The story of BIM from design to use
Case Study29-37 Davies Street
Whole Lifecycle BIM
#BSL201429-37 Davies St
25D
BIM there before…
#BSL201429-37 Davies St
Richard BaglowLondon Regional
DirectorIBSECAD
Rebecca Hodgson-Jones
Head of BIMSIR ROBERT McALPINE
Your Speakers today
#BSL201429-37 Davies St
i. Project Backgroundii. Cocktail for Successiii. The Processiv. The Objectivesv. The Benefitsvi. FM Handovervii. BIM Journey continuesviii. Questions & Answers
Agenda
#BSL201429-37 Davies St
• UK building and civil engineering contractor
• Design Division
• Family-owned and founded in 1869
• Collaborative approach to business
Sir Robert McAlpine
#BSL201429-37 Davies St
Our BIM Journey
#BSL201429-37 Davies St
• Established in 1996
• Over 17 years experience in the Construction Industry at all levels
• We provide BIM Solutions to our clients in the UK, AUS & US markets.
• Our Focus is bringing design and people together
Ibsecad
Project Background
#BSL201429-37 Davies St
Cocktail for Success
#BSL201429-37 Davies St
2009 – 2012 I Olympic Stadium2006 – 2008 I New Street 2004 – 2005 I Emirates 2001 – 2003 I No.1, London Wall
Ingredient 1PR
OJE
CT M
ANAG
ER’S
IN
TERE
ST
SUCCESS OF IMPLEMENTATION
Project Managers Interest
“I didn’t see any other way the project could be run”
#BSL201429-37 Davies St
Ingredient 2
Buy-In & Willingness
#BSL201429-37 Davies St
Ingredient 3
Scale, Scope & Complexity
#BSL201429-37 Davies St
Ingredient 4
Contractual positionTRADITIONAL PROCESS
Stage Design
C
Design Development
Stage Design
E
S/C Tender Period
Detailed Coordination
Construction Issue
Installation Begins
“START EARLY” PROCESS
TIME SAVEDFabricatio
n Drawings
S/C Tender Period
Accelerated Construction Model
Production / Coordination
Stage Design C
Stage Design
E Installation
Begins
Construction Issue
Fabrication
Drawings
#BSL201429-37 Davies St
Ingredient 5
v
Design Validation
Reduce Risk & Transparency
Early Coordination & Clash Detection
Safety
Softer Handover
Sequence & Constructability IBSECAD
Aspiration
Capability
Aspiration & Capability
#BSL201429-37 Davies St
Project Managers InterestBuy-In
WillingnessAspirationCapability
ScaleScope
Complexity
Contractural position
Cocktail for Success
#BSL201429-37 Davies St
The Process
#BSL201429-37 Davies St
The Process
#BSL201429-37 Davies St
The Process
#BSL201429-37 Davies St
The Process
#BSL201429-37 Davies St
BIM Management & Authoring
Ibsecad were appointed by Sir Robert McAlpine in 2011.
BIM Management & MEP Authoring
#BSL201429-37 Davies St
• Design Validation• Reduce Risk & Transparency• Early Co-ordination & Clash Detection
• Safety• Sequence & Constructability• Softer Handover
Objectives
#BSL201429-37 Davies St
The Project guidelines
No PAS1192-2 2013…What do we need to deliver BIM?
Our Golden Rules document was the Project BIM Execution Plan
Level of Detail was defined by our knowledge of Sub Contractor requirements.
The BIM “savvy” design team needed little encouragement.
#BSL201429-37 Davies St
Collaboration
Collaborative workshops to drive solutions were held weekly at Ibsecad & HOK’s offices.
All stakeholders had representation at meetings
#BSL201429-37 Davies St
Design Validation Co-ordination
Challenge highlighted with HOK & MTT at one of the BIM workshops.
On Floor Heat Exchanger unit located in WC Core.
In order to carry out maintenance or to replace the unit a problem arose…
#BSL201429-37 Davies St
Design Validation The services were
positioned directly above the WC Cubicles.
The WC Cubicles were finished flush with the ceiling level.
In order to remove the equipment, complete cubicle removal would be required…
#BSL201429-37 Davies St
Design Validation Several solutions
were tested in the model.
Design team consulted at collaborative workshops.
Equipment and Attenuation re-selected to aid the final solution.
