Vogtle 3 & 4Current Status and Owner’s Perspective
Dale LloydVogtle 3 & 4 Project Support Director
Southern Nuclear Company
Southern Company Nuclear Fleet
• Operated by Southern Nuclear– Operates Southern Company’s 6 nuclear units
– 3,200 employees
• Experienced Operator
Southern Company Nuclear Fleet
• Experienced Operator– Plant operations
– In-house operational and engineering support
– Best practices and lessons learned
– O&M budget requirements
• Site location
– 30 miles southeast of Augusta, Georgia
– 3,169 acres
– 2 existing units in operation
– site originally designed for four units
Plant Vogtle Units 3 & 4
– site originally designed for four units
– adequate transportation access
• Low population density
• Supportive community
• Two new units at existing Vogtle site
• Westinghouse AP1000 technology
• Submit Early Site Permit (ESP) followed by a
Plant Vogtle Units 3 & 4
• Submit Early Site Permit (ESP) followed by a Combined Operating License (COL)
• Unit 3 COD Apr 2016
• Unit 4 COD Apr 2017
Ownership
• Georgia Power Company - 45.7%
• Oglethorpe Power (OPC) – 30%
• MEAG Power – 22.7%
• Dalton Utilities – 1.6%
• Task Force to evaluate feasibility (Spring 2005)
– Site selection
– Technology selection
• Initiated licensing work (2005)
Vogtle 3 & 4 Project History
• Initiated licensing work (2005)
• Project development
– Letter of Intent (Jan 2006)
– Contract negotiations (2006 – Apr 2008)
• Full Notice to Proceed Issued March 31, 2009
Vogtle 3 & 4 Key Dates
• August 2006 ESP application filed
• August 2009 ESP received
• March 2008 COL application filed• March 2008 COL application filed• Fall 2011 Expected receipt of COL
• April 2008 Execution of EPC contract with Westinghouse – Shaw consortium
Vogtle 3 & 4 Key Dates
• August 2008 Filed for Georgia Public Service Commission certification
• March 2009 Received certification from GeorgiaPublic Service Commission
• March 2009 Issued Full Notice to Proceed
• 2016 and 2017 Commercial operation
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 20172005
ESP Preparation ESP and LWA Review
08-15-06
ESP and LWA Received 8-27-09
PSC Certification Process
Proposal Submitted to the PSC for Certification
EPC Contract Signed
COLA Preparation NRC COL Review
4-8-08
8-1-08
Vogtle 3&4 Schedule
COLA Preparation NRC COL Review
COL Received (expected)
Non-Safety Related Construction
and Safety Related LWA Items
Safety Related Construction
10-2011
S/UCOD U34-1-2016
COD U44-1-2017
3-31-08
S/U
Vogtle 3 and 4
expansion is expansion is underway.
ConstructionMarch 23, 2009
Construction
Construction
Construction
Construction
Construction
October 21, 2009
25
30
Construction
Safety
• Safety Culture
–Industrial Safety Culture
–Nuclear Safety Culture–Nuclear Safety Culture
Licensing
• NRC Interaction
–Communication
–Resources–Resources
–NRC Inspectors On Site 2010
Licensing• ESP/COLA
COL RAI Performance Metrics
20
25
60
70
80
90
0
5
10
15
Jul-2008 Aug-2008 Sep-2008 Oct-2008 Nov-2008 Dec-2008 Jan-2009 Feb-2009 Mar-2009 Apr-2009 May-2009
RA
I
0
10
20
30
40
50
60
Cum
ula
tive R
AI
RAIs Received RAIs Officially Late Cumulative RAIs Received RAI Responses Submitted Cumulative
Licensing
• ITAAC Performance
VEGP 3 & 4 ITAAC Closure Loading (Initial Estimate)
500
600
700
800
900
ITA
AC
Clo
sure
0
100
200
300
400
500
3rd QTR
2009
3rd QTR
2010
3rd QTR
2011
3rd QTR
2012
3rd QTR
2013
3rd QTR
2014
3rd QTR
2015
3rd QTR
2016
3rd QTR
2017
3rd QTR
2018
Year
ITA
AC
Clo
sure
Vogtle 3 Vogtle 4 Vogtle 3 & 4Combined
Engineering
• Design Finalization
– I&C Design
– Simulator Development
• Impacts to Operating Units (Vogtle 1&2)
• Establishing Engineering Programs
Construction
• Establishment of Integrated Schedule
• Determining Amount of Oversight
• Implementing Lessons Learned
• Craft Labor
Procurement• World Wide Components Fabrication
Procurement
• Implementing Surveillance Program
• Module Fabrication
Steam Generator Tube Sheet InspectionSNC Materials and Inspection Services Principal Engineer
Quality Assurance
• Managing Expectations
• International Vendors• International Vendors
• Finding Qualified Staff
Operational Readiness
• INPO Program Accreditation
• Experience Requirements
– MOU with Existing Fleet– MOU with Existing Fleet
– Pre-training at Augusta Technical College
• Operator License Success Rate
Operational Readiness
• Instructor training class in progress
• 80 new hires at existing 6 units
• Detailed training schedule developed
• Additional staffing in progress
AP1000 Generic Staffing TimelineTotal Plant – Two Units
Safe,
On Schedule, On Schedule,
On Budget!