Outline of Presentation
I. Site Development Plan II. Updates per Component a. Off-Site b. Resettlement Site Development c. Farm Lot Development d. Beneficiaries Selection III. Budgetary Requirements IV. Facilitating and Hindering Factors V. Ways Forward
Outline of Presentation
A. Offsite development
Access road construction
including 3 spillways (14.2 KM)
= PHP237M
Start of KALAHI CIDSS
road project
Start of proposed road
improvement project
Road and Spillway KALAHI CIDDS ROAD PROJECT 2.65 KM
Before
Before
After
After
DSWD
Completion of
the 2.65-km
Road Project of
KALAHI CIDDS.
Housing Model and Cost Proposed unit of 30 sqm. Duplex Tagkawayan, Quezon
Developed lot = PHP 150, 000
Housing Units = PHP 240, 000
Cost Per Unit = PHP 390, 000
Cost for 200 Units = PHP 78, 000, 000
C. Farm/Plantation Area
400 sqm. nursery site • 2 - storey bunkhouse
• (approx. 15 sqm. Floor area)
• 6-unit potting shed of various
propagules.
• Species planted: Malunggay,
Bamboo, Rambutan and Coffee
C. Farm/Plantation Area DA
• Developed “Integrated Farming System for
Sustainable Upland Agriculture” : a guided
farm project for Brgy. Maguibuay,
Tagkawayan, Quezon. – Instruments used: Soil Sampling & Soil Test
• Prepared POW, Cost Estimate and
Detailed Engineering Design of the
proposed Diversion Dam. – Instrument used: Site validation & topographic
survey.
D. Beneficiaries
Source of Livelihood: Farming, charcoal making,
laborer, sari-sari store, marketing for copra
Skills for Development : Farming, marketing training
for copra and other coconut by-products.
144 prospected families
9 (7%) from Brgy Maguibuay
135 (93%) from adjacent Barangays
III. Budgetary Requirement COMPONENT ACTIVITIES
BUDGETARY REQUIREMENT (Php '000)
Site Preparation 3,760
Site Validation
Preparation of seedling production area and resettlement area Mapping
3,760
Farm Lot Development 206,407
Provision of agricultural support, infrastructure support and trainings 206,407
* with funding 11,780
Beneficiary Selection/ Skills Enhancement
9,200
In coordination with DSWD for identification, site orientation, actual transfer and
other related activities involving the ISF 8,900
Training skills 6,300
Social preparation/continuous provision of livelihood 300
Resettlement Site Development 82,000
Site development and
core housing construction 78,000
Electrification 4,000
Off Site (Infrastructure and Services Development)
258,905
Construction of access roads, land development, and water supply 237,285
Upgrading of school facilities (chairs,textbooks,etc) 20,000
Medical equipment and
other health support facilities 1,620
TOTAL
560,272
IV. Facilitating and Hindering Factors
Facilitating Factors
• LGU Support
• Site accessibility
• Soil suitability to various agricultural crops
• Source of water for irrigation
• Resettlement area adjacent to electricity
source
• Huge area available to be allotted for
farm and plantation area
Hindering Factors
o Distant proximity to Metro Manila
o Per agency budget commitments
o No current interventions in the relocation
site aside from DENR-NGP
o High cost for access road improvement
o Market for the various agricultural products
• Road improvement of 14.2 KM access
road may commence once
Site/Farm/Resettlement area
development is finished (Off-Site)
• Clear agency accountability on site
development e.g. water supply, infra
other than housing units (Resettlement Site
Development)
• Ground validation for consistency in
terms of land classification and
boundary on the proposed farms areas
(Farm Lot Development)
• Complementation of LGU, DSWD, DILG
and related agencies to shortlist the
existing ISF list (Beneficiaries Selection)
TABLE OF CONTENTS
Profile 1
Initial Site Validation Overview 1
Institutional Linkages 1
Initial Activities 2
DENR under NGP 2012 2
BPP Technical Working Group Accomplishment 2
BPP-Oas Planning and Implementation Phase Timeline 2
Detailed Engineering Design: Access Road 4
House Model 5
Site Development Plan 6
Agro- Development Plan 7
Water Resource 8
Results of the Physical and Chemical Analysis of Potable Water
9
Topographic Map Survey in the Model Farm 10
Recommended Land Use Plan 11
Recommended Soil and Water Conservation Technologies and Practices
12
Target Beneficiaries Profile 15
Profile of the Beneficiaries 15
Inventory of the Forest Occupants 15
Number of Households According to Educational levels 15
Source of Family Income 15
Skills Development 15
List of Forest Occupants under DSWD 4Ps Program 16
Summary of Budgetary Requirement per Agency 17
Annex1: Survey Form 18
1
BALIK PROBINSYA PROGRAM (OAS, ALBAY) BRIEFER AND UPDATES PROFILE
Location Total Area (hectares)
Barangays Cagmanaba, Tapel and Nagas, Oas, Albay Legazpi City
2000.00
INITIAL SITE VALIDATION OVERVIEW
The project area covers 2,000.00 hectares forestlands covering three (3) barangays of Oas, Albay: Barangays Nagas, Tapel and Cagmanaba. It is accessible by land travel with more or less 40 kilometers from the town proper of Oas, Albay via Pantao, Libon, Albay. It will take almost 2 and ½ hours of travel from the City of Legazpi to the project site. The resettlement site is 1.6 kilometers away from the National Highway of Cagmanaba. The site covers forestland and mixed-cultivated perennial crops. There are existing facilities around the area such as schools (day care center and elementary school), health center, barangay hall, cemetery and dignity plant (coconut). The project area can accommodate 500 informal settlers families.
