SHIMLA JAL PRABANDHAN NIGAM LTD. DETAILED PROJECT REPORT€¦ · Detailed Project Report Design &...
Transcript of SHIMLA JAL PRABANDHAN NIGAM LTD. DETAILED PROJECT REPORT€¦ · Detailed Project Report Design &...
SHIMLA JAL PRABANDHAN NIGAM LTD.
DETAILED PROJECT REPORT
Hydraulic Design & Network modelling for Shimla Water Supply
Volume 6 - Estimates
SEPTEMBER 26, 2019
AURANGABAD, MAHARASHTRA, INDIA
Areas
Water and Waste Water
Solid Waste Management
Roads and highways
Urban infrastructure
Project management
Services
Feasibility Studies
Detailed Project Report
Design & Detail Engineering
Hydraulic Modelling
Water Audit and Leak Detection Studies
Construction Supervision
Head Office “Sai Complex”
Plot No. 72, Flat No. 05, New SBH Colony, Shahanoorwadi,
Aurangabad – 431005.
Recapitulation Sheet
S.N. Sub work Cost in Lacs Page no
1 Distribution System 42768.00 1 to 110
2 Pumping Manis 5651.00 111 to 224
3 Transmission Mains 7208.00 225 to 326
Total 55627.00
DISTRIBUTION SYSTEM
ESTIMATE
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Cost (in Rs. Lakh)
1
Providing and Laying of Pipes, Specials, Valves, Meters for
Distribution System (GI Pipes (Heavy) 80 mm to 150 mm -
285.573 Km and MSERW Fe 410 Pipes 206.5 mm to 388.8
mm - 34.14 Km )
8900.00
2
Civil Works for Distribution System (GI Pipes (Heavy) 80 mm to
150 mm - 285.573 Km and MSERW Fe 410 Pipes 206.5 mm to
388.8 mm - 34.14 Km )
7578.00
3
Construction of Reservoirs of various capacities (Capacity
Enhancement capacity of 30 existing and 11 newly proposed
Reservoirs)
2474.00
4 Acquisition of Land for various Reservoirs 1910.00
5 Plantation 200.00
6 Staff Quarters at 11 Newly Pproposed Reservoirs 336.00
7 SCADA (Cloud Based) System 154.00
8House Service Connection, AMR Consumer Meter and Direct
Acting PRV14044.00
9Operation and Maintenance of the Distribution System for 15
years5926.00
41522.00
1246.00
42768.00Total Gross Cost
Hydraulic Design & Network modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Total Net Cost
Add 3% for Contingencies
Recapitulation Sheet for Distribution System
World Bank Program
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.1
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Providing and Laying in trenches Galvanised mild steel pipe of following description conforming to I.S 1239/2000 Heavy
class, jointing all fitting , bends, Tees, Collars, Tappers etc.including hydraullic testing of pipes as per direction of Engineer
in charge etc all complete
Galvanized Iron Pipes (Heavy class)
80 mm 204369.00 Rmt 1005.48 205488521.00
As per Rate Analysis -1
100 mm 31083.00 Rmt 1402.08 43580777.00
As per Rate Analysis -2
150 mm 50121.00 Rmt 2079.89 104246299.00
As per Rate Analysis -3
2Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade Fe 410 with wall
thickness , weight per meter, flanges as described in analysis
206.5 mm dia 6.3 mm thk 21412.00 RMT 3676.43 78719719.00
As per Rate Analysis -4
260.4 mm dia 6.3 mm thk 5643.00 RMT 4601.77 25967788.00
As per Rate Analysis -5
309.7 mm dia 7.1 mm thk 6620.00 RMT 5985.01 39620766.00
As per Rate Analysis -6
339.6 mm dia 8 mm thk 163.00 RMT 7172.32 1169088.00
As per Rate Analysis -7
388.8 mm dia 8.8 mm thk 302.00 RMT 8788.15 2654021.00
As per Rate Analysis -8
Hydraulic Design & Network modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Providing and Laying of Pipes, Specials, Valves, Meters for Distribution System (GI Pipes (Heavy) 80 mm to 150 mm - 285.573 Km and MSERW Fe 410 Pipes 206.5 mm to 388.8 mm -
34.14 Km )
Abstract
World Bank Program
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.2
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
3 Providing, Suppying, fixing Specials such as Tee, Bend, Reducer, Tailpiece, etc.
GI Specials 20% Job 353315597 70663119.00
MS Specials 20% Job 148131382 29626276.00
4
Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller, communication, data logger,
standby battery. With inbuilt communication the controller can send the data directly to SCADA system. No RTU,
Communication moden, external battery is required. for Flow Control Valves
As per rate anlysis- 32
100 mm dia 2.00 No. 214053.18 428106.00
150 mm dia 21.00 No. 259659.71 5452854.00
200 mm dia 29.00 No. 361152.92 10473435.00
250 mm dia 10.00 No. 464510.07 4645101.00
300 mm dia 25.00 No. 514163.76 12854094.00
350 mm dia 2.00 No. 659106.23 1318212.00
400 mm dia 1.00 No. 889566.13 889566.00
5
Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller, communication, data logger,
standby battery. With inbuilt communication the controller can send the data directly to SCADA system. No RTU,
Communication moden, external battery is required. for Pressure Reducing Valves
As per rate anlysis- 32
80 mm dia 266.00 No. 209734.73 55789439.00
100 mm dia 103.00 No. 214053.18 22047478.00
150 mm dia 141.00 No. 259659.71 36612019.00
200 mm dia 51.00 No. 361152.92 18418799.00
250 mm dia 12.00 No. 464510.07 5574121.00
300 mm dia 6.00 No. 514163.76 3084983.00
350 mm dia 0.00 No. 659106.23 0.00
400 mm dia 3.00 No. 889566.13 2668698.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.3
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
6 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of Non Rising
spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion by electro-statically applying
epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland sealing & pocket less body passage for
unobstructed flow and debris free bottom. Body, Bonnet, Gland will be in Ductile Iron grade GGG50 / SGI 500-7, Lower
grade shall not be supplied. Spindle shall be of SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper
resistant and will be separate unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut
will be housed separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall have
Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be interchangeable design. The
flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS: 14846. The Valve will be suitable for PN 1.6
Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Isolation Valve
As per rate anlysis- 33
80 mm dia 352.00 No. 38346.81 13498079.00
100 mm dia 141.00 No. 42300.52 5964374.00
150 mm dia 348.00 No. 51688.96 17987757.00
200 mm dia 101.00 No. 81696.12 8251308.00
250 mm dia 8.00 No. 98157.36 785259.00
300 mm dia 41.00 No. 128438.40 5265974.00
350 mm dia 0.00 No. 51920.00 0.00
400 mm dia 1.00 No. 279070.00 279070.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.4
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
7 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of Non Rising
spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion by electro-statically applying
epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland sealing & pocket less body passage for
unobstructed flow and debris free bottom. Body, Bonnet, Gland will be in Ductile Iron grade GGG50 / SGI 500-7, Lower
grade shall not be supplied. Spindle shall be of SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper
resistant and will be separate unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut
will be housed separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall have
Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be interchangeable design. The
flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS: 14846. The Valve will be suitable for PN 1.6
Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Scour Valve
As per rate anlysis- 33
80 mm dia 234.00 No. 38346.81 8973154.00
100 mm dia 8.00 No. 42300.52 338404.00
150 mm dia 6.00 No. 51688.96 310134.00
200 mm dia 1.00 No. 81696.12 81696.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.5
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
8
Manufacturing, Testing and Supplying Ductile Iron, Tamper Proof, Single chamber, High Performance, Umbrella Sealing
Arc design, Full port (Equal Size inlet & outlets), Kinetic Air Release valve, for High Discharge, Venting, and Anti Vacuum
Function. The Inlet & Outlet parts of Air Valves should be equal to or larger than the area of the nominal valve size to
provide full flow area through the valve. The Valve will be supplies with DI Resilient Seated Isolating Sluice Valve of PN
1.6 Rating. The Valve shall be WRAS Approved. Body & top Cover will be in Ductile Iron Grade GGG-50 or SGI 500/7.
Lower grade shall not be supplied. The Ball, Ball Cage and Umbrella sealing arc will be in SS: 304. The Valve will be
suitable for PN 1.6 Pressure Ratings. All the top cover fasteners shall be of L & Key type with weather proof PV cap,
moisture & ingression resistant. The Sealing Arc shall be guided at top and shall be capable of sealing at 0.2 kg/cm2.
Valve will be fully protected from corrosion by electro-statically applying epoxy coating of minimum 250 microns. The
flanges shall be drilled as per IS: 1538. The Cage, Ball, Arc, Gaskets, all will be interchangeable.
AIR VALVE
Body, Bonnet - Ductile Iron DIN:1693 Gr. GGG - 50.
Float, Guide Barrel - Stainless Steel - ASTM A 276 Type - 304
Seat - Nitrile Rubber
Sealing Arc, Bolt, Small Nozzle - Stainless Steel - ASTM A 276 Type - 304
O-Ring - Rubber NBR/EPDM
Nozzle, Buffer - Rubber EPDM
ISOLATING SLUICE VALVE
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM.
As per rate anlysis- 34
25 mm dia (Rates not avialable Hence rates of 50 mm are taken, Valve shall also be of 50 mm) 2.00 No. 37630.32 75261.00
50 mm dia 60.00 No. 37630.32 2257819.00
80 mm dia 2.00 No. 58814.98 117630.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.6
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
9
Supply, install and commission Electromagnetic Flow Meter (EMF) As Per ISO 4064, for Raw/Pure water with accuracy +/-
0.5% of measured value & protection as per given specifications for size 100 mm-1000mm including sensor, transmitter
surge arrestor, cable suitable size for 25 mtrs built in GSM ( with Simcard and its charges,valid for 36 months) including
the pipe cutting, leveling and installation of flow meter in the pipelines with necessary tool tackles, cranes including 36
months guarantee etc complete, as may be required at site & based on technical specifications
As per rate anlysis- 36
100 mm dia 2.00 No. 127257.22 254514.00
150 mm dia 21.00 No. 137188.22 2880953.00
200 mm dia 30.00 No. 162429.12 4872874.00
250 mm dia 10.00 No. 179509.51 1795095.00
300 mm dia 25.00 No. 205886.16 5147154.00
350 mm dia 2.00 No. 284731.88 569464.00
400 mm dia 1.00 No. 323360.36 323360.00
10
Designing, Supplying, Installing, commissioning & testing of pressure transmitter CE markd with following technical
parameters at Raw Water Pump House and Interfacing with PLC panel including Mounting arrangement.
Output 4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.1 % of full scale or better
Enclosure- IP 67
640.00 No. 43679.00 27954559.00
As per rate anlysis- 35
Total Net Cost 889977171.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.7
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Providing and Laying in trenches Galvanised mild steel pipe of following description conforming to I.S
1239/2000 Heavy class, jointing all fitting , bends, Tees, Collars, Tappers etc.including hydraullic testing
of pipes as per direction of Engineer in charge etc all complete
Galvanized Iron Pipes (Heavy class)
80 mm 204369 204369.00 Rmt
100 mm 31083 31083.00 Rmt
150 mm 50121 50121.00 Rmt
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade
Fe 410 with wall thickness , weight per meter, flanges as described in analysis
206.5 mm dia 6.3 mm thk 21412 21412.00 Rmt
260.4 mm dia 6.3 mm thk 5643 5643.00 Rmt
309.7 mm dia 7.1 mm thk 6620 6620.00 Rmt
339.6 mm dia 8 mm thk 163 163.00 Rmt
388.8 mm dia 8.8 mm thk 302 302.00 Rmt
3 Providing, Suppying, fixing Specials such as Tee, Bend, Reducer, Tailpiece, etc.
GI Specials 20% Job
MS Specials 20% Job
4 Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller,
communication, data logger, standby battery. With inbuilt communication the controller can send the data
directly to SCADA system. No RTU, Communication moden, external battery is required. for Flow
Control Valves
100 mm dia 2 2.00 No.
150 mm dia 21 21.00 No.
200 mm dia 29 29.00 No.
Unit
1
Hydraulic Design & Network modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Providing and Laying of Pipes, Specials, Valves, Meters for Distribution System (GI Pipes (Heavy) 80 mm to 150 mm - 285.573 Km and MSERW Fe 410 Pipes 206.5
mm to 388.8 mm - 34.14 Km )
Measurement Sheet
World Bank Program
2
Sr.
No.Description
MeasurementsQty.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.8
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
250 mm dia 10 10.00 No.
300 mm dia 25 25.00 No.
350 mm dia 2 2.00 No.
400 mm dia 1 1.00 No.
5 Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller,
communication, data logger, standby battery. With inbuilt communication the controller can send the data
directly to SCADA system. No RTU, Communication moden, external battery is required. for Pressure
Reducing Valves
80 mm dia 266 266.00 No.
100 mm dia 103 103.00 No.
150 mm dia 141 141.00 No.
200 mm dia 51 51.00 No.
250 mm dia 12 12.00 No.
300 mm dia 6 6.00 No.
350 mm dia 0 0.00 No.
400 mm dia 3 3.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.9
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
6 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of
Non Rising spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion
by electro-statically applying epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland
sealing & pocket less body passage for unobstructed flow and debris free bottom. Body, Bonnet, Gland
will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall not be supplied. Spindle shall be of
SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper resistant and will be separate
unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be
housed separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall
have Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be
interchangeable design. The flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS:
14846. The Valve will be suitable for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Isolation
Valve
80 mm dia 352 352.00 No.
100 mm dia 141 141.00 No.
150 mm dia 348 348.00 No.
200 mm dia 101 101.00 No.
250 mm dia 8 8.00 No.
300 mm dia 41 41.00 No.
350 mm dia 0 0.00 No.
400 mm dia 1 1.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.10
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
7 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of
Non Rising spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion
by electro-statically applying epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland
sealing & pocket less body passage for unobstructed flow and debris free bottom. Body, Bonnet, Gland
will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall not be supplied. Spindle shall be of
SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper resistant and will be separate
unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be
housed separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall
have Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be
interchangeable design. The flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS:
14846. The Valve will be suitable for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Scour
Valve
80 mm dia 234 234.00 No.
100 mm dia 8 8.00 No.
150 mm dia 6 6.00 No.
