ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.
Brian Foster - ILC@KEK 1 European perspectives for the ILC Brian Foster Oxford Specific examples of...
-
Upload
marvin-boyd -
Category
Documents
-
view
216 -
download
1
Transcript of Brian Foster - ILC@KEK 1 European perspectives for the ILC Brian Foster Oxford Specific examples of...
Brian Foster - ILC@KEK
1
European perspectives for the ILC
Brian Foster
Oxford
Specific examples of ongoing workfrom collaborations and major countries
Summary
ILC@KEKNov. 13th, 2004
General outline of ILC-related collaboration in Europe.
Important areas for future work
Brian Foster - ILC@KEK
2
Euro Collaborations
TESLA (wider than Europe alone)
Coordinated Accelerator Research in Europe
EuroTeV - LC research programme
UK Linear Collider Accelerator & Beam DeliveryLCABD – PPARC & CCLRC-funded
European XFEL
Brian Foster - ILC@KEK
3
TESLA
55 Institutes in 12 countries(43 institutes 9 countries in Europe).
Successful (ever growing) collaboration for over a decade.
Responsible for developing SCRF to the point where it is a viable option for a Linear Collider.
TESLA collaboration continues to evolve:- no longer a collaboration focused on ILC; - many institutes interested in ‘technology’ (for light sources, ERL etc.);- ‘mission’ now to advance SCRF technology(main customers: XFEL, ILC, Proton Driver…)
Brian Foster - ILC@KEK
4
TESLA TTF
Significant (currently unique) infrastructure(~140 M€ investment)
Brian Foster - ILC@KEK
5
TESLA TTFFacilities:Cavity preparationClean roomsHP rinsing facilityEP facility
Test stands:Vertical test cryostat (low power)Horizontal test stand(CHECHIA, high-power)Module test stand (end 2005)800 MeV LINAC (TTF2)Complete systems testingVUV-FEL user facility(currently being commissioned)30% dedicated beam time for ILC R&D.
Brian Foster - ILC@KEK
6
ACC 2 & ACC 3
TTF2 Commissioning
VUV FEL User Facility:
linac Commissioning done;beam established to dump without major delay;SASE FEL Comm. is starting.
RF gun
400 MeV 120 MeV800 MeV
ACC 1ACC 2ACC 3ACC 4ACC 5
4 MeV
TESLA like tunnel for ACC 6 & ACC 7
Second BunchCompressor
ACC 4 & ACC 5
Brian Foster - ILC@KEK
7
Euro XFEL
German government Feb. 2003 gave go-ahead for XFEL as European project, incl. funding 50% of total 684 M€ (year 2000) project cost, + contribution from Länder HH & Schleswig-Holstein. ~ 40% required from European Partners.
Project currently being organised at European Level (scientific/tech. & admin./financial) ongoing- to be completed by 2005.
In Sep. 2004, 9 European countries decided to sign MoU for project preparation phase.
Brian Foster - ILC@KEK
8
Euro XFEL Synergy4th generation SR user facility with SASE-FEL concept in the 1 – 64 Angstrom wavelength and 100fs (→ < 1fs) pulse length regime.
In first stage, 3 SASE & 2 spontaneous undulator beam lines, 10 experimental stations.
Driver: 1.5km linac in TESLA technology, 20GeV beam energy @ gradient of 23MV/m.
120 accelerator modules (~ 1000 cavities) and ~35 RF stations to be produced by industry.
~15 M€ R&D on LINAC TECH. (including Infrastructure); ~40 DESY FTE.
Brian Foster - ILC@KEK
9
Euro XFEL SynergySome examples of ongoing work relevant to ILC:
Qualification of 3 vendors (Eu., US and J) for 10 MW MBK production (2004 – 2005);Industrial studies & prototypes for horizontal klystron/tunnel installation (2005 – 2006).Involve industry in string & module assembly: 3 industrial studies;Industrial studies for RF coupler fabrication (procurement & tests of prototypes at LAL/Orsay);Improvement of tuner design incl. piezo (Coll. CEA/Saclay);Further experience with EP treatment, improve statistics for cavities with 800C/not 1400C baking.Build up module test stand (1st test candidate will be Module#6 with 35MV/m cavities) → end of 2005.Develop & test cold BPMs (coll. CEA/Saclay).
Brian Foster - ILC@KEK
10
CARECARE is EU FP6-funded programme on CoordinatedAccelerator Research in Europe. It is a very broad programme, incorporating e.g. work on SC high-intensityproton linacs, high-field magnet development, etc. Herewe are concerned only with those elements directly related to ILC.
The most relevant workpackage is on SCRF. Here thereare 11 institutions involved: DESY, CEA/DSM/DAPNIA,CNRS-IN2P3-Orsay, INFN Legnaro, Milano, Roma2, Frascati, Paul Scherrer Institute, Technical University of Lodz,Warsaw University of Technology, IPJ Swierk.
Budget is 19 M€ over 4 years, incorporating ~44 FTE. There issignificant overlap with TESLA / TTF / XFEL.
