope for Fircosoft
applications is limited to L1,L2 support
For L3 and customisation related requirement
the Bidder will coordinate with the OEM , the
same will be part of ATS agreement between
BAnk and OEM. Please confirm if our
understanding is correct
As per RFP. Bidder has to develop
interface for fircosoft solution also.
63 20 viii. Fircosoft
Applications :
The bidder shall address all kind of vulnerabilities as pointed out by the Info Security Cell/
RBI/CERT-In/ statuary/regulatory authorities time to time.
Bidder will resolve the issues that is possible .
However, any OEM related issues will be routed
to them and addressed as part of ATS
arrangment between Bank and OEM.Bidders
role will be coordination and track with the OEM
for resolution. Please confirm
As per RFP
64 22 iv Universal
Banking
Solution(UBS),
FEBA ,
Fircosoft ,
Mobile
Banking
Hardware –
Bank may opt for version migration of Finacle to the next higher version (Latest version
to be released by M/s Infosys) . Bidder shall provide the necessary solution design of the
latest version and perform the version migration Bidder shall quote the price in the
relevant section of the price schedule (6.3 part 1 3). The version migration would be done
as per discretion of Bank.
For major upgrades OEM involvement is
required. It will be difficult to provide any cost for
such migration/upgrade without target version
details.
As per RFP
65 23-26 vii. Interfacing,
Integration and
Support of
Delivery
Channels (
Mobile
Banking, ATM,
Kiosk, Cards,
e-galleries etc
and other
Digital Banking
Channels) -
Overseas centres may introduce above mentioned facilities in Foreign/Overseas centres
In such case SI should be able in installation, integration, monitoring and maintenance
without any extra cost to the Bank.
ur understanding is that SI scope is limited to
any interfaces from UBS,FEBA applications from
DC in India. Any interaction with Local agencies
onsite other than Mumbai will be taken care by
Bank.
As per RFP
66 40 N. ESCROW
Agreement/Arr
angement
The source code will be base source code, customizations and any other enhancements
in the UBS, FEBA and allied applications.
The Escrow agreement will be done once and
source code deposit once during the contract
period as per the standard practice
As per RFP
67 41 3.3 Detailed
Scope of
Facility
Management
Services
Facility Management for all purposes means all Annual Maintenance Contract (AMC),
warranties, ATS (Annual Technical Support) for all applications - UBS, FEBA, Fircosoft
and its allied solutions.
Please confirm, ATS for all applicaions including
UBS,FEBA,Fircosoft and allied application is
directly with bank. Hence not in scope of the
bidder.
ATS of Finacle,FEBA and fircosoft
is direcly with Bank
68 General GBM application name is coming in header of RFP the same need to be corrected to
match to RFP
Our understanding is that GBM scope is not part
of this bid. Please confirm
Please Refer Corrigendum-1
69 25 xiv The Bidder shall provide support to maintain the applications, implementation of new
versions of application/databases and its optimization, customization of new functionality
/ interfaces, implementation of new modules, performance tuning of applications during
the term of the contract without extra cost to bank.
SI scope is maintenance of solution
implemented at Bank and also ATS is with bank
directly by OEM. Request bank to keep
Implementation of new modules and new
version out of scope of this bid as the details are
not available and the effort for the same cannot
be estimated . This will also have OEM
dependency
As per RFP
70 29 E.Application
Services,
Support,
Administration
and
Management
x.The bidder shall use an orchestration tool for starting/stopping and managing the
services/ applications.
Our understanding is that Bank has ITSM tools
that has this functionaility available. Bidder
needs to leverage the same tools only. Please
confirm whether our understanding is correct.
As per RFP
71 3.2 Scope of
Work, Point
A (iv)
21 Bidder has to fulfil the necessary requirement for running all solution / entire setup along
with Hardware. The necessary Hardware along with AMC is being procured separately
and handed over to CBS SI for further migration, support and management.
All the hardware procured by bidder will be
handed over to bank. In this case all the security
components including antivirus/antimalware,
policy compliance, vulnerability scanning etc.,
will be supplied and supported by bank. Please
clarify
As per RFP
72 3.2 Scope of
Work, Point
D
28 The bidder shall be responsible for resolutions/closing of incidents/service calls
/tickets/alerts reported in various medium/tools. Implementation of Oracle Advance
Security and Active Data Guard Services-
Implementation of Oracle TDE requires a key
management solution in place to store the
cryptographic keys. Should bidder propose this
solution or can use the existing key
management solution with the bank? Please
confirm
As per RFP
73 3.2 Scope of
Work, Point
E (xvi)
31 The bidder shall also perform the Integrated Application Security Testing (IAST),
DAST/SAST and Source Code Audit (SCA) of new modules/interfaces/changes/scripting
or change in existing modules as made by the onsite customization/development team.
The bidder should record and submit the necessary reports/ documentation supporting
IAST and SCA for new modules/ customizations/ interfaces/ changes/ scripting or change
in existing modules. These reports should be furnished before auditors at the time of
Audit /IT Thematic examination as per regulatory guidelines.
Bidder understands that bank has a vulnerability
management solution, currently in place. Can
this be leveraged to perform IAST, DAST and
SAST scans by the bidder?
As per RFP
74 4.39
Confidentialit
y, Point 9
208 The Bidder shall provide certificate/assurance from application providers/OEMs that the
application is free from embedded malicious / fraudulent code.
With respect to this point bidder assumes that
submitting Format 6.17 on Page 277 will fulfill
this criteria, no other certificate/assurance is
needed in this case. Please confirm
As per RFP
75 139 4.4.Performan
ce Security /
Performance
Bank
Guarantee
4.4.1.The Selected Bidder shall furnish an unconditional and irrevocable Bank Guarantee
of 3% of the total value of contract, in favor of the Bank, from a scheduled Commercial
Bank / Nationalized bank of India, other than Bank of India, towards performance of the
contract in accordance with the specification and conditions of the bid document and
agreed upon on final bid evaluation.
