Fib Various Types of Structures for Namma Metro

download Fib Various Types of Structures for Namma Metro

of 34

Transcript of Fib Various Types of Structures for Namma Metro

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    1/34

    1

    BANGALORE METRO RAIL PROJECT

    Some Interesting Construction features in Namma MetroViaducts and Stations.

    Sudhir Chandra B.S.Director (Project & Planning), BMRCL.

    INTRODUCTION

    The burgeoning growth of population, vehicular traffic and advent of IT and electronic industries in thelast four decades in Bangalore, reminded the need for a Mass Rapid Transit System (MRTS) inBangalore as far back as in 1983. Several studies were undertaken including a World Bank study in1988. A Light Rail Transit(LRT) system on Public-Private Partnership (PPP), based on a feasibilitystudy by IL &FS, after fixing a private partner was also tried; but it failed to takeoff due to a variety ofreasons. The success of opening a few sections in Delhi by Delhi Metro Rail Corporation (DMRC)resulted in the award of a contract in 2002 to DMRC to make a DPR for a metro system in Bangaloreconsisting of two corridors and costing about Rs.5000 crores. DMRCs report in May 2003recommended two corridors, one East-West corridor from Byappanahalli to Mysore Road terminalupto Ring Road junction, 18.10 kms long and another North-South corridor from Yeshwantpur to RVRoad Terminal 14.90kms long a total length of 33 kms at a completion cost of Rs.4989 crores. GoIapproved the project in May 2006 at a completion cost of Rs.6395 crores meeting out the inflation in

    the intervening period. Equity participation of both governments, GoI and GoK, was equal at 15%each. Total share of GoI was 25% and GoK 30% including subordinate debt and the balance 45%was the senior term debt. Further in 2010, GoI approved extensions of 5.60km on north toNagasandra and 3.70kms on South to Yelachenahlli on North-South corridor at a completion cost ofRs.1763 crores, making the metro net work Phase-1 in Bangalore, 42.30 kms long, at a completioncost of Rs. 8158 crores. On account of phenomenal increase in prices of cement and steel, buildingmaterials -especially sand-and fuel, the estimate was revised and Govt. of India approved the revisedcost of Rs.11609 crores on 4thOctober 2011.(Rs. 1 crore = Rs. 10 millions).

    The Phase-2 of Bangalore Metro, 72.10 kms in length, consists of 61 stations( 49 elevated and 12underground) and the cost of the project is INR 264.05 billion( about 5.0 billion USD) It consists of

    four extensions on the N,S,E & W of N-S and E-W corridors of Phase-1 and two new lines 18.8 kmsand 21.2 kms long. Except for a length of 14 kms, rest 58.1 kms is elevated. The Public InvestmentBoard(PIB) has approved the proposal and the Govt.of India sanction is expected shortly. It isplanned to be completed in 2019.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    2/34

    2

    2. Salient features of the Project:

    Gauge : Standard Gauge(1435mm) double line.

    Design speed : 80 kmphCommercial speed : 34 kmph

    Total length of lines : East-West corridor - 18.10kms

    North-South corridor - 24.20kms

    Total - 42.30kms

    Elevated corridor - 33.50kms

    Underground corridor - 8.80kms.

    Total number of stations : At grade 1 (Byappanahalli)

    Elevated - 32

    Underground - 7(incl. common Majestic interchange station)

    Centre to centre distance of tracks :

    Elevated 4.20m Underground 15.04m (twin tunnels).

    Station platforms:

    Elevated : Side platforms, 4m wide generally.Underground : Island platform, 12 to 16m wide.Sharpest curve (horizontal) : 120m radius in main line in elevated corridor

    200m radius in main line in underground corridor100m radius in depots and yards.

    Maximum cant : 125mmMaximum cant deficiency : 100mmVertical curve radius : 1500 m (min)

    Steepest gradient : 3.3% (permitted 4%)Percentage of curved track : about 40%Rolling stock : Modern rolling stock with Stainless steel body and air

    conditioned automatic closing doors.

