Tailings Deposition into Open Pit Consolidation Modelling · 2017-03-21 · Tailings Deposition...
Transcript of Tailings Deposition into Open Pit Consolidation Modelling · 2017-03-21 · Tailings Deposition...
McArthur River Mine
Overburden Management Project
Draft Environmental Impact Statement
ACAppendix AC
Tailings Deposition intoOpen Pit Consolidation Modelling
3 November 2016
Jamie Hacker
McArthur River Mining
PO Box 36821
Winnellie NT 0821
Our ref: 32/17476/05 65221 Your ref:
Dear Jamie
Tailings Deposition into Open Pit
Consolidation Modelling and Deposition Concept
1 Introduction
McArthur River Mine (MRM) is planning to utilise the existing pit void, approximately 385 m deep, for long
term storage of the tailings and Potential Acid Forming (PAF) waste rock at closure. Tailings are
currently stored at the out-of-pit Tailings Storage Facility (TSF) and will be dredged and reprocessed and
the resulting tailings slurry would be pumped to the pit void for in-pit disposal. The in-pit deposition will
be undertaken over a 10-year period at a production rate of 10.5 Mtpa.
This letter report summarises the results of consolidation analyses undertaken for the in-pit disposal of
the tailings under short-term and long-term conditions.
To assist with the analysis, MRM has provided the ultimate pit design, inclusive of the In-Pit Dump (IPD),
which is a volume of waste rock that MRM intend to place into the pit during the last 5 to 6 years of mine
operation – i.e. before the tailings deposition commences.
In addition to the IPD, MRM has also advised that they intend to co-dispose 7.5MT of PAF waste rock
into the pit during the second year of tailings deposition. Waiting until Year 2 – by which point the pit will
be partially filled with tailings – will help to reduce the haulage distance for the PAF waste rock.
The rate of rise is anticipated to be very high during initial years (e.g. estimated 96 to 98 metre rise in
Year 1) and gradually decreases to 5 to 10 m per year during final years.
2 Objectives
The objectives of the consolidation analyses are to
to estimate how tailings deposited into the MRM open pit would consolidate under self-weight
during and after deposition
to estimate consolidation water and rate of release into the pond in the pit
to estimate consolidation time after completion of deposition at closure
to estimate the dry density of deposited tailings and the storage volumes of tailings during and
after deposition under long-term conditions
2
32/17476/05/65221
3 Scope of Work
Desktop study only, using available information on tailings properties and GHD’s experience in
tailings consolidation properties from similar tailings.
Review KCB groundwater model with regards to the forecast groundwater recharge with time
following the cessation of mining activities.
Review available geotechnical information on the tailings to establish model parameters.
Model the consolidation of the tailings under self-weight during the deposition cycles and water
losses through drainage boundaries using a one dimensional self-weight consolidation program.
Model consolidation to determine volume of water released to the pit.
Estimate water loss due to evaporation.
Estimate the dry density profile of the tailings and the storage capacity of the pit void, including the
elevation of the tailings surface is to reach during deposition cycles.
Make recommendations on next steps to enabling more detailed estimates to be made, including
further testing of tailings.
4 Large Deformation Modelling of Tailings Consolidation under Self-Weight
4.1 Tailings Consolidation and Drying
After deposition discharge, tailings slurry with low solids content will bleed due to settling of the tailings
particles. Following settling, the tailings will undergo self-weight consolidation and consolidation water
will be expelled out of the tailings matrix due to the volume change of the tailings during consolidation.
The rate of water coming to the surface from self-weight consolidation is generally greater than
evaporation rates due to high moisture content. After initial consolidation, evaporation starts to have an
effect on the void ratio when the initial large volume change due to consolidation is diminishing.
4.2 Initial consolidation of tailings – large deformation modelling
During self-weight consolidation, tailings will undergo large deformations because the initial effective
stress is low and the void ratio is high in the early stage of development of the tailings matrix. During
tailings deposition, the drainage path increases as the thickness of the deposit gradually increases.
Therefore, for self-weight consolidation problems, the conventional Terzaghi consolidation theory
becomes invalid due to the inherent assumption of infinitesimal strains and fixed drainage paths. Gibson
et al. (1967) developed a finite strain consolidation theory for self-weight consolidation and established
the governing differential equation. Li et al. (2012) developed an approach to model self-weight
consolidation using analytical solutions solved for Gibson consolidation theory. It was proposed to use
the following power function to capture high nonlinearity due to initial large volume change at high void
ratio for tailings:
3
32/17476/05/65221
e = AB
where:
e = void ratio.
' = effective stress.
A, B = material constants
The material constants A and B can be obtained from fitting the void ratio - logarithm effective stress
curve using the above equation.
The modelling approach proposed by Li et al. (2012) was developed specifically for tailings consolidation
during deposition at rate of rise and consolidation after deposition. This approach was adopted to model
the consolidation behaviour of the MRM tailings during in-pit deposition.
