    ADDITIONAL POINTS TO ADDRESS

    PROGRAMME 6 : PROGRAMMES

    AND PROJECTSDr W Barnard

    Deputy Director General

    29 October 2013

  • 5/21/2018 131029 Additional Points

    2/29

    PROGRAMMES AND PROJECTS

    2

    A. ENERGY ADJUSTED BUDGET SUMMARY, VOTE 29

    5. There was also a roll-over of R 28 million. Why was there a problem herewith non-grid electrification?

    1. The non-grid programme is a negotiation process -wall-to-wall grid licences to either

    municipalities or Eskom. Neither were interested in non-grid programme until recently,

    since it was seen as a pilot. The negotiations between the communities, Municipalities,

    Eskom and the private implementers are a very complex and time consuming process.

    Since one year contacts have been issued to the concessionaires the last two years,

    the areas been identified to implement non-grid are only secured 4-6 months into the

    financial year, which leaves a very short period to do the physical implementation.2. Long procurement process in the re-appointing of non-grid service providers.

    3. Critical shortage of INEP staff working on non-grid programme.

    Examples:

    In 2011/12 for 2012/13 period INEP was requested to roll-out non-grid in Nqutu municipality.

    These areas were agreed upon by all stakeholders for non-grid electricity i.e Eskom,Municipality and Municipality.

    At the time when implementation was supposed to have happened, the service provider was

    stopped by Eskom from installing the Solar Home System, since they had changed their grid

    roll-out plan.

  • 5/21/2018 131029 Additional Points

    3/29

    PROGRAMMES AND PROJECTS (cont.)

    3

    5. There was also a roll-over of R 28 million. Why was there a problem herewith non-grid electrification? (cont.) DOE had to find an alternative area to roll-out the non-grid allocations in order to honour our

    contractual obligation with the service provider. Okhahlamba Municipality was interested and

    the whole negotiation process had to be started all over again.

    By the time this process was finalised it was near the end of the financial year 2012/13 and

    the service provider was only then able to order material which also had some kind of delay

    to be delivered.

    The project is continuing well in Okhahlamba and will be completed in January 2014

    An additional challenge was that the contracts of the non-grid service providers expired at the

    end of November 2012. The process to extend their contract was only concluded in January

    2013, making it difficult to organize themselves to complete some of the connections in time.

    The New Household Electrification strategy was not been approved at the time the non-grid

    contacts expired, hence no clear strategy exist regarding the non-grid programme. As a

    result the last two years DOE had to go through a procurement process to procure the non-

    grid service providers. This process also added to the time delay before the non-grid projects

    could been roll-out, since the BAC needed more information in terms of the contract

    extension, as well as legal advise on the long history the Department had with the non-grid

    service providers concerned.

  • 5/21/2018 131029 Additional Points

    4/29

    PROGRAMMES AND PROJECTS (cont.)

    4

    A. ENERGY ADJUSTED BUDGET SUMMARY, VOTE 29

    7.1. The DoE is also to give reasons for underperformance as declaredin the mid-year performance status. Here focus on

    Electrification and energy programme management

    Response

    The achievements for Q2 of Programme 6 is as follows:

    10 quarterly targets been achieved

    5 partially achieved and 2 not achieved.

    A total of 92 085 connections have already been completed, which is about21 000 more than has been achieved in Q2 of last year.

    Q2 is only the first quarter of the municipal programme.

    The first few months is always the slow period and the majority of

    connection are completed in the latter part of Q3 and in Q4. The performance is a vast improvement on the similar quarter last year,

    when the Branch was just been established.

  • 5/21/2018 131029 Additional Points

    5/29

    PROGRAMMES AND PROJECTS (cont.)

    5

    B. BRIEFING BY THE DEPARTMENT OF ENERGY ON THEIR

    2ND QUARTERLY PERFORMANCE REPORT 2013/14

    Update on the progress of the non-grid electrification programme

    Response

    See response in A 5 above

    Current non-grid progress:

    Province 1st Q 2nd Q 3rd Q Achieved Planned Remaining

    EC 0 708 708 1228 520

    KZN 1021 1233 814 3068 9518 6450

    Limpopo 0 400 1000 2000 1600

    NC 0 210 210

    Other 0 0 0 3000 3000Total 1021 2341 814 4776 15956 11780

  • 5/21/2018 131029 Additional Points

    6/29

    PROGRAMMES AND PROJECTS (cont.)

