Transfer Station
-
Upload
vanilivanili -
Category
Documents
-
view
9 -
download
1
description
Transcript of Transfer Station
-
Module 4 (3)
Collection, transport, transfer
-
Types of transfer stations Direct load TS : the wastes in the collection vehicles are
emptied directly into the open top transfer vehicle, or into the compacting facilities, or into waste bales that are transported to landfill, or onto a moving conveyor to transport them to processing facilities. Sometimes the wastes are emptied onto an unloading platform, and then pushed into transfer vehicles (surge capacity, emergency storage capacity)pushed into transfer vehicles (surge capacity, emergency storage capacity)
Storage load TS: wastes from collection vehicles are placed in the storage pit, and pushed into open-top transport trailers or into compaction facilities, or into a moving conveyor to transport them to processing facilities
Combined direct load and discharge load: wastes discharged onto unloading platform. After recyclable materials have been removed, the remaining waste is loaded into transport trailers with front end loaders
-
Types of TS
-
Classification of TS according to capacity
Small (less than 100 ton/day)
Medium (between 100 - 500 ton/day)
Large (more than 500 ton/day)
-
Direct load TS without compaction
Wastes are directly emptied to transport vehicle
TS consists of 2 levels: Elevated level: unloading platform, where wastes from
collection vehicle are emptied
Lower level: loading platform, where wastes are loaded to transport vehicletransport vehicle
Operation: Arriving truck is weighed in the weigh bridge
Truck driver is given stall number for unloading
Unloading process
Reweighing of the trucks
Payment of disposal fee
-
Direct Load TS
Weigh
booth
Platform
Approach ramp
Platform
scale
-
Direct load TS
-
Direct load TS with compactors
Equipped with compactors
Wastes are compacted in the trailers
Wastes are compacted to produce waste bales
Rubber tired vehicle is used to load the wastes Rubber tired vehicle is used to load the wastes
from the unloading zone into the compactor
Objective of compaction: to reduce volume for
reducing transfer cost
-
Compactor with open
top direct load chute
Large capacity baler.Wastes are loaded into baler with continuous
feed conveyor
-
Medium
capacity direct
load TS
-
Small capacity direct load TS
-
Direct load TS with compaction
-
Storage load TS
Wastes are emptied directly into a storage pit
Then the wastes are loaded into transport
vehicles by auxiliary equipment
The storage load TS has a capacity to store The storage load TS has a capacity to store
wastes 1-3 days
-
Large capacity
storage load TS
(2000 t/day)
-
Storage load TS without compaction
-
Combined direct load and discharge
load TS
This system is used when material recovey
from SW (MRF) is operated
Collection trucks are weighed, and proceed
direct load of SW to the trailersdirect load of SW to the trailers
Individual waste haulers go to scale house for
check in. Recyclable materials should be
stored in the Recycling area. Other wastes are
disposed of in the public unloading area.
-
Combined direct
load and discharge
load TS
-
TS with MRF
Generally involves loading of trailers with
separated and or processed materials (eg
baled paper, cardboard, plastics)
Involves direct load and storage load Involves direct load and storage load
operations
-
Storage load TS with processing and
compaction facilities
-
TS design requirements
Type of transfer operation to be used
Storage and throughput capacity
requirements
Equipment and accessory requirements Equipment and accessory requirements
Sanitation requirements
-
TS capacity requirements
Throughput and storage capacity
requirements must be evaluated carefully
Throughput capacity: collection vehicles
should not wait too long to unload (WHY?)should not wait too long to unload (WHY?)
Trade-off analysis between the TS capacity
and transport operation (equipment & labor
components) cost should be made.
-
Transport vehicles
Requirements:
Wastes must be transported at minimum costs
Wastes must be covered during the haul operation
Vehicles must be designed for highway traffic Vehicles must be designed for highway traffic
Vehicle capacity must not exceed allowable weight
Methods for unloading must be simple
-
Types of transport vehicles
-
Unloading must be simple
-
MATERIAL RECOVERY FACILITIES (MRF)
MRF is a facility where solid wastes are separated and processed.
