3 rd. year -Industrial Eng. Chapter 3 Production Planning & control 2011- 2012 Dr. May George What is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed for production, inventory, staffing, etc. It sets the quantity of each end item to be completed in each week of a short-range planning horizon. A Master Production Schedule is the master of all schedules. It is a plan for future production of end items. The Master Production Schedule gives production, planning, purchasing, and top management the information needed to plan and control the manufacturing operation. The application ties overall business planning and forecasting to detail operations through the Master Production Schedule. The Master Production Schedule will drive detailed material and production requirements in the Material Requirements Planning module. 1

Transcript of What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or...

Page 1: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

What is Master Production Schedule or MPS?

A Master Production Schedule or MPS is the plan that a company has developed for production, inventory, staffing, etc.  It sets the quantity of each end item to be completed in each week of a short-range planning horizon. A Master Production Schedule is the master of all schedules.  It is a plan for future production of end items.

The Master Production Schedule gives production, planning, purchasing, and top management the information needed to plan and control the manufacturing operation. The application ties overall business planning and forecasting to detail operations through the Master Production Schedule. The Master Production Schedule will drive detailed material and production requirements in the Material Requirements Planning module.

1

Page 2: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

Fig. (1) an overview of manufacturing planning activities

MPS INPUTS: 1. Forecast Demand2. Production Costs3. Inventory Costs4. Customer Orders5. Inventory Levels6. Supply7. Lot Size8. Production Lead Time9. Capacity

A comparison of different product type strategies are depicted in the fig. below:

Type A Type X Type V

MPS OUTPUT (production plan): 1. Amounts to be Produced2. Staffing Levels3. Quantity Available to Promise4. Projected Available Balance

2

Page 3: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

Fig.(2) a comparison of MPS, BOM and FAS MTS=Make To Stock, ATO= Assemble To Order

MTO= Make To Order FAS= Final Assemble Scheduledule

Materials requirements planningMaterials requirements planning (MRP) is used for determining the number of parts, components, and materials needed to produce a product (end item). In brief, MRP is a means designed to answer what, when, how many for each part, component, subassemblies and final products. MRP is most valuable in industries where products are assembled in batches (batch shop, assemble to stock, assemble to order.) MRP provides time scheduling information specifying when each of the

subassemblies, parts, and components should be ordered or produced. The objectives of MRP are to determine quantity and timing of material requirements

to keep schedule priorities updated and valid.MRP needs three inputs:

1. The authorized MPS,2. The BOM file, and3. The inventory records file.

Once the MPS has been input, MRP checks inventory availability. If a need is determined, MRP checks the BOM file for material needed, and then generates planned orders. MRP outputs are:

1. Planned orders to be released at a future time.2. Order release notices to execute the planned orders.3. Changes in due dates of open orders due to rescheduling. 4. Cancellations or suspensions of open orders due to cancellation or suspension

of orders on the master production schedule.Inventory status data: Planned order releases. The inventory records consist of:

3

Page 4: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

1. Gross requirements: The total period demand for the item 2. Scheduled receipts: An open order with an assigned due date3. Projected available: The projected inventory balance for the period4. Planned orders: Quantities & released dates suggested by the MRP system

Fig. (3) MRP system

Material Requirements Planning can provide the following benefits:

1. Reduced Inventory Levels 2. Reduced Component Shortages3. Improved Shipping Performance4. Improved Customer Service 5. Improved Productivity

6. Simplified and Accurate Scheduling

7. Reduced Purchasing Cost 8. Improve Production Schedules9. Reduced Manufacturing Cost

4

Page 5: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

10.Reduced Lead Times11.Less Scrap and Rework12.Higher Production Quality13.Improved Communication14.Improved Plant Efficiency15.Reduced Freight Cost 16.Reduction in Excess Inventory

17.Reduced Overtime 18.Improved Supply Schedules19.Improved Calculation of Material

Requirements20.Improved Competitive Position

Bill Of Materials:

BOM: a listing of all of the raw materials, parts, subassemblies, and assemblies, purchased and manufactured needed to produce one unit of a product.

Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.

Some terms used with MRP:- Time bucket: period, usually 1 week.- Planning horizon: number of periods, then this is divided into time fences.- Lead time offset: offsets a planned order release from a required replenishment.- Net requirement: difference between the gross requirements and the available

inventory.- Gross requirements: anticipated future usage of (or demand for) the item during

each period.- Scheduled receipts: existing replenishment orders due in at the beginning of the

period.- Projected on hand: projected inventory status for the item at the beginning of

each period.- Net requirements: Gross Requirements minus Scheduled Receipts minus

Projected on hand. - Planned order receipt: planned receipt of replenishment orders at the beginning

of the period.- Planned order release: release of planned replenishment orders for the item

using lead-time offset.