5 Assumptions
For the base case considered, the following key assumptions were made in the analyses.
The permeability of the rock at the bottom of the pit and around the pit wall is relatively low in
comparison to the permeability of the tailings. Therefore, it is reasonably assumed that a one-
way drainage to the top will prevail and tailings will consolidate under a one-dimensional
condition.
Tailings and the waste rock will be not comingled.
The volume change of waste rock is negligible.
The additional approximately 100m depth of water on top of the subaqueous tailings would have
negligible effect on the consolidation of the tailings during post deposition periods, because the
tailings are assumed to be essentially saturated throughout the deposit at the end of the
deposition in the final year. The 100 m of water would increase the total stress but will not
change the effective stress in between tailings particles.
The potential evaporation rate was assumed to be the same as that used in the O’Kane report
(2016). The pan factor due to potential reduced sunlight and wind was not assessed in this
study; these could be considered in more detailed future studies.
6 Model Parameters
Two column settling tests were conducted on slurry samples with initial solids content of 55.0% by weight
(ATC Williams, 2014) and the settled dry density was estimated to be 1.17 t/m3 and 1.24 t/m3
respectively. The specific gravity of the tailings is approximately 3.2. The consolidation tests have been
carried out by GHD (2016) and University of Queensland (2016) on tailings samples recovered from the
TSF. Figure 1 summarises the results of the previous consolidation tests. Sample 2 was taken from the
tailings beach with coarser tailings and Sample 5 was taken near the decant pond with finer tailings.
Sample 1 represents an average sample with respect to particle size distribution. Using Eq. 1 to match
4
32/17476/05/65221
the results of the settling test and consolidation tests, the power function constants A and B were
estimated to be 1.5 and -1.2, respectively.
A coefficient of consolidation of 2.0 m/month was selected based on the average value of the coefficients
of consolidation measured in the laboratories as shown in Figure 2.
Figure 1 Results of Consolidation Tests and Selected Consolidation Curve for in-pit Tailings
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
0.1 1 10 100 1000 10000
Vo
id R
atio
Consolidation Pressure (kPa)
Sample (2015) at depth 6.65m Sample 1 Sample 2
Sample 5 Settling tests Selected in-pit tailings
UQ Density 1.7t/m3 UQ Density 1.9t/m3
5
32/17476/05/65221
Figure 2 Coefficient of Consolidation
0
1
2
3
4
5
6
7
8
9
10
0 100 200 300 400 500 600 700 800
Co
nso
lidat
ion
Co
effi
cien
t (m
2/m
on
th)
Consolidation Pressure (kPa))
Sample (2015) at depth 6.65m UQ Density 1.7t/m3 UQ Density 1.9t/m3 Average
6
32/17476/05/65221
7 Modelling Results
7.1 Consolidation During Deposition
The initial consolidation analyses were carried out to predict the elevation of the tailings surface at the
end of each year based on the production of the tailings for in-pit disposal. The tailings surface level was
determined through iterative analyses based on the average dry density of the tailings deposit and the
estimated volume of the tailings at each modelling period. Table 1 summarises the results of the
predicted tailings surface levels and the average dry density for each year.
Table 1 Predicted Dry Density Widths of sections to calculate seepage
Year Stored Dry Mass (tonne)
Dry Density
d (t/m3)
Height from Base* (m)
Elevation MGA94* (m)
Rate of Rise* (m/yr)
Year 1 10,500,000 1.387 96.0 -289.0 96.0
Year 2 21,000,000 1.399 136.0 -248.0 41.0
Year 3 31,500,000 1.415 154.0 -230.0 18.0
Year 4 42,000,000 1.427 169.0 -214.0 16.0
Year 5 52,500,000 1.420 183.0 -200.0 14.0
Year 6 63,000,000 1.445 194.0 -188.0 12.0
Year 7 73,500,000 1.452 204.0 -177.0 11.0
Year 8 84,000,000 1.459 214.0 -167.0 10.0
Year 9 94,500,000 1.464 223.0 -157.0 10.0
Year 10 105,000,000 1.473 227.0 -152.0 5.0
*Note: The levels and heights shown here are based on the pit storage spreadsheet provided by MRM
on 16 Sep 2016 and were the basis of the consolidation modelling. In the attached drawings SK001 to
SK005, GHD has also calculated tailings fill volumes and levels based upon the pit CAD model provided
by MRM on 06 Sep 2016. There are some minor differences between the year-to-year levels shown in
the table above and the attached drawings (on average less than 0.5m per year), which are considered
to be negligible for the current study.
Figure 3 shows the predicted density profile at the end of each operating year. Due to one-way drainage
condition and the relatively high rate of rise of the tailing surface, the tailings in the upper part the pit
would not experience significant consolidation during deposition and the dry density would be constant at
the initial dry density after settling. The tailings in the lower part of the pit will consolidate during
7
32/17476/05/65221
deposition and the density increases with depth. The degree of consolidation with respect to settlement
ranges from 9.9% at the end of the first year to 33.0% at the end of the last year.
