Abington Senior High School Construction Progress Update Presented to the Board of School Directors March 10, 2020

Transcript of Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High...

Page 1: Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High School Construction Progress Update Presented to the Board of School Directors March

Abington Senior High School Construction Progress

Update

Presented to the

Board of School Directors

March 10, 2020

Page 2: Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High School Construction Progress Update Presented to the Board of School Directors March

Schedule ProgressArea / Phase Description of Phase Projected Phase Completion

Phase 1 New Two-Story Addition 65% Complete In Progress – Phased Summer 2020

Phase 2 Administration / Entrance 75% Complete In Progress – May 1, 2020

Phase 3A Nurses Area 75% Complete In Progress – May 1, 2020

Phase 3B Family Consumer Science Completed – August 28, 2019

Phase 4A Mechanical Room Not Yet Started – July 1, 2021

Phase 4B Band Not Yet Started – May 1, 2021

Phase 5A Renovations Two-Story Classrooms Not Yet Started – July 3, 2021

Phase 5B Renovations Two-Story Stairs & Core Not Yet Started – December 1, 2020

Phase 6 New Cafeteria & Classrooms Not Yet Started – January 2, 2021

Phase 7 Renovate Cafeteria Not Yet Started – September 1, 2020

Phase 8 New Auxiliary Gym 25% Complete In Progress – September 15, 2020

Phase 9 Locker Rooms Not Yet Started – August 1, 2021

Phase 10 Renovation Classrooms G Not Yet Started – May 1, 2021

Phase 11 Renovations to Pool Area Not Yet Started – August 1, 2021

Phase 12 Renovation Existing Gym Not Yet Started – August 1, 2021

Page 3: Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High School Construction Progress Update Presented to the Board of School Directors March

Project Considerations

Maintaining Schedule – The project team is working to maintain the progress

in the new classroom wing and planning is underway for the summer cleaning

and move-in

Reducing Costs – The project team is working to find ways continue to reduce

costs and provide options for scope reduction/cost reduction

Maintaining Utilities – The project team continues to work to keep all utilities

in operation throughout the building during the construction; this will be an

ongoing effort for the remainder of the project.

Page 4: Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High School Construction Progress Update Presented to the Board of School Directors March

Project

Photographs

Phase 1

Page 5: Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High School Construction Progress Update Presented to the Board of School Directors March

Project

Photographs

Phase 2

Page 6: Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High School Construction Progress Update Presented to the Board of School Directors March

Project

Photographs

Phase 8

Page 7: Abington Senior High School Construction Progress Update · 2020-03-10 · Abington Senior High School Construction Progress Update Presented to the Board of School Directors March