No Crystal Ball Gazing -...

63
[email protected], @djaa_dja No Crystal Ball Gazing Risk Management & Delivery with Kanban Using qualitative risk assessment & probabilistic forecasting for better business results Devlin Linkoping, March 2013

Transcript of No Crystal Ball Gazing -...

  • [email protected], @djaa_dja

    No Crystal Ball Gazing Risk Management & Delivery with Kanban

    Using qualitative risk assessment &

    probabilistic forecasting for better business

    results

    Devlin Linkoping, March 2013

  • [email protected], @djaa_dja

    Understanding Kanban Systems

  • [email protected], @djaa_dja

    H

    F F

    F F F

    F J

    I

    Pull

    Change Requests

    Kanban are virtual! Backlog

    D

    E

    A

    I

    Engin- eering Ready

    G

    5 Ongoing

    Development Testing

    Done 3 3

    Test Ready

    5

    PTCs

    F

    B

    C Pull

    Pull These are the virtual kanban

    *

    These are the virtual kanban These are the virtual kanban These are the virtual kanban

    The board is a visualization of the workflow process, the work-in-progress and the kanban

    Boards are not required to do Kanban!

    The first system used database triggers to signal pull. There was no board!

    UAT

    Deploy-ment

    Ready ∞ ∞

  • [email protected], @djaa_dja

    Wish to avoid discard after commitment

    Commitment is deferred Backlog

    H

    E

    C A

    I

    Engin- eering Ready

    D

    5 Ongoing

    Development Testing

    Done 3 3

    Test Ready

    5

    Commitment point

    UAT

    Deploy-ment

    Ready ∞ ∞

    F F

    F F F

    F F

    G

    Pull

    Pool of

    Ideas

    Backlog

    Items in the backlog remain optional………………………..

    Items in the backlog remain optional and unprioritized

    We are committing to getting started. We are certain we want to take

    delivery.

  • [email protected], @djaa_dja

    F F

    F F F

    F F

    Specific delivery commitment may be deferred even later

    UAT

    H

    E

    C A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    5 ∞

    Pull

    Ongoing

    Development Testing

    Done 3 3

    Test Ready

    5

    PTCs

    Change Requests

    2nd Commitment

    point*

    Discarded

    I

    We are now committing to a specific deployment and delivery date

    *This may happen earlier if circumstances demand it

    Pool of

    Ideas

  • [email protected], @djaa_dja

    F F

    F F F

    F F

    Replenishment Cadence UAT

    H

    E

    C A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    5 ∞

    Replenishment Ongoing

    Development Testing

    Done 3 3

    Test Ready

    5

    PTCs

    Change Requests

    Discarded

    I

    The frequency of system replenishment should reflect arrival

    rate of new information and the transaction & coordination costs of

    holding a meeting

    Pull

    Frequent replenishment is more agile.

    On-demand replenishment is

    most agile!

    Pool of

    Ideas

  • [email protected], @djaa_dja

    F F

    F F F

    F F

    Delivery Cadence UAT

    H

    E

    C A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    5 ∞

    Delivery Ongoing

    Development Testing

    Done 3 3

    Test Ready

    5

    PTCs

    Change Requests

    Discarded

    I

    The frequency of delivery should reflect the transaction & coordination

    costs of deployment plus costs & tolerance of customer to take delivery

    Pull Deployment buffer size can reduce as frequency of delivery increases

    Frequent deployment is more agile.

    On-demand deployment is

    most agile!

    Pool of

    Ideas

  • [email protected], @djaa_dja

    F F

    F F F

    F F

    Defining Kanban System Lead Time UAT

    H

    E

    C A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    5 ∞

    Pull

    Ongoing

    Development Testing

    Done 3 3

    Test Ready

    5

    PTCs

    Change Requests

    System Lead Time

    The clock starts ticking when we accept the customers order, not when

    it is placed!

    Until then customer orders are merely available options

    Lead time ends when the item reaches the

    first ∞ queue.

