Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick...

15
Update on FCPS Construction/Renovation Projects August 2019

Transcript of Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick...

Page 1: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

Update on FCPSConstruction/Renovation Projects

August 2019

Page 2: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

Brenda Cowan Elementary Architect: EOP Architects

General Contractor: Griggs Enterprises

GC Contract Sum: $17,860,200

Total Project Cost: $23,801,841

Change Orders to Date (14): $1,381,951.89

Scheduled Contract Completion Date: August 2019

% of Contract Completed: 82.92%

Revised Completion Date Areas C, D & E – August 8, 2019per GC: Areas A & B – September 11, 2019

August 2019

Page 3: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

Brenda Cowan ElementarySchematic Rendering of Final Façade

August 2019

Page 4: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

Brenda Cowan Elementary Work Completed (July):

Front Entry curtainwall 99% complete

Painting 99% complete in corridor Sectors D & E

Terrazzo 100% complete on Sectors C, D, E

Gym 100% complete (punch list ongoing)

Walkway Canopy wiring 100% complete

South brick retaining walls 100% complete

North brick retaining wall 100% complete at Sector A exterior sidewalk.

Front Foyer drywall installation 100% complete

Exterior sidewalks 95% complete

Playground area sidewalks 95% complete

August 2019

Page 5: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

Brenda Cowan Elementary Current Work Effort (August):

Casework 55% complete Sectors A & B

First coat of painting completed in Sectors A & B

Complete metal wall and roof panels

Complete storm and earthwork

Complete Food Service equipment installation

Window installation started in Sectors A & B

Final grading to be completed.

Retaining walls to be completed.

Terrazzo to be started in Sectors A & B

Start Plumbing fixture installation Sectors A & B

Media Center and computer classrooms to be completed

Ribbon Cutting held on August 12th with first day of school August 14thh.

August 2019

Page 6: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

August 2019

Page 7: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

August 2019

Page 8: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

Brenda Cowan Elementary

August 2019

Entrance Lobby

Cafeteria Gym

Page 9: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

Brenda Cowan Elementary

August 2019

Sector B Classroom Sector B Corridor

Sector A Corridor Sector A Classroom

Page 10: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

STEAM & Success Academies Architect: Ross Tarrant Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $22,108,500.00

Total Project Cost: $26,990,125.53

Change Orders to Date (0): $0

Scheduled Contract Completion Date: October 15, 2020

% of Contract Completed: 4.0%

Revised Completion Date per GC: No Change

August 2019

Page 11: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

STEAM & Success AcademiesSchematic Rendering of Final Façade

August 2019

Page 12: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

STEAM & Success Academies Work Completed (July):

General Contractor has mobilized. Contractor and major subcontractor bonds and insurance are secured.

First floor demolition & disposal is in progress—30% of total interior demolition work (excluding sanctuary balcony seating) is complete.

Gym floor protection is fully installed.

New interior footings are being laid out to cut in existing slab.

August 2019

Page 13: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

STEAM & Success Academies Current Work Effort (August):

Silt fence and temporary job fence to be installed.

Site demolition to begin in the area where geothermal drilling is to occur.

Interior building demolition to be nearly complete in areas A & C and to continue in Area B.

Foundations to be completed in Area B and MEP underslab rough-ins to begin.

Foundations to begin in Areas A & C

August 2019

Page 14: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

STEAM & Success Academies

August 2019

Demo Disposal 1st Floor Demo

1st Floor Demo 1st Floor Demo

Page 15: Update on FCPS Construction/Renovation Projects · Walkway Canopy wiring 100% complete South brick retaining walls 100% complete North brick retaining wall 100% complete at Sector

STEAM & Success Academies

August 2019

1st Floor Demo Storefront Demo for Debris Removal

Gym Floor Protection Gym Floor Protection