    6

    B. BRIEFING BY THE DEPARTMENT OF ENERGY ON THEIR

    2ND QUARTERLY PERFORMANCE REPORT 2013/14

    Under programme 6: Programmes and Projects, the DoE reportedthat six out of the nine planned targets were not achieved. How is

    this being addressed in the current financial year to ensure there is

    no repeat of this situation?

    Response

    See comments under 7.1 above.

    The achievements for Q2 of Programme 6 is as follows:

    10 quarterly targets been achieved

    5 partially achieved and

    2 not achieved.

  • 5/21/2018 131029 Additional Points

    7/29

    PROGRAMMES AND PROJECTS (cont.)

    7

    B. BRIEFING BY THE DEPARTMENT OF ENERGY ON THEIR

    2ND QUARTERLY PERFORMANCE REPORT 2013/14 (cont.)

    The Branch was established in July 2012. The approved structure at

    that stage was not fully funded and therefore didnthad enough staff to

    perform all the functions necessary to complete the responsibilities of

    the Branch. However, with the new financial year and matching and

    placing process been implemented from April 2013 this situation is in

    the process of improving.

    BRANCH: ENERGY PROGRAMMES

    AND PROJECTS

    INEP

    REGIONAL ENERGY

    OFFICES

    COMMUNITY UPLIFTMENT

    PROGRAMMES AND PROJECTS

    ELECTRICITY INFRASTRUCTURE/INDUSTRY

    TRANSFORMATION

    PROGRAMMES AND

    PROJECTS OFFICE

  • 5/21/2018 131029 Additional Points

    8/29

    PROGRAMMES AND PROJECTS (cont.)

    8

    D. UPDATE ON THE CONSTRUCTION OF WINDOWS 1 AS WELL

    AS WINDOWS 3 BY THE DOE

    BW1 construction is progressing well and most of BW2 developers

    are busy with site clearance and development. BW3 has not beenannounced, will be done in the next few days. as been

    Eastern Cape Free State Limpopo Northern CapeNorth-West

    Province

    Western Cape

    Onshore Wind 806.05 72.75 317.59

    Solar CSP 200

    Solar Photovoltaic 69.6 124 58 658.97725 79.255 58.8

    Small Hydro 4.3 10

    0

    100

    200

    300

    400

    500

    600

    700800

    900

    Megawatts

    Preferred Bidders in Provinces:BW 1 and 2

  • 5/21/2018 131029 Additional Points

    9/29Slide 9

  • 5/21/2018 131029 Additional Points

    10/29

    PROGRAMMES AND PROJECTS (cont.)

    10

    C. BRIEFING ON THE PILOT PROJECT ON ADAM BY THE DOE,

    SALGA, FFC AND MISA

    Response

    Briefing on Mini ADAM programme will be made to this Committee on

    1 November.

  • 5/21/2018 131029 Additional Points

    11/29

    BW1 Approved Projects (1)

