TABLE OF CONTENTS - Online PIU Information System ...nhai.org.in/spw/IEReport/MAIN REPORT (pages...
Transcript of TABLE OF CONTENTS - Online PIU Information System ...nhai.org.in/spw/IEReport/MAIN REPORT (pages...
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
1.0 PROJECT OVERVIEW
1.1 PROJECT BACKGROUND
The Government of India under the nodal Ministry of Shipping, Road Transport and Highways (MOSRT&H) has taken up the development of the National Highways in the country to enhance the traffic capacity and safety for efficient transportation of goods as well as passenger traffic. The National Highways Authority of India (NHAI) has been entrusted with implementation of this development project. NHAI under NHDP Phase II programme aims at developing section of NH-47, by widening the existing two lane road to four lane dual carriageway including strengthening of existing 2 lanes on Design, Built, Finance, Operation & Transfer (DBFOT) basis.
NHAI appointed the Artefact Projects Limited India, as Independent Engineer for Walayar – Vadakkancherry Section of NH-47 from Km. 182+250 to Km. 240+000 in the state of Kerala to carry out the review of Designs, Drawings, Construction, Progress Monitoring, affirmation of all certifications done by the Concessionaire, etc. The Independent Engineer shall be involved in day-to-day implementation of the Project.
1.2 THE SITE
The Project Highway starting point is near Walayar (Km.182+250) and the termination point is near Vadakkancherry (Km. 240+000. The Project Highway covers Palakkad District in State of Kerala.
1.3 THE CONCESSION AGREEMENT
The Concession Agreement for Design, Built, Finance, Operation & Transfer (DBFOT) basis of NH-47 under NHDP phase II was signed on 17th September, 2012 between National Highways Authority of India having principal office at G-5 & 6, Sector-10, Dwarka, New Delhi-110075 and KNR WALAYAR TOLLWAYS PRIVATE LIMITED (KWTPL) having registered office at Plot no. 114, Phase 1, Kavuri Hills, Jubilee Hills, Hyderabad – 500033, Andhra Pradesh.
1.4 INDEPENDENT ENGINEERING SERVICES
Independent Engineering Services for four laning of Walayar – Vadakkancherry from existing Km.182.250 to Km.240.000 in the state of Kerala under NHDP Phase-II to be executed on BOT (Toll) on DBFOT Basis (Package No.NS-2/BOT-KL-2/Phase-II) was signed on 15th April 2013 between National Highways Authority of India and Artefact Projects Limited (India), Nagpur.
The Independent Engineering Services commenced on the 15th June 2013. An office has been established at Palakkad. The Resident cum Highway Engineer and other key and Sub professionals have been mobilized in June -July 2013.
1.5 THE SCOPE OF PROJECT
The scope of the Project shall include the followings during the Concession Period:Construction of the Project Highway on the Site set forth in Schedule-A and as specified in Schedule-B together with provision of Project Facilities as specified in Schedule-C, and in conformity with the Specifications and Standards set forth in Schedule-D;Operation and Maintenance of the Project Highway in accordance with the provisions of the Concession Agreement and Performance and fulfillment of all other obligations of the Concessionaire in accordance with the provisions of the Concession Agreement and matters incidental thereto or necessary for the performance of any or all of the obligations of the Concessionaire under the Concession Agreement.
Construction of Project Highway 53.885 Kms Construction of Service Roads with RCC Drains. 47.230 Km Construction of Grade Separated Intersections 2 Nos. Construction of Major Junctions 9 Nos.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Construction of Minor Intersections 36 Nos. Construction of Major Bridges 2 Nos. Construction of Rail Over Bridges 1 Nos. Construction of Vehicular Under Passes 4 Nos. Construction of Cattle Under Passes 4 Nos. Construction of Minor Bridges 12 Nos. Construction of Culverts 148 Nos. Construction of toll Plaza at Km 344+438 1 Nos. Construction of Bus bays & Bus Shelter 49 Nos.
1.6 SALIENT FEATURES OF THE PROJECTPROJECT DETAILS
i. Name of Project : Four Laning of Walayar – Vadakkancherry Section in Kerala from Km. 182.250 (Design Chainage Km. 182.250) to Km. 240.000 (Design Chainage Km. 236.135) of NH-47 – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II. (Total Length 53.885 Kms)
ii. Construction Package No. : NS-2/BOT/KL-2.
iii. Performance Security : Rs. 34.10 Crores, (To be Refunded after 1 year or earlier upon expending 20% of the Total Project Cost i.e. 136.40 Crores)
AGENCIES INVOLVED
iv. Client : General Manager (Kerala)National Highways Authority of IndiaG5 & 6, Sector – 10, Dwaraka, New Delhi – 110 075
v. PIU : Project Director,National Highways Authority of India,Project Implementation Unit (PIU), No. 8/1187, Arumughan Colony,Chandranagar, Palakkad, Kerala – 678 007
vi. Independent Engineer : Artefact Projects Limited“SRIVATSAN”Chandranagar Extension,Pirivusala, Palakkad,Kerala – 678 007
vii. Concessionaire : KNR Walayar Tollways Pvt. Ltd, (KWTPL)KNR House, 3rd & 4th Floor,Plot No. 114, Phase-I, Kavuri Hills,Jubilee Hills, Hyderabad – 500 033, Andhra Pradesh.
viii. EPC Contractor : KNR Constructions Limited, (KNRCL)KNR House, 3rd & 4th Floor,Plot No. 114, Phase-I, Kavuri Hills,
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 2
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Jubilee Hills, Hyderabad – 500 033, Andhra Pradesh.
ix. Lenders Independent Engineer (LIE) : Feedback Infra Limited, Bengaluru
x. Lenders Legal Council (LLC) : India Law Services, New Delhi
xi. Lenders Insurance Advisor (LIA) : India Insurance
PROJECT TIMELINES
xii. Date of Submission of Bid : 30th June, 2010.
xiii. Date of LOA : 03rd August , 2012
xiv. Date of Concession Agreement : 17th September, 2012
xv. Appointed Date : 18th May, 2013
xvi. Construction Period : 910 Days
xvii. Scheduled Project Completion : 13th November, 2015Date
xviii. Concession Period : 20 Years (Including Construction Period)xix. Anticipated End of Concession Period : 17th May 2033
PROJECT FINANCIALS
Project Cost Amt. in Rs. Cr.EPC CostsCivil Construction Costs 775.00Contingency (as % of Civil Construction Costs 15.50Total EPC Cost 790.50Non – EPC CostInsurance during Construction 2.37Preliminary Exp. 7.75Other SPC Overheads 17.44Total Non-EPC Cost 27.56Premium to be paid on COD 0.00Total Capital Cost (excluding IDC) 818.06IDC 82.46Total Project Cost (including IDC) 900.51
Sl. Particulars Amount %Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to
Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 3
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
No. (Rs. Crores)
1 KNR Constructions Limited 135.91 100 % of equity
2 Others 0.00 0 % of equity
3 Promoters’ Equity 135.91 15.09% of TPC
4 Grant 264.60 29.38% of TPC
5 Senior Debt 500.00 55.52% of TPC
Total Project Cost 900.51 100.0
LENDERS DETAILS AND CONTRIBUTION:
Sl No. Bank Name
Amount of Contribution(Rs. Crores)
Remarks
1. Central Bank of India 175 Lead Bank
2. Bank of India 100 Consortium Bank
3. Corporation Bank 90 Consortium Bank
4. Canara Bank 85 Consortium Bank
5. Vijaya Bank 50 Consortium Bank
Total Loan Amount 500
PROJECT MILESTONES AS PER SCHEDULE - G OF CA Sl
No. Mile stone Target Date Target Percentage
1. I 180 Days from the Appointed date (November 13, 2013)
10%
2. II 400 Days from the Appointed Date (June 21, 2014)
35%
3. III 650 Days from the appointed date(February 26, 2015)
70%
4. IV 910 Days from the Appointed date(November 13, 2015)
100%
SCOPE OF THE PROJECT CONSTRUCTION SCHEDULES B, C & D
xx. Project Length : 53.885 Kms
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 4
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
xxi. Service Roads : LHS : 3.500 Kms RHS : 0.990 Kms BHS : 42.740 Kms Total : 47.230 Kms
xxii. Major Intersections : 9 No’s
xxiii. Minor Junctions : 36 No’s
xxiv. Grade Separated Intersections : 2 No’s
xxv. Underpasses : VUP’s : 4 No’sCUP’s : 4 No’s
Total : 8 Nos xxvi. Major Bridges : 2 No’s
xxvii. ROB : 1 No.
xxviii. Minor Bridges : 12 No’s
xxix. Culverts : Reconstruction : 17 No’s New Construction/ Widening : 148 No’s
xxx. Toll Plaza : 1 No. (Km. 189+400)
xxxi. Bus Bay and Bus Shelters : LHS : 26 No’sRHS : 23 No’s
Total : 49 No’s
xxxii. Truck Lay bays : Nil
xxxiii. Rest Areas : Nil
xxxiv. HTMS : Not Required till Traffic reaches 40,000 PCU
xxxv. Financial Progress Up to 31st July-2013 : 11.37 %
1.7 GENERAL FEATURES OF THE PROJECT
i. Width of Paved Carriagewaya) Main Carriageway (4 Lanes) : 17.5mb) Service Road : 7.0m
ii. Carriageway Width : 8.75m (including 1.5m Hard Shoulder)
iii. Unpaved Shoulder : 1.5m (on Both Sides)
iv. Bridge width : 12m (end to end)
v. Median Width : 1.5 mtrs to 4.5 mtrs: 1.0m (at Median openings)
vi. Cross slope : 2.5% (on carriage way): 3% (on shoulder)
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 5
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
vii. Embankment Side Slop : 1 in 1 to 1 in 2
viii. Super Elevation : 7% (Maximum)
ix. Gradient (maximum) : ……..% Maximum (at Km ____ to _____)
x. Radius (minimum) : ……..m (at Km _______ & at Km. _______)
xi. Pattern of widening as per Existing Chainage (Given in CA)a) Concentric : 28.857Kms.b) Eccentric
LHS : 13.678 Kms. RHS : 11.452 Kms.
c) Transition : 3.763 Kms.Total : 57.750 Kms.
xii. Design speed : 100 KMPH (except few locations)xiii. Pavement Design for Rigid Pavement for Toll Plazas.
Sl No. Layer Thickness (Tentative)1 PQC 280 mm2 DLC 150 mm3 GSB 200 mm4 Sub Grade 500mm
xiv. Pavement Design for New Construction / Reconstruction and Widening
Direction: Walayar to Vadakkancherry
Homogeneous Section HS-01 HS-02Existing Chainage (From – To) 182.250 – 204.000 204.000 – 240.000
New Design Chainage (From – To) 182.250 – 204.000 204.000 – 236.140
Design CBR Value in % 10 10
Design Traffic in MSA 63 (up to end of Concession Period)
77 (up to end of Concession Period)
Wearing Course (BC), mm 45 50
Binder Course (DBM), mm 115 120
Base Course (WMM), mm 250 250
Granular Sub-base Course (GSB), mm 200 200
Sub-grade layers, mm 500 500
Direction: Vadakkancherry to Walayar
Homogeneous Section HS-01 HS-02
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 6
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Existing Chainage (From – To) 182.250 – 204.000 204.000 – 240.000
New Design Chainage (From – To) 182.250 – 204.000 204.000 – 236.140
Design CBR Value in % 10 10
Design Traffic in MSA 76 (up to end of Concession Period)
66 (up to end of Concession Period)
Wearing Course (BC), mm 50 45
Binder Course (DBM), mm 120 115
Base Course (WMM), mm 250 250
Granular Sub-base Course (GSB), mm 200 200
Sub-grade layers, mm 500 500
xv. Pavement Design for Service Roads / Slip Roads
Design CBR Value in % 10
Design Traffic in MSA 5
Wearing Course (SDBC), mm 25
Binder Course (DBM), mm 50
Base Course (WMM), mm 250
Granular Sub-base Course (GSB), mm 150
Sub-grade layers, mm 500
2.0 EXECUTIVE SUMMARY
2.1 PHYSICAL & FINANCIAL PROGRESS:
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 7
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Cost of the Project: 900.51 CroresConstruction Period: 910 days Construction Time Lapse at the end of July 2013 : 74 days – 8.13%Construction Time Remaining at the end July 2013 : 836 days – 91.8%
Physical Progress Till Last Month This Month To Date
Scheduled (%) -- -- --
Actual (%) -- -- --
Financial Progress Till Last Month This Month To Date
Scheduled (%) 1.5 1.49 2.99
Actual (%) 6.11 5.26 11.37
Note: The S – Curve of the Financial Progress is shown in Annexure – 10.
