Translated document AFRICAN DEVELOPMENT FUND CHAD EDUCATION SECTOR SUPPORT PROJECT (PASE) PROJECT COMPLETION REPORT (PCR) OSHD DEPARTMENT September 2013

Transcript of Chad - Education Sector Support Project (PASE) - Project ... · The project development objective...

Page 1: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

Translated document

AFRICAN DEVELOPMENT FUND

CHAD

EDUCATION SECTOR SUPPORT PROJECT (PASE)

PROJECT COMPLETION REPORT

(PCR)

OSHD DEPARTMENT

September 2013

Page 2: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

1

PROJECT COMPLETION REPORT

I Basic Data

A Report Data

Report date

Date of report: 14 February 2013

Mission date (if field mission) 11-20 January 2013

From: 9 January 2013 To: 28 January 2013

B Responsible Bank staff

Positions At Approval At Completion

Regional Director M. Kanga, Director, ORCE

Country Manager Michel-Cyr Djiena-Wembou, Resident Representative, TDFO

Sector Director Z. B. El Bakri, Director, OCSD A. Soucat, Director, OSHD

Sector Manager N. Safir, Manager, OCSD.3 M. B. Savadogo, Manager, OSHD. 2

Task Manager C.M. Guedegbe, OCSD.2 C.M. Guedegbe, OSHD.2

Alternate Task Manager T. Djogoye, TDFO

PCR Team Leader T. Djogoye, TDFO

PCR Team Members S. Maouloud, D. Tilengar, M. Laba, (TDFO),

A. Capo (Consultant); M. Outman, D. Nadji (CSPE)

C Project Data

Project Name: Education Sector Support Project (PASE)

Project Code: P-TD-IAZ-002 Instrument Number(s): ADF Grant 2100155002166 6540654000382 (OPEC Loan)

Project Type: Investment project Sector: Social

Country: CHAD Environmental Categorization (1-3): 2

Processing milestones - Bank approved

financing only (add/delete rows depending

on the number of financing sources)

Key Events (Bank approved financing only)

Disbursement and closing dates (Bank approved financing only)

Financing Source/Instrument 1: ADF Financing Source/Instrument 1: ADF Financing Source/Instrument 1: ADF

Date approved: March 31, 2004 Canceled amounts: UA 662,891.53 Original disbursement deadline: 04/05/2005

Date signed: 26 May 2004 Supplementary financing: 0 Original closing date: 30/06/2010

Date of entry into force: 14 February 2005 Restructuring: The project was not restructured

Revised disbursement deadline: 30/06/2012

Date effective for 1st disbursement: 4 May 2005 Extensions: 31/12/2011 30/06/2012

Revised closing date: 30/06/2012 31/12/2012

Date of actual 1st disbursement:

Financing Source/Instrument 2: Government Financing Source/instrument 2:

Government

Financing Source/Instrument 2:

Government: UA 320,000 UA

Date approved: 31 March 2004 Cancelled amounts: UA 00 Original disbursement deadline: 17 June 2008

Date signed: 26 May 2004 Supplementary financing: 0 Original closing date: 30/06/2010

Date of entry into force: 14 February 2005 Restructuring: The project was not restructured

Revised disbursement deadline: 31/12/2012

Page 3: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

2

Date effective for 1st disbursement: 1 October 2005

Extensions: 30/12/2011 30/06/2012

Revised closing date: 30/06/2010 31/12/2012

Date of actual 1st disbursement: 17 June 2008

Financing Source/Instrument 3:

OPEC Fund

Financing Source/Instrument 3:

OPEC Fund

Financing Source/Instrument 3:

OPEC Fund

Date approved: 16/05/2005 Canceled amounts Original disbursement deadline: 04/08/2009

Date signed: 08/05/2005 Supplementary financing: 0 Original closing date: 31/12/2010

Date of entry into force: 13/08/2007 Restructuring: The project was not restructured

Revised disbursement deadline: 30/11/2012

Date effective for 1st disbursement: 13/08/2007 Extensions: 23/03/2011 16/12/2011 31/07/2012

Revised closing date: 31/12/2011 30/06/2012 31/12/2012

Date of actual 1st disbursement: 2008

Financing Source (UA): Disbursed Amount (amount, UA):

Percentage Disbursed (%):

Undisbursed Amount (UA):

Percentage Undisbursed (%):

Financing Source/Instrument 1: ADF 1,737,108.01 72.38% 662,891.53 27.62%

Financing Source/Instrument 2: Government 289,024 92.32% 30,976 07.68%

Financing Source/Instrument 3: OPEC Fund 2,892,000 87.90 398,000 12.10%

TOTAL 4,918,132.01 81.83 1,091,867.99 18.17

Financing Source (UA): Committed Amount (UA):

Percentage Committed (%):

Uncommitted Amount (UA):

Percentage Uncommitted (%):

Financing Source/Instrument 1: ADF 2,400,000 72% 662,891.53 27.62%

Financing Source/Instrument 2: Government 320,000 90.32% 30,976 07.68%

Financing Source/Instrument 3: OPEC 3,290,000 87.90 398,000 12.10%

TOTAL 6,010,000 81.83 1,091,867.99 18.17

Co-financiers and other external partners: N/A

Executing and implementing agency(ies): Ministry of Education, Education Project Implementation and Monitoring Unit (CSPE)

D Management Review and Comments

Report reviewed by Name Date reviewed Comments

Country Manager M. Djiena-Wembou, Resident Representative, TDFO

31 May 2013 Report validated

Regional Director M. Kanga, Director, ORCE

Sector manager M. B. Savadogo, Manager, OSHD. 2 27 June 2013 Report validated

Sector Director A. Soucat, Director, OSHD 28 June 2013 Report validated

Page 4: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

3

II Project performance assessment

A Relevance

1. Relevance of Project Development Objective

Rating* Narrative Assessment

3

The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the Millennium Development Goals (MDGs) for the sector. The Bank's interventions in regional member countries' education sector are based on country sector policies as well as the Bank's policies relating to the sector. The Bank recommends a holistic approach to the development of primary education. The education sector strategy at the time of Chad's assessment was based on the Education Reform Support Project (PARSET). The Government had adopted an education policy strategy based on: (i) increased access and equity; (ii) improved quality of teaching and learning conditions; and (iii) enhanced capacities to plan and manage Chad's education system. The overall goal of PARSET is to ensure quality universal primary education by 2015 so as to achieve EFA objectives and the MDGs. The present PASE project (Education VI) is fully consistent with the Bank's vision for poverty reduction and the Country Strategy Paper (CSP) for 2002-2004 period, which focuses on government capacity building in economic management and social services, with special emphasis on initial and continuing training of teachers and pedagogic control and monitoring staff. The Bank financed five projects in Chad over the 1976-2001 period. The two most recent are Education Project IV approved in 1991 and closed in 2001, and Education project V approved in March 2001 and closed on 31 March 2011. Other interventions financed by UNDP, World Bank, French Development Agency, UNICEF and Swiss Agency for Development and Cooperation are being implemented at various levels of the education system.