We request PBG to be submitted for 3% of the
Annual contract value to be renewed annually
for the subsequesnt year value.
As per RFP
76 139 4.4.
Performance
Security /
Performance
Bank
Guarantee
4.7.5 If, any components and/or software fails to pass the acceptance test, the Bidder
shall be given maximum 30 days to rectify the defects and pass the acceptance test;
failing which Bank reserves the right to get the respective component
(Hardware/Software) replaced (replacement to be completed within max 21 days) by the
Bidder at no additional cost to Bank. If replacement is not done by the Bidder, Bank
reserves the right to cancel the order and recall all the payments made by Bank or
invoke performance bank guarantee. No request for extension of period for rectification
of defects will be considered from the SIs. Bank reserves rights in this matter.
Request to change as below
If, any components and/or software fails to pass
the acceptance test, the Bidder shall be given
maximum 30 days to rectify the defects and
pass the acceptance test; failing which Bank
reserves the right to get the respective
component (Hardware/Software) replaced
(replacement to be completed within max 21
days) by the Bidder at no additional cost to
Bank. If replacement is not done by the Bidder,
Bank reserves the right to cancel the order and
recall all the payments made by Bank or invoke
performance bank guarantee. No request for
extension of period for rectification of defects will
be considered from the SIs. Bank reserves
rights in this matter.
As per RFP
77 147 4.13 Prices 4.13.2 The Bidder will pass on to the Bank the benefit of discounts, if any, announced in
respect of the cost of the items for which orders have been placed during the time of
contract period.
Request deletion of this clause As per RFP
78 194 4.18.6
Liquidation
Damages/
Penalty for
delay
If the Supplier fails to deliver any or all of the products and/or systems and/or services
solutions within the time period(s) specified in the Delivery Schedule i.e. within 8 weeks
from the date of Purchase Order or installation within 12 weeks from the date of
Purchase Order, the Bank shall, without prejudice to its other remedies under the
Contract, deduct from the Contract Price, as liquidateddamages, a sum equivalent to 0.5
percent per week or part thereof of Contract Price subject to maximum deduction of 10%
of the total contract value of undelivered services / solution for each week or part thereof
of delay, until actual delivery, installation or performance as per related clauses
mentioned in RFP. Once the maximum deduction is reached, the Bank may consider
termination of the Contract at its discretion.
If the Supplier fails to deliver any or all of the
products and/or systems and/or services
solutions within the time period(s) specified in
the Delivery Schedule i.e. within 8 weeks from
the date of Purchase Order or installation within
12 weeks from the date of Purchase Order, the
Bank shall, without prejudice to its other
remedies under the Contract, deduct from the
Contract Price, as liquidateddamages, a sum
equivalent to 0.5 percent per week or part
thereof of Contract Price the total contract value
of undelivered services / solution subject to
maximum deduction of 10% of the total contract
value of undelivered services / solution for each
week or part thereof of delay, until actual
delivery, installation or performance as per
related clauses mentioned in RFP. Once the
maximum deduction is reached, the Bank may
consider termination of the Contract at its
discretion.
As per RFP
79 4.20
Termination for
Default
4.20.2 In the event the Bank terminates the Contract in whole or in part, it may procure,
up on such terms and in such manner as it deems appropriate, Products and Services
similar to those undelivered, and the Supplier shall be liable to the Bank for any excess
costs for such similar Products or Services. However, the Supplier shall continue
performance of the Contract to the extent not terminated.
We request to modify that Bank shall procure
the services following a similar process for
bidder selection for current scope. Further the
maximum liability of bidder towards the
incremental cost will be 5% of the undelivered
cost.
As per RFP
80 82 4.20
Termination for
Default
Request to include bidder to have right to
terminate/suspension of services in case of non-
payment of bidders invoice upon due date.
As per RFP
81 197 4.23
Termination for
Convenience
The Bank, by written notice sent to the Supplier, may terminate the Contract, in whole or
in part, at any time for its convenience by giving 90 days’ notice. The notice of
termination shall specify that termination is for the Bank’s convenience, the extent to
which performance of the Supplier under the Contract is terminated, and the date upon
which such termination becomes effective.
We request to included Upon termination Bank
will pay the demobilisation charges & termination
charges equivalent to 10% of annual contract
value
As per RFP
82 201 4.28 Taxes
and Duties
4.28.1 The Supplier will be entirely responsible for all applicable taxes, duties, levies,
charges, license fees, road permits, etc. in connection with delivery of products at site
including incidental services and commissioning.
Prices should be excluding GST and will be
invoiced at actual rate applicable on the date of
invoicing.
As per RFP
83 125 4.18.5
Resource
Replacement
If SI fails to make provision or replace, the service credit would be computed at the rate
of 0.5% of the total monthly cost for all the resources of that support category to which
that resource belongs to L1, L2, L3, and Management, for every day of delay/absence.
We request delat penalty of 0.5% per week
should be only on cost of resources not
deployed and to be capped at 10% of total price
of such un deployed resources.
As per RFP
84 126 4.18 SLA,
Uptime &
Liquidation
Damages
Total penalty imposed by the Bank under this contract shall not exceed 10% of the order
value (TCO), upon which Bank reserves the right to terminate the Contract within 90 days
from notice to the Vendor..
We request Total penalty Imposed by under this
contract for any quarter shall not exceed 10% of
the quaterly implied invoice value (AMC + ATS +
FMS) , Bank will reserve the right to terminate
the contract incase the penalty cap is breach for
3 consecutive quarter.
As per RFP
85 126 4.18.7 On
delay in
Deployment of
FMS
The Bidder shall deploy the required resources as per scope under FMS at Bank
centralized locations within 6 weeks from the date of Purchase order. If the Supplier fails
to deploy the resources within the time period specified in the Contract, the Bank shall,
without prejudice to its other remedies under the Contract, deduct a sum equivalent to
0.5% per week of the total FMS cost for each week or part thereof of delay, until actual
delivery subject to maximum deduction of 10% of the total price of the Facility
Management Support.