200 mm dia 1 1.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.11
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
8 Manufacturing, Testing and Supplying Ductile Iron, Tamper Proof, Single chamber, High Performance,
Umbrella Sealing Arc design, Full port (Equal Size inlet & outlets), Kinetic Air Release valve, for High
Discharge, Venting, and Anti Vacuum Function. The Inlet & Outlet parts of Air Valves should be equal to
or larger than the area of the nominal valve size to provide full flow area through the valve. The Valve will
be supplies with DI Resilient Seated Isolating Sluice Valve of PN 1.6 Rating. The Valve shall be WRAS
Approved. Body & top Cover will be in Ductile Iron Grade GGG-50 or SGI 500/7. Lower grade shall not
be supplied. The Ball, Ball Cage and Umbrella sealing arc will be in SS: 304. The Valve will be suitable
for PN 1.6 Pressure Ratings. All the top cover fasteners shall be of L & Key type with weather proof PV
cap, moisture & ingression resistant. The Sealing Arc shall be guided at top and shall be capable of
sealing at 0.2 kg/cm2. Valve will be fully protected from corrosion by electro-statically applying epoxy
coating of minimum 250 microns. The flanges shall be drilled as per IS: 1538. The Cage, Ball, Arc,
Gaskets, all will be interchangeable.
AIR VALVE
Body, Bonnet - Ductile Iron DIN:1693 Gr. GGG - 50.
Float, Guide Barrel - Stainless Steel - ASTM A 276 Type - 304
Seat - Nitrile Rubber
Sealing Arc, Bolt, Small Nozzle - Stainless Steel - ASTM A 276 Type - 304
O-Ring - Rubber NBR/EPDM
Nozzle, Buffer - Rubber EPDM
ISOLATING SLUICE VALVE
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM.
25 mm dia (Rates not avialable Hence rates of 50 mm are taken, Valve shall also be of 50 mm) 2 2.00 No.
50 mm dia 60 60.00 No.
80 mm dia 2 2.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.12
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
9 Supply, install and commission Electromagnetic Flow Meter (EMF) As Per ISO 4064, for Raw/Pure water
with accuracy +/-0.5% of measured value & protection as per given specifications for size 100 mm-
1000mm including sensor, transmitter surge arrestor, cable suitable size for 25 mtrs built in GSM ( with
Simcard and its charges,valid for 36 months) including the pipe cutting, leveling and installation of flow
meter in the pipelines with necessary tool tackles, cranes including 36 months guarantee etc complete,
as may be required at site & based on technical specifications
100 mm dia 2 2.00 No.
150 mm dia 21 21.00 No.
200 mm dia 30 30.00 No.
250 mm dia 10 10.00 No.
300 mm dia 25 25.00 No.
350 mm dia 2 2.00 No.
400 mm dia 1 1.00 No.
10
Designing, Supplying, Installing, commissioning & testing of pressure transmitter CE markd with
following technical parameters at Raw Water Pump House and Interfacing with PLC panel including
Mounting arrangement.
Output 4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.1 % of full scale or better
Enclosure- IP 67
640 640.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.13
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m stacking
the soil not more than 3 meters clear from the edge of the excavation and then
returning the stacked soil in 15cm layers, when required into the plinths sides of
foundations etc., consolidating each deposited layer by ramming and watering
and then disposing of all surplus excavated earth as directed within a lead of 20
meters
139509.85 Cum 547.71 76410649.00
As per Rate Analysis -9
Constructing chambers with C.I surface box 100mm top dia & 180mm deep
(inside) with chained lid & RCC Walls and slab 1:1.5:3 (M20), 230mm thick and
100mm thick PCC 1:2:4 (M15) finished with a floating coat of neat cement
including curing complete
a) 600mmx600mmx750mm inside size with 200 mm thick RCC Wall 1172.00 No. 18681.03 21894168.00
As per Rate Analysis -11
b) 900mmx900mmx750mm inside size with 200 mm thick RCC Wall 749.00 No. 27116.61 20310337.00
As per Rate Analysis -12
c) 1200mmx1200mmx750mm inside size with 200 mm thick RCC Wall 137.00 No. 36851.71 5048685.00
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Civil Works for Distribution System (GI Pipes (Heavy) 80 mm to 150 mm - 285.573 Km and MSERW Fe 410 Pipes 206.5 mm to 388.8 mm - 34.14
Km )
Abstract
2
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.14
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
As per Rate Analysis -13
d) 1500mmx1500mmx750mm inside size with 200 mm thick RCC Wall 10.00 No. 47886.35 478864.00
As per Rate Analysis -14
3Providing and constructing Anchor blocks/Thrust blocks for the pipeline
(Considering 30 blocks per km)9582.00 No. 27077.27 259454383.00
As per Rate Analysis -15
4 Road Restoration including road permission charges (80% of total length) 255770.40 Sqm 1400.00 358078560.00
As per Rate Analysis -16
5 Utility Shifting For pipe laying of given length in Km 319.71 Km 50397.60 16112768.00
As per Rate Analysis -17
Total Net Cost 757788414.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.15
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
1
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m
stacking the soil not more than 3 meters clear from the edge of the
excavation and then returning the stacked soil in 15cm layers, when
required into the plinths sides of foundations etc., consolidating each
deposited layer by ramming and watering and then disposing of all surplus
excavated earth as directed within a lead of 20 meters
For Galvanized Iron Pipes (Heavy class)
80 mm 204369 0.70 0.60 85834.98 Cum
100 mm 31083 0.70 0.60 13054.86 Cum
150 mm 50121 0.75 0.60 22554.45 Cum
For MSERW Pipes
206.5 mm dia 6.3 mm thk 21412 0.80 0.60 10277.76 Cum
260.4 mm dia 6.3 mm thk 5643 0.85 0.60 2877.93 Cum
309.7 mm dia 7.1 mm thk 6620 0.90 0.75 4468.50 Cum
339.6 mm dia 8 mm thk 163 0.95 0.90 139.37 Cum
388.8 mm dia 8.8 mm thk 302 1.00 1.00 302.00 Cum
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Civil Works for Distribution System (GI Pipes (Heavy) 80 mm to 150 mm - 285.573 Km and MSERW Fe 410 Pipes 206.5 mm to 388.8 mm - 34.14
Km )
Measurement Sheet
Sr. No. DescriptionMeasurements
Qty. Unit
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.16
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DSr. No. Description
MeasurementsQty. Unit
2
Constructing chambers with C.I surface box 100mm top dia & 180mm
deep (inside) with chained lid & RCC Walls and slab 1:1.5:3 (M20), 230mm
thick and 100mm thick PCC 1:2:4 (M15) finished with a floating coat of
neat cement including curing complete
a) 600mmx600mmx750mm inside size with 200 mm thick RCC Wall 1172 1172.00 No.
b) 900mmx900mmx750mm inside size with 200 mm thick RCC Wall 749 749.00 No.
c) 1200mmx1200mmx750mm inside size with 200 mm thick RCC Wall 137 137.00 No.
d) 1500mmx1500mmx750mm inside size with 200 mm thick RCC Wall 10 10.00 No.
3 Providing and constructing Anchor blocks/Thrust blocks for the pipeline
(Considering 30 blocks per km)9582 9582.00 No.
4 Road Restoration including road permission charges (80% of total length) 1 255770.4 1 255770.40 Sqm
5 Utility Shifting For pipe laying of given length in Km 319.713 319.713 Km
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.17
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Designing, providing, constructing, testing and commissioning of reservoirs of
required capacity including excavation, foundation, RCC works, reinforcement,
all type of acceessories, provding and erecting all pipes and valves alongwith
required specials , hydraulic testing , epoxy painting externally and foodgrade
epoxy painting internally, leveliing the plot, backfilling, constrcution of compound
wall in RCC framed structure and Brickwork, plaster, painting, providing erecting
gate of required size, including all leads and lifts at various places in Shimla as
directed by Engineer-In-Charge
Capacity Enhancement of existing Tanks
Corner House 244.00 Cum 10000.00 2440000.00
Totu 1797.00 Cum 10000.00 17970000.00
Kelestone 1 509.00 Cum 10000.00 5090000.00
Fingask_2 506.00 Cum 10000.00 5060000.00
Tutikandi_2 713.00 Cum 10000.00 7130000.00
Advance_Study_Steel_Tank 437.00 Cum 10000.00 4370000.00
Chakkar/Sandal 739.00 Cum 10000.00 7390000.00
Kamnadevi_Temple 713.00 Cum 10000.00 7130000.00
Tara_Hall 1131.00 Cum 10000.00 11310000.00
Phagali 413.00 Cum 10000.00 4130000.00
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Construction of Reservoirs of various capacities (Capacity Enhancement capacity of 30 existing and 11 newly proposed Reservoirs)
Abstract
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.18
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
Mains_Field1 604.00 Cum 10000.00 6040000.00
Shivpuri 362.00 Cum 10000.00 3620000.00
Khalini_Forest_Steel_Tank 731.00 Cum 10000.00 7310000.00
SDA_Complex 291.00 Cum 10000.00 2910000.00
New_Shimla_Sector3A 142.00 Cum 10000.00 1420000.00
New_Shimla_Sector4 298.00 Cum 10000.00 2980000.00
Dhingodevi1 1056.00 Cum 10000.00 10560000.00
Dhingodevi2 113.00 Cum 10000.00 1130000.00
Mashobra 1.00 Cum 10000.00 10000.00
Dhalli_WTP1_Sump 220.00 Cum 10000.00 2200000.00
Dhalli_WTP2_Sump 367.00 Cum 10000.00 3670000.00
Sackrala 407.00 Cum 10000.00 4070000.00
Basant_Vihar 462.00 Cum 10000.00 4620000.00
Vikasnagar 340.00 Cum 10000.00 3400000.00
IAS_Colony2 128.00 Cum 10000.00 1280000.00
HP_PWD_Near_Kusumpti 849.00 Cum 10000.00 8490000.00
Jakhu 2003.00 Cum 10000.00 20030000.00
North_Oak_1 227.00 Cum 10000.00 2270000.00
New Tanks
Z7_Tutikandi_3 565.00 Cum 10000.00 5650000.00
Z6_Baluganj_Harinagar 1005.00 Cum 10000.00 10050000.00
Z4_New1 393.00 Cum 10000.00 3930000.00
Z3_Knolls_Wood 1272.00 Cum 10000.00 12720000.00
Z8_Dhingo5 1272.00 Cum 10000.00 12720000.00
Z5_Dhingodevi4 884.00 Cum 10000.00 8840000.00
Z1_Dhingodevi3 501.00 Cum 10000.00 5010000.00
Z11_Sargeen_Chowk 10.00 Cum 10000.00 100000.00
Z10_Tibti_Panthaghati 565.00 Cum 10000.00 5650000.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.19
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
Z2_Jakhu2 1901.00 Cum 10000.00 19010000.00
Z9_Shoghi 565.00 Cum 10000.00 5650000.00
Total Net Cost 247360000.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.20
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1 Acquisition of land for Varoius Reservoirs in Shimla
Capacity Enhancement of existing Tanks
Corner House 225
Old Housing Board 225
Totu 625
Kelestone 1 324
Fingask_2 400
Tutikandi_2 625
Advance_Study_Steel_Tank 400
Chakkar/Sandal 324
Kamnadevi_Temple 400
Tara_Hall 441
Phagali 400
Summer hill bazar 256
Mains_Field1 324
Shivpuri 324
Khalini_Forest_Steel_Tank 441
SDA_Complex 225
New_Shimla_Sector3A 225
New_Shimla_Sector4 225
Dhingodevi1 441
Dhingodevi2 225
Dhalli_WTP1_Sump 324
Dhalli_WTP2_Sump 400
Hydraulic Design & Network modelling for Shimla Water Supply
Acquisition of Land for various Reservoirs
ABSTRACT OF COST
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.21
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
Sackrala 324
Basant_Vihar 400
Vikasnagar 324
IAS_Colony2 225
HP_PWD_Near_Kusumpti 441
Jakhu 625
North_Oak_1 225
New Tanks
Z7_Tutikandi_3 400
Z6_Baluganj_Harinagar 625
Z4_New1 324
Z3_Knolls_Wood 729
Z8_Dhingo5 729
Z5_Dhingodevi4 625
Z1_Dhingodevi3 400
Z11_Sargeen_Chowk 100
Z10_Tibti_Panthaghati 400
Z2_Jakhu2 1024
Z9_Shoghi 400
Total area 16119 Sqm 11850.00 191010150.00
Net Amount 191010150.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.22
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1 Plantation in forest land/ cost of trees etc.
L.SLS 20000000.00
Net Amount 20000000.00
Plantation
ABSTRACT OF COST
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.23
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty Rate Unit Amount
1 Construction of staff quarters Type-I,II & III. At New Reservoir 100 sqm
x 11 reservoirs
1100 30545 Per Sqm. 33599500.00
As per PWD, Himachal Pradesh rates for plinth area for buildings of
area more than 500 sqm is 24436 in 2014 and increased by 25% for
5years.
33599500.00
Staff Quarters at 11 Newly Pproposed Reservoirs
ABSTRACT OF COST
Total Rs. In Lac.
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.24
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Supply, Installation, Commissioning, Testing, Terminating & Interfacing
Software Design to PLC and commissioning of SCADA software with
required hard tags plus 25% extra and with unlimited soft Tags & life time
licence Development version 1.00 Nos 450000 450000
2Developing/programming charges to install the software as per logic
defined by the dept. 1.00 Nos 250000 250000
3
Supply, Installation, Testing, Terminating & Interfacing Centralised
Historian Server grade Historian PC with Window 7 or latest window
operating system & Historian software development cost etc. complete
1.00 Nos 85000 85000
4Supply, Installation, Testing, Terminating & Interfacing Secondary
Computer Station Secondary computer station etc. 1.00 Nos 65000 65000
5Supply, Installation, Testing, Intgeration & Commissioning of 46" LCD
monitor at Conf. Room for display of total water system (Online) 1.00 Nos 98000 98000
6
Supplying and erecting window model mounted type room Air-Conditioner
3 star 230/250 V 50 cycles single phase A.C.supply 2 TRcapacity complete
with gas R410A/R32 at position in provided recess with wooden frame as
per specification No.AP-AC/WAC 1.00 Nos 45000 45000
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
SCADA (Cloud Based) System
Abstract
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.25
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
7Power Supply From Electrcity Department at each location of PRV and
FCV and Reservoirs735.00 Job 10000.00 7350000.00
8 Power Cable from Supply point to PRV/FCV and allied works 735.00 Job 5000.00 3675000.00
9
Designing, Supplying, Installing, commissioning & testing of Ultrasonic
level transmitter CE marked with following technical parameters and
Interfacing with PLC panel including Mounting accessories.