    Slide 11

    IPP ID PROJECT PROVINCE LOCATION TECHNOLOGYNET

    CAPACITY

    IPPID031Letsatsi Power Company Free State Bloemfontein Solar Photovoltaic 64.0

    IPPID032Lesedi Power Company Northern Cape Postmasburg Solar Photovoltaic 64.0

    IPPID035Witkop Solar Park Limpopo Waterberg Solar Photovoltaic 30.0

    IPPID036Noblesfontein Wind Farm Northern Cape Noblesfontein Onshore Wind 72.8

    IPPID037Touwsrivier Project Western Cape Touwsrivier Solar Photovoltaic 36.0

    IPPID043Dorper Wind Farm Eastern Cape Stormberg Onshore Wind 97.0

    IPPID052Soutpan Solar Park Limpopo Waterberg Solar Photovoltaic 28.0

    IPPID064Mulilo Renewable Energy Solar PV

    De Aar

    Northern Cape De Aar Solar Photovoltaic 9.7

    IPPID065Mulilo Renewable Energy Solar PV

    Prieska

    Northern Cape Prieska Solar Photovoltaic 19.9

    IPPID118KaXu Solar One Northern Cape Pofadder Consentrated Solar

    Power

    100.0

    IPPID123Dassiesklip Wind Energy Facility Western Cape Caledon Onshore Wind 26.2

    IPPID128Konkoonsies Solar Northern Cape Pofadder Solar Photovoltaic 9.7

    IPPID138MetroWind Van Stadens Wind

    Farm

    Eastern Cape Port Elizabeth Onshore Wind 26.2

  • 5/21/2018 131029 Additional Points

    12/29

    BW1 Approved Projects (2)

    Slide 12

    IPP ID PROJECT PROVINCE LOCATION TECHNOLOGYNET

    CAPACITY

    IPPID148Red Cap Kouga Wind Farm -

    Oyster Bay

    Eastern Cape Port Elizabeth Onshore Wind 77.6

    IPPID155RustMo1 Solar Farm North West Rustenburg Solar Photovoltaic 6.8

    IPPID159Kalkbult Soutpan Solar Park North West Phillipstown Solar Photovoltaic 72.5

    IPPID163Aries Solar Northern Cape Kenhardt Solar Photovoltaic 9.7

    IPPID164SlimSun Swartland Solar Park Western Cape Swartland Solar Photovoltaic 5.0

    IPPID182De Aar Solar Power Northern Cape Pixley Ka seme Solar Photovoltaic 48.3IPPID186Jeffreys Bay Wind Farm Eastern Cape Jeffereys Bay Onshore Wind 133.9

    IPPID202Hopefield Wind Farm Western Cape Hopefield Onshore Wind 65.4

    IPPID225Cookhouse Wind Farm Eastern Cape Cookhouse Onshore Wind 135.0

    IPPID443Greefspan PV Power Plant Northern Cape Douglas Solar Photovoltaic 10.0

    IPPID444Kathu Solar Energy Facility Northern Cape Kathu Solar Photovoltaic 75.0

    IPPID564Solar Capital De Aar (Pty) Ltd Northern Cape De Aar Solar Photovoltaic 75.0

    IPPID572Droogfontein Solar Power Northern Cape Kimberley Solar Photovoltaic 48.3

    IPPID696Herbert PV Power Plant Northern Cape Douglas Solar Photovoltaic 19.9

    IPPID798Khi Solar One Northern Cape Upington Consentrated Solar

    Power

    50.0

  • 5/21/2018 131029 Additional Points

    13/29

    BW2 Approved Projects (1)

    Slide 13

    IPP ID PROJECT PROVINCE LOCATION TECHNOLOGYNET

    CAPACITY

    IPPID002Bokpoort CSP Project Northern Cape Kheis Consentrated

    Solar Power

    50.00

    IPPID014Gouda Wind Facility Western Cape Gouda Wind 135.24

    IPPID168Solar Capital Aggenys Northern Cape De Aar Solar Photovoltaic 75.00

    IPPID207Sishen Solar Facility Northern Cape 16km NW of Kathu Solar Photovoltaic 74.00

    IPPID240Amakhala Emoyeni (Phase 1)

    Eastern Cape

    Eastern Cape 14km SW of Bedfrod Wind 137.90

    IPPID303Tsitsikamma Community Wind

    Farm

    Eastern Cape Tsitsikamma Wind 94.80

    IPPID309West Coast 1 Western Cape 8km N of Vredenburg Wind 90.82

    IPPID362Waainek Wind Power Project Eastern Cape 6km SW of

    Grahamstown

    Wind 23.28

    IPPID364Grassridge Wind Power Eastern Cape Coega Wind 59.82

    IPPID372Chaba Wind Power Eastern Cape 6km E of Komga Wind 20.58IPPID373Aurora Solar Park Western Cape 2km N of Aurora Solar Photovoltaic 9.00

