Sustainable Energy Sustainable Energy IrelandIreland
Exploiting the Resource
David Raubenheimer
March 2004
![Page 2: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/2.jpg)
2
Fibrowatt OverviewFibrowatt Overview
• Developer owner operator• Power from agricultural residues• 65 MW operational• 2,650,000 MWh produced, 3.7
million tonnes fuel• Overview of Fibrowatt’s plants
![Page 3: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/3.jpg)
3
NUTRIENTS
CARBON (CO2)
Flue Gases
Ash
ELECTRICITY
EN
ER
GY
BIOMASSBEDDING
& FEED
MANURE
The Carbon CycleThe Carbon Cycle
![Page 4: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/4.jpg)
4
Power StationsPower Stations
Power Station
Company MW Location
Eye (World’s first)
Fibropower 12.7MW Suffolk
Glanford Fibrogen 13.5MW N Lincs
Thetford Fibrothetford 38.5MW Norfolk
![Page 5: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/5.jpg)
FibropowerFibropower
Commissioned Jul 1992 Design output 12.7MW
Burns 150,000 t/yr of poultry litter & other biomass
![Page 6: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/6.jpg)
6
Fibropower - Operational Fibropower - Operational ExperienceExperience
• Development of know-how• Fuel characterisation difficult• Biomass knowledge fragmented• No available standards• Now runs exceptionally well• New fuels trialled
![Page 7: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/7.jpg)
FibrogenFibrogen
Commissioned Nov 1993Design output 13.5MW
3-5 yr Govt contract for 85,000 t/yr of meat & bone meal
![Page 8: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/8.jpg)
8
FibrogenFibrogen
• Commercially similar to Fibropower
• 8% larger• New fuel handling – design trials• Technically very successful• Achieves 90 – 100% availability• Converted to burn MBM
![Page 9: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/9.jpg)
FibrothetfordFibrothetford
Commissioned 1998 Design output 38.5MWBurns 460,000 t/yr of poultry litter & other biomass
![Page 10: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/10.jpg)
10
FibrothetfordFibrothetford
• Significant scale up – 3x• New fuel storage – design trial• Environmentally sensitive site• Environmental standards changed• Construction contractors more
cautious• Scale up caused technical
problems• Now running well
![Page 11: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/11.jpg)
11
How it Works – How it Works – in the plantin the plant
![Page 12: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/12.jpg)
12
Technology – Current Technology – Current PlantsPlants
Fibropower Fibrogen Fibrothetford
Fuel Handling Cranes Cranes Augers/Conveyors
Fuel Feeding Mass Pneumatic Air Distributor
Grate Reciprocating Chain Grate Chain Grate
Boiler ‘Folded’ ‘Folded’ Bi-Drum
Balance Conventional Conventional Conventional – Ash more complex
Emissions Control
Electrostatic Precipitator
Bag Filter/
Semi dry scrubber
Bag Filter/
Dry line injection
Steam Conditions - 65 Bar, 450°C to 475°C – all plants
![Page 13: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/13.jpg)
13
Fuel Pits at FibrogenFuel Pits at Fibrogen
![Page 14: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/14.jpg)
14
Thetford Fuel HallThetford Fuel Hall
![Page 15: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/15.jpg)
15
Fuel Trucks UnloadingFuel Trucks Unloading
![Page 16: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/16.jpg)
16
Fibrogen - MBM Fibrogen - MBM ConversionConversion
![Page 17: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/17.jpg)
17
Inside Inside the the
BoilerBoiler
![Page 18: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/18.jpg)
18
Technology - ResultsTechnology - Results
• Poultry litter burns very well• Characterisation is difficult• Handling needs care• Combustion performance• Certain arrangements excluded
![Page 19: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/19.jpg)
19
Technologies ReviewedTechnologies Reviewed
• Have reviewed a number• Stepwise development strategy• Fluidised Bed• Gasification• Digestion• High tech may be
counterproductive
![Page 20: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/20.jpg)
20
What a Project NeedsWhat a Project Needs
• Available, contactable & characterised fuel supply
• Affordable electrical connection• €4+ million to develop• 2 - 5 yrs development, 2 yrs
construction• Incentivised construction
contractors• Available land and local support
![Page 21: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/21.jpg)
21
What a Project Needs (2)What a Project Needs (2)
• Power Purchase Agreement– Bankable
– Long term (construction +15 years)
– Technology specific
• Ash fertiliser sales routes• Abundant political support
![Page 22: Sustainable Energy Ireland](https://reader035.fdocuments.us/reader035/viewer/2022062217/56814930550346895db67196/html5/thumbnails/22.jpg)
22
SummarySummary
• 2,650,000 MWh• 3,700,000 tonnes of fuel • Significant teething problems
overcome• Structure new market with care• Particularly the Power Sale
arrangements• Consistent and broad political
support