Figure 3 Dry Density Profiles of the Tailings During Deposition
-390.0
-380.0
-370.0
-360.0
-350.0
-340.0
-330.0
-320.0
-310.0
-300.0
-290.0
-280.0
-270.0
-260.0
-250.0
-240.0
-230.0
-220.0
-210.0
-200.0
-190.0
-180.0
-170.0
-160.0
-150.0
0.0 0.5 1.0 1.5 2.0
De
pth
MG
A9
4
(m)
dry density (t/m3)
Year 1
Year 2
Year 3
Year 4
Year 6
Year 5
Yaer 7
Year 8
Year 9
Year 10
8
32/17476/05/65221
7.2 Consolidation Water
Table 2 shows the accumulative consolidation water released to the surface, estimated flow rate and
average flux during the 10 years of the operating period. Figure 4 shows the estimated accumulative
consolidation water, increasing from approximately 0.93 Mm3 in Year 1 to 13,07 Mm3 in Year 10. The
estimated annual average flux from the underlying tailings to the tailings surface ranges from 12.4
mm/day/m2 in Year 1 to 3.7 mm/day/m2 in Year 10.
The average annual potential evaporation rate is approximately 1990 mm/year corresponding to 5.5
mm/day (O’Kane Consultants, 2016). Based on the estimated release rate of consolidation water to the
pit, the tailings are anticipated to be essentially saturated from Year 1 to Year 9 under average weather
conditions. In other words, the rate of tailings water loss due to the evaporation would be at a rate of 5.5
mm/day/m2 under the average weather conditions. The results of the consolidation analysis suggest that
the subaerial deposition would not provide significant advantages with respect to water losses and
volume change of the tailings under the average weather conditions.
Table 2 Estimated Consolidation Water, Flow Rate and Average Flux during Deposition
Tailings Accumulative Consolidation Water
Average Flow Rate
Surface Area
Average Flux
(tonne) (m3) m3/year
m2 mm/day/m2
Year 1 10,500,000 933,578 933,578 205,966 12.4
Year 2 21,000,000 1,994,680 1,061,102 373,075 7.8
Year 3 31,500,000 3,244,492 1,249,813 446,472 7.7
Year 4 42,000,000 4,575,578 1,331,086 509,506 7.2
Year 5 52,500,000 5,538,522 962,945 573,851 4.6
Year 6 63,000,000 7,415,108 1,876,585 640,036 8.0
Year 7 73,500,000 8,894,673 1,479,565 676,049 6.0
Year 8 84,000,000 10,442,897 1,548,223 736,427 5.8
Year 9 94,500,000 11,987,700 1,544,804 768,886 5.5
Year 10 100,000,000 13,066,624 1,078,924 805,614 3.7
9
32/17476/05/65221
Figure 4 Estimated Consolidation Water to be Released to the Pond
7.3 Consolidation after Deposition
After deposition, the tailings will continue to consolidate under self-weight and water in the tailings matrix
will be expelled and release to the tailings surface due to volume change and decrease in void ratio.
Consolidation settlement will also develop and result in a lowering tailings surface with time until
consolidation is completed. The degree of the consolidation is estimated based on the settlement.
Figure 5 shows the estimated maximum settlement at the centre of the pit (i.e. the deepest location)
versus time. It is estimated that the tailings will reach 35.0%, 43.0%, 90.0% and 98% consolidation after
1 year, 10 years, 100 years and 300 years respectively, during the post deposition periods. The
maximum consolidation settlement would be 54.0 m at the centre of the pit. However, the average
settlement could be less than 27.0 m due to the three dimensional effect. Figure 8 shows the dry density
profiles at Year 20, Year 100, Year 300 and at the end of consolidation. The final average dry density is
estimated to be 1.93 t/m3.
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
0 2 4 6 8 10 12
Co
nso
lidat
ion
Wat
er
(m3
)
Time (year)
DuringDeposition
10
32/17476/05/65221
Figure 5 Settlement vs. Time After Deposition
The estimated accumulative consolidation water after the deposition is shown in Figure 6. The volume of
the consolidation water is estimated to decrease from 220,900 m3 in the initial year (Year 11) to less than
4,000 m3 in Year 300. The estimated daily flow rate is shown in Figure 7.