* For all ratings in the PCR, use the following scale: 4 (Highly Satisfactory), 3 (Satisfactory), 2 (Unsatisfactory), 1 (Highly Unsatisfactory)

2. Relevance of Project Design

Rating* Narrative assessment

3

With assistance from its development partners, the Government prepared the Education and Training Action Programme (PAEF 2000-2003) and the Education Reform Support Project (PARSET 2004-2007), adopted in January 2000 and March 2002 respectively. The National Education for All Action Plan (PAN/EPT), the PAEF and the PARSET constitute the framework for education sector development actions for the 2002-2015 period. The Government submitted a request to the Bank for the Education VI Project (PASE). The project is the response to the Government's request for strengthening human resources in the education system and the social sectors. The project was prepared by Bank missions using a participatory approach that involved broad consultations with the authorities, civil society, community organizations, local administrations and parents of students. The project design took account of the policy implemented by the Government with assistance from the development partners, and addresses Goal 2 of the MDGs, i.e., universal primary education. The project incorporated experiences drawn from the PCR prepared for Education Project III in 2000 and Education Project IV closed in 2004. The project design provided a diagnosis of Chad's education system, reviewed the institutional framework, and consulted the National Strategy for Education, Training and Employment (EFE), the PAEF, the PARSET and the PAN/EPT. The shortage of teaching and supervisory staff was taken into account, and training was provided to many teachers and supervisors.

3. Lessons learned related to relevance

Key issues (max. 5; add rows as needed) Lessons learned Target audience

1. Given that the project contributed to the PARSET, which is also financed by the World Bank, there were changes with respect to the original identified sites, and the difficult access to certain sites resulted in increased costs. 2. Security risk. The events of February 2008 (looting, vandalism, theft, destruction of the Ministry and executing agency premises) caused significant delays in project implementation.

1. The selection of construction sites should be finalized prior to project start-up. 2. The Government should undertake to provide security for the project sites.

1. The Bank and the Borrower 2. Government

Page 5: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

4

B Effectiveness

1. Progress towards the project’s development objective (project purpose)

Comments

Provide a brief description of the project (components) and the context in which it was designed and implemented. State the project

development objective (usually the project purpose as set out in the RLF) and assess progress. Unanticipated outcomes should also

be accounted for, as well as specific reference of gender equality in the project. The consistency of the assumptions that link the

different levels of the results chain in the RLF should also be considered. Indicative max. length: 400 words.

The project development objective is to help Chad achieve the Education for All (EFA) objectives and the Millennium Development

Goals (MDGs) for the sector. This objective was to be achieved by: (i) improving the school infrastructure and environment so as to

increase the proportion of classrooms in the project areas made of durable materials by 75%; (ii) training teachers and pedagogic

supervisors so as to increase the number of primary education inspectors by 50% in 2010 and re-qualify 75% of secondary teachers;

(iii) managing the project with emphasis on financial and physical implementation. The project helped increase school infrastructure for

basic education and sustainably reinforced initial and continuing training structures for teachers as well as staff of the primary and

secondary supervision and inspection agency, the Higher Institute of Education (ISSED). It also helped strengthen the national and

decentralized pedagogic supervision and monitoring mechanisms. It improved institutional conditions for training qualified personnel in

the country for primary and secondary education institutions. In addition, the project helped enhance scientific and technical education

for girls by providing computer and science equipment to Am-Riguebe Girls' High School.

2. Outcome Reporting

Outcome indicators (as

per RLF; add more rows as needed)

Baseline Value

(year)

Most Recent Value

(A)

End Target

(B) (expected value at project

completion)

Progress towards Target

(% realized)

(A/B)

Narrative Assessment

(Indicative max. length: 50 words per outcome)

Core Sector Indicator

(Yes/No)

Outcome 1: Gross primary and secondary enrollment rate.

85% (51% girls)

(2001)

12% (Seconda

ry

94% (80% girls)

(2011)

23% (2011)

100% (2015)

30%

94%

76.6%

These increases are the result of concerted action through the PARSET.

Yes

Outcome 2: Number of girls admitted each year to the scientific baccalaureate programme at Am-Riguebe Girls’ High School

0

39

50

78%

The number of girls admitted each year to the scientific baccalaureate programme at Am-Riguebe Girls’ High School is highly erratic and varies from one year to the next.

Yes

Outcome 3. Ratios: -Student/teacher ratio

160/1 in 2004

63/1 in 2010/201

1

60/1 in 2015

95.24% The increased number of teacher training schools, and emphasis on the training of pedagogic staff under context of PARSET and PASE were crucial in the improved student/teacher ratio.

Yes

Outcome 4: Success rate of interns in training at ISSED

80% 95 99 95.95% The creation of improved teaching conditions at ISSED through provision of modern infrastructure and pedagogic materials produced satisfactory results.

Yes

Page 6: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

5

Rating (see IPR

methodology)*

Narrative Assessment

2 The baseline situation and outcomes could not be precisely defined for each outcome indicator due to weaknesses in monitoring and evaluation.

3. Output Reporting

Output Indicators (as

specified in the RLF; add more rows if needed)

Most Recent Value

(A)

End Target (B)

(expected value at project

completion)

Progress towards Target

(% realized) (A/B)

Narrative Assessment

(indicative max. length: 50 words per output)

Core Sector Indicator

(Yes/No)

Output 1: Number of new primary classrooms built

147 225 classrooms

65.33% The original plan provided for construction of 225 classrooms, but the objective was reduced to 147 classrooms in light of cost overruns due to increased costs of building materials.

Yes

Yes

Output 2:

Number of two-unit latrine blocks built for primary schools

49 75 two-unit latrine blocks

65.33% The original plan provided for construction of 75 two-unit latrine blocks, but the objective was reduced to 49 two-unit latrine blocks in light of cost overruns due to increased costs of building materials.

