Abington Senior High School Construction Progress
Update
Presented to the
Board of School Directors
March 10, 2020
Schedule ProgressArea / Phase Description of Phase Projected Phase Completion
Phase 1 New Two-Story Addition 65% Complete In Progress – Phased Summer 2020
Phase 2 Administration / Entrance 75% Complete In Progress – May 1, 2020
Phase 3A Nurses Area 75% Complete In Progress – May 1, 2020
Phase 3B Family Consumer Science Completed – August 28, 2019
Phase 4A Mechanical Room Not Yet Started – July 1, 2021
Phase 4B Band Not Yet Started – May 1, 2021
Phase 5A Renovations Two-Story Classrooms Not Yet Started – July 3, 2021
Phase 5B Renovations Two-Story Stairs & Core Not Yet Started – December 1, 2020
Phase 6 New Cafeteria & Classrooms Not Yet Started – January 2, 2021
Phase 7 Renovate Cafeteria Not Yet Started – September 1, 2020
Phase 8 New Auxiliary Gym 25% Complete In Progress – September 15, 2020
Phase 9 Locker Rooms Not Yet Started – August 1, 2021
Phase 10 Renovation Classrooms G Not Yet Started – May 1, 2021
Phase 11 Renovations to Pool Area Not Yet Started – August 1, 2021
Phase 12 Renovation Existing Gym Not Yet Started – August 1, 2021
Project Considerations
Maintaining Schedule – The project team is working to maintain the progress
in the new classroom wing and planning is underway for the summer cleaning
and move-in
Reducing Costs – The project team is working to find ways continue to reduce
costs and provide options for scope reduction/cost reduction
Maintaining Utilities – The project team continues to work to keep all utilities
in operation throughout the building during the construction; this will be an
ongoing effort for the remainder of the project.
Project
Photographs
Phase 1
Project
Photographs
Phase 2
Project
Photographs
Phase 8