    Motored axles - 67%

    Axle load - 15 tonnes

    Class of accommodation - One

    Capacity of 3 car unit 975 Capacity of 6 car unit 2005.

    Size: 20.80 x 2.88 x 3.80m high.

    Maintenance facilities : E-W corridor - Baiyappanahalli depot N-Scorridor - Peenya depot

    Train operations:

    Minimum headway : 3 mins.

    Design Phpdt (peak hour peak direction trips) : 40,100

    Operating hours : 5.00 hrs to 24.00 hrs

    Projected ridership : 19.7 lakhs by 2021

    Financial Internal Rate of Return (FIRR) : 5.46%

    Economic Internal Rate of Return (EIRR) : 24%

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    3/34

    3

    3. Construction features in brief:

    3.1. Viaducts

    Metro corridors are passing through one of the densest areas in Bangalore City. The roads

    are narrow; at times it is hardly 14m wide. Immediately, alongside the road are the utilities

    (water supply pipelines, sewers, communication cables, electric cables, etc) buried hardly

    600mm below the ground. There is storm water drain thereafter with a foot-path on top of it.

    Hugging on to the footpath are the shops or residences with or without setbacks and

    compound walls. When the viaduct pier is located in the centre of the road, the road which is

    already narrow becomes narrower still to the extent of the foot print of the pier. Hence in

    narrow roads, the lateral dimension of the pier had to be kept to the minimum to affect the road

    width least. So design of pier had to be suited accordingly.

    Similarly, the superstructure girders were designed to suit the segmental construction with

    launching girders (overhead and under slung) single cell, box shaped, deck type to support

    both tracks (Up and Down). I girders were used as an exception.

    Typical viaduct structure

    3.2 Elevated Stations:

    Design of elevated stations had to be done depending on the local conditions, road widths, foot

    path widths available, etc. Broadly Station structures designed in Bangalore Metro Project can

    be classified into two categories:

    (i) Cantilever structure - Tracks, platforms & concourses are on single central pier.

    Staircases/Escalators from concourse to platform have been housed in off road

    structure. Station entry is also in off road structure. Off road structures provided are

    connected through linking bridges to the station structure.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    4/34

    4

    (ii) Portal structure- It houses entire station including staircases & escalators fromconcourse to platform. Only station entry staircases/escalators are on footpath or off

    road.

    4. Viaducts Construction details:

    4.1 Nature of foundation Open individual footing,Strip footing,Raft,Pile

    Open /Raft foundations are seldon used as the availability of rock at shallow depths is rare.

    This is also limited to availability of hard strata at depths less than 4 to 5 meters. Beyond this

    depth, pile foundations are adopted. The substrata consist of silty sand, sandy silt,

    disintegrated rock and hard rock (230 to 300 mpa). For Viaduct, pile foundations, circular piles

    of 1200mm dia have been used. The bearing piles capacity is taken as 500t and friction piles

    capacity as 300t to 400t the lateral load capacity is taken as 20 to 28t depending on strata &

    site constraints and conditions.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    5/34

    5

    OPEN FOUNDATION :

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    6/34

    6

    RAFT FOUNDATION :

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    7/34

    7

    STRIP FOOTING :

    PILE FOUNDATION :

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    8/34

    8

    PILES CASTED :

    4.2 Sub structure Pier and Pier cap for Viaduct:

    The pier width of 1.6m is chosen normal to traffic direction to minimize occupation of the road

    foot print and least reduction in the carriageway.

    4.2.1 Elliptical Piers:

    Circular pier is the best shape for a pier- most efficient cross section. But since Bangalore

    metro goes in narrow roads, the lateral dimension of pier should be reduced to have more

    carriageway width. So, in the first reach elliptical pier was designed with the minor axis kept

    square to the road and major axis parallel to the road. Since the pier is elliptical in shape, theshuttering for pier becomes cumbersome, costly and time taking. So in other reaches, it was

    changed to Double-D shape, shutters for which is comparatively easier to make; Pier cap

    shuttering is also not complicated. In the case of elliptical piers the pier cap shuttering is also

    very complicated. All piers are having flutes (serrations) with horizontal bands in between.