NGP also established three (3) nurseries located in the barangays of Nagas, Tapel and Cagmanaba. The program identified land use in the area such as pili (Canariumovatum), cacao (Theobroma cacao) and coffee (Robusta) ; fast growing species Yemane (Gmelina arborea), Acacia (Samanea saman) and Mahogany (Swietenia macrophylla) and fuel wood species like Ipil-ipil (Leucaenaleucocephalla). INSTITUTIONAL LINKAGES
The area is in direct need of basic social services which can be realized through the participation of other government agencies such as:
DPWH- for the construction of road, network and other infrastructure facilities; NHA- land development and construction of housing units for the beneficiaries; DA- provision of support services for the development of the beneficiaries’ farm
lot DSWD – for provision of conditional cash transfer MSWD- (Municipal Social Welfare and Development Office) -social preparation
and other basic social services for the beneficiaries DepEd- construction of school buildings and educational facilities; LGU - for the provision of assistance in accessing basic services/facilities DILG- for the provision of security and fire protection amenities; TESDA- for the provision of trainings and capacity development; NEA - provision of electricity; DOH- provision of health facilities and potable water.
2
INITIAL ACTIVITIES DENR under NGP (2012)
Nursery Establishment in the Barangays of Nagas, Tapel and Cagmanaba On-going planting of the donated seedlings by FCF Minerals, Inc. (100 has
planted) Identification of Forest Occupants Employed 10 Bantay Gubat Hired extension officers Organized one (1) People’s Organization
BPP Technical Working Group Accomplishments (Marc h2013- May 2015)
Survey Form (Identification of Forest Occupants) Inventory of Forest Occupants Water Resource identified Rapid Assessment of water resources Topographic Survey in the resettlement area Detailed Engineering (1.6 kilometers access road going to the resettlement site) Land Acquisition Consultation Topographic survey, land use survey in the model farm (3 ha) and actual farm
area (3 ha) and water resource survey Recommended Land Use House Model (Single Detached) Subdivision Plan Sanitary Survey of Potential Water Sources Topographic Map Survey in the proposed model farm Recommended Land Use plan Recommended Soil and Water Conservation Technologies and Practices Detailed Farm Plan Barangay Hazard Assessment of Phivolcs Geohazard Identification Survey Brgy. Health station and health centers are enhanced
Training on Sustainable Upland Farming Through Soil Conservation Guided Farm Approach.
Distributed gardening tools for the existing forest occupants. BPP Planning and Implementation Phase Timeline
March 1, 2013 A BPP National Inter-Agency Meeting was called to discuss the implementation of
the Balik Probinsya Program. This meeting was attended by some representatives from DSWD, DPWH, NHA,
HUDCC, NEA, DOH, DepEd and was co-chaired by DA, DENR and DILG.
3
The three identified sites namely, Doña Remedios Trinidad, Bulacan, Tagkawayan, Quezon and Oas, Albay were presented. To facilitate the implementation, it was agreed that a site validation be immediately conducted.
March 5-7, 2013 NCI-SRD team conducted a site validation participated by the representatives from-
DA, DENR, DSWD, DILG, NHA, HUDCC, DPWH. The Draft Master Plan was created. March 8, 2013 The 2nd National BPP Inter-agency Meeting at the BSWM Convention Hall and the
results of the Site Validation and draft Master Plan were presented.