    IPPID375Vredendal Solar Park Western Cape 2km N of Vredendal Solar Photovoltaic 8.82

  • 5/21/2018 131029 Additional Points

    14/29

    BW2 Approved Projects (2)

    Slide 14

    IPP ID PROJECT PROVINCE LOCATION TECHNOLOGYNET

    CAPACITY

    IPPID490 Stortemelk Hydro (Pty) Ltd Free State Clarens Small Hydro 4.31

    IPPID523 Linde Northern Cape South-Eastern cnr

    Northern Cape

    Solar Photovoltaic 36.80

    IPPID527 Dreunberg Eastern Cape Northern part of

    Eastern Cape

    Solar Photovoltaic 69.60

    IPPID562 Jasper Power Company Northern Cape Northern Cape Solar Photovoltaic 75.00

    IPPID750 Boshoff Solar Park Free State Lejweleputswa District Solar Photovoltaic 60.00

    IPPID764 Upington Solar PV Northern Cape Upington Solar Photovoltaic 8.90

    IPPID815 Neusberg Hydro Electrical

    Project A

    Northern Cape Neusberg Small Hydro 9.99

    rogress ep

  • 5/21/2018 131029 Additional Points

    15/29

    rogress epP L A N N E D A C T U A L

    A C T U A L

    >3 5

    031 Letsatsi Power Company FS Bloemfontein Solar Photovoltaic 2012/11/19 2014/05/21 Southdrift R2.4 billion Posts 47840 546 580 373 47840

    Structures 1568 1514

    Modules 277000 207180

    Inverters 64 26

    032 Lesedi Power Company NC Postmasburg Solar Photovoltaic 2012/11/19 2014/05/21 Gazzelle R2.4 billion Posts 47840 546 969 668 44758

    Structures 1568 1258

    Modules 277000 170424

    Inverters 64 27

    035 Witkop Solar Park L Waterberg Solar Photovoltaic 2013/04/15 2013/04/25 Witkop R 1 394 495 222.00 Site Clearance 750728 80 123 19 7,23,478

    Civil Foundation ~14,384 2257

    Tracker Blocks 97 0

    Modules 11,943 0

    LV MV Tranches 7791m 3508

    Inverters 25 0

    036 Noblesfontein NC Noblesfontein Onshore Wind 2012/12/17 2014/07/11 Biesiesport R 1 574 354 265.00 Road network 1 335.5 282 75 0

    Turbine foundation 41 0

    Turbine erection 41 0

    IPP Substation 1 0

    Eskom Substation 1 0

    Overhead Line 1 0

    Grid Connection 1 0

    037 Touwsriver Project WC Touwsriver Solar Photovoltaic 2012/11/19 2014/06/16 Touwsrivier R 412 669 263.00 CPV SYSTEMS: Mech 1500 210 630 441 507

    Electrical 0

    043 Dorper Wind Farm EC Stormberg Onshore Wind 2013/02/05 2014/07/01 Carrickmore R 2 310 714 286.00 Substations 2 294 337 173 0

    Road construction 22km 20km

    WT Foundations 40 34

    Erection of Towers 40 11

    Tower Commission 40 0

    052 Soutpan Solar Park L Waterberg Solar Photovoltaic 2013/01/15 2014/01/30 Soutpan R 1 246 228 735.00 Civil Foundation ~13,584 260 375 83 9973

    Tracker Blocks 93 11

    Modules 1,05,090 6535

    Inverters 26 8

    0 64 Mu li lo Re ne wa bl e En er gy S ol ar P V D e Aa r NC D e Aa r S ol ar P ho to vo lt ai c 2013/04/15 2014/04/01 De Aar 1 R 239 320 277.00 Polycrystaline 44880 68 262 14410887290W st orted on

    site

    PV inverter 20 12

    1250kVA Transformer 10 6

    22kV Grid connection 1

    St eel & a lum s tructure 20MW 2Mw

    0 65 Mu li lo Re ne wa bl e En er gy So la r PV Pr ie sk a NC P ri es ka S ol ar Ph ot ovo lt ai c 2013/04/15 2014/04/01 Cuprum R 486 071 689.00 Polycrystaline 89760 101 187 12216.190.660W stored on