Brian Foster - ILC@KEK
11
CARE
CARE SCRF activities include:Improved Standard Cavity Fabrication;Seamless Cavity Production;Thin Film Cavity Production;Surface Preparation - EP, dry ice;Material Analysis: Scanning;Input coupler;Cold tuners;Low Level RF (LLRF);Cryostat Integration Tests;Beam Diagnostics (BD);Hydroforming
Dry-ice cleaning
Coupler design(industrialisation)
Cold tuner development
Improvements in EP
Brian Foster - ILC@KEK
12
EuroTeV
EuroTeV programme alsoEU FP6 funded. It is purely concerned with LC – generic matters of use both to ILC and CLIC. Focussing on ITRP R2 items. Will form part of European Design Team.
Beam Delivery System
Damping Rings
Diagnostics
Metrology &
Stabilisation
Global Accelerator
Network
IntegratedLuminosity
PerformanceStudies
Polarised Positron Source
Scientific coordinationfrom CERN &DESY
Brian Foster - ILC@KEK
13
EuroTeV27 institutes participate: HU Berlin, Birmingham, Bristol,Cambridge, CCLRC, CEA, CERN, Darmstadt, DESY,Elettra, FHI-IGD, GSI, LAL, INFN-Frascati, Lancaster,LAPP, Liverpool, Manchester, Mannheim, Oxford, PSI,QMUL, RHUL, Rostock, UCL, Udine, Uppsala
Total Budget is 27.6 M€, of which EU contribution is 9 M€.Funds 110 FTE, of which 30 are new posts funded by EU.
Expect to align detailed activities within GDE context over next few months. There is some flexibility – but we are contractually obliged to deliver on whatever we finally define.
Mostly Accelerator-Physics-related R&D.Little effort included for major engineering – i.e. actuallybuilding a major accelerator facility.
Brian Foster - ILC@KEK
14
UK LC-ABDAbertay, B’ham, Bristol, Cambridge, CCLRC(DL & RAL), Durham, Lancaster, Liverpool, Manchester, Oxford, QMUL, RHUL, UCL working on coordinated beam-delivery system project. Also two newAccelerator Institutes, Cockroft & Adams, playing major role.
Lattice design:
Xing angle, extraction, interaction region, collimation
optimising optics designs w. DESY, Saclay, Orsay ….
0
100
200
300
0 100 200 300 400 500 600S(m)
b1/2
(m1/2
)
0.00
0.04
0.08
0.12
0.16
0.20
h(m
)
HorzVertDispersion
Final Focus Optics for L*=5m with quadruplet
Beam transport:
damping ring to dump, halo modelling, backgrounds
developing integrated simulations w. DESY, SLAC, LBL …
Instrumentation:
laserwire, longit. profile, polarimetry, E-spectrometry
building prototype devices + beam tests w. DESY, KEK, SLAC …
Alignment:
LiCAS FSI automated survey system, active stabilisation
building prototype survey-car system w. DESY
Beam feedback/control:
FONT fast (intra-train) FB system building prototype kickers, amplifiers, BPMs + beam tests w. SLAC, KEK
Positron source undulator, crab cavity, collimators:
building + testing prototypes / design study / materials simulations+tests
Three-year progamme; 41 post-doc physicists + technical staff + graduate students + 23 new posts (20 now filled). 15 M€ programme; significant overlap with EuroTeV – ~ 2/3 of staff in EuroTeV – to which UK is biggest contributor.Committed to produce list of concrete deliverables.
Brian Foster - ILC@KEK
15
Other UK interestsRF system components:
industrial interest in engineering prototypes of klystrons, modulators, couplers . Nb cavity&module assembly + system tests: synergy with 4GLS project.
Damping ring design: long experience from SRS to DIAMOND/4GLS;synergy with Diamond 3rd gen light source.
Diagnostics, feedback, control:BPMs, charge monitors, FB etc. beyond BDS - SRS, Diamond experience
Electron source: RF photocathode: synergy with 4GLS. Long experience with lasers in many applications.
Vacuum science & general beam dynamics: electron cloud, NEG pumping etc.
CDR&TDR production will require LOTS of generic accel.engineering expertise– of which UK has much.
Brian Foster - ILC@KEK
16
10
France in CAREWP1 Coordination : LAL (8 mm)WP5 Electropolishing : DAPNIA (85 mm)WP7 Couplers : LAL (258 mm)WP8 Tuning systems : DAPNIA (16 mm), IPNO (24 mm)WP10 CRYHOLAB tests: DAPNIA (66 mm), IPNO+LAL (36 mm)WP11 Beam position monitor : DAPNIA (58 mm)
5
7
8 11
Brian Foster - ILC@KEK
17
France in EuroTeVWP1 Coordination : LAPP (6 mm)WP2 BDS Optics+ Quadrupole Nb3Sn : DAPNIA (73 mm)WP5 Polarimetry : LAL (156 mm)WP6 Machine-detector Interface : LAL (96 mm)WP7 Alignment and stabilisation : LAPP (144 mm)
1
5
6
7
Brian Foster - ILC@KEK
18
France otherHorizontal test cryostat CRYHOLAB
Industrialisation of couplers and study of new prototypes.