Yes

Output 3: Number of

wells sunk at primary schools

24 75 32% The original plan provided for 75 wells to be sunk, but the target was reduced to 24 wells in light of the reduced number of classrooms built.

Yes

Yes

Output 4:

Quantity of scientific and computer equipment purchased for the girls' high school

1 lot of scientific

equipment

20 computers

1 lot of scientific

equipment

20 computers

100%

100%

The scientific equipment for the student programme was purchased and made available to the students for science classes. 20 computers were purchased as planned.

Yes

Output 5:

Number of tables/benches and teachers’ desks purchased for the classrooms

2,016

96

5,000

225

40.32

42.66

Because of the lengthy procurement process, only 2,016 tables/benches and 96 teachers’ desks were delivered at project completion. The Government should provide payment for the equipment to be delivered after the project closing date of 29 June 2013.

Yes

Output 6: Number of

primary school pedagogic advisors and inspectors trained (initial training)

627 1,070 58.60 The competitive recruitment process did not produce the anticipated 1,070 pedagogic staff. However, a total of 627 candidates from all categories (teachers, pedagogic advisors, and inspectors) were recruited and trained.

Yes

Output 7:

Kits for pedagogic advisors and inspectors

630 700 90 630 of the 700 kits planned were purchased and made available to teachers.

Yes

Output 8:

New buildings completed at ISSED/ -Classrooms -Office -Language lab -Cartography lab -Computer room -Residence

5 1 1 1 1

150 places

5 1 1 1 1

96 places

100% 100% 100% 100% 100% 64%

The ISSED was provided with new infrastructure enabling it to fulfill its role as training institute.

Yes

Output 9:

ISSED infrastructure

The project renovated and equipped the badly aged ISSED infrastructure.

Yes

Page 7: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

6

rehabilitated -Classrooms -Offices -Library

8 12 1

8 12 1

100% 100% 100%

Output 10:

Scientific and didactic equipment purchased for ISSED 30 student workstations, 1 teacher control station, 11 video recorders. 1 lot of laboratory equipment, 2 generator units, transportation equipment vehicles library equipment, 250 sets of cutlery

30 student workstations, 1 teacher control station, 11 video recorders. 1 lot of laboratory equipment, 2 generator units, transportation equipment vehicles library equipment, 250 sets of cutlery, and kitchen refrigeration equipment

30 student workstations, 1 teacher control station, 11 video recorders. 1 lot of laboratory equipment, 2 generator units, transportation equipment vehicles library equipment, 250 sets of cutlery, and kitchen refrigeration equipment

100% 100% 100%

All the equipment planned for the various ISSED facilities (i.e., language laboratory, audiovisual room, classrooms, computer room, dormitories and canteen) was purchased and delivered.

Yes

Output 11: Institutional

study of ISSED completed

One study One study was

completed

100% The structural and pedagogic reform of ISSED is based on that study.

Yes

Output 12:

Secondary education programs revised

Education programmes

The education programmes

were prepared

100% This activity was conducted entirely by the National Curricula Centre (CNC), which received institutional strengthening in that context.

Yes

Output 13: MDG

indicator monitoring and evaluation put in place and operational -Study completed and indicators defined -Annual report produced, including sector MDGs

1 study

1 annual report

1

1 annual report

100%

100%

The MDG indicator monitoring and evaluation mechanism was put in place.

Yes

Rating (see IPR

methodology)*

Narrative Assessment

2 The expected results were not attained for certain indicators, particularly with respect to the number of classrooms to be built. However, the teacher training activities established the conditions for a lasting improvement in quality.

4. Development Objective (DO) rating

1

Development objective (DO) rating (derived

from updated IPR)*

Narrative assessment

2 The project contributed to progress towards achieving the MDGs for education (particularly basic education) by improving primary and secondary teacher training and improving secondary science education for girls.

1 For operations using the old supervision report and rating system in SAP, the DO rating for the PCR shall be calculated

using the IPR methodology.

Page 8: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

7

5. Beneficiaries (add rows as needed)

Actual (A) Planned (B) Progress towards Target

(% realized A/B)

% of Women Category (e.g., farmers,

students)

8000 12,000 primary school students,

girls and boys, from 2 priority areas representing

42.33% of total students

66.6% NA Students

647 1,070 primary and secondary

teachers, inspectors and pedagogic

advisors

60.4% NA Teachers and pedagogic supervisory staff

6. Unanticipated or Additional Outcomes (add rows as needed)

Description Type (e.g. gender,

climate change, social, other)

Positive or Negative

Impact on Project

(High, Medium, Low)

The wells provided by the project at certain schools represent a contribution to access to drinking water and lighten the burden of women who previously traveled longer distances every day to find water.

Social Positive Medium

7. Lessons learned related to effectiveness (add rows as needed)

Key Issues (max. 5; add rows as needed) Lessons Learned Target Audience

1. Inadequate harmonization of various complementary project activities (construction, rehabilitation and equipment) delayed the start of teacher training and the overall project implementation schedule.

1. Better programming at the outset and better planning of procurements are required for proper implementation of complementary activities.

1. The Bank and the Borrower

C Efficiency

1. Timeliness

Planned Project Duration – years (A)

(as per PAR)

Actual implementation time – years (B) (from effectiveness for 1st

disbursement)

Ratio of planned and actual implementation time (A/B)

Rating*

5 years 8 years 62.5% 2

Narrative Assessment (indicative max. length: 250 words)

There was a delay of more than two years with respect to the initial schedule. This was due to delays in start-up as well as the events of February 2008 (destruction and looting of the Ministry and Executing Agency offices), which necessitated rehabilitation of sites and equipment and reconstitution of files.

2. Resource Use Efficiency

Median% physical implementation of RLF outputs financed by all financiers

(A) (see II.B.3)

Commitment rate (%) (B)

(see Table 1.C – Total commitment rate of all financiers)

Ratio of the median percentage physical implementation and

commitment rate (A/B)

Rating*

80% 81.83% 97.76% 2

Narrative assessment (indicative max. length: 250 words)

The problem was more a matter of timeliness than resource use efficiency. The resources were used in proportion to the works completed, but the physical organization of works did not comply with the implementation schedule. The results obtained are commensurate with the resources mobilized by the partners.

Page 9: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

8

3. Cost-benefit Analysis

Economic Rate of Return (at approval)

Updated Economic Rate of Return (at completion)

Rating*

NA NA 3

Narrative Assessment

The economic rate of return was not calculated under the project assessment due to the nature of the project.