63 Jobs 53125.842 3346928.00
Total Net Cost 15364928.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.26
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Providing, Supplying, Installing and Commissioing of House Service
Connection including all material and labour such as GI pipe 10 m, GI
union, tee, bends, etc. brass ferrule, ball valve, chamber with surface box
for meter, trenching, refilling, etc. as directed by Engineer-in-charge
As per Rate Analysis -39
15 mm dia 52250.00 No 5026.32 262625220.00
20 mm dia 1650.00 No 5570.03 9190554.00
25 mm dia 1100.00 No 6096.74 6706409.00
2
Providing, installing and giving satisfactory field testing of domestic battery
operated ultrasonic AMR water meters with no measurement of air along
with manufacturing test certificate and guarantee certificate with battery life
of minimum 10 years with GSM / RF technology for communication to
server with PC software including 36 months guarantee, etc. complete.
As per Rate Analysis -37
15 mm dia 52250.00 No 10363.23 541478872.00
20 mm dia 1650.00 No 11302.98 18649924.00
25 mm dia 1100.00 No 13179.89 14497881.00
3Providing, fixing Direct acting PRV for each house service connection
including all materail and labour as directed by Engineer-in-charge
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
House Service Connection, AMR Consumer Meter and Direct Acting PRV
Abstract
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.27
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
As per Rate Analysis -38
15 mm dia 52250.00 No 9718.13 507772084.00
20 mm dia 1650.00 No 14250.74 23513724.00
25 mm dia 1100.00 No 18136.95 19950649.00
Total Net Cost 1404385317.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.28
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1 Providing staff for the operation and Maintenance of distribution system
1 Fitter for 10 to 15 km of Dist System as per CPHEEO manual
2 Helper for 10 to 15 km of Dist System as per CPHEEO manual
1 Watchman for each ESR as per CPHEEO manual
Total length of network in three zone is 320 Km
For Years 2021 to 2035
2021 1.00 Job 18208128.00 18208128.00
2022 1.00 Job 19488636.00 19488636.00
2023 1.00 Job 20859588.00 20859588.00
2024 1.00 Job 22326276.00 22326276.00
2025 1.00 Job 23895660.00 23895660.00
2026 1.00 Job 25576476.00 25576476.00
2027 1.00 Job 27375720.00 27375720.00
2028 1.00 Job 29300496.00 29300496.00
2029 1.00 Job 31361244.00 31361244.00
2030 1.00 Job 33566772.00 33566772.00
2031 1.00 Job 35927592.00 35927592.00
2032 1.00 Job 38454252.00 38454252.00
2033 1.00 Job 41159040.00 41159040.00
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Operation and Maintenance of the Distribution System for 15 years
Abstract
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.29
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
2034 1.00 Job 44054244.00 44054244.00
2035 1.00 Job 47153928.00 47153928.00
2Maintenance and repairs of distribution system including all material and
labour required.
2021 1.00 Job 6204975.00 6204975.00
2022 1.00 Job 6515223.75 6515224.00
2023 1.00 Job 6840984.94 6840985.00
2024 1.00 Job 7183034.18 7183034.00
2025 1.00 Job 7542185.89 7542186.00
2026 1.00 Job 7919295.19 7919295.00
2027 1.00 Job 8315259.95 8315260.00
2028 1.00 Job 8731022.95 8731023.00
2029 1.00 Job 9167574.09 9167574.00
2030 1.00 Job 9625952.80 9625953.00
2031 1.00 Job 10107250.44 10107250.00
2032 1.00 Job 10612612.96 10612613.00
2033 1.00 Job 11143243.61 11143244.00
2034 1.00 Job 11700405.79 11700406.00
2035 1.00 Job 12285426.08 12285426.00
Total Net Cost 592602500.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.30
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Name of work :- Providing Water Supply for Shimla town.
Cement/Steel/G.I Pipe
Dhalli Store (IPH)
6 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Sand Deothi Solan
60 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Aggrigate below 40 mm size
115 K.M 0.5 K.M.
Punchakula By Mech Transport By Head load Site of work
Aggrigate above 40 mm size
115 K.M 0.5 K.M.
By Mech Transport By Head load Site of work
Steel/wood/Frame/Shuttering and Shutter
6 K.M 0.5 K.M.
Shimla By Mech Transport By Head load Site of work
Brick/MSERW Pipe/GI
130 K.M 0 K.M.
Chandigarh By Mech Transport By Head load Site of work
Flanges
6 K.M. 0.5 K.M.
Local By Mech Transport By Head load Site of work
Certified that lead is taken as per actual ,shortest and feasible as well as
economical route by all means.
Lead Statement
LEAD CHART
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.31
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1) Cement from IPH 2) STEEL:
LEAD : By Mech. 6 Km. LEAD : By Mech. 6 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.5 0.00 1 Km. 0 103.50 0.00
2 Km. 0 119.49 0.00 2 Km. 0 119.49 0.00
3 Km. 0 135.32 0.00 3 Km. 0 135.32 0.00
4 Km. 0 150.70 0.00 4 Km. 0 150.70 0.00
5 Km. 1 165.35 165.35 5 Km. 1 165.35 165.35
5- 10 Km. 1 13.56 13.56 5- 10 Km. 1 13.56 13.56
10-20 Km. 0 11.32 0.00 10-20 Km. 0 11.32 0.00
Beyond 20 Km. 0 9.51 0.00 Beyond 20 Km. 0 9.51 0.00
TOTAL : 178.91 TOTAL : 178.91
2 By Head load 2 By Head load
1st. 1 Km. 0 431.84 0.00 1st. 1 Km. 0 911.43 0.00
1st. 100 Mtr 1 68.60 68.60 1st. 100 Mtr 1 144.81 144.81
Bey:1 Km.Per 1/2Km. 0 215.92 0.00 Bey:1 Km.Per 1/2Km. 0 455.72 0.00
Bey:100 Mtr Per 50 Mtr 8 20.18 161.44 Bey:100 Mtr Per 50 Mtr 8 42.59 340.72
Total : 230.04 Total : 485.53
3) Sand: 4)
LEAD : By Mech. 60 Km. LEAD : By Mech. 115 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 155.25 0.00 1 Km. 0 155.25 0.00
2 Km. 0 179.24 0.00 2 Km. 0 179.24 0.00
3 Km. 0 202.98 0.00 3 Km. 0 202.98 0.00
4 Km. 0 226.05 0.00 4 Km. 0 226.05 0.00
5 Km. 1 248.03 248.03 5 Km. 1 248.03 248.03
5- 10 Km. 5 20.34 101.70 5- 10 Km. 5 20.34 101.70
10-20 Km. 10 16.98 169.80 10-20Km 10 16.98 169.80
Beyond 20 Km. 40 14.27 570.80 Beyond 20 Km. 95 14.27 1355.65
TOTAL : 1090.33 TOTAL : 1875.18
CARRIAGE OF MATERIALS
Stone aggregate below
40mm.:
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.32
Shimla Jal Prabandhan Nigam Limited Rate Analysis
2 By Head load 2 By Head load
1st. 1 Km. 0 732.74 0.00 1st. 1 Km. 0 732.74 0.00
1st. 100 Mtr 1 116.42 116.42 1st. 100 Mtr 1 116.42 116.42
Bey:1 Km.Per 1/2Km. 0 366.37 0.00 Bey:1 Km.Per 1/2Km. 0 366.37 0.00
Bey:100 Mtr Per 50 Mtr 8 34.24 273.92 Bey:100 Mtr Per 50 Mtr 8 34.24 273.92Total : 390.34 Total : 390.34
5) 6)
LEAD : By Mech. 115 Km. LEAD : By Mech. 6 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech.
1 Km. 0 168.02 0.00 1 Km. 0 155.25 0.00
2 Km. 0 193.98 0.00 2 Km. 0 179.24 0.00
3 Km. 0 219.67 0.00 3 Km. 0 202.98 0.00
4 Km. 0 244.64 0.00 4 Km. 0 226.05 0.00
5 Km. 1 268.43 268.43 5 Km. 1 248.03 248.03
5- 10 Km. 5 22.01 110.05 5- 10 Km. 1 20.34 20.34
10-20 Km. 10 18.38 183.80 10-20 Km. 0 16.98 0.00
Beyond 20 Km. 95 15.44 1466.80 Beyond 20 Km. 0 14.27 0.00
TOTAL : 2029.08 TOTAL : 268.37
2 By Head load 2 By Head load
1st. 1 Km. 0 792.22 0.00 1st. 1 Km. 0 585.93 0.00
1st. 100 Mtr 1 125.86 125.86 1st. 100 Mtr 1 93.09 93.09
Bey:1 Km.Per 1/2Km. 0 396.11 0.00 Bey:1 Km.Per 1/2Km. 0 292.97 0.00
Bey:100 Mtr Per 50 Mtr 8 37.02 296.16 Bey:100 Mtr Per 50 Mtr 8 27.38 219.04
Total : 422.02 Total : 312.13
7) 7.1)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.5 0.00 1 Km. 0 103.5 0.00
Stone aggregate 40mm and
above:
Timber(Local wood for
shuttering)and Shutter
GI Pipe below 100mm dia
:GI Pipe below 100mm dia :
LEAD From Chandigarh :LEAD From IPH Store :
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.33
Shimla Jal Prabandhan Nigam Limited Rate Analysis
2 Km. 0 119.49 0.00 2 Km. 0 119.49 0.00
3 Km. 0 135.32 0.00 3 Km. 0 135.32 0.00
4 Km. 0 150.70 0.00 4 Km. 0 150.70 0.00
5 Km. 1 165.35 165.35 5 Km. 1 165.35 165.35
5- 10 Km. 5 13.56 67.80 5- 10 Km. 5 13.56 67.80
10-20 Km. 10 11.32 113.20 10-20 Km. 10 11.32 113.20
Beyond 20 Km. 116 9.51 1103.16 Beyond 20 Km. 116 9.51 1103.16
TOTAL : 1449.51 TOTAL : 1449.51
2 By Head load 2 By Head load
1st. 1 Km. 0 535.00 0.00 1st. 1 Km. 0 535.00 0.00
1st. 100 Mtr 1 85.00 85.00 1st. 100 Mtr 1 85.00 85.00
Bey:1 Km.Per 1/2Km. 0 267.50 0.00 Bey:1 Km.Per 1/2Km. 0 267.50 0.00
Bey:100 Mtr Per 50 Mtr 8 25.00 200.00 Bey:100 Mtr Per 50 Mtr 8 25.00 200.00
Total : 285.00 Total : 285.00
8) 9)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 706.97 0.00 1 Km. 0 964.05 0.00
2 Km. 0 816.21 0.00 2 Km. 0 1113.02 0.00
3 Km. 0 924.31 0.00 3 Km. 0 1260.42 0.00
4 Km. 0 1029.37 0.00 4 Km. 0 1403.69 0.00
5 Km. 1 1129.45 1129.45 5 Km. 1 1540.16 1540.16
5- 10 Km. 5 92.62 463.10 5- 10 Km. 5 126.30 631.50
10-20 Km. 10 77.34 773.40 10-20 Km. 10 105.46 1054.60
Beyond 20 Km. 116 64.96 7535.36 Beyond 20 Km. 116 88.59 10276.44
TOTAL : 9901.31 TOTAL : 13502.70
2 By Head load 2 By Head load
1st. 1 Km. 0 3057.20 0.00 1st. 1 Km. 0 5373.33 0.00
1st. 100 Mtr 1 485.72 485.72 1st. 100 Mtr 1 853.71 853.71
Bey:1 Km.Per 1/2Km. 0 1528.60 0.00 Bey:1 Km.Per 1/2Km. 0 2686.67 0.00
Bey:100 Mtr Per 50 Mtr 8 142.86 1142.88 Bey:100 Mtr Per 50 Mtr 8 251.09 2008.72
MSERW Pipe 200 mm dia :
MSERW Pipe 250 mm dia
:
LEAD (From Chandigarh to
IPH and IPH to Site) :
LEAD (From Chandigarh
to IPH and IPH to Site) :
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.34
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Total : 1628.60 Total : 2862.43
10) 11)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 1247.59 0.00 1 Km. 0 1767.42 0.00
2 Km. 0 1440.37 0.00 2 Km. 0 2040.53 0.00
3 Km. 0 1631.13 0.00 3 Km. 0 2310.77 0.00
4 Km. 0 1816.54 0.00 4 Km. 0 2573.43 0.00
5 Km. 1 1993.15 1993.15 5 Km. 1 2823.63 2823.63
5- 10 Km. 5 163.45 817.25 5- 10 Km. 5 231.56 1157.80
10-20 Km. 10 136.48 1364.80 10-20 Km. 10 193.35 1933.50
Beyond 20 Km. 116 114.64 13298.24 Beyond 20 Km. 116 162.41 18839.56
TOTAL : 17473.44 TOTAL : 24754.49
2 By Head load 2 By Head load
1st. 1 Km. 0 6724.09 0.00 1st. 1 Km. 0 9613.31 0.00
1st. 100 Mtr 1 1068.31 1068.31 1st. 100 Mtr 1 1527.35 1527.35
Bey:1 Km.Per 1/2Km. 0 3362.05 0.00 Bey:1 Km.Per 1/2Km. 0 4806.66 0.00
Bey:100 Mtr Per 50 Mtr 8 314.21 2513.68 Bey:100 Mtr Per 50 Mtr 8 449.22 3593.76
Total : 3581.99 Total : 5121.11
12) Flange / Sluice Valve 13) Bricks: Per 1000.Nos.
By Mech. 136 LEAD : By Mech. 130 Km.
By Head : 0.5 By Head : 0 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.50 0.00 1 Km. 0 388.13 0.00
2 Km. 0 119.49 0.00 2 Km. 0 448.10 0.00
3 Km. 0 135.32 0.00 3 Km. 0 507.45 0.00
4 Km. 0 150.70 0.00 4 Km. 0 565.13 0.00
5 Km. 1 165.35 165.35 5 Km. 1 620.07 620.07
5- 10 Km. 5 13.56 67.80 5- 10 Km. 5 50.85 254.25
(Assumed as
locallyavailable) LEAD :
MSERW Pipe 350 mm dia
:
LEAD (From Chandigarh
to IPH and IPH to Site) :
LEAD (From Chandigarh to
IPH and IPH to Site) :
MSERW Pipe 300 mm dia :
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.35
Shimla Jal Prabandhan Nigam Limited Rate Analysis
10-20 Km. 10 11.32 113.20 10-20 Km. 10 42.46 424.60
Beyond 20 Km. 116 9.51 1103.16 Beyond 20 Km. 110 35.67 3923.70
TOTAL : 346.35 TOTAL : 5222.62
2 By Head load 2 By Head load
1st. 1 Km. 0 911.43 0.00 1st. 1 Km. 0 1367.88 0.00
1st. 100 Mtr 1 144.81 144.81 1st. 100 Mtr 0 217.32 0.00
Bey:1 Km.Per 1/2Km. 0 455.72 0.00 Bey:1 Km.Per 1/2Km. 0 683.94 0.00
Bey:100 Mtr Per 50 Mtr 8 42.59 340.72 Bey:100 Mtr Per 50 Mtr 0 63.92 0.00
Total : 144.81 Total : 0.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.36
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr.
