Water Security and Dams Rehab. Workshop - World...
-
Upload
doankhuong -
Category
Documents
-
view
218 -
download
1
Transcript of Water Security and Dams Rehab. Workshop - World...
19 September 2017
Dam Rehabilitation:
Financial Instruments, O&M and Sustainability
Water Security and Dams Rehab. Workshop
• The financial instruments, PPP and new instruments and approaches developed by the
Bank applicable to large dams rehab and construction considering the context of ECA
countries and Bulgaria in particular;
• World Bank’s «cascade approach»;
• Examples of private financing of dam rehabilitation.
2
PRESENTATION OUTLINE
3
Value of dams as “collateral”
➢ Like all immoveable assets, dams are … worthless as collateral without an enforceable contract
that provides for a secure stream of revenues.
➢ It is necessary to take security over them, mostly as a defensive measure.
• This can be difficult under the laws of most countries because under the laws of most countries it is
not possible to transfer the ownership interest in a riverbed / dam.
• Instead, the government issues a license or – in the case of the Republic of Georgia, for example – a
right to build. Local law governing the transfer of such licenses or rights to build is critical.
➢ Lenders address these issues in the Direct Agreement.
4
Benefits, issues
➢ Potential benefits
• Additional power
• Additional energy / water
• Life extension.
➢ Issues
• Interruption of generation / production
6
World Bank Group’s “cascade approach” (1/3)
➢ a “cascade approach” to investment decision-making to encourage private sector participation,
while leveraging and preserving scarce public dollars for critical public investments.
➢ If commercial financing is available, that is the preferred course.
➢ If it is absent, we try to address market failures.
➢ If those efforts are unsuccessful, we use utilize risk instruments and our own matching capital to
try to encourage private investment.
➢ Finally, if absolutely necessary, then public and concessional financing will be used.
7
World Bank Group’s “cascade approach” (2/3)
Project is economically
viable and a government
priority?
Financially
Viable?
Political
Risk Ok?
Commercial
Risk Ok?
Project Risk
Ok?
Overt
subsidy?
Partial risk
Guarantees
Government
Guarantees?Mitigate /
Insure?
Public Sector
Project
Private Sector
Project
PPP
Yes
Yes Yes Yes Yes
No No No No
No No No No
Yes Yes Yes Yes
9
Overview of financial products
Types of Finance Source Interest Tenor
Concessionary finance grants or soft loans
Bilateral sources or multilateral development agencies; carbon credits
Very low interest rates Long term
Public equity
Public investment (Government supported). At times public equity is indirectly funded through bilateral/multilateral development banks
Dividends cans start low and increase over time
Indefinite
Public debtLoans from the Government, public bonds or multilateral development banks
Low; interest rate set by Government or Development Banks
Medium to long-term with optional grace period
Export credit Finance through Export Credit Agencies Medium to high Variable but commonly short to medium term
Private commercial debtPrivate banks, commercial arm of Development Banks
High interest (may be lower in presence of a guarantee)
Short to medium term (possibly extended with guarantees)
Private equityPrivate sponsors, private investors, commercial arm of Development Banks
High dividends are expect for risk compensation
Depends on length of concession
10
World Bank Group offers a wide range of financial products
➢ Sovereign loans
➢ Political insurance guarantees
➢ Partial risk / credit guarantees
➢ …
➢ Subnational loans
➢ Corporate Debt
➢ Equity
➢ Project Debt
11
Subnational and “Private-sector” financial products
➢ Subnational Finance
• Banks lend to state-owned corporations (SOEs) / subnational entity which will
implement the hydro project: they will be responsible for debt service
• SOEs need to be operated at “arm’s length”.
• Credit assessment focused on the borrower’s ability to service the interest: credit rating,
assessment of cash flows (e.g. local tax revenue).
➢ Corporate Finance
• Banks lend to private project companies which will implement the project
• Project company is responsible for debt service (multiple revenue streams?)
• Credit Assessment is not focused on what the debt will be used for but rather on the overall project
company’s ability to service the interest and to repay the debt.
➢ Project Finance
• Focus on bankability rather than the collateral of the investor
• Project Company repays the interest and capital from the free cash available to service the debt
• Project Company assets may serve as collateral to reduce the risk of the sponsor (e.g. proceeds of
sales agreements (off-take agreements), a pledge of shares in the project company…).
12
Financing decision – key risks (1/2)
➢ Hydrological risk:
• most sensitive issue
• determines the income generated / availability payments
• reliable data basis is highly important
• risk mitigation through long-term time series of daily hydrological data and a sound
methodology for the determination of the expected flow at the potential site
• still uncertainties due to climate change
• can be simulated with a financial model
➢ Permitting risk/Political risk:
• inefficient administration/changes in legal framework might seriously hamper the project
development process
• liaison with responsible administrative body can mitigate this risk
➢ Payment default:
• off-taker (utility) might not be able to hold payment obligations
• Escrow account with a minimum holding or Government guarantees can mitigate this
risk
13
Financing decision – key risks (2/2)
➢ Local currency devaluation:
• If the financial market is not developed enough to provide for formal hedging, the risk
has to be borne by the project company.