4. Implementation Progress (IP)2

IP Rating (derived from updated IPR) *

Narrative comments (commenting specifically on those IP items that were rated Unsatisfactory or Highly Unsatisfactory, as per the last IPR)

2 The implementation of project activities, originally planned for five years, was delayed even with the two justified requests for extension granted by the Bank on 31 December 2011 and 29 June 2012. The original schedule was delayed by a total of 24 months. The mid-term review planned for June 2007 was not conducted until 8-17 December 2008, and the original closing date of 30 June 2010 was extended to 29 June 2012. The purpose of the two extensions was to make up for the delays and other setbacks, including the damage caused during the political events of 2008. However, the weak capacity of certain firms and the extent of the work uncompleted continue to have a negative effect on the expected results in terms of quality of construction work. Close monitoring of project activities by the Bank's Country Office in Chad from 2007 could have improved the situation, but weaknesses on the part of construction firms were a major handicap. The frequency of Steering Committee meetings and efforts of the inspection office did not provide the relevant monitoring to clearly identify weaknesses and failings in project implementation. The project helped strengthen national capacities in initial and continuing teacher training and trained primary and secondary teaching and pedagogic supervisory staff. The overall physical implementation rate may be estimated at 80% compared to a financial implementation rate of 72.38% (grant). The environmental safeguard measures were observed by most of the construction firms. People were not relocated.

5. Lessons learned related to efficiency

Key issues (max. 5; add rows as needed) Lessons learned Target audience

1. The number of classrooms to be built appeared too high in light of the distances between sites spread over several regions, the available resources and the cost of building materials in Chad. The executing agency reallocated resources to take account of actual circumstances.

1. Limit interventions of this type to modest proportions and to one or two clearly delimited regions, taking account of site accessibility.

1. The Bank and the Borrower

D Sustainability

1. Financial Sustainability

Rating* Narrative Assessment

2 The project is a social project. However, unless the Government takes charge of the outstanding construction work, financial sustainability will be compromised.

2. Institutional Sustainability and Strengthening of Capacities

Rating* Narrative Assessment

3 The project had a significant impact on strengthening institutional capacities and teacher training for primary and secondary education through institutional support for ISSED (infrastructure, equipment, technical assistance and effective implementation of the initial and continuing training programmes). As a result, ISSED will sustainably help provide Chad with the teachers it needs to improve access to quality education.

2 For operations using the old supervision reporting and rating system in SAP, the IP ratings need to be converted from the

old 0-3 scale used in SAP to the 1-4 scale used in the IPR.

Page 10: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

9

3. Ownership and Sustainability of Partnerships

Rating* Narrative assessment

3 Project implementation helped increase the involvement of beneficiaries (local authorities, parent associations) in site selection and the monitoring of construction works. The overall implementation context of the PARSET (multi-donor programme) to which the project contributed encouraged stakeholder participation, which will help ensure sustainability of project outcomes.

4. Environmental and Social Sustainability

Rating* Narrative Assessment

3 The project had no adverse effects on the environment. The environmental safeguard measures were observed by most of the construction firms. People were not relocated.

5. Lessons learned related to sustainability

Key Issues (max. 5; add rows as needed) Lessons Learned Target Audience

1) The performance and reliability of construction firms

The process of awarding construction contracts should accord considerable weight to the construction firms' financial and technical capacity in the area of civil engineering works.

Government

2) Need to continue teacher training to ensure steady improvement of the student/teacher ratio

The Government should continue teacher training at ISSED with its own resources in order to ensure continuity of training for secondary school teachers and achieve the objective of better student supervision.

Government

3) Maintenance of buildings constructed The school buildings should receive periodic maintenance from the Government in order to maintain satisfactory learning conditions. The local authorities and parent associations should be involved in this effort.

Government

III Performance of Stakeholders

A Relevance

1. Bank Performance

Rating* Narrative assessment by the Borrower on the Bank’s performance, as well as any other aspects of the project (both quantitative and qualitative). See guidance note on issues to cover.

3 The Government prepared the project completion report jointly with the Bank and appreciated the monitoring conducted by the Bank from project start-up. However, the Government criticized the delays in handling procurements.

Comments to be inserted by the Bank on its own performance (both quantitative and qualitative). See guidance note on issues to cover.

The project was designed in cooperation with the other development partners under PARSET. The Bank fulfilled its commitments to the Borrower. It disbursed the approved resources (OSHD and TDFO) and helped the Borrower resolve problems impacting on implementation. For example, following the events of February 2008 (looting, vandalism, theft, destruction of the Executing Agency’s equipment and documents), the Bank disbursed funds to enable the Executing Agency to resume operations. The opening of N'Djamena Country Office facilitated close monitoring of technical implementation by TDFO as from 2008. However, financial management was not monitored on a regular basis. The May 2011 financial management mission considered the project financial management unsatisfactory. Not all audit report recommendations were implemented. Supervision missions were conducted on a regular basis, but it should be noted that the teams generally did not include experts in fiduciary aspects. The sole procurement expert assigned to TDFO has too heavy a workload to process procurement documents on a timely basis.

Key issues (related to Bank performance, max. 5; add rows as

needed) Lessons learned

1. Composition of supervision missions. The project financial implementation revealed problems that could have been avoided through more rigorous financial monitoring.

The supervision teams should be required to include experts on fiduciary issues (FFCO, ORPF).

2. Delays by the Bank in processing procurement documents. Insufficient ORPF1 staffing resulted in delays in processing procurement document. The office staffs should include additional procurement experts.

Page 11: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

10

3. Borrower Performance

Rating* Narrative assessment on the Borrower performance to be inserted by the Bank (both quantitative and qualitative, depending on available information). See guidance note on issues to cover.

2 The Borrower's commitment to the project objectives was maintained throughout the implementation phase. However, frequent structural and institutional changes hampered continuity of ownership at the responsible Ministry. The counterpart contribution was not disbursed on a regular basis. There were numerous weaknesses in construction contract management, undermining discipline at the firms and resulting in uncompleted work. There were also non-eligible expenditures paid from the revolving capital, leading to rejections by the Bank and delays in renewing the special advance. The annual audits were not conducted on time, and the reports were submitted to the Bank late. The audit recommendations were only partially implemented.

Key issues (related to borrower performance, max. 5; add rows as

needed ) Lessons learned

1) The performance of the Project executing Agency was not satisfactory.