No.RATE UNIT
1 AGGREGATE 40 MM 550.00 /CUM
2 AGGREGATE 20 MM 725.00 /CUM
3 AGGREGATE 10 MM 725.00 /CUM
4 CEMENT 5120.00 /MT
5 SAND 650.00 /CUM
6 FINE SAND (FILTER MEDIA) 650.00 /CUM
7 M.R. TOR STEEL 4500.00 /QTL.
8 DRILLING EQUIPEMENT 3600.00 /DAY
9 SAFETY COILS 30.00 /COIL
10 DETONATORS 300.00 /100 Nos.
11 SPECIAL GELATINE 75.00 KG
12 STONE 500.00 /CUM
13 THROUGH BOUND STONE 1000.00 /100
14 MS ANGLE/ MS STRAPS 5000.00 /QTL.
15 WELDING CHARGES 4.00 /CMT.
16 WELDING CHARGES WITH GENERATOR SET 5.00 /CMT.
17 MS BOLTS 22 mm 5975.00 /QTL.
18 MS FLAT 5000.00 /QTL.
19 BOULDER/HARD STONE/PLUM 450.00 /CUM
20 CAST IRON M/H 90.00 /KG
21 BRICKS (I st Class) 4500.00 /1000
22 BRICKS II nd
Class) 4000.00 /1000
23 WHITE CEMENT 21500.00 /MT
24 Bitumen/Mexphalt 80/100 34500.00 /MT
25 KEROSENE OIL 14.00 /LTS.
26 DISEIL 56.00 /LTS.
27 M.OIL 285.00 /LTS.
28 FUEL WOOD 5.00 /KG
29 HIRING CHARGES OF TRUCK ( M.R.) 2500.00 /DAY
30 HIRE CHARGES OF PUMP 500.00 /DAY
31 HESSIAN CLOTH 25.00 /SQMT.
32 22mm RIVETS 6975.00 / QTL.
33 LIME(UNSLAKED) 1000.00 / QTL.
34 M.S.PLATES 4500.00 / QTL.
35 R.S.JOISTS 5000.00 / QTL.
36 C.I.RUNGS 40.00 /KG
37 ENAMELLED PAINT(OTHER THAN WHITE) 200.00 / LTS.
38 KAIL WOOD (Ist CLASS) 44500.00 /CUM
39 KAIL WOOD (IInd CLASS) 33830.00 /CUM
40 CHIL WOOD (Ist CLASS) 18100.00 /CUM
41 CHIL WOOD (IInd CLASS) 15800.00 /CUM
42 DEODAR WOOD 45200.00 /CUM
43 SAW CHARGES OF SLEEPERS TO PLANKS 700.00 /CUM
44 SAW CHARGES OF SLEEPERS TO BATTENS 500.00 /CUM
45 WOODEN BALLIES OF KAIL 125.00 /RMT.
46 WIRE GAUGE 250.00 /SQMT.
47 CI VENT PIPE 1.80 Mtr.Long 750.00 /EACH
48 Barbed Wire 56.68 Per Kg. (RC)
** BASIC RATE **
Name of work:- Hydraulic Design & Network Modelling for Shimla Water Supply
DESCRIPTION OF ITEM
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.37
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr.
No.RATE UNITDESCRIPTION OF ITEM
49 Ready Mixed Paint (other than white) 150.00 /ltr
50 Ready Mixed Paint (Pink Primer) 200.00 /ltr
51 Ready Mixed Red Mixed Paint 150.00 /ltr
52 Sliding Door Bolt (250 x 16 mm) 95.00 Each
53 Sliding Door Bolt (200X16 mm) 65.00 Each
54 Tower Bolt (Barrel Type 250 x 10 mm 35.00 Each
55 Tower Bolt (Barrel Type 200 x 10 mm 30.00 Each
56 Tower Bolt (Barrel Type 100 x 10 mm 25.00 Each
57 Tower Bolt (Barrel Type 150 x 10 mm 20.00 Each
58 Dry DisTamper 65.00 Kg
59 Oil Bound DisTamper 125.00 /ltr
60 Handles 100 mm 20.00 Each
61 Handles 125 mm 30.00 Each
62 SFRC Man Hole Cover 1700.00 Each
63 Terrazo Tiles 900.00 /SQMT.
64 Pink Makrana Marble 20 mm thick 1200.00 /SQMT.
64 Glass Strips 10.00 /Mtr.
65 Mild Steel Screws 40 mm 40.00 /Cent
66 Mild Steel Screws 25 mm 30.00 /10 nos
67 Mild Steel Screws 20 mm 25.00 /10 nos
68 Cement Paint 250.00 /ltr
69 Wood Perservative(Oil TYpe) 180.00 /ltr
70 Glass 2 mm to 3 mm 375.00 /Mtr
71 Iron Hinges ( 100 x 30 x 19 mm ) 25.00 /Cent
73 Iron Hinges ( 50 x 30 x 15 mm ) 15.00 /Cent
74 Ceramic Tile (153 x 152 x 6 mm) 750.00 /Sqm
82 C.G.I.SHEET 0.63 mm THICK 8000.00 /MT
83 P.G.I. SHEET 6000.00 /MT
84 800.00 /Cent
85 MS Flange of all tables 64.00 /KG
86 70.00 /KG
87 73.00 /KG
88 1373.00 /Meter
89 1703.00 /Meter
90 2318.00 /Meter
91 2880.00 /Meter
92 0.00 /Meter
93 4350.00 /Meter
94 0.00 /Meter
95 6140.00 /Meter
96 100 MM 105.00 EACH
97 150 MM 124.00 EACH
98 200 MM 171.00 EACH
99 250MM 295.00 EACH
100 300 MM 390.00 EACH
101 350 MM 703.00 EACH
102 400 MM 798.00 EACH
103 450 MM 1121.00 EACH
Rubber Gasket EPDM
DI PIPE 400 MM DIA Including frieght charges Upto Kalka
DI PIPE 450 MM DIA Including frieght charges Upto Kalka
DI PIPE 500 MM DIA Including frieght charges Upto Kalka
DI PIPE 250 MM DIA Including frieght charges Upto Kalka
DI PIPE 300 MM DIA Including frieght charges Upto Kalka
DI PIPE 350 MM DIA Including frieght charges Upto Kalka
API Pipes (IS/ISO:3183-2007) Gr, X
- 42 , 600 mm diaDI PIPE 150 MM DIA Including frieght charges Upto Kalka
DI PIPE 200 MM DIA Including frieght charges Upto Kalka
60 mm Thick Precast Interlocked Paver Blocks
API Pipes (IS/ISO:3183-2007) Gr, X
- 42 450 mm dia
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.38
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr.
No.RATE UNITDESCRIPTION OF ITEM
104 500 MM 1350.00 EACH
105 Plastic Steps 166.00 EACH
(B)
Rate i/c P/H Basic Rate Unit
88 FITTER (G-I) 292.00 252.00 /DAY
89 FITTER (G-II) 292.00 252.00 /DAY
90 MASON(G-1) 292.00 252.00 /DAY
91 MASON(G-II) 292.00 252.00 /DAY
92 PAINTER(G-I) 292.00 252.00 /DAY
93 PAINTER(G-II) 265.00 225.00 /DAY
94 BLACK SMITH (G-I) 292.00 252.00 /DAY
95 BLACK SMITH (G-II) 292.00 252.00 /DAY
96 CARPENTER G-I 292.00 252.00 /DAY
97 CARPENTER G-II 292.00 252.00 /DAY
98 BELDAR 250.00 210.00 /DAY
99 BHISTI 250.00 210.00 /DAY
100 MATE 250.00 210.00 /DAY
101 STONE DRESSER 250.00 210.00 /DAY
102 BHANDHANI 250.00 210.00 /DAY
103 DRILLER 250.00 210.00 /DAY
104 STONE CHISLER 250.00 210.00 /DAY
105 WHITE WASHER 265.00 210.00 /DAY
106 PUMP OPERATOR 262.00 252.00 /DAY
107 BLASTER 250.00 210.00 /DAY
108 Electrician 371.00 300.00 /DAY
109 BELDAR SKILLED 292.00 252.00 /DAY
RATE OF LABOUR AS APPLICABLE IN DEPTT. Vide Govt. notification No.FIN - ( PR ) B ( 7) -
33/2010 dt. 07-04-2017
Designation
Certified that above rates of materials are the lowest one pervailing markets rates & rates of
labour have been taken as applicable in this Department as per latest notification as issued by the Govt.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.39
Shimla Jal Prabandhan Nigam Limited Rate Analysis
56.00 285.00 250.00 2500.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 12.00 5.65 17.30 5.77 323.12 0.22 62.70 1500.00 2500.00 4385.82 776.25
2 12.75 5.12 26.48 8.83 494.48 0.33 94.05 1500.00 2500.00 4588.53 896.20 119.95
3 13.12 4.69 34.14 11.38 637.28 0.43 122.55 1500.00 2500.00 4759.83 1014.89 118.69
4 13.50 4.34 40.72 13.57 759.92 0.51 145.35 1500.00 2500.00 4905.27 1130.25 115.36
5 13.88 4.06 46.60 15.53 869.68 0.58 165.30 1500.00 2500.00 5034.98 1240.14 109.89
6 14.25 3.82 51.84 17.28 967.68 0.65 185.25 1500.00 2500.00 5152.93 1348.93 108.79
7 14.63 3.62 56.68 18.89 1057.84 0.71 202.35 1500.00 2500.00 5260.19 1453.09 104.16
8 15.10 3.46 61.36 20.45 1145.20 0.77 219.45 1500.00 2500.00 5364.65 1550.48 97.39
9 15.38 3.31 65.58 21.86 1224.16 0.82 233.70 1500.00 2500.00 5457.86 1648.90 98.42
10 15.75 3.17 69.40 23.13 1295.28 0.87 247.95 1500.00 2500.00 5543.23 1748.65 99.75 101.70
11 16.13 3.06 73.32 24.44 1368.64 0.92 262.20 1500.00 2500.00 5630.84 1840.14 91.49
12 16.50 2.96 77.04 25.68 1438.08 0.96 273.60 1500.00 2500.00 5711.68 1929.62 89.48
13 16.88 2.87 80.62 26.87 1504.72 1.01 287.85 1500.00 2500.00 5792.57 2018.32 88.70
14 17.25 2.78 83.84 27.95 1565.20 1.05 299.25 1500.00 2500.00 5864.45 2109.51 91.19
15 17.63 2.71 87.30 29.10 1629.60 1.09 310.65 1500.00 2500.00 5940.25 2191.97 82.46
16 18.00 2.64 90.48 30.16 1688.96 1.13 322.05 1500.00 2500.00 6011.01 2276.90 84.93
17 18.38 2.58 93.72 31.24 1749.44 1.18 336.30 1500.00 2500.00 6085.74 2358.81 81.91
18 18.75 2.52 96.72 32.24 1805.44 1.21 344.85 1500.00 2500.00 6150.29 2440.59 81.78
19 19.13 2.47 99.86 33.29 1864.24 1.25 356.25 1500.00 2500.00 6220.49 2518.42 77.83
20 19.50 2.42 102.80 34.27 1919.12 1.29 367.65 1500.00 2500.00 6286.77 2597.84 79.42 84.92
21 19.88 2.38 105.96 35.32 1977.92 1.32 376.20 1500.00 2500.00 6354.12 2669.80 71.96
22 20.25 2.34 108.96 36.32 2033.92 1.36 387.60 1500.00 2500.00 6421.52 2744.24 74.44
23 20.63 2.30 111.80 37.27 2087.12 1.40 399.00 1500.00 2500.00 6486.12 2820.05 75.81
24 21.00 2.26 114.48 38.16 2136.96 1.43 407.55 1500.00 2500.00 6544.51 2895.80 75.75
25 21.38 2.23 117.50 39.17 2193.52 1.48 421.80 1500.00 2500.00 6615.32 2966.51 70.71
26 21.75 2.20 120.40 40.13 2247.28 1.51 430.35 1500.00 2500.00 6677.63 3035.29 68.78
27 22.13 2.17 123.18 41.06 2299.36 1.54 438.90 1500.00 2500.00 6738.26 3105.19 69.90
28 22.50 2.14 125.84 41.95 2349.20 1.57 447.45 1500.00 2500.00 6796.65 3176.00 70.81
29 22.88 2.11 128.38 42.79 2396.24 1.60 456.00 1500.00 2500.00 6852.24 3247.51 71.51
30 23.25 2.09 131.40 43.80 2452.80 1.64 467.40 1500.00 2500.00 6920.20 3311.10 63.59 71.33
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT Sl.No.
Lead
inK.M
.(L)
Average speed Km/hour(s) No.of Trips
No.
No.of Km.
done
2NL+6
Litre of
diesel
consumed
Litre of
Diesel @
per Ltr.
Litres of
M.Oil
consumed
Cost of
M.Oil @
per litre
Cost of 6
Beldar @
per day
Hire
Charges
of Truck
@ per day
Total
cost
Col.No6+
8+9+10
Cost per
trip
Increase
in Cost
per Km
over
previous
Km.
Average
cost per
additional
Km.after
five Km.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.40
Shimla Jal Prabandhan Nigam Limited Rate Analysis
776.25 896.20 1014.89 1130.25 1240.14 101.70 84.92
1 2 3 4 5 6 7 8 9 10 11 12
1 Lime, moorum , building rubish. 6 cu.m 6.00 1 cu.m 129.38 149.37 169.15 188.38 206.69 16.95 14.15
2 Earth work. 6 cu.m 4.80 1 cu.m 161.72 186.71 211.44 235.47 258.36 21.19 17.69
3 Manure or sludge 6 cu.m 5.52 1 cu.m 140.63 162.36 183.86 204.76 224.66 18.42 15.38
4 Excavated rock. 6 cu.m 3.00 1 cu.m 258.75 298.73 338.30 376.75 413.38 33.90 28.31
5 Sand,stone agg. below 40mm 5 cu.m 5.00 1 cu.m 155.25 179.24 202.98 226.05 248.03 20.34 16.98
6 Stone agg.40mm & above,build.
Stones.