    This helps in easy tearing of bills pasted on piers by miscreants.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    9/34

    9

    Elliptical Piers

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    10/34

    10

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    11/34

    11

    Double D Pier:

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    12/34

    12

    4.2.2 Eccentric/ Inverted L-shaped Piers:

    At certain locations, where the piers cannot be placed in the road lanes, as it becomes anobstruction, the piers are placed in the road median and eccentric piers are constructed, ie, the

    box girder centre is eccentric wrt the centre of the pier. However, the maximum eccentricity is

    limited to 1900mm.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    13/34

    13

    4.2.3 Portal Piers:

    Where eccentricity goes beyond 1.80m, eccentric piers are not preferred. But a Portal is

    constructed with two legs and a beam on top to span the legs, which will support the Box

    girder. In such a case, the rail level goes up compared to standard piers/eccentric piers.

    4.2.4. Shuttering used for piers in both the above cases(4.2.2 and 4.2.3) are not interchangeable with

    the standard circular piers shuttering, whereas the Double D pier shuttering are

    interchangeable. Hence, the non-circular pier scores over circular pier in this respect.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    14/34

    14

    4.3 Superstructure for Viaduct

    Single cell, box type, segmental girder has been mostly used on viaducts. They are posttensioned. Blisters are left in 2ndand 3rdsegments for future pristressing, if required.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    15/34

    15

    4.3.1 The standard viaduct span is 28m. Each segment is 3m long except the pier segments (first

    and last which are 1.95m long). The 3m modules when taken out / added in from the standard

    span make the spans 25m, 22m and 31m. On sharp curves (120m radius) shorter spans of

    22m are used as otherwise there is uplift of bearings in larger spans.

    4.3.2 At road junctions or while crossing rail tracks,etc non-standard spans, cast-in-situ, post

    tensioned girders are used viz 41m,50m,66m on Bangalore Metro project. The 66m span only

    one of its kind is on a 136m radius sharp curve crossing electrified railway tracks, a single cell

    box girder, post-tensioned. To prevent uplift of the bearings, vertical prestressing with 96

    strands, 7 ply is being done for both the piers. A dummy hole has also been left in each pier,

    for future use, if need be.

    4.3.3 The viaduct spans are designed as simply supported spans except for those at track cross

    over and turnout locations where the slabs are designed as continuously supported over

    girders.

    4.3.4. Elastomeric bearings have been used for spans upto 31m and POT and PTFE bearings for

    longer spans as well as spans carrying track cross-overs and turnouts.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    16/34

    16

    ELASTOMETRIC ( UPTO 31M SPANS GENERALLY ) :

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    17/34

    17

    POT-PTFE ( FOR SPANS ABOVE 31 M , SHARP CURVES 120M RADIUS ,CROSSOVERS AND TURNOUT

    SPANS)

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    18/34

    18

    5. Elevated stations Construction details:

    There are two types of elevated stations in Bangalore Metro Rail.

    5.1 Cantilever stations:

    There is a central pier carrying the tracks; the concourse and the platforms cantilever out from

    this pier. They are spaced 15 to 20m apart. It has limitations in that the cantilever length is

    limited as otherwise there will be excessive deflections. Also resonance is to be specially

    checked up. But it gives a very sleek and pleasant look. The diversion of utilities is minimized

    in this configuration of stations. The concourse girders are I type (precast, pretensioned/post

    tensioned) or Pi type (precast RCC). There are pier arms at concourse and platform levels to

    support I type or Pi type girders. Platform girders are I type (precast, pretensioned/ post

    tensioned, steel) or Pi type (precast RCC).

    Track girders are I type posttensioned girders (4 nos) or U type pretensioned girders (3 nos).

    U type girders are not suitable in the spans where the d.c. electric traction cables have to bebrought from the track level to the Traction substation in the station building at concourse level

    as there is no space between the girders to puncture hole/slit through the deck slab. Hence,

    in such spans, I-girders have been used as there is enough space available between the top

    flanges of the adjacent girders for hole/slit to be made through the deck slab. They rest on

    elastomeric bearings.

