ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

38
ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE

Transcript of ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Page 1: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

ILC R&D and Future ILC Plan in Americas

Shekhar Mishra

Fermilab/ILC-ART/ILC-GDE

Page 2: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

International Spirit"One World One Dream" fully reflects the essence and the universal values of the Olympic spirit -- Unity, Friendship, Progress, Harmony, Participation and Dream. It expresses the common wishes of people all over the world, inspired by the Olympic ideals, to strive for a bright future of Mankind. In spite of the differences in colors, languages and races, we share the charm and joy of the Olympic Games, and together we seek for the ideal of Mankind for peace. We belong to the same world and we share the same aspirations and dreams.

One ILC

Copyright Beijing Olympics

04/19/23 2CCAST Meeting at IHEP

Page 3: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Jet Set: Prof. Shin-ichi Kurokawa

04/19/23 3CCAST Meeting at IHEP

A true International Sprit for ILC

ACFA

ILCSC

Thank You

(I Hope you will continue to be around for ILC)

Page 4: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Outline

04/19/23 4CCAST Meeting at IHEP

• Introduction

• American Regional Team

• ILC Accelerator R&D• Polarized Electron Source• Positron Source• Damping Ring• High Level RF• Main Linac Cavity and Cryomodule• Beam Delivery System• Interaction Region

• ATF-II• ESA

• ILC R&D at TRIUMF

• Conventional Facility and Site studies

• ILC Detector R&D

• International Collaboration

• Summary

Page 5: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Americas Regional Team• The Americas Regional Team (ART) is led by Mike Harrison and

US Institutional Leaders with support from Jerry Blazey at DOE

• A large collaborative effort of US national laboratories:– FNAL, SLAC, ANL, BNL, Jlab, LBNL, LLNL, LANL, Cornell,…– And a number of Universities– TRIUMF (A Canadian Laboratory)– Exploring several bilateral collaborations

• Focused on ILC R&D and development of the Engineering Design Report– Strong effort which has grown rapidly over last few years

Estimated FY05

ActualFY06

AppropriatedFY07

PlannedFY08

RequestedFY09

TOTAL ILC line $21,923 $29,700 $41,700 $60,000 $75,000

SRF Infrastructure and Industrialization $8,725 $12,000 $19,000 $23,400 $35,000

Overall total: ILC+SRF $30,648 $41,700 $60,700 $83,400 $110,000

Approximate US ILC Accelerator and SRF Infrastructure Budgets

04/19/23 5CCAST Meeting at IHEP

Page 6: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Americas Level-2 ManagersThe Americas Regional Team (ART) program is constructed with the

help of the Level-2 managers who manages the specific programs

Global Systems J. Carwardine and R. Larsen

Electron Source A. Brachmann and M. Poelker

Positron Source J. Sheppard and J. Gronberg

Damping Rings A. Jackson and M. Palmer

RTML and ML BD P. Tenenbaum and N. Solyak

Main linac RF C. Adolphsen and S. Nagaitsev

Main linac Cavity & S. Mishra, H. Padamse, Cryomodule J. Mammoser, and M. Kelly

BDS A. Seryi and B. Parker

CFS V. Kuckler and F. Asiri

Regional Interest B. Kephart and E. Paterson

04/19/23 6CCAST Meeting at IHEP

Page 7: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Damping Rings• Contributing Institutions: Alfred U., ANL, U. of British Columbia, Cornell U., FNAL,

U. of Illinois, LBNL, LLNL, SLAC

• Major Efforts– Accelerator Design

• Baseline Lattice design and evaluation • Impedance and Instabilities

– R&D• Electron Cloud experiments• Fast High Voltage Pulser and Kickers

– Component and System Engineering• Vacuum and Magnet Systems design• Systems Integration

– Test Facilities• KEK-ATF instrumentation support and experiments at CESR-TA

• Key R&D Results– Promising results on electron cloud mitigation with coatings and grooved

surfaces– Demonstration of DSRD pulser meeting timing requirements for 3 ns bunch

spacing

6 kV

3 ns

A. Krasnykh (SLAC, in collab. w/Ioffe PTI, St. Petersburg)

DSRDPulser

04/19/23 10CCAST Meeting at IHEP

Page 8: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Electron Cloud Studies• Experiments at PEP-II in FY07 and FY08 will clarify the utility of TiN

coatings and longitudinal grooves

• Subsequent experiments at KEK and CESR-TA will study clearing electrodes as well as above techniques with parameters closer to ILC damping rings

