Construction Update 4-14-2010

3
Building the Future Current Activities this Week : Mass Excavation : Remaining Mass Excavation Activities are ongoing and are nearling completion. Removal of the Haul Road to Area C is complete and restoration of the Speedway Property is ongoing. Site Utilities : Installation of the new electrical ductbank is ongoing. Approximately 150 linear feet is installed. Awaiting BPU resolution on manhole tie-in. Boring of the service line and Sanitary Main Line D is complete, installation of the steel casing is ongoing. Foundations : Area 1 Field Level – Column Pad placement in Area 1 is nearly complete. Installation of Field Walls has started. Area 1 Mezzanine Level – E-Line Footing installation is complete. E-Line Wall installation is ongoing. Area 1 Concourse Level – E-Line Footing installation Has started at Column Line 23.2. Area 2 Field Level – Excavation for the footings has started. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 4/14/2010 Re: Wizards Stadium Project Update – Week of 4/12/2010 Speedway Property – Sod and seeding installation has commenced. Field Level Area 2 – Soil nail wall installation on remaining section (east of Column Line 14) has commenced. Concourse Level Area 2 – Waterline relocation piping is nearly complete and backfill of line has started.

description

KC Soccer Stadium construction update from Turner Construction.

Transcript of Construction Update 4-14-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Remaining Mass Excavation Activities are ongoing

and are nearling completion. Removal of the Haul Road

to Area C is complete and restoration of the Speedway

Property is ongoing.

Site Utilities:

Installation of the new electrical ductbank is ongoing.

Approximately 150 linear feet is installed. Awaiting

BPU resolution on manhole tie-in.

Boring of the service line and Sanitary Main Line

D is complete, installation of the steel casing is ongoing.

Foundations:

Area 1 Field Level – Column Pad placement in Area 1

is nearly complete. Installation of Field Walls has

started.

Area 1 Mezzanine Level – E-Line Footing installation

is complete. E-Line Wall installation is ongoing.

Area 1 Concourse Level – E-Line Footing installation

Has started at Column Line 23.2.

Area 2 Field Level – Excavation for the footings has

started.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 4/14/2010

Re: Wizards Stadium Project

Update – Week of

4/12/2010

Speedway Property – Sod and seeding

installation has commenced.

Field Level Area 2 – Soil nail wall installation

on remaining section (east of Column Line

14) has commenced.

Concourse Level Area 2 – Waterline

relocation piping is nearly complete and

backfill of line has started.

Building the Future

Soil Nail Wall:

Area 2 – Shotcrete installation on the remaining sections

has begun.

Structural Steel Erection:

Field Bowl – 300 Ton Crane has been mobilized and

assembled (230’ Boom Length).

Projected Activities occurring next Week:

Mass Excavation:

Removal of the ledges for soil nail wall installation will

continue to be removed.

Site Utilities:

Waterline relocation will be complete.

Installation of the Sanitary Manhole at the North end of

Area 1 will begin.

Installation of the Storm Line on the East Side (France

Family Drive) of the site will begin.

Deep Underground Sanitary in Area 1/2 will continue.

Foundations:

Area 2 Field Level – Placement of footings around stage

will begin.

Area 1 Mezzanine Level – Drilled Pier installation at D-Line

will begin.

Area 1 Concourse Level – E-Line footing will be completed.

Soil Nail Wall:

Area 2 – Shotcrete wall installation east of Column 13

will continue.

Structural Steel Erection:

Erection of Structural Steel Sequence 1-1 will begin.

Field Level Bowl – Crane assembly

underway.

Field Level Area 1 – Shot looking north from

Concourse Level showing column pads and

deep underground sanitary line installation.

Field Level Area 2 – Excavation for A-Line

footing has started.

Building the Future

Additional Photos:

Field Level Area 1 – Placement of Elevator

F1 Pit Walls.

Field Level Area 1 – Field Wall installation is

ongoing at the base of the north section of

on-grade seating.

Mezzanine Level Area 1 – Placement of

concrete for D-Line Wall and Rebar set in

place for E-Line Wall at VIP Entrance.

Concourse Level Area 1 – E-Line Footing

Placement at Column Line 23.2

Mezzanine Level Area 1 – Steel Casing

installation under Village West Parkway for

Sanitary Main Line.

Field Level Area 1/2 – Making the turn from

Area 1 into Area 2 with Foundations.