Building the Future
Current Activities this Week:
Mass Excavation:
Remaining Mass Excavation Activities are ongoing
and are nearling completion. Removal of the Haul Road
to Area C is complete and restoration of the Speedway
Property is ongoing.
Site Utilities:
Installation of the new electrical ductbank is ongoing.
Approximately 150 linear feet is installed. Awaiting
BPU resolution on manhole tie-in.
Boring of the service line and Sanitary Main Line
D is complete, installation of the steel casing is ongoing.
Foundations:
Area 1 Field Level – Column Pad placement in Area 1
is nearly complete. Installation of Field Walls has
started.
Area 1 Mezzanine Level – E-Line Footing installation
is complete. E-Line Wall installation is ongoing.
Area 1 Concourse Level – E-Line Footing installation
Has started at Column Line 23.2.
Area 2 Field Level – Excavation for the footings has
started.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 4/14/2010
Re: Wizards Stadium Project
Update – Week of
4/12/2010
Speedway Property – Sod and seeding
installation has commenced.
Field Level Area 2 – Soil nail wall installation
on remaining section (east of Column Line
14) has commenced.
Concourse Level Area 2 – Waterline
relocation piping is nearly complete and
backfill of line has started.
Building the Future
Soil Nail Wall:
Area 2 – Shotcrete installation on the remaining sections
has begun.
Structural Steel Erection:
Field Bowl – 300 Ton Crane has been mobilized and
assembled (230’ Boom Length).
Projected Activities occurring next Week:
Mass Excavation:
Removal of the ledges for soil nail wall installation will
continue to be removed.
Site Utilities:
Waterline relocation will be complete.
Installation of the Sanitary Manhole at the North end of
Area 1 will begin.
Installation of the Storm Line on the East Side (France
Family Drive) of the site will begin.
Deep Underground Sanitary in Area 1/2 will continue.
Foundations:
Area 2 Field Level – Placement of footings around stage
will begin.
Area 1 Mezzanine Level – Drilled Pier installation at D-Line
will begin.
Area 1 Concourse Level – E-Line footing will be completed.
Soil Nail Wall:
Area 2 – Shotcrete wall installation east of Column 13
will continue.
Structural Steel Erection:
Erection of Structural Steel Sequence 1-1 will begin.
Field Level Bowl – Crane assembly
underway.
Field Level Area 1 – Shot looking north from
Concourse Level showing column pads and
deep underground sanitary line installation.
Field Level Area 2 – Excavation for A-Line
footing has started.
Building the Future
Additional Photos:
Field Level Area 1 – Placement of Elevator
F1 Pit Walls.
Field Level Area 1 – Field Wall installation is
ongoing at the base of the north section of
on-grade seating.
Mezzanine Level Area 1 – Placement of
concrete for D-Line Wall and Rebar set in
place for E-Line Wall at VIP Entrance.
Concourse Level Area 1 – E-Line Footing
Placement at Column Line 23.2
Mezzanine Level Area 1 – Steel Casing
installation under Village West Parkway for
Sanitary Main Line.
Field Level Area 1/2 – Making the turn from
Area 1 into Area 2 with Foundations.