March 13 2013 The BPP Regional Technical Working Group was called in the National Office for the
refinement of the master development plan for the three sites. This was held at the BSWM Lecture Room 2.
March 15, 2013 The 3rd BPP National Inter-agency Meeting was held at the PCA Auditorium. The
refined Master Development Plan was presented.
April 25, 2013 The 4th National Inter-Agency Meeting was conducted to present the enhanced BPP
Framework and some updates on the preparatory work on the ground.
May 21-23, 2013 With the issuance of the enhanced BPP Framework, a revalidation of the site and
further refinement of the master plan were conducted.
June 24, 2013 The 5th Inter-agency Meeting was called and the results of the master plan as well as
the recent initiatives on the ground were presented.
July 25-26, 2013
BPP Regional Inter-agency meeting and Site Validation with BPP Technical Working
Group and Atty. Emerson U. Palad, the Alternate Chairman of National Steering
Committee. The master plan, subdivision plan and house model were presented.
August 27, 2013
The BPP Regional Inter-agency Meeting was held at the Department of Public Works
and Highways Conference room. The criterion for BPP Site Prioritization was
presented.
September 25, 2013
The 6th BPP National Inter-agency Meeting was called and the updated master plan
of the three sites was presented to the newly designated Alternate Chairman of NCI
National Steering Committee, Usec. Dante S. De Lima of Field Operations Services.
4
Usec Delima tasked the agencies to give alternative name suggestions for BPP and
asked DSWD to produce a final list of Informal Settlers Families (ISF).
October 17-18, 2013
BPP Regional Inter-agency Meeting was held at the Department of Environment
and Natural Resources Conference Room. Updates from each agency and the
minutes of the recent BPP National Inter-agency Meeting were presented.
Dr. Oscar Parawan, NCI-SRD National Focal Person, graced the meeting in Oas,
Albay for the first time to visit the area in the Site Validation.
Highlights included the request for the involvement of DSWD-LGU regarding lists of
ISF and the finalization of the budget allocation per agency.
November 22, 2013
BPP Regional Inter-agency Meeting at the Department of Agriculture Conference
Room in Pili, Camarines Sur. OAS BPP Team recapped the accomplishments set in
the last meeting for updates.
Each agency was tasked to submit its respective Work and Financial Plan which will
be the bases for the team to take off in 2014.
November 26, 2013
The 7th BPP National Inter-agency Meeting was called to follow up the agreements
achieved in the last national meeting on renaming BPP and DSWD’s ISF list at the
Field Operations Services Conference Room.
NCI-SRD was tasked to organize a BPP Summit in February 2014.
January 17, 2014
BPP Regional Inter-agency Meeting at the Sangguniang Bayan Building, LGU Oas
Albay Office. The Local Executive of Municipality of Oas, Albay joined meeting.
BPP OAS TWG suggested for MGB to conduct a survey and Phivolcs to ascertain the
environmental hazards/safeness of the area. They also suggest for PEO and LGU
Oas to conduct water source mapping survey and design.
March 25, 2014
The barangay hazard assessment issued by Phivolcs , the unofficial geo-hazard
identification survey of MGB, comparative analysis of the Site 1 ( within the
timberland area of Brgy. Oas, Albay) and Site 2 ( within the A and D land along
national road of Bgry. Cagmanaba, Oas Albay) and detailed farm plan were
presented and being discussed.
5
DETAILED ENGINEERING: ACCESS ROAD
HOUSE MODEL
Single detached house with an area of 20 square meters. The estimated house
construction would cost 150,000 Php per beneficiary.
