1 · Web viewChain Sling 链绳/ Wire Rope钢丝绳/ Webbing Sling吊带/ Shackle铁链/...
Transcript of 1 · Web viewChain Sling 链绳/ Wire Rope钢丝绳/ Webbing Sling吊带/ Shackle铁链/...
Form No: LP (EHS-OP-26) Rev 00
Lifting Plan 举吊计划1. General Details一般细节Project 工地名称 : YCKEC Date 日期 :
Location of Lifting Operation 施工位置 :
Time of Lifting Operation (Start) 举吊作业开始时间 :
Contractor (for Lifting Operation) 承包商名称 :
Time of Lifting Operation (End)举吊作业结束时间 :
2. Details of Load(s) 负载详情Configuration of Load:
1
Rebar Bundle螺纹钢捆绑
2
Precast Unit预制构件
3
Scaffold Items支架材料
4
G.I Pipes镀锌铁管
5
Concrete Bucket混凝土桶6
Sand Bucket砂桶
7
Perimeter Screen周边屏幕
8
Prefab Metal Form预制金属模板
9
Man/Cylinder Cage人/气瓶吊笼
10
Timber/Plywood木材/合板11
Cement/Tile Pallet水泥/地砖托盘
12
C.I/PVC PipesPVC 管子
13
Sheet Piles/I-Beams板桩 / I - 横梁
17
(Draw herein)(在该空白格绘画)
14
Prefab Rebar Cage预制钢筋笼
15
BRC/Wire MeshBRC / 网片
16
Crane Mast塔吊骨架
Form No: LP (EHS-OP-26) Rev 00
Lifting Plan 举吊计划
Load Configuration No.
举吊编号Dimension (in Metre)尺寸 (按米计算)
….…………….(L)x(W)x(H)
(长)x(宽)x(高)
……………….(L)x(W)x(H)
(长)x(宽)x(高)
……………….(L)x(W)x(H)
(长)x(宽)x(高)
……………….(L)x(W)x(H)
(长)x(宽)x(高)
……………….(L)x(W)x(H)
(长)x(宽)x(高)Weight of Load (in Ton / Kg)负载重量 (吨/千克)
….……………. ….……………. ….……………. ….……………. ….…………….
Centre of Gravity (Load)负载的重力中心
Central 中央 Estimated 估计
Central 中央 Estimated 估计
Central 中央 Estimated 估计
Central 中央 Estimated 估计
Central 中央 Estimated 估计
3. Details of Lifting Equipment起重设备详情Type of Lifting Equipment
举吊设备的类型: Tower Crane塔式起重机 / Crawler Crane履带式起重机 / Mobile Crane移动式起重机 / Lorry Crane随车起重机 / Gantry Crane门式起重机/ Excavator挖掘机 / Chain Block手拉葫芦 / Other其他…………………..
LM Certificate No.举吊设备证书编号 : …………………………………………..Expiry Date到期日 : ………………………
Safe Working Load 安全工作负荷 : …………………. Ton / Kg 吨/千克 Distance距离 : ……………… m 米
Safe Working Load安全工作负荷 : …………………. Ton / Kg 吨/千克 Distance距离 : ……………… m 米
4. Details of Lifting Gear(s) 起重装置详情Load Configuration No. 举吊编号 …………… …………… …………… …………… ……………
Type of Lifting Gear(s)起重装置的类型
Chain Sling 链绳/ Wire Rope钢丝绳/ Webbing Sling吊带/ Shackle铁链/
Other其他
Chain Sling 链绳/ Wire Rope钢丝绳/ Webbing Sling吊带/ Shackle铁链/
Other其他
Chain Sling 链绳/ Wire Rope钢丝绳/ Webbing Sling吊带/ Shackle铁链/
Other其他
Chain Sling 链绳/ Wire Rope钢丝绳/ Webbing Sling吊带/ Shackle铁链/
Other其他
Chain Sling 链绳/ Wire Rope钢丝绳/ Webbing Sling吊带/ Shackle铁链/
Other其他LG Cert. No.举吊机械有效合格证书编号
…………… …………… …………… …………… ……………
Expiry Date举吊机械有效合格证书到期日
…………… …………… …………… …………… ……………
Lifting Container to be used使用举吊集装箱 No否 Yes是
If yes, please circle如果是,请圈:Concrete Bucket混凝土桶 / Sand Bucket砂桶 / Metal Box金属盒 / Man-cage吊笼 / Metal Cage金属笼 / Cargo Net货网 / Other其它 ……………..