Figure 6 Consolidation Water to Be Released to the Pond During Post Deposition Periods
0
10
20
30
40
50
60
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300
Sett
lem
en
t (m
)
Time (year)
Settlement
-
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
18,000,000
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300
Co
nso
lidat
ion
Wat
er
(m3)
Time (year)
Post Deposition
11
32/17476/05/65221
Figure 7 Flow Rate of Consolidation Water During Post Deposition Periods
0
500
1000
1500
2000
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300
Flo
w r
ate
(m
3/d
ay)
Time after Deposition (year)
Flow rate (m3/day)
12
32/17476/05/65221
Figure 8 Estimated Dry Density Profiles During Post Deposition Periods
-390.0
-380.0
-370.0
-360.0
-350.0
-340.0
-330.0
-320.0
-310.0
-300.0
-290.0
-280.0
-270.0
-260.0
-250.0
-240.0
-230.0
-220.0
-210.0
-200.0
-190.0
-180.0
-170.0
-160.0
-150.0
0.0 0.5 1.0 1.5 2.0 2.5 3.0
De
pth
(m
)
Dry density (t/m3)
Year 20 Year 100 Year 300 Final
13
32/17476/05/65221
8 Water Balance Estimates
In addition to the estimates of consolidation water volumes provided above in Section 7, we have also
estimated the overall volume of free water that could be generated by the tailings in-pit deposition
operation, and the volume of make-up water that could be required each year at the TSF to continue
slurrying of the tailings with water monitors as described in the draft Retreat Concept report (MRM,
2016).
The water balance estimates take into consideration the following elements:
Tailings density and moisture content characteristics as summarised in Table 3 below.
Bleed water recovered from the initial settlement of the tailings once deposited into the pit (i.e. the
differential water content between Stages 2 and 3 in Table 3 below).
Free water generated from consolidation of the tailings (i.e. consolidation water, as calculated in
Section 7 above).
Annual average evaporation from the surface area of the tailings (2,735 mm per annum).
Annual average rainfall over the plan area of the pit (805 mm per annum over an area of 2.55Mm2).
A run-off coefficient of 1 has been selected for rainfall, and a sensitivity analysis was conducted by
considering a range of annual rainfalls from the 10th percentile (i.e. dry) year to the 90th percentile
(i.e. wet year).
As advised by KCB (refer email dated 20th Sep 2016, titled “MRM In-Pit Tailings Consolidation Works -
notes from kick off meeting - groundwater inputs”), groundwater and potential inflows from McArthur
River, were not considered in this water balance estimate, on the basis that:
There will be no river flow entering the pit during tailings/waste rock placement.
Groundwater will continue to be managed through the dewatering system and will not enter the pit.
Table 3 Tailings Density at Various Stages During the In-Pit Deposition Operations
Property Stage 1
Tailings in TSF
Stage 2 Tailings Slurry Piped from TSF
to Pit
Stage 3 Tailings in Pit
Following Initial Settlement
Stage 4 Tailings in Pit After 10 Years
% solids by weight 82% 45% 66.1% 72.2%
% water by weight 18% 55% 33.9% 27.8%
% solids by volume 59% 21% 38.1% 45.2%
% voids by volume 41% 79% 61.9% 54.8%
Dry density [t/m3] 1.85 0.65 1.21 1.43
14
32/17476/05/65221
Property Stage 1
Tailings in TSF
Stage 2 Tailings Slurry Piped from TSF
to Pit
Stage 3 Tailings in Pit
Following Initial Settlement
Stage 4 Tailings in Pit After 10 Years
Wet density [t/m3] 2.26 1.44 1.82 1.98
Specific gravity 3.16 3.16 3.16 3.16
Reference 2016 lab data
on tailings samples
MRM (2016) Retreat Concept
ATC Williams (2014) Outcomes of the study contained
herein.
Table 4 provides a summary of the water balance calculations undertaken and indicates that make up
water in the range of 0.62 to 2.11 Mm3 would be required at the TSF in order to slurry the tailings for the
case of average annual rainfall in each year.
Table 4 Summary of Water Balance Calculations
Year
Water required at
TSF to slurry
tailings [m3]
At the Pit
Make Up Water
Required at TSF (Mm3)
Bleed water from initial settlement
[m3]
Consolidation water [m3]
Evaporation from tailings beach area
[m3]
Average rainfall
inflow from pit
catchment
1 10,478,170 7,440,153 933,578 -563,317 2,049,216 0.62
2 10,478,170 7,440,153 1,061,102 -1,020,360 2,049,216 0.95
3 10,478,170 7,440,153 1,249,813 -1,221,101 2,049,216 0.96
4 10,478,170 7,440,153 1,331,086 -1,393,499 2,049,216 1.05
5 10,478,170 7,440,153 962,945 -1,569,482 2,049,216 1.60
6 10,478,170 7,440,153 1,876,585 -1,750,498 2,049,216 0.86
7 10,478,170 7,440,153 1,479,565 -1,848,994 2,049,216 1.36
8 10,478,170 7,440,153 1,548,223 -2,014,128 2,049,216 1.45
9 10,478,170 7,440,153 1,544,804 -2,102,903 2,049,216 1.55
10 10,478,170 7,440,153 1,078,924 -2,203,354 2,049,216 2.11
15
32/17476/05/65221
In the case of 10th percentile rainfall occurring each year, an additional 0.9Mm3 of make-up water would
be required each year.
