Commissioning Plan Robert Thelander, Svenska kraftnät

25
Commissioning plan NBS information day in Helsinki – 2015.04.20 Robert Thelander, NBS project, Svenska kraftnät

Transcript of Commissioning Plan Robert Thelander, Svenska kraftnät

Page 1: Commissioning Plan Robert Thelander, Svenska kraftnät

Commissioning plan

NBS information day in Helsinki – 2015.04.20

Robert Thelander, NBS project, Svenska kraftnät

Page 2: Commissioning Plan Robert Thelander, Svenska kraftnät

2

The commission part of the information day will focus on…

About the commissioning plan

Overall time plan

Import of structure data

Testing

Go-live preparations

Page 3: Commissioning Plan Robert Thelander, Svenska kraftnät

3

Agenda

About the commissioning plan

Overall time plan

Import of structure data

Testing

Go-live preparations

Page 4: Commissioning Plan Robert Thelander, Svenska kraftnät

4

To smoothen the transition towards NBS, the market model and necessary changes have been thoroughly documented

• Provides an overview of the NBS model for all market participants

• Clarifies rules, and regulations as well as local adaptations

• New version this weekwww.esett.com

NBS Handbook

• Connection guidelines describes the technical integration towards eSett

• Will be published in June 2015

www.esett.com

Connection guideline

• The Commissioning plan serves as a guideline for all market participants when commissioning

• Launched today

www.esett.com

Commissioning plan

Page 5: Commissioning Plan Robert Thelander, Svenska kraftnät

5

To further describe the technical changes the BRS, XML user guide and XML example files have been provided

• XML User guide is based on the BRS and aims to clarify technical aspects of the change based ENTSO-E Implementation Guides and ebIX®

www.ediel.org

XML User guide

• Business Requirement Specification (BRS) aims to detail the information exchange between the market participants to enable NBS

www.ediel.org

BRS

• XML example files have been established to enable and smoothen the change for the market participants

www.ediel.org

Example files for XML

Page 6: Commissioning Plan Robert Thelander, Svenska kraftnät

6

The establishment of a commissioning plan will support market participants in their transition towards Nordic balance settlement

Background• As part of the preparation for the commissioning (Go-Live) a

commissioning plan is critical to prepare and discuss with market participants to support a smooth transition over to the new NBS model.

Purpose• Establishment of a commissioning plan for the hand over of

settlement business from TSOs to eSett. Including contingency plans, training plans, communication plans, etc.

• This to support both eSett, TSOs and market participants.

Delimitations• Descriptions of daily operations• Only “one-time events” to be covered by the commissioning plan,

day-to-day routines to be covered by the NBS handbook

Page 7: Commissioning Plan Robert Thelander, Svenska kraftnät

7

The commissioning plan focus on issues that influence market participants and TSOs during the commissioning period

Commissioning plan

Chapter Content

1. Introduction• Introduction to the commissioning plan• Purpose• Goal

2. Commissioning • Definition of commissioning• Defining the different phases of commissioning

3. Organization and resources • eSett organization and available resources• Structure of eSett customer service

4. Training of all parties• Training• Online Service• User accounts

5. Market preparations• Establishment of MGAs in Finland and Norway• Handling of corrections• Reporting on RE-level

6. Quality assurance

• Shadow settlement• Submitting structural data• Calendar and time zones• Regulatory changes

7. IT preparations

• Communication testing• User Acceptance Test• Testing Partner Test• Operational Test Run• Market preparations

Page 8: Commissioning Plan Robert Thelander, Svenska kraftnät

8

and will together with all other provided material act as the guideline for all market participants when commissioning

Commissioning plan

Chapter Content

8. Invoicing, payments and collateral

• Establishment of contractual framework & settlement bank network• Required preparation by BRPs• Required testing of invoicing, funds transfers and balance reporting• Collateral requirements

9. Go-Live readiness • Check-list per market participant prior to Go-Live

10. Transition period • Parallel reporting• Holidays during transition period

11. Contingency plan • Contingency plan

12. Communication plan • Sources of information and channels for communication

13. Risks • Main commissioning risks• Mitigation actions

14. Documentation • Information available

15. Lessons learned • Lessons learned from first roll-out

16. Change log

17. Appendices • Appendix 1 - National Changes Compared to Imbalance Settlement Model• Appendix 2 – Checklists for Go-Live readiness

