Successful Instrument and Control System Design

download Successful Instrument and Control System Design

of 16

Transcript of Successful Instrument and Control System Design

  • 8/4/2019 Successful Instrument and Control System Design

    1/16

    2011/6/26

    1

    Successful Instrument and ControlSuccessful Instrument and Control

    System DesignSystem Design

    Part III (3/3) Ch 15 to 18

    8th-Jul-2011

    AgendaAgenda

    Chapter 15 Panel Arrangement

    Chapter 16 Procurement

    Chapter 17Quality Control

    The Integrated Design Check

    Chapter 18 Phase Three

    Construction Support

  • 8/4/2019 Successful Instrument and Control System Design

    2/16

    2011/6/26

    2

    Chapter 15Chapter 15 Panel ArrangementPanel Arrangement

    Panel arrangement drawings accomplish

    several things:

    Contents and placement of front-panel equipment

    such as control switches and lights.

    Contents and placement of back-panel equipment.

    Contents of any engraved labels.

    Bill of material for each item.

    The external enclosure to be sized with confidence.

    Panel Arrangement SamplePanel Arrangement Sample

    Graphic detail should be minimized, and no wiring detail need

    to be included.

  • 8/4/2019 Successful Instrument and Control System Design

    3/16

    2011/6/26

    3

    Arrange a Junction Box DrawingArrange a Junction Box Drawing

    Set up a scale

    Metric units or Imperial units

    Design the panel

    How many terminals are needs?

    What kinds of terminals should be used?

    Most specifications require 50% spare capacity on a

    new installation.

    Explosion proof and enclosure protection.

    Arrange a Junction Box DrawingArrange a Junction Box Drawing

    For each item, place at least one bubble and leader. And

    generate a bill of materials on the left side of graphic.

    Generate a Bill of Materials

  • 8/4/2019 Successful Instrument and Control System Design

    4/16

    2011/6/26

    4

    Field Panel SampleField Panel Sample

    Leaving a minimum of 1.5 inches

    between a terminal and adjacent

    wiring duct is good practice.

    The space for cable entry shall be

    consider.

    SummarySummary

  • 8/4/2019 Successful Instrument and Control System Design

    5/16

    2011/6/26

    5

    Chapter 16Chapter 16 ProcurementProcurement A design package is built from the conceptual

    to the actual andprocurementis about as

    actual as it gets.

    A frequent lament from the construction

    partner is How can I build something if I

    dont have the parts

    Primarily two types of material are specifiedby the I&C design team:

    Electrical material

    Mechanical material

    Bulk MaterialsBulk Materials

    Electrical material

    Including cable, conduit, enclosure, and termination

    hardware.

    Mechanical material

    Including pneumatic tubing, flanges gaskets, and

    mounting brackets.

    These types of materials are called bulk materials.

    Instruments, items that require long lead time for

    manufacture, or other equipment items that require

    individual specifications do not fall into the bulk

    materials category.

  • 8/4/2019 Successful Instrument and Control System Design

    6/16

    2011/6/26

    6

    Typical Purchasing CycleTypical Purchasing Cycle

    When a design is nearly complete, the design

    team begins whats called a takeoff.

    Someone begins building lists of materials for

    purchase. These lists are called bill of

    materials (B/M, or BOM.)

    The BOM is a document that lists all the

    materials required for construction. On large projects, it is critical that each BOM

    be given a unique designation and that a bill of

    materials index be maintained.

    Typical Purchasing CycleTypical Purchasing Cycle

    Once a bill of materials is produced, they are given to the

    purchasing department. Purchasing pares the material,

    reorganizing it according to vendor. A purchase order (PO) is

    then produced for each vendor.

  • 8/4/2019 Successful Instrument and Control System Design

    7/16

    2011/6/26

    7

    Material ClassificationMaterial Classification

    Bulk materials can be stored in bulkor in

    detail.

    The materials on the bulk bill of materials are

    nonspecific materials.For example: cable, conduit, conduit fitting, cable tray, bolts &

    nuts and hookup wiring.

    The detail bill of materials is for Bulk materials that

    have specific uses as shown on detail drawings.

    For example: most instrument, and instrument fitting.

    Bulk materials TakeoffBulk materials Takeoff

    Cost-effective

    Most vendors allow quantity discounts. The amounts

    of these discounts very as the quantity rises, so it is

    desirable to make large orders. Wastage and contingencies

    We must always allow for wastage as the excess ends

    will be clipped and disposed. We usually allow for at

    least 20% wastage, plus about another 5-10% for

    contingencies.

    Takeoff quantity * 1.25 = Procured quantity

  • 8/4/2019 Successful Instrument and Control System Design

    8/16

    2011/6/26

    8

    Bulk materials TakeoffBulk materials Takeoff

    SummarySummary

  • 8/4/2019 Successful Instrument and Control System Design

    9/16

    2011/6/26

    9

    Chapter 17Chapter 17Quality ControlQuality Control The Integrated Design CheckThe Integrated Design Check Having progressed to the end of the design

    phase, it is now necessary to validate the work

    before sending it to the field to be built.

    If the design events are properly logged as theyare executed, then the design check at the end is

    much easier and much time will be saved.

    Goal of design check Zero defects will not occur

    No showstoppers or major problem will stop the

    construction effort.