    site

    PV inverter 40 28

    1250kVA Transformer 20 14

    22kV Grid connection 1

    St eel & a lum s tructure 40MW 2Mw

    LOCATIONPROK E Y IT EM S

    T O T A LK E Y IT EM S S U B S T A T I ON IPP ID

    C O M M I T T E

    D C O D

    A C T U A L

    C O M M E N C

    E D A T E

    TECHNOLOGYPROJECT NAME

    J O B C R E A T I O N

    A C T U A L K E Y

    I T EM S I N S T

    T O T A L

    P R O J E C T

    B U D G E T

  • 5/21/2018 131029 Additional Points

    16/29

    BW1 ProgressSep2013

    118 KaXu Solar One NC Pofadder Solar CSP 2012/11/16 2015/02/16 Paulputs R 7 812 000.51 Solar field-1200PTC - 1078 754 18%

    HTF System 12%

    Thermal Energy Storage 15%

    Solar Steam Generator 0

    Steam Turbine 0

    123 Da ssiesklip Wind Energy Facility WC Ca ledon Onshore Wind 2013/01/04 2014/01/14 Klipheuwel- R 439 022 329.00 Road network 1 205 190 117 100%

    Hou Hoek Turbine foundation 9 100%

    Erection of Turbines 9 8%

    IPP Substation 1 80%

    Eskom Substation 1 90%

    Overhead Line 1 88%

    Grid Connection 1 0

    Commercial Operation 1

    128 Konkoosies Solar NC Pofadder Solar Photovoltaic 2013/04/05 2013/12/13 Paulputs MTS R 227 331 608.00 Solar PV Modules 43008 198 194 133 27876

    Mounting System 896 594

    Inverters 16 16

    Transformers 8 0

    138 Metrowind Van Stadens Wind Farm EC Port El izabeth Onshore Wind 2012/11/15 2014/02/01 Fitches Corner R 500 322 092.00 Towers 9 80 115 48 5

    Nancelle 9 5

    Blades 27 15

    Turbine Transform 9 9

    Switchroom 1 1

    22kV Powerline t 1 0

    148 Red Cap Kouga Wind Farm-Oyster Bay EC Port Elizabeth Onshore Wind 2013/03/21 2014/12/16 Kouga R 1 866 147 859.00 Wind Turbines 32 94 101 33

    BoP 344407491 (ZAR)

    Eskom 83750005 (ZAR)

    Turbine transformers 3241MVA transformers 2

    Met masts 2

    155 RustMo1 Solar Farm NW Rustenburg Solar Photovoltaic 2013/02/18 2013/11/15 Spruitfont R 221 134 000.00 BYD 235 7,005kWp 44 90 61 7,005kWp

    SMA 630 SC 11 11

    Minisubstations 6 6

    Structures 621

    HV substation 1 93%

    Module Racks 621

    159 Kalkbult NW Phillipstown Solar Photovoltaic 2012/11/19 2014/01/01 Kalkbult R 2 200 000 000.00 BYD P6-30 312504 450 496 234 312504

    Substructrures 13021 13021Inverters SMA CP800 84 84

    SMA TCS 1660VA 42 42

    BW1 Progress Sep2013

  • 5/21/2018 131029 Additional Points

    17/29

    BW1 ProgressSep2013163 Aries Solar NC Kenhardt Solar Photovoltaic 2013/04/05 2013/12/13 Paulputs MTS R 231 635 203.00 Solar PV Modules 43008 102 94 76 43008

    Mounting System 896 896

    Inverters 16 16

    Transformers 8 8

    164 SlimSun Swa rtland Solar Park WC Swa rtla nd Solar Photovolta ic 2013/09/01 2014/07/01 Eenboom R 103 960 000.00 Solar Panels 41850908 0 0 0 0

