Namma Metro Project Group 3

download Namma Metro Project Group 3

of 4

Transcript of Namma Metro Project Group 3

  • 8/13/2019 Namma Metro Project Group 3

    1/4

    Assignment on project scope statement

    Submitted by

    Lovepreet Singh

    Suman Pradhan

    Jillam Praida

  • 8/13/2019 Namma Metro Project Group 3

    2/4

    Namma Metro project

    Namma Metro also known as Bangalore Metro is a metro system for the city ofBangalore, Karnataka, India. The agency responsible for its implementation is the

    Bangalore Metro Rail Corporation Ltd (BMRCL), a joint venture of the Government ofIndia and the Government of Karnataka. The first stretch between Baiyyappanahalli andM.G. Road was inaugurated on 20 October 2011.

    Project Scope Statement

    Project name : Namma metro project phase1

    Project manager : N. Sivasailam was the managing director and the StateGovernment removed N Sivasailam as MD of Namma Metro on 10 August 2013.He was replaced by Pradeep Singh Kharola.

    Project goal and objective : The main objective of the namma metro projectis to provide mass rapid transit services to people.

    Deliverables : Phase 1

    East West corridor ---------------18.10 kms

    North-South corridor--------------- 24.20 kms

    Total------------------------------------- 42.30 kms

    Stations

    Elevated Stations------------------------ 33

    Underground Stations ------------------7

    Total-----------------------------------------40

  • 8/13/2019 Namma Metro Project Group 3

    3/4

    Key mile stone

    Till today they have only completed the reach-1 of the project .so this is the onlymilestone for this project

    Reach Terminals Opening date

    Reach-1 (east) Baiyyappanahalli M.G. Road 20 October 2011

    Assumption and constraints:

    Constraints: Allowing free flow of vehicular traffic on the already congestedalong with chosen alignment, Paucity availability of land, Problems topedestrians, Problems to existing residents.

    Assumption: First assumption was that the project was scheduled to start in2005 but was delayed by a February 2006 due to change of government inKarnataka and continued debate over whether the project was financiallyfeasible and appropriate for the city. The cost for the phase 1 was assumed tobe INR 54 billion and later revised to INR 116 billion.

    Phase I spans a length of 42.3 km and consists of 2 lines: Implementation ofPhase I has been divided into 4 "reaches" and 2 underground sections. Theschedule for completion of Phase I is assumed as follows:

    Reach Terminals Opening date Reach-1 (east) Baiyyappanahalli M.G. Road 20 October 2011Reach-2 (west) Mysore Road Magadi Road End of 2013 (Dependency on E-

    W underground section) Underground UG2

    (east to west)

    M.G. Road Magadi Road End of 2013

    Reach-3 (north) Sampige Road Yeshwanthapura November 2013 Reach-3A (north) Yeshwanthapura Peenya

    Industrial AreaNovember 2013

    Reach-3B (north) PeenyaIndustrial Area

    Nagasandra End of 2013

    Underground UG1 Sampige Road National College End of 2014

  • 8/13/2019 Namma Metro Project Group 3

    4/4