Construction Update 09-1-2010

4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of foundations is nearly complete in Area 3. Site Utilities : Tie in of domestic and fire line services are complete on the east side of France Family Drive. Installation of the gas service has commenced. Foundations : Area 4 Field Level – Field wall installation up to the crane road is complete. Concrete Flatwork : Area 2 Concourse – Prep work for next slab pour for South Concession Buildings is nearly complete. Area 3 Field Level – Prep work for slab pour at upper dock is nearly complete. Structural Steel Erection : Area 2 – Main Canopy Truss Erection are set to Column Line 10. Structural Precast Concrete : Area 3 – Precast tread/riser erection complete. Underground MEP : Area 3 - Deep underground Plumbing is ongoing. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 9.1.2010 Re: Wizards Stadium Project Update – Week of 8.30.2010 Area 4 – North field wall complete to the Crane Road. Area 3 – Precast tread/riser erection is complete. Area 2 – Stage concrete slab placement is complete.

Transcript of Construction Update 09-1-2010

Page 1: Construction Update 09-1-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of foundations is nearly complete in Area 3.

Site Utilities:

Tie in of domestic and fire line services are complete

on the east side of France Family Drive. Installation of

the gas service has commenced.

Foundations:

Area 4 Field Level – Field wall installation up to the

crane road is complete.

Concrete Flatwork:

Area 2 Concourse – Prep work for next slab pour for

South Concession Buildings is nearly complete.

Area 3 Field Level – Prep work for slab pour at upper

dock is nearly complete.

Structural Steel Erection:

Area 2 – Main Canopy Truss Erection are set to Column

Line 10.

Structural Precast Concrete:

Area 3 – Precast tread/riser erection complete.

Underground MEP:

Area 3 - Deep underground Plumbing is ongoing.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 9.1.2010

Re: Wizards Stadium Project

Update – Week of

8.30.2010

Area 4 – North field wall complete to the

Crane Road.

Area 3 – Precast tread/riser erection is

complete.

Area 2 – Stage concrete slab placement is

complete.

Page 2: Construction Update 09-1-2010

Building the Future

MEP Rough-in:

Area 3 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite and Press Levels

are ongoing. Plumbing rough-in is ongoing on Suite and

Press Levels. Fire Protection rough-in is ongoing on

Suite and Press Levels. Electrical rough-in is ongoing on

Suite and Press Levels.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels are ongoing. Exterior metal stud framing

and sheathing installation is ongoing at Field, Suite, and

Press Levels.

Masonry:

Area 1 Field Level – Masonry wall installation is ongoing

in Areas F, G and H.

Area 3 Concourse Level – Masonry wall installation at

Main Concourse Buildings are underway.

Curtainwall:

Area 1 – Curtainwall framing installation will continue

at West Elevation. Installation of Curtainwall glass is

ongoing.

Projected Activities occurring next Week:

Site Utilities:

Gas Service installation will continue on France Family Drive.

Deep Underground MEP:

Deep Plumbing installation will continue in Area 3.

Foundations:

Area 4 Field Level – Foundation wall installation for Main

Stair will begin.

Area 1 – Shot of the West Building from the

Stage (Field Level).

Area 1 – Exterior Metal Stud Framing and

sheathing installation ongoing at north side

of Stadium Suite.

Area 2 – Canopy Truss erection is complete

in Sequence 2-2 (installation of Truss to 10

Line shown).

Page 3: Construction Update 09-1-2010

Building the Future

Concrete Flatwork:

Area 2 Concourse Level – Concrete placement for Slab-on

Grade for Main Concourse Buildings will begin.

Area 1, 2 and 3 Field Level – Installation of on-grade seating

risers and intermediate stairs will continue.

Structural Steel Erection:

Area 2 – Canopy truss installation at South side of Stadium

will continue. Area 3 – Canopy Truss installation will begin.

Underground MEP:

Deep underground plumbing will continue in Area 3.

MEP Rough-in:

MEP Rough-in at Suite and Press Levels will continue.

Ductwork installation on Press Level will continue. Fire

Sprinkler installation will continue on Suite and Press Levels.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels will continue. Exterior Framing and

sheathing installation will continue.

Curtainwall:

Area 1 – Curtain Framing and Glass installation will

continue.

Area 1 – Installation of curtainwall framing

and Glass at West Building is ongoing.

Roof Level Area 1 – Installation of decking

on Canopy Trusses has started.

Page 4: Construction Update 09-1-2010

Building the Future

Additional Photos:

Area 2 – Shot looking south from roof above

Stadium Suite.

Field Level Area 1 – Curtainwall glass, metal

stud framing and exterior sheathing being

installation at and above Main Club

Entrance.

Concourse Level Area 1 – Masonry at Main

Concourse Level is underway (Stair 4

shown).

Field Level Area 1 – Subroof framing

installation is ongoing.

Field Level Area 3 – Upper Dock Formwork

and MEP rough-in is ongoing in preparation

for concrete slab placement.

Field Level Area 2 – Masonry installation at

Field Level (underneath terrace seating).