General R2E Activities Status Report
description
Transcript of General R2E Activities Status Report
General R2E ActivitiesStatus Report
M. Brugger for the R2E Study Group
30th LMC Meeting, September 30th
Many Thanks for The Continuous SupportEN/MEF, EN/HE, EN/EL, BE/OP, DG/PRJ, DG/SCR,
EN/CV, BE/ABP, TE/ABT , EN/GMS, TE/EPC, FP/PI, BE/ASR, PH/LBD,…
R2E Status Report
Critical Area Overview
2September 30th 2009
Collimation Area(high losses possible at an early stage)
LHCb: reaches early significantradiation levelsInjection & Adjacent Areas:
losses on collimators and dumps on TED
High-Luminosity Experiments(UJs, RRs, possibly UPS)
LHC Tunnel Electronics
R2E Status Report 3
Postulate: Measurements: “Everybody believes in them… except the
person who did the measurement…” Simulations: “Nobody believes in them… except the person
who performed it…” Recommendations: “Everybody argues… including the
person who is giving them … “ Conclusion: … it takes time…
Observation: Every postulate has its flaw...
Lot’s of improvements were implemented…
Let’s Start with an Example
September 30th 2009
R2E Status Report 4
Let’s Start with an Example
September 30th 2009
SHIELDING
additional Monitoring
SHIELDING
R2E Status Report 5
Postulate: Measurements: “Everybody believes in them… except the
person who did the measurement…” Simulations: “Nobody believes in them… except the person
who performed it…” Recommendations: “Everybody argues… including the
person who is giving them … “ Conclusion: … it takes time…
Observation: Every postulate has its flaw...
Lot’s of improvements were implemented… But there is some truth…
Much more work is required
Let’s Start with an Example
September 30th 2009
R2E Status Report 6
Let’s Start with an Example
September 30th 2009
future high radiation
‘bulky’ electronics
limited shieldingoptions
difficult relocation
R2E Status Report
Good News
7September 30th 2009
R2E Status Report
This Presentation Focuses On
The Achievements 8September 30th 2009
R2E Status Report
As a Reminder …
9September 30th 2009
R2E Status Report 10
The R2E Mandate The R2E Study Group forms a small committee consisting of experts in the
various fields related to electronics damage and shall drive other working groups (RADWG). This way the R2E assists LHC operations and equipment groups with expert knowledge and assessments of radiation-induced failures in electronics of the accelerator, as well as directly coordinates studies of remedial actions:
Immediate propose and evaluate short-term measures to reduce failure risks conduct simulations studies to evaluate radiation fields establish, extend and evaluate the inventory of information needed
to assess radiation-induced electronics failures ensure accurate monitoring of radiation fields in critical areas to
evaluate risks of electronics failures advice on planned CNGS irradiation tests, including calculations commission and evaluate machine studies to understand the
possibility of reducing/displacing losses
Long-Term coordinate studies of radiation-induced failures, including calculations
and proposals of solutions, and complement the inventory with measured data and experience gained during operation
advice on further dedicated irradiation tests, including calculations assist LHC operations and concerned groups in the identification and
short-term mitigation of failures
Prioritization
Inventory
Short-Term
TestingMonitoring
CoordinationLong-Term
Mid-Term
September 30th 2009
R2E Status Report 11
R2E Structure1. Policy for Electronics
installed in areas with elevated radiation levels (R2E)
2. Evaluation of Radiation Levels: simulations, monitoring, proposal of measures and general coordination (R2E)
3. Structure to implement the Policy (RadWG)
4. Organization and Analysis of Radiation Tests (RadWG)
5. Control (LHC Point-Owners)
R2E
RadWG
Point-Owners
Equipment Owners
Installations
Testing
Monitoring
Electronics Policy
LHC Machine Committee
September 30th 2009
R2E Steps ( first part of 2009) Part 1 Priority List of Areas based on available Monte-Carlo simulations linked to operational assumption for the various ‘years’
Update and detailed analysis of Simulations Collection of existing simulations Launch of new simulation effort clear identification of critical areas and respective radiation levels (over time!)
