Building the Future Current Activities this Week : Mass Excavation : Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1. Site Utilities : Installation of the new electrical ductbank is ongoing. Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Foundations : Area 2 Field Level – Footing installation will be complete to Column Line 12 by the end of the day. Area 1 Mezzanine Level – Installation of Elevator Pit walls are complete. Area 4 Mezzanine Level – Installation of Drilled Piers are ongoing. Structural Steel Erection : Area 1 – Steel Erection in sequence 1-1 is nearly complete. Sequence 1-2 has started and is currently being erected in the Column Line 27/26 Bay. Decking is nearly complete in sequence 1-1 on Mezzanine and Concourse Levels. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 5.12.2010 Re: Wizards Stadium Project Update – Week of 5.10.2010 Field Level Area 2 – A-Line and Field Wall Footings ready for concrete placement. France Family Drive – Storm Line 6000 installation is ongoing. Field Level Area 3 – Drilled Pier installation is ongoing.

description

KC Soccer Stadium construction update from Turner Construction.

Transcript of Construction Update 5-12-2010

Page 1: Construction Update 5-12-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Grading is ongoing in Area 3. Backfilling of on-grade

is ongoing in Area 1.

Site Utilities:

Installation of the new electrical ductbank is ongoing.

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Foundations:

Area 2 Field Level – Footing installation will be complete

to Column Line 12 by the end of the day.

Area 1 Mezzanine Level – Installation of Elevator Pit walls

are complete.

Area 4 Mezzanine Level – Installation of Drilled Piers

are ongoing.

Structural Steel Erection:

Area 1 – Steel Erection in sequence 1-1 is nearly

complete. Sequence 1-2 has started and is currently

being erected in the Column Line 27/26 Bay.

Decking is nearly complete in sequence 1-1 on

Mezzanine and Concourse Levels.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 5.12.2010

Re: Wizards Stadium Project

Update – Week of

5.10.2010

Field Level Area 2 – A-Line and Field Wall

Footings ready for concrete placement.

France Family Drive – Storm Line 6000

installation is ongoing.

Field Level Area 3 – Drilled Pier installation is

ongoing.

Page 2: Construction Update 5-12-2010

Building the Future

Underground Electrical:

Secondary service ducts is complete from Electrical Room

01.34.04 south past Column Line 25.

Installation of secondary service ducts at Column Line D

are ongoing.

Projected Activities occurring next Week:

Mass Excavation:

Grading at Truck Dock Area will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue.

Deep Underground Plumbing:

Sanitary in Area 3 will begin.

Foundations:

Area 2 Field Level – Placement of foundation walls east of

Stage will begin.

Area 3 Field Level – Footing excavation will begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-2 will continue.

Area 1 – Structural Steel Erection at West

Building continues. B-Line Columns being

set at Column Lines 26 and 27.

Field Level Area 1 – Shot looking north from

Concourse Level.

Concourse Level Area 1 – Decking installed

at Main Club.

Page 3: Construction Update 5-12-2010

Building the Future

Additional Photos:

Mezzanine Level Area 1 – VIP Entrance

taking shape.

Field Level Area 2 – Foundations taking

shape at Stage.

Field Level Area 1 – Shot of the Stadium

Suite from Column Line 30 (Field Level).

Concourse Level Area 2 – E-Line Footings

installed to Column Line 20.

Area 1 – Shot looking North West showing

West Building Structural Steel.

Concourse Level Area 2 – Electrical ductbank

installation is ongoing.