LG Certificate No………………………………..举吊机械有效合格证书编号
Expiry Date.........................到期日
Form No: LP (EHS-OP-26) Rev 00
Lifting Plan 举吊计划
5. Means of Communications通信方式 Standard hand signals 标准手势 Walkie-Talkie步话机 Other 其他 …………………….
6. Personnel Involved In Lifting Operation参与起重作业人员Position Name Statutory Job Safety
QualificationContact No.
Site Engineer / Supervisor工程师/主管 BCSS 建筑施工安全监督员课程
Lifting Supervisor举吊监督 LSS举吊监督课程Crane Operator起重机操作员 MOM Reg.人力部注册号Rigger / Signalman索具装配工 /信号员 R/S索具装配工 /信号员课程Rigger / Signalman索具装配工 /信号员 R/S索具装配工 /信号员课程Rigger / Signalman索具装配工 /信号员 R/S索具装配工 /信号员课程7. Crane & Hoisting Region Lay-out Plan起重机和起重地区计划Lay-out Plan 地区计划 :
Form No: LP (EHS-OP-26) Rev 00
Lifting Plan 举吊计划
(Highlight the area涂彩区域)
8. Other Pre-Inspection Points其他预检测点Area区域 Condition条件 Finding状态Base / Ground基础/地面 Firm with concrete base or steel plates稳定与混凝土基础或钢板 Yes / No / NA是/ 否/ 不适用
Outriggers evenly extended & rested on hard pads均匀延伸并支承在硬垫 Yes / No / NA是/ 否/ 不适用Obstacles障碍
Presence of overhead obstacles such as power lines 存在障碍,如电源线架空 Yes / No / NA是/ 否/ 不适用Adjacent buildings or structure, equipment or stacked materials that may obstruct lifting operation from being carried out safely 相邻建筑物或结构,设备或堆放物料,可能会阻碍被安全地进行起重作业
Yes / No / NA是/ 否/ 不适用Lighting照明 Sufficiency in lighting condition 充足照明条件 Yes / No / NA是/ 否/ 不适用Demarcation划界 Zone of operation with warning signs and barriers操作区的警告标志和障碍 Yes / No / NA是/ 否/ 不适用Weather天气 Fair 晴好 Yes / No / NA是/ 否/ 不适用Tag-line标记线 Provided 提供 Yes / No / NA是/ 否/ 不适用Intended lift’s radius 预期负载半径 Within the crane’s reach 起重机的范围内 Yes / No / NA是/ 否/ 不适用Intended lift’s load inclusive of LG weight 预期负载,包括起重装置重量
Within the crane’s capacity 在起重机的能力 Yes / No / NA是/ 否/ 不适用
Form No: LP (EHS-OP-26) Rev 00
Lifting Plan 举吊计划Risk Assessment风险评估 Available (Ref.: ………………………………………)风险评估的参考号 Yes / No / NA是/ 否/ 不适用Safe Work Procedure安全工作规程 Available (Ref.: ………………………………………) 安全工作规程的参考号 Yes / No / NA是/ 否/ 不适用Tool Box Meeting安全会议 Conducted and record available 传导和记录 Yes / No / NA是/ 否/ 不适用Daily Inspection checklist (by Crane Operator)每日检查清单(由起重机操作员) Available 在现场有 Yes / No / NA是/ 否/ 不适用Daily Crane Operation Log Sheet (by Crane Operator)每日起重机操作日志表(由起重机操作员)
Available 在现场有 Yes / No / NA是/ 否/ 不适用Monthly Maintenance Report每月维护报告 Available 在现场有 Yes / No / NA是/ 否/ 不适用9. Action Manner 行动方式Action Name 姓名 Designation职务 Signature签名 Date日期Applied by申请人
Engineer/Supervisor(Straits / Sub-con)工程师/主管 (海峡/承包商)
Checked by检查人 G. BALAMURUGAN / R.RAJESH
WSHC / Officer(Straits)安全协调员/安全官 (海峡)
Approved by批准人MOSES ANTON / SYLVIA LEE / ALAN HEI
Senior Manager( Projects ) / Project Manager / Senior Project Engineer (Straits)项目经理 (海峡)