We request delay penalty of 0.5% per week
should be only on cost of resources not
deployed and to be capped at 10% of total price
of such un deployed resources.
As per RFP
86 199 4.18.8 On
Delay in
completion of
Transition
within 3
months
If the transition is not completed within 3 months, attributed to new System Integrator as
per bank’s understanding, Liquidated Damages will be applicable , a sum equivalent to
0.5% of the total transition cost for each week or part thereof of delay, until actual
delivery subject to maximum deduction of 10% of the total price of the Facility
Management Support.
we request to change as below
If the transition is not completed within 3
months, attributed to new System Integrator as
per bank’s understanding, Liquidated Damages
will be applicable , a sum equivalent to 0.5% of
the total transition cost for each week or part
thereof of delay, until actual delivery subject to
maximum deduction of 10% of the total price of
the Facility Management Support Transiton.
As per RFP
87 196 4.19 Payment
Schedule
i. Payment of
Solution/Applia
nce Cost-
a. On delivery- 40% payment of solution/ Appliance cost upon complete delivery of
appliance at BOI DC ,DR and Local DC-DR Site (for licenses, software, application,
allocation of licenses in the name of Bank) as per Bill of Materials. The payment for
partial delivery shall not be made.
b. On commissioning / Implementation/ Integration of the solution/Appliance - 50% of
Solution/ Appliance Cost/ Implementation Cost on successful commissioning of the
solution at BOI DC,BOI DR and Local DC-DR site and integration with all UBS, FEBA,
Fircosoft and allied applications with full high availability and redundancy at both the sites
and its acceptance from Bank team.
c. On sign off- 10% after successful deployment of the solution /Appliance along with all
licenses in Production and its acceptance & signoff from the Bank.
We request ammend as follow:
a. On delivery- 50% payment of solution/
Appliance cost upon complete delivery of
appliance at BOI DC ,DR and Local DC-DR Site
(for licenses, software, application, allocation of
licenses in the name of Bank) as per Bill of
Materials. The payment for partial delivery shall
not be made.
b. On commissioning / Implementation/
Integration of the solution/Appliance - 50% of
Solution/ Appliance Cost/ Implementation Cost
on successful commissioning of the solution at
BOI DC,BOI DR and Local DC-DR site and
integration with all UBS, FEBA, Fircosoft and
allied applications with full high availability and
redundancy at both the sites and its acceptance
from Bank team.
As per RFP
88 196 4.19 Payment
Schedule
i. Payment of
Solution/Applia
nce Cost-
a. On delivery- 40% payment of solution/ Appliance cost upon complete delivery of
appliance at BOI DC ,DR and Local DC-DR Site (for licenses, software, application,
allocation of licenses in the name of Bank) as per Bill of Materials. The payment for
partial delivery shall not be made.
b. On commissioning / Implementation/ Integration of the solution/Appliance - 50% of
Solution/ Appliance Cost/ Implementation Cost on successful commissioning of the
solution at BOI DC,BOI DR and Local DC-DR site and integration with all UBS, FEBA,
Fircosoft and allied applications with full high availability and redundancy at both the sites
and its acceptance from Bank team.
c. On sign off- 10% after successful deployment of the solution /Appliance along with all
licenses in Production and its acceptance & signoff from the Bank.
Please clarify that this will also include payment
of the implementation of these solutions.
As per RFP
89 196 C. Payment of
FMS
i. The Facility Management charges shall be paid by the bank in equal quarterly
instalments in arrears within thirty (30) days from the date submission of invoice after
completion of respective quarterly period after deducting the applicable pro-rata amount
of absent / deficit resources. The payment will be subjected to satisfactory services
rendered from the date of commencement of services and acceptance of the support
system at the rates quoted in the price schedule.
We request as below
i. The Facility Management charges shall be
paid by the bank in equal quarterly Monthly
instalments in arrears within thirty (30) days from
the date submission of invoice after completion
of respective quarterly Monthly period after
deducting the applicable pro-rata amount of
absent / deficit resources. The payment will be
subjected to satisfactory services rendered from
the date of commencement of services and
acceptance of the support system at the rates
quoted in the price schedule.
As per RFP
90 214 C. Payment of
AMC/ATS
i. The AMC/ATS charges shall be paid by the bank quarterly in arrears within thirty (30)
days from the date submission of invoice with adequate and correct / undisputed
supporting documents and after deducting the applicable penalty.
We request changes as below:
i. The AMC/ATS charges shall be paid by the
bank quarterly in arrears annually in advajce
within thirty (30) days from the date submission
of invoice with adequate and correct /
undisputed supporting documents and after
deducting the applicable penalty.
As per RFP
91 196 4.19 Payment
Schedule
request to include that all bidder invoices to be
be paid with 30 days of invoice date
As per RFP
92 40 3.2 Scope of
Work
N. ESCROW Agreement/Arrangement The selected bidder has to arrange and facilitate
into ESCROW Agreement along with OEM for depositing original source code into a
mutually agreed third party vendor for safe keeping of source code for the entire duration
of contract. The source code will be base source code, customizations and any other
enhancements in the UBS, FEBA and allied applications. The cost /expenses of
arrangement for operating of the account with for ESVROW agreement shall be borne by
Bidder
1) The Escrow Account shall be only for
Application software supplied by Third Party
OEM subject to their agreement
2) The cost of Escrow shall be borne by the
Bank
3) Source code for the customization shall be
uploaded on the Bank's repository server as
mutually agreed
As per RFP
93 126 Bid Security 3.17.7 The Bid security may be forfeited: a) If a the Bidder withdraws its Bid during the
period of Bid validity specified by the Bidder on the Bid Form; or b) If a the Bidder makes
any statement or encloses any form which turns out to be false / incorrect at any time
prior to signing of Contract; or c) In the case of a successful the Bidder, if the Bidder
fails; (i) To sign the Contract; OR (ii) To furnish Performance Security, as mentioned in
Clause 4.4 herein. OR (iii) To accept of Purchase Orders issued for the items as
mentioned in this RFP Process
3.17.7 The Bid security may be forfeited: a) If a
the Bidder withdraws its Bid during the period of
Bid validity specified by the Bidder on the Bid
Form; or b) If a the Bidder makes any statement
or encloses any form which turns out to be false
/ incorrect at any time prior to signing of
Contract; or c) In the case of a successful the
Bidder, if the Bidder fails; (i) To sign the mutually
agreed Contract; OR (ii) To furnish Performance
Security, as mentioned in Clause 4.4 herein. OR
(iii) To accept of Purchase Orders issued for the
items as mentioned in this RFP Process
As per RFP
94 132 The Recipient unconditionally acknowledges by submitting its response to this RFP
document that it has not relied on any idea, information, statement, representation, or
warranty given in this RFP document
Bidder has submitted the bid based on inputs
given by the bank with respect to its solution
requirements
As per RFP
95 135 3.33 Signing of Contract At the time when the Bank notifies the successful Bidder that its
Bid has been accepted, the Bank will send the Bidder the Contract Draft, incorporating all
terms, conditions of agreements between the parties. The Bank reserves the right to
incorporate additional clauses as per legal and regulatory requirements of the Bank.