In the case of 90th percentile rainfall occurring each year we estimate that 0.98Mm3 less make-up water
would be required each year, such that there would be a surplus of water in Years 1, 2, 3 and 6.
9 Tailings Deposition Concept
The attached drawings SK001 to SK005 provide an indication of the filling of the pit over the 10 years.
Key aspects of the deposition concept include:
Tailings discharge pipe installed along the Western Ramp, and then down the western pit wall which
has a gradient of approximately 20°. Access to the discharge point would be required so that it could
be regularly adjusted – to allow for the increasing tailings beach elevation – and realigned
northwards / southwards to maximise the efficiency of the tailings deposition into the pit.
Tailings beach of a similar gradient (1V:150H) to that at the TSF has been estimated for this study.
A decant pond at the eastern side of the pit, to enable access to the pond via the main ramp for
installation and maintenance of pump(s) and associated infrastructure.
Construction of the 7.5 MT PAF waste rock cell in Year 2, based on its height being the same as the
depth of tailings deposited in Year 2. We have attempted to maximise the founding of the PAF
waste rockfill on rock (i.e. the IPD and the pit), however the drawings indicate that a portion of the
rockfill would be founded on tailings. The feasibility of this will require further analysis and
consideration because the tailings may not have sufficient strength to support such a rapid
development of the waste rockfill without careful design, planning and implementation.
10 Recommendations
It should be noted that consolidation of the tailings under self-weight will depend on the consolidation
characteristics of the tailings under different stress conditions encompassing a stress range from very
low effective stress after settling to very high effect stress at the bottom of the pit. The following
recommendations are provided for the further study of the project.
Column settling tests should be carried out at the target solids content.
Slurry consolidation tests should be carried out on the representative tailings samples to characterise
the consolidation properties of the tailings at different initial solids content.
It is recommended to carry out the slurry consolidation tests in connections of permeability tests at
different stress levels.
More detailed analyses should be undertaken with consolidation of three dimensional effect of the pit
geometries and the effect of the waste rock on the consolidation of the tailings.
The evaporative drying modelling of the tailings and drying tests should be carried out only to
investigate the effects of volume change during desiccation if a subaerial deposition is to be adopted
and the tailings are anticipated to be desiccated during dry seasons.
16
32/17476/05/65221
Options for co-disposal of the 7.5MT PAF rockfill with the tailings in Year 2 should be further
considered. From a geotechnical perspective, it would be preferable to found the rockfill on rock. In
this regard, the possibility of spreading the rockfill disposal over a longer time period so that it could
have a greater height, and lesser footprint area could be considered. If the rockfill is to be founded
on tailings, further analysis and modelling should be undertaken to determine a suitable way for
undertaking this safely, in order to maintain stability of the placed rockfill and so as to maintain the
decant water quality.
11 References
GHD, 2016. MRM TSF – Stability Analysis for Life of Mine Preliminary Design, 8 March 2016.
Li, A.L., Been, K., Wislesky, I, Eldridge, T. and Williams, D. (2012). Tailings initial consolidation and
evaporative drying after deposition. The International Seminar on Paste and Thickened Tailings, Paste
2012, 16–19 April, 2012, Sun City, South Africa, pp.25-42.
ATC Williams, 2014 –McArthur River Mine Tailings Storage Facility Projected 5-Year Management Plan,
August 2014, document 111351.16.R01-b
MRM, 2016. MRM Tailings Retreatment Project Concept Study, 04 April 2016 Version 1 (Draft)
O’Kane Consultants, 2016, McArthur River Mine – Initial Consolidation Modelling for In-Pit Tailings; Fatal
Flaw Analysis for Pit Water Quality. 29 May 2016.
Kind Regards
GHD Pty Ltd
Allen LI & Matthew Daley
10025
10025
10025 10025
10025
10025 10025 10025
10025
10025
10075
10075
10075
1007
5
10075
10050
10050
10050
10050 1005
0
10050
1005
0
10050
10050
10050
10050
10050
10050
1005
0
1005
0
10050
10050
10050
10050
1005
0
10050
10050
10050
10050
10050
1005
0
10050
1005
0
10050
10050
10050
10050 10050 10050
10050
10050
10025
10025
10025
10025
10025
10025 10025
10025
10025
10025
1002
5
10025 1002
5
1002
5
10025
1002
5
10025
10025
1002
5
1002
5 10025
10025
10025
1002
5 10025
10025
1002
5 10
025
10025 10025 10025
10025 10025
10025
10025
10025
10025
10025 10025
1002
5 10025
10025 10025 10025 10025
1002
5 10
025
1002
5 10
025
10025
10025
10025
10025
10025
10025
10025
10025
1002
5
1002
5
1002
5
1002
5
1002
5
1002
5
10025
10025 10025
10025
10000 10000
10000
1000
0 10
000
10000
10000 10000
10000
10000 10000
1000
0
10000
10000
10000 10000
1000
0 10000
10000
10000 10000
10000
1000
0
10000
1000
0 10
000
10000 10000
10000
10000
10000
1000
0
10000
1000
0
1000
0
10000
10000 10000
10000 1000
0
10000
10000
10000 10
000
10000
10000
1000
0 10000
1000
0
10000
1000
0 1000
0
10000 10000 10000
10000
10000
9975 9975
9975
9975
9975
9975
9975 99
75
9975 9975
9975
9975
9975
9975
9975
9975
9975
9975 9975
9950
9950
9950 9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950 99
50
9950
9925
9925
9925
9925
9925
9925
9925
9925 99
25 99
25
9925
9925 9925
9925
9925
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9875 98
75 98
75 9875
ASK005
ASK005
9712
.5
9711
.5
9713
.5
date
for A3
rev no.