2) The counterpart funds were not disbursed on a regular basis.

1) Members of the Project Executing Agency should be recruited based on performance criteria and evaluated each year.

2) The disbursement of counterpart funds should be better planned.

4. Performance of other Stakeholders

Rating* Narrative assessment on the performance of other stakeholders, including co-financiers, contractors and service providers. See guidance note on issues to cover. (indicative max. length: 250 words)

3 The project was prepared in cooperation with the World Bank under the PARSET 2004-2007. The World Bank provided for the wells drilled at two of the AfDB school sites (Mourrakatchine and Assartini). The AfDB and World Bank missions are not joint missions, but they exchange information relating to two complementary projects. The World Bank faced the same problem of cost overruns. The parents’ associations were very cooperative in monitoring the classroom construction works. Certain civil engineering firms played a negative role in not cooperating with the Government and not producing quality of work. The OPEC Fund contributed substantially to financing the classroom and ISSED infrastructure. In the absence of a local representative of the OPEC Fund, communication between the Bank and the OPEC Fund was somewhat problematic.

Key issues (related to performance of

other stakeholders, max. 5; add rows as needed)

Lessons learned (max. 5) Target audience (for

lessons learned)

1) Coordination of monitoring. The absence of an OPEC representative in N'Djamena hampered effective coordination of technical and financial implementation. The Bank implemented the OPEC payroll disbursement procedures; the payments were often late.

2) Certain firms lacked the financial capacity and technical expertise required for the construction works.

1) The Bank and OPEC should arrange for joint technical monitoring in order to develop a consistent perception of progress that facilitates management of the OPEC loan.

2) Construction firms should be hired on the basis of criteria compatible with the public procurement code.

Bank, OPEC, Government Government, Bank

IV. Summary of key lessons learned and recommendations

1. Key lessons learned

Key issues (max. 5; add rows as needed) Key lessons learned Target audience

1. Security risk. The events of February 2008 (looting, vandalism, theft, destruction of the Ministry and Executing Agency offices) caused significant delays in project implementation.

1. The Government should undertake to provide security for project sites.

Government

2. A large number of classrooms were not completed. This construction is financed with the OPEC loan.

2. Cover the cost of completing the works with own resources or OPEC resources.

Government

3. Coordination of monitoring. The absence of an OPEC 3. The Bank and OPEC should arrange for Bank, OPEC

Page 12: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

11

representative in N'Djamena hampered proper coordination of technical and financial implementation. The Bank implemented the OPEC payroll disbursement procedures; the payments were often late.

joint technical monitoring to develop a consistent perception of progress that facilitates management of the OPEC loan.

4. Composition of supervision missions. The project financial implementation recorded problems that could have been avoided through more rigorous financial monitoring.

4. The supervision teams should include experts in fiduciary issues (FFCO, ORPF).

Bank

2. Key Recommendations (with particular emphasis on ensuring the sustainability of project

benefits)

Key Issues (max. 10; add rows as needed) Key Recommendations Responsible Deadline

1. Actual costs greatly exceeded the forecasts. 1. Provide a larger margin for inflation during project design.

Bank -

-

2. The monitoring of construction works by the Executing Agency and consulting was deficient.

2. Systematize technical audits for projects including infrastructure components.

Bank

3. The long distances between sites hampered the implementation and monitoring of works.

3. Clearly delimit the project area and refrain from selecting sites located far apart.

Government -

4. A large number of tasks were assigned to a single firm that lacked the requisite capacities.

4. The selection of firms should be based on their effective capacity and performance on similar projects.

Government, Bank -

5. Composition of supervision missions. The project financial implementation revealed recorded that could have been avoided through more rigorous financial monitoring.

5. The supervision teams should include experts in fiduciary issues (FFCO, ORPF).

Bank -

6. A large number of classrooms were not completed. This construction is financed with the OPEC loan.

6. Cover the cost of completing the works with own resources or OPEC resources.

Government End 2013

V Overall PCR rating

Dimensions and criteria Rating*

DIMENSION A: RELEVANCE 3

Relevance of project development objective (II.A.1) 3

Relevance of project design (II.A.2) 3

DIMENSION B: EFFECTIVENESS 2

Development objective (DO) (II.B.4) 2

DIMENSION C: EFFICIENCY 2.25

Timeliness (II.C.1) 2

Resource use efficiency (II.C.2) 2

Cost-benefit analysis (II.C.3) 3

Implementation progress (IP) (II.C.4) 2

DIMENSION D: SUSTAINABILITY 2.75

Financial sustainability (II.D.1) 2

Institutional sustainability and strengthening of capacities (II.D.2) 3

Ownership and sustainability of partnerships (II.D.3) 3

Environmental and social sustainability (II.D.4) 3

OVERALL PROJECT COMPLETION RATING 2.62

Page 13: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

12

VI Acronyms

Acronym (add rows as needed) Description

BEPC: First Cycle Certificate (Brevet d’études du premier cycle) IDB: Islamic Development Bank CAP: Vocational Proficiency Certificate (Certificat d’aptitude professionnel) CAPEL: Teacher Certification (Certificat d’aptitude au professorat de l’enseignement littéraire) CEG: General Secondary School (Collège d’enseignement général) CEPE: Primary School Leaving Certificate (Certificat d’études primaires élémentaires) CONEFE: National Education, Training and Employment Committee (Comité National pour l'Education et la Formation en liaison avec l'Emploi) CET: Technical Secondary School (Collège d'Enseignement Technique) CNC: National Curricula Centre CPES: Secondary Education Pedagogic Advisor (Conseiller pédagogique de l’enseignement secondaire) CPOP: Practical Education Pedagogic Advisor (Conseiller pédagogique à orientation pratique) CSPE: ADF Education Projects Monitoring Unit (Cellule de suivi des projets Education FAD) BD: Bidding Documents DREN: Regional National Education Delegate (Délégué régional de l’éducation nationale) PRSP: Poverty Reduction Strategy Paper CSP: Country Strategy Paper ETE: Education-Training-Employment (Strategy) ENI: Teacher Training School (Ecole normale d’instituteurs) ADF: African Development Fund GTZ: German Cooperation IEE: Primary Education Inspector IGES: Secondary Education Inspector INSE: National Institute of Education (Institut national des sciences de l’Éducation) IPEN: National Primary Education Inspectorate (Inspection primaire de l’éducation nationale) ISSED: National Institute of Education (Institut National des Sciences de l’Éducation) LOC: West Logone Region LOR: East Logone Region MEN: Ministry of National Education MEPEC: Ministry of Primary and Civic Education MESRSFP: Ministry of Tertiary Education, Scientific Research and Vocational Training NICT: New Information and Communication Technologies MDG Millennium Development Goals OPEC: Organization of Petroleum Exporting Countries PAEF: Education and Training Action Programme (Programme d’action pour l’éducation et la formation) PAN/EPT: National Education for All Action Plan PARSET: Chad Education Reform Support Project (Projet d’appui à la réforme de l’éducation au Tchad) PDDEA: Ten-year Education and Literacy Development Plan (Plan décennal de développement de l'éducation et de