Page 9: Commissioning Plan Robert Thelander, Svenska kraftnät

9

The go-live checklist are to be seen as a supportive tool when preparing for NBS

Go-live checklist (BRP example)

Finland Norway & Sweden

Activity ID Activity Date due [YYYY-MM-DD]

Date due [YYYY-MM-DD]

Status Priority[1-3]

Responsible[Optional]

Read more: Comment[Optional]

BRP.0 Activity #0 2016-02-01 2016-04-18 Action needed 1 Project manager NBS handbook section:1.1.1 Separate meeting to be scheduled

d BRP.1 Sign imbalance settlement agreement NBS handbook section 2.4

BRP.2 Sign balance agreement NBS handbook section 2.4

BRP.3Report the settlement data for the full w eek of 39 (21/9-27/9 2015) to eSett' settlement system

Commissioning plan section 6.2eSett w ill carry out shodow settlement based on this data

BRP.4 Verify settlement result in Online Service Commissioning plan section 6.2

BRP.5Test and receive certif icate regarding communication tow ards testing portal for f innish market

Before Operational Test Run

n.a. Commissioning plan section 7.2

BRP.6Test and receive certif icate regarding communication tow ards the Ediel portal

n.a.Before Operational Test Run

Commissioning plan section 7.2

BRP.7 Test tow ards eSett (Operational Test Run) Commissioning plan section 7.1

BRP.8Ensure access to Online Service (eSett to request details for administrative account)

NBS handbook 10.3.3Commissioning plan section 7.2

BRP.9Provide structure information to eSett according to provided template

Commissioning plan section 6.2

BRP.10 Verify initial settlemement structure via Online Service September 2015 September 2015 Commissioning plan section 6.2

BRP.11 Final verif ication of Settlement data (via Online Service) 2016-01-17 2016-04-03

BRP.12 Testing of Information Service (optional) Commissioning plan chapter 7

BRP.13 Testing of Messaging Service Commissioning plan chapter 7

BRP.14 Prepare ow n IT system -

BRP.15 Understand, align and adapt to new market model NBS handbook all chapters

BRP.16 Read and understand provided information material www.esett.com

BRP.17 Communicate and report any problems to eSett www.esett.com

BRP.18 Adapt to new processes and routines in the daily business Commissioning plan chapter 8

Before Operational Test Run

Well before go-live

Before testing (w ell before go-live)

Continuously

End of May 2015

During the Operational Test Run

During the Operational Test Run

BRP Checklist

Continuously

At Go-Live

To be defined

To be defined

2015-11-13 (during w eek 46)

During the Operational Test Run

2015-11-20 (during w eek 47)

Finland Norway & SwedenActivity

IDActivity Date due

[YYYY-MM-DD]Date due

[YYYY-MM-DD]Status

Priority

Responsible[Optional]

Read more: Comment[Optional]

BRP.0 Activity #0 2016-02-01 2016-04-18 Action needed 1 Project manager NBS handbook section:1.1.1Separate meeting to be

scheduled

BRP.1 Sign imbalance settlement agreement NBS handbook section 2.4

BRP.2 Sign balance agreement NBS handbook section 2.4

BRP.3Report the settlement data for the full w eek of 39 (21/9-27/9 2015) to eSett settlement system

Commissioning plan section 6.2eSett w ill carry out shodow settlement based on this data

BRP.4 Verify settlement result in Online Service Commissioning plan section 6.2

BRP.5Test and receive certif icate regarding communication tow ards testing portal for f innish market

Before Operational Test Run

n.a. Commissioning plan section 7.2

BRP.6Test and receive certif icate regarding communication tow ards the Ediel portal

n.a.Before Operational Test Run

Commissioning plan section 7.2

BRP.7 Test tow ards eSett (Operational Test Run) Commissioning plan section 7.1

BRP.8Ensure access to Online Service (eSett to request details for administrative account)

NBS handbook 10.3.3Commissioning plan section 7.2

BRP.9Provide structure information to eSett according to provided template

Commissioning plan section 6.2

BRP.10 Verify initial settlemement structure via Online Service Commissioning plan section 6.2

BRP.11 Final verif ication of Settlement data (via Online Service) 2016-01-17 2016-04-03 Commissioning plan section 6.2