Specification
BUDGETARY ESTIMATES
Road Construction
(18,750,000.00/ km @ 1.6 km)
29,072,000.00
Road Right of Way
TOTAL Php 29, 072,000.00
8
AGRO-DEVELOPMENT PLAN
PARTICULARS AREA (ha) Total Suitable Area 380 Proposed Area for Development 320 Farm Model 3
9
WATER RESOURCE
Proposed Structures Unit Cost Total Cost One (1) unit concrete overflow weir 3,000,000.00 3,000,000.00
Total Cost 3,000,000.00
13
RECOMMENDED SOIL AND WATER CONSERVATION TECHNOLOGIES AND PRACTICES
a. Contouring
b. Buffer strip cropping or Hedgerows
Legumes Hedgerows Pineapple Hedgerows
c. Crop Cover
Forest trees or fruit trees crop cover Vegetable or other crop cover
14
d. Crop Rotation
e. Multi-storey/Multiple cropping
Multi-storey Cropping System Multiple Cropping System
16
TARGET BENEFECIARIES PROFILE Profile of Beneficiaries
Item
Direct Beneficiaries (a) 200 Indirect Beneficiaries (b) 11,043 Service Coverage (Number of Barangays) 5 Investment per household (PhP) 863.10 Investment per household (PhP) 15.35 Inventory of Forest Occupants
Barangay Number of Household
Household Members TOTAL
Male Female Cagmanaba 21 64 60 124
Tapel 13 37 30 67 Nagas 23 65 56 121
TOTAL 61 166 146 312
Number of Household Members According to Educational levels (1-21years old)
Level Cagmanaba Tapel Nagas TOTAL
No Grade (1-5yrs old) 8 1 11 20
Kinder/preparatory 6 2 4 12
Elementary 25 16 28 69
High School 12 10 10 32
TESDA Scholar 1 0 0 1
College level 2 1 0 3
Out of School Youth 16 7 17 40
GRAND TOTAL 70 37 70 177
Source of Family Income Main Source: Farming Alternative Source: Fishing and Laborer Skills for Development Carpentry Tailoring
17
Welding List of Forest Occupants under DSWD 4P’s Program (18)
NAMES LOCATION
Avila, Norminda D. Cagmanaba Cańada, Josephine D. Cagmanaba Eco/Paraiso, Asuncion Cagmanaba Sabaulan, Lilia E. Cagmanaba Sabaulan, Susan V. Cagmanaba Timog, Marlyn O. Cagmanaba TOTAL: 6
NAMES LOCATION Aguilar, Genedina L. Tapel Lasala, Erlinda P. Tapel Manuel, Monica S. Tapel Oribiana, Florina A. Tapel Rio Beverly O. Tapel TOTAL: 5
NAMES LOCATION Bollosa Charlie B. Nagas Dela Torre, Helena S. Nagas Pavia, Emelinda S. Nagas Pedido, Chona D. Nagas Raytana, Marites N. Nagas Villaraza, Vilma R. Nagas Saurani, Theodora Nagas TOTAL: 7
20
Summary of Budgetary Requirement per Agency
AGENCY BUDGETARY REQUIREMENT
COMMITTED BUDGET
2014 2015
Department of Agriculture 25,640,000.00 (2014-2015)
144,000.00 (CY 2014)
Bureau of Soils and Water Management
5,000,000.00
Department of Health 510,000.00 200,000.00 National of Housing Authority
73,720,000.00
Department of Public Works and Highways
31,700,000.00 down to 29,072,000.00
29,072,00.00
Department of Environment and Natural Resources
80, 785,000.00
ALECO 1,800,000.00 Department of Education 10,240,000.00
Technical Education and Skills Development Authority
6,300,000.00
Department of Interior and Local Government
5,000,000.00
Local Government Unit 2,000,000.00 TOTAL 240,067,000.00 344,000.00 29,072,00.00
21
Annex1: SURVEY FORM
HH No.: _________
Republic of the Philippines Department of Environment and Natural Resources
COMMUNITY ENVIRONMENTAL AND NATURAL RESOURCES OFFICE (CENRO) Guinobatan, Albay
“BALIK-PROBINSYA PROJECT”
Inventory of Forest Occupants (IFO) General Information Location: Number of Households: Total Area Occupied: Length of Occupancy: _____ Forest Occupants Data Name of Head of Family: ______________ Number of Children: _______________________________ Number of Children: _______________________________ Number of Household Members: _______ Names: 1. ______ Gender: Age: Annual Income: ____________ Work:_______ Highest Educational Attainment: _______________________ (___) In-school (___) out-of school Skills possessed: _________________ Training program needed:_______________________ 2. ______ Gender: Age: Annual Income: ____________ Work:_______ Highest Educational Attainment: _______________________ (___) In-school (___) out-of school Skills possessed: _________________ Training program needed:_______________________ 3. ______ Gender: Age: Annual Income: ____________ Work:_______ Highest Educational Attainment: _______________________ (___) In-school (___) out-of school Skills possessed: _________________ Training program needed:_______________________ 4. ______ Gender: Age: Annual Income: ____________ Work:_______ Highest Educational Attainment: _______________________ (___) In-school (___) out-of school Skills possessed: __________________ Training program needed:_______________________ 5. ______ Gender: Age: Annual Income: ______ Work:_______ Highest Educational Attainment: _______________________ (___) In-school (___) out-of school Skills possessed: __________________ Training program needed: _______________________
22