l'alphabétisation) UNDP: United Nations Development Program SE/CONEFE: Executive Secretariat of the National Committee on Education, Training and Employment SIPEA: Interim Education and Literacy Strategy (Stratégie intérimaire pour l’éducation et l’alphabétisation) NPRS: National Poverty Reduction Strategy EU: European Union

Page 14: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

I

Annex 1: Supervision Missions

No. Missions

Start

End

1

2

3

4

5

6

7

8

9

10

11

12

13

14

SUPERVISION

SUPERVISION

SUPERVISION

SUPERVISION

MID-TERM REVIEW

SUPERVISION

SUPERVISION

SUPERVISION

SUPERVISION

SUPERVISION

SUPERVISION

SUPERVISION

SUPERVISION

SUPERVISION

03/08/2005

10/23/2005

10/31/2006

06/10/2007

12/08/2008

05/25/2009

12/15/2009

04/21/2010

11/22/2010

05/02/2011

06/27/2011

12/01/2011

03/01/2012

06/18/2012

03/16/2005

11/02/2005

11/11/2006

06/24/2007

12/17/2008

06/04/2009

12/30/2009

04/30/2010

12/06/2010

05/13/2011

06/30/2011

12/09/2011

03/10/2012

06/22/2012

Page 15: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

II

Annex 2: Implementation Progress and Results (IPR) Report

A Summary of report and proposed actions

Report data

Type of report:

Report date: 05/23/2013 Mission date (if field mission)

Start-up/field supervision mission/MTR/summary review/other (specify): Project completion report

From: 01/09/2013 A:01/28/2013

Prepared by: Talansadi Djogoye

Project Manager: Corbin Michel Guedegbe

Alternate Project Manager: Talansadi Djogoye

Division Manager: Boukary Savadogo

Project data

Project Code: P-TD-IAZ-002 Instrument Number(s):

2100155002166 (grant)

Project Title: Education Sector Support Project (PASE) Country: CHAD Sector: EDUCATION

Processing milestones - Bank approved financing only

(add/delete rows depending on the number of financing sources

Key Events (Bank approved financing only)

Disbursement and closing dates (Bank approved financing only)

Financing source/instrument 1:

ADF Grant: UA 2,400,000 Date approved: 03/31/2004 Date signed: 05/26/2004 Date of entry into force: 02/14/2005 Date effective for 1st disbursement: 4 May 2005 Date effective for 1st disbursement: 4 May 2005

Financing source/instrument 1: ADF

Grant: UA 2,400,000 Canceled amounts: UA 662,891.53 Supplementary financing: NA Restructuring (specify date and amount involved): NA

Extensions (specify dates): 12/31/2011 06/30/2012

Financing source/instrument 1: ADF

Grant: UA 2,400,000 Original disbursement deadline: 06/30/2010 Original closing date: 06/30/2010 Revised disbursement deadline (if applicable): 12/31/2011 Revised closing date (if applicable): 06/30/2012

Financing source/instrument 2: UA

320,000 Date approved: 03/31/2004 Date signed: 26 May 2004 Date of entry into force: 14 February 2005 Date effective for 1st disbursement: 1 October 2005 Date effective for 1st disbursement: October 1, 2005

Financing source/instrument 2: UA

320,000 Canceled amounts: 0 Supplementary financing: SO Restructuring (specify date and amount involved): SO Extensions (specify dates):

12/31/2011 06/30/2012

Financing source/instrument 2: UA 320,000

Original disbursement deadline: 06/30/2010 Original closing date: 06/30/2010 Revised disbursement deadline (if applicable): 12/31/2011 Revised closing date (if applicable): 06/30/2012

Financing source/instrument (add/delete rows depending on the number of financing sources):

Foreign currency (UA) Local currency (AU):

TOTAL (UA)

Financing source/instrument 1: ADF Grant: UA 2,400,000

1,500,000 900,000 2,400,000

Financing source/instrument 2: Government: UA 320,000

SO 320,000 320,000

OPEC Fund: UA 3,290,000 2,870,000 420,000 3,290,000

TOTAL: 4,370,000 1,650,000 6,000,000

Financing source/instrument(add/delete rows depending on the number of financing sources):

Disbursed amount (amount,

UA):

Disbursed to date (%):

Undisbursed to date (amount,

UA):

Undisbursed to date (%):

Financing source/instrument 1: UA 2,400,000

1,737,108.01 72.38 662,891.53 UA 37.62

Financing source/instrument 2: UA 320,000

289,024 90.32 30,976 07.68

Financing source/instrument 3: UA 3,290,000

2,892,000 87.90 398,000 12.10

TOTAL: 4,918,132.01 81.96 1,081,860 18.04

Page 16: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

III

Executing and implementing agency(ies):

MINISTRY OF NATIONAL EDUCATION, EDUCATION PROJECTS MONITORING UNIT (CSPE)

Co-financiers and other external partners:

<ENTER HERE>

Project Performance

Progress towards the development objective

Development objective (DO) rating

Performance rating Summary of Main Conclusions

Current Previous The project development objective is to help Chad achieve the Education for All (EFA) objectives and the Millennium Development Goals (MDGs) for the sector. This objective was to be achieved by: (i) improving the school infrastructure and environment so as to increase the proportion of classrooms in the project areas made of durable materials by 75%; (ii) training teachers and pedagogic supervisors so as to increase the number of primary education inspectors by 50% in 2010 and re-qualify 75% of secondary teachers; (iii) managing the project with emphasis on financial and physical implementation. The project helped increase school infrastructure for basic education and sustainably reinforced initial and continuing training structures for teachers as well as staff of the primary and secondary supervision and inspection agency, the Higher Institute of Education (ISSED). It also helped strengthen the national and decentralized pedagogic supervision and monitoring mechanisms. It improved institutional conditions for training qualified personnel in the country for primary and secondary education institutions. In addition, the project helped enhance scientific and technical education for girls by providing computer and science equipment to Am-Riguebe Girls' High School.