job no.scale
approved (PD)
Conditions of Use: This document may only be used by GHD's client (and any other
person who GHD has agreed can use this document) for the purpose for which it was
prepared and must not be used by any other person or for any other purpose.
rev description app'd date
SK
2 Salamanca Square Hobart TAS 7000 Australia
GPO Box 667 Hobart TAS 7001
T 61 3 6210 0600 F 61 3 6210 0601
E [email protected] W www.ghd.com
GHD STANDARD A3 SHEET CAD File No.: GHD_G_1022 Updated: 08-07-03 Version: 1.1
Plot Date: Cad File No:5 October 2016 - 1:15 PM G:\32\1747605\CADD\Drawings\32-1747605-SK001.dwgPlotted by: Stephanie Magaling
McARTHUR RIVER MINING
TAILINGS IN-PIT CONSOLIDATION
YEAR 1 TAILINGS BEACH
PLAN
001
A
32-1747605
PRELIMINARY
1:10000
OCT 2016
A INITIAL ISSUE
0 300m100 200
SCALE 1:10,000 AT ORIGINAL SIZE
N
MAIN RAMP
TAILINGS BEACH
DECANT POND
OREBODYFOOTWALL
POSSIBLE TAILINGSDISCHARGE PIPE ROUTE
WESTERN RAMP
IN PIT DUMP
IPD
10025
10025
10025 10025
10025
10025 10025 10025
10025
10025
10075
10075
10075
1007
5
10075
10050
10050
10050
10050 1005
0
10050
1005
0
10050
10050
10050
10050
10050
10050
1005
0
1005
0
10050
10050
10050
10050
1005
0
10050
10050
10050
10050
10050
1005
0
10050
1005
0
10050
10050
10050
10050 10050 10050
10050
10050
10025
10025
10025
10025
10025
10025 10025
10025
10025
10025
1002
5
10025 1002
5
1002
5
10025
1002
5
10025
10025
1002
5
1002
5 10025
10025
10025
1002
5 10025
10025
1002
5 10
025
10025 10025 10025
10025 10025
10025
10025
10025
10025
10025 10025
1002
5 10025
10025 10025 10025 10025
1002
5 10
025
1002
5 10
025
10025
10025
10025
10025
10025
10025
10025
10025
1002
5
1002
5
1002
5
1002
5
1002
5
1002
5
10025
10025 10025
10025
10000 10000
10000
1000
0 10
000
10000
10000 10000
10000
10000 10000
1000
0
10000
10000
10000 10000
1000
0 10000
10000
10000 10000
10000
1000
0
10000
1000
0 10
000
10000 10000
10000
10000
10000
1000
0
10000
1000
0
1000
0
10000
10000 10000
10000 1000
0
10000
10000
10000 10
000
10000
10000
1000
0 10000
1000
0
10000
1000
0 1000
0
10000 10000 10000
10000
10000
9975 9975
9975
9975
9975
9975
9975 99
75
9975 9975
9975
9975
9975
9975
9975
9975
9975
9975 9975
9950
9950
9950 9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950 99
50
9950
9925
9925
9925
9925
9925
9925
9925
9925 99
25 99
25
9925
9925 9925
9925
9925
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9875 98
75 98
75 9875
ASK005
ASK005
9750
.6
9753
.6
9751
.6
9752
.6
date
for A3
rev no.
job no.scale
approved (PD)
Conditions of Use: This document may only be used by GHD's client (and any other
person who GHD has agreed can use this document) for the purpose for which it was
prepared and must not be used by any other person or for any other purpose.