➢ Affordability of local domestic tariffs:
• debt service is highest during initial years
• grace periods and tenors need to be maximized and the government may defer its
dividends, royalties or taxes to mitigate this risk
➢ Cost overrun:
• 30+% risks for HPPs
• exposure to external factors makes these costs very difficult to predict
➢ Seasonality dynamics:
• Resource / demand risk
14
Sector considerations
➢ Irrigation water :
• Water value: < 0.01 €/m3.
➢ Energy generation :
• Water value: 0.002 – 0.11 €/m3.
➢ Bulk potable water supply:
• Water value: 0.10 – 0.50 €/m3.
15
Example project financed expansion: Bumbuna Phase II
➢ The Bumbuna II hydropower project, located on the Upper Seli River in North East Sierra Leone,
is the country's largest infrastructure project and is a key part of the Government of Sierra Leone’s
long term Energy Plan.
➢ The project involves building an extension to the existing 50 MW Bumbuna I facility. When
complete, Bumbuna II will add 143MW of new capacity and, critically, will provide Sierra Leone
with a minimum of 80MW of reliable, all-year round affordable electricity.
➢ Construction on Bumbuna II is anticipated to start by mid-2018 with operations forecast to start
four years later. Seli Hydropower, the local project company jointly owned by Joule Africa and its
local partner Energy Services Company (ESCO,) will be responsible for building, owning and
operating Bumbuna II.
➢ In August 2017, Joule Africa signed a 25 year Power Purchase Agreement (PPA) with the
Government of Sierra Leone, marking an important milestone in the development of the project.
16
Example of corporate-financed rehabilitation: Binga (1/2)
➢ A recent refurbishment project has transformed Binga – among the oldest hydroelectric facilities in
the Philippines – into a modern, state of the art plant.
➢ The 100MW power plant is connected to a zoned earth, rockfill embankment dam with an inclined
clay core. The facility began commercial operation in 1960 - four years after construction began by
the Philippine government for the purposes of power generation and flood control.
➢ In 2001, the government restructured the power industry and a component of this initiative was the
privatisation of state-owned power facilities. SN Aboitiz Power (SNAP, a joint venture between SN
Power of Norway and local company Aboitiz Power Corporation) won the public bid in 2007 for the
Binga power plant, which was sold as a package with nearby Ambuklao hydro facility. Even as
SNAP took over operations the following year, the dam remained government-owned.
17
Example (rehabilitation): Binga (2/2)
➢ Three-year rehabilitation project.
• Civil works for the new headrace and intake began in May 2010. Due to silt accumulation, the new
intake would be 15m higher than the old one. A 240m access tunnel was built to connect the new
160m headrace and intake to a part of the existing headrace. This phase was completed in
September 2011.
• The next step was replacing the electrical and mechanical components. Each of the four units was
taken down and replaced with new turbines, generators, transformers and main inlet valves. To keep
the plant in operation, unit rehabilitation was done one at a time.
• Rehabilitation of the first unit (Unit 4) commenced in April 2011, followed by Unit 1 in January 2012
and Unit 3 in July 2012. Work on the final unit (Unit 2) was completed in July 2013. The 50-year old
plant was transformed into a modern, state-of-the-art facility: new transformers were installed at the
switchyard and the powerhouse buildings also underwent repairs.
• Although its nameplate capacity is 125MW, the plant is actually capable of generating up to 132MW
and potentially even more. Binga now generates additional capacity, which is being traded at the
Wholesale Electricity Spot Market, and supplies ancillary services for grid stability. Its expected
annual output is about 426GWh.
Example of project-financed bulk water supply project: Lima OCC (1/3)
Rímac riverPomacocha
Reservoir
Río Blanco river
reservoirs
(future)
South
branch
(future)
PTA
Huachipa
1st stage
(existing)
PTA
Huachipa
2nd stage
(future)
Lima
Huarochirí
Yauli
Huallacocha
Bajo
Reservoir
Trans-Andean
tunnel (future)North
branch
(existing)
Left Bank Canal
Right Bank
Canal
19
Example (expansion): Lima OCC (2/3)
➢ .
LEFT BANK CANAL
POMACOCHA DAM ELEVATION
HUALLACOCHA BAJO DAM
ELEVATION OR CONDITIONING
EXIT GATEWAY
00RIGHT BANK CANAL
Pomacocha Dam (Today)
24.4 MMC at 4262 masl
Huallacocha Dam (Today)
11.7 MMC at 4345 masl
90 MMC
Example (expansion): Lima OCC (3/3)
➢ US$ 600m expansion project.
➢ Long term bulk water purchase agreement with SEDAPAL (public water utility of Lima)
➢ 15% “average” total tariff increase.
➢ Will eliminate summer water deficit.
➢ Least cost solution
➢ Low NRW (29%)
➢ SEDAPAL is financially solid (no need for sovereign guarantee)
➢ Possible credit enhancement: escrow of receivables (outsourced).