At the time when the Bank notifies the
successful bidder that it’s Bid has been
accepted, the Bank will send the bidder the
Contract Form to be mutually agreed as per
format 6.5, incorporating all agreements
between the parties.
As per RFP
96 139 4.3 Patent
Rights/Intellect
ual Property
Rights
4.3.1 In the event of any claim asserted by a third party of infringement of copyright,
patent, trademark, industrial design rights, etc. arising from the use of the products or
any part thereof in India, the Supplier shall act expeditiously to extinguish such claim. If
the Supplier fails to comply and the Bank is required to pay compensation to a third party
resulting from such infringement, the Supplier shall be responsible for the compensation
to claimant including all expenses, court costs and lawyer fees. The Bank will give notice
to the Supplier of such claim, if it is made, without delay. The Supplier shall indemnify the
Bank against all third-party claims of infringement of patent, trademark, intellectual
property, copyrights or industrial design rights arising from use of the Products or any
part thereof
1) Any issues arising out of third party products
or services shall be governed exclusively by the
EULA and support agreement signed directly
between the BOI and the OEM
(2) BOI acknowledges that the ownership of the
Software will always be with the respective
licensors
(3) Bidder claims and represents that it has
obtained appropriate rights to provide the
Deliverables upon the terms and conditions
contained in this Agreement. BOI agrees and
acknowledges that save as expressly provided
in this Agreement, all Intellectual Property Rights
in relation to the Software, Deliverables and any
adaptations, translations and derivative works
thereof whether protectable as a copyright, trade
mark, patent, trade secret design or otherwise,
provided by Bidder during, in connection with or
in relation to fulfilling its obligations under this
Agreement belong to and shall remain a
property of Bidder or its licensor.
(5) All copyrights and other intellectual property
rights existing prior to the "Effective Date" will
belong to the party that owned such rights
immediately prior to the "Effective Date". All
modifications and enhancements to, and
derivative works from, pre-existing intellectual
property rights will belong to the party that
owned such pre-existing intellectual property
rights. Neither party will gain by virtue of this
Agreement any rights of ownership of
copyrights, patents, trade secrets, trademarks or
any other intellectual property rights owned by
the other.
As per RFP
97 143 Acceptance TestThe Bidder and Bank officials shall sign ATP documents after checking all applications
accessibility. Pending completion of acceptance tests, the bank reserves the right to
use the system and such usage shall not be deemed as acceptance of the system
by the selected Bidder
The Bidder and Bank officials shall sign ATP
documents after checking all applications
accessibility. Pending completion of
acceptance tests, the bank reserves the right
to use the system and such usage only for
testing purpose which shall not be deemed
as acceptance of the system by the selected
Bidder. Deemed acceptance shall happen if
Bank uses the system for commercial
purpose
As per RFP
98 146 CTR 4.10.5 If the Supplier, having been notified, fails to remedy the defect(s) within the 2
hours’ time duration from the incident, the Bank may proceed to take such remedial
action as may be necessary, at the Supplier’s risk and expense and without prejudice to
any other rights, which the Bank may have against the supplier under the Contract. The
Bank shall also impose penalty as mentioned in clause for such defects in the solution as
per Clause 4.18. 4.10.6 Please refer to Clause 3 for related scope and Clause 4.18 for
details of uptime required by the Bank.
4.10.5 If the Supplier, having been notified, fails
to remedy the defect(s) within the 6 hours’ time
duration from the incident
As per RFP
99 148 4.14 Change
Orders
4.14.1 The Bank may, at any time, by a written order given to the Supplier, make
changes within the general scope of the Contract in any one or more of the following: (a)
Technical and functional specifications. (b) Services to be provided by the Supplier.
4.14.2 If any such change causes an increase or decrease in the cost of, or the time
required for the Supplier’s performance of any provisions under the Contract, an
equitable adjustment shall be made in the Contract Price or delivery schedule, or both,
and the Contract shall accordingly be amended. Any claims by the Supplier for
adjustment under this clause must be asserted within thirty (30) days from the date of
Supplier’s receipt of the Bank's change order.
Any change in the scope shall undergo through
change management process. The change
requirement will be analyzed and its impact on
the effort, time, and resource will be mutually
discussed.
As per RFP
100 148 4.16 Assignment4.10.5 If the Supplier, having been notified, fails to remedy the defect(s) within the 6
hours’ time duration from the incident
In the event Bank is privatised, the onerous
terms being agreed by the Bidder due to Bank
status as government Bank (Art 12 State) may
need to be re-visited and accordingly mutually
agreed at the time of assignment
As per RFP
101 194 4.18.5
Resource
Replacement
If SI fails to make provision or replace, the service credit would be computed at the rate
of 0.5% of the total monthly cost for all the resources of that support category to
which that resource belongs to L1, L2, L3, and Management, for every day of
delay/absence. Total penalty imposed by the Bank under this contract shall not exceed
10% of the order value (TCO), upon which Bank reserves the right to terminate the
Contract within 90 days from notice to the Vendor.