2 2.33

Implementation progress

Implementation Progress (IP)

Performance Rating Summary of Main Conclusions

Current Previous The implementation of project activities, originally planned for five years, was delayed even with the two justified requests for extension granted by the Bank on 31 December 2011 and 29 June 2012. The original schedule was delayed by a total of 24 months. The mid-term review planned for June 2007 was not conducted until 8-17 December 2008, and the original closing date of 30 June 2010 was extended to 29 June 2012. The purpose of the two extensions was to make up for the delays and other setbacks, including the damage caused during the political events of 2008. However, the weak capacity of certain firms and the extent of the work uncompleted continue to have a negative effect on the expected results in terms of quality of construction work. Close monitoring of project activities by the Bank's Country Office in Chad from 2007 could have improved the situation, but weaknesses on the part of construction firms were a major handicap. The frequency of Steering Committee meetings and efforts of the inspection office did not provide the relevant monitoring to clearly identify weaknesses and failings in project implementation. The project helped strengthen national capacities in initial and continuing teacher training and trained primary and secondary teaching and pedagogic supervisory staff. The overall physical implementation rate may be estimated at 80% compared to a financial implementation rate of 72.38% (grant). The environmental safeguard measures were observed by most of the construction firms. People were not relocated.

2 2.14

Overall Performance Classification

Overall project performance classification (PP, PPP or NPPP)

Project Status Summary of Main Conclusions

Current Previous At the closing date, the project was neither a potentially problematic project nor a problem project. Not PPP, Not

PP Not PPP, Not

PP

Page 17: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

IV

Problems, risks and measures submitted for management review

Problems affecting project implementation (Identify main obstacles to project implementation and measures submitted to management's attention)

Key problems Corrective measures Responsible Deadline

Cost overruns: The depreciation of the Bank's Unit of Account (UA), which was CFAF 847 at appraisal and averaged CFAF 740 over the 2005-2010 period, and the increased costs of building materials led to a reduction of the works and equipment planned.

The volume of works was reduced. Provide a larger margin for inflation during project design.

Bank/Government Ongoing

Unbalanced, ill-advised award of public contracts: A single firm (Al Mourque) was awarded three lots of classroom construction, or 105 of the total 147 classrooms (71.42%) compared to only 45 classrooms awarded to two other firms.

Close monitoring of the defaulting firm. The lesson for the future is not to award multiple lots to a single firm.

Government/Bank Ongoing

Long delays in the procurement process: Delays

ranging from 16 to 24 months were observed in the procurement process. This was due to slow administrative action in reviewing bidding documents and in routing contracts for sign-off.

Enforce the deadlines prescribed in the public procurement code.

Government Ongoing

Key risks and mitigation measures

(Identify main risks to project implementation and measures submitted to management)

Risks Mitigating measures applied or proposed

Responsible Deadline

The Government could record delays in taking charge of the completion of unfinished classrooms

A formal recommendation was made to the Government to take over responsibility for the unfinished works.

Ministry of Education

December 2013

Lack of maintenance of the completed buildings could result in rapid deterioration

Institution managers and parents’ associations (APEs) are made aware and involved in maintenance.

Institution managers, parents’ associations, MEN

Ongoing

An insufficient number of teachers to provide good student-teacher coverage.

Maintain the pace of teacher training.

Ministry of Education

Ongoing

Education statistics are not produced on a regular basis

Support INSEED in its role as source of data.

Government/Bank Ongoing

Management review and comments

Report reviewed by

Name Date of Review

Comments

Res.Rep Michel-Cyr Djiena Wembou 05/31/2013 Report validated

Regional Director Marlène Kanga <DD/MM/YYY

Y> <ENTER HERE>

Sector Manager Boukary Savadogo <DD/MM/YYY

Y> <ENTER HERE>

Sector Director Agnès Soucat <DD/MM/YYY

Y> <ENTER HERE>

Page 18: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

V

B Results Reporting and Assessment

Progress towards the project's development objective (project purpose)

State the project development objective (usually the project purpose as set out in the RLF) and assess progress

The project aims to contribute to the achievement of the Education For All (EFA) objectives for sustainable human development. This objective will be achieved by: (i) improving the school infrastructure and environment, (ii) enhancing the quality of teachers and pedagogic supervisors, and (iii) improving the capacity of the education system to monitor and evaluate performance.

Outcome Reporting

Outcome Indicators (as specified in

the RLF; add more rows as needed)

Reference value

Most recent value

Final target

(value expected at project completio

n)

Progress towards target (% realized)

Assessment

Outcome 1: Gross primary and secondary enrollment rate.

85% (51% girls) (2001)

12%

(Secondary

94% (80% girls) (2011)

23% (2011

100% (2015)

30%

94%

76.6%

The increase in the gross primary and secondary enrollment rate is the combined effect of all education sector projects.

Outcome 2: Number of girls admitted each year to the scientific baccalaureate programme at Am-Riguebe Girls’ High School

0

39

50

78%

The number of girls admitted each year to the scientific baccalaureate programme at Am-Riguebe Girls’ High School is highly erratic and varies from one year to the next.

Outcome 3. Ratio: Student/teacher ratio

160/1 in 2004

63/1 in 201/2011

60/1 in 2015

95.24% The increased ratio is the combined effect of sector projects in general.

Outcome 4: Success rate of interns in training at ISSED

80% 95 99 95.95% The interns' high success rate is attributable to the favorable learning conditions.

Outcomes Rating

Project Outcomes Rating

This report Previous report

Justification:

(A rating of 2 or 1, and the remedial measures proposed, should be discussed in the section on Issues, risks and measures submitted for management review).

2 - Progress towards the outcomes was achieved, particularly through the training of teachers and pedagogic supervisory staff. However, since fewer classrooms were completed than originally planned, the projected level of access was not achieved.

Page 19: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

VI

Output Reporting

Output Indicators (as

specified in the RLF; add more rows as needed)

Most recent value

Annual target

(cumulative

value expected at the end of

the year covered

in the report)

Final target

(cumulative value

expected at

completion)

Progress towards target (% realized)

Progress towards

the project's

final target (% realized)

Assessment

Output 1:

Number of new primary school classrooms built

147 225 classrooms

65.33 Due to increased costs of building materials, the number of classrooms to be built (225) was reduced to 147.

Output 2:

Number of primary school two-unit latrine blocks built

49 75 two-unit latrine blocks

65.33 Due to increased costs of building materials, the number of two-unit latrine blocks to be built (75) was reduced to 49.

