Dear All,
kindly focus on our 4th meeting of TRS VSM PROJECT-2,
MOM For TRS VSM PROJECT-2 (1/7/2013) &(4/7/2013)
Team member attendence:- on 1/7/2013 : Mr. Manoj (On Leave)
Mr. Narender (On Leave)
on 4/7/2013 : Mr. Nagraj (on leave)
Today's team discussion :-( Following are the combined discussion point of two days)
1. Four report :- Line-5 Operation wise WIP :- WIP @ line reduced to 600pc.
A/c to report at Front & Back we have 60% inventory of Total WIP. Attendence report :-less than 1% M/C Breakdown summery report :- Total B/D 65 min and
yesturday B/D on 10 m/cs Quality report :- not
discuss
2. Cutting feeding plan :- Discuss with Mahadev, By 2/7/2013he will be feed"200pc before 10:30am" and "200pc Between 2:00 to3:00".
3. Machine and Trolly:- We have only 200 trolly in line-5, trying to arrange 100 more as soon as
possible. SINGLE PC MOVEMENT by Brain-
storming :- Team member : 15 member (Operator & lineQC). BRAINSTORMING ON 5/7/2013 @ 11:00 TO 12:00 IN HR AUDITORIAM Meeting time :- New meeting time: 3:00 to 4:00 ( TUESDAY,THRUSDAY & SATURDAY)
-
7/30/2019 Vsm Streamlining
2/6
Next meeting Target and Discusion Point :
1. Four report :- Data collection of last month2. Trolly details of each line :- Plan for arranging 100 trolly and its
identification mark.
3. SINGLE PC MOVEMENT by Brain-storming :- Team membersDiscussion on Brain-storming .
THANX & REGARDS
TRS VSM TEAM
From: Dhiraj Kumar
Sent: Sunday, June 30, 2013 3:44 PMTo: Manojkumar Mr; Nagaraj YK; Narendra M; Sudhakar RajuCc: [email protected]; Hiral N Lakdawala; Brijkishore Sharma;[email protected]: MOM of Trs VSM project-2
Dear All,
Kindly focus on our 3rd meeting of TRS VSM PROJECT-2,
MOM For TRS VSM PROJECT-2 (28/6/2013)
Team member attendence:- Mr.Mruthunjay (absent)
Mr. Narender (absent)
Today's team discussion :-
1. Project Time line :- Time line will be decided after completion ofBrain-storming.
2. Four report :- Line-5 Operation wise WIP :- WIP @ line
reduced to 800pc. A/c to report at Front & Back wehave 60% inventory of Total WIP.
Attendence report :-less than 4%.
-
7/30/2019 Vsm Streamlining
3/6
M/C Breakdown summery report :- Notdiscuss
Quality report :- Majority Issue , 1) BottomHeming & 2)Pintack
3. Cutting feeding plan :- We have plan of "200pc before 10:30am" and"200pc Between 2:00 to 3:00". (Next meeting need to discuss with cutting incharge)
4. On next Topic SINGLE PC MOVEMENT by Brain-storming :-Team has decided that Brain-Storming will started from Bottom. So we going to make a team
from each section one-one member.
Next meeting Discussion on :-
1.Four report2.Cutting feeding plan ( With Mahadev )3.Machine and Trolly
SINGLE PC MOVEMENT by Brain-storming :- Team member Selection (Only forBrain-storming)
Meeting time :- Need to change our meeting time because other few meetingtime collapsed.
Thanx & Regards
TRS VSM TEAM
-
7/30/2019 Vsm Streamlining
4/6
From: Dhiraj KumarSent: Wednesday, June 26, 2013 8:02 PMTo: Manojkumar Mr; Narendra M; Nagaraj YKCc: [email protected]; Hiral N Lakdawala; Brijkishore Sharma;[email protected]: MOM of Trs VSM project-2
Dear ALL
MOM For TRS VSM PROJECT-2 (26/6/2013)
Team member attendence:-All member present
One new member :- Mr. Nagraj (I.E)
Today team discuss on Topic :-
Operation Breakdown and Layout :-1. M/c's layout change (Added 5 m/c in line before Auto-serging)2. Manpower : Plan to set 7 operator a/c to change (dont have any operator
requirement)3. Shortage of Team leader : Team has decided to give a chance to
KANTHAMMA(5259) for Assembly-14. Trolly or Hangers : We have decided to maintain 300 trolly from loading table to
end operation and also make a mark on that with some spacial colour.
All team member will be meet in line @ 12:00 to 1:00 (Daily) During project period, Vasant will be the maintanace member for Line-5
Only
Next meeting Discussion on :-
1. Project Time line2. Four report3. Cutting feeding plan4. On next Topic SINGLE PC MOVEMENT by Brain-storming
Regards
-
7/30/2019 Vsm Streamlining
5/6
VSM TROUSER
From: Dhiraj KumarSent: Sunday, June 23, 2013 1:06 PM
To: Manojkumar Mr; Narendra MCc: [email protected]; Hiral N Lakdawala; Brijkishore Sharma;[email protected]:
Dear ALL,
This is information to you that Our TRS VSM starting 2ND project for sewing line-5 from 22/6/2013. Below mention MOM of first meeting:---
MOM For TRS VSM PROJECT-2
PROJECT TITLE:- LINE-'5' STREAM LINE
TEAM MEMBERS:-
1) Narander ( Production )
2) Manoj ( Quality )
3) Mruthunjay ( Maint. )
4) Dhiraj (Production )
MEETING TIME:- Every Monday , Wednesday , Friday @ 3:30 to 4:00
PROJECT TOPIC:-
Reduce existing WIP ( Standarization of wip ) Operation Breakdown and Layout ( layout including preparatory itself in line ) Single pc. movement ( Brain-
storming )
REPORT:- DISCUSSING DURING MEETING
-
7/30/2019 Vsm Streamlining
6/6
Line-5 Operation wise WIP (Daily report) :- ( By Dhiraj) Attendence report :- ( By Narender) M/C Breakdown summery report :- ( By Mruthunjay) Quality report :- ( By MANOJ)
Regards
DHIRAJ KUMAR
TRS VSM