If SI fails to make provision or replace, the
service credit would be computed at the rate of
0.5% of the related monthly cost for the said
resources of that support category to which that
resource belongs to L1, L2, L3, and
Management, for every day of delay/absence.
Total penalty imposed by the Bank under this
contract shall not exceed 10% of the order value
(TCO), upon which Bank reserves the right to
terminate the Contract within 90 days from
notice to the Vendor.
As per RFP
102 194 4.18.6 Liquidation Damages/ Penalty for delay On Delay in delivery implementation of
the Solution under scope of this RFP: If the Supplier fails to deliver any or all of the
products and/or systems and/or services solutions within the time period(s) specified in
the Delivery Schedule i.e. within 8 weeks from the date of Purchase Order or installation
within 12 weeks from the date of Purchase Order, the Bank shall, without prejudice to its
other remedies under the Contract, deduct from the Contract Price, as liquidated
damages, a sum equivalent to 0.5 percent per week or part thereof of Contract Price
subject to maximum deduction of 10% of the total contract value of undelivered services
/ solution for each week or part thereof of delay, until actual delivery, installation or
performance as per related clauses mentioned in RFP. Once the maximum deduction is
reached, the Bank may consider termination of the Contract at its discretion.
4.16.1 If the Supplier fails to deliver any or all of
the Products or perform the Services within the
time period(s) specified in the Contract, the
Bank shall, without prejudice to its other
remedies under the Contract, deduct from the
Contract Price, as liquidated damages, a sum
equivalent to 0.5 percent per week or part
thereof of the delayed portion of such product
/ services subject to maximum deduction of
10% of the delivery Price of delayed Products
or unperformed services, until actual delivery
or performance. Once the maximum deduction
is reached, the Bank may consider termination
of the Contract.
As per RFP
103 195 4.19 Payment
Schedule
B. i. Payment of Solution/Appliance Payment of Solution/Appliance Cost- All payment will be done within 30 days of
receipt of Invoice
As per RFP
104 197 4.19 Payment
Schedule
C. Payment of AMC/ATS i. The AMC/ATS charges shall be paid by the bank quarterly in
arrears within thirty (30) days from the date submission of invoice with adequate and
correct / undisputed supporting documents and after deducting the applicable penalty.
C. Payment of AMC/ATS i. The AMC/ATS
charges shall be paid by the bank quarterly in
advance within thirty (30) days from the date
submission of invoice with adequate and correct
/ undisputed supporting documents and after
deducting the applicable penalty.
As per RFP
105 197 4.20
Termination for
Default
4.20.1 The Bank, without prejudice to any other remedy for breach of Contract, by a
written notice of default sent to the Supplier, may terminate the Contract in whole or in
part: (a) if the Supplier fails to deliver any or all of the Products and Services, within the
period(s) specified in the Contract, or within any extension thereof granted by the Bank;
OR (b) if the Supplier fails, to perform any other obligation(s) under the Contract.
4.20.2 In the event the Bank terminates the Contract in whole or in part, it may
procure, up on such terms and in such manner as it deems appropriate, Products
and Services similar to those undelivered, and the Supplier shall be liable to the
Bank for any excess costs for such similar Products or Services. However, the
Supplier shall continue performance of the Contract to the extent not terminated.
4.20.1 The Bank, without prejudice to any other
remedy for breach of Contract, by a written
notice of default with 30 days cure period sent to
the Supplier, may terminate the Contract in
whole or in part: (a) if the Supplier fails to deliver
any or all of the Products and Services, within
the period(s) specified in the Contract, or within
any extension thereof granted by the Bank; OR
(b) if the Supplier fails, to perform any other
obligation(s) under the Contract. 4.20.2 In the
event the Bank terminates the Contract in whole
or in part, it may procure, up on such terms and
in such manner as it deems appropriate,
Products and Services similar to those
undelivered, and the Supplier shall be liable to
the Bank for any 10% of the differential excess
costs for such similar Products or Services.
However, the Supplier shall continue
performance of the Contract to the extent not
terminated.
In case of delay or default in payment beyond
60 days, supplier shall have the right to suspend
the services / terminate the contract.
As per RFP
106 198 4.21 Force Majeure 4.21.1 Notwithstanding the provisions of TCC, the Supplier shall not be liable for
forfeiture of its performance security, liquidated damages, or termination for default if and
to the extent that it’s delay in performance or other failure to perform its obligations under
the Contract is the result of an event of Force Majeure. 4.21.2 For purposes of this
clause, “Force Majeure” means an event beyond the control of the Supplier and not
involving the Supplier’s fault or negligence and not foreseeable. Such events may
include, but are not restricted to, acts of the Bank in its sovereign capacity, wars or
revolutions, fires, floods and freight embargoes.
4.20.2 For purposes of this clause, “Force
Majeure” means an event beyond the control of
the Supplier and not involving the Supplier’s
fault or negligence and not foreseeable. Such
events may include, but are not restricted to,
acts of the Bank in its sovereign capacity, wars
or revolutions, fires, floods, epidemics,
pandemics; quarantine restrictions, and freight
embargoes. 4.20.3 If a Force Majeure situation
arises, the Supplier shall promptly notify the
Bank in writing of such condition and the cause
thereof. Unless otherwise directed by the Bank
in writing, the Supplier shall continue to perform
its obligations under the Contract as far as is
reasonably practical, and shall seek all
reasonable alternative means for performance
not prevented by the Force Majeure event
As per RFP
107 198 4.21 Force Majeure4.21.4 If a Force Majeure situation arises, the Supplier shall ensure minimum half of
resources strength for ensuring continuity of critical setup. The bidder shall arrange all
kind of arrangements, conveyance, accommodation and logistics to their resources for
ensuring availability onsite for supporting the operations and continuity of business
operations with no extra cost to the Bank. Failing which, the penalty for non-availability of
resources shall be applicable in case of force majeure too.