    Structures 14367262 0

    Inverters 10561743 0

    182 De Aar So lar Power (Propr ietary) L td RF N C Pixley Ka seme Solar Photovoltaic 2013/01/07 2014/03/03 Chameleon R 1 424 666.90 PV modules 167580 380 420 195 165300

    Inverters 76 72

    Inv Trfrs 76 48Cables Approx 40km ~37km

    50MVA Trfr 1 1

    1 86 J effr ey s B ay (P ro pr ie ta ry ) L im it ed (R F) EC J effr ey s Ba y On sh or e W in d 2013/11/13 2014/05/15 Sunnyside R2.9 b Turbine 60 320 ~620 Not recorded 1

    Substation 1 69%

    Roads ~53km 45km

    Crane 60 37

    22kV Cabling ~100km 60km

    O&M Buidling 1 37%

    Wind Monitoring Mast 2 0

    202 H opefield Wind Farm WC Hopefield Onshore Wind 2012/12/07 2014/02/01 Kerschbosch R 1 151 172 949.00 Wind Turbines 37 229.33 433.1 232.81 15

    225 C ookhouse Wind Farm EC Cookhouse Onshore Wind 2012/11/19 2014/05/31 Poseidon R 2 259 358 010.00 2.1MW Turbines 66 489 355 196 0443 Greefspan PV Power Plant NC Douglas Solar Photovoltaic 2013/03/04 2014/04/11 Greefspan R 311 689 569.00 Panels 45954 359 359 234 40250

    Trackers 1998 1750

    Inverters 300 132

    Minisubstations 13 4

    Deliv Cabin 1 0

    444 Kathu Solar Energy Facility NC Kathu Solar Photovoltaic 2012/11/15 2014/08/15 Kathu R 2 368 752 527.00 P iers 50050 330 720 533 50050

    Tracking Beams 42900 29076

    PV Modules 343200 181212

    Inverters 110 84

    Combiner Box 990 324

    564 Solar Capital De Aar (Pty) Ltd NC De Aar Solar Photovoltaic 2013/01/15 2013/02/28 Bushbuck R 1 844 015 083.00 Modules 226374 781 1759 963 104290

    Structures 71752

    572 Droogfonte in Solar Power (Proprietary) L td N C K imberley Solar Photovolta ic 2013/01/07 2014/04/03 Elk R 1 388 840 000.00 PV modules 168720 300 309 217 163346

    Sinvert Inverters 76 76

    Inverter Trfr 76 8

    50MVA Trfr 1 1

    696 Herbert PV Power Plant NC Douglas Solar Photovoltaic 2012/12/03 2014/04/11 Herbert R 619 465 453.00 Panels 91908 527 527 356 85238

    Trackers 3996 3706

    Inverters 600 477

    Minisubstations 25 13

    Deliv Cabin 1 0

    798 Khi Solar One NC Upington Solar CSP 2012/11/30 2014/11/30 R 4 078 000 000.95 H eliostat Solar Field - 722 505 3%

    Solar Tower 100%Solar Receiver 10%

    Thermal Energy Storage 50%

    To be

    consctructed

  • 5/21/2018 131029 Additional Points

    18/29

    Analysis of RE MW allocation and remaining

    MW

    Slide 18

    Technology

    MW allocation in

    accordance with

    the Determination

    MW capacity

    allocated in the

    First Bid

    Submission

    Phase

    MW capacity

    allocated in the

    Second Bid

    Submission

    Phase

    MW capacity for

    allocation in

    future Bid

    Submission

    Phases

    Onshore wind 1 850.0 MW 634.0 MW 562.5 MW 653.5 MW

    Solar photovoltaic 1 450.0 MW 631.5 MW 417.1 MW 401.4 MW

    Concentrated solar

    power200.0 MW 150.0 MW 50.0 MW 0.0 MW

    Small hydro (

    10MW)75.0 MW 0.0 MW 14.3 MW 60.7 MW

    Landfill gas 25.0 MW 0.0 MW 0.0 MW 25.0 MW

    Biomass 12.5 MW 0.0 MW 0.0 MW 12.5 MWBiogas 12.5 MW 0.0 MW 0.0 MW 12.5 MW

    Total 3 625.0 MW 1 415.5 MW 1 043.9 MW 1 165.6 MW

    C i

  • 5/21/2018 131029 Additional Points

    19/29

    BW1 Community Issues

    Slide 19

    There seems to have been inadequate consultation with some local municipalities

    regarding the bidding process, bidding criteria and the scope of the IPP projects.

