PROJECT UPDATE Construction Progress PROJECT UPDATE
Transcript of PROJECT UPDATE Construction Progress PROJECT UPDATE
Construction Progress
A significant milestone has been reached in the construction with the
completion of stage 3a of the redevelopment project. Witness testing and
training was completed in March and the building (levels 3– 7) handed over to
LBH in April 2016. Operational commissioning of the new departments has
commenced and access to these areas remains restricted. Staff tours of the new
building will be arranged within the next two weeks and all staff will be advised
of the same.
Some pictures of the new facility:
Level 4 Link Bridge Level 4 Lift Lobby
Renal Unit - Haemodialysis Treatment Renal Unit - Staff Station
Renal Unit—Reception Peritoneal Dialysis - Staff Station
PROJECT UPDATE
Project Update - Issue 26
May 2016
Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]
The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service
infrastructure investment initiative under the Health and Hospitals Fund Program, with the
Australian Government contributing $60 million and the State providing $20 million.
PROJECT UPDATE - MAIN WORKS
ED - Admin Area ED - Short Stay Staff Station
ED - Short Stay Treatment Bays ED - Acute Staff Station
ED - CT Scanning Unit ED—Resuscitation Area
ED Fastrack - Staff Station New Theatre Floor
Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]
Project Update - Issue 26
May 2016
The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service
infrastructure investment initiative under the Health and Hospitals Fund Program, with the
Australian Government contributing $60 million and the State providing $20 million.
New Theatre Floor
Stage 3b1
Stage 3b1 is the construction of the shell and core for levels 8 - 12 and
the construction of a Helicopter Landing Site (HLS) on levels 13 & 14.
Works are also progressing on completing construction of the front
entrance forecourt area outside the renal unit, the ED ambulance bay and
the extended vehicle drop off zone.
ED Ambulance Bay Helicopter Landing Site
Helicopter Landing Site Liftwell
Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]
Project Update - Issue 26
May 2016
The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service
infrastructure investment initiative under the Health and Hospitals Fund Program, with the
Australian Government contributing $60 million and the State providing $20 million.
Multi Level Car Park
Construction of the new car park is nearing completion with all floor slabs and on grade car park works completed. Lighting and street signage installed and façade works ongoing.
Interesting Facts
In construction so far:
9150 cubic metres of concrete has been poured which equates to
approximately 91.5km’s of footpath.
715 tonnes of steel reinforcement have been laid to date which equates to
approximately 477 Holden Commodores.
175 tonne of structural steel installed to date. Total structural for the
project is 100 tonnes.
To end of the month, 25,050 man hours with cumulative total of 461,528
man hours for the project to date.
Any feedback or enquiries should be directed to Scott Huxley
([email protected]) and will be addressed by the project
team
Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]
Project Update - Issue 26
May 2016
The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service
infrastructure investment initiative under the Health and Hospitals Fund Program, with the
Australian Government contributing $60 million and the State providing $20 million.