    This provides the correct result for Little’s Law and

    visualization on a Cumulative Flow

    Diagram Discarded

    I

    Pool of

    Ideas

  • [email protected], @djaa_dja

    Delivery Rate Lead Time

    WIP =  

    Avg. Lead Time

    Avg. Delivery Rate WIP

    Pool of

    Ideas

    Ready To

    Deploy

    Little’s Law & Cumulative Flow

  • [email protected], @djaa_dja

    F F

    F F F

    F F

    Defining Customer Lead Time UAT

    H

    E

    C A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    5 ∞

    Pull

    Ongoing

    Development Testing

    Done 3 3

    Test Ready

    5

    PTCs

    Change Requests

    Customer Lead Time

    The clock still starts ticking when we accept the customers order, not when

    it is placed!

    Discarded

    I

    Pool of

    Ideas

    Done

    The frequency of delivery cadence will affect customer lead time in

    addition to system capability

  • [email protected], @djaa_dja

    Flow Efficiency

    Done

    Pool of

    Ideas

    F

    H E

    C A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G D

    GY PB

    DE MN

    2 ∞

    P1

    AB

    Lead Time

    Ongoing

    Development Testing

    Done Verification Acceptance 3 3

    Flow efficiency measures the percentage of total lead time is spent actually adding value (or knowledge)

    versus waiting

    Until then customer orders are merely available options

    Waiting Waiting Waiting Working

    Flow efficiency = Work Time x 100%

    Lead Time Flow efficiencies of 2% have been reported*. 5% -> 15% is normal, >

    40% is good!

    * Zsolt Fabok, Lean Agile Scotland, Sep 2012, Lean Kanban France, Oct 2012

    Working

    Multitasking means time spent in working columns is often waiting time

  • [email protected], @djaa_dja

    Observe Lead Time Distribution as an enabler of a Probabilistic Approach to Management

    Lead Time Distribution

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148

    Days

    CRs &

    Bugs

    SLA  expecta+on  of  44  days  with  85%  on-‐+me  

    Mean  of  31  days  

    SLA  expecta+on  of  105  days  with  98  %  on-‐+me  

    This is multi-modal data!

    The work is of two types: Change Requests (new features); and

    Production Defects

    This is multi-modal data!

    The work is of two types: Change Requests (new features); and

    Production Defects

  • [email protected], @djaa_dja

    Filter Lead Time data by Type of Work (and Class of Service) to get Single Mode Distributions

    85%  at  10  days  

    Mean  5  days  

    98%  at  25  days  

    Cha

    nge

    Req

    uest

    s

    Pro

    duct

    ion

    Def

    ects

    85%  at  60  days  

    Mean  50  days  

    98%  at  150  days  

  • [email protected], @djaa_dja

    Lead Time

    Lead Time

    Allocate Capacity to Types of Work

    Done

    Pool of

    Ideas

    F

    H

    E

    C

    A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    GY

    PB DE

    MN

    2 ∞

    P1

    AB

    Separate understanding of Lead Time for each type of work

    Ongoing

    Development Testing

    Done Verification Acceptance 3 3

    Change Requests

    Production Defects

    Separate understanding of Lead Time for each type of work

    4

    3

    Consistent capacity allocation should bring some consistency to delivery rate

    of work of each type

    Consistent capacity allocation should bring more consistency to delivery rate

    of work of each type

  • [email protected], @djaa_dja

    The Optimal Time to Start

    impact  

    When we need it

    85th percentile

    Ideal Start Here

    Commitment point

    If we start too early, we forgo the option and opportunity to do

    something else that may provide value.

    If we start too late we risk incurring

    the cost of delay

    With a 6 in 7 chance of on-time delivery, we can always expedite to

    insure on-time delivery

  • [email protected], @djaa_dja

    Metrics for Kanban Systems

    Cumulative flow integrates demand, WIP, approx. avg. lead time and delivery rate capabilities Lead time histograms show us actual lead time capability Flow efficiency, value versus failure demand (rework), initial quality, and impact of blocking issues are also useful

  • [email protected], @djaa_dja

    Scaling Up (Probabilistic Forecasting)