5 cu.m 4.62 1 cu.m 168.02 193.98 219.67 244.64 268.43 22.01 18.38
7 Soling stone, stone block &
stone for filling crates
5 cu.m 4.25 1 cu.m 182.65 210.87 238.80 265.94 291.80 23.93 19.98
8 Bricks. 2000Nos. 2000.00 1000 Nos. 388.13 448.10 507.45 565.13 620.07 50.85 42.46
9 Bricks tiles. 3200Nos. 3200.00 1000 Nos. 242.58 280.06 317.15 353.20 387.54 31.78 26.54
10 Slates. 14450Nos. 14450.00 1000 Nos. 53.72 62.02 70.23 78.22 85.82 7.04 5.88
11 Terrazzo Tiles. 2500Nos. 2500.00 1000 Nos. 310.50 358.48 405.96 452.10 496.06 40.68 33.97
12 Cement G.I. CI. AC. CC pipes
below 100mm dia & other heavy
materials.
7.50 Tonne 7.50 1 Tonne 103.50 119.49 135.32 150.70 165.35 13.56 11.32
13 Steam Coal 5.5 Tonne 5.50 1 Tonne 141.14 162.95 184.53 205.50 225.48 18.49 15.44
14 Steel i/c C.G.I & A.C.sheet. 7.50 Tonne 7.50 1 Tonne 103.50 119.49 135.32 150.70 165.35 13.56 11.32
15 Timber 5 cu.m 5.00 1 cu.m 155.25 179.24 202.98 226.05 248.03 20.34 16.98
16 Tar Bitumen etc. 4.50 Tonne 4.50 1 Tonne 172.50 199.16 225.53 251.17 275.59 22.60 18.87
17 R.C.C.,A.C. Hume, steel
C.I.Pipes:- 80 mm dia
329.40m 329.40 100m 235.66 272.07 308.10 343.12 376.48 30.87 25.78
14.27
15.85
21.65
4.94
28.53
9.51
12.97
9.51
14.27
15.44
16.78
35.67
22.29
13
11.89
14.86
12.92
23.78
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALSS.No MATERIALS CAPACITY NET QTY.TO
BE PAID
AFTER
DEDUCTION
OF VOIDS.
UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW
1 Km. 2Km. 3Km. 4Km. 5Km. BEYOND
5Km.UP TO
10 Km.
BEYOND
10Km.UP
TO 20 Km.
BEYOND 20Km
/Km.
71.33
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.41
Shimla Jal Prabandhan Nigam Limited Rate Analysis
776.25 896.20 1014.89 1130.25 1240.14 101.70 84.92
1 2 3 4 5 6 7 8 9 10 11 12 13
S.No MATERIALS CAPACITY NET QTY.TO
BE PAID
AFTER
DEDUCTION
OF VOIDS.
UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW
1 Km. 2Km. 3Km. 4Km. 5Km. BEYOND
5Km.UP TO
10 Km.
BEYOND
10Km.UP
TO 20 Km.
BEYOND 20Km
/Km.
71.33
18 100 mm dia 292.80m 292.80 100m 265.11 306.08 346.62 386.01 423.55 34.73 29.00
19 125 mm dia 219.6m 219.60 100m 353.48 408.11 462.15 514.69 564.73 46.31 38.67
20 150 mm dia 183m 183.00 100m 424.18 489.73 554.58 617.62 677.67 55.57 46.40
21 200 mm dia 109.80m 109.80 100m 706.97 816.21 924.31 1029.37 1129.45 92.62 77.34
22 250 mm dia 80.52m 80.52 100m 964.05 1113.02 1260.42 1403.69 1540.16 126.30 105.46
23 300 mm dia 62.22m 62.22 100m 1247.59 1440.37 1631.13 1816.54 1993.15 163.45 136.48
24 350 mm dia 43.92m 43.92 100m 1767.42 2040.53 2310.77 2573.43 2823.63 231.56 193.35
25 400 mm dia 32.94m 32.94 100m 2356.56 2720.70 3081.03 3431.24 3764.85 308.74 257.80
26 450 /500mmdia 25.62m 25.62 100m 3029.86 3498.05 3961.32 4411.59 4840.52 396.96 331.46
27 600, 700, 750 & 800 mm dia 18.30m 18.30 100m 4241.80 4897.27 5545.85 6176.23 6776.72 555.74 464.04
28 900,1000,1100 & 1200 mm dia. 11.00m 11.00 100m 7056.82 8147.27 9226.27 10275.00 11274.00 924.55 772.00
278.42
389.78
648.45
32.48
38.98
64.96
88.59
114.64
162.41
24.36
216.55
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.42
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
LIGHT MATERIALS A : 7.67 250.00 1917.50 2301.00
1 Lime, moorum and building rubish. 35 cu.m 35.00 1 cu.m 1917.50 65.74 27.39 93.13 586.15 293.08
2 .Earth work. 35 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
3 Manure or sludge 35cu.m 32.20 1 cu.m 1917.50 71.46 29.77 101.23 637.09 318.55
4 Excavated rock. 35 cu.m 17.50 1 cu.m 1917.50 131.49 54.79 186.28 1172.50 586.25
5 Sand,stone agg.below 40mm size. 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
6 Stone agg.40mm & above,build. Stones. 28 cu.m 25.90 1 cu.m 1917.50 88.84 37.02 125.86 792.22 396.11
7 Soling stone, stone block & stone for filling crates 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
8 Bricks. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
9 Bricks tiles. 24000
Nos.
24000.00 1000 Nos. 1917.50 95.88 39.95 135.83 854.93 427.47
10 Slates. 80000
Nos.
80000.00 1000 Nos. 1917.50 28.76 11.98 40.74 256.38 128.19
11 Terrazzo Tiles. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
HEAVY MATERIALS A : 9.20 250.00 2300.00 B : =(Col.No.7/2+Col.No.7*1.40/2) 2760.00
1 Stone blocks G.I,C.C. pipes below 100mm dia and
other heavy materials.
46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
2 cement 57 Tonne 57.00 1 Tonne 2300.00 48.42 20.18 68.60 431.84 215.92
3 Steel including C.G.I & asbestos sheet. 27 Tonne 27.00 1 Tonne 2300.00 102.22 42.59 144.81 911.43 455.72
4 Timber 42 cu.m 42.00 1 cu.m 2300.00 65.71 27.38 93.09 585.93 292.97
5 Tar Bitumen etc. 46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
No's Beldar @ B : =(Col.No.7/2+Col.No.7*1.40/2)
No's Beldar @
CARRIAGE OF MATERIAL BY MANUAL LABOUR INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID
AFT
ER
DE
DU
CT
IO
N O
F
VO
ID
S.
UN
IT
S
CO
ST
OF 8
HO
UR
S COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IR
ST
50
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF 5
0
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
FO
R 1
00
MT
R
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.43
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID
AFT
ER
DE
DU
CT
IO
N O
F
VO
ID
S.
UN
IT
S
CO
ST
OF 8
HO
UR
S COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IR
ST
50
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF 5
0
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
FO
R 1
00
MT
R
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
6 Concrete, R.C.C. Hume, steel C.I.Pipes:-
100mm dia
1702m 1702.00 100m 2300.00 162.16 67.57 229.73 1445.99 723.00
7 Concrete, R.C.C. Hume, steel C.I.Pipes:- 125mm dia 1391m 1391.00 100m 2300.00 198.42 82.67 281.09 1769.15 884.58
8 Concrete, R.C.C. Hume, steel C.I.Pipes:- 150mm dia 1208m 1208.00 100m 2300.00 228.48 95.20 323.68 2037.28 1018.64
9 Concrete, R.C.C. Hume, steel C.I.Pipes:- 200mm dia 805m 805.00 100m 2300.00 342.86 142.86 485.72 3057.20 1528.60
10 Concrete, R.C.C. Hume, steel C.I.Pipes:- 250mm dia 458m 458.00 100m 2300.00 602.62 251.09 853.71 5373.33 2686.67
11 Concrete, R.C.C. Hume, steel C.I.Pipes:- 300mm dia 366m 366.00 100m 2300.00 754.10 314.21 1068.31 6724.09 3362.05
12 Concrete, R.C.C. Hume, steel C.I.Pipes:- 350mm dia 256m 256.00 100m 2300.00 1078.13 449.22 1527.35 9613.31 4806.66
13 Concrete, R.C.C. Hume, steel C.I.Pipes:- 400mm dia 220m 220.00 100m 2300.00 1254.55 522.73 1777.28 11186.42 5593.21
14 Concrete, R.C.C. Hume, steel C.I.Pipes:-
450mm,500mm dia
165m 165.00 100m 2300.00 1672.73 696.97 2369.70 14915.16 7457.58
15 Concrete, R.C.C. Hume, steel C.I.Pipes:-
600,700,750 & 800mm dia
150m 150.00 100m 2300.00 1840.00 766.67 2606.67 16406.73 8203.37
16 Concrete, R.C.C. Hume, steel C.I.Pipes:-
900,1000,1100&1200mm dia
125m 125.00 100m 2300.00 2208.00 920.00 3128.00 19688.00 9844.00
17 Asbestes cement pipes: - 50mm dia =5032 pipes
of 2m length 10064m
10064m 10064.00 100m 2300.00 27.42 11.43 38.85 244.59 122.30
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.44
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID
AFT
ER
DE
DU
CT
IO
N O
F
VO
ID
S.
UN
IT
S
CO
ST
OF 8
HO
UR
S COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IR
ST
50
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF 5
0
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
FO
R 1
00
MT
R
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
18 As bestes cement pipes: - 80mm dia 1620 pipes of
2m length=3660
3660m 3660.00 100m 2300.00 75.41 31.42 106.83 672.39 336.20
19 As bestes cement pipes:- 100mm dia 1281 pipes of
2m length=2562m
2562m 2562.00 100m 2300.00 107.73 44.89 152.62 960.64 480.32
20 As bestes cement pipes:- 125mm dia 1100 pipes of
2m length= 2200m
2200m 2200.00 100m 2300.00 125.45 52.27 177.72 1118.58 559.29
21 As bestes cement pipes:- 150mm dia 915 pipes of
2m length =1830m
1830m 1830.00 100m 2300.00 150.82 62.84 213.66 1344.78 672.39
22 As bestes cement pipes:- 200mm dia 800 pipes of
2m length= 1600m
1600m 1600.00 100m 2300.00 172.50 71.88 244.38 1538.22 769.11
23 As bestes cement pipes:- 250mm dia 700 pipes of
2m length= 1400m
1400m 1400.00 100m 2300.00 197.14 82.14 279.28 1757.80 878.90
24 As bestes cement pipes:- 300mm dia 600 pipes of
2m length= 1200m
1200m 1200.00 100m 2300.00 230.00 95.83 325.83 2050.77 1025.39
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.45
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 1
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 80 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1Basic rates on F.O.R. destination
Chandigarh Mtr.10.00 691.8399 6918.40
Add 10% for Specials 0.10 691.84
Add 0.5% for inspection charges. 34.59
Add 3% for entry tax 207.55
White lead hemp oil etc., L.S. 35.00
Sub Total:- 7887.38 (A)
2 Carriage
130Km by Mech Transport Chandigarh to
ShimlaTonne 0.101 1449.51 146.40
6 Km by Mech. Transport from IPH.Store Tonne 0.101 1449.51 146.40
0.5 Km by Head Load Tonne 0.101 285.00 28.79
Sub total:- 321.59 (B)
3 Labour
1 Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total:- 414.30 (C)
Total (A+B+C) 8623.27
4 Other additions
Add 10% C.P & 5 % O.H charges 8623.27 15.00% 1293.49
Add GST 0.00% 0.00
Add 1% Labour Cess 1.00% 86.23
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 1431.51 (D)
Cost for 10 Rmt. (A+B+C+D) 10054.78
Cost per running meter 1005.48
Cost of excavation 412.73
Cost per meter including excavation 1418.21
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.46
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 2
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 100 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1 Chandigarh Mtr. 10.00 996.6616 9966.62
Add 10% for Specials 0.10 996.66
Add 3 % Entry tex 299.00
Add 0.5% for inspection charges. 49.83
White lead hemp oil etc., L.S. 35.00
Sub Total:- 11347.11 (A)
2 Carriage
130Km by Mech Transport Chandigarh to
ShimlaTonne 0.148 1449.51 214.53
6 Km by Mech. Transport from IPH.Store Tonne 0.148 1449.51 214.53
0.5 Km by Head Load Tonne 0.148 285.00 42.18
Sub total:- 471.23 (B)
3 Labour
1 Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total:- 414.30 (C)
Total (A+B+C) 10852.15
4 Other additions
Add 10% C.P & 5 % O.H charges 10852.15 15.00% 1627.82
Add GST 0.00% 0.00
Add 1% Labour Cess 1.00% 108.52
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 1788.13 (D)
Cost for 10 Rmt. (A+B+C+D) 14020.78
Cost per running meter 1402.08
Cost of excavation 412.73
Cost per meter including excavation 1814.81
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.47
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 3
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 150 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1 Basic rates on F.O.R. destination
Chandigarh Mtr. 10.00 1474.7898 14747.90
Add 10% for Specials 0.10 1474.79
Add 3 % Entry tex 442.44
Add 0.5% for inspection charges. 73.74
White lead hemp oil etc., L.S. 35.00
Sub total 16773.86 (A)
2 Carriage
130 Km by Mech Transport Chandigarh to Shimla Tonne 0.219 1449.51 317.44
6 Km by Mech. Transport from IPH.Store Tonne 0.219 1449.51 317.44
0.5 Km by Head Load Tonne 0.219 285.00 62.42
Sub total 697.30 (B)
3 Labour
Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total 414.30 (C)
Total (A+B+C) 17885.46
4 Other additions
Add 10% C.P & 5 % O.H charges 17885.46 15.00% 2682.82
Add GST 0.00% 0.00
Add 1% Labour Cess 1.00% 178.85
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 2913.46 (D)
Cost for 10 Rmt. (A+B+C+D) 20798.93
Cost per running meter 2079.89
Cost of excavation 412.73
Cost per meter including excavation 2492.63
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.48
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 206.50 mm dia
Diameter in mm 206.5
Thickness in mm 6.3
Density in Kg per Cum 7850
WT per Meter in Kg 33.06
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.21
Wt of pair of flange in Kg 4.41
No of Nut bolts 24
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 4.8
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 206.50 mm dia 3372.12 Kg 58.00 195582.96
Add GST 18.00% 35204.93
Cost of Pipe including GST 230787.89
Add entry tax 3.00% 6923.64
Add inspection Charges 0.50% 1153.94
Cost of pipe 238865.47
Carriage of pipes by mechanical transportation 1 job 9901.31 9901.31
Carriage of pipes by head load 1 job 1628.60 1628.60
Unloading and stacking 1 job 1628.60 1628.60
Cost of Transportation of pipe (100 m length) 13158.51
Cost of Pipe Welding 5231.25 cm 5.00 26156.25
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
RATE ANALYSIS - 4
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade Fe 410
with wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.49
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 3381.33 Kg 1.02 3448.96