04/19/23 11CCAST Meeting at IHEP

Page 9: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

CESR-TA: Damping Ring Test Facility

Parameter Value

No. of Wigglers 12

Wiggler Field 2.1 T

Beam Energy 2.0 GeV*

E/E 8.6 x 10-4

v (geo) target ~5 – 10 pm

h (geo) 2.3 nm

Damping Time 47 ms

Bunch Spacing 4 ns

Bunch Length 9 mm

Bunch-by-bunch,Turn-by-turn BPM

Goal: Provide a vehicle for ILC Damping Rings R&D on the timescale of the EDR.

The primary focus is to study the impact of the electron cloud on ultra low emittance beams and mitigation methods in a wiggler-dominated storage ring.

Witness BunchMeasurements –

EC Tune Shift

0.75 mA/bunch e+ @ 1.9 GeV

*CESR operating range is 1.5-5.5 GeV

• EC Growth and Mitigation Studies– Probe bunch configurations similar to ILC DR– Conduct unique studies in high field damping wigglers

• Ultra Low Emittance Operation & Beam Dynamics Studies– Validate correction algorithms– Measure and maintain ultra low emittance beams – Characterize sources of emittance growth in ultra low

emittance beams– Probe species dependent effects

• Deliver design inputs to the ILC EDR

Baseline Lattice R&DPlans

04/19/23 12CCAST Meeting at IHEP

Page 10: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Main Linac High Level RF• Development and evaluation of modulators,

klystrons, rf distribution, and couplers– Baseline design is being developed for XFEL at

DESY• Use much of what is done for XFEL although some

requirements differ somewhat

– Alternate paths for significant cost reduction and performance improvements being investigated in US

• Marx modulator

• Sheet beam klystron

• Alternate RF distribution

• Incremental improvements

04/19/23 13CCAST Meeting at IHEP

Page 11: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Bouncer (Baseline) Modulator

Capacitor Banks IGBT Redundant Switch Bouncer Choke04/19/23 14CCAST Meeting at IHEP

Page 12: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Marx Generator Modulator• Prototype is operating well at 5Hz and ~100

kW

120 kV Output Cable

Buck Regulator

CoarseVernier

(3+1 Redundancy)

12 kV Cells(10+2

Redundancy)

Fine Vernier

100kV; 150A; 5Hz; 100kW.

Vernier boards to flatten pulse will be testednext month

04/19/23 15CCAST Meeting at IHEP

Page 13: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Klystron R&D• Baseline is 10 MW multi-beam klystron

– Toshiba, Thales, CPI manufacturing horizontal tubes for XFEL– US will be testing vertical

Toshiba klystron– Concerns about

industrializing tubesin US

• Sheet Beam Klystrons– Allows higher beam

current (at a given beam voltage) while still maintaining low current density for efficiency

– Will be smaller and lighter than other options– PPM focusing eliminates power required for solenoid

Designed to be MBK plug compatible with

similar or better efficiency

04/19/23 16CCAST Meeting at IHEP

Page 14: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

RF Distribution• Developing improved rf distribution designs to

optimize distribution with cavity gradient variation and reduce cost– To be tested in ILCTA (Fermilab)

Baseline RF Distribution

Variable Tap-offs (VTOs)

3 dB Hybrids

Case Sorted [%]Individual P's and Q's 0.0 (VTO and Circ) P’s in pairs, Q’s in pairs 0.8+/-0.2 (VTO but no Circ) 1 P, Q’s in pairs 3.3+/-0.5 (no VTO, no Circ) Gi set to lowest Glim 19.8+/-2.0 (no VTO, no Circ)

04/19/23 17CCAST Meeting at IHEP

Page 15: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

18

US Cavity Program • Number of cavity goal: Fabricate 1/3 of the Cavity

needed for the Global S0 program, with focus on getting US Industry involved and qualified – FY05

• 4 Cavities from ACCEL (Type-III+ length)

– FY06• 4 Cavities from AES (Type-III+ length)• 4 Jlab (2 Fine, 2 Large)• 9 Cavities from ACCEL (To be delivered by 12/31/07)• 6 Cavities from AES (To be delivered by 12/31/07)