Relocation/Replacement of equipment from UX85 work completed
Preparation of TZ76 and displacement of equipment in UJ76: TZ76 preparation fully integrated infrastructure preparation (cooling,…) done UPS relocation and pre-cabling for PC relocation
Additional shielding UJ76 SafeRoom, RRs, new maze, P6 ducts, not needed holes & penetrations
Prioritization
Inventory
Short-Term
Short-TermandMid/Long-Term
September 30th 2009
12
R2E Status Report
R2E Status Report 13
R2E Steps (2009) Part 2 Detailed Point-Iterations
visit of areas looking into integration options, available monitoring (Etat des Lieux)
Priority List of Equipment (Classes) direct interaction with equipment groups (starting with machine protection)
(!!! to be continued !!!) identified safety related equipments proposal to prepare ‘short-term’ actions (ongoing)
RadWG: organization of radiation tests in CNGS and outside CERN (FIP, QPS, Cryo, Power Converters …) Tests conducted at PSI, Louvain, Prospero, continuous testing in CNGS
Documentation R2E Website (Presentations, Minutes), R2E Library, Picture Gallery of Critical
Areas, Inventory of Monitor, Publications (ECRs, Chamonix, Point-Reviews, …)
Inventory, Monitoring
Prioritization
Testing
Mid-Term
September 30th 2009
R2E Status Report
besides R2E meetings, minutes and presentations @ LMC, Chamonix,… R2E Website: www.cern.ch/r2e Document Database (linked through above):
www.cern.ch/info-r2e-documents Memorandum for possible temporary move betatron cleaning to IR3 UJ76 Relocation (see ECR) R2E Status Report @ Chamonix (see paper) RR73/77 Shielding Improvement (see ECR) Mid/Long-Term Action Plan (see report) R2E Memorandum for Short-Term Resources Power-Converter Summary (see internal report) Point-8 Iteration Summary (see final draft) Point-1/5 Iteration Summary (in preparation) Online Mitigation Project Tracking (see link) R2E Radiation School (see program and summary)
Documentation & Reports
14September 30th 2009
R2E Status Report
Mitigation Project Tracking Tool
15September 30th 2009
list of projects
toggle betweenfinished and ongoing projects
acquire statusreport
check to have all comments- The tool is functional and used in R2E
- Some improvements to be done- Some cosmetics required
R2E Status Report
30.09.2009Status Report
…
16September 30th 2009
R2E Status Report
short-term: minimize the risk of radiation induced electronics failures perform possible relocations (within shutdown constraints) install additional shielding improve monitoring to prepare analysis for early operation
mid-term: operational experience and towards a complete solution prepare (plan for) additional shielding preparations of early relocations
(in case time slots become available or urgent requirements) finalize equipment inventory prepare integration studies (full relocations, alternative solutions)
long-term: implement subsequently the chosen solution, new policy and continuous follow-up based on early measurements, decision/integration on long-term
solution
Current R2E Main Objectives
17September 30th 2009
R2E Status Report
Finished: RR73/77,UJ76 shielding and TZ76 preparation
final integration and installation of mobile shielding plug and lateral shielding walls, TZ76 preparation, UPS removal,…
US85: Fire/ODH Detectors and Control Rack Relocation
US85 Shielding of Safe-Room BIS/BIC/PIC/WIC Study (preparation done) of possibly
short-term relocationAdvanced: Order of New Iron Shielding Blocks (~2MCHF) UJ22/23 & UJ87/88 Shielding Improvements Full Integration Study for US85 Equipment Missing Point-Iterations and Equipment Inventories
Update: Finished & Ongoing Projects
18September 30th 2009
R2E Status Report
Finished: RR73/77,UJ76 shielding and TZ76 preparation
final integration and installation of mobile shielding plug and lateral shielding walls, TZ76 preparation, UPS removal,…
Fire/ODH Detectors and Control Rack Relocation US85 Shielding of Safe-Room BIS/BIC/PIC/WIC Study (partly preparation) of possibly
short-term relocationOngoing: Order of New Iron Shielding Blocks (~2MCHF) UJ22/23 & UJ87/88 Shielding Improvements Full Integration Study for US85 Equipment Missing Point-Iterations and Equipment Inventories
Update: Finished & Ongoing Projects
19September 30th 2009
R2E Status Report
RR73/77and UJ76 Shielding, TZ76
20September 30th 2009
RR73/77
TZ76 Preparations UJ76 Safe Room Shielding
R2E Status Report
US85 Safe-Room Shielding
21September 30th 2009
R2E Status Report
UJ87/88 – UJ23/22 – Shielding
22September 30th 2009
Location of the future shielding
Holes will be filledAdditional penetration in plug
Shielding wall will be install parallel to this wall + 90deg leg (L-shape)
- UJ88 Shielding already in place for the last TI2/8 tests- UJ87 Shielding installed yesterday- First analysis confirms the expected improvement- ~Factor of 10 less radiation (high-energy hadron fluence)- Relaxed situation for 2010 operation- Long-Term solution will require measurements- Possible issue with low-energy neutrons