6. ______ Gender: Age: Annual Income: ______ Work:_______ Highest Educational Attainment: _______________________ (___) In-school (___) out-of school Skills possessed: __________________ Training program needed: _______________________ 7. ______ Gender: Age: Annual Income: ______ Work:_______ Highest Educational Attainment: _______________________ (___) In-school (___) out-of school Skills possessed: __________________ Training program needed: _______________________ Total Annual Family Income: Total Area Cultivated (ha): Trees Planted: 1. 2. ___________ Agricultural Crops Planted: 1. 2. ________ Source of income: 1. Major Source: ____________________________________ 2. Other Source: ____________________________________ IFO:_________________ Source of drinking water:_______________ Access to Sanitation: __________________ Date Accomplished: Forest Occupant: (Signature over printed name) Extension Officer: (Signature over printed name)
Conforme: Punong Barangay
Date: _
Lists of forest occupants under 4P’s Program Brgy.Tapel Aguilar, Genedina L. Oribiana, Florina Brgy.Cagmanaba Avila, Norminda
Brgy. Nagas Pedido, Chona D. Villaraza, Vilma R. Dela Torre, Helena S. Bollosa,Charlie
Eco, Asuncion
BALIK PROBINSYA PROGRAM (DOÑA REMEDIOS TRINIDAD, BULACAN) BRIEFER AND
UPDATES
I. PROFILE
Location Physical Configuration and land cover Total Area (hectares)
Dona Remedios Trinidad, Bulacan
Flat to rolling terrain. Forest land with mixed cultivated perennial crops.
1005
II. INITIAL SITE VALIDATION The proposed relocation site is situated in Sitios Cucong and Tamsi in Barangay Kalawakan, DRT, Bulacan. 6x6 truck and four wheel drive (4WD) vehicle are needed to access the site due to the old logging road. The terrain is moderately rolling to steep slopes with elevation ranging from 100-150 meters above sea level. The area is generally covered with cogon and bushes. There are also buho and patches of pioneer tree species present in the area. The site is bisected by Malibay River, Cucong, and Bintong creeks and undetermined number of tributaries continuously flowing all year round. The DENR has previously identified the appropriate land use for the whole site. This includes proposed area for agroforestry, coffee, bamboo, reforestation, and the resettlement area. Moreover, there has been previously established bunkhouse, 2 hectares nursery, 34 concrete seedbeds, a recovery facility, and a water system in the area.
III. INITIAL ACTIVITIES (2012)
A. Nursery Establishment with Bunkhouse
B. Seedling Production
C. Plantation Establishment
D. SWIS Construction
IV. Series of Meetings and Site Visits for CY 2013 BPP Implementation
On March 1, 2013, an inter-agency meeting of DA-DAR-DENR-DILG National
Convergence Initiative for Sustainable Rural Development (NSI-SRD) with DPWH,
DSWD, NHA, HUDCC, and NEA was conducted to discuss the making/drafting of BPP
Masterplan.
A site validation was conducted by National Convergence Initiative Team (NCI),
DENR R3, PENRO, CENRO and other involved agencies on March 5, 2013
On March 6, 2013, an Inter-agency meeting was conducted to discuss the Balik
Probinsiya Operational Framework of the different agencies involved.
A revalidation of the BPP site was conducted on March 11, 2013.
On March 14, 2013, a second interagency meeting was conducted in the DENR
Regional Office to discuss BPP inputs.
On March 25, 2013, the DILG R3 together with DSWD conducted a coordination
meeting with the local officials and functionaries of the Municipality of Dona
Remedios Trinidad, Bulacan.
On April 8, 2013 a meeting has been hosted by DILG R3 to discuss and address some
issues and concerns that were raised by local officials and functionaries/receiving
LGUs of DRT, Bulacan.
On May 3, 2013, a Regional BPP TWG Meeting was conducted to present the
enhanced BPP Framework and to accomplish the BPP WFP.
V. Geohazard Assessment of BPP
A preliminary geohazard assessment was conducted on March 11, 2013 by the Mines
and Geohazard Bureau (MGB) on the proposed resettlement of BPP. According to their
assessment, the following were recommended:
i. resettlement site should be adjusted to the possible expansion site in order to
minimize effects of any hazard that will occur in the future; (already considered)
ii. all structures to be built should conform to the specifications, design and
construction practices set by the National Building Code of the Philippines to
mitigate the identified geohazards;
iii. soil sampling and soil investigation studies should be made on the proposed site
and the area for possible expansion to determine site specific soil parameters
needed for project design;
iv. sufficient no-build buffer zones along the creekbanks should be observed; and
v. settlers should be organized into a Homeowners Association and an emergency
preparedness plan should be formulated.