In the ongoing Covid-19 situation, due to any
government guidelines / regulations any impact
on service delivery will be mutually resolved
between Bank and EIT. The Bank will provide
EIT all necessary support as may be required
from its side during this period.
As per RFP
108 199 4.23
Termination for
Convenience
The Bank, by written notice sent to the Supplier, may terminate the Contract, in whole or
in part, at any time for its convenience by giving 90 days’ notice. The notice of
termination shall specify that termination is for the Bank’s convenience, the extent to
which performance of the Supplier under the Contract is terminated, and the date upon
which such termination becomes effective.
Bank will accordingly pay mutually agreed exit
fees
As per RFP
109 199 4.24
Resolution of
Disputes
(a) In case of dispute or difference arising between the Bank and the Supplier relating to
any matter arising out of or connected with this agreement, such disputes or difference
shall be settled in accordance with the Arbitration and Conciliation Act, 1996
The arbitration shall be held in accordance with
the Arbitration and Conciliation Act, 1996 or any
statutory modification or re-enactment thereof.
As per RFP
110 201 4.28 Taxes and Duties 4.28.1 The Supplier will be entirely responsible for all applicable taxes, duties, levies,
charges, license fees, road permits, etc. in connection with delivery of products at site
including incidental services and commissioning
Road Permits if any need to be issued by the
Bank wherever as applicable
GST shall be extra by Bank
As per RFP
111 203 4.30 Supplier’s
obligations
The Supplier will abide by the job safety measures prevalent in India and will free the
Bank from all demands or responsibilities arising from accidents or loss of life, the cause
of which is the Supplier’s negligence. The Supplier will pay all indemnities arising from
such incidents and will not hold the Bank responsible or obligated
The Supplier will abide by the job safety
measures prevalent in India and will free the
Bank from all demands or responsibilities arising
from accidents or loss of life, the cause of which
is the Supplier’s negligence. The Supplier will
pay all damges arising from such incidents and
will not hold the Bank responsible or obligated
As per RFP
112 203 4.31 Patent
Rights/Intellect
ual Property
Rights
In the event of any claim asserted by a third party of infringement of trademark, trade
names, copyright, patent, intellectual property rights or industrial design rights arising
from the use of the Products or any part thereof in India, the Supplier shall act
expeditiously to extinguish such claim. If the Supplier fails to comply and the Bank is
required to pay compensation to a third party resulting from such infringement, the
Supplier shall be responsible for the compensation including all expenses, court costs
and lawyer fees. The Bank will give notice to the Supplier of such claim, if it is made,
without delay.
This repeated and need to be deleted at clause
4.3 Page 139
As per RFP
113 205 4.37 Limitation
of Liability
4.37.1 For breach of any obligation mentioned in this agreement, subject to clause
4.37.3, in no event Service Provider shall be liable for damages to the Bank arising under
or in connection with this agreement for an amount exceeding the total Project Cost.
4.37.2 Service Provider will ensure Bank’s data confidentiality and shall be responsible
for liability arising in case of breach of any kind of security and/or leakage of confidential
customer/ Bank’s related information to the extent of loss so caused. 4.37.3 The
limitations set forth herein shall not apply with respect to: i. claims that are the
subject of indemnification pursuant to IPR infringement, ii. damage(s) occasioned by the
gross negligence, fraud or willful misconduct of Service Provider, iii. damage(s)
occasioned by Service Provider for breach of Confidentiality Obligations, iv. when a
dispute is settled by the Court of Law in India, v. loss occasioned by non-
compliance of Statutory or Regulatory Guidelines. 4.37.4 In no event shall either
party be liable for any consequential, incidental, indirect, special or punitive damage, loss
or expenses (including but not limited to business interruption, lost business, lost profits,
or lost savings) nor for any third party claims (other than those set-forth in Clause 4.38)
even if it has been advised of their possible existence.
1) Gross negligence / wilful misconduct need to
be defined
2) Bank need to remove wording related to v.
when a dispute is settled by the Court of Law in
India, v. loss occasioned by non-compliance of
Statutory or Regulatory Guidelines applicable to
Bidder's scope.
As per RFP
114 205 4.38 Indemnity 4.38.1 The Bidder has to Indemnify the Bank, and shall keep indemnified and hold the
Bank harmless from and against any and all losses, liabilities, claims, actions, costs and
expenses (including attorneys' fees) and also relating to and/or resulting from or in any
way arising out of any claim, suit or proceeding brought against the Bank by a third party
as a result of:
1) Indemnity shall be only for 3rd Party Claim
2) Under no circumstances, shall either party be
liable for any indirect, consequential or incident
losses, damages or claims including loss of
profit or business or revenue.
3) The bidder has to Indemnify the Bank, and
shall keep indemnified and hold the Bank
harmless from and against any and all losses,
liabilities, claims, actions, costs and expenses
(including attorneys’ fees) and also relating to
and/or resulting from or in any way arising out of
any claim, suit or proceeding brought against the
Bank by a third party as a result of:
As per RFP
115 206 4.38 Indemnity (c) Breach of any of the material term of this Agreement and/or its Annexures or breach
of any representation or warranty of the Company under this Agreement related to the
scope of the RFP and/or contract, and/or (d) Violation of the Confidentiality obligations by
the Company and/or its officials/employees or any other person employed by them in
connection with the Contract, and/or (e) Any breach of IPR violations by the Company on
material if any supplied by Company.
b) To be deleted: by any statutory/regulatory/
govt. authority and/
c) . Breach of any of the material term of the
Contract /or its Service Level Agreement or
Breach of any of the material terms of this
agreement by their subcontractors, if
subcontracting of any part of this agreement is
permitted by Bank in writing.