R2E Status Report
Shielding integration studies for: UJ14/16 UJ56 (limited to lower floor) RR13/17/53/57
Early relocation of critical electronics (scenarios partly available): BIC/PIC/WIC, Fire/ODH, Timing, Remote Reset,…
Budget estimate and planning update for consolidation project
Relocation of Cryo-equipment in the US85 including local iron shielding for new rack locations (bottom floor) study ongoing, final location defined, shielding foreseen
Integration studies for full relocations of critical areas to verify the possibility, impact and costs and constraints
Study of alternative solutions possibly including heavy civil engineering
Partly Ongoing and Future Steps
23September 30th 2009
R2E Status Report
Point-Inspections and review of monitor locations Additional RadMon calibration measurements and extension of
response analysis to low- and intermediate-neutron energies calibration experiment at CERF for mixed fields calibration additional measurement proposal at PTB (including funding through
EFNUDAT), Prague (low-energy neutrons) and possible at 14MeV Passive detectors (TLD monitors) installed in LHC to allow for early
monitoring even at low radiation levels more than 200 samples (RP locations, RadMons, R2E specific)
Relocation of some RadMons in LHC in order to increase statistics and allow for early extrapolation of measured values for critical areas
Voltage setting change of RadMons in DS in order to optimise the possible analysis (ARC remains unchanged)
Combined Monitoring Tool for offline analysis, first beta-version will be available for injection tests end of October
New RadMon Developments Battery driven RadMon (soon ready) Next Generation (internal workshop to be held October 27th)
Monitoring Improvements
24September 30th 2009
R2E Status Report
Point-Inspections and review of monitor locations Additional RadMon calibration measurements and extension of
response analysis to low- and intermediate-neutron energies calibration experiment at CERF for mixed fields calibration additional measurement proposal at PTB (including funding through
EFNUDAT), Prague (low-energy neutrons) and possible at 14MeV Passive detectors (TLD monitors) installed in LHC to allow for early
monitoring even at low radiation levels more than 200 samples (RP locations, RadMons, R2E specific)
Relocation of some RadMons in LHC in order to increase statistics and allow for early extrapolation of measured values for critical areas
Voltage setting change of RadMons in DS in order to optimise the possible analysis (ARC remains unchanged)
Combined Monitoring Tool for offline analysis, first beta-version will be available for injection tests end of October
New RadMon Developments Battery driven RadMon (soon ready) Next Generation (internal workshop to be held October 27th)
Monitoring Improvements
25September 30th 2009
R2E Status Report
TLDs around the LHC: e.g, Point-8 Right
26September 30th 2009
R2E Status Report
Combined Monitoring Tool
27September 30th 2009
Monitor selection through areas (graphical, list, beam element, DCUM,…)
Easy navigation troughcritical areas
Numerous monitor types at the same time BLMs, RadMons, BCTs, RAMSES (in work) Collimator settings
Combined Viewer to checkcorrelations
Still under development Final Beta-Version ready
for extended injection Tests (End Of October)
R2E Status Report
R2E Radiation school (see program and summary) Jointly organised with PH-ESE, 2-3 June: ~55 participants, 16 lecturers Very good feedback, intensifies exchange between experiments and the
machine Power-Converters:
Internal discussion to evaluate future strategy Strong constraints in terms of what can be done Summary document available (see link)
WIC Failure during TI8 Injection Test WIC failure observed in June (stopped CNGS and LHC Injection) Immediate analysis of available measurement data FLUKA simulations to estimate respective radiation levels Detailed review of WIC layout and available test measurements Analysis confirmed that the failure was very unlikely Foreseen WIC relocation (only one rack is concerned) to location upstream the
injection line collimator, urgency to be defined following next (last) injection tests During the last TI2/8 test about 4x1013 protons were ‘dumped’ on the upstream
collimator -> no WIC failure observed -> still to be relocated when time
Furthermore…
28September 30th 2009
R2E Status Report
Simulation Studies required for: P7: additional absorbers for UJ76 P8 losses in RA84/86 and impact on adjacent UAs P1/5 update: UPS, Spectra P8/2 shielding studies P1/5 shielding studies DS/ARC update on radiation levels
Point-Iterations and reports Detailed and continuous review during early operation -
direct link to operations through point-owners Additional Shielding Improvements
(e.g., P6, US85 SafeRoom after measurements) R2E Policy for the Accelerator Sector
