Network & Gantt chart

14
Network & Gantt chart Project management (lecture)

description

Network & Gantt chart. Project management ( lecture ). Why to translate a network to a Gantt chart?. Gantt chart is more readily to understood by ‘unskilled’ people. It is especially useful when presenting to the top management. Progress can be easily displayed on it - PowerPoint PPT Presentation

Transcript of Network & Gantt chart

Page 1: Network & Gantt chart

Network & Gantt chart

Project management(lecture)

Page 2: Network & Gantt chart

Why to translate a network to a Gantt chart?

• Gantt chart is more readily to understood by ‘unskilled’ people. It is especially useful when presenting to the top management.

• Progress can be easily displayed on it• Visualise floats and activity times. Effective

explanatory and teaching instrument.• Resource allocation can be performed on it.

Page 3: Network & Gantt chart

Two ways af translating networks into bar chart

• Calculating activity times and loacting these on the bar chart

• Drawing activities directily to a time-scale, using the node numbers ensuring correct relationships (time-scaled network)– AoA type– AoN type

Page 4: Network & Gantt chart

The time-scaled network (AoA)

• Mark activities by nodes (events)• Any dummy must be drawn in as a vertical line

with its head and tail node-labels• Activitiy bars will fall from top-left to bottom-

right. Dependent activities are always lower in the chart.

Page 5: Network & Gantt chart

The time-scaled network (AoA)

41

3

42

0 10 15 20 25 305

a

b

c

dburst merge

free float

10

0

27

13a7

423

23

c10

315

15

b15

d8

Page 6: Network & Gantt chart

Dummy activities on a time-scaled AoA network

a15

10

0

215

20

4 2525

3 2020

b

20c5

dummy

a

b c

Page 7: Network & Gantt chart

Time-scaled AoN network (example 1)

• Re-draw the first AoA project as an AoN network:

START

0 00

0 00

0

FINISH

20 200

20 200

0

b

0 150

0 1515

0

a

0 76

6 137

0

d

15 200

15 205

0

c

7 170

13 2310

0

• On AoN networks start and finish activities should be created if thereis no single starting/ending activities.

Page 8: Network & Gantt chart

Translate standard AoN to a time-scaled network

0 10 15 20 25 305

FINISH

7 17 23

START

a c

b d

Page 9: Network & Gantt chart

Re-draw the second AoA:

Time-scaled AoN network (example 2)

START

0 00

0 00

0

FINISH

25 250

25 250

0

b

0 200

0 2020

0

a

0 155

5 2015

5

c

20 250

20 255

0

Translate it to a time-scaled network.

Page 10: Network & Gantt chart

Solution

0 10 15 20 25 305

START

a

cb

FINISH

Page 11: Network & Gantt chart

Time-scaled AoN network(individual exercise)

START

0 00

0 00

0

e

10 130

10 133

0

d

2 73

5 105

3

c

2 100

2 108

0

b

0 55

5 105

5

a

0 20

0 22

0

FINISH

13 130

13 130

0

Page 12: Network & Gantt chart

Solution0 10 15 20 25 305

START FINISH

d

b

a c

Page 13: Network & Gantt chart

Reading

• Lockyer – Gordon (2005): Chapter 16

Page 14: Network & Gantt chart

Thank you for the attention