  • [email protected], @djaa_dja

    Scaling Up - Planning a big project Device Management Ike II Cumulative Flow

    020406080100120140160180200220240

    10-Feb

    17-Feb

    24-Feb

    2-Mar

    9-Mar

    16-Mar

    23-Mar

    30-Mar

    Time

    Feat

    ures

    Inventory Started Designed Coded Complete

    Slope  in  middle  3.5x  -‐  5x  slope  

    at  ends   5x  

    Required  (local  average)  delivery  rate  

    2006   2008  

    During  the  middle  60%  of  the  project  schedule  we  need  Throughput  (velocity)  to  average  220  features  

    per  month  

  • [email protected], @djaa_dja

    Delivery Rate Lead Time

    WIP =  

    Little’s Law

    From observed capability

    Treat as a fixed

    variable

    Target to

    achieve plan

    Calculated based on known lead time

    capability & required delivery rate

    Determines staffing level

    Changing the WIP limit without maintaining the staffing level ratio represents a change to the way of

    working. It is a change to the process and will produce a change in the

    observed ‘common cause’ capability of the system

    Plan based on currently observed capability and current working practices. Do not assume process improvements.

    If changing WIP to reduce undesirable

    effects (e.g. multitasking), get new sample data (perform a spike) to observe

    the new capability

  • [email protected], @djaa_dja

    55/week 0.4 weeks

    WIP = 22 =  

    Using Little’s Law

    From observed capability

    Treat as a fixed

    variable

    Target to

    achieve plan

    Calculated based on known lead time

    capability & required delivery rate

    Determines staffing level

    At this point perhaps just a little black magic and experience may be required.

    Rounding 22 up to 25 would

    conveniently provide for 5 teams with a WIP limit of 5 items each

    If our current working practices/process exhibited an average WIP of 1 item per

    person then we require 25 people organized in 5 teams of 5 people to

    complete the project on-time

  • [email protected], @djaa_dja

    1 lane per team

    2-tiered board Kanban System within a Kanban System

  • [email protected], @djaa_dja

    Lead time

    WIP in this area should be 25 items*

    *photo taken early in the project before it

    was fully staffed/loaded

    Median lead time target is 2 days

    Alert managers if beyond 5 days

  • [email protected], @djaa_dja

    Risks & Qualitative Assessment

  • [email protected], @djaa_dja

    A Lean approach to alignment with business risks uses Qualitative Assessment

    But how do we determine the risks in a work item that we must manage? We need a fast, cheap, accurate, consensus forming

    approach to risk assessment. We need Lean Risk Assessment!

    The answer is to use a set of qualitative methods to assess different dimensions of risk such as urgency

  • [email protected], @djaa_dja

    Sketch market payoff function R

    oom

    nig

    hts

    sold

    per

    day

    Actual rooms sold

    Cost of delay

    Estimated additional rooms sold

    When we need it When it arrived

    Cost of delay for an online Easter holiday marketing promotion is difference in integral between the two curves

    time

  • [email protected], @djaa_dja

    Cost of Delay based on Market Payoff Sketches

    Cost of delay function for an online Easter holiday marketing campaign delayed by 1 month from mid-January (based on diff of 2 integrals on previous slide)

    Treat  as  a  Standard  Class  item  

    2me  

    impa

    ct  

    Total cost of delay

  • [email protected], @djaa_dja

    Establish urgency by qualitative matching of cost of delay sketches

    +me  

    impact  

    +me  

    +me  

    +me  

    impact  

    impact  

    impact  

    +me  

    impact  

    +me  

    impact  

    impact  

    Expedite – critical and immediate cost of delay; can exceed kanban limits (bumps other work)

    Fixed date – cost of delay goes up significantly after deadline; Start early enough & dynamically prioritize to insure on-time delivery

    Standard - cost of delay is shallow but accelerates before leveling out; provide a reasonable lead-time expectation

    Intangible – cost of delay may be significant but is not incurred until much later; important but not urgent

    +me  

  • [email protected], @djaa_dja

    Cost of Delay has a 2nd Dimension

    +me  

    impact  

    +me  

    impact  

    +me  

    impact  

    impact  

    Extinction Level Event – a short delay will completely deplete the working capital of the business

    Major Capital – the cost of delay is such that a major initiative or project will be lost from next year’s portfolio or additional capital will need to be raised to fund it

    Discretionary Spending – departmental budgets may be cut as a result or our business misses its profit forecasts

    Intangible – delay causes embarrassment, loss of political capital, affects brand equity, mindshare, customer confidence, etc

    +me  

    ?