2.2 REVIEW OF DESIGNS & DRAWINGS
STATUS OF DRAWING APPROVALS (Highways)
S. No Details of drawings
Submitted by Concessionai
re
Comments/ Conditional
Approval given by IC/
NHAI.
Resubmitted by Concessionaire
after incorporating all
comments
GFC drawings
issuedRemarks
ROAD
1Plan & Profile182+250 to 202+000 (19.75 Kms)
19.75 km No No No
206+000 to 233+000 (27 Kms) 27 km No No No
2 Typical Cross-section (Total 10 Nos) 17 17 17 No
3 Miscellaneous Drawings No No No No
STATUS OF DRAWING APPROVALS (STRUCTURES)
MAJOR BRIDGES
SUB STRUCTURE SUPER STRUCTURESUBMITTED APPROVED GFC
ISSUED SUBMITTED APPROVED GFC ISSUED
1.198+870 YES NO NO YES NO NO2.207+900 YES NO NO YES NO NO
MINOR BRIDGES
SUB STRUCTURE SUPER STRUCTURESUBMITTED APPROVED GFC
ISSUED SUBMITTED APPROVED GFC ISSUED
1.182+2372.190+970 YES NO NO YES NO NO3.194+470 YES NO NO YES NO NO4.201+295 YES NO NO YES NO NO5.204+680 YES NO NO YES NO NO6.209+950 YES NO NO YES NO NO
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 8
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
7.213+160 YES NO NO YES NO NO8.214+272 YES NO NO YES NO NO9.219+570 YES NO NO YES NO NO10.222+165 YES NO NO YES NO NO11.224+902 YES NO NO YES NO NO12.235+180 NO NO NO NO NO NO
GRADE SEPARATOR SUB STRUCTURE SUPER STRUCTURE
SUBMITTED APPROVED GFC ISSUED SUBMITTED APPROVED GFC
ISSUED1.203+900 YES NO NO NO NO NO 2.225+507 NO NO NO NO NO NO
VEHICULAR UNDERPASS SUBMITTED APPROVED GFC ISSUED
1. 197+730 YES NO NO2. 209+076 NO NO NO3. 217+310 YES NO NO4.235+600 NO NO NO
PEDESTRIAN UNDERPASS SUBMITTED APPROVED GFC ISSUED
1. 187+350 YES NO NO2. 216+400 NO NO NO3. 222+680 NO NO NO4. 223+530 NO NO NO CULVERTS TOTAL SUMITTED APPROVED1.PIPE CULVERTS 22 0 02.BOX CULVERTS 126 54 0
2.3 STATUS OF MOBILISATIONa) Independent Engineer has mobilized their project team with effect from 15 th June 2013 with
their key personnel; Resident cum Highway Engineer, Sr. Quality Material Expert, Highway Design Engineer, Structural cum Bridge Engineer, Sr. Bridge Design Engineer, Assistant
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 9
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Highway Engineers, Assistant Bridge Engineers, Assistant Material Engineers, Survey Engineer and Administrative staff. The project office was set up in Palakkad Town.
Sl. No Name Designation DateProfessionals
1 TBN TL cum Sr. HE2 Mr. Ashok Gupta Sr. Bridge Design Engineer3 Mr. Mohan Raj Highway Design Engineer4 Mr. Sandeep M Battah Financial Expert 5 Mr. Raju Chhabra Legal Expert6 Mr. Arif Zafar Road/Safety Expert7 Mr. Murali Krishna Traffic Expert8 TBN Electrical Engineer9 TBN Environmental Engineer
10 TBN HTMS/TE11 TBN Horticulturist 12 Mr. Mohan Chawla Sr. Pavement Specialist13 Mr. K. Chandrasekhar Reddy Resident cum HE14 Mr. Shaik Khasim Peera Bridge/Structural Engineer15 Mr. J.K. Joshi Sr. Quality cum Material Expert
Sub Professionals 1 Mr. M Ankaiah Survey Engineer2 TBN AHE (1)3 Mr. Elango C AHE (2)4 Mr. Jaganathan ABE (1)5 TBN ABE (2)6 Mr. Rejith Balakrishnan AME (1)7 Mr. Mohammed Rafi AME (2)8 TBN CAD Expert
Administration Staff 1 Mr. V.P. Radhakrishnan Office Manager2 Mr. Shankar M Office Accountant3 Mr. Prasadan C Cashier4 Mr. Mohammed Rafi Steno 5 Mr. Vaisakhan M.S Computer Operator6 Mr. Manoj M Office Boy7 Mr. Vijayan K Xerox Operator8 Mr. Gopi Night Guard9 Mr. Manikandan Day Guard
Note: Details are shown in Independent Engineer Organization Chart – Annexure 1.
b) The Concessionaire has mobilized their key personnel and technical personnel for the
project. The project office was set up near Walayar. They have constructed project office at
Km. 187+420.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 10
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Project Monitoring & Control Team
Sl No. Name Designation1. E. Sreenivasa Rao Team Leader Cum Sr. Highway Engineer2. C. Prabhu Swamy Sr. Project Manager (Structures)3. K.D.P. Rao Sr. Material Engineer4. Ajo Abraham Safety In- charge5. T. Gopal Krishna Land Acquisition In-charge6. Sudhakar Bridge Engineer7. Surendra Highway Engineer8. Sekhar Q.C. Engineer9. Ravi Survey Engineer
10. Prasanth Reddy Lab Technician
Status of EPC Contractor Man Power mobilized at Site
Sl. No. Name Designation Nos
. Remarks
1. V.Venugopal Reddy Project Co-ordinator 1
2. M. Ramakrishna Reddy Project Manager 1
3. Ch. Yakambaram Construction Manager 1
4. C.Rajender Reddy Asst. General Manager (Mech.) 1
5. Vijay Kumar Pandey Chief Surveyor 1
6. Ritesh N Sr. Mechanical Engineer 1
7. P. Surender Reddy Manager Q & C 1
8. Tirupathi Reddy A In-charge Crusher / Plant 1
9. Panicker R S Admin. Manager 1
10. Purshottam Dash Accounts Manager 1
11. Accounts Team 3
12. Administration Team 17
13. Civil-Highway 17
14. Civil-Structure 38
15. Civil-Survey 8
16. Lab. Team 26
17. Earth Moving Equipment Operators 71
18. Workshop / Garage Team 42
19. All Plants Team 53
20. Drivers 89
21. Helpers 39
22. Store Team 24
23. Supervisor's Mechanical 16
Total 458
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 11
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Note: Organization charts of SPV, EPC Contractor enclosed in Annexure – 2 & 3.
LIST OF PLANTS, MACHINERIES & EQUIPMENT
a) Plants
Sl.No
Name of the Equipment Make /Model Qty
Mobilized
Location (Road Side,
Quarry, Plant)
Date of Mobilizati
onRemarks
1
Crusher
Puzzalona 150 TPH 1 No. Palathurai 05-01-2013
2 Nawa 250 TPH 1 No. Mangalamdam
18-01-2013
3 Puzzalona 250TPH 1 No. Pudussery East Village
24-04-2013
Total 3 No's
4
Batching Plant
Penta 60 Cum/Hr 1 No. PLANT @ Km. 187.000
10-10-2012
5 Miller 30 Cum/Hr 1 No. PLANT @ Km. 231.735
08-02-2013
6 Schwing Stetter 30 Cum/Hr 1 No. PLANT @
Km. 207.00030-03-2013
Total 3 No's
7 HOT MIXING PLANT D&G 240 TPH 1 No. PLANT @
Km. 231.73531-03-2013
Total 1 No.
b) Machineries & Vehicles
Sl No. Name of the Equipment Make /Model Qty Mobilized1
Generators
Crompton Greaves 7.5 KVA 1 No.
2 Kirloskar 15 KVA 1 No.
3 Cummins 40 KVA 1 No.
4 Greaves 40 KVA 1 No.
5 Kirloskar 40 KVA 3 No’s6 Kirloskar 50 KVA 2 No’s7 Kirloskar 62.5 KVA 1 No.
8 Kirloskar 75 KVA 1 No.9 Kirloskar 100 KVA 1 No.
10 Cummins 125 KVA 1 No.
11 Catterpiller 200 KVA 1 No.
12 Catterpiller 365 KVA 1 No.
13 Catterpiller 500 KVA 2 No’s
14 Catterpiller 600 KVA 3 No’s
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 12
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Total 20 No's
15
Excavators
KOBELCO SK 140 LC 8 3 No's
16 KOBELCO SK 210 12 No’s
17 Kobleco SK-350 LC 8 8 No's
18 Kobleco SK-480 LC 8 2 No’s.
Total 26 No's19
Soil Compactor
IR SD 110 5 No’s
20 CAT - 533E 3 No’s
21 CAT - CS533E 1 No.
22 IR ISD 100 5 No’s
23 IR SD Roller 2 No’s
24 PTR – 220 1 No.
Total 17 No's
25 Asphalt Compactor/Tandom Roller
Greaves 1 No.
26 Baby HD-12W 1 No.
Total 2 No's
27
Motor Grader
CAT-120 H 2 No’s
28 CAT-140 K 2 No’s
29 CAT-140 H 5 No’s
Total 9 No's
30
Dozers
CAT D5G 1 No.
31 CAT D5G XL 1 No.
32 CAT D6G XL 1 No.
Total 3 No's
33 Weigh Bridge Essae 3 No’s
34 Tyre Mounted Crane KATO 1 No.
35Hydra Crane
Escorts TRX 2319 1 No.
36 Escort F15 1 No.37 TIL 1 No.38 Tadano 2 No’s
39 Hydraulic crawler 100 Ton 2 No’s
Total 8 No’s
40 Boom Placer Putzmeister 1 No.
41
Loader
HM 2021 2 No’s
42 Liugon – CLG856 2 No’s
43 CAT 950H 2 No’s
Total 6 No’s
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 13
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
44 Lighting Source IR 4 No’s
45 Kerb Machines Appolo KP 40 1 No.
46Paver
Vogele 1 No.
47 CAT 1 No.
Total 2 No’s
48 Containers 11 No’s
49 Cement Silo 2 No’s
50 Riggers SANDVIK DX-700 1 No.
51 Breakers Doosan XL1700 3 No’s
52 Piling Machine MAIT 180 1 No.
53 Hydraulic Breaker Doosan 3 No’s
54
Tippers
Volvo 36 No’s
55 Bharat Benz 10 No’s
56 Bharat Benz (Rock Body) 4 No’s
57 AMW 16 No’s
58 Hino 10 No’s
59 Man 3 No’s
60 Ashok Leyland 9 No’s
Total: 85 No’s
61
Transit Mixers
Ashok Leyland 1 No.
