    Dear All,

    kindly focus on our 4th meeting of TRS VSM PROJECT-2,

    MOM For TRS VSM PROJECT-2 (1/7/2013) &(4/7/2013)

    Team member attendence:- on 1/7/2013 : Mr. Manoj (On Leave)

    Mr. Narender (On Leave)

    on 4/7/2013 : Mr. Nagraj (on leave)

    Today's team discussion :-( Following are the combined discussion point of two days)

    1. Four report :- Line-5 Operation wise WIP :- WIP @ line reduced to 600pc.

    A/c to report at Front & Back we have 60% inventory of Total WIP. Attendence report :-less than 1% M/C Breakdown summery report :- Total B/D 65 min and

    yesturday B/D on 10 m/cs Quality report :- not

    discuss

    2. Cutting feeding plan :- Discuss with Mahadev, By 2/7/2013he will be feed"200pc before 10:30am" and "200pc Between 2:00 to3:00".

    3. Machine and Trolly:- We have only 200 trolly in line-5, trying to arrange 100 more as soon as

    possible. SINGLE PC MOVEMENT by Brain-

    storming :- Team member : 15 member (Operator & lineQC). BRAINSTORMING ON 5/7/2013 @ 11:00 TO 12:00 IN HR AUDITORIAM Meeting time :- New meeting time: 3:00 to 4:00 ( TUESDAY,THRUSDAY & SATURDAY)

  • 7/30/2019 Vsm Streamlining

    2/6

    Next meeting Target and Discusion Point :

    1. Four report :- Data collection of last month2. Trolly details of each line :- Plan for arranging 100 trolly and its

    identification mark.

    3. SINGLE PC MOVEMENT by Brain-storming :- Team membersDiscussion on Brain-storming .

    THANX & REGARDS

    TRS VSM TEAM

    From: Dhiraj Kumar

    Sent: Sunday, June 30, 2013 3:44 PMTo: Manojkumar Mr; Nagaraj YK; Narendra M; Sudhakar RajuCc: [email protected]; Hiral N Lakdawala; Brijkishore Sharma;[email protected]: MOM of Trs VSM project-2

    Dear All,

    Kindly focus on our 3rd meeting of TRS VSM PROJECT-2,

    MOM For TRS VSM PROJECT-2 (28/6/2013)

    Team member attendence:- Mr.Mruthunjay (absent)

    Mr. Narender (absent)

    Today's team discussion :-

    1. Project Time line :- Time line will be decided after completion ofBrain-storming.

    2. Four report :- Line-5 Operation wise WIP :- WIP @ line

    reduced to 800pc. A/c to report at Front & Back wehave 60% inventory of Total WIP.

    Attendence report :-less than 4%.

  • 7/30/2019 Vsm Streamlining

    3/6

    M/C Breakdown summery report :- Notdiscuss

    Quality report :- Majority Issue , 1) BottomHeming & 2)Pintack

    3. Cutting feeding plan :- We have plan of "200pc before 10:30am" and"200pc Between 2:00 to 3:00". (Next meeting need to discuss with cutting incharge)

    4. On next Topic SINGLE PC MOVEMENT by Brain-storming :-Team has decided that Brain-Storming will started from Bottom. So we going to make a team

    from each section one-one member.

    Next meeting Discussion on :-

    1.Four report2.Cutting feeding plan ( With Mahadev )3.Machine and Trolly

    SINGLE PC MOVEMENT by Brain-storming :- Team member Selection (Only forBrain-storming)

    Meeting time :- Need to change our meeting time because other few meetingtime collapsed.

    Thanx & Regards

    TRS VSM TEAM

  • 7/30/2019 Vsm Streamlining

    4/6

    From: Dhiraj KumarSent: Wednesday, June 26, 2013 8:02 PMTo: Manojkumar Mr; Narendra M; Nagaraj YKCc: [email protected]; Hiral N Lakdawala; Brijkishore Sharma;[email protected]: MOM of Trs VSM project-2

    Dear ALL

    MOM For TRS VSM PROJECT-2 (26/6/2013)

    Team member attendence:-All member present

    One new member :- Mr. Nagraj (I.E)

    Today team discuss on Topic :-

    Operation Breakdown and Layout :-1. M/c's layout change (Added 5 m/c in line before Auto-serging)2. Manpower : Plan to set 7 operator a/c to change (dont have any operator

    requirement)3. Shortage of Team leader : Team has decided to give a chance to

    KANTHAMMA(5259) for Assembly-14. Trolly or Hangers : We have decided to maintain 300 trolly from loading table to

    end operation and also make a mark on that with some spacial colour.

    All team member will be meet in line @ 12:00 to 1:00 (Daily) During project period, Vasant will be the maintanace member for Line-5

    Only

    Next meeting Discussion on :-

    1. Project Time line2. Four report3. Cutting feeding plan4. On next Topic SINGLE PC MOVEMENT by Brain-storming

    Regards

  • 7/30/2019 Vsm Streamlining

    5/6

    VSM TROUSER

    From: Dhiraj KumarSent: Sunday, June 23, 2013 1:06 PM

    To: Manojkumar Mr; Narendra MCc: [email protected]; Hiral N Lakdawala; Brijkishore Sharma;[email protected]:

    Dear ALL,

    This is information to you that Our TRS VSM starting 2ND project for sewing line-5 from 22/6/2013. Below mention MOM of first meeting:---

    MOM For TRS VSM PROJECT-2

    PROJECT TITLE:- LINE-'5' STREAM LINE

    TEAM MEMBERS:-

    1) Narander ( Production )

    2) Manoj ( Quality )

    3) Mruthunjay ( Maint. )

    4) Dhiraj (Production )

    MEETING TIME:- Every Monday , Wednesday , Friday @ 3:30 to 4:00

    PROJECT TOPIC:-

    Reduce existing WIP ( Standarization of wip ) Operation Breakdown and Layout ( layout including preparatory itself in line ) Single pc. movement ( Brain-

    storming )

    REPORT:- DISCUSSING DURING MEETING

  • 7/30/2019 Vsm Streamlining

    6/6

    Line-5 Operation wise WIP (Daily report) :- ( By Dhiraj) Attendence report :- ( By Narender) M/C Breakdown summery report :- ( By Mruthunjay) Quality report :- ( By MANOJ)

    Regards

    DHIRAJ KUMAR

    TRS VSM