High gradient cavity R&D.
Beam physics @ TTF2
Total of 10 extra FTEs – and longer term studies on:SC magnets (solenoid, final doublet- laser backscattering for γγ-collider- reliability studies (synergy with ADS)
Brian Foster - ILC@KEK
19
Extracted bunches
MAIN LINAC
Italy – INFN & TESLACryomodules, Cavities and Ancillaries R&D, Construction and CommissioningCost Optimization and Industrial Studies
Damping Rings - Layout and Engineering DesignCost Optimization and Industrial StudiesUltra-fast Multi-frequency RF Kickers
Beam Diagnostics:OTR, DF, Bunch Length
Photocathode preparation and handling
Brian Foster - ILC@KEK
20
Italy – INFN for ILCINFN has had a Special Project on R&D for Future Accelerators, NTA, for 12 years.Major Financed Activities: TTF, TESLA, CTF3Average Budget: 2 M€ / yINFN Staff dedicated: > 30 m / y
INFN Paricipate in CARE and EUROTeVLeads 1 JRA and several WPs15 staff/y dedicated + 15 m/y from EU
INFN Participate in EU and OECD Programs for ADS (Accelerator Driven Systems), based on TESLA Technology - Accelerator DesignReliability/Availabitity AnalysisSC Cavities, Cryomodules and Ancillaries
Brian Foster - ILC@KEK
21
CERNR&D on generic key issues independent of technology:-Participation in EUROTeV, CARE and ELAN network-R&D on Beam dynamics, Beam diagnostics, BDS, Ecloud…..Resources: 2.3 MEur. Material + 25 staff-y + 20 fellows-y = 6.75 MEur. total
Additional key issue common to ILC and CLIC (not funded):Multi-Beam Klystrons with long RF pulse aiming for very high efficiency (80%) (novel scheme based on RF cavities with high order modes)
Tests with beam in CTF3 Test facility:Beam instrumentation and benchmarking of beam simulation codes. Beam combination as possible DR injection/extraction with RF transv. cavities
Brian Foster - ILC@KEK
22
CERN
Participation in R&D on low-emittance generation @ ATF/KEK.
Available expertise on superconducting technology;Large scale cryogenics systems (8*18kW @ 4.5K and 8*2.4kW @ 1.8K in LHC) comparable to ILC (industrialisation, costing…..) Nb-coated Copper SC cavities (LEP2 352 MHz and 1.5 GHz high gradient R&D)
Brian Foster - ILC@KEK
23
Spain & Russia
Spain has contributed to SC magnets for TTF and XFEL and has also looked at optics design and collimation systems.
They plan to look at corrector magnets, kickers and septum and RF structures for CTF3 and optics design, beam dynamic simulation and instrumentation in the spent beam line (MDI) and very forward detector region from 2005.
Russia has a long-standing interest in ILC-related issues – from INP in Novosibirsk on (polarized) positron production, storage rings, final focus, accelerator structures, etc. Theyexpect to expand this participation as the needs of the ILCand the GDI become better defined.
Brian Foster - ILC@KEK
24
Project Timelines2006 2007 2008 2015
CDR
TDR
GDE process
construction
commissioning
physics
EUROTeV
preparation
2010 2012
constructionoperation
2005
CARE
EURO XFEL
ILC
UK LC-ABD
Brian Foster - ILC@KEK
25
Important issues for GDIMain LINAC is still the biggest challenge: Cost driver; complexity; reliability; sheer number of components Priority must go now to Engineering! QA/QC cavity production → 35MV/m. Design / testing of tuner(s), couplers, etc.- Test facilities for long-term reliability testing.Qualification of klystrons / ModulatorsINDUSTRIALISATION - Cost reductionAll other sub-system design (inc. parameterspecifications) can run in parallel.Linac tech. is a building block which is quite flexibleAt all design consideration stages, $$-impact must be included.At all design consideration stages, $$-impact must be included.The number of ILC meetings is proliferating. This is good!However, we risk drowning in meetings. Until GDI is working,we need someone to be responsible for optimally coordinatingmeetings. We should agree this by the end of this meeting.
Brian Foster - ILC@KEK
26
SummaryThere is a lot of work going on in Europe either directly on, or closely related to, the ILC. Much of that work is carried out in the context of large multinational collaborations, which are often relatively inflexible and have well defined deliverables and milestones. The total European resource relevant for ILC R&D over the next 3 years is ~100M€. Europe is conscious of the need to work out structures by which resources can be devoted to issues the GDI identifies as critical.We have identified several areas of the current designs on thetable where work is needed; we believe that in some we have the necessary resources and expertise to play a leading role.We look forward to implementing the GDI and taking thenext steps to the realisation of the ILC as rapidly as possible.