62 TATA 1 No.
63 AMW 3 No.
64 Taurus 6 No’s
Total: 11 No’s
65 Eichers 6 No’s
66 Trailors 4 No’s
67 Water Tankers Ashok Leyland 5 No’s68 Tata 2 No’s
Total: 7 No’s69 Diesel Tankers TATA 2 No’s
70 Ashok Leyland 1 No.
Total: 3 No’s
71 Tractor with Compressors 9 No’s
72 LMV’s 24 No’s
73 Two Wheelers 16 No’s
c) List of Lab Equipments Mobilized at Site
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 14
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Sl. No Description UnitEquipment Available
at LabRemarks
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 15
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
1 Hot air Oven (size 900mm X 600mm) No 1
2 Hot air Oven size 600mm X600mm No 1
3 Electronic Weighing Balance 20Kg capacity No’s 1
4 Electronic Weighing Balance 10Kg capacity No’s 5
5 Electronic Weighing Balance 50 kg capacity No’s 3
6 Electronic Weighing Balance 200 gm capacity No’s 1
7 Electronic Weighing Balance 60 Kg capacity No’s 2
8 Weighing Balance 30kg capacity with weights, manual operating No’s 3
9 Digital Thermometer range up to 0 deg C to 300 deg C No’s 10
10 Mercury in Glass Thermometer 0 deg C to 360 deg C No’s 10
SOIL TESTING EQUIPMENTS
11 Plastic Limit Set Set 2
12 Cone Penetrometer Set 2
13Atterberg Liquid Limit Device with casa Grande tools Hand operated with Counter as per IS: 2720(part - V)
No’s 2
14 Sand Pouring Cylinder (Sand Replacement Method) 100mm dia No’s 3
15 Sand Pouring Cylinder (Sand Replacement Method) 150mm dia No’s 6
16 Sand Pouring Cylinder (Sand Replacement Method) 200mm dia No’s 5
17 Trays with centre hole 100mm dia No’s 3
18 Trays with centre hole 150mm dia No’s 6
19 Trays with centre hole 200mm dia No’s 6
20 Sample Container 50mm No’s 6
21 Sample Container 75mm No’s 60
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 16
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
22 Sample Container 100mm No’s 40
23 Spatula No’s 4
24 Standard Compaction Test (Proctor Compaction Mould) 100mm internal dia No. 1
25 Standard Compaction Test (Proctor Compaction Mould) 150mm internal dia No’s 10
26 Speedy Moisture Meter 0% to 50% complete with chemicals No’s 4
27 Pycnometer (1 Ltr glass jar with brass cone locking ring and rubber seal) No’s 3
28 California Bearing Ratio Apparatus Electrically operated. No. 2
29 CBR Mould 150mm dia No’s 50
30 Displacer Block 148mm dia & 47.7mm long No’s 10
31 Surcharge Weight 2.5kgs No’s 100
32 Perforated Brass Plate with locking nut & stem No’s 80
33 Tripod Stand No’s 6
34 Cutting Collar No’s 7
35 Dial Gauge 0.01 mm X 25 BAKER make No’s 10
36 Test sieves for Coarse Aggregate made of GI Sheet 450mm dia as per IS-460(Part - I) sizes 125mm, 106, 100, 90, 16, 13, 2, 12.5, 11.2, 10, 9.5, 6.7, 6.3, 5.6, 4.75,2.36, 1.18mm
Set 2
37
Test sieves for Coarse Aggregate made of GI Sheet 300mm dia as per IS-460(Part - I) sizes 125mm, 106, 100, 90, 80, 75, 63, 60, 53, 50, 45, 40, 37.5, 31.5, 26.5, 25.22, 4, 20, 19, 16, 13.2, 12.5, 11.2, 10, 9.5, 6.7, 6.3, 5.6, 4.75, 2.36, 1.18mm
Set 2
38
Test sieves for Fine Aggregate made of Brass frame and Stainless Steel Mesh as per IS: 460(Part-I) sizes 1.00mm 1.18, 1.40, 1.70, 2.00, 2.8, 2.36, 3.35, 4.75mm and 850microns, 710, 600, 500, 425, 355, 250, 212, 180, 150, 100
Set 4
39 -do- 75microns and 90 microns Set 14
40 Standard Sand each bag of 25kgs (Grade I,II,III Set 2
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 17
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
AGGREGATE & CEMENT TESTING EQUIPMENTS
41 Flakiness index (Thickness gauge) No’s 5
42 Elongation index (Length gauge) No’s 7
43 Cylindrical Measures (Metal Measures) 3 Lit, 15 Lit, 30 Lit capacity No’s 1
44 Density Basket No’s 4
45 Riffle Box No’s 1
46 Aggregate Impact Tester. No’s 2
47 Slump Test Apparatus No’s 10
48 Tamping Rod No’s 9
49 Flow Table motorized as IS:5512 No. 1
50 Laboratory Concrete Mixer Motorized capacity 1 cuft No. 1
51 Standard Spatula as per IS: 4031 No’s 2
52 Gauging Trowel as per IS: 4031 No. 1
53 Flexure Testing Machine motorized 100 KN capacity as IS: 516 No. 1
54Cube Moulds made of Cast Iron size 150mm X 150mm (8.25Kgs) as per IS: 4031, 516
No’s 200
55Cube Moulds made of Stainless steel 7.06cm X 7.06cm X 7.06cm as per IS: 4031,516
No’s 18
56 Vibrating Table size 1 mtr X 1 mtr No’s 1
57 Motor Cube Vibrator or Vibrating Machine No’s 1
58 Le- chrtlier Apparatus Set 10
59 Core Drilling Machine No’s 1
60 Flexure Beams as IS: 516 No’s 9
BITUMEN & BITUMENIOUS TESTING EQUIPMENT
60 Water bath capacity of 10 Ltrs. No’s 2
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 18
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
61 Ring and Ball Apparatus as per IS: 1205 - 1958 No’s 1
62 Flash & Fire Apparatus No’s 1
63 Specific Gravity Bottle 50ml BOROSIL make No’s 5
64 Dial Thermometer No’s 10
65 Depth Gauge - 12" No’s 10
66 Standard Penetro meter with needles electrically operated No’s 1
67 Ductility Testing Apparatus as per IS: 1208, 1958, ASTMD:D113 No’s 1
68 Centrifuge Bitumen Extractor (Motorized) No’s 2
69Marshall Stability Test apparatus Electrically operated load frame capacity 50KN
No’s 1
70 Marshall Moulds with base plate 100mm dia No’s 24
71 Marshall Rammer for 100mm mould No’s 8
72 Commercial Benzene Ltr 200
73 Say bolt Viscometer No. 1
74 Straight Edge with Steel Wedge Size 3 mtrs No’s 2
75 Camber Board No. 1
76 Trays 45cm X 45cm Set 43
77 Rain Gauge No’s 3
78 Compressive Testing Machine motorized 2000 KN capacity as IS: 516 No’s 1
79 Ten% fines value Apparatus No’s 1
80 Max - Minimum Thermometers No’s 5
81 Le- chatlier Flask No’s 4
82 Borosil jars 100ml No’s 8
83 Sand equivalent Apparatus No’s 1
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 19
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
84 Rubber Hammers No’s 4
85 Cube Moulds made 10cm X 10cm X 10cm as per IS: 4031,516 No’s 37
86 Cube Moulds made 5 cm X 5 cm X 5 cm as per IS: 4031,517 No’s 17
87 Electronic Weighing Balance 40 kg capacity No’s 2
88 Diamond Core Bits 100mm Dia No’s 4
89 Gmm Jars with vacuum pump No’s 2
90 Marshall Pedestal No’s 1
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 20
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Line Diagram of the EPC Contractor Camp Set up
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 21
KNR WALAYAR TOLLWAYS PRIVATE LIMITED
COIMBATORE THRISSUR
Km. 1
82+2
50
(Sta
rt Po
int o
f th
e Pro
ject)
Walayar Km
. 187
+500
Four laning of Walayar – Vadakkancherry Section in Kerala (Km 182/250 to Km 240/000 of NH – 47) – Package NS-2/BOT/KL-2 – on DBFOT (Toll) basis under NHDP Phase-IILINE DIAGRAM OF THE EPC CONTRACTOR CAMP SET UP
BP - I
Km. 2
07+0
00Police Station
Km. 2
36+1
35Va
dakk
anch
eery
(End
Poi
nt o
f th
e Pro
ject)
BC - I
Palathurai
Q & C - I
Q & C - III
BC - II
Mangalamdam
NOTE:BC : BASE CAMPQ & C : QUARRY & CRUSHER PLANTBP : BATCHING PLANTHMP : HOT MIX PLANT
Km. 2
31+7
35
8.00 Kms
WWMP : WET MIX PLANT
5.25 Kms
13.5
Kms
WMMP - II,BP - II
WAL
AYAR
10.5
Kms
Offset 1.5 Kms
Offset 0.100 Kms
4.4 Kms
53.885 Kms
Q & C - II
0.500
Km
s
HMP - I
0.100
Km
s
BP - IIIHMP - II,
WMMP - I&
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
2.4. a HIGHWAY PROGRESS LEANIER
Sl. No
Description
Total length of the project(KM)
Length (Km) Completed in July –
2013
Cumulative length (Km) Completed up
to July – 2013
LHS RHS LHS RHS LHS RHS
1 Clearing & Grubbing 53.885 53.885 19.49 15.89 38.610 35.850
2 Embankment Top 53.885 53.885 10.60 12.59 17.660 18.550
3 Sub grade Top 53.885 53.885 0.32 0.04 3.460 4.650
4 GSB 53.885 53.885 -- -- -- --
5 WMM – 1st 53.885 53.885 -- -- -- --
6 WMM – 2nd 53.885 53.885 -- -- -- --
7 Kerb 53.885 53.885 -- -- -- --
8 DBM Top 53.885 53.885 -- -- -- --
9 BC Top 53.885 53.885 -- -- -- --
2.4. b HIGHWAY PROGRESS SERVICE ROADS
Sl. No Description
Total length of the Service Roads
(KM)
Length (Km) Completed in August-11
Cumulative length (Km) Completed up to
August-11
LHS RHS LHS RHS LHS RHS
1 Clearing & Grubbing
-- -- -- -- -- --
2 Embankment Top -- -- -- -- -- --
3 Sub grade Top -- -- -- -- -- --
4 GSB -- -- -- -- -- --
5 WMM – 1st -- -- -- -- -- --
6 WMM – 2nd -- -- -- -- -- --
7 Kerb -- -- -- -- -- --
8 DBM Top -- -- -- -- -- --
9 BC Top -- -- -- -- -- --
Note: Details are given in Annexure – 5, 6 & 7
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 22
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
2.5 STATUS OF STRUCTURES PROGRESS UPTO 31st July 2013
SL. No. Description Total No. Completed In
ProgressBalance to be
Taken up Remarks
1 Pipe Culverts 22 - 9 132 Box Culverts 126 24 28 743 Minor Bridges 12 - 10 24 CUP / PUP 4 - 4 -5 VUP 4 - 2 36 Major Bridges 2 - 2 -7 R.O.B 1 - - 18 Grade Separators 2 - - 29 Toll Plaza 1 - 1 -
Note: Details are given in Annexure – 8 2.6 MATERIAL TESTING AND CERTIFICATION
1. TESTING All basic and routine tests for earth work, granular materials, bitumen materials and concrete
works are carried out at project laboratory. Test for cement, water, aggregate, admixture, reinforcement steel, low relaxation steel, bitumen
emulsions are being done at approved Independent Laboratory. Tests Like bearings, sheathing duct, NP4 Pipe etc are also done. Calibration for testing apparatus, Laboratory equipments and plants has been carried out. Concessionaire has established site Laboratory at the following Location:
Location Test Coverage
KM 187 + 400 LHS 1. Earthworks2. GSB3. Wet Mix Maccadam4. Mineral Aggregates5. Concrete
2. SOURCES OF AGGREGATE AND SAND
Fine and coarse aggregate for WMM,DBM,DC,BM,SDBC and Concrete etc are made available from a quarry located at off 5 Km 166+000 LHS about 20 Km from project starting point. Concessionaire is setting up and quarry and crusher at 187+400 and 8Km off 232+000 LHS (near Mangalam dam location).
3. CONCRETE MIX DESIGN
The Concrete mix design carried out by the concessionaire have been verified and approved for permanent works using Chettinad Cement OPC 43 Grade.