BRP.12 Testing of Information Service (optional) Commissioning plan chapter 7

BRP.13 Testing of Messaging Service Commissioning plan chapter 7

BRP.14 Prepare ow n IT system -

BRP.15 Understand, align and adapt to new market model NBS handbook all chapters

BRP.16 Read and understand provided information material www.esett.com

BRP.17 Communicate and report any problems to eSett www.esett.com

BRP.18 Adapt to new processes and routines in the daily business Commissioning plan chapter 8

BRP.19 BRPs to have opened a Settlement account Commissioning plan chapter 8

BRP.20 Pledged Cash Account Agreements signed Commissioning plan chapter 8

BRP.21

Ensure readiness to receive invoices from eSett* Establish an agreement w ith an e-invoice operator to receive e-invoices* Agree w ith the e-invoice operator on the format in w hich eSett's e-invoices w ill be provided by the operator* Inform eSett of the selected e-invoice operator and the BRP's e-invoicing address* Implement interface for reading e-invoice into accounting system (optional)* In case the BRPs does not w ant to receive e-invoices, inform eSett of an email address to w hich the invoices should be sent as PDF files (optional)

Commissioning plan chapter 8

Before Operational Test Run

Well before go-live

Before testing (w ell before go-live)

Continuously

One month prior to Go-Live

One month prior to Go-Live

One month prior to Go-Live

End of May 2015

During the Operational Test Run

During the Operational Test Run

October 2015

Continuously

At Go-Live

One month prior to Go-Live

One month prior to Go-Live

2015-11-20 (during w eek 46-47)

During the Operational Test Run

2015-11-20 (during w eek 48)

BRP Checklist

Page 10: Commissioning Plan Robert Thelander, Svenska kraftnät

10

Agenda

About the commissioning plan

Overall time plan

Import of structure data

Testing

Go-live preparations

Page 11: Commissioning Plan Robert Thelander, Svenska kraftnät

11

The commissioning phase will be most active in the second half of 2015 and in the beginning of 2016

Overall time plan for commissioning

2015 2016

September October November December January February March April

36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Co

mm

issi

on

ing

Basic Structure Data to be input (June-August)

Preparations for Go-Live

NBS Settlement in Sweden and NorwayParallel Settlement

in Finland

NBS Settlement in FinlandFinalize Structure

Data (FI)

Finalize Structure Data (SE, NO)

Customers finalize Structure Data

Shadow settlement

Parallel Settlement in Norway

Permission to start submitting data to eSett

Operational Test Runs in FI, SE, NO TSO OTR

Parallel Settlement in Sweden

Unsupported testing period

Page 12: Commissioning Plan Robert Thelander, Svenska kraftnät

12

Agenda

About the commissioning plan

Overall time plan

Import of structure data

Testing

Go-live preparations

Page 13: Commissioning Plan Robert Thelander, Svenska kraftnät

13

Structure data is the backbone of the settlement calculations. Market participants are required to submit structure data to eSett

• eSett is dependent on a correct baseline of structure (standing) data to be able to perform a correct imbalance settlement

• Due to higher granularity in the imbalance settlement eSett is not able to only collect standing data from the TSOs, hence eSett will be dependent on structure data updates from all market participants

• eSett will during summer and autumn 2015 input basic data to the new balance settlement system (Basse)

Structure data – The background

Page 14: Commissioning Plan Robert Thelander, Svenska kraftnät

14

Structure data will be collected and verified in a step-wise approach with verifications and quality checks

Beginning of MayeSett provides structure data template to market

participants

June SeptembereSett imports basic

structure data structure

2015-06-14Last day for reporting basic

structure data to eSett according to template

2015-08-30Last day for reporting full range of structure data to

eSett according to template

OctoberVerification of structure

data by market participants

2016-01-17Last day for final verification of

settlement data for Finnish market participants

2016-04-03Last day for final

verification of settlement data for Norwegian &

Swedish market participants

Page 15: Commissioning Plan Robert Thelander, Svenska kraftnät

15

Structure data will be collected in 2 phases of which the first phase focus on basic data and the second on the full scope

• The first round of structure data will focus on importing:• TSO information

• MBAs• MGAs• Regulation Objects• Reserves

• Basic market participant data• Communication IDs• Main contacts• Administrator for Online Service• Limited amount of market relations