    Working  capital  

    Working  capital  

  • [email protected], @djaa_dja

    Risk is a multi-dimensional problem

    So understanding cost of delay enables us to know what to pull next? Yes, however, it isn’t always relevant! Cost of delay

    attaches to a deliverable item. What if that item is large? Whole projects, minimum marketable features (MMFs) or minimum viable products (MVPs) consist of many smaller items. We need to understand the risks in those smaller

    items too, if we are to know how to schedule work, replenish our system and make pull decisions wisely

  • [email protected], @djaa_dja

    Market Risk of Change

    Mar

    ket R

    isk

    Sche

    dulin

    g

    Highly likely to change

    Highly unlikely to

    change

    Start Early

    Start Late

    Differentiators

    Spoilers

    Table Stakes

    Cost Reducers

    Potential Value Profits

    Market Share etc

    Regulatory Changes

    Buy (COTS) Rent (SaaS)

    Build (as rapidly as

    possible)

  • [email protected], @djaa_dja

    Product Lifecycle Risk

    Prod

    uct R

    isk

    Inve

    stm

    ent

    Not well understood High demand for innovation &

    experimentation

    Well understood Low demand for

    innovation

    Low

    Low

    Innovative/New

    Major Growth Market

    Cash Cow

    Growth Potential

    High

    Low

    High

  • [email protected], @djaa_dja

    Shelf-Life Risk

    Short (days, weeks,

    months)

    Medium (months, quarters,

    1-2 years)

    Long (years, decades)

    Known Expiry Date,

    Seasonal (fixed window of

    opportunity)

    Fashion Craze Fad

  • [email protected], @djaa_dja

    Shelf-Life Risk

    Sche

    dule

    Ris

    k

    Short (days, weeks,

    months)

    Medium (months, quarters,

    1-2 years)

    Long (years, decades)

    High

    Low

    Known Expiry Date,

    Seasonal (fixed window of

    opportunity)

    Fashion Craze Fad

    Inno

    vatio

    n High

    Low

    Num

    ber o

    f Opt

    ions

    Many

    Few

  • [email protected], @djaa_dja

    Shelf-Life Risk

    Diff

    eren

    tiato

    r

    Short (days, weeks,

    months)

    Medium (months, quarters, 1-2 years)

    Long (years,

    decades)

    Low

    Low

    Known Expiry Date,

    Seasonal (window of opportunity)

    Fashion Craze Fad

    Inno

    vatio

    n

    High

    Low

    Num

    ber o

    f Opt

    ions

    Many

    Few

    Spoi

    ler/F

    ollo

    wer

    High

    Low

    Schedule Risk

    If we are market leading our innovations are less time critical

  • [email protected], @djaa_dja

    Risk is a multi-dimensional contextual problem

    These are just useful examples!

    We must develop a set of risk taxonomies that work in context for a

    specific business.

    We can easily envisage other risk dimensions such as technical risk, vendor dependency risk, organizational

    maturity risk and so forth.

    It may be necessary to run a workshop with stakeholders to explore and expose the real business risks requiring

    management

  • [email protected], @djaa_dja

    (Just a taste of) Risk Management with Kanban

  • [email protected], @djaa_dja

    How much risk do you want to take?

    Given our current capabilities, our desired strategic position and go-to-

    market strategies, how much risk do you want to take?

    We only have capacity to do so much work. How we allocate that capacity across different risk dimensions will

    determine how aggressive we are being from a risk management perspective.

