Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick...
Transcript of Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick...
Update on FCPSConstruction/Renovation Projects
August 2019
Brenda Cowan Elementary Architect: EOP Architects
General Contractor: Griggs Enterprises
GC Contract Sum: $17,860,200
Total Project Cost: $23,801,841
Change Orders to Date (14): $1,381,951.89
Scheduled Contract Completion Date: August 2019
% of Contract Completed: 82.92%
Revised Completion Date Areas C, D & E – August 8, 2019per GC: Areas A & B – September 11, 2019
August 2019
Brenda Cowan ElementarySchematic Rendering of Final Façade
August 2019
Brenda Cowan Elementary Work Completed (July):
Front Entry curtainwall 99% complete
Painting 99% complete in corridor Sectors D & E
Terrazzo 100% complete on Sectors C, D, E
Gym 100% complete (punch list ongoing)
Walkway Canopy wiring 100% complete
South brick retaining walls 100% complete
North brick retaining wall 100% complete at Sector A exterior sidewalk.
Front Foyer drywall installation 100% complete
Exterior sidewalks 95% complete
Playground area sidewalks 95% complete
August 2019
Brenda Cowan Elementary Current Work Effort (August):
Casework 55% complete Sectors A & B
First coat of painting completed in Sectors A & B
Complete metal wall and roof panels
Complete storm and earthwork
Complete Food Service equipment installation
Window installation started in Sectors A & B
Final grading to be completed.
Retaining walls to be completed.
Terrazzo to be started in Sectors A & B
Start Plumbing fixture installation Sectors A & B
Media Center and computer classrooms to be completed
Ribbon Cutting held on August 12th with first day of school August 14thh.
August 2019
August 2019
August 2019
Brenda Cowan Elementary
August 2019
Entrance Lobby
Cafeteria Gym
Brenda Cowan Elementary
August 2019
Sector B Classroom Sector B Corridor
Sector A Corridor Sector A Classroom
STEAM & Success Academies Architect: Ross Tarrant Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $22,108,500.00
Total Project Cost: $26,990,125.53
Change Orders to Date (0): $0
Scheduled Contract Completion Date: October 15, 2020
% of Contract Completed: 4.0%
Revised Completion Date per GC: No Change
August 2019
STEAM & Success AcademiesSchematic Rendering of Final Façade
August 2019
STEAM & Success Academies Work Completed (July):
General Contractor has mobilized. Contractor and major subcontractor bonds and insurance are secured.
First floor demolition & disposal is in progress—30% of total interior demolition work (excluding sanctuary balcony seating) is complete.
Gym floor protection is fully installed.
New interior footings are being laid out to cut in existing slab.
August 2019
STEAM & Success Academies Current Work Effort (August):
Silt fence and temporary job fence to be installed.
Site demolition to begin in the area where geothermal drilling is to occur.
Interior building demolition to be nearly complete in areas A & C and to continue in Area B.
Foundations to be completed in Area B and MEP underslab rough-ins to begin.
Foundations to begin in Areas A & C
August 2019
STEAM & Success Academies
August 2019
Demo Disposal 1st Floor Demo
1st Floor Demo 1st Floor Demo
STEAM & Success Academies
August 2019
1st Floor Demo Storefront Demo for Debris Removal
Gym Floor Protection Gym Floor Protection