rev description app'd date
SK
2 Salamanca Square Hobart TAS 7000 Australia
GPO Box 667 Hobart TAS 7001
T 61 3 6210 0600 F 61 3 6210 0601
E [email protected] W www.ghd.com
GHD STANDARD A3 SHEET CAD File No.: GHD_G_1022 Updated: 08-07-03 Version: 1.1
Plot Date: Cad File No:5 October 2016 - 1:15 PM G:\32\1747605\CADD\Drawings\32-1747605-SK002.dwgPlotted by: Stephanie Magaling
McARTHUR RIVER MINING
TAILINGS IN-PIT CONSOLIDATION
YEAR 2 TAILINGS BEACH
PLAN
002
A
32-1747605
PRELIMINARY
1:10000
OCT 2016
A INITIAL ISSUE
0 300m100 200
SCALE 1:10,000 AT ORIGINAL SIZE
N
MAIN RAMP
TAILINGS BEACH
DECANT POND
OREBODYFOOTWALL
POSSIBLE TAILINGSDISCHARGE PIPE ROUTE
WESTERN RAMP
IN PIT DUMP
IPD
LEGEND:
PAF CELL ABOVE YR1 DRY TAILINGS BEACH
PAF CELL
10025
10025
10025 10025
10025
10025 10025 10025
10025
10025
10075
10075
10075
1007
5
10075
10050
10050
10050
10050 1005
0
10050
1005
0
10050
10050
10050
10050
10050
10050
1005
0
1005
0
10050
10050
10050
10050
1005
0
10050
10050
10050
10050
10050
1005
0
10050
1005
0
10050
10050
10050
10050 10050 10050
10050
10050
10025
10025
10025
10025
10025
10025 10025
10025
10025
10025
1002
5
10025 1002
5
1002
5
10025
1002
5
10025
10025
1002
5
1002
5 10025
10025
10025
1002
5 10025
10025
1002
5 10
025
10025 10025 10025
10025 10025
10025
10025
10025
10025
10025 10025
1002
5 10025
10025 10025 10025 10025
1002
5 10
025
1002
5 10
025
10025
10025
10025
10025
10025
10025
10025
10025
1002
5
1002
5
1002
5
1002
5
1002
5
1002
5
10025
10025 10025
10025
10000 10000
10000
1000
0 10
000
10000
10000 10000
10000
10000 10000
1000
0
10000
10000
10000 10000
1000
0 10000
10000
10000 10000
10000
1000
0
10000
1000
0 10
000
10000 10000
10000
10000
10000
1000
0
10000
1000
0
1000
0
10000
10000 10000
10000 1000
0
10000
10000
10000 10
000
10000
10000
1000
0 10000
1000
0
10000
1000
0 1000
0
10000 10000 10000
10000
10000
9975 9975
9975
9975
9975
9975
9975 99
75
9975 9975
9975
9975
9975
9975
9975
9975
9975
9975 9975
9950
9950
9950 9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950 99
50
9950
9925
9925
9925
9925
9925
9925
9925
9925 99
25 99
25
9925
9925 9925
9925
9925
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9875 98
75 98
75 9875
ASK005
ASK005
9798
.39799
.3
9797
.3
9796
.3
9800
.3
date
for A3
rev no.
job no.scale
approved (PD)
Conditions of Use: This document may only be used by GHD's client (and any other
person who GHD has agreed can use this document) for the purpose for which it was
prepared and must not be used by any other person or for any other purpose.
rev description app'd date
SK
2 Salamanca Square Hobart TAS 7000 Australia
GPO Box 667 Hobart TAS 7001
T 61 3 6210 0600 F 61 3 6210 0601
E [email protected] W www.ghd.com
GHD STANDARD A3 SHEET CAD File No.: GHD_G_1022 Updated: 08-07-03 Version: 1.1
Plot Date: Cad File No:5 October 2016 - 1:14 PM G:\32\1747605\CADD\Drawings\32-1747605-SK003.dwgPlotted by: Stephanie Magaling
McARTHUR RIVER MINING
TAILINGS IN-PIT CONSOLIDATION
YEAR 5 TAILINGS BEACH
PLAN
003
A
32-1747605
PRELIMINARY
1:10000
OCT 2016
A INITIAL ISSUE
0 300m100 200
SCALE 1:10,000 AT ORIGINAL SIZE
N
MAIN RAMP
OREBODYFOOTWALL
TAILINGS BEACH
POSSIBLE TAILINGSDISCHARGE PIPE ROUTE
WESTERN RAMP
IN PIT DUMP
IPD
DECANT POND
10025
10025
10025 10025
10025
10025 10025 10025
10025
10025
10075
10075
10075
1007
5
10075
10050
10050
10050
10050 1005
0
10050
1005
0
10050
10050
10050
10050
10050
10050
1005
0
1005
0
10050
10050
10050
10050
1005
0
10050
10050
10050
10050
10050
1005
0
10050
1005
0
10050
10050
10050
10050 10050 10050
10050
10050
10025
10025
10025
10025
10025
10025 10025
10025
10025
10025
1002
5
10025 1002
5
1002
5
10025
1002
5
10025
10025
1002
5
1002
5 10025
10025
10025
1002
5 10025
10025
1002
5 10
025
10025 10025 10025
10025 10025
10025
10025
10025
10025
10025 10025
1002
5 10025
10025 10025 10025 10025
1002
5 10
025
1002
5 10
025
10025
10025
10025
10025
10025
10025
10025
10025
1002
5
1002
5
1002
5
1002
5
1002
5
1002
5
10025
10025 10025
10025
10000 10000
10000
1000
0 10
000
10000
10000 10000
10000
10000 10000
1000
0
10000
10000
10000 10000
1000
0 10000
10000
10000 10000
10000
1000
0
10000
1000
0 10
000
10000 10000
10000
10000
10000
1000
0
10000
1000
0
1000
0
10000
10000 10000
10000 1000
0
10000
10000
10000 10
000
10000
10000
1000
0 10000
1000
0
10000
1000
0 1000
0
10000 10000 10000
10000
10000
9975 9975
9975
9975
9975
9975
9975 99
75
9975 9975
9975
9975
9975
9975
9975
9975
9975
9975 9975
9950
9950
9950 9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950
9950 99
50
9950
9925
9925
9925
9925
9925
9925
9925
9925 99
25 99
25
9925
9925 9925
9925
9925
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9900
9875 98
75 98
75 9875
ASK005
ASK005
9847
.5
9848
.5
9849
.5
9846
.5
9845
.5
9844
.59850
.5
date
for A3
rev no.