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 64.87
Outer side 68.83
Cost of Painting of 100 m pipeline (rate as per
CPWD DSR 2016- I.N. 13.52.1 P.N. 804133.7 Sqm 122.5 16378.25
Hasion cloth wraping
Clothe 0.69 Sqm 25.00 17.25
Bitumen 0.69 Sqm 40.00 27.60
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 141.78
Cost of wraping for 100 meters 100 Rmt 141.78 14178.00
Add 10% C.P.& 5% O.H.Charges on amount
excluding cost of taxes.269948.31 % 15.00% 40492.25
Pair of Flange 4.41 Kg 64.00 282.24
Nut Blots 4.8 Kg 59.75 286.8
Add GST 12.00% 34.42
Cost of Flanges including GST 603.46
Add entry tax 3.00% 18.1
Add inspection Charges 0.50% 3.02
Cost of flange 624.58
Gasket 2 No 105.00 210.00
Length of welding from inside 129.75 cm 5.00 648.75
Length of welding from outside 275.33 cm 5.00 1376.65
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.50
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of pair of flange 2866.34
Add 10% C.P.& 5% O.H.Charges on amount
excluding cost of taxes.2810.7997 % 15.00% 421.62
Cost of pair of flange 3287.96
Add 1% Labour Cess 272759.11 % 1.00% 2727.59
Add EPF 12.5% on all Labour 63232.24 % 12.50% 7904.03
Cost of Piping including all for 100 meter 367642.65
Cost of Piping including all per meter 3676.43
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.51
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 260.40 mm dia
Diameter in mm 260.4
Thickness in mm 6.3
Density in Kg per Cum 7850
WT per Meter in Kg 41.44
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.385
Wt of pair of flange in Kg 4.77
No of Nut bolts 36
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 7.2
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 260.40 mm dia 4226.88 Kg 58.00 245159.04
Add GST 18.00% 44128.63
Cost of Pipe including GST 289287.67
Add entry tax 3.00% 8678.63
Add inspection Charges 0.50% 1446.44
Cost of pipe 299412.74
Carriage of pipes by mechanical transportation 1 Job 13502.70 13502.70
Carriage of pipes by head load 1 Job 2862.43 2862.43
Unloading and stacking 1 Job 2862.43 2862.43
Cost of Transportation of pipe 100 m length 19227.56
Cost of Pipe Welding 6518.18 cm 5.00 32590.90
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
RATE ANALYSIS - 5
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade Fe 410 with wall
thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.52
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of laying of 100 m pipeline 4238.85 Kg 1.02 4323.63
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 81.81
Outer side 85.77
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804167.58 Sqm 122.5 20528.55
Hasion cloth wraping
Clothe 0.86 Sqm 25.00 21.50
Bitumen 0.86 Sqm 40.00 34.40
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 152.83
Cost of wraping for 100 meters 100 Rmt 152.83 15283.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.338158.06 % 15.00% 50723.71
Pair of Flange 4.77 Kg 64.00 305.28
Nut Blots 7.2 Kg 59.75 430.2
Add GST 12.00% 51.62
Cost of Flanges including GST 787.1
Add entry tax 3.00% 23.61
Add inspection Charges 0.50% 3.94
Cost of flange 814.65
Gasket 2 No 105.00 210.00
Length of welding from inside 163.61 cm 5.00 818.05
Length of welding from outside 343.06 cm 5.00 1715.30
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 3564.36
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.3485.1897 % 15.00% 522.78
Cost of pair of flange 4087.14
Add 1% Labour Cess 341643.25 % 1.00% 3416.43
Add EPF 12.5% on all Labour 76304.81 % 12.50% 9538.10
Cost of Piping including all for 100 meter 460177.14
Cost of Piping including all per meter 4601.77
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.53
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 309.70mm dia
Diameter in mm 309.7
Thickness in mm 7.1
Density in Kg per Cum 7850
WT per Meter in Kg 55.47
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.485
Wt of pair of flange in Kg 4.97
No of Nut bolts 36
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 7.2
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 309.70mm dia 5657.94 Kg 58.00 328160.52
Add GST 18.00% 59068.89
Cost of Pipe including GST 387229.41
Add entry tax 3.00% 11616.88
Add inspection Charges 0.50% 1936.15
Cost of pipe 400782.44
Carriage of pipes by mechanical transportation 1 Job 24754.49 24754.49
Carriage of pipes by head load 1 Job 285.00 285.00
Unloading and stacking 1 Job 285.00 285.00
Cost of Transportation of pipe 100 m length 25324.49
Cost of Pipe Welding 7733.47 cm 5.00 38667.35
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 5670.11 Kg 1.02 5783.51
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 6
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade Fe 410 with wall
thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.54
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 97.3
Outer side 101.76
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804199.06 Sqm 122.5 24384.85
Hasion cloth wraping
Clothe 1.02 Sqm 25.00 25.50
Bitumen 1.02 Sqm 40.00 40.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 163.23
Cost of wraping for 100 meters 100 Rmt 163.23 16323.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.439689.10 % 15.00% 65953.37
Pair of Flange 4.97 Kg 64.00 318.08
Nut Blots 7.2 Kg 59.75 430.2
Add GST 12.00% 51.62
Cost of Flanges including GST 799.9
Add entry tax 3.00% 24
Add inspection Charges 0.50% 4
Cost of flange 827.9
Gasket 2 No 105.00 210.00
Length of welding from inside 194.59 cm 5.00 972.95
Length of welding from outside 407.02 cm 5.00 2035.10
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 4052.31
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.3972.6897 % 15.00% 595.90
Cost of pair of flange 4648.21
Add 1% Labour Cess 443661.79 % 1.00% 4436.62
Add EPF 12.5% on all Labour 89212.14 % 12.50% 11151.52
Cost of Piping including all for 100 meter 598500.74
Cost of Piping including all per meter 5985.01
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.55
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 339.60 mm dia
Diameter in mm 339.6
Thickness in mm 8
Density in Kg per Cum 7850
WT per Meter in Kg 68.58
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 3.989
Wt of pair of flange in Kg 7.98
No of Nut bolts 48
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 9.6
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 339.60 mm dia 6995.16 Kg 58.00 405719.28
Add GST 18.00% 73029.47
Cost of Pipe including GST 478748.75
Add entry tax 3.00% 14362.46
Add inspection Charges 0.50% 2393.74
Cost of pipe 495504.95
Carriage of pipes by mechanical transportation 1 Job 24754.49 24754.49
Carriage of pipes by head load 1 Job 285.00 285.00
Unloading and stacking 1 Job 285.00 285.00
Cost of Transportation of pipe 100 m length 25324.49
Cost of Pipe Welding 8490.34 cm 5.00 42451.70
Labour for laying (Detail of cost for 514 kg)
Fitter 0.36 Nos 292.00 105.12
Assistant Fitter. 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 550.24
Cost of laying per Kg 1.07
Cost of laying of 100 m pipeline 7012.74 Kg 1.07 7503.63
Labour for jointing (Detail for 10 Joints.)
RATE ANALYSIS - 7
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade Fe 410 with wall
thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.56
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Plumber 0.30 Nos 292.00 87.60
Assistant plumber 0.30 Nos 292.00 87.60
Beldar. 1.20 Nos 250.00 300.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 485.20
Cost of laying per joint 48.52
Cost of Jointing of 100 m pipeline 19 Joints 48.52 921.88
Painting two or more coat in and out side of the pipe.
Innner side 106.69
Outer side 111.72
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804218.41 Sqm 122.5 26755.23
Hasion cloth wraping
Clothe 1.12 Sqm 25.00 28.00
Bitumen 1.12 Sqm 40.00 44.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 169.73
Cost of wraping for 100 meters 100 Rmt 169.73 16973.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.525649.21 % 15.00% 78847.38
Pair of Flange 7.98 Kg 64.00 510.72
Nut Blots 9.6 Kg 59.75 573.6
Add GST 12.00% 68.83
Cost of Flanges including GST 1153.15
Add entry tax 3.00% 34.59
Add inspection Charges 0.50% 5.77
Cost of flange 1193.51
Gasket 2 No 105.00 210.00
Length of welding from inside 213.38 cm 5.00 1066.90
Length of welding from outside 446.86 cm 5.00 2234.30
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 4717.43
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.4608.2394 % 15.00% 691.24
Cost of pair of flange 5408.67
Add 1% Labour Cess 530257.45 % 1.00% 5302.57
Add EPF 12.5% on all Labour 97906.64 % 12.50% 12238.33
Cost of Piping including all for 100 meter 717231.83
Cost of Piping including all per meter 7172.32
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.57
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 388.80 mm dia
Diameter in mm 388.8
Thickness in mm 8.8
Density in Kg per Cum 7850
WT per Meter in Kg 86.29
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 4.650
Wt of pair of flange in Kg 9.3
No of Nut bolts 48
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 9.6
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 388.80 mm dia 8801.58 Kg 58.00 510491.64
Add GST 18.00% 91888.5
Cost of Pipe including GST 602380.14
Add entry tax 3.00% 18071.4
Add inspection Charges 0.50% 3011.9
Cost of pipe 623463.44
Carriage of pipes by mechanical transportation 1 Job 24754.49 24754.49
Carriage of pipes by head load 1 Job 285.00 285.00
Unloading and stacking 1 Job 285.00 285.00
Cost of Transportation of pipe 100 m length 25324.49
Cost of Pipe Welding 9703.25 cm 5.00 48516.25
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 8820.48 Kg 1.02 8996.89
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 8
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade Fe 410 with wall
thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.58
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 122.15
Outer side 127.67
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804249.82 Sqm 122.5 30602.95
Hasion cloth wraping
Clothe 1.28 Sqm 25.00 32.00
Bitumen 1.28 Sqm 40.00 51.20
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 180.13
Cost of wraping for 100 meters 100 Rmt 180.13 18013.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.642990.60 % 15.00% 96448.59
Pair of Flange 9.3 Kg 64.00 595.2
Nut Blots 9.6 Kg 59.75 573.6
Add GST 12.00% 68.83
Cost of Flanges including GST 1237.63
Add entry tax 3.00% 37.13
Add inspection Charges 0.50% 6.19
Cost of flange 1280.95
Gasket 2 No 105.00 210.00
Length of welding from inside 244.29 cm 5.00 1221.45
Length of welding from outside 510.7 cm 5.00 2553.50
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 5278.62
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.5166.4694 % 15.00% 774.97
Cost of pair of flange 6053.59
Add 1% Labour Cess 648157.07 % 1.00% 6481.57
Add EPF 12.5% on all Labour 110949.42 % 12.50% 13868.68
Cost of Piping including all for 100 meter 878814.83
Cost of Piping including all per meter 8788.15
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.59
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Details of cost for 10 Cubic meters :
Sr. Item Unit Qty. Rate Amount
1 Pick Work
1 Labour : Beldar Each 8.32 250.00 2080
Bhisti Each 0.28 250.00 70
Add for water charges @ 1.5% 32.25
Total Rs. 2182.25
Add 10% for Contractor profit 218.23
Add 5% for overhead charges 109.11
Cost of 10 cubic meters Rs. 2509.59
Cost per cum Rs. 250.96
2 Chiselling work in hard rock (Where blasting is prohibitted)1 Labour:
Beldar Each 11.71 250.00 2927.50
Stone Chiseller Each 23.43 250.00 5857.50
Black smith (G-II) Each 0.59 292.00 172.28
Total 8957.28
Add 10% Contractor profit 895.73
Add 5% Overhead Charges 447.86
Cost of 10 cubic meters Rs. 10300.87
Cost per cum Rs. 1030.09
Classification of soil Amount
Pick Work (70%) 250.96 70% 175.67
Chiselling Work (Hard work) (30%) 1030.09 30% 309.03
Average Rate 484.70
Add labour cess @ 1.00 % 484.70 1% 4.85
Add 12 % GST 12.0% 58.16
Total Cost Rs. Per Cum 547.71
Analysis of Rates - 9
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m stacking the soil not more than 3 meters clear from
the edge of the excavation and then returning the stacked soil in 15cm layers, when required into the plinths sides of
foundations etc., consolidating each deposited layer by ramming and watering and then disposing of all surplus excavated
earth as directed within a lead of 20 meters.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.60
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Detail of cost for 10 cubic metre
1. Soft rock.
Sr. Item Unit Qty. Rate Amount.