Output 3: Number of

wells sunk at primary schools

24 75 32 The number of wells initially planned (75) was reduced to 49 in light of the reduced number of schools, but only 24 could be constructed.

Output 4:

Quantity of scientific and computer equipment purchased for the girls' high school

1 lot of scientific

equipment

20 computers

1 lot of scientific

equipment

20 computers

100

100

The scientific equipment provided for was purchased and delivered to Am-Riguebe Girls’ High School.

Output 5:

Number of tables/benches and teachers’ desks purchased for classrooms

2,016

96

5,000

225

40.32

42.66

The reduction in the number of classrooms to be built led to a reduction in the number of tables/benches and desks to be delivered.

Output 6: Number of

primary school pedagogic advisors and inspectors trained (initial training)

627 1,070 58.60 The competitive recruitment of training candidates did not produce the anticipated staff of 1,070.

Output 7:

Kits for pedagogic advisors and inspectors

630 700 90

Output 8:

New buildings completed at the ISSED/ -Classrooms -Office -Language lab -Cartography lab -Computer room -Residence

5 1 1 1 1

150 places

5 1 1 1 1

96 places

100 100 100 100 100 64

Output 9:

ISSED infrastructure rehabilitated -Classrooms -Offices -library

8 12 1

8 12 1

100 100 100

Page 20: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

VII

Output 10:

Scientific and didactic equipment purchased for ISSED 30 student workstations, one teacher control station, 11 video recorders. 1 lot of laboratory equipment, 2 generator units, transportation equipment vehicles library equipment, 250 sets of cutlery

30 student workstations, one teacher control station, 11 video recorders. 1 lot of laboratory equipment, 2 generator units, transportation equipment vehicles

library equipment, 250 sets of cutlery,

and kitchen

refrigeration

equipment.

30 student workstations, one teacher control station, 11 video recorders. 1 lot of laboratory equipment, 2 generator units, transportation equipment vehicles library equipment, 250 sets of cutlery, and kitchen refrigeration equipment.

100

100

100

100

100

100

Output 11: Institutional study of ISSED completed

One study One study was completed

100

Output 12: Secondary education programmes revised

Education programm

es

The education programmes were prepared

100

Outputs rating

Project outputs rating

This report Previous report Justification

(A rating of 2 or 1, and the remedial measures proposed, should be addressed in the section on Issues, risks and measures submitted for management review).

2 - Certain outputs fell short of the quantities planned (e.g., classrooms, latrine blocks, wells, teachers and supervisory staff).

Development Objective (DO) rating

Development Objective (DO) rating

This report Previous report Justification (A rating of 2 or 1, and the remedial measures proposed, should be discussed in the section on Issues, risks and measures submitted for management review)

2 - <see staff guidance>

Page 21: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

VIII

C Project implementation progress report and assessment

Compliance with Clauses

Criteria Number/percentage of

conditions met

Rating Assessment Accompanied by explanations of (a) ratings of 2 or 1 and (b) ratings below those of the

previous report

This report

Previous report

Compliance with project clauses (Complete report on compliance to be provided in Annex 2)

100% 4 - All other conditions precedent to entry into force, to first disbursement and Other conditions were fully met.

Compliance with environmental and social safeguards clauses (Complete report on compliance with safeguards clauses to be provided in Annex 3)

100% 4 - The environmental safeguard measures were observed by most of the construction firms. People were not relocated.

Compliance with audit clauses

75 3 - Six of the eight reports to be produced by the Executing Agency were prepared and transmitted to the Bank.

Project systems and procedures

Criteria Rating Assessment Accompanied by explanations of (a) ratings of

2 or 1 and (b) ratings below those of the previous report

This report Previous

report

Procurement of goods and services 2 - There were many difficulties with procurements conducted by the Executing Agency, particularly those involving certain civil engineering firms.

Financial management

1 - There were delays in conducting the audits of the annual project financial statements. The 2011 and closing financial statements have yet to be audited. The project also made ineligible expenditures that were reimbursed on the recommendation of the Bank's supervision missions.

Monitoring and evaluation

1 - The Executing Agency does not include an individual responsible for monitoring and evaluation. As a result, the coordinator performs the monitoring and evaluation function himself.

Page 22: Chad - Education Sector Support Project (PASE) - Project ... · The project development objective is to contribute to Chad's achieving the Education for All (EFA) objectives and the

IX

Project implementation and financing

Criteria Total amount

(a) UA

Cumulative

amount to date

(b)

Cumulative amount at beginning of year (c)

Annual projection (cumulated

amount expected at year end)

(d)

Progress towards

the annual

projection (%

realized) (b-c)/(d-

c)

Progress towards the total projectio

n (% realized)

Rating

This report

Previous report

Disbursements (Bank approved financing only)

1,737,108.01

1,737,108.01

1,737,108.01

72.38% 3 -

Budget commitments (Bank approved financing only)

Disbursements of counterpart funds

289,024 289,024 90.32% 3 -

Disbursements of co-financing funds

2,892,000 2,892,000 87.90 3

Criteria Assessment With explanation for (a) ratings of 2 or 1 and (b) ratings lower than in the previous report

Disbursements (Bank approved financing only)

Bank disbursements proceed without difficulties if the donor complies with Bank procedures.

Budget commitments (Bank approved financing only)

<see staff guidance>

Disbursements of counterpart funds The Government did not disburse all the counterpart funds. Moreover, the disbursements made were irregular, and this sometimes delayed the implementation of activities financed with counterpart funds.

Disbursements of co-financing funds The OPEC Fund is the co-financier, but the Bank administers the funds. There were some communication problems between the OPEC Fund and the Bank and between the Government and the OPEC Fund.

Overall Implementation Progress (IP) rating

IP rating

This report Previous

report

Justification

(A rating of 2 or 1, and the remedial measures proposed, should be discussed in the section on Issues, risks and measures submitted for management review)

2 - The implementation of project activities, originally planned over five years, was delayed even with the two justified requests for extension granted by the Bank on 31 December 2011 and 29 June 2012. The original schedule was delayed by a total of 24 months. The overall physical implementation rate is estimated at 80%.