Keywords Features Y3, Y4 equipment or facility / system or software electricity D Construction Z4 Smart Micro Grid Energy Management System Kyudenko Corporation Basic Concept or Summary E-50 u 24-hour power supply is possible with a power storage control system for low-cost lead storage batteries. u Efficiently manage multiple energy sources, including solar-, wind- and mini-hydraulic- power generation. u To meet the demands of our customers, power supply is supported from 100% renewable energy sources to their combination with the diesel power generation, emphasizing stable power supply. u In addition to single installations, power sharing between multiple power generation facilities is also possible. u Provide technical training on operation and maintenance. Reasons for Kyudenko developing the “Kyudenko EMSInternal combustion power is still the main form of power in remote islands/areas There is a high cost of transporting fuel to remote islands/areas. High CO2 emissions. Kyudenko Corporation Renewable energy is unstable Generated electric power (kW) Kyudenko EMS” is a “Renewable Energy Stable Supply SystemKyudenko Corporation Outputs of rough renewable energy power convert into a “tofu-like” stable waveform Kyudenko Corporation “Longer life Span” of lead storage batteries by controlling the charging and discharging cycle Kyudenko Corporation The EMS is developed by top-class Renewable Energy development company "Kyudenko" Note: Performance of domestic solar power generation facilities = 1,950 MW (panel output basis) Rated output Clear weather Clear but partially cloudy Cloudy Time of day If systems are connected under such violent fluctuation ... Fragile microgrids cannot be received ... Amount of solar power generation Amount of power supplied Generated power Power supply Time Time DC variable voltage DC/AC Inverter Convert rough variable power to constant power Saw-type waveform stabilized to tofu-like one Make use of all the generated power to the last drop! DC 380V Conversion BUS To grid Stable supply! Battery controller Cycle use lead storage battery More than 11 years in operation Joint development of lead storage battery residual management technology etc.! Successfully extended the life of low-cost lead storage batteries Actual trend graph of power sent to the microgrid at the Sumba Island Demonstration Facility (case of July 7, 2018) Outputs waveform of EMS to the grid EMS output waveform EMS output waveform Solar power generation Source:JASE-W Japanese Smart Energy Products & Technologies https://www.jase-w.eccj.or.jp/technologies/index.html

Transcript of Smart Micro Grid Energy Management System...Smart Micro Grid Energy Management System Kyudenko...

Page 1: Smart Micro Grid Energy Management System...Smart Micro Grid Energy Management System Kyudenko Corporation Basic Concept or Summary E-50 u 24-hour power supply is possible with a power

Keywords

Features

Y3, Y4 equipment or facility / system or software electricity D ConstructionZ4

Smart Micro Grid Energy Management System

Kyudenko Corporation

Basic Concept or Summary

E-50

u 24-hour power supply is possible with a power storage control system for low-cost lead storage batteries.u Efficiently manage multiple energy sources, including solar-, wind- and mini-hydraulic- power generation.u To meet the demands of our customers, power supply is supported from 100% renewable energy sources

to their combination with the diesel power generation, emphasizing stable power supply. u In addition to single installations, power sharing between multiple power generation facilities is also

possible.u Provide technical training on operation and maintenance.

Reasons for Kyudenko developing the “Kyudenko EMS”

Internal combustion power is still the main form of power in

remote islands/areas

There is a high cost of transporting fuel to remote islands/areas.High CO2 emissions.

Kyudenko Corporation

Renewable energy is unstableGenerated electric power (kW)

“Kyudenko EMS” is a “Renewable Energy Stable Supply System”Kyudenko Corporation

Outputs of rough renewable energy power convert into a “tofu-like” stable waveform Kyudenko Corporation

“Longer life Span” of lead storage batteries by controlling the charging and discharging cycle Kyudenko Corporation

The EMS is developed by top-class Renewable Energy development company "Kyudenko"Note: Performance of domestic solar power generation facilities = 1,950 MW (panel output basis)

Rated output

Clear weatherClear but partially cloudyCloudy

Time of day

If systems are connected under such violent fluctuation ...Fragile microgrids cannot be received ...

Amount of solar power generation Amount of power supplied

Generated power Power supply

TimeTime

DC variable voltageDC/AC Inverter

Convert rough variable power to constant power

Saw-type waveform stabilized to tofu-like one

Make use of all the generated power to the last drop!

DC 380V Conversion BUS

To grid

Stable supply!