job no.scale
approved (PD)
Conditions of Use: This document may only be used by GHD's client (and any other
person who GHD has agreed can use this document) for the purpose for which it was
prepared and must not be used by any other person or for any other purpose.
rev description app'd date
SK
2 Salamanca Square Hobart TAS 7000 Australia
GPO Box 667 Hobart TAS 7001
T 61 3 6210 0600 F 61 3 6210 0601
E [email protected] W www.ghd.com
GHD STANDARD A3 SHEET CAD File No.: GHD_G_1022 Updated: 08-07-03 Version: 1.1
Plot Date: Cad File No:5 October 2016 - 1:17 PM G:\32\1747605\CADD\Drawings\32-1747605-SK004.dwgPlotted by: Stephanie Magaling
McARTHUR RIVER MINING
TAILINGS IN-PIT CONSOLIDATION
YEAR 10 TAILINGS BEACH
PLAN
004
A
32-1747605
PRELIMINARY
1:10000
OCT 2016
A INITIAL ISSUE
0 300m100 200
SCALE 1:10,000 AT ORIGINAL SIZE
N
MAIN RAMP
TAILINGS BEACH
DECANT POND
OREBODYFOOTWALL
POSSIBLE TAILINGSDISCHARGE PIPE ROUTE
WESTERN RAMP
IN PIT DUMP
IPD
PAF ROCK
IPD SURFACE
PIT SURFACE
FALL 1:150 APPROXIMATE
FALL 1:150 APPROXIMATE
DECANTPOND
RL 9888
YR2 TAILINGS BEACH - RL 9754.5
YR3 TAILINGS BEACH - RL 9772.5
YR4 TAILINGS BEACH - RL 9787.5
YR5 TAILINGS BEACH - RL 9802.0
YR6 TAILINGS BEACH - RL 9813.0YR7 TAILINGS BEACH - RL 9824.0
YR8 TAILINGS BEACH - RL 9834.0YR9 TAILINGS BEACH - RL 9843.0
YR10 TAILINGS BEACH - RL 9851.5
YR1 TAILINGS BEACH - RL 9714.0
RL 9616
TAILINGS DISCHARGE PIPE
date
for A3
rev no.
job no.scale
approved (PD)
Conditions of Use: This document may only be used by GHD's client (and any other
person who GHD has agreed can use this document) for the purpose for which it was
prepared and must not be used by any other person or for any other purpose.
rev description app'd date
SK
2 Salamanca Square Hobart TAS 7000 Australia
GPO Box 667 Hobart TAS 7001
T 61 3 6210 0600 F 61 3 6210 0601
E [email protected] W www.ghd.com
GHD STANDARD A3 SHEET CAD File No.: GHD_G_1022 Updated: 08-07-03 Version: 1.1
Plot Date: Cad File No:5 October 2016 - 1:16 PM G:\32\1747605\CADD\Drawings\32-1747605-SK005.dwgPlotted by: Stephanie Magaling
McARTHUR RIVER MINING
TAILINGS IN-PIT CONSOLIDATION
CROSS SECTION
005
A
32-1747605
PRELIMINARY
1:2500
OCT 2016
A INITIAL ISSUE
0 75m25 50
SCALE 1:2500 AT ORIGINAL SIZE
SECTIONASK001-SK004 SCALE 1:2500
NOTE:1. SECTION IS FOCUSED ON LOWER PORTION OF PIT AND
DOES NOT SHOW FULL EXTENT.