    Roofing is supported on steel trusses. Galvalume sheeting of different colors with

    polycarbonate sheets interspersed for adequate lighting is used. Sides of the platform to the

    extent possible are kept open for good ventilation.

    Station entry to concourse is provided in off road structures.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    19/34

    19

    REACH - 2 (ALL SIX STATIONS): CANTILEVER STATION (EXAMPLE MAGADI ROAD).

    SUPER STRUCTURE FOR TRACK SUPPORT : I GIRDER (POST-TENSIONED)

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    20/34

    20

    PLATFORM LEVEL AND CONCOURSE LEVEL PIER ARM DETAIL :

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    21/34

    21

    SUPERSTRUCTURE CONCOURSE SUPPORT : Pi - GIRDER (PRE-CAST RCC)

    (SUPERSTRUCTURE PLATFORM SUPPORT : Pi GIRDER (PRE-CAST RCC)

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    22/34

    22

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    23/34

    23

    ROOF STRUCTURE STEEL FRAME WITH GALVALUME SHEETING.

    PLATFORMSUPPORT

    TTGIRDERS

    CONCOURSESUPPORT

    TT

    GIRDERS

    DOUBLEDCOLUMNS

    PIERARMSWITHLBEAMS

    SUPPORTTHE

    CONCOURSEGIRDERS

    ANDPLATFORMGIRDERS

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    24/34

    24

    5.2 Portal structure stations:

    Station structure consists of portals, generally three-legged, to span the road widths. The

    other members and components remain more or less the same. Such structures have

    been adopted in reaches R-1, 3b and 4a. The merit of this structure is that it is more stable

    and the internal stair cases & escalators are within the main structure. With such aconfiguration, the land acquisition is minimum at the sides.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    25/34

    25

    SUPER STRUCTURE FOR TRACK SUPPORT: I GIRDER (POST-TENSIONED)

    SUPERSTRUCTURE PLATFORM SUPPORT: I GIRDER (PRE-TENSIONED)

    SUPERSTRUCTURE CONCOURSE SUPPORT : I - GIRDER (PRE-TENSIONED)

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    26/34

    26

    6. Some unique design of Viaduct and Stations.

    6.1 Special Curved span 66m flyover over Electrif ied Railway tracks (Cast-in-si tu):

    The Northern line of Bangalore Metro from Peenya to Sampige Road station flies over theSWR Tumkur electrified main lines at Malleshwaram (Kuvempu Road). It is a skew crossing

    with curvature of 136 mtrs radius. The span across the railway land is 66mtrs. It consists of a

    single cell box girder, post tensioned. Due to the sharp curvature and long span, the outer

    bearings are subject to uplift; replacement of bearings often over running tracks will be

    difficult. To prevent uplift of the bearings, vertical prestressing was thought of in the beginning,

    but was given up considering the durability, the need to have spare arrangements for

    prestressing during service, if the need arises, as very limited periods will be available for

    repairs, retrofitting, etc once the commercial operations are commenced.

    CONCOURSESUPPORTIGIRDER

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    27/34

    27

    Salient Features:

    OVERALL SPAN (C/C OF EXP JT) : 66M

    RADIUS AT CENTRELINE OF ALIGNMENT : 136M

    DEPTH OF THE BOX GIRDER : 4.0 M

    WIDTH OF THE BOX GIRDER AT TOP : 8.8 M

    WIDTH OF THE BOX GIRDER AT BOTTOM : 3.6 M

    TYPE OF BEARING PROPOSED :POT-CUM-PTFE

    MAX. NO OF AXLES ON THE SPANS : 13 AXLES / TRACK (OF 15 TONS)

    TOTAL NO OF PRESTRESSING CABLES (LONG.) : 24 NOS OF 19 T 15

    TOTAL NO OF VERTICAL PRESTRESS STRANDS : 95 NOS OF 15 DIA

    HEIGHT FROM RAIL LEVEL TO PILE CAP TOP :13.7M (MAX)

    OVERALL HEIGHT OF PIER : 8.82M (MAX)

