Agenda1. New shieldings2. New RP
calculations3. Protection against
overpressure4. Motorization (TAS
alignment)5. Survey issues6. Cooling7. Schedule8. AOB
Protection against overpressure
By O. Beltramello
Cooling
• Demineralized water• Routing agreed by integration (J-P Corso)• UJ 14 RB14• UJ16 RB16• Stainless steel pipes 2 x DN15 4 X DN12• Flexibles EPDM/Kevlar rad-hard 4m long• Adjustable circuit pressure• Target : installation in August
Schedule ATLAS TAS SCHEDULE
Date Week RB14 RB16 UX15
22-Jun 26
29-Jun 27
06-Jul 28 Cool-down --> 8o K
13-Jul 29 Bake-out
20-Jul 30 Cool-down --> 8o K Bake-out
27-Jul 31 Dome installation Shielding in monobloc
03-Aug 32 Dome installation Octogonal parts installation
10-Aug 33
17-Aug 34 Shielding in octogonal parts and Survey
24-Aug 35
31-Aug 36
07-Sep 37
14-Sep 38
Drawing
LHCTAS0044
Drawing
Pics
RB14 RB16