VI. Subdivision and Perimeter Survey of the metes and bounds
DENR surveyed and subdivide farm lots within 3 parcels of land with a total area of 308.07 hectares.
Summary of the farmlot subdivision survey conducted last April 4, 2013 at the BPP site.
PROJECT LOCATION PARCEL No. of
Farmlots surveyed
Area (Has.)
BALIK PROBINSIYA
PROJECT
So. Duplas, Talamsi and Cocong, Barangay Kalawakan, Municipality of Dona Remedios Trinidad, Province of Bulacan
I 149 228.62
II 25 38.72
III 26 40.73
Total 200 308.07
In total, there are 200 farmlots surveyed with approximately 1.5 hectares each. For
homelot/residential lots each of family shall be allocated has 200 sq.m. The farmlots are
already subdivided. However, the homelot subdivision will be subdivided and monumented
after the establishment of the road network.
The farmlots of the Balik Probinsiya Program (BPP) in three (3) parcels for the plantation of fuelwood and reforestation and Agroforestry component .
VII. Recent Activities
A Regional Executive Order No. 2013-179-Designating some DENR Personnel as
Focal Person in the Implementation of Balik Probinsiya Program (BPP) was
approved on June 14, 2013. (See Annex F. Regional Executive Order No. 2013-179
Designating Some DENR Personnel as Focal Persons in the Implementation of Balik
Probinsiya Project)
A recent visit was conducted by the Central Office to the Balik Probinsiya project site
together with the Gawad Kalinga staff and guests last June 25, 2013 to inspect the
resettlement and plantation area. The group of Gawad Kalinga intend to support
sustainable livelihood for the families to be relocated in the site, particularly on the
productions and processing of cacao.
VIII. Updates for BPP DRT A. Profile of Beneficiaries
Profile
Direct Beneficiaries (a) 200 Indirect Beneficiaries (b) 19478 Service Coverage (Number of Barangays) 8 Investment per HH in PHP (a) 2,072.06 Investment per HH in PHP (a + b) 21.06
B. Site Development Plan
Dimensions and Materials for the Housing Unit
Budgetary Estimates (Proposed Budget)
PARTICULARS COST
Developed Lot PHP 285,000.00 (c/o NHA)
Housing Units PHP 70,000.00 (c/o DSWD)
Cost per unit PHP 355,000.00
Cost for 200 House and Lot units (200 units x PHP 355,000.00)
PHP 71,000,000.00
C. Infrastructure: Access Roads and Proposed Bridge Construction
Budgetary Estimates (Proposed Budget) PARTICULARS COST
Design Analysis for 16.2 km Proposed Access Road
PHP 190,000,000
Proposed Construction of 1 x 120m Bridge PHP 70,000,000
*Detailed Engineering Design is ongoing.
D. Suitable Area for Agro-Development
PARTICULARS AREA (ha) Total Suitable Area 600
Proposed Area for Development 308 Farm Model 3
E. Water Resource Map
Budgetary Estimates (Proposed Budget) PARTICULARS QUANTITY PER UNIT COST TOTAL COST
Concrete Overflow Weir 2 PHP 1,000,000.00 PHP 2,000,000.00 Small Farm Reservoir 20 PHP 80,000.00 PHP 1,600,000.00 5 hp pump and engine sets with 100L plastic tank
5 PHP 50,000 PHP 250,000.00
OVERALL COST PHP 3,850,000.00
IX. Summary of Budgetary Requirement for Each Agency*
Agency Proposed Committed Total
DA PHP 37,650,000.00 PHP 630,000.00 PHP 38,280,000.00
DILG 3,658,400.00 3,658,400.00
DSWD 19,202,000.00 19,202,000.00
DPWH 260,000,000.00 260,000,000.00
NHA/HUDCC 57,000,000.00 57,000,000.00
DOH 2,355,000.00 2,355,000.00
DENR 6,264,000.00 12,000,000.00 18,264,000.00
TESDA 5,200,000.00 5,200,000.00
DepEd 10,453,333.00 10,453,333.00
Total PHP 401,782,733.00 PHP 12,630,000.00 PHP 414,412,733.00 *See Attached BPP DRT Work and Financial Plan for detailed particulars