    CheckpointsCheckpoints

    There are few specific issue to consider in

    terms of establishing checkpoints. Two

    different points of view need to be consider:

    administrative and technical.Administrative content Individual Checks

    Technical content Squad Check

    Squad check roster

    Design check summary

  • 8/4/2019 Successful Instrument and Control System Design

    10/16

    2011/6/26

    10

    Administrative contentAdministrative content Individual ChecksIndividual Checks

    Non-technical experts should be designated to

    page through the document set to check for

    specific appearance aspects:

    Is the title block correct in terms of drawing number,

    revision level, and title?

    Are the proper project data in place?

    Are the proper initials in place? Designed, check, and

    so on.

    Are notes legible and grammatically complete?

    Technical contentTechnical content Squad CheckSquad Check

    Do the instrument specifications reflect the intent of

    the P&ID, and will they meet the scope

    requirements?

    Do the elementaries reflect the intent of the

    instrument specs and the P&ID?

    Do the wiring diagram reflect the intent of the

    elementaries?

    Do the BOM reflect the needs presented on process

    plans and cabinet arrangement?

    Are all these properly reflected in the instrument

    database?

  • 8/4/2019 Successful Instrument and Control System Design

    11/16

    2011/6/26

    11

    Technical contentTechnical content Squad CheckSquad Check

    The revised drawing should always be attached to its

    original markup to retain the document trail.

    When the design check is complete, the markups

    should be rescued and stored. They should be

    retained for one year after plant startup.

    In CTCI I&C department principle:

    Using design input/output check sheet.

    Squad check rosterSquad check roster

    Who should be on squad-check team?

    For the most part, the design team itself.

    If possible, the members not check their own work.

    Rotating the personnel away from their own work does acouple of good things:

    First, it makes sense. If a mistake was made once, it will

    probably be missed if the same person look at it again.

    Another benefit is the cross-training aspect.

    One other addition to the squad should be an

    experienced outsider. (AE)

  • 8/4/2019 Successful Instrument and Control System Design

    12/16

    2011/6/26

    12

    Design check summaryDesign check summary

    All the designers prepare for the check by

    logging their progress in the database, by

    keeping a personal log of potential problems

    to watch out for, and by communicating with

    each other. At the end of the project, the

    database can be used as a checking tool that

    streamlines the squad-check process andmaximizes the effectiveness of the time spent

    in its execution.

    summarysummary

  • 8/4/2019 Successful Instrument and Control System Design

    13/16

    2011/6/26

    13

    Chapter 18Chapter 18Phase ThreePhase Three Construction SupportConstruction Support

    Phase two has ended, and phase three has

    begun (E C)

    The designers may be able to spend some extra time

    on-site with the constructor as well. Construction

    support and support during checkout and startup are

    key to the success of the design team as a whole.

    If the designers are in the field and known to be

    helpful, then perceptions will be enhanced all

    around.

    Construction SupportConstruction Support

    There are two kinds of construction support:

    on-site and off-site. It is a good idea to

    determine ahead of time the periods that are

    critical for on-site support and have people

    available continuously through those periods.Otherwise, having someone on call off-site is

    usually acceptable.

    The construction phase breaks down into

    several periods, each with a different set of

    needs in terms of the design team.

  • 8/4/2019 Successful Instrument and Control System Design

    14/16

    2011/6/26

    14

    Construction Phase PeriodsConstruction Phase Periods

    Kickoff Meeting:

    Each construction activity should begin with a kickoff

    meeting. At this meeting, the phase-three lead for

    the design team should present the package. The

    presentation should cover, at a minimum, the

    following topics:1. Bill of material

    2. Design overview

    3. Off-site support infrastructure

    4. On-site support plan

    Construction Phase PeriodsConstruction Phase Periods

    Construction Period:

    Construction activities usually provide a bit of a lull

    for the design team. Some members of the team

    may be reassigned to other duties at this time, never

    to return to the project. Others may monitor theproject, getting involved only when a problem arises.

    During certain predefined periods of particular risk to

    the project, design team representative(s) may travel

    to the site to observe and provide direct support.

    Construction activities during this time include

    installation and verification.

  • 8/4/2019 Successful Instrument and Control System Design

    15/16

    2011/6/26

    15

    Construction Phase PeriodsConstruction Phase Periods

    Checkout(Bump and Stroke):

    The checkout period increases the level of attention

    needed by design team. The following activities

    occur during this time:1. Each analog sensor is checked for proper ambient reading

    and electrically disconnected.

    2. Each digital input is forced by either making it react to its

    process condition or by shorting across its terminals.3. Motors are bumped to verify proper direction of rotation.

    4. Valves are stroke to make sure they function and their

    travel is not obstructed.

    Construction Phase PeriodsConstruction Phase Periods

    Startup:

    Upon successful completion of the checkout phase,

    the system is ready to run. At this point, the

    customer begins to take command of the system.

    The customers operators will have recevied trainingfrom the system integrator. It is now time to light

    the candle.

    This is the time for the customer and the system

    integrator to assume primary roles.

    The design and construction teams stand by to

    respond should a need be identified.

  • 8/4/2019 Successful Instrument and Control System Design

    16/16

    2011/6/26

    Adjustment of Document to ReflectAdjustment of Document to ReflectConstruction ModificationConstruction Modification

    Construction drawings are usually copied,

    since redlines only exist there and cannot be

    removed from the site. These copies are sent

    to the engineering service provider to be

    formally incorporated into the document.

    As soon after startup as practical, thedrawings should be released back into

    customers possession. This is an official

    turnover of responsibility for the project.

    Finally, the entire project is shipped to the customer.