Final solution reached to suit MTT, HOK & FM team.
#BSL201429-37 Davies St
Design Validation
This is just one example where BIM was used to make a decision and enable the design process
#BSL201429-37 Davies St
Scheduling
Builderswork take off for Blockwork & Concrete FD take off for Gratte Brothers
#BSL201429-37 Davies St
Logistics Testing
Site logistics were co-ordinated at the right time
Tower crane influenced final co-ordination in Basement areas.
#BSL201429-37 Davies St
Commissioning review
Services re-routed to accommodate plant Installation & replacement hatch
Ensuring full installation “no gaps” for commissioning
#BSL201429-37 Davies St
CDM Sign Off
Carrying a key “lesson learnt” for CDM sign off
Rodding Eye access; always overlooked Opportunity to capture before installation
#BSL201429-37 Davies St
Sequence of Install
Install workshops Tablet site reviews Areas assessed with trades prior to install
#BSL201429-37 Davies St
Integrate with FM team
Workshops held with Grosvenor FM team = Createmaster embraced the collaborative
process
#BSL201429-37 Davies St
The BIM curve?
BIM Process was being delivered;
Draw It Once Evolve to S/C Integrate F.M
#BSL201429-37 Davies St
29-37 Davies St BIM
#BSL201429-37 Davies St
Ability to visualise the building during BIM workshops In particular Ground Floor Reception & WC
Cores and increased net-letable areas where possible.
What main benefits did the Client gain?
Integration of his existing FM solution FM Team already utilised the Createmaster
Document Park Facilities Management software system
Benefits
Re-Allocate risk contingency
#BSL201429-37 Davies St
No additional Access Panels or bulkheads Final co-ordination agreed earlier allowed
collaborative review of Access requirements
What main benefit did the Architect gain?
Benefits
#BSL201429-37 Davies St
No un-planned Builderswork; Concrete Slabs and Shear Walls approved
before build commenced.
What main Benefit did Structures gain?
Benefits
Steelwork openings influenced to suit co-ordination prior to Fabrication
#BSL201429-37 Davies St
De-risked design Visualise design
and collaborate on solutions with all stakeholders prior to site Installation.
What main benefit did the MEP Consultant gain?
Benefits
#BSL201429-37 Davies St
Programme advantage No design issues at site level,
install could begin “day one” Confidence in the co-ordinated
solutions Simple integration of final
procured equipment details.
What main benefits did the Sub-Contractors gain?
Benefits
#BSL201429-37 Davies St
Soft Handover - The Brief Client had existing established O&M Document
park Link 3D Model and utilise as an additional FM
Tool Needs to be “mobile” and accessed via Tablet Integrate with Client FM Team
Most Important of all;
…Keep it simple…
Handover
Development Working alongside Createmaster; their DOCUMENT
PARK software was enhanced to include a 3D Model route as well as the standard Asset Information.
Asset Information Model
Handover
Development Navisworks was the chosen navigation tool to
develop. Created a web browser “freedom” style version –
therefore Full license not required for the client’s FM Team.
Handover
#BSL201429-37 Davies St
The Product Fully integrated Model and online Document Park
system FM Team can now utilise the model to review
their planned works prior to leaving the office. Valuable man hours will be saved by utilising the
BIMSimply click in the model to be taken to that particular Asset information in the online Document Park.
This has bidirectional features to keep it simple…
Handover
#BSL201429-37 Davies St
Cocktail for Success The Process The Objectives The Benefits FM Handover
Summary
#BSL201429-37 Davies St
The Journey continues
#BSL201429-37 Davies St
Workshop Driven
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
Workstreams
Workstreams
Management
4D Logistics & Planning
6D Handover & Operation
SustainabilityTrainingMDGField
5D Cost Planning & Estimating
BIM4Safety
#BSL201429-37 Davies St
The Big Picture
#BSL201429-37 Davies St
Typical Stage E ModelExcessive Clashes Lack of Constructability during designInaccurate Data drop
The Journey continues
#BSL201429-37 Davies St
Start Early Process – Construction experience is vital
Earlier Contractor involvementResolved clashes and constructible detailImproved routes saving on fittingsMORE accurate data drop
The Journey continues
The Journey continues
#BSL201429-37 Davies St
Questions & Answers