Time FencesA policy or guideline established to note where various restrictions or changes in operating procedures take place. For example, changes to the master production

5

Page 6: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

schedule can be accomplished easily beyond the cumulative lead time, while changes inside the cumulative lead time become increasingly more difficult to a point where changes should be resisted. Time fences can be used to define these points.Time Zones1-Frozen Zone

In forecasting, this is the period in which no changes can be made to scheduled work orders based on changes in demand. Use of a frozen zone provides stability in the manufacturing schedule.

2- Firm planned order (FPO):A planned order that can be frozen in quantity and time. The computer is not allowed to change it automatically; this is the responsibility of the planner in charge of the item that is being planned. This technique can aid planners working with MRP systems to respond to material and capacity problems by firming up selected planned orders. In addition, firm planned orders are the normal method of stating the master production schedule. 3- Slushy Zone Capacity and material are committed to less extent. Tradeoffs must be met between marketing and manufacturing

4- Liquid Zone Any changes can be made to the MPS

Fig (4) time zones with allowances.

6

Page 7: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

Fig.(5) product structure tree without lead time

Master Production Schedule Record an Example:In Make-to-stock environment, with fixed orders of 125 units. There are 110 units in inventory to start. When is new order (quantities) needed to satisfy the forecasted demand?For a given product, the demand for 12 months, and Projected available are listed in the table (1). The calculation will follow these equations (lead times, lot size and time fence: fixed period, must be known):

Projected Available = beginning inventory + MPS shipments – forecasted demand . The MPS row shows when replenishment shipments need to arrive to avoid a stock out (negative projected available just to show the calculation)Week BI 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 50 50 50 50 75 75 75 75 50 50 50 50

Projected available 110 60 10 -40

MPS

Week BI 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 50 50 50 50 75 75 75 75 50 50 50 50

Projected available 110 60 10 85 35 -40

MPS 125

7

Page 8: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

Week BI 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 50 50 50 50 75 75 75 75 50 50 50 50

Projected available 110 60 10 85 35 85 10 -65

MPS 125 125

Week BI 1 2 3 4 5 6 7 8 9 10 11 12

Forecast 50 50 50 50 75 75 75 75 50 50 50 50

Projected available 110 60 10 85 35 85 10 60 110 60 10 85 35

MPS 125 125 125 125 125

And a typical Product structure diagram is shown in fig. below:

Fig.(6) Product structure diagram for product X with lead times.Assume 1 week to assemble X, to calculate the lead times for each part and then we have to set parts and the Quantities of Product -X in the table below:

parts quantity Unit scale Lead time(week)

Items Q. Total Q.

X 500 1 500 500A 2 each 1 500X2 1000

B 1 = 2 500X1 500C 3 = 2 500X3 1500

8

Page 9: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

D 2 = 1 500X2 1000E 3 = 2 500X3 1500

5 weeks 4 3 2 1 0

Fig. (7) lead times for Product X

Time-phased Bills: lead time scheduling:Forward scheduling: start at today‘s date and schedule forward to determine the earliest date the job can be finished. If each item takes one period to complete, the clipboards can be finished in three periods.

Backward scheduling: start at the due date and schedule backwards to determine when to begin work. If an order for clipboards is due by period three, we should start production now.

Lot sizing rules: For purchased items or for technical reasons, there may be a minimum or maximum order sizes .Purchased items/subassemblies may require multiples of predetermined amounts (e.g., multiples of 50).Rules are used to change the frequency of replenishment orders & set the quantity of each order (balance holding & ordering costs to reduce total costs). Common rules used for lot sizing determination are:

Lot-for-lot ordering policy: Lot-for-Lot (L4Lor LFL) you plan using lot-

for-lot order quantity, when you want to procure the exact lot size again. Lots as

9

B- sub assemble

X: end

E

A- sub C

D

Page 10: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George

required or planned.

Fixed-size lot ordering policy (FOQ): It is useful to select a fixed lot size for

a material, if it is only delivered, for example, in pallets of a certain quantity

or in tanks of a certain size.

- Minimum order quantities

- Maximum order quantities

- Multiple order quantities

- Economic order quantity

- Periodic order quantity

Example Comparing Lot Size Rules: Three common lot sizing rules used within MRP Systems are fixed order quantity (FOQ), lot for lot (L4L), and period order quantity (POQ). Cost comparison is based on Inventory holding costs ($0.10 per period) and ordering cost ($25 per order). In this example POQ is best at $133.50.

10

Page 11: What is Master Production Schedule or MPS? - … · Web viewWhat is Master Production Schedule or MPS? A Master Production Schedule or MPS is the plan that a company has developed

3 rd. year -Industrial Eng. Chapter 3 Production Planning & control2011- 2012 Dr. May George