– FY07• 12 Cavities (ACCEL) (Mid CY08)• 12 1-cell Cavities (AES & ACCEL) (AES 9/18/07, ACCEL 12/31)

– FY08-09• 18 & 48 Cavities (Planned)

All of these cavities are fine grain Nb and ILC design

04/19/23 CCAST Meeting at IHEP

Page 16: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

19

108

109

1010

1011

0 10 20 30 40

A7 - Vertical Qualify Test Data

Qo - First Qualify TestQo - 2nd Qualify TestQo- 3rd Qualify TestQo

Eacc (MV/m)

EP and Vertical Test @ Jlab

Quench at ~ 42 MV/Mbut back down to ~32 MV/M

EP and Vertical Test at TJNL

• FNAL collaborates closely with Jlab on cavity processing• Jlab modified existing infrastructure for Electropolish, High

Pressure Rinse, and Vertical Test of ILC cavities– Capable of > 40 process and test cycles/yr– Completed 32 in FY07

04/19/23 CCAST Meeting at IHEP

Page 17: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

20

ACCEL cavity EP Processed & tested at Cornell

EP & Vertical Test: Cornell

Limited by quench@ 30 MV/M

Vertical EP Infrastructure

HPR ( High Pressure Rinse)

Vertical test

New vertical EP R&D infrastructure

HPR & Vertical Test of ILC cavities

3 ACCEL cavities processed # 5, 8, 9

8 process and test cycles in FY07

Gradients achieved 24-30 MV/M

Limited by quench

04/19/23 CCAST Meeting at IHEP

Page 18: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

21

ART: Cavity Process & VTS Results

ACCEL (Europe) AES (U.S.)

ILCGoal

Most cavities, esp U.S. cavities are limited by Quench vs FE

04/19/23 CCAST Meeting at IHEP

Page 19: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

22

ANL-FNAL Processing Facility

New Clean Rooms

New Chemistry Rooms & EP

1st EP Aug 07Single cell

Chemistry, Clean rooms, BCP, HPR & EP @ANL: ~ 50 cy/yr

HPR

04/19/23 CCAST Meeting at IHEP

Page 20: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

New Vertical Test @ FNAL• Recently commissioned (IB1)

– Existing 125W@ 1.8 K Cryogenic plant– RF system in collaboration with Jlab– Capable of testing ~50 Cavities/yr– Evolutionary upgrades:

• Thermometry for 9-cells, 2 cavities at a time, 2 top plates, Cryo upgrades

• Plan for two additional VTS cryostats– Ultimate capacity ~ 264 cavity tests/yr

VTS Cryostat:IB1

New RF & Control Room

Plan for 2 more VTS pits

Nine-cell Tesla-style cavity

04/19/23 23CCAST Meeting at IHEP

Page 21: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Horizontal Test System • Dressed cavities are tested with pulsed RF power• 300 KW klystron & modulator complete and tested• Extensive MDB cryo modifications 100 W @ 1.8 K• HTS currently cold & being commissioned with 1st cavity • Serves as test bed for LLRF, tuner & coupler studies• Unique capability in Americas: Goal 24 cavity tests/yr

1st 1.3 GHz Cavity in HTS

C22 Reached17 MV/m

04/19/23 24CCAST Meeting at IHEP

Page 22: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

T4 Cryomodule 3-D Model

04/19/23 25CCAST Meeting at IHEP

Page 23: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Cryomodule Assembly Facility• Goal: Assemble R&D Cryomodules • Where: MP9 and ICB buildings

– MP9: 2500 ft2 clean room, Class 10/100 – Cavity dressing and string assembly– ICB: final cryomodule assembly

• Infrastructure:– Clean Rooms, Assembly Fixtures– Clean Vacuum, gas, water & Leak Check

• DESY Cryomodule “kit” being assembled now

String Assembly MP9 Clean RoomCavity string for 1st CM

ICB clean: FinalAssembly fixtures installed

04/19/23 26CCAST Meeting at IHEP

Page 24: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

RF Unit Test Facility (ILCTA)• Overall Plan

– Build an ILC RF Unit Test Facility at New Muon Lab Building (NML)• One ILC RF Unit (3 Cryomodules)• 10-MW RF System• ILC-like Beam (3.2 nC/bunch @3 MHz, Up to 3000 bunches @ 5Hz, 300-μm rms bunch length)