Drilling equipment Day 0.18 3600.00 648.00
Material
Special gelatine (80%) kg. 2.520 75.00 189.00
Detonators ordinary 100 Nos 12.00 300.00 36.00
Safety fuse wire (coil 10 Mtrs length) Coil 1.00 75.00 75.00
Labour
Hole Driller each 0.54 250.00 135.00
Blaster each 0.36 250.00 90.00
Beldar each 6.67 250.00 1667.50
Total 2840.50
Add 10% Contractor profit 284.05
Add 5% Overhead Charges 142.03
Total 3266.58
Cost for 10 cum. 3266.58
Cost for 1 cum 326.66
Detail of cost for 10 cubic metre
2. Hard Rock
Drilling equipment Day 0.28 3600.00 1008.00
Material
Special gelatine (80 % ) Kg. 3.92 75.00 294.00
Detonators ordinary 100 Nos. 14.00 300.00 42.00
Safety fuse wire (coil 10 mtr. length ) Coil 1.25 75.00 93.75
Labour
Hole Driller Each 0.84 250.00 210.00
Blaster Each 0.56 250.00 140.00
Beldar Each 8.33 250.00 2082.50
Total 3870.25
Add 10% Contractor profit 387.025
Add 5% Overhead Charges 193.5125
Total 4450.79
Cost for 10 cum 4450.79
Cost of per cum 445.08
Classification of Rocks Amount
Soft Rock (70%) 326.66 70% 228.66
Hard Rock (30%) 445.08 30% 133.52
Average Rate 362.18
Add labour cess @ 1.00 % 362.18 1% 3.62
Add 12 % GST 12.0% 43.46
Total Cost Rs. Per Cum 409.27
Analysis of Rate - 10
Cutting in earth work and disposal of excavated earth upto a lead of 20 Mtrs soft rock.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.61
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand:
4graded stone aggregate 20 mm nominal size ) and
curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
1 1.30 1.30 0.15 0.25 Cum 7957.06 2017.11
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in Bottom raft slab
1 1 1 0.2 0.20 Cum 8,139.12 1627.82
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in Vertical Walls
2 0.6 0.2 0.75 0.18 Cum 8,139.12 1465.04
2 1 0.2 0.75 0.30 Cum 8,139.12 2441.74
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in chamber top cover
2 1 0.5 0.2 0.20 Cum 8,139.12 1627.82
As per Rate Analysis - 25
Chamber of size 600 mm X 600 mm X 750 mm
Rate Analysis -11
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.62
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
5
Providing tor steel reinforcement for RCC work
including bending binding and placing in position
complete, @ 80 Kg per Cum,
0.88 80 70.40 Kg 62.31 4386.82
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo
(Ballies) in Vertical Walls and Slab
For Foundation 1 1 1 1.00 Sqm 289.27 289.27
As per Rate Analysis - 18
Verical walls - inner face 4 0.6 0.75 1.80 Sqm 487.14 876.85
Verical walls - outer face 4 1 0.75 3.00 Sqm 487.14 1461.41
For Top Cover 1 1 1 1.00 Sqm 487.14 487.14
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 18681.03
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.63
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand:
4graded stone aggregate 20 mm nominal size ) and
curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
1 1.60 1.60 0.15 0.38 Cum 7957.06 3055.51
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in Bottom raft slab
1 1.3 1.3 0.2 0.34 Cum 8,139.12 2751.02
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in Vertical Walls
2 0.9 0.2 0.75 0.27 Cum 8,139.12 2197.56
2 1.3 0.2 0.75 0.39 Cum 8,139.12 3174.26
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in chamber top cover
3 1.3 0.43 0.2 0.34 Cum 8,139.12 2751.02
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work
including bending binding and placing in position
complete, @ 80 Kg per Cum,
1.34 80 106.88 Kg 62.31 6659.99
Rate Analysis -12
Chamber of size 900 mm X 900 mm X 750 mm
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.64
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo
(Ballies) in Vertical Walls and Slab
For Foundation 1 1.3 1.3 1.69 Sqm 289.27 488.86
As per Rate Analysis - 18
Verical walls - inner face 4 0.9 0.75 2.70 Sqm 487.14 1315.27
Verical walls - outer face 4 1.3 0.75 3.90 Sqm 487.14 1899.84
For Top Cover 1 1.3 1.3 1.69 Sqm 487.14 823.26
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 27116.61
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.65
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded
stone aggregate 20 mm nominal size ) and curing complete
e/c the cost of form work and reinforcement in foundation &
plinth. (PCC M-150)
1 1.90 1.90 0.15 0.54 Cum 7957.06 4308.75
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in Bottom raft
slab
1 1.6 1.6 0.2 0.51 Cum 8,139.12 4167.23
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in Vertical Walls
2 1.2 0.2 0.75 0.36 Cum 8,139.12 2930.08
2 1.6 0.2 0.75 0.48 Cum 8,139.12 3906.78
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in chamber top
cover
4 1.6 0.4 0.2 0.51 Cum 8,139.12 4167.23
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work including
bending binding and placing in position complete, @ 80 Kg per
Cum,
1.86 80 149.12 Kg 62.31 9292.09
Rate Analysis -13
Chamber of size 1200 mm X 1200 mm X 750 mm
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.66
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo (Ballies) in
Vertical Walls and Slab
For Foundation 1 1.6 1.6 2.56 Sqm 289.27 740.52
As per Rate Analysis - 18
Verical walls - inner face 4 1.2 0.75 3.60 Sqm 487.14 1753.70
Verical walls - outer face 4 1.6 0.75 4.80 Sqm 487.14 2338.26
For Top Cover 1 1.6 1.6 2.56 Sqm 487.14 1247.07
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 36851.71
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.67
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded stone
aggregate 20 mm nominal size ) and curing complete e/c the cost
of form work and reinforcement in foundation & plinth. (PCC M-
150)
1 2.20 2.20 0.15 0.73 Cum 7957.06 5776.82
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix of " M - 20 "
with 20 mm & down gauge nominal size graded stone aggregate)
& curing complete excluding the cost of form work & reinforcement
for reinforced concrete work in Bottom raft slab
1 1.9 1.9 0.2 0.72 Cum 8,139.12 5876.45
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix of " M - 20 "
with 20 mm & down gauge nominal size graded stone aggregate)
& curing complete excluding the cost of form work & reinforcement
for reinforced concrete work in Vertical Walls
2 1.5 0.2 0.75 0.45 Cum 8,139.12 3662.61
2 1.9 0.2 0.75 0.57 Cum 8,139.12 4639.30
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix of " M - 20 "
with 20 mm & down gauge nominal size graded stone aggregate)
& curing complete excluding the cost of form work & reinforcement
for reinforced concrete work in chamber top cover
5 1.9 0.38 0.2 0.72 Cum 8,139.12 5876.45
As per Rate Analysis - 25
5Providing tor steel reinforcement for RCC work including bending
binding and placing in position complete, @ 80 Kg per Cum,2.46 80 197.12 Kg 62.31 12283.10
As per Rate Analysis - 28
Rate Analysis -14
Chamber of size 1500 mm X 1500 mm X 750 mm
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.68
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
6Providing form work with steel plates and Bamboo (Ballies) in
Vertical Walls and Slab
For Foundation 1 1.9 1.9 3.61 Sqm 289.27 1044.25
As per Rate Analysis - 18
Verical walls - inner face 4 1.5 0.75 4.50 Sqm 487.14 2192.12
Verical walls - outer face 4 1.9 0.75 5.70 Sqm 487.14 2776.69
For Top Cover 1 1.9 1.9 3.61 Sqm 487.14 1758.57
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 47886.35
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.69
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. No. Item of work No L W D Quantity Rate Unit Amount
1 Excavation in foundation trenches etc. in earth work lift upto 1.5
mtr. stacking the excavated soil not more than 3 mtr. clear from
the edge of excavation and then returning the stacked soil in
15cm layers when required into plinths sides of foundation etc.
consolidating each deposited layer by ramming and watering
then disposing of all surplus soil as directed within a lead of
20mtr. in soft & hard rock.
1 1.35 1.65 1 2.23 547.71 Per cum. 1220.02
2 Prov. & laying cement conc.1:2:4(1cement:2sand:4graded stone
aggregate 20 mm nominal size ) and curing complete e/c the
cost of form work and reinforcement in foundation & plinth. 1 1.35 1.65 0.15 0.33 7957.06 Per Cum. 2658.65
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work &
reinforcement for reinforced concrete work in Bottom raft slab
(a)foundation footintg basis of columns and like mass concrete. 1 1.2 1.5 0.45 0.81 8,139.12 Per Cum. 6592.69
(b)Columns pillar posts and struts upto floor two level. 1 0.3 0.9 2.15 0.58 8139.12 Per Cum 4724.76
4 Providing mild steel/Tor steel reinforcement for R.C.C. work
including bending, binding and placing in position complete upto
floor two level. Tor steel.139.05 62.31 Per Kg. 8664.60
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Rate Anlysis - 15 SH:-Construction of RCC Anchor Block size 0.3m*0.9m
ABSTRACT OF COST
3
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.70
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. No. Item of work No L W D Quantity Rate Unit Amount
Providing form work with steel plates 3.15mm thick welded with
angle iron in frame 30x30x5mm so as to give a fair finish
including centring shuttering strutting and propping etc., with
wooden battens and ballies, height of propping and centring
below supporting floor to ceiling not exceeding 4 meters and
removal of the same for in-situ-reinforced concrete and plain
concrete work in:-
a)Foundation, footing, basis of columns etc., and mass
concrete. 2.43 289.27 Per Sqmt. 702.92
b) Columns pillar posts and struts square, rectangular or
polygonal in plan. 5.16 487.14 Per Sqmt. 2513.63
27077.27Total Rs. In Lac.
5
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.71
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L W D Qty Unit Rate Amount
1
Construction of granular sub-base by providing close
graded Material conforming to specifications, mixing in a
mechanical mix plant at OMC, carriage of mixed material
by tippers to work site, for all leads & lifts, spreading in
uniform layers of specified thickness with motor grader on
prepared surface and compacting with vibratory power
roller to achieve the desired density, complete as per
specifications and directions of Engineer-in-Charge.
With material conforming to Grade-I (size range 75 mm to
0.075 mm) having CBR Value-30 CPWD DSR Vol 2
16.78.1
1 1 1 0.2 0.2 Cum 2089.7 417.94
2Providing and constructing WBM CPWD DSR Vol 2
16.13.21 1 1 0.175 0.175 Cum 1407.15 246.25
3
Providing and laying bituminous macadam using crushed
stone aggregates of specified grading premixed with
bituminous binder, transported to site by tippers, laid over
a previously prepared surface with paver finisher equiped
with electronic sensor to the required grade, level and
alignment and rolling with smooth wheeled, vibratory and
tandem rollers as per specifications to achieve the
desired compaction and density, complete as per
specificatons and directions of Engineer-in-Charge.
50 to 100 mm average compacted thickness with bitumen
of grade VG-30 @ 3.50% (percentage by weight of total
mix) prepared in Batch Type Hot Mix Plant of 100- 120
TPH capacity. CPWD DSR Vol 2 16.55.1
1 1 1 0.075 0.075 Cum 5708.05 428.10
Rate Analysis -16 : Road Restoration
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.72
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L W D Qty Unit Rate Amount
4
2.5 cm premix carpet surfacing with 2.25 cum and 1.12
cum of stone chippings of 13.2 mm and 11.2 mm size
respectively per 100 sqm and 52 kg and 56 kg of hot
bitumen per cum of stone chippings of 13.2 mm and 11.2
mm size respectively, including a tack coat with hot
straight run bitumen, including consolidation with
road roller of 6 to 9 tonne capacity etc. complete (tack coat
to be paid for separately). With paving Asphalt grade VG -
10 heated and then mixed with solvent at the rate of 70
grams per kg of asphalt CPWD DSR Vol 2 16.33.1
1 1 1 1 Sqm 169.6 169.60
Total 1261.90
Add 12% for GST 151.43
Total 1413.32
Say 1400.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.73
Shimla Jal Prabandhan Nigam Limited Rate Analysis
A
B
C
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
A Water Supply Connections
ROVIDING & LAYING IN TRENCHES GALVANISED MILD STEEL
PIPE CONFORMING TO IS 1239/1990 (5th Revision) HEAVY
CLASS INCLUDING BENDS OF ALL DEGREES, TEES, COLLARS,
TAPERS, CROSSES, FLANGED SOCKET & SPIGOTS AND
JOINTING
As per RA
i) Residential Connections- 15 mm dia 29 5 145 Rmt 200.96 29139.62
ii) Commercial Connections- 25mm dia 4 5 20 Rmt 243.58 4871.66
34011.27
B Electrical Lines & Poles
B-1 Electrical Poles - RA for 10 km
RATE ANALYSIS - 17
Utility Shifting:
1 nos of breakage per km occurred with required of cable length per breakage is assumed as 6 m. 3.0 mtr assumed as Optical cable and 3.0 metre Jelly filled
telephone cable
Amount A / 1 Km
Assumptions
Water Supply Connections
Total No. of properties in 1.00 Km length in city Area Consider property connection at 30 mtr distance is 1000/30 = 34 Nos, Assuming that out of 34 Nos 10% are
commercial connections and 90% are residential Connections. Commercial connections are of 25mm in size and Residential connections are 15 mm Size hence
Commercial connections are 4 Nos. and Residential Connections are 29 Nos Per Km. Connections Pipe length per connections are assumed as 2.5 mtr.
Electrical Lines & Poles
For RA purpose, shifting of one pole per 10 km length of network in city area , Hence RA is estimated for 10 km length. Electrical Cable joints required per km is
assumed as 2 nos
Communication Cable - Jelly Filled telephone lines and optical Fibre Cable
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.74
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
i)
Pole Foundation : providing cement concrete foundation including
excavation for the pole 60 cms x 60 cms x 1.5 mtr deep in1:3:6
cement concrete (20x 25 mm stone metal) and 45 cm x 45cm x45
cm / 45 cm x 45 cm height plinth duly plaster and with necessary
curing & finishing in above manner ( for 9 mtr pole)
1 1 Nos 3158.4 3158.40
PWD DSR 16-17 E&M, Item No. 16.3.2, Page No.306
ii)
Dismantling of existing poles above 6 mtr height with brackets.
Clamps, insulators stay from the cement concrete foundation and
making the site clear by refilling the pits with excavated materials and
bringing it to ground level
1 1 Nos 840 840.00
PWD DSR 16-17 E&M, Item No. 8.8.2, Page No. 191
i)
Re-Erecting: Supplying and erecting steel tubular swaged pole 165.1
X 139.7 X 114.3 mm dia with 4.5 X 4.5 X3.65 mm thick (5+2+2m)
length respectively and total 9 m long with pole cap, base plate in
provided foundation (weight 147 kg) as per specifications.
1 1 Nos 13971.3 13971.30
PWD DSR 16-17 E&M, Item No. 8.1.3, Page No. 174
i)
Earthling : Providing pipe type earthing with 40mm. dia.G.l. pipe or 20
mm dia. G.l. Rod complete with all materials as per specification No.
EA-EP
1 1 Nos 1597.05 1597.05
i) PWD DSR 16-17 E&M, Item No. 9.1.4, Page No. 193
19566.75
1956.68
B-2 Electrical Cable - Providing and Jointing 391.34
CCommunication Cable - Jelly Filled telephone lines and optical Fibre
Cable
i)
Supply & Erecting of Jelly filled armoured telephone cable 10 pair
with 0.5 mm dia laid in provided trench as per specification no. WG-
TW
1 3 3 Rmt 114.45 343.35
PWD DSR 16-17 Item 1-10-10, Page No. 38
Amount B-1 /10 km
Amount B-1/ 1 Km
Amount B-2/ 1 Km
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.75
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
ii)
Supply & erecting of FR grade PVC armourd multi mode Optical
Fibre Cable with 6 fibres with core dia 50 µM, suitable for 1 GBps
Ethernet distance at 850 nm of wavelength on wall/ ceiling or laid in
provided pipe / trench as per specification no. WG- COC/ OFC
1 3 3 Rmt 236.25 708.75
PWD DSR 16-17 Item 1-12-8, Page No.41
iii)
Supply & fixing of wall /rack type 12 port light guide interconnection
unit for termination of optical fibre cable on wall /provided U rack
complete as per specification no. EG- NAS / LIU
1 1 Nos 4586.4 4586.40
PWD DSR 16-17 Item 1-14-5, Page No. 44 5638.50
41998.00
50397.60Total rate of utility Shifting per Km considering this project
Total rate of utility Shifting per Km for Maharashtra is
Amount C-1/ 1 Km
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.76
Shimla Jal Prabandhan Nigam Limited Rate Analysis
(a)Foundation footing basis of columns etc and mass concrete
Detail of cost for 10 Sqm.
Sr. Description. Unit Qty. Rate. Amount
Material
Rate as per above in Sub Analysis. Sqm. 10.15200 6174.44 62682.92
Battens IInd class kail wood
6 X 1 X 0.075 X 0.10m. = 0.045 cum.
Wastage @ 5% per kg. = 0.002 cum.