SL.NO GRADE OF CONCRETE USED FOR
1 M15 PCC in Structures
2 M20 PCC in Structures
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 23
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
3 M25 RCC in Structures4 M30 RCC in Structures5 M35 Pile, Under Pass Slab
6 M40 RCC for Crash BarrierPQC for rigid pavement
7 M45 PSC Girder
QUALITY CONTROL TEST
Material testing has been done as per requirement of the contract and MORTH specification.
Quality Control Report From IE For the Month Of July 2013
CEMENT TESTING
Sl.No Name of testTotal no of test done
Total no of test passed
Total no of test failed Remarks
1 Consistency 4 4 _ 2 Initial setting time 4 4 _ 3 Final setting time 4 4 _ 4 Fineness - - _ 5 Soundness 4 4 _ 6 Cement mortar cubes(3days) 4 4 _ 7 Cement mortar cubes(7days) 4 4 _ 8 Cement mortar cubes(28days) 1 1 _
AGGREGATE TESTING1 Gradation of 20mm 4 4 _ 2 Gradation of 12.5mm 4 4 _ 3 Gradation of Sand 4 4 _ 4 AIV 4 4 _ 5 Flakiness Index 4 4 _
COMPRESSIVE STRENGTH OF CONCRETE OF CUBES1 M-15 PCC (7 days) 4 4 _ 2 M-15 PCC (28 days) 3 3 _ 3 M-20 (7 days) 3 3 _ 4 M-20 (28 days) _ _ _ 5 M-25 (7 days) 9 9 _ 6 M-25 (28 days) 15 15 _ 7 M-30 (7 days) 11 11 _ 8 M-30 (28 days) 32 32 _ 9 M-35 (7 days) _ _ _
10 M-35 (28 days) _ _ _ 11 M-40 (7 days) _ _ _ 12 M-40 (28 days) _ _ _ 13 M-45 (7 days) 4 4 _ 14 M-45 (14 days) 1 1 15 M-45 (28 days) 1 1 _
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 24
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Note: Summary of Monthly Quality Control Test is shown in Annexure – 11.
5. MATERIALS SUPPLIERS
SL.NO PARTICULAR SUPPLIER
1 Cement, Grade OPC 43 1.Chettinad Cement2.Penna Cement
2 Reinforcing Steel bar (TMT) 1.RINL Vizag Plant2.JSW Steel Ltd, Salem
3 Admixture for Concrete 1.Fair mate Chemicals2.BASF
4 Low Relaxation, PC Stranded Wires 1.Tata Steel Wire Division5 Sheathing pipes 2.Rex Poly Extrution Ltd.
6 NP4 pipes 1.Chennai Span Pipes Industries, Pollachi
7 Strip seal 1.Z-Tech (Industries) Ltd, New Delhi
8 Bitumen 1.MRPL Ltd, Mangalore
9 Emulsion 1.Hincol, Chennai
10 Bearing (POT-PTEE Megaba Bridge Products Pvt Ltd, Kolkata 11 Pre-stressing System BBR India Pvt Ltd, Banglore12 RE Wall System STRATA GEO SYSTEM (I) PVT LTD13 Strip Seal Expansion Joints SANFIELD BHOPAL
2.7 ENVIRONMENTAL PROTECTIONIE staff carries out regular site visits and observe the construction areas and check the following areas:
Stone quarries and borrow areas;
Crusher plants;
Storage area of Oil and Lubricants yard;
Roadways and Campsite;
Disposal of debris and unsuitable materials.
Keeping in view to the environment compliances, the Concessionaire has been instructed to avoid damage or nuisance to persons or to property of the public or other resulting from pollution, noise or other causes arising as a consequence of their method of operation.
There were certain issues to be complied by the Concessionaire as mentioned below: - Improper debris disposal and management. Improper waste management. Inadequate drainage/waste water treatment facility. Improper Borrow area operation and management.
2.8 ROAD SAFETY
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 25
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
The existing two lanes though in good shape and in service the riding quality were constantly
checked. Some Potholes had been filled up. In places where construction is in progress the
following action has to be implemented by Concessionaire to increase the safety to road users;
a)Warning and information signs in line with IRC/MORT&H standards and specification;
b)Signage boards at junction/urban areas to control the speed;
c)Barricades and reflector tapes to areas where ongoing excavation are carried out;
Concessionaire was regularly reminded to keep acceptable safety arrangements at construction zones as per IRC-SP-55 for smooth flow of traffic. Independent Engineer instructed to Concessionaire to improve the road safety vide our letter no. IE/APL/KL-2/2013/002 and letter no IE/APL/Kl-2/2013/005 safety measures during four lane construction.
2.9 ROAD ACCIDENT REPORT
Independent Engineer is given instructions to Concessionaire to collect and submit the accidental data for every month, identify accidental prone zones to made adequate safety arrangements, signboards etc. to avoid accidents. And advised to carryout safety audit along with IE representative for every month
2.10 MAINTENANCE OF EXISTING TWO LANE HIGHWAY
Independent Engineer given instructions to concessionaire to carry out the routine maintenance of existing carriage way i.e., filling of pot holes, patches and removal of water in water logged areas on the existing carriage way.The Concessionaire is taking regular actions in the maintenance of the existing carriage way in the month of July 2013.It was made aware to the Concessionaire road maintenance shall be a continuous process until the Schedule Date of Completion and until the O and M team to takes over the Highway.
2.11 METHOD ADOPTED IN CONSTRUCTION
The method of construction adopted by the concessionaire as per construction methodology of activities has been regularly checked and reviewed by the Independent Engineer through conducting field and laboratory tests, whether materials used are in compliance with Specification and Standards.
2.12 CONFORMITY OF CONSTRUCTION WORK
The source of materials used for the construction works are regularly checked by Independent Engineer for conformity with the Specifications and Standards. Routine checks were regularly conducted by the Independent Engineer field team. The Acting Team Leader also attended to some tests like cube crushing etc. during his site inspection with the Concessionaire. It was found that the materials used were within limits of Specifications and Standards were being maintained by the Concessionaire in the month of July 2013. The quality of materials used for execution and other tests were all within the specified limits.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 26
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
The structural works that is major bridges, minor bridges, VUP and Box Culverts are in progress; Independent Engineer representatives are regularly attending and checking the activities.
2.13 NON COMPLIANCE REPORT (N C R)
So far no NCR was issued to the Concessionaire.
2.14 REQUEST FOR INSPECTION (R F I)
Number of RFI’s submitted by Concessionaire and attended/checked and closed by IE: From 01-07-2013 to 31-07-2013
Sl. No. DescriptionTotal No. of RFIs
submitted by Concessionaire
Attended/ Checked
by IE% age
attendedNo. of RFIs
approvedRemarks
1 For Materials 16 13 81% 13 2 For Highway 40 2 5% - 3 For Structures 351 85 24% 54
2.15 TEAM LEADER’S COMMENTS
The Concessionaire submitted 2 copies of July 2013 Monthly Progress Report (MPR) on 14.08.2013. After review and verification comments are as follows: -
1. The weather was not good due to heavy rains for the entire July month for carrying out construction activities like earth works, GSB, WMM, DBM & BC. The structural works are in little progress.
2. The Concessionaire has reported that their slacking in progress was mainly due to heavy rains. It is expected that concessionaire should achieve a much higher percentage in physical progress in forth coming months and after monsoon season.
3. There are total no 174 cross structures. The progress of structures, 2 nos. major bridges, 10 nos. minor bridges, 1 no. VUP, 4 nos of CUP/PUP 28 nos. Box culverts are in progress. 22 nos. pipe culverts, 74 nos. box culverts, 2 no. minor bridges, 3 nos. VUP, 1 no. ROB, 2 nos. Grade separators, 1no. Toll plaza to be taken up. Box culverts 24 nos. completed.
4. Highway progress, Embankment top 17.660 (LHS), 18.550 (RHS) kms. Sub grade top 3.46 (LHS), 4.65 (RHS) kms. Completed. GSB, WMM, BBM, BC, etc. not yet started.
5. Due to heavy rains there are so many pot holes patches are formed on existing carriage way concessionaire is instructed by the Independent Engineer representative to take up the maintenance of existing carriage way i.e. filling of pot holes and patches, the work is in progress.
2.16 WEATHER CONDITIONS & REPORTIn the month of July 2013 heavy rain falls due to monsoon.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 27
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Sl. No Date
TEMPARATURE 0C RAIN FALL (mm)Camp: at Km. 187+500
(RHS)Camp: at Km. 232+180
(LHS) Camp: at Km. 187+500 (RHS)
Camp: at Km. 232+180 (LHS)
Max 0C Min0C Max 0C Min0C
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 28
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
1 01.07.2013 25.3 23.6 32.4 23.0 0.0 1.2
2 02.07.2013 28.5 23.4 34.6 25.6 15.0 4.3
3 03.07.2013 28.0 23.5 33.5 24.6 30.0 22.2
4 04.07.2013 28.5 23.2 31.6 22.8 0.2 47.6
5 05.07.2013 28.0 24.5 32.1 23.4 2.2 20.0
6 06.07.2013 29.1 24.7 29.0 21.8 0.0 17.2
7 07.07.2013 27.8 24.2 31.6 22.9 0.2 5.2
8 08.07.2013 27.8 24.5 32.9 23.4 4.0 10.6
9 09.07.2013 25.9 23.7 31.8 22.4 7.4 5.2
10 10.07.2013 24.9 24.5 30.7 21.8 2.2 10.2
11 11.07.2013 27.0 23.2 32.6 22.3 12.4 20.2
12 12.07.2013 26.5 23.5 31.8 21.5 7.0 12.0
13 13.07.2013 27.0 23.4 32.1 22.4 4.8 4.6
14 14.07.2013 28.0 23.8 33.4 23.1 0.4 15.0
15 15.07.2013 27.0 24.1 32.6 21.8 15.0 19.5
16 16.07.2013 28.9 23.7 32.2 21.1 15.0 20.2
17 17.07.2013 24.9 23.4 33.4 23.2 20.5 0.6
18 18.07.2013 25.0 24.0 32.9 22.3 13.2 11.9
19 19.07.2013 24.8 23.0 32.1 22.1 11.0 18.4
20 20.07.2013 25.6 23.3 31.8 21.6 3.2 4.4
21 21.07.2013 24.8 23.0 34.6 23.9 5.2 9.2
22 22.07.2013 24.0 22.8 32.9 22.4 9.6 4.8
23 23.07.2013 25.0 22.4 33.8 22.1 10.0 12.9
24 24.07.2013 24.0 23.4 32.1 21.9 18.0 4.4
25 25.07.2013 25.4 22.7 33.2 23.9 10.0 8.9
26 26.07.2013 25.3 22.5 32.6 22.4 1.2 18.6
27 27.07.2013 25.8 22.4 32.1 22.1 4.7 11.8
28 28.07.2013 27.8 24.0 34.2 24.4 1.3 5.5
29 29.07.2013 28.9 24.0 33.5 23.9 0.0 2.8
30 30.07.2013 27.6 23.8 31.7 22.4 23.4 30.631 31.07.2013 27.4 24.1 31.7 22.4 30.0 6.8
277.100 386.800This Month Total Rain fall: mm 663.900
Up to previous Month Rainfall: mm 662.800
Total Rainfall: mm 1326.700
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 29
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 30
BOARD OF DIRECTORS
VICE PRESIDENT/PROJECT HEAD
GENERAL MANAGER IN HOUSE DESIGN &FINANCE (HO) MONITORING TEAM
SITE OPERATIONS PROJECTMANAGEMENT & CONTROL TEAM
CHEIF PROJECT MANAGERHIGHWAY BRIDGES
SAFETY TEAM O & M TEAM QUALITY LAOFFICERCONTROL
EPC CONTRACTOR(M/s KNR Constructions Limited)
Four Laning of Walayar - Vadakancherry Section in Kerala (Km. 182.250 to Km. 240.000 of NH-47) - Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
ORGANIZATION CHART OF SPV
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
2. Organization Chart of SPV
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 31
BOARD OF DIRECTORS
VICE PRESIDENT/PROJECT HEAD
GENERAL MANAGER IN HOUSE DESIGN &FINANCE (HO) MONITORING TEAM
SITE OPERATIONS PROJECTMANAGEMENT & CONTROL TEAM
CHEIF PROJECT MANAGERHIGHWAY BRIDGES
SAFETY TEAM O & M TEAM QUALITY LAOFFICERCONTROL
EPC CONTRACTOR(M/s KNR Constructions Limited)
Four Laning of Walayar - Vadakancherry Section in Kerala (Km. 182.250 to Km. 240.000 of NH-47) - Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
ORGANIZATION CHART OF SPV
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
3. Organization Chart of EPC Contractor
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 32
Jr. ENGINEERs – 10
CIVIL MATEs – 10
SUPERVISORs – 10
SR. ENGINEERs– 2(to be named)
STORES MANAGERMr. Ravinder Reddy
STORE ASST.s– 4
STORE CLERKs -10
AGM (MECHANICAL)
Mr. C. Rajender Reddy
PRO
ASST. LIAISONING OFFICERs -2
Sr. MECHANICAL ENGINEER(Mr. Ritesh)
Jr.MECHANICAL ENGINEERs -5
MECHANICs -20
PLANTS INCHARGEA. Tirupathi Reddy
CRUSHER INCHARGE -3
H M PLANT INCHARGE -2
BATCHING PLANT
INCHARGE -3
ACCOUNTS MANAGER
ACCOUNTANTS -3
ADMIN. & HR MANAGER
ASST. MANAGERADMIN.