• Phase-1 (FY07 - FY08)– Prepare Facility for Testing of First Cryomodule (CM1) without Beam

• Infrastructure, RF Power, controls• Cryogenics (Refrigerator #1) => reuse of existing TeV refrigerator

• Phase-2 & 3 (FY08 - FY10)– Install Gun, Injector, CM2 and CM3, Test with Beam

• New RF Gun• Move A0 Photo-Injector to NML and Install Test Beamlines• Extend Building to fit Third Cryomodule• Cryogenics (Refrigerator #2 (existing) and New Cryoplant-300W@2K)• Upgrade RF System to 10 MW

• FY11 and beyond run ILC RF unit with full ILC parameters

04/19/23 28CCAST Meeting at IHEP

Page 25: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

29

ILCTA Layout

40-50 MeV Injector: well characterized beamLow energy test area (e.g. 3.9 GHz Crab cavities) Twin tunnel design to allow 2nd RF unit and to study tunnel layout and maintenance issuesNew bldg for diagnostics & AARDAlso houses new cryo plant

Bunch Compressor

ILC RF unitDiagnosticsGun

CC I,II

Laser

3rd har

Test Area

~ 22 M72 M

Existing Building

New Building

New ILC like tunnel

2nd ILC RF unit

Test Areas

new 300 W cryo plant

RF Equipment

04/19/23 CCAST Meeting at IHEP

Page 26: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Beam Delivery System• Design

– Integrate worldwide BDS design efforts, develop EDR plans

– Accelerator & detector physics design

– Address GDE goals on design optimization & cost reduction

– Develop revised IR designs compatible with push-pull

• R&D & Test Facilities (ATF2 and ESA)– Prototypes and performance enabling hardware

– Long IR magnet prototype, study vibration issues in SC FD

– Study nanometer BPM system at ATF

– ESA experiments on energy spectrometers, collimator wakefields, bunch length diagnostics and IP feedback

– ATF2 design and construction

04/19/23 30CCAST Meeting at IHEP

Page 27: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Interaction Region Integration

(old location)

Final doublet magnets are grouped into two cryostats, with warm space in between, to provide break point for push-pull

ILC detectors assembled on surface, like CMS 04/19/23 32CCAST Meeting at IHEP

Page 28: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Preparation for FD prototype: winding machine modifications to accommodate longer coils, integrated coil heater to test quench threshold, engineering integrated design

IR FD prototype @ BNL

Earlier ~foot long prototype of self-shielding BNL quad

to be prototypedduring EDR

coil integrated quench heater04/19/23 33CCAST Meeting at IHEP

Page 29: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

ATF2 Scaled down model of ILC final focus

04/19/23 34CCAST Meeting at IHEP

Page 30: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

ATF-2 Final Focus Test• Rapid progress being made on infrastructure at KEK

• US is contributing a large number of components and expertise:– Magnets: dipoles, final quadrupoles, and sextupoles– Beam line tuning software packages– High availability power

supplies– ATF damping ring BPMs– Fast kicker pulsers– RF bpm electronics– Magnet movers– Optics design– Operational support

38 ILC-like HA Power Supplies for ATF204/19/23 35CCAST Meeting at IHEP

Page 31: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

BDS beam tests at ESA

Runs: three 2-week runs in 2006 & 07;request two runs in 2008

• BPM energy spectrometer (T-474/491)• Synch Stripe energy spectrometer (T-475)• Collimator design, wakefields (T-480)• IP BPMs/kickers—background studies (T-488)• EMI (electro-magnetic interference)• Bunch length diagnostics (T-487)

March 7-26, 2007~ 40 participants

04/19/23 36CCAST Meeting at IHEP

Page 32: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

interferometer

Energy Spectrometer at ESA

• BPM & SR based

• Interferometer metrology grid for BPMs

• NMR probes in magnets

• 0.5um BPMs with =5mm => 1e-4 energy resolution

• Study calibrations, systematics, stability

• SR version with quartz fiber detector will be used next run

BPM

magnet of the chicane

04/19/23 37CCAST Meeting at IHEP

Page 33: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

RF Measurments

Boot-upPreparation

Area

Boot Area

RF Meas HPWR Rinse Clean Area

SCRF Test Clean Area

Test Pit

Clean Assembly

AreaBCP

Chemical Lab

RF Controls

Lab

TRIUMF SCRF Infrastructure

04/19/23 38CCAST Meeting at IHEP

Page 34: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

TRIUMF 5-Year Plan• TRIUMF now preparing 5-year plan for Canadian

Government for 2010-2015– Funds allocated in 5-year units – ILC being discussed on how it might be included in plan