As per RFP
116 206 4.38 Indemnity 4.38.3 The Service provider shall indemnify and keep fully and effectively indemnified the
Bank against any fine or penalty levied on the Bank for improper payment of tax for the
reasons attributable to the Service Provider.
This clause need to be mutually discussed.
4.38.3 The Service provider shall indemnify and
keep fully and effectively indemnified the Bank
against any fine or penalty levied on the Bank
for improper payment of tax for the reasons
attributable to the Service Provider.
As per RFP
117 206 4.38 Indemnity 4.38.4 The Service Provider hereby undertakes the responsibility to take all possible
measures, at no additional cost, to avoid or rectify any issues which thereby results in
non-performance of software/ hardware/ deliverables within reasonable time. The Bank
shall report as far as possible all material defects to the Service Provider without undue
delay. The Service Provider also undertakes to co-operate with other service providers
thereby ensuring expected performance covered under scope of work.
This clause need to be removed from Indemnity
and added to scope
As per RFP
118 207 4.39
Confidentiality
4.39.3 The Company agrees to keep in confidence and not disclose to any third party
and all Confidential Information available to the Company and whether such information
is given in writing or oral or visual, and whether such writing is marked to indicate the
claims of ownership and/or secrecy or otherwise.
The Company agrees to keep in confidence and
not disclose to any third party and all
Confidential Information available to the
Company and whether such information is given
in writing or oral or visual, and whether such
writing is marked to indicate the claims of
ownership and/or secrecy or otherwise.
As per RFP
119 207 4.39
Confidentiality
4.39.5 The provisions of this Article shall survive notwithstanding the expiration or
termination of this Agreement for any reason whatsoever
4.39.5 The provisions of this Article shall survive
for additional 2 years after expiry / termination of
the contract
As per RFP
120 208 4.39
Confidentiality
4.39.9 The Bidder shall provide certificate/assurance from application providers/OEMs
that the application is free from embedded malicious / fraudulent code.” 4.39.10 The
Bidder shall ensure that the equipment / application / software being supplied shall be
free from malicious code (Viruses, Trojan, Spyware etc.) and shall be liable for any loss
(information, data, equipment, theft of Intellectual Property Rights, network breach,
sabotage etc.) incurred to the Bank arising due to activation of any such embedded
malware / malicious code. The Bidder shall further supply a certificate to the Bank in the
form Appended herewith. 4.39.11 The Bidder shall ensure that subsequent patch,
hotfixes and upgrades are also free from malicious code. 4.39.12 The Bidder shall abide
by the Corporate Information Security Policy/ other applicable IT Policies of the Bank (as
amended from time to time), which will be shared by the Bank with the Successful Bidder
on need to know basis. The Successful Bidder shall
This clause need to be removed from
Confidentiality and added to scope
As per RFP
121 209 4.39
Confidentiality
ensure that the equipment/application/software supplied under the RFP shall be
compliant with the CISP at all times. 4.39.13 The Bidder shall submit the background
verification and provide the training on information security awareness for their
employees, in the case of deputing them to work in Bank premises. 4.39.14 The Bidder
shall provide the DC/DR/Local DC/DR (at overseas centre) support for the application /
servers hosted on behalf of the Bank and the same to be in line with respect to the
Recovery Time Objective (RTO) and Recovery Point Objective (RPO) of Bank’s
Business Continuity Policy (BCP).
This clause need to be removed from
Confidentiality and added to scope
As per RFP
122 212 4.42
INSPECTION
AND AUDIT
4.42.3 Service Provider further agrees that whenever required by the Bank, it will furnish
all relevant information, records/data to such auditors and/or inspecting officials of the
Bank/ Reserve Bank of India and/or any regulatory authority required for conducting the
audit. The Bank reserves the right to call and/or retain for any relevant material
information / reports including audit or review reports undertaken by the Service Provider
(e.g. financial, internal control and security reviews) and findings made on the Service
Provider in conjunction with the services provided to the Bank.
1) Bidders financial information shall be
excluded from such audit
2) Cost of audit shall be borne by the Bank
As per RFP
123 Bank General
Responsibilitie
s
(1) Bank to set out standard bank dependencies
(2) Bidder suggest adding appropriate relief
event/savings clause to enable Bidder ability to
obtain schedule adjustments or financial relief in
case of delay / inaction attributable to Bank
As per RFP
124 Site Not Ready Wherever installation could not be carried out by
Bidder due to the Bank’s dependencies like Site
not ready etc. even after 30 days beyond the
date of delivery then the payment would be
released, upon Bidder submission of certificate
from location concerned duly signed (with
Bank’s seal affixed) by the Bank Authority
concerned on the Bank’s dependencies like site
is not ready etc. However, in such a case EIT
Services India Pvt. Ltd. has to give an
undertaking to complete installation within a
week of being informed that the site is ready
As per RFP
125 Compliance
with Applicable
Laws of India
1) Bidder shall be responsible for the laws that
are applicable to it in its capacity as a system
integratorion services to the extent that such
requirements relate to the performance of DXC's
obligations under the contract. Such obligations
shall be restricted to Bidder's scope of work.
2) Each Party hereto is solely responsible for
complying with the applicable laws or regulations
as applicable to it, when performing its activities
under or in connection with the signed
Agreement.
3) If any regulatory requirements change during
the Term, the Parties will adjust the Services in
accordance with the Change Control Procedure
to the extent required due to changes in any
regulatory requirements applicable to the BOI’s
business or the Network. Bidder is not providing
any legal, tax, accounting or other professional
advice as part of the Services
As per RFP
126 Deemed
Acceptance
The Acceptance is deemed to be granted in the
following circumstances:
1.Any delay in the License or implementation
milestones which is beyond DXC’s scope and
has dependency on any other 3rd party or Bank
except DXC shall be deemed accepted when
DXC has delivered its portion of service or when
it was originally due whichever is earlier
2.When customer puts equipment into
commercial service prior to issuing the
Acceptance certificate
3.If the customer uses the equipment (if
necessary, with a limited time period such as 2
days) without issuance of the Acceptance
certificate, then customer must accept that
equipment is ready for use
4.Bank would provide signoff for each
deliverable within 5 days from submission of
signoff-document after mutual agreement of
acceptance of deliverable else the same would
be treated as deemed signoff
5.In the event the software is in production for
a period of 5 days, if Go Live is not signed-off, it
is deemed accepted and signed-off.