Batterycontroller

Cycle uselead storage battery

More than11 years inoperation

Joint development of lead storage battery residual

management technology etc.!

Successfully extended the life of low-cost lead storage batteries

Actual trend graph of power sent to the microgrid at the Sumba Island Demonstration Facility (case of July 7, 2018)

Outputs waveform of EMS to the grid

EMS output waveform

EMS output waveform

Solar power generation

Source:JASE-W Japanese Smart Energy Products & Technologieshttps://www.jase-w.eccj.or.jp/technologies/index.html

Page 2: Smart Micro Grid Energy Management System...Smart Micro Grid Energy Management System Kyudenko Corporation Basic Concept or Summary E-50 u 24-hour power supply is possible with a power

Effects or Remarks

Contact: Kyudenko CorporationInternational Business Department, Engineering Head DivisionTel: +81-92-533-0300 Fax: +81-92-533-0303URL: http://www.kyudenko.co.jp

E-50

Installation in Practice or Schedule

u Allows on/off-grid power generation control using only renewable energy, without the use of fossil fuels.u Power generation control utilizes a DC circuit (DCBUS), eliminating the need for frequency and power

factor control etc. in comparison with AC control.u Daily EMS operation management can be performed online, allowing remote monitoring and operation.u Can be used as an independent power supply for specific applications.u Adopted as Ministry of the Environment Subsidized Project.u Adopted as JICA Subsidized Project.u Patent acquired (Patent No. 6235061)

Domestic

Overseas

Kyudenko Corporation

Kyudenko Corporation

Energy Management System (EMS) Supplying Stable Renewable EnergyDomestic demonstration within Huis Ten Bosch villa area (Sasebo, Nagasaki) – Off-grid model

Huis Ten Bosch Demonstration and Experiment Facility

Wind powergeneration(5 kW*2)

Solar powergeneration

(30 kW)

Lead storagebattery

(200 kW)

DC/AC Inverter(DC 380/AC 200)

Cloud server(EMS)

EV charger

Administrative building(lighting/air conditioning)

Load of water pump etc.

Completely off-grid

Table: Features of each EMS controlled system

Kyudenko EMS Off-grid type model

Features: Allows the synchronized operation of similar facilitiesInstallation Location: Non-electrified settlement

Eco-resort independent power supply etc.Effect: Improved electrification

Realization of an independent power supply of 100% renewable energy

Figure: Overview of Huis Ten Bosch Demonstration Facility

● With the cooperation of the Huis Ten Bosch Technical Center we constructed a 100% renewable energy power generation system within their villa area (completed in July 2015).

● Developed an EMS to control the efficient supply and demand for energy, with a demonstration project underway.

● At the end of 2015, Kyushu Electric Power lines were cut off, with all the needed electric power covered by the power generated at the villa management center.

Implementing an overseas demonstration project on Sumba Island, Indonesia, as a Ministry of the Environment Subsidized Project

Stable power from renewable energy sources is supplied with our EMS to the microgrid operating in the Western part of Sumba Island (population about 650,000). Attempting to provide stable power supply from renewable energy as the regional power grid

Existing Facilities Improvement Target

State in which proper power supply/demand operation is not possible, and power generation and storage are not constant

By controlling the generation and storage of renewable energy by EMS, it is possible to autonomously supply stable power for a fixed time/in certain amounts.

BPPT Demonstration and Experiment Facility BPPT Demonstration and Experiment Facility

Microgrid network

Scope of BPPTDemonstration

Scope of KyudenkoDemonstrationSolar power

generation(500kW)

Mini hydraulicpower generation

(2.3MW)Owned by statepower company

Main large diesel generator(4MW+2MW)

Owned by state power company

PowerDistribution

network

Emergency diesel generator(135kW)

Redox flow accumulator(500kW)

PowerDistribution

network

Microgrid network

Solar powergeneration(400kW)

Solar powergeneration(100kW)

DC/AC Inverter(DC 380/AC 380)

Lead storage battery(1,000kW)

Cloud server(EMS)Internet

Emergency diesel generator(135kW)

Main large diesel generator(4MW+2MW)

Owned by state power company

Sumba Island Demonstration Model(On-grid model)

Introduced our system at the request of BPPT (Badan Pengkajian dan

Penerapan Teknologi)

Mini hydraulicpower generation

(2.3MW)Owned by statepower company

Figure: Sumba Island, Indonesia, Microgrid Experiment Facility (Left: Before project, Right: After project)