Besides, Next & Some Requirements
29September 30th 2009
R2E Status Report
A brief overview of the ongoing R2E related work Numerous mitigation actions and other improvements were
directly followed through R2E with a focus on possible short-term actions (some mid/long-term parts had to be put on hold)
Important inter-departmental effort to get as far as possible Stringent time constraints, it will not be enough to do things
‘sequentially’ (i.e., first observe and then react) Parallel work required (we started in this direction)
Required resources will not decrease but rather… We have the feeling of gone a good step forward, but… Continued support required from various key contributors
(Planning and Integration, Point-Owners, FLUKA Team, RadMon Team, RP, RadWG,…)
Early operation will be an important input
Many Thanks to Everybody
Conclusions
30September 30th 2009
R2E Status Report
Backup
31September 30th 2009
Mitigation Project - Status 32
aim is to continuously follow up on the Mitigation Project (not only R2E tasks as listed in the ‘Open Actions’)
facilitate ongoing coordination and increase ‘transparency’
structured by: Project (active or finished) Task (multiple, status, deadlines, last comment) Comments (text, documents, links)
reporting option for status summary or full report including all comments
directly linked on the R2E-webstite
Online Tracking Tool
September 23rd 2009
Mitigation Project - Status 33
Fire and ODH Control Rack Relocation (including detectors)
September 23rd 2009
Fire detectors relocated
Cabling, installation prepared offline
Temporary safety procedures were put in place
Control rack relocated in short time
Fully commissioned
Mitigation Project - Status 34
UJ87/88 Shielding Improvement
September 23rd 2009
Location of the future shielding
UJ87
Holes will be filled
Additional penetration in plug
Mitigation Project - Status 35
UJ87/88 Shielding Improvement
September 23rd 2009
Shielding wall will be install parallel to this wall + 90deg leg (L-shape)
UJ88
Mitigation Project - Status 36
UJ87/88 Shielding Improvement
September 23rd 2009
crane tests:
Mitigation Project - Status 37
UJ87/88 Shielding Improvement
September 23rd 2009
intermediate layout
Mitigation Project - Status 38
UJ87/88 Shielding Improvement
September 23rd 2009
final layout intermediate layout
Mitigation Project - Status 39
UJ87/88 Shielding Improvement
September 23rd 2009
final layout
Mitigation Project - Status 40
UJ23/22 and 87/88 Shielding Improvement
September 23rd 2009
Status: UJ87/88 shielding in place (final work performed
yesterday) Remaining work for P8 to be scheduled afterwards
(possible) Work for P2 to be prepared (simpler integration), more
difficult to find a two-day slot in the planning -> agreed on two separate days
Early measurements required to check for final shielding efficiency
Not optimum solution concerning the lateral opening, as well as low-energy neutrons
Mitigation Project - Status 41
Shielding Block Inventory
September 23rd 2009
Mitigation Project - Status 42
tender documents prepared iteration with FI finished (one additional company added) final tender documents approved distributed to companies firms have 4 weeks to respond supply of 1000 cast iron or steel blocks
(800mmx400mmx400mm) the total mass of all blocks is about 925 tonnes. delivery is foreseen in two batches, one half 3 months from
the placement of the Contract, the second half to be completed 3 months later
storage place identified
New Order For Iron Shielding
September 23rd 2009
Mitigation Project - Status 43
first integration studies available for UJ14/16 integration team working on optimum (maximum)
solution for UJ56 (important space and handling constraints)
final decision on shielding integration requires updated shielding block inventory (available) simulation studies to optimize the shielding layout combined integration studies to evaluate mechanical
installation preparation of shielding blocks slot for installation (estimate exists for two weeks)
full relocation campaign and alternative solutions to be studied in parallel
P1/P5 Shielding of UJs
September 23rd 2009
Mitigation Project - Status 44
P1/P5 Shielding of UJs
September 23rd 2009
Mitigation Project - Status 45
P1/P5 Shielding of UJs
September 23rd 2009
Mitigation Project - Status 46
Replacement of pressure transmitter (new feature) is not yet included as it would require heavy pipe work.
Equipment concerned in US85: Cold Compressor Box (QURCB) and ex-LEP, cold box (QURA)
Consolidation concerned: magnetic bearings, PLC's, profibus equipment, Valve positioners and associated cabinets and cabling
Cost estimate: Special cables for cold compressors: 100'000 CHF Cryo cabinets and work: 60'000 CHF EN-EL cabling for cryo: 54'000 CHF Siemens positioners: 60'000 CHF Ethernet and controls infra: 20'000 CHF => Total: 294'000 CHF
Budgeting Update - Cryogenics
September 23rd 2009