WORKS CO-ORDINATOR
CAMP INCHARGE
ASST. CAMP INCHARGEs-2
SITEINCHARGEs-3
Dy. PROJECT MANAGER Mr. G. Bamhananda Reddy
CONSTRUCTION MANAGER
CONSTRUCTION MANAGER
PROJECT MANAGER -HIGHWAYSMr. M. Ramakrishna Reddy
Jr. ENGINEERs – 8
CIVIL MATEs – 8
SUPERVISORs – 10
Jr. ENGINEERs – 8
CIVIL MATEs – 8
SUPERVISORs – 10
CONSTRUCTION MANAGER -
Mr. Vinod Saga
Material Engineer1. Mr. P. Surender Reddy2. Mr. Gopinath Pathudu
QCE -3
LAB TECHNICIANs-6
LAB HELPERs -10Jr. ENGINEERs – 2
SUPERVISORs – 2
CONSTRUCTION MANAGER(to be named)
PROJECT MANAGER -STRUCTURESMr. C. H. Yakambaram
CHIEF SURVEYORMr. Vijay Kunar Pandey
ASST. SURVEYORs -2
SURVEY HELPERs -6
PROJECT HEADMr. Venugopal Reddy
EXECUTIVE DIRECTOR/PROJECT EXECUTIVE, HO (VP)
PLANNING ENGINEER
QUANTITY SURVEYOR
J. Surender Reddy
CAD ENGINEERJ. Dinesh Kumar
DATA ENTRY OPERATORs -3
SAFETY ENGINEER
SUPERVISORs – 2
SAFETY HELPERs– 6
CASTING YARD INCHARGE
Four Laning of Walayar - Vadakancherry Section in Kerala (Km. 182.250 to Km. 240.000 of NH-47) - Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
ORGANIZATION CHART OF EPC CONTRACTOR
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
4 STRIP PLAN SHOWING THE DETAILS OF PROJECT
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 33
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
5 STATUS OF LHS MAIN CARRIAGEWAY
Sl No.
ChainageLeng
th
Progress Status
From To C & G
EMB Top
SG TOP
GSB Top
WMM Top
Prime/TackCo
atDMB BC
1 182.250
183.000
0.750 0.750 2 183.0
00185.0
002.000 2.000 2.000
3 185.000
185.200
0.200 4 185.2
00186.0
000.800 0.800 0.800 0.800
5 186.000
186.200
0.200 0.200 6 186.2
00186.8
600.660 0.660 0.660 0.660
7 186.860
187.200
0.340 8 187.2
00191.4
004.200 4.200
9 191.400
191.500
0.100 10 191.5
00191.7
000.200 0.200
11 191.700
192.000
0.300 12 192.0
00192.1
000.100 0.100
13 192.100
192.300
0.200 14 192.3
00192.4
000.100 0.100
15 192.400
194.200
1.800 16 194.2
00194.7
000.500 0.500
17 194.700
194.900
0.200 18 194.9
00195.0
000.100 0.100
19 195.000
195.100
0.100 20 195.1
00195.2
000.100 0.100
21 195.200
196.000
0.800 22 196.0
00197.0
001.000 1.000
23 197.000
201.300
4.300 24 201.3
00201.4
000.100 0.100
25 201.400
203.600
2.200 26 203.6
00205.0
001.400 1.400
27 205.000
207.600
2.600 2.600 2.600 28 207.6
00208.0
000.400
29 208.000
209.100
1.100 1.100 30 209.1
00209.7
000.600 0.600 0.600
31 209.700
212.400
2.700 2.700 32 212.4
00214.2
001.800 1.800 1.800
33 214.200
214.400
0.200 0.200 34 214.4
00215.0
000.600
35 215.000
215.100
0.100 0.100 36 215.1
00215.3
000.200 0.200 0.200
37 215.300
215.600
0.300 0.300 38 215.6
00216.0
000.400
39 216.000
217.500
1.500 1.500 40 217.5
00218.2
000.700
41 218.200
218.400
0.200 0.200 0.200
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 34
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
42 218.400
219.000
0.600 0.600 43 219.0
00219.5
000.500 0.500 0.500
44 219.500
220.000
0.500 0.500 45 220.0
00220.4
000.400 0.400 0.400
46 220.400
220.900
0.500 0.500 47 220.9
00221.2
000.300 0.300 0.300
48 221.200
221.500
0.300 0.300 49 221.5
00222.0
000.500
50 222.000
222.900
0.900 0.900 51 222.9
00223.2
000.300 0.300 0.300
52 223.200
223.800
0.600 0.600 53 223.8
00226.3
002.500 2.500 2.500
54 226.300
226.400
0.100 0.100 0.100 0.100 55 226.4
00226.8
000.400 0.400 0.400
56 226.800
227.400
0.600 0.600 0.600 0.600 57 227.4
00227.9
000.500 0.500
58 227.900
228.100
0.200 59 228.1
00228.7
000.600 0.600 0.600
60 228.700
228.900
0.200 61 228.9
00229.4
000.500 0.500 0.500 0.500
62 229.400
229.600
0.200 0.200 0.200 63 229.6
00229.7
000.100
64 229.700
229.800
0.100 0.100 65 229.8
00229.9
000.100
66 229.900
230.100
0.200 0.200 0.200 67 230.1
00230.3
000.200
68 230.300
230.700
0.400 0.400 0.400 0.400 69 230.7
00231.1
000.400 0.400 0.400
70 231.100
231.300
0.200 0.200 71 231.3
00231.7
000.400
72 231.700
231.800
0.100 0.100 0.100 73 231.8
00231.9
000.100 0.100 0.100 0.100
74 231.900
232.100
0.200 0.200 75 232.1
00232.4
000.300 0.300 0.300 0.300
76 232.400
232.700
0.300 0.300 77 232.7
00232.9
000.200
78 232.900
233.200
0.300 0.300 79 233.2
00233.5
000.300 0.300 0.300
80 233.500
233.600
0.100 0.100 81 233.6
00233.7
000.100
82 233.700
233.900
0.200 0.200 83 233.9
00234.0
000.100
84 234.000
234.600
0.600 0.600 85 234.6
00235.0
000.400
86 235.000
235.200
0.200 0.200 87 235.2
00235.8
000.600 0.600 0.600
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 35
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
88 235.800
236.000
0.200 0.200 89 236.0
00236.1
350.135
Total:
38.610
17.660
3.460
6 STATUS OF RHS MAIN CARRIAGEWAY
Sl No.
ChainageLengt
h
Progress Status
From To C & G EMB Top
SG TOP
GSB Top
WMM Top
Prime/TackCo
atDMB BC
1 182.250
182.900 0.650 0.650 0.650 0.650
2 182.900
187.000 4.100 4.100 4.100
3 187.000
187.800 0.800 0.800
4 187.800
187.900 0.100
5 187.900
188.300 0.400 0.400
6 188.300
188.900 0.600 0.600 0.600 0.600
7 188.900
189.200 0.300 0.300 0.300
8 189.200
189.300 0.100 0.100
9 189.300
189.500 0.200
10 189.500
190.500 1.000 1.000 1.000 1.000
11 190.500
190.600 0.100
12 190.600
190.700 0.100 0.100 0.100 0.100
13 190.700
190.800 0.100
14 190.800
190.900 0.100 0.100 0.100
15 190.900
191.000 0.100
16 191.000
191.000 0.000 0.000 0.000
17 191.000
192.000 1.000
18 192.000
197.400 5.400 5.400 5.400
19 197.400
198.000 0.600 0.600
20 198.000
198.600 0.600 0.600 0.600
21 198.600
199.400 0.800 0.800
22 199.400
200.000 0.600
23 200.000
203.500 3.500 3.500
24 203.500
205.300 1.800
25 205.3 206.6 1.300 1.300 Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to
Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 36
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
00 0026 206.6
00207.0
00 0.400 27 207.0
00207.6
00 0.600 0.600 0.600 28 207.6
00207.9
00 0.300 29 207.9
00209.0
00 1.100 1.100 30 209.0
00209.8
00 0.800 31 209.8
00210.2
00 0.400 0.400 32 210.2
00211.4
00 1.200 1.200 1.200 1.200 33 211.4
00211.7
00 0.300 0.300 0.300 34 211.7
00212.5
00 0.800 0.800 35 212.5
00214.4
00 1.900 36 214.4
00214.7
00 0.300 0.300 37 214.7
00215.2
00 0.500 38 215.2
00216.0
00 0.800 0.800 0.800 39 216.0
00216.6
00 0.600 0.600 40 216.6
00217.2
00 0.600 0.600 0.600 41 217.2
00217.6
00 0.400 0.400 42 217.6
00218.2
00 0.600 43 218.2
00218.4
00 0.200 0.200 44 218.4
00219.2
00 0.800 45 219.2
00221.3
00 2.100 2.100 46 221.3
00221.6
00 0.300 47 221.6
00221.7
00 0.100 0.100 0.100 48 221.7
00222.0
00 0.300 49 222.0
00222.2
00 0.200 0.200 50 222.2
00222.3
00 0.100 0.100 0.100 51 222.3
00222.7
00 0.400 0.400 52 222.7
00223.0
00 0.300 0.300 0.300 53 223.0
00223.8
00 0.800 54 223.8
00224.3
00 0.500 0.500 55 224.3
00224.5
00 0.200 0.200 0.200 Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to
Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 37
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
56 224.500
224.600 0.100 0.100
57 224.600
224.900 0.300
58 224.900
225.500 0.600 0.600
59 225.500
226.000 0.500
60 226.000
226.200 0.200 0.200
61 226.200
226.400 0.200 0.200 0.200
62 226.400
227.200 0.800
63 227.200
228.300 1.100 1.100 1.100 1.100
64 228.300
228.900 0.600
65 228.900
229.600 0.700 0.700
66 229.600
230.300 0.700
67 230.300
231.000 0.700 0.700
68 231.000
232.500 1.500
69 232.500
232.700 0.200 0.200
70 232.700
233.600 0.900
71 233.600
233.900 0.300 0.300
72 233.900
234.000 0.100
73 234.000
234.200 0.200 0.200 0.200
74 234.200
236.135 1.935
Total: 35.85
018.55
0 4.650
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 38
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
7 Highway Strip Chart
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 39
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Highway Layer Wise Bar ChartKm. 182.250 – Km. 188.000
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 40
BC 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
DBM 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Shoulder 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
WMM II 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
WMM I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
GSB II 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
GSB I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
SG Top 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1
SG-2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1
SG-1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1
Embankment 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1
Excavation 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1
C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0
182
183
184
185
186
187
188
C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0
Excavation 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1
Embankment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1
SG-1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
SG-2 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
SG Top 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
GSB I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
GSB II 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
WMM I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
WMM II 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Shoulder 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
DBM 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
BC 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 1 1 0 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
189
190
191
192
193
194
0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 1 0 1 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0 0 1 0 1 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0 0 1 0 1 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 188.000 – Km. 194.000
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 41
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 0 0 0 0 0 1 1 0 1 0 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
195
196
197
198
199
200
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 194.000 – Km. 200.000
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 42
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
201