As per RFP
129 239 Format 6.3:
Price Schedule
Part II
10) Bank at its discretion can terminate the AMC contract in whole or as part thereof with
the Bidder and discontinue the same without citing any reason by giving 90 days’ notice
and applicable amount, on a pro-rata basis, for the service rendered shall be payable.
Request deletion of the clause. As per RFP
130 248 Format 6.4:
Bid Security
Form
. If the Bidder, having been notified of the acceptance of its Bid by the Purchaser during
the period of Bid validity: (a) fails or refuses to execute the Contract Form if required; or
We request the clause to be modified as below:
If the Bidder, having been notified of the
acceptance of its Bid by the Purchaser during
the period of Bid validity: a) fails or refuses to
execute the mutually Contract Form if required;
As per RFP
131 250 Format 6.5:
Contract Form
2. The following documents of Bid No.: BOI:HO:IT:RFP:CBS:SI:1684 dated 07/05/2021
shall be deemed to form and be read and construed as part of this Agreement, viz.: a)
the Bid Form and the Price Schedule submitted by the Bidder; b) the Bill of Material; c)
the Technical Functional Specifications; d) the Terms and Conditions of Contract; e) the
Purchaser's Notification of Award; f) Schedule of Dates, Amounts etc
We request the clause to be modifed as below:
(A detailed contract / agreement between the
Bank and bidder will be executed covering RFP
clauses, Bill of Material, Price, SLA etc ) The
vendor shall execute the contract/ Agreement/
Service Level Agreement (SLA) in the format
devised by the Bank & mutually agreed by
Bidder / Bank.
As per RFP
132 271 Format 6.15:
Compliance
Statement
We certify and agree to abide by all other clauses, terms, conditions and specifications
mentioned in the RFP. Deviations if any
We certify and agree to abide by all other
clauses, terms, conditions and specifications
mentioned in the RFP along with the bid
response. Deviations if any
As per RFP
133 272 Format 6.15:
Compliance
Statement
Note: There should not be any deviations in the solution proposed by the Bidder. Bidder
has to give his response by writing ‘NIL’ in the statement. It shall be deemed that there is
no deviation, irrespective of the fact whether any mention in the bid document anywhere.
Note: There should not be any deviations in the
solution proposed by the Bidder other than the
assumptions as set forth in our bid. Bidder has
to give his response by writing ‘NIL’ in the
statement. It shall be deemed that there is no
deviation, irrespective of the fact whether any
mention in the bid document anywhere.
As per RFP
136 283 Format 6.18:
Pre-Contract
Integrity Pact
5.3 In case of the successful Bidder a clause would also be incorporated in the Article
pertaining to Performance Bond in the Purchase Contract that the provisions of
Sanctions for Violation shall be applicable for forfeiture of Performance Bond in case of a
decision by the BUYER to forfeit the same without assigning any reason for imposing
sanction for violation of this Pact.
Bidder shall issue PBG As per RFP
139 296 Format 6.25:
Unconditional
Acceptance Of
The Terms
&Amp;
Conditions Of
The Rfp
This is to confirm that we unconditionally accept all the terms and conditions as
mentioned in the said RFP including all addendum/amendment/ corrigendum floated for
Bank of India pertaining to this RFP Ref. No. BOI:HO:IT:RFP:CBS:SI:1684 dated
07/05/2021
This is to confirm that we unconditionally accept
all the terms and conditions as mentioned in the
said RFP including all addendum/amendment/
corrigendum floated for Bank of India pertaining
to this RFP Ref. No.
BOI:HO:IT:RFP:CBS:SI:1684 dated 07/05/2021
along with the bid response.
As per RFP
140 304 Format 6.29:
Checklist
Unconditional acceptance of all clauses, terms and conditions of RFP (Format clause
6.25)
Unconditional acceptance of all clauses, terms
and conditions of RFP (Format clause 6.25)
along with the bid response
As per RFP
141 284 Format 6.18:
Pre-Contract
Integrity Pact
(vi) To cancel all or any other Contracts with the Bidder Bidder requests deletion of the clause. As per RFP
1 31 E. Application Services, Support, Administration and Management ->xviii
We understand the testing activities such as
UAT, SIT, Performance Testing to be executed
by System integration for new changes,
updates & Customizations for the applications
defined in the RFP . Please confirm
As per RFP
2 31 E. Application Services, Support, Administration and Management ->xvii
We request to consider involvement of
independent QA vendor by System Integrator
for the defined testing activities such as UAT,
SIT, Performance Testing. Kindly consider as
this helps in providing test assets of various
applications which will accelerate overall
delivery cycle and quality testing without any
bugs.
As per RFP
3 236 FORMAT 6.3: PRICE SCHEDULE
We request to include additional table for
testing resources cost as below
1. Functional Testing - Y1 to Y7- No of resources
Qty(2500 Test cases design & execution)
2. Performance Testing - Y1 to Y7- No of
resources Qty(2500 Concurrency)
As per RFP
4 234 Section-C version migration of Finacle to the next higher version
Finacle CBS migration involves Data migration
as an activity which is complex and time taking
and hence validation of data migration is also a
time taking activity. We recommend to ensure
the validation of data migration using
automated utility and kindly include line time
as " Migration Testing Cost".
As per RFP
5 31 E. Application Services, Support, Administration and Management ->xvii
Considering the duration period as 7 years and
complexity of Finacle CBS, FEBA, Fircosoft and
Allied Services migration and its assurance,
Automation first strategy is recommended to
shorten the implementation duration. We
recommend to include critical functionality test
automation to fast track the engagement.
As per RFP