• TRIUMF has signed an umbrella MOU with Fermilab for ILC (draft MOU -- DESY detector)– Addendum being prepared

• Make three single-cell cavities 1.3 GHz using multi-grain niobium (electro-polish elsewhere)

• Move towards single crystal large grain version which only needs BCP

– Produce a 1-Cell followed by 9-cell cavity(ies) and qualify PAVAC as an ILC vendor for North America

• University researchers getting involved in SRF

04/19/23 39CCAST Meeting at IHEP

Page 35: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

f

CCAST, ILC, Nov. 5-7, 2007 -- M. Demarteau Slide 40

Detector R&D Foci at Fermilab• Development of pixel detector technologies

– State of the SOI (Silicon On Insulator) Pixel Sensors– Vertically Integrated (3D) circuits

• Development of low-mass silicon trackers– Hybrid-less silicon tracker design with

emphasis on tracking in forward region – Investigating possibility of double-sided silicon

• Characterization of Geiger-mode Avalanche Photo Diodes and their application

– New silicon based photon detection technology – Allows highly integrated detector design – Studying applicability for calorimetry – Applications beyond HEP (medical applications)

• Test Beam Operation and Instrumentation – Availability of beam line for detector tests – Upgrading the beam line instrumentation

• Strip and pixel tracking telescopes with 1 micron pointing resolution

• Particle identification systems • Software Development

– Optimization of detector design in various software frameworks

– Study of physics processes

1mm

1m

m

IRST

DUTDUT

Page 36: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

f

CCAST, ILC, Nov. 5-7, 2007 -- M. Demarteau Slide 41

Example: Dual Readout Calorimetry• Study of Total Absorption Dual Readout Calorimeter• Dual-Readout: measure every shower twice

– Scintillation light: from all charged particles – Čerenkov light: =1 particles, mainly EM

• Goal – Uniform, integrated electromagnetic and

hadronic calorimeter– High density (~8g/cm3), corresponding

to 6-7 in a typical ILC calorimeter application – Linear response to hadrons and e- (e/h=1)– Excellent single particle and jet energy

resolution (<25%/sqrt(E))

• Primary challenge is crystals for dual readout: Scintillator/Čerenkov radiator

• PbWO4, PbF2 doped with scintillator?• Scintillating glass transparent for Čerenkov?• Need samples and demonstration of scintillation/Čerenkov light

separation using timing and/or wavelength • Is the Čerenkov/scintillation separation possible with the WLS fiber

readout?• Efficient photodetector for Čerenkov light

DREAM200 GeV

Page 37: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

International Collaboration• American Regional Team is collaborating on ILC Cavity and

Cryomodule R&D with DESY and KEK.– We are participating in the S0, S1 and S2 R&D programs

• Finished US Cavity “Tight Loop”– US purchased/produced cavities will go to KEK and DESY for “Tight

Loop” S0 processing– KEK and DESY cavities will come to US for processing.

• We collaborate with INFN – Development and testing of Tuner– Development of Cryomodule

• We are developing new collaboration– India (RRCAT, BARC, VECC, IUAC, UD)

• Detailed MOU signed for collaboration on Main Linac Cavity and Cryomodule R&D that could lead to an RF unit fabrication

– TRIUMF • Cavity fabrication• Tuner

– China, Korea,…

04/19/23 42CCAST Meeting at IHEP

Page 38: ILC R&D and Future ILC Plan in Americas Shekhar Mishra Fermilab/ILC-ART/ILC-GDE.

Summary• Very strong program across the US covering a

broad spectrum of ILC topics– Led the RDR effort and coordinated many of the Area

and Technical Systems– Strong R&D programs – Narrowing focus of design efforts during EDR phase

as international partners assume larger role– Will need to re-align programs when actual EDR effort

becomes clear• Rapid buildup of SCRF infrastructure for ILC as

well as other future projects using SCRF– Industrialization process for SCRF components is

beginning• International Collaboration

04/19/23 43CCAST Meeting at IHEP