0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
201
202
203
204
205
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 200.000 – Km. 205.000
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 43
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
206
207
208
209
210
211
1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 205.000 – Km. 211.000
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 44
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0
212
213
214
215
216
217
0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0
0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0
0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 211.000 – Km. 217.000
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 45
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 0 0 1 1 1 1 1 1 0 0 0 0 0 1 1 1 1 1 0
1 1 1 1 1 1 1 1 1 1 1 0 0 1 1 1 1 1 1 0 0 0 0 0 1 1 1 1 1 0
0 0 0 0 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
218
219
220
0 0 0 0 0 1 1 1 1 1 1 0 0 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0
0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 1 1 1 1 1 0 0 0 1 1 1 1 1 1 1 1 1
0 0 0 1 1 1 1 1 0 0 0 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 0
221
222
0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 0 1 1 1 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 217.000 – Km. 222.000
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 46
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
223
224
225
226
227
228
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 222.000 – Km. 228.000
Km. 228.000 – Km. 234.000Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on
DBFOT (Toll) Basis under NHDP Phase II pg. 47
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
229
230
231
232
233
234
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
BCDBM ShoulderWMM IIWMM IGSB IIGSB ISG TopSG-2SG-1EmbankmentExcavationC&G
C&GExcavationEmbankmentSG-1SG-2SG TopGSB IGSB IIWMM IWMM IIShoulderDBM BC
Remark
LEFT SIDE
RIGHT SIDE
Chainage (KM)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
235
236
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Km. 234.000 – Km. 236.135
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 48
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
8 STATUS OF STRUCTURES Status of Pipe Culverts
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 49
Box Box Box Box
Remarks
2nd
Lift
A2
2nd
Lift
A1
1st L
iftA
21s
t Lift
A1
Hau
nch
A2
Hau
nch
A1
Raft
2nd
Lift
A2
Leve
lling
Co
urse
Exca
vatio
n
Exca
vatio
n
Leve
lling
Co
urse
L H S Box Portion BOX R H S Box Portion
Para
pet
Slab
Slab
Para
pet
2nd
Lift
A1
No Of Span
Hau
nch
A1
Hau
nch
A2
1st L
ift A
1
1st L
ift A
2
Raft
Chainage
As Per CA
As per Site
182+338 182+693 1.0x1.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1182+900 182+897 4.0x3.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1183+052 183+050 3.0x2.0 0.1 0.1184+392 183+662 1.0x1.0 0.1 0.1 0.1184+000 184+391 1.0X1.50 Re-construction
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 184+974 184+934 1.0X1.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 186+180 186+097 2.0X1.500.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 187+200 187+241 1.0X1.20 0.1 0.1
187+700 187+772 1.5X1.5 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1188+100 187+974 1.0X1.50 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1189+400 188+370 1.0X1.50 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 Re-construction189+520 189+315 1.0X1.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1189+740 189+606 1.5X1.5190+640 190+653 2.0X2.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1190+920 190+823 1.0X1.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 Re-construction191+100 191+154 1.0X1.0 Re-construction191+254 191+257 1.0X1.0191+547 191+551 1.0X1.0
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 192+349 192+352 1.0X1.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.10.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 192+490 192+493 1.0X1.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 192+940 192+982 2.0X2.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 193+240 193+322 1.0X1.0 Re-construction0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 193+421 193+422 1.0X1.0
193+620 193+624 1.0X1.0193+902 193+868 1.0X1.50 0.1 0.1194+080 193+907 1.0x1.50 0.1 0.1
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 194+764 194+767 1.0x1.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 195+031 194+990 1.0X1.50 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.10.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 195+094 195+035 1.0x1.0 0.1 0.10.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 195+420 195+096 1.0x1.20
195+520 195+401 1.0x1.0
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Status of Box Culverts
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 50
Fina
l Lift
2nd
Lift
Pipe
Lay
ing
1st L
ift
Barr
el
Porti
on
180m
mH
ead
Wal
l 15
0mm
Barr
el
Hea
d W
all
Hea
d W
ALL
Barr
el
Hea
d W
all
150m
mBa
rrel
Po
rtion
18
0mm
1st L
ift
Pipe
Lay
ing
2nd
Lift
Fina
l Lift
203+600 203+600 1 1000
206+320 206+928 1 1000
208+592 208+588 1 1000
209+376 209+373 1 1000
209+626 209+626 1 1000
209+776 209+774 1 1000
209+862 209+864 1 1000
210+017 210+013 1 1000
210+251 210+248 1 1000
210+676 210+676 1 1000
210+680 210+764 1 1000
211+306 211+303 1 1000
211+497 211+495 1 1000
211+822 211+817 1 1000
211+957 211+953 1 1000
212+184 212+181 1 1000
212+332 212+328 1 1000
212+490 212+487 1 1000
212+726 212+722 1 1000
214+120 1 1000
214+640 214+743 1 1000
219+180 219+010 1 1000
Total No. of HPC: 22
Misc
ella
neou
s Ite
ms
As Per Site
ROW
S
DIA
E Work Levelling Course
CA Chainage
Head WallE Work
L H S H P C R H S
Misc
ella
neou
s Ite
ms
Enca
sem
ent
Crad
le C
oncr
ete
Head Wall Levelling Course
Crad
le C
oncr
ete
Enca
sem
ent
196+040 195+505 1.0X1.50 Re-construction0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 196+980 196+860 1.0x1.0
197+040 196+952 1.0x1.0198+492 198+498 1.0x1.0199+580 199+585 1.0x1.0 Re-construction199+680 199+683 1.0x1.0200+111 199+937 1.0x1.0200+420 200+429 1.0x1.0
202+170 202+175 2.0x2.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 LHS Box CulvertRHS Pipe Culvert
202+480 202+492 1.0x1.0 0.1203+140 203+140 1.0x1.00204+000 204+000 1.0x1.0204+100 204+100 1.0x1.00204+200 204+192 1.0x1.0 MCW 20mtr SCW 8.5Mtr204+320 204+311 1.0x1.0 Re-construction204+820 204+823 4.0x4.80205+020 205+015 1.0x1.0 Existing Pipe205+320 205+317 1.0x1.0 Existing Pipe
205+480 205+485 1.0x1.0 Existing PipeMCW 15mtr SCW 8.5Mtr(BHS)
205+580 206+047 1.0x1.0 MCW 25mtr SCW 8.5Mtr205+960 206+518 1.0x1.0 MCW 25mtr SCW 8.5Mtr206+060 206+645 1.0x1.0 MCW 12mtr SCW 8.5Mtr(BHS)206+160 206+788 1.0x1.0 MCW 12mtr SCW 8.5Mtr(BHS)206+346 207+207 1.0x1.0 MCW 12mtr SCW 8.5Mtr(BHS)206+980 207+286 1.0x1.0 MCW 12mtr SCW 8.5Mtr(BHS)207+708 207+704 3x1.5 MCW 12mtr SCW 8.5Mtr(BHS)
0.1 0.1 207+739 207+665 1x1.20 MCW 12mtr SCW 8.5Mtr(BHS)208+144 208+141 1.0x1.0208+442 208+440 5.0x2.75210+500 Not Found
Box Box Box Box
Remarks
2nd
Lift
A2
2nd
Lift
A1
1st L
iftA
21s
t Lift
A1
Hau
nch
A2
Hau
nch
A1
Raft
2nd
Lift
A2
Leve
lling
Co
urse
Exca
vatio
n
Exca
vatio
n
Leve
lling
Co
urse
L H S Box Portion BOX R H S Box Portion
Para
pet
Slab
Slab
Para
pet
2nd
Lift
A1
No Of Span
Hau
nch
A1
Hau
nch
A2
1st L
ift A
1
1st L
ift A
2
Raft
Chainage
As Per CA
As per Site
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 51
Box Box Box Box
Remarks
2nd
Lift
A2
2nd
Lift
A1
1st L
iftA
21s
t Lift
A1
Hau
nch
A2
Hau
nch
A1
Raft
2nd
Lift
A2
Leve
lling
Co
urse
Exca
vatio
n
Exca
vatio
n
Leve
lling
Co
urse
L H S Box Portion BOX R H S Box Portion
Para
pet
Slab
Slab
Para
pet
2nd
Lift
A1
No Of Span
Hau
nch
A1
Hau
nch
A2
1st L
ift A
1
1st L
ift A
2
Raft
Chainage
As Per CA
As per Site
210+531 210+528 1.0x1.00210+610 0.1 0.1 0.1 0.1 0.1 Not Found213+886 213+883 1.5x1.5214+459 214+455 1.5x1.5214+570 214+566 1.0x2.0214+747 Not Found215+010 215+007 1.0x1.0215+179 215+175 2.5x1.5215+286 215+282 2.5x1.5
0.1 0.1 215+647 215+985 2.5x2.5215+987 215+645 1.0x1.0216+357 216+351 1.0x1.0
0.1 0.1 216+520 216+512 3.0x2.5
216+800 Re-constructionNot Found
217+018 217+011 1.0x1.0217+160 217+155 4.0x2.0217+200 217+233 1.0x1.0217+241 Not Found217+400 Not Found217+642 217+634 2.0x2.0217+711 217+704 6.6x2.5218+002 217+993 1.0x1.0 Re-construction218+293 218+286 2.5x2.0218+400 218+391 1.0x1.0 Re-construction218+586 218+579 1.5x1.5218+911 218+904 1.0x1.50219+087 218+965 1.0x1.0219+260 219+079 2.0x2.0
0.1 0.1 219+427 219+420 2.0x2.0219+510 Not Found
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 52
Box Box Box Box
Remarks
2nd
Lift
A2
2nd
Lift
A1
1st L
iftA
21s
t Lift
A1
Hau
nch
A2
Hau
nch
A1
Raft
2nd
Lift
A2
Leve
lling
Co
urse
Exca
vatio
n
Exca
vatio
n
Leve
lling
Co
urse
L H S Box Portion BOX R H S Box Portion
Para
pet
Slab
Slab
Para
pet
2nd
Lift
A1
No Of Span
Hau
nch
A1
Hau
nch
A2
1st L
ift A
1
1st L
ift A
2
Raft
Chainage
As Per CA
As per Site
219+651 219+643 1.0x2.0220+589 220+581 1.0x1.0 Re-construction220+732 220+724 1.0x1.50 Re-construction221+000 221+063 2.0x2.0221+260 221+251 1.0x1.50 Re-construction221+365 221+357 1.50x1.50221+600 221+592 2.0X1.50222+274 222+267 1.0x1.0 Re-Construction222+512 222+506 1.0x1.0222+665 222+658 1.0x3.0222+872 222+864 2.5x2.5223+370 223+363 1.50x1.0223+630 223+621 4.0x2.0224+409 224+407 1.0x1.0
0.1 0.1 224+697 224+690 1.0x2.0224+800 225+061 1.5x1.5225+257 225+251 1.5x1.5225+582 225+574 1.0x1.0225+737 225+720 4.5x2.5225+838 225+830 1.5x1.0226+015 226+008 2.0x1.5226+160 Not Found226+352 226+347 1.0x1.50 Re-Construction226+434 226+438 2.0x1.5
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 227+530 227+560 1.5x1.5 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.10.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 227+780 227+773 2.0x1.5 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.10.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 228+021 228+014 2.0x1.5 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