    The more aggressive we are in allocating capacity to

    riskier work items the less likely it is that the outcome will match our expectations

  • [email protected], @djaa_dja

    Hedge Delivery Risk by allocating capacity in the kanban system

    Done

    F H

    E

    C

    A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    GY

    PB MN

    2 ∞

    P1 AB

    Ongoing

    Development Testing

    Done Verification Acceptance 3 3

    Expedite 1

    3

    Fixed Date

    Standard

    Intangible

    2

    3 DE

  • [email protected], @djaa_dja

    Aligning with Strategic Position or Go-to-Market Strategy

    Done

    F

    H

    E

    C

    A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    GY

    PB MN

    2 ∞

    P1 AB

    Ongoing

    Development Testing

    Done Verification Acceptance 3 3

    Table Stakes 3

    1

    Cost Reducers

    Spoilers

    Differentiators

    2

    1 DE

    DA

    The concept of a minimum viable product (MVP) will contain the table

    stakes for at least 1 market niche Market segmentation can be used to narrow the

    necessary table stakes for any given market niche! Enabling early delivery for narrower markets but

    potentially including value generating differentiating features

  • [email protected], @djaa_dja

    Trade off growing market reach against growing share & profit within a niche

    Done

    F

    H

    E

    C

    A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    GY

    PB MN

    2 ∞

    P1 AB

    Ongoing

    Development Testing

    Done Verification Acceptance 3 3

    Table Stakes 3

    1

    Cost Reducers

    Spoilers

    Differentiators

    2

    1 DE

    DA

    It is important to define a MVP in terms of table stakes and differentiators required to enter a specific market

    segment

    Capacity allocated to Table Stakes will determine how fast new niches can be developed.

    Allocate more to Table Stakes to speed market reach/

    breadth.

    Allocate more to differentiators to grow market share or profit margins

    Allocate more to spoilers to defend market share

  • [email protected], @djaa_dja

    An underlying philosophy of pragmatism

  • [email protected], @djaa_dja

    Some simple rules to improve delivery forecasting

    1.  Limit WIP 2.  Observe what really happens in your own

    environment 3.  Measure current system capability as lead

    time distribution, throughput rate and flow efficiency

    4.  Forecast Probabilistically

    Assume that the past is a strong predictor of the future

    In low flow efficiency systems, environmental conditions (system factors) outweigh technical performance factors

    by up to 20 times in determining the outcome. If the environment isn’t changing neither should results.

  • [email protected], @djaa_dja

    Prediction based on qualitative risk assessment

    Stop Crystal Ball Gazing!

    Do not speculate!

    Do not “estimate” the size, weight, complexity of an

    item. Instead qualitatively assess the risks inherent in

    a work item

  • [email protected], @djaa_dja

    Some simple rules to improve risk management

    1.  Establish a list of risks that are applicable in your business domain

    2.  Create a qualitative taxonomy of 2 to 6 categories for each dimension of risk

    3.  Work with things that can be established by consensus as (soft) facts. Do not speculate about the future!

    4.  Use meaningful business language

    Cost of delay, shelf-life, product adoption lifecycle, market risk of change

    All can be established as (soft*) facts. Risks associated with different classifications within these risk dimensions

    are understood and the dynamics of how they might affect an outcome are predictable

    * Where hard facts cannot be established by measurement or market research, a strong consensus opinion is achieved

  • [email protected], @djaa_dja

    Prediction based on qualitative risk assessment

    For example, if we load our entire capacity with fixed delivery date

    demand then it is highly likely that some items will be delivered late and we will incur a (significant)

    cost of delay

  • [email protected], @djaa_dja

    Allocate capacity to hedge risks

    5.  Our key strategy to manage risk is to allocate capacity in accordance with our capability, risk tolerance and business risks under management

    6.  Set kanban limits across risk categories

    7.  Allow the kanban to signal what type of risk item to pull next

  • [email protected], @djaa_dja

    Defer Commitment. Banish Backlogs

    8.  Defer Commitment to manage uncertainty

    9.  The Lean concept of “Last Responsible Moment” is at the point of commitment – the point of replenishment

    10. “Backlog” implies committed. Uncommitted items are options. Develop a “pool of ideas”

    When developing options upstream of the commitment point, classify the item for each dimension of risk under

    management.

    A good mix of options, providing choices within each risk category is required. The more risks under management the more options will be required. The greater the min-

    max upstream kanban limits will need to be

  • [email protected], @djaa_dja

    Abandon Prioritization. Banish Priority

    11. Prioritization is waste!

    Prioritization is an exercise to schedule a sequence of items at a specific point in time. Only at the point of commitment can a proper assessment be made of what to pull next. Filter options based on kanban signals. Select from filtered subset

    Priority is a proxy variable for real business risk information.