Structure data – First phase

Page 16: Commissioning Plan Robert Thelander, Svenska kraftnät

16

Agenda

About the commissioning plan

Overall time plan

Import of structure data

Testing

Go-live preparations

Page 17: Commissioning Plan Robert Thelander, Svenska kraftnät

17

Testing will be done both towards testing platforms (messages) and towards the sub-sytems of Basse

• In order to verify both the functionality of the new XML-messages as well as the functionality of the sub-systems of Basse and the market participants readiness testing will be done prior to go-live

• Testing of the new xml-messages will be performed on a specific portal

• Testing towards the sub-systems of Basse will be performed directly towards eSett

Testing in general

Page 18: Commissioning Plan Robert Thelander, Svenska kraftnät

18

Initial portal tests for market participants and system vendors

• A testing portal for the new XML-messages for the Finnish market participants will be provided by Fingrid

• Testing will be made available before the operational test run starts in October

Testing portal for the new XML messages

Page 19: Commissioning Plan Robert Thelander, Svenska kraftnät

19

Testing of the new settlement system will be performed in three distinct steps to gain insights and finalize the system before go-live

User Acceptance Tests

• By eSett

• Ensure the functioning of Balance Settlement Solution (Basse)

• First half of 2015

Testing Partner Tests

• By Selected Testing Partners

• Ensure that Market Participants with different roles can operate with Basse

• Kick-off in November 2014

• First half of 2015

Operational Test Run

• By All Market Participants

• Ensure the company specific readiness for the Nordic Imbalance Settlement

• Starting in October 2015

• Shadow settlement

• Parallel operations

Step-wise approach to testing

Page 20: Commissioning Plan Robert Thelander, Svenska kraftnät

20

The scope of the OTR is focused towards the subsystems of Basse and their integrations towards the market participants systems

Testing towards the Basse subsystems

The objective is to test the market participant capabilities with focus on:

Online Service (ONLS) the essential day-to-day activities from the market participant perspective

Messaging Service (MS) market role specific information transfer via market messages – to submit and receive

required and preferred information from eSett

Information Service (IS) testing of the market role specific information to be requested and received through the

information service

Page 21: Commissioning Plan Robert Thelander, Svenska kraftnät

21

Shadow settlement will be performed during the OTR. the objective is to perform imbalance settlement for a restricted period of time

Shadow settlement

• During the Operational Test Run one week of shadow settlement will be performed. Shadow settlement means that market participants will send settlement data to eSett and eSett will perform a settlement calculation based on received data.

• Shadow settlement is performed in order to verify quality and correct operation of the settlement system (Basse), the market participant’s systems and processes.

• Shadow settlement will be performed for the whole imbalance settlement process scope, simulating operations after go-live in all countries.

• The shadow settlement period will be performed based on settlement data from the full week 39, 2015.

• Market participants will report this data during weeks 46 & 47 (9/11-22/11 2015

• eSett will perform the settlement calculations during week 48 (23/11-27/11 2015) and present the results of the calculations to each market participant respectively

Page 22: Commissioning Plan Robert Thelander, Svenska kraftnät

22

Parallel reporting will be enabled one month prior to go-live

Parallel reporting

• Finnish market participants will be able to submit their settlement data to eSett 1 month prior to go-live.

• Imbalance settlement procedures and calculations will during this period be performed by both Fingrid’s and eSett’s settlement systems

• This is the possibility to fine tune the integration towards Basse

Page 23: Commissioning Plan Robert Thelander, Svenska kraftnät

23

Agenda

About the commissioning plan

Overall time plan

Import of structure data

Testing

Go-live preparations

Page 24: Commissioning Plan Robert Thelander, Svenska kraftnät

24

What would I do if I were you? (the 13-step approach)

No

Well done!

Yes

Read and understand provided material

1

Ask clarifying questions!!!

2

Initiate cooperation with system vendor

3

Start using the go-live checklist

4

Prepare my IT-system and align

necessary processes

5

Submit requested structural data to

eSett according to template

6

Sign necessary agreements (if

applicable)

7

Initiate testing towards testing portal

8Prepare for

operational test run towards Basse

9Prepare for and

participate in shadow settlement

10

Verify final structure data

11

Make sure all items on the checklist have

been finalized

12

“Are we ready for NBS?”

13

Page 25: Commissioning Plan Robert Thelander, Svenska kraftnät

Thank you!