    PIER SIZE : 4M X 2.5 M

    PIER CAP SIZE AT TOP : 4.9M X 4.5M

    THICKNESS OF PIER CAP : 0.6 M ST + 0.9M VARYING

    NO. OF PILES : 8 & 9NOS RESPECTIVELY.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    28/34

    28

    6.2 Deepanjalinagar Station:

    Deepanjalinagar station is the penultimate station on the Magadi Road-Mysore Road stretch of

    E-W Corridor. The station is sandwiched between the ROB across the Mysore Bangalore SWR

    lines and the National Highway to Mysore. The topography on either side of the station is

    undulating and the formation is in deep cutting. It is also surrounded by three built up areasand an important temple just at the edge of the station which have to be saved and these

    constraints make entire station (three legged portal structure) an indeterminate structure with

    unequal spans. The portals have also unequal legs.

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    29/34

    29

    6.3 Some special features at stations:

    6.3.1 Foundations : Mono Piles:

    At times the extreme rows of columns go very near to the property line making construction of

    multipiles and pile cap construction impossible. Mono piles of higher diameter 1600mm have

    been used (normal piles are 1200mm diameter)

    6.3.2 Floating columns:

    Due to space constraints and shifting of utilities (sewer lines especially) not

    becoming feasible, floating column concept has also been adopted.

    MONOPILES (1600MMDIA)

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    30/34

    30

    6.3.3 Replacement of girders/bearings dur ing maintenance:

    Generally elastomeric bearings are provided for all standard spans and at stations. POT and

    PTFE bearings are provided for special spans greater than 31m and cross over spans. The

    bearings have life of 20-25 years. Bearings have to be replaced in viaduct by lifting girders by

    taking temporary block for train movement. In case of station, replacement of bearings will berequired only on the track girder where trains are moving. This can be replaced by opening the

    rail fastening system and connection to the bearings and refitted after replacement of the

    bearings. Other bearings of the stations at concourse are not subjected to heavy load thus

    unlikely to be replaced.

    6.3.4 Transition spans:

    In the station lengths the track supporting structure is either I-girders or U-girders whereas the

    viaduct in the approaches of the station consists of segmental box girders. Hence the first pier,

    just after the station ends, is a transition pier on which from one side I or U girders of station

    rest and on the other side the segmental box girder rests. As the depths of girders vary, thebearings are at different levels and the pier cap has to be meticulously designed to take care of

    the extra moments due to the couple action. These transition spans are kept normally not

    more than 20m in length.

    FLOATINGCOLUMN

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    31/34

    31

    6.3.5 Electrostatic insu lating membrane:

    As the mode of traction is 750 v dc, to prevent electrocution of passengers while alighting or

    boarding the train (one hand being held against the coach and the foot being on the platform)

    special electrostatic membranes are placed below the floor finish for a width of about 4 meters,

    which acts as an insulating medium.

    7 Stray current protection:

    A special feature of this metro is that since 750V dc third rail system is used, there is the

    problem of stray current corrosion which doesnt arise in other metro systems where AC

    traction is used. We have to guard against it. Special measures have been adopted to

    minimize the corrosion of neighboring utilities, of steel members, rebar of metro structures

    which will otherwise weaken the structure and reduce its life. This has been done by inter

    connecting rebars from the track level to the foundation bottom level of piers, columns, etc so

    that they get earthed.

    MAHATMA GANDHI ROAD STATION:

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    32/34

    32

    SWAMI VIVEKANAND ROAD STATION:

    BYAPPANAHALLI STATION:

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    33/34

    33

    YESHWANTHPUR STATION:

    VIJAYANAGAR STATION:

  • 8/11/2019 Fib Various Types of Structures for Namma Metro

    34/34

    34

    NATIONAL COLLEGE STATION

    Conclusions:

    Stations have been designed passenger -friendly, persons with disabilities- friendly (lifts and

    tactile provision), etc. Bangaloreans, being especially aesthetic loving and connoisseurs, the

    stations have been architecturally designed to give a pleasing look in the Bangalore sky line.

    ------A THING OF BEAUTY IS A JOY FOR EVER-----