    There are challenges in managing expectations of local municipalities and

    communities. IPPs have to implement relevant SED/ED programs in the

    communities. More awareness/education at municipal/community level is required.

    The SED programmes to start during operation phase, not construction phase.

    There is a need for an engagement and communication between different

    government departments and municipalities to clarify roles. Communications from

    national to province to municipal are lacking.

    The biggest challenge the project managers are facing is the non-responsiveness

    from responsible municipal departments in certain municipalities.

    Some IPPs have alleged incidences of destructive and inappropriate interference at

    the local government level, which may hinder project completion.

    Emergency response infrastructure and resources appear inadequate in most far-

    flung municipalities.

    There is at times an impasse on hiring of labour between the municipality and the

    developers. The labour broker issue, if not handled properly could be problematic.

    Labour rates sometimes differ for different disciplines in the same area resulting in

    discontent among workers, which could lead to unwanted industrial action.

  • 5/21/2018 131029 Additional Points

    20/29

    BW1 Community Recommendations

    Slide 20

    The IPPs should ensure that they engage municipalities and most specifically the LED

    officials.

    IPPs should try as far and possible to ensure that SED is sustainable (as opposed to

    being a tick box exercise to achieve a target) in the locality of their project and thatexpectations are sufficiently managed.

    IPPs need to ensure that through their processes they source as much as possible

    locally and more specifically in the locale of the project. This should not only be limited

    to labour but also services that are necessary for project development and maintenance.

    IPPs must ensure that local people are part of skills development and there is a skills

    transfer process to enable locals to participate in the process rather than bringing in all

    skilled workers from outside South Africa. Clearer guidelines with respect to local content and local content targets. Should also

    consider the introduction of more specific local content targets related to the local

    manufacturing of components, particularly associated with solar PV, solar CSP and wind

    technologies.

    Future bid closure dates should be non-negotiable, as this will provide certainty to

    foreign and domestic investors, and continuity of renewable energy investments. The

    certainty so provided will also allow supplier industries to adjust their plans accordingly,

    as well as facilitate the promotion of localisation and skills development.

    L li ti L l C t t

  • 5/21/2018 131029 Additional Points

    21/29

    Localisation vs. Local Content

    Slide 21

    It should be noted that Window 1 and 2 reflect fairly low thresholds for local

    content based on what the DOE deemed to be achievable during the first

    phase of the renewable energy construction programme . Thresholds reflect

    the minimum local content achievable, whilst the targets provide the upper

    band of what the DOE determined to be achievable. Local content as stipulated by the dti should not be confused with localisation.

    The dti defines local content as The local content of a product,is the tender

    price less the value of imported content, expressed as a percentage.

    Local content therefore includes services such as consultations and

    transportation, and is based on percentage of total spend. In many large

    projects the civil works and rest of plant comprise of a significant percentageof total cost, and thus can be easily used to meet any local content thresholds.

    This is evident in the Solar and Wind REIPP projects where local content

    thresholds have been largely met by the civil and rest of plant costs. The

    impact on local manufacturers of solar and wind components has therefore

    been limited.

    Localisationhowever is focused on the development of domestic production

    capacity and capabilities in order to assemble/produce parts, components

    and/or finished goods. Not with respect to the local area where the

    development is taking place.