Total Qty:- = 0.047 cum.. Cum. 0.047 33,830.00 1590.01
Ballies 125mm dia Kail wood
6 X 1.50 = 9.00 Rmt.
Wastage @ 5% per kg. = 0.45Rmt.
Total Qty:- =9.45 Rmt. Rmt. 9.45 125.00 1181.25
Carriage of Timber :-
Ballies 125mm dia Kail wood
9.45 X 0.785 X (0.125)2 = 0.116 cum.
Battens IInd class kail wood =0.047 cum.
Total Qty:- = 0.163 cum..
50 K.M.by Mechanical Transport. Cum. 0.163 178.91 29.16
0.5 M.by head load. Cum. 0.163 485.53 79.14
Total Rs:- 2879.56
Carriage cost of wood i.e.1/16 Rs:- 6.77
Each. 0.01 62682.92 626.83
cent 0.01 62682.92 626.83
ANALYSIS OF RATES - 18
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Assuming that steel plates shall become unservicable after being used 100
times. Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling oiling and greasing etc.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.77
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cum. 0.0625 2879.56 179.97
cent 0.05 2879.56 143.98
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.52 292.00 151.84
Beldar. Each. 1.30 250.00 325
Total Rs:- 2054.45
Sundries @ 10% of labour cost. Rs:- 205.445
Total Rs:- 2259.895
Add 10% Contractor profit 225.99
Add 5% Overhead Charges 112.99
Add labour cess @ 1.00 % 22.60
Add 12 % GST 271.192892.67
289.27
Add 5% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling
Cost for 10 Sq.m
Cost per Sqmt. Rs:-
Assuming that Timber shall become unservicable after being used 16
times.Hence cost for using once = 1/16
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.78
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
d)Columns,Pillar;Posts and struts Square Rectangular and Polygonal in Plan
Sr. Description. Unit Qty. Rate. Amount
Rate as per above in Sub Analysis. Sqm. 5.46 6174.44 33712.44
Ballies 125mm dia.(Kail wood 2nd class.) Meter 15.96 125.00 1995.00
50 Carriage of Timber :-K.M.by Mechanical Transport. Cum. 0.196 178.91 35.07
0.5 Carriage of Timber :-M.by head load. Cum. 0.196 485.53 95.16
Total Rs:- 2125.23
Carriage cost of wood i.e.1/16 Rs:- 8.14
Each. 0.01 33712.44 337.12
cent 0.01 33712.44 337.12
Cum. 0.0625 2125.23 132.83
cent 0.05 2125.23 106.26
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.59 292.00 172.28
Beldar. Each. 1.47 250.00 367.50
Total Rs:- 1453.11
Sundries @ 10% of labour cost. On Rs:- 539.78 Rs:- 145.311
Total Rs:- 1598.421
Add 10% Contractor profit 159.84
Add 5% Overhead Charges 79.92
Add labour cess @ 1.00 % 15.98
ANALYSIS OF RATES - 19
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Detail of cost for area in contact 4 X 0.30 X 3.50 = 4.20 Sqm.
Assuming that steel plates shall become unservicable after being used 100
times.Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling oiling and greasing etc.
Assuming that Timber shall become unservicable after being used 16
times.Hence cost for using once = 1/16
Add 5% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.79
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Add 12 % GST 191.812045.98
487.14Cost per Sqmt. Rs:-
Cost for 10 Sq.m
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.80
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Sr. Description. Unit Qty. Rate. Amount
Material:-
3.15 mm Thick M.S. Plate.
0.90 X 0.60 = 0.54 Sqm.
Weight @ 24.72kg per Sqm. =13.35kg.
Wastage @ 5% per kg. =0.66kg
Total Qty:- =14.01kg or 0.14 Qtl. Qtl. 0.14 4500.00 630.00
Angle iron in frame 30X30X5mm Size
2(0.90+0.60) = = 3.00 Rmt.
Weight @ 2.20kg per Rmt.. =13.35kg.
Wastage @ 5% per kg. =0.33kg
Total Qty:- =6.93kg or 0.0693 Qtl. Qtl. 0.0693 5,000.00 346.50
Sub Total Rs. 976.50 A
Carriage of M.S. Plate and angles.
M.S.Plate. = 0.140 Qtl
Angle iron =0.0693 Qtl.
Total Qty:- =0.2093 Qtl or 0.02093 Tonne.
50 K.M.by Mechanical Transport. Tonne 0.02093 178.91 3.74
0.5 M.by head load. Tonne 0.02093 485.53 10.16
Sub Total Rs. 13.90 B
Labour.
Black Smith Ist. Class. Each 0.066 292.00 19.27
Bandhani Each 0.066 250.00 16.50
Beldar Each 0.154 250.00 38.5
Sundries Each 10
Sub Total Rs. 84.27 C
ANALYSIS OF RATES - 20
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for
shuttering steel work welded in built up section I/c cutting fixing in positionin angles,plates etc. Detail of cost for 90cm X 60cm size of plates
complete 0.54 Sqm.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.81
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Welding charges by Electric Plant CM. 300.00 5.00 1500.00 D
Total Rs. (A+B+C+D) 2574.67
Add 1.5% water charges. Rs:- 38.62
Add 10% Contractor profit 257.47
Add 5% Overhead Charges 128.73
Add labour cess @ 1.00 % 25.75
Add 12 % GST 308.963334.20
6174.44
Cost for 0.54 Sqmt.Rs:-
Cost per Sqmt. Rs:-
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.82
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Discription Unit Qty. Rate Amount
Materials
Cement Tonne 0.32 5,120.00 1638.40
Sand Cum 0.445 650.00 289.25
10mm stone aggregate Cum 0.22 725.00 159.50
20mm stone aggregate Cum 0.67 725.00 485.75
Subtotal 2572.90 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.89 1875.18 1668.91
0 K.M. by Head Load Cum 0.89 390.34 347.40
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.45 1090.33 490.65
0 K.M. by Head Load Cum 0.45 390.34 175.65
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.32 178.91 57.25
0 K.M. by Head Load Tonne 0.32 230.04 73.61
Subtotal 2813.47 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
RATE ANALYSIS - 21
Providing & laying cement concrete 1:2:4, 20mm nominal size & curing complete for RCC work in: Suspended floor, roofs, landing and shelves and their
supports, balconies, beams, girders, bressumers and cantilever upto floor two level.
Details of Cost for 1 Cubic Meter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.83
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 693.65 (C)
(A+B+C) 6080.02
Add for water charges @1.5% 6,080.02 1.50% 91.20
6171.22
Add 1% Labour cess 6,171.22 1.00% 61.71
Add GST 12.00% 740.55
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4532.82 15% 679.92
Rs:- 7,653.40
Total
Gross Total
Cost for one cubic meter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.84
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.165 5,758.44 950.14
Subtotal 950.14 (A)
Labour :
Mason II nd class Each 0.80 294.00 235.20
Beldar Each 0.80 245.00 196.00
Bhishti Each 0.98 245.00 240.10
Sundries(Scaffolding etc.) L.S. 45.00
Subtotal 716.30 (B)
Total (A+B) 1666.44
Add for water charges @1.5% 1,666.44 1.50% 25.00
Gross Total 1691.44
Add 1% Labour cess 1,691.44 1.00% 16.91
Add GST 12.00% 202.97
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement741.30 15% 111.20
Cost for 10 square meter Rs:- 2,022.52
Cost of 1 Sqm. Rs:- 202.25
20 mm cement plaster in single coat on fair side f brick/stone masonry for interior plastering up to floor two level including arrises, internal rounded angles,
chamfers and/or rounded angles not exceeding 80mm in girth and finished even and smooth .
In cement mortar 1:4
Details of cost for 10 Sqm.
Desciption
RATE ANALYSIS - 22
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.85
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.224 6,592.42 1476.7
Sand & Gravel Crushed stone graded from 6 mm to 12mm Cum. 0.1 725.00 72.5
Grounded hydrated lime Kg 9.28 100.00 928
Subtotal 2477.2 (A)
Labour :
Mason II nd class Each 1.71 294.00 502.74
Beldar Each 1.58 245.00 387.10
Bhishti Each 1.7 245.00 416.50
Sundries(Scaffolding etc.) L.S. 45.00
Extra labour for coping
Mason II nd class Each 0.25 294.00 73.50
beldar Each 0.25 245.00 61.25
Extra labour for dashing of crushed stone
RATE ANALYSIS - 23
Rough side exterior cement plaster on wall up to a height of 10 mtr. above ground level with a mixture of sand and gravel or crushed stone graded from 6mm
to 12 mm nominal size dashed over and including fresh plaster in two coats, backing coat 10 mm cement plaster 1:3 (1cement:3sand) and finishing coat 10
mm cement mortor 1:3 (1cement:3sand) mixed with 10 % finely grounded hydrated lime by volume of cement including arrises, chamfersb and/or rounded
angles not exceeding 80 mm in girth. (natural cement finish using ordinary cement)
In cement mortar 1:3
Details of cost for 10 Sqm.
Desciption
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.86
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Mason II nd class Each 0.5 294.00 147.00
beldar Each 0.5 245.00 122.50
bhisti Each 0.1 245.00 24.50
sundries ( scaffolding etc.) 10.00
Subtotal 1790.09 (B)
Total (A+B) 4267.29
Add for water charges @1.5% 4,267.29 1.50% 64.01
Gross Total 4331.30
Add 1% Labour cess 4,331.30 1.00% 43.31
Add GST 12.00% 519.76
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2854.60 15% 428.19
Cost for 10 square meter Rs:- 5,322.56
Cost of 1 Sqm. Rs:- 532.26
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.87
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 1875.18 1593.90
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 1090.33 463.39
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 178.91 71.56
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 2718.55 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Discription
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 24
Prov.& laying c.conc. 1:2:4 (1cement:2 sand:4 graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work & reinforcement for
RCC work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.88
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 6361.03
Add for water charges @1.5% 6,361.03 1.50% 95.42
Gross Total 6456.45
Add 1% Labour cess 6,456.45 1.00% 64.56
Add GST 12.00% 774.77
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4408.45 15% 661.27
Cost for one cubic meter Rs:- 7,957.06
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.89
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 1875.18 1593.90
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 1090.33 463.39
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 178.91 71.56
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 2718.55 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
RATE ANALYSIS - 25
P/L cement concrete 1:1.5:3 (1cement:2sand:4graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work in
suspended floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level.
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.90
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 842.12 ( C)
Total (A+B+C) 6501.17
Add for water charges @1.5% 6,501.17 1.50% 97.52
Gross Total 6598.69
Add 1% Labour cess 6,598.69 1.00% 65.99
Add GST 12.00% 791.84
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4550.69 15% 682.60
Cost for one cubic meter Rs:- 8,139.12
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.91
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 1875.18 1425.14
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 1090.33 272.58
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 178.91 109.14
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 2341.43 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 294.00 79.38
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 245.00 12.25
Mate Each 0.04 245.00 9.80
RATE ANALYSIS - 26
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work
in suspended floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level. (Slab for For RCC GSR)
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.92
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Beldar for extra ramming Each 0.25 0.00 0.00
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 791.65 ( C)
Total (A+B+C) 6969.78
Add for water charges @1.5% 6,969.78 1.50% 104.55
Gross Total 7074.33
Add 1% Labour cess 7,074.33 1.00% 70.74
Add GST 12.00% 848.92
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement3951.13 15% 592.67
Cost for one cubic meter Rs:- 8,586.66
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.93
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 1875.18 1425.14
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 1090.33 272.58
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 178.91 109.14
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 2341.43 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Discription
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 27
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work &
reinforcement for RCC work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level. (Wall for For
RCC GSR)
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.94
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 6880.11
Add for water charges @1.5% 6,880.11 1.50% 103.20
Gross Total 6983.31
Add 1% Labour cess 6,983.31 1.00% 69.83
Add GST 12.00% 838.00
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement3860.11 15% 579.02
Cost for one cubic meter Rs:- 8,470.16
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.95
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty Rate Amount
Material:-
Mild Steel Bars Qtl. 1.00
Wastage @ 5% Qtl. 0.05
Total 1.05 Qtl. 1.05 4,500.00 4725.00 (A)
By Mech TransportK.M By Mechanical Transport Tonne 0.105 178.91 18.79
0 K.M ByHead load. Tonne 0.105 485.53 50.98
Subtotal 69.77 (B)
Labour:-
Black Smith Ist class Each 1.00 292.00 292.00
Beldar Each 1.00 245.00 245.00
Sundries LS 10.00
Subtotal 547.00 ( C)
Total (A+B+C) 5341.77
Add for water charges @1.5% 5,341.77 1.50% 80.13
Gross Total 5421.90
Add 1% Labour cess 5,421.90 1.00% 54.22
Add GST 12.00% 650.63
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Steel
696.90 15% 104.54
Cost per Qtl Rs:- 6,231.28
Cost per Kg Rs:- 62.31
RATE ANALYSIS - 28
Providing mild steel/tor steel reinforcement for RCC work includng bending binding and placing in position complete.
Detail of cost for 1 Qtl.
Description.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.96
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:4 ( 1CEMENT : 4SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.38 5,120.00 1,945.60
Sand Cum 1.07 650.00 695.50
Subtotal 2,641.10 (A)
Carriage
Carriage of Sand
106 K.M. by Mechanical Transport Cum 1.07 1090.33 1,166.65
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.38 178.91 67.99
0 K.M. by Head Load Tonne 0.38 230.04 87.42
Subtotal 1,739.72 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 4,656.94
Add for water charges @1.5% 4,656.94 1.50% 69.85
Gross Total 4726.79
Add 1% Labour cess 4,726.79 1.00% 47.27
Add GST 12.00% 567.21
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2781.19 15% 417.18
Cost for one cubic meter Rs:- 5,758.44
Details of cost for 1cum
RATE ANALYSIS - 29
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.97
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:3 ( 1CEMENT : 3SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.51 5,120.00 2,611.20
Sand Cum 1.07 650.00 695.50
Subtotal 3,306.70 (A)
Carriage
Carriage of Sand
0 K.M. by Mechanical Transport Cum 1.07 1090.33 1,166.65
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.51 178.91 91.24
0 K.M. by Head Load Tonne 0.51 230.04 117.32
Subtotal 1,792.87 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 5,375.69
Add for water charges @1.5% 5,375.69 1.50% 80.64
Gross Total 5456.33
Add 1% Labour cess 5,456.33 1.00% 54.56
Add GST 12.00% 654.76
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2845.13 15% 426.77
Cost for one cubic meter Rs:- 6,592.42
RATE ANALYSIS - 30
Details of cost for 1cum
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.98
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 80 mm dia 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including
transportation141583 144910 180046 248238 327866 366120 467