0.1 0.1 0.1 228+270 228+263 2.5x1.5 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.10.1 0.1 0.1 228+400 228+389 1.5x1.50.1 0.1 0.1 228+620 228+612 1.0x1.5 0.1 0.1 0.1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 53
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 54
0.1 0.1 228+660 228+650 1.5x1.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 228+775 228+769 1.5x1.0 0.1 0.1 0.10.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 229+150 229+141 1.0x2.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 229+244 229+236 1x1.50
229+572 229+563 2.5x2.0229+983 230+048 2.0x3.0230+057 229+974 1.0x1.5230+740 230+730 1.0x1.0 Re-Construction
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 231+903 231+900 1.0x1.50
232+666 232+657 1.0x1.0233+804 233+792 1.5x1.0234+400 234+365 1.0x1.5234+950 234+929 2.0x1.5235+250 Not Found235+410 235+474 1.0x1.0235+590 235+585 1.0x1.0235+633 235+795 1.0x1.50235+807 Not Found
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Status of VUPs & PUPs
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 55
0.1 0.1 228+660 228+650 1.5x1.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 228+775 228+769 1.5x1.0 0.1 0.1 0.10.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 229+150 229+141 1.0x2.00.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 229+244 229+236 1x1.50
229+572 229+563 2.5x2.0229+983 230+048 2.0x3.0230+057 229+974 1.0x1.5230+740 230+730 1.0x1.0 Re-Construction
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 231+903 231+900 1.0x1.50
232+666 232+657 1.0x1.0233+804 233+792 1.5x1.0234+400 234+365 1.0x1.5234+950 234+929 2.0x1.5235+250 Not Found235+410 235+474 1.0x1.0235+590 235+585 1.0x1.0235+633 235+795 1.0x1.50235+807 Not Found
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
Excavation 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1 0.1 0.1
2nd Lift 0.1 0.1 0.1
3rd Lift
Abutment Cap
Dirt Wall
Slab
Excavation 0.1 0.1 0.1 0.1 0.1
Levelling Course 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1
2nd Lift 0.1
3rd Lift
Abutment Cap
Dirt Wall
Slab
4 4
MCWStage of works
197+727 (VUP) 209+076 (VUP) 217+500 (VUP) 235+000 (VUP) 187+350 (PUP) 216+337 (PUP) 222+622 (PUP) 223+530 (PUP)
A1
MCW REWALL
REWALL MCW RE
WALL MCW REWALL MCW RE
WALLMCW REWALL MCWMCW RE
WALLRE
WALL
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Status of Minor Bridges
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 56
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
Excavation 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1 0.1 0.1
2nd Lift 0.1 0.1 0.1
3rd Lift
Abutment Cap
Dirt Wall
Slab
Excavation 0.1 0.1 0.1 0.1 0.1
Levelling Course 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1
2nd Lift 0.1
3rd Lift
Abutment Cap
Dirt Wall
Slab
4 4
MCWStage of works
197+727 (VUP) 209+076 (VUP) 217+500 (VUP) 235+000 (VUP) 187+350 (PUP) 216+337 (PUP) 222+622 (PUP) 223+530 (PUP)
A1
MCW REWALL
REWALL MCW RE
WALL MCW REWALL MCW RE
WALLMCW REWALL MCWMCW RE
WALLRE
WALL
MCW MCW MCW SWC SWC MCW MCW MCW MCW SCW SCW MCW MCW MCW MCW SCW SCW MCW SCW
RHS RHS LHS LHS RHS LHS RHS RHS RHS LHS RHS RHS LHS RHS LHS LHS RHS LHS RHS
Excavation 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
2nd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
3rd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Final Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Abutment Cap --------- 0.1 -------- 0.1 -------- 0.1 -------- 0.1 -------- -------- 0.1 -------- -------- -------- --------
Dirt Wall --------- -------- -------- -------- -------- -------- -------- -------- -------- --------
Excavation 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1
2nd Lift 0.1 0.1
3rd Lift
Final Lift -------- -------- -------- -------- -------- -------- -------- -------- --------
Pier Cap -------- -------- -------- -------- -------- -------- -------- -------- --------
Excavation 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1
2nd Lift 0.1 0.1
3rd Lift
Final Lift -------- -------- -------- -------- -------- -------- -------- -------- --------
Pier Cap -------- -------- -------- -------- -------- -------- -------- -------- --------
Excavation 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
2nd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
3rd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Final Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Abutment Cap 0.1 -------- 0.1 -------- 0.1 -------- 0.1 -------- -------- -------- -------- -------- --------
Dirt Wall -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab A1 To P1 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab A1 To A2 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab P1 To P2 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab P1 To A2 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab P2 To A2 -------- -------- -------- -------- -------- -------- -------- -------- --------
222+156 (MNB)
Stage of works
190+970 (MNB) 194+470 (MNB)
M.W
ALL
M.W
ALL
182+237 (MNB)
M.W
ALL
201+295 (MNB) 224+895 (MNB) 235+180
(MNB)204+680(MNB)
209+950 (MNB) 213+160 (MNB) 214+272
(MNB)219+562 (MNB)
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
A1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Status of Major Bridges
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 57
MCW MCW MCW SWC SWC MCW MCW MCW MCW SCW SCW MCW MCW MCW MCW SCW SCW MCW SCW
RHS RHS LHS LHS RHS LHS RHS RHS RHS LHS RHS RHS LHS RHS LHS LHS RHS LHS RHS
Excavation 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
2nd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
3rd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Final Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Abutment Cap --------- 0.1 -------- 0.1 -------- 0.1 -------- 0.1 -------- -------- 0.1 -------- -------- -------- --------
Dirt Wall --------- -------- -------- -------- -------- -------- -------- -------- -------- --------
Excavation 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1
2nd Lift 0.1 0.1
3rd Lift
Final Lift -------- -------- -------- -------- -------- -------- -------- -------- --------
Pier Cap -------- -------- -------- -------- -------- -------- -------- -------- --------
Excavation 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1
2nd Lift 0.1 0.1
3rd Lift
Final Lift -------- -------- -------- -------- -------- -------- -------- -------- --------
Pier Cap -------- -------- -------- -------- -------- -------- -------- -------- --------
Excavation 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Levellling Course 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Raft 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
1st Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
2nd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
3rd Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Final Lift 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Abutment Cap 0.1 -------- 0.1 -------- 0.1 -------- 0.1 -------- -------- -------- -------- -------- --------
Dirt Wall -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab A1 To P1 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab A1 To A2 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab P1 To P2 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab P1 To A2 -------- -------- -------- -------- -------- -------- -------- -------- --------
Slab P2 To A2 -------- -------- -------- -------- -------- -------- -------- -------- --------
222+156 (MNB)
Stage of works
190+970 (MNB) 194+470 (MNB)
M.W
ALL
M.W
ALL
182+237 (MNB)
M.W
ALL
201+295 (MNB) 224+895 (MNB) 235+180
(MNB)204+680(MNB)
209+950 (MNB) 213+160 (MNB) 214+272
(MNB)219+562 (MNB)
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
M.W
ALL
A1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Details of Girders & Planks
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 58
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Abut
men
t Cap
Dirt
Wal
l
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Abut
men
t Cap
Dirt
Wal
l
Slab
A1 T
o P1
Slab
P1 T
o P2
Slab
P2 T
o P3
Slab
P3 T
o A2
MCW LHS 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
0.1 0.1 0.1 ------
------
------
------
------
------
------
------
------
------
------
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Abut
men
t Cap
Dirt
Wal
l
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
MCW LHS 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
------
------
------
------
------
------
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Pier
Cap
Exca
vatio
n
Leve
lllin
g Co
urse
Raft
1st L
ift
2nd
Lift
3rd
Lift
4th
Lift
5th
Lift
Fina
l Lift
Abut
men
t Cap
Dirt
Wal
l
Slab
A1 t
o P1
Slab
P1 t
o P2
Slab
P2 t
o P3
Slab
P3 t
o P4
Slab
P4 t
o P5
Slab
P5 t
o P6
Slab
P6 t
o P7
Slab
P7 t
o A2
MCW LHS 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
------
------
------
------
------
------
------
------
------
------
------
------
------
P6 P7
P1 P2 P3 P4
P5 A2
Stage of works
P1 P2
Stage of works
198+
870 (
MJB
)20
7+90
0 (M
JB)
MEDIAN WALL
P3 A2A1
MEDIAN WALL
A1
Stage of works
207+
900 (
MJB
)
MEDIAN WALL
Sl.No Designed Chainage
Length of Span in Mtrs
Length of Girder/ Plank in
Mtrs
Height of Girder/ Plank in
Mtrs
Side Service Road
Type of Structure
No of Spans
No of Girders/Planks
per Span
Total Girders Completed Balance Total
Planks Completed BalanceNo of
PSC Box Girders
Strands MT
Type of
Cable
Anchorages Dead End
Nos
Anchorages Live End
Nos
Round Sheating
HDPE RMT
Flat Sheating
HDPE RMT
1 198+870 26.60 25.90 1.625 LHS PSC Girder 4 4 16 15 1 - - - - 19.0 12T13 80 80 21742 207+900 21.40 20.00 1.325 LHS PSC Girder 8 4 32 16 16 - - - - 24.5 12T13 128 128 2833
1 182+237 9.15 9.15 0.40 PSC Plank 3 10 - - - 30 0 30 2.43 5T15 40 40 4902 190+970 16.50 16.10 1.075 RHS PSC Girder 1 4 4 4 0 - - - - 1.75 12T13 12 12 2073 194+490 22.00 21.60 1.325 LHS PSC Girder 1 4 4 4 0 - - - - 3.10 12T13 16 16 355