MRF may be integrated with transfer facilities (MR/TF)
MRTF include the functions of: A drop off center for separated wastes. Recyclable wastes have
been separated at source. People bring separated waste to the been separated at source. People bring separated waste to the drop off center
A materials separated facility: manual or mechanical
Size reduction facility: shredders, hammer mill, cyclone separator rtc
A facility for composting and bioconversion of solid wastes
A facility for the production of refuse derived fuel, and transfer & transport facility
-
Waste separation
-
MRF Activities
-
Most commonly used SW
transformation
Objective: to reduce SW quantity to be
disposed of
Chemical transformation: combustion, in
conjunction to energy recoveryconjunction to energy recovery
Biological transformation: aerobic composting
-
Studi kasus I
TPS Permukiman di Kota Surabaya memiliki luas 100-300 m2
Jumlah KK yang dilayani 500, dengan timbulan sampah rumah tangga 0.3 kg/kap.hari. Rata2 jumlah anggota keluarga = 4 orang
Densitas sampah lepas 150 kg/m3, di dalam kontainer 300 kg/m3
Komposisi sampah:
Sampah basah 70% - Gelas : 2% Sampah basah 70% - Gelas : 2%
Plastik : 15% - Tekstil : 2%
Kertas: 6 % - Logam: 1 %
Karet/kulit: 2 % - Sampah lain : 2%
Teknologi apakah yang dapat diterapkan, serta jelaskan pula akan kebutuhan SDM dan sarana prasarana
Berapa luas minimum lahan yang dibutuhkan untuk realisasi rekomendasi Anda tersebut?
-
Studi kasus II
TPS Pasar di Kota Surabaya memiliki luas rata-rata 200 m2
Timbulan sampah 20 m3/hari
Densitas sampah lepas 200 kg/m3, di dalam kontainer 400 kg/m3
Komposisi sampah:
Sampah basah 80%- Gelas : 0.5%
Plastik : 14% - Tekstil : 0%
Kertas: 3 % - Logam: 0.5 % Kertas: 3 % - Logam: 0.5 %
Karet/kulit: 1 % - Sampah lain : 1%
Rekomendasikan upaya pengembangan TPS tersebut menjadi prasarana yang berbasis pengurangan sampah
Teknologi apakah yang dapat diterapkan, serta jelaskan pula akan kebutuhan SDM dan sarana prasarana
Berapa luas minimum lahan yang dibutuhkan untuk realisasi rekomendasi Anda tersebut?
-
Studi kasus III
TPS sebuah kompleks Pertokoan di Kota Surabaya memiliki luas 200 m2
Timbulan sampah 25 m3/hari
Densitas sampah lepas 200 kg/m3, di dalam kontainer 400 kg/m3
Komposisi sampah:
Sampah basah 60% - Gelas: 2 %
Plastik : 25% - Tekstil : 1 %
Kertas: 3 % - Logam: 2 % Kertas: 3 % - Logam: 2 %
Karet/kulit: 1 % - Sampah lain : 1%
Rekomendasikan upaya pengembangan TPS tersebut menjadi prasarana yang berbasis pengurangan sampah
Teknologi apakah yang dapat diterapkan, serta jelaskan pula akan kebutuhan SDM dan sarana prasarana
Berapa luas minimum lahan yang dibutuhkan untuk realisasi rekomendasi Anda tersebut?
-
Asumsi2
Laju pemilahan manual oleh seorang pekerja: 1 m3/jam
Harga conveyor sepanjang 100 m USD 50.500. Sedangkan harga yang memiliki panjang 200 m USD 80.000 Laju pemilahan dengan conveyor 2 m3/jam.pekerja
Upah pekerja Rp. 40.000/hari. 1 hari 8 jam kerja, dengan waktu istirahat 1 jamistirahat 1 jam
Harga produk daur-ulang/hasil pemilahan:
Kompos: Rp. 1000/kg
Plastik campuran: Rp. 1500/kg
Kertas campuran: Rp. 900/kg
Logam campuran: Rp. 1500/kg
Harga plastik, kertas, dan logam yang terpisah lebih lanjut lebih tinggi, dan dapat diasumsikan secara khusus.