  • 5/21/2018 131029 Additional Points

    22/29

    Local Content Thresholds

    Slide 22

    Technology

    Window 1 Window 2 Window 3

    Current

    ThresholdTarget

    Current

    ThresholdTarget

    Current

    ThresholdTarget

    Onshore Wind 25% 45% 25% 60% 40% 65%

    Solar PV 35% 50% 35% 60% 45% 65%

    Solar CSP without

    storage

    35% 50% 35% 60% 45% 65%

    CSP with Storage 25% 50% 25% 60% 40% 65%

    Biomass 25% 45% 25% 60% 40% 65%

    Biogas 25% 45% 25% 60% 40% 65%

    Landfill gas 25% 45% 25% 60% 40% 65%

    Small scale hydro 25% 45% 25% 60% 40% 65%

  • 5/21/2018 131029 Additional Points

    23/29

    Slide 23

    Environmental Impact Assessment - it is the responsibility of the Bidders

    to conduct Environmental Impact Assessment and the approval thereafter.

    However, as the department we look at the conditions attached to such

    Environmental Approval and the impact of such conditions to the RE project.There were number of conditions noted, but did not warrant any concern

    especially in relation to the preferred bidders. However, it should be noted

    that as the department we do not have sight of EIA related to Eskom's

    portion of the projects (building or transmission or distribution connection

    lines).

    Eskom Is involved in the final evaluation process with regards to grid

    constrains. No bidders are appointed if there is capacity constrains on the

    grid, Eskom is required to give confirmation before the appointment. For

    BW1 the Eskom interconnectivity projects are on track. In the majority of

    cases the developers are constructing their own sub-stations, but underEskomssupervision and standards.

    Update on BW 1, BW2 & BW3

  • 5/21/2018 131029 Additional Points

    24/29

    What Areas in BW 2& BW3 were improved?

    Slide 24

    It is not possible to address in detail at this stage the improvements from

    BW2 to BW3, but between BW1 and BW2 there already has been

    improvements with regards to the following: The IPPs had to provide their Economic Development (ED) plans as

    part of their bid submission in BW1. However, in BW2, we have

    allowed the IPPs to submit their ED plans after Financial Close.

    These plans also then need to be updated yearly in order to take

    into account any changes within the community.

    An increase in local content from BW1 to BW2 to BW3

    Lessons learnt from site visits for BW1 in dealing with the

    community, has helped BW2 approach their communities differentlyand with more foresight.

    In general for BW3, the prices and the ED offering are much better

    compared to BW1 and BW2.

  • 5/21/2018 131029 Additional Points

    25/29

    Slide 25

  • 5/21/2018 131029 Additional Points

    26/29

    Slide 26

  • 5/21/2018 131029 Additional Points

    27/29

    27

    Solar park.pdf

    Kaxu consentrated solar September 2013_DoE.pdf

    http://localhost/var/www/apps/conversion/tmp/scratch_10/Solar%20park.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/Kaxu%20consentrated%20solar%20September%202013_DoE.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/Kaxu%20consentrated%20solar%20September%202013_DoE.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/Kaxu%20consentrated%20solar%20September%202013_DoE.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/Kaxu%20consentrated%20solar%20September%202013_DoE.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/Kaxu%20consentrated%20solar%20September%202013_DoE.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/Kaxu%20consentrated%20solar%20September%202013_DoE.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/Solar%20park.pdf
  • 5/21/2018 131029 Additional Points

    28/29

    Thank you

    28

    PROGRAMMES AND PROJECTS ( t )

  • 5/21/2018 131029 Additional Points

    29/29

    PROGRAMMES AND PROJECTS (cont.)

    29

    B. BRIEFING BY THE DEPARTMENT OF ENERGY ON THEIR

    2ND QUARTERLY PERFORMANCE REPORT 2013/14

    Update on the progress of the non-grid electrification programme

    Response

    See response in A 5 above

    Service Provider Budget Expenditure Outstanding Balance

    ILITHA R 7 159 668.00 R 5 364 520.00 R 1 795 148.00 R 0.00

    KES R 39 340 765.00 R 2 134 182.00 R 5 178 016.80 R 32 028 566.20

    NURA R 32 070 500.00 R 12 356 835.40 R 19 713 664.60

    SOLAR VISION R 15 160 568.00 R 3 935 964.00 R 1 603 524.00 R 9 621 080.00

    OTHERR 25 500 000.00 R 25 500 000.00

    TOTAL R 119 231 501.00 R 11 434 666.00 R 20 933 524.20 R 86 863 310.80