    Do not mask risk behind a proxy. Enable better

    governance and better decision making by exposing the business risks under management throughout the

    workflow

  • [email protected], @djaa_dja

    Abandon Formulas & Calculations

    12. Do not try to give relative weight to risk categories or calculate a risk number using a formula

    Weightings and formulas mask real risk information and may lead us to unbalanced, misallocated capacity and poor risk management decisions

    Without a formula calculating a priority should be impossible!

    Embrace the idea that formulas and proxy variables such

    as “priority” have no place in sound risk management decision making

    Transparently expose business risks throughout the

    system

  • [email protected], @djaa_dja

    Visualize Risks on the Ticket

    Title

    Checkboxes… risk 1 risk 2 risk 3 risk 4

    req

    com

    plet

    e

    Color of the ticket

    Typically used to indicated

    technical or skillset risks

    H

    Decorators

    Letter

    SLA or Target Date

    Business risk visualization

    highlighted in green

  • [email protected], @djaa_dja

    Visualize Risks on the Board

    Done

    F H

    E

    C

    A

    I

    Engin- eering Ready

    Deploy-ment

    Ready

    G

    D

    GY

    PB MN

    2 ∞

    P1 AB

    Ongoing

    Development Testing

    Done Verification Acceptance 3 3

    Expedite 1

    3

    Fixed Date

    Standard

    Intangible

    2

    3 DE

  • [email protected], @djaa_dja

    Conclusions

  • [email protected], @djaa_dja

    Focus on Sources of Delay

    In low flow efficiency systems, focusing on sources of delay – queues, blocking issues, rework, provides high leverage improvement

    in observed capability Lead time performance is strongly biased to

    environmental factors, not technical capabilities

  • [email protected], @djaa_dja

    Forecast Probabilistically

    Use observed capability data!

    Accept that the future is likely to strongly reflect past performance. Use historical

    data to forecast probabilistically

    Abandon Cartesian decomposition and speculative

    attempts to deterministically estimate size, complexity or level

    of effort

  • [email protected], @djaa_dja

    Qualitative Approaches are Lean

    Qualitative approaches to risk assessment are fast, cheap and drive consensus

    There is no crystal ball gazing! Risk

    analysis is not speculative!

    Stop speculating about business value and ROI.

    Instead assess real risks and design kanban systems to

    manage them!

  • [email protected], @djaa_dja

    Kanban enables more predictable delivery and better risk management

    Kanban systems address variability in, and focus attention on improving, flow!

    Kanban enables predictable delivery

    Exploit predictability in delivery with qualitative risk

    management.

    Stop Crystal Ball Gazing!

  • [email protected], @djaa_dja

    Thank you!

  • [email protected], @djaa_dja

    About

    David Anderson is a thought leader in managing effective software teams. He leads a consulting, training and publishing and event planning business dedicated to developing, promoting and implementing sustainable evolutionary approaches for management of knowledge workers.

    He has 30 years experience in the high technology industry starting with computer games in the early 1980’s. He has led software teams delivering superior productivity and quality using innovative agile methods at large companies such as Sprint and Motorola.

    David is the pioneer of the Kanban Method an agile and evolutionary approach to change. His latest book is published in June 2012, Lessons in Agile Management – On the Road to Kanban. David is a founder of the Lean Kanban University, a business dedicated to assuring quality of training in Lean and Kanban for knowledge workers throughout the world.

  • [email protected], @djaa_dja

    Acknowledgements

    Donald Reinertsen directly influenced the adoption of virtual kanban systems and the assessment of cost of delay & shelf-life as criteria for scheduling work into a kanban system. Daniel Vacanti helped with a deeper understanding of Little’s Law and the long term planning approach. Troy Magennis has been inspiring with his work on probabilistic planning, risk management and Monte Carlo simulation. I borrowed the term “Stop Crystal Ball Gazing” from Chris Matts.

  • [email protected], @djaa_dja

    David J Anderson & Associates, Inc.

  • [email protected], @djaa_dja

    Appendix

  • [email protected], @djaa_dja

    Example Distributions

    Sta

    ndar

    d Exp

    edite

    Inta

    ngib

    le

    Fixe

    d D

    ate

  • [email protected], @djaa_dja