194+490 22.00 21.60 1.325 B/ S PSC Girder 1 3 6 0 6 - - - - 4.64 12T13 24 24 5324 201+295 11.20 11.20 0.40 LHS PSC Plank 1 10 10 8 2 2.43 5T15 40 40 4905 204+680 21.40 21.00 1.325 RHS PSC Girder 1 4 4 4 0 - - - - 3.10 12T13 16 16 3556 209+950 13.00 13.00 0.40 PSC Plank 2 10 20 4 16 5.65 5T15 80 80 11407 213+160 20.00 19.60 1.325 PSC Girder 1 4 4 0 4 - - - - 3.06 12T13 16 16 3558 214+272 13.50 13.50 0.45 PSC Plank 1 10 - - - 10 0 10 3.90 5T15 50 50 7409 219+570 9.00 9.00 0.35 LHS PSC Plank 1 10 - - - 10 7 3 5T1510 222+165 9.00 9.00 0.35 RHS PSC Plank 3 10 - - - 30 10 20 5T1511 224+902 16.40 16.00 1.075 LHS PSC Girder 3 4 12 0 12 - - - - 5.30 12T13 36 36 619
224+902 16.40 16.00 1.075 B/ S PSC Girder 3 3 18 0 18 - - - - 7.95 12T13 54 54 92812 235+180 16.40 16.00 1.075 PSC Girder 3 4 12 0 12 - - - - 5.30 12T13 36 36 619
235+180 16.40 16.00 1.075 RHS PSC Girder 3 3 9 0 9 - - - - 7.95 12T13 27 27 464
1 187+350 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 11402 216+400 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 11403 222+680 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 11404 223+300 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 1140
1 197+730 17.50 17.00 1.075 B/ S PSC Girder 1 4 8 8 0 - - - - 5.10 12T13 32 32 5802 209+076 13.20 13.20 RHS PSC Plank 1 10 - - - 10 0 10 -3 211+310 25.00 24.60 1.625 B/ S PSC Girder 1 4 8 0 8 - - - - 9.35 12T13 40 40 10954 235+000 17.50 17.00 1.075 B/ S PSC Girder 1 4 8 0 8 - - - - 5.10 12T13 32 32 580
1 209+000 28.00 RHS PSC Girder 1 5 5 0 5 - - - -
1 203+900 25.00 1.625 PSC Girder 14 4 56 0 56 - - - - 65.30 12T13 280 280 7645203+900 60.00 3.60 BOX Girder 1 1 - - - - - - 1
2 225+507 25.00 1.625 B/ S PSC Girder 14 4 112 0 112 - - - - 130.60 12T13 560 560 15290225+507 45.00 2.50 B/ S BOX Girder 1 1 - - - - - - 2
318 51 267 200 29 171 3
MAJOR BRIDGE
MINOR BRIDGE
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
9. ACHIEVEMENT AGAINST SCOPE OF WORK
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 59
Sl.No Designed Chainage
Length of Span in Mtrs
Length of Girder/ Plank in
Mtrs
Height of Girder/ Plank in
Mtrs
Side Service Road
Type of Structure
No of Spans
No of Girders/Planks
per Span
Total Girders Completed Balance Total
Planks Completed BalanceNo of
PSC Box Girders
Strands MT
Type of
Cable
Anchorages Dead End
Nos
Anchorages Live End
Nos
Round Sheating
HDPE RMT
Flat Sheating
HDPE RMT
1 198+870 26.60 25.90 1.625 LHS PSC Girder 4 4 16 15 1 - - - - 19.0 12T13 80 80 21742 207+900 21.40 20.00 1.325 LHS PSC Girder 8 4 32 16 16 - - - - 24.5 12T13 128 128 2833
1 182+237 9.15 9.15 0.40 PSC Plank 3 10 - - - 30 0 30 2.43 5T15 40 40 4902 190+970 16.50 16.10 1.075 RHS PSC Girder 1 4 4 4 0 - - - - 1.75 12T13 12 12 2073 194+490 22.00 21.60 1.325 LHS PSC Girder 1 4 4 4 0 - - - - 3.10 12T13 16 16 355
194+490 22.00 21.60 1.325 B/ S PSC Girder 1 3 6 0 6 - - - - 4.64 12T13 24 24 5324 201+295 11.20 11.20 0.40 LHS PSC Plank 1 10 10 8 2 2.43 5T15 40 40 4905 204+680 21.40 21.00 1.325 RHS PSC Girder 1 4 4 4 0 - - - - 3.10 12T13 16 16 3556 209+950 13.00 13.00 0.40 PSC Plank 2 10 20 4 16 5.65 5T15 80 80 11407 213+160 20.00 19.60 1.325 PSC Girder 1 4 4 0 4 - - - - 3.06 12T13 16 16 3558 214+272 13.50 13.50 0.45 PSC Plank 1 10 - - - 10 0 10 3.90 5T15 50 50 7409 219+570 9.00 9.00 0.35 LHS PSC Plank 1 10 - - - 10 7 3 5T1510 222+165 9.00 9.00 0.35 RHS PSC Plank 3 10 - - - 30 10 20 5T1511 224+902 16.40 16.00 1.075 LHS PSC Girder 3 4 12 0 12 - - - - 5.30 12T13 36 36 619
224+902 16.40 16.00 1.075 B/ S PSC Girder 3 3 18 0 18 - - - - 7.95 12T13 54 54 92812 235+180 16.40 16.00 1.075 PSC Girder 3 4 12 0 12 - - - - 5.30 12T13 36 36 619
235+180 16.40 16.00 1.075 RHS PSC Girder 3 3 9 0 9 - - - - 7.95 12T13 27 27 464
1 187+350 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 11402 216+400 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 11403 222+680 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 11404 223+300 12.00 12.00 0.50 B/ S PSC Plank 1 10 - - - 20 0 20 - 6.30 5T15 80 80 1140
1 197+730 17.50 17.00 1.075 B/ S PSC Girder 1 4 8 8 0 - - - - 5.10 12T13 32 32 5802 209+076 13.20 13.20 RHS PSC Plank 1 10 - - - 10 0 10 -3 211+310 25.00 24.60 1.625 B/ S PSC Girder 1 4 8 0 8 - - - - 9.35 12T13 40 40 10954 235+000 17.50 17.00 1.075 B/ S PSC Girder 1 4 8 0 8 - - - - 5.10 12T13 32 32 580
1 209+000 28.00 RHS PSC Girder 1 5 5 0 5 - - - -
1 203+900 25.00 1.625 PSC Girder 14 4 56 0 56 - - - - 65.30 12T13 280 280 7645203+900 60.00 3.60 BOX Girder 1 1 - - - - - - 1
2 225+507 25.00 1.625 B/ S PSC Girder 14 4 112 0 112 - - - - 130.60 12T13 560 560 15290225+507 45.00 2.50 B/ S BOX Girder 1 1 - - - - - - 2
318 51 267 200 29 171 3
MAJOR BRIDGE
MINOR BRIDGE
107.77 107.77 107.77 107.77 107.77 107.77 107.77 107.77 22 143 4 4 12 2 318 200 660000
74.46 36.210 8.110 0.000 0.000 0.000 0.000 0.000 8 26 0 0 0 0 49 26 46143
35.38 23.190 0.36 0.000 0.000 0.000 0.000 0.000 8 5 0 0 0 0 35 26 35134
69% 34% 8% 0% 0% 0% 0% 0% 36% 18% 0% 0% 0% 0% 15% 13% 7%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
C&G EMB TOP Sub Grade GSB WMM DBM,1st Layer
DBM,2nd Layer
BC PipeCulverts
BoxCulverts
PUP VUP MinorBridges
MajorBridges
Girders Plank s RE WallBlocks
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
10 “S” CURVE
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 60
107.77 107.77 107.77 107.77 107.77 107.77 107.77 107.77 22 143 4 4 12 2 318 200 660000
74.46 36.210 8.110 0.000 0.000 0.000 0.000 0.000 8 26 0 0 0 0 49 26 46143
35.38 23.190 0.36 0.000 0.000 0.000 0.000 0.000 8 5 0 0 0 0 35 26 35134
69% 34% 8% 0% 0% 0% 0% 0% 36% 18% 0% 0% 0% 0% 15% 13% 7%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
C&G EMB TOP Sub Grade GSB WMM DBM,1st Layer
DBM,2nd Layer
BC PipeCulverts
BoxCulverts
PUP VUP MinorBridges
MajorBridges
Girders Plank s RE WallBlocks
77.00 78.00 79.00 80.00 81.00 82.00 83.00 84.00 85.00 86.00 87.00 88.00 89.00 90.00 91.00 92.00 93.00 94.00 95.00 96.00 97.00 98.00 99.00 100.00 101.00 102.00 103.00 104.00 105.00 106.00 107.00 108.00
Month
COMMENCEMENT DATE 18-May-2013 Concessionare : KNR Walayar Tollways Private Limited. CONSTRUCTION PERIOD 910 Days
AGREEMENT DATE 17-Sep-2013 Four Laning of Walayar - Vadakancherry Section in Kerala Km. 182.250 (Design Chainage Km. 182.250) to Km. 240.000 (Design Chainage Km. 236.135) of NH-47 –Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II CONCESSION PERIOD 20 Yrs
EPC : K N R Constructions Ltd. CONTRACT AMOUNT IN Lac Rs: 79050.00
Mile Stone -1 ( 180 Days) 10% (Fn) : 13/Nov/2013 Mile Stone-2 (400 Days) 35%(Fn) : 21/Jun/2014 Mile Stone-3 (650 Days) 70% (Fn) : 26/Feb/2015 Mile Stone-4 (910 Days) 100% Length : 14/Nov/2015
TARGET / COMPLETION DATE 13-Nov-2015
0.00 0.51 1.49 2.
99 5.32 7.
73 10.3
9
13.2
1
16.4
6
19.8
1
23.1
9
26.8
4
30.0
1
33.4
7
35.8
7
38.7
0
41.9
1 48.1
3 54.3
8 60.3
2 66.4
8 72.1
3 77.7
4 82.4
7 87.2
7
90.9
0
92.9
7
95.4
3
97.3
0
99.5
4
99.9
7
100.
00
0
3.31 6.11 11
.37
0
10
20
30
40
50
60
70
80
90
100
110
Apr
-13
May
-13
Jun-
13
Jul-1
3
Aug
-13
Sep
-13
Oct
-13
Nov
-13
Dec
-13
Jan-
14
Feb-
14
Mar
-14
Apr
-14
May
-14
Jun-
14
Jul-1
4
Aug
-14
Sep
-14
Oct
-14
Nov
-14
Dec
-14
Jan-
15
Feb-
15
Mar
-15
Apr
-15
May
-15
Jun-
15
Jul-1
5
Aug
-15
Sep
-15
Oct
-15
Nov
-15
Cum
ulat
ive w
ork
%
Month
MS-2 (35%) 21/Jun/2012
MS-3 (70%) 26/Feb/15
MS-1 (10%) 13/Nov/13
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 61
77.00 78.00 79.00 80.00 81.00 82.00 83.00 84.00 85.00 86.00 87.00 88.00 89.00 90.00 91.00 92.00 93.00 94.00 95.00 96.00 97.00 98.00 99.00 100.00 101.00 102.00 103.00 104.00 105.00 106.00 107.00 108.00
Month
COMMENCEMENT DATE 18-May-2013 Concessionare : KNR Walayar Tollways Private Limited. CONSTRUCTION PERIOD 910 Days
AGREEMENT DATE 17-Sep-2013 Four Laning of Walayar - Vadakancherry Section in Kerala Km. 182.250 (Design Chainage Km. 182.250) to Km. 240.000 (Design Chainage Km. 236.135) of NH-47 –Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II CONCESSION PERIOD 20 Yrs
EPC : K N R Constructions Ltd. CONTRACT AMOUNT IN Lac Rs: 79050.00
Mile Stone -1 ( 180 Days) 10% (Fn) : 13/Nov/2013 Mile Stone-2 (400 Days) 35%(Fn) : 21/Jun/2014 Mile Stone-3 (650 Days) 70% (Fn) : 26/Feb/2015 Mile Stone-4 (910 Days) 100% Length : 14/Nov/2015
TARGET / COMPLETION DATE 13-Nov-2015
0.00 0.51 1.49 2.
99 5.32 7.
73 10.3
9
13.2
1
16.4
6
19.8
1
23.1
9
26.8
4
30.0
1
33.4
7
35.8
7
38.7
0
41.9
1 48.1
3 54.3
8 60.3
2 66.4
8 72.1
3 77.7
4 82.4
7 87.2
7
90.9
0
92.9
7
95.4
3
97.3
0
99.5
4
99.9
7
100.
00
0
3.31 6.11 11
.37
0
10
20
30
40
50
60
70
80
90
100
110
Apr
-13
May
-13
Jun-
13
Jul-1
3
Aug
-13
Sep
-13
Oct
-13
Nov
-13
Dec
-13
Jan-
14
Feb-
14
Mar
-14
Apr
-14
May
-14
Jun-
14
Jul-1
4
Aug
-14
Sep
-14
Oct
-14
Nov
-14
Dec
-14
Jan-
15
Feb-
15
Mar
-15
Apr
-15
May
-15
Jun-
15
Jul-1
5
Aug
-15
Sep
-15
Oct
-15
Nov
-15
Cum
ulat
ive w
ork
%
Month
MS-2 (35%) 21/Jun/2012
MS-3 (70%) 26/Feb/15
MS-1 (10%) 13/Nov/13
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
12 PHOTOGRAPHS
Cement Specific Gravity testing Cube testing checked by PD, NHAI & IE
Cubes Testing checked by Manager (T), NHAI & IE Flexural Beam Testing checked by IE
Results Checking by Manager (T), NHAI & IE Grouting Cube Casting Cchecked by IE
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 62
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Project Informatory Board @ Start Point of the Package, Km. 182+250
Project Informatory Board @ End Point of the Package, Km. 236+135
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 63
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Casting of PSC Planks @ Minor Bridge, Casting of PSC Girders at Major Bridge,Km. 222.165 Km. 198+870
Casting of PSC Planks @ Minor Bridge, Casting of PSC Planks @ Minor Bridge,Km. 201+295 Km. 219+570
Casting of PSC Girders at VUP, Km. 197+730
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 64
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U L Y 2 0 1 3
Display of Speed Limit and other informatory Boards on Highway
Pot Hole Filling due to Heavy Rains along the Project Highway
PQC Mix Design Flexural Testing Concrete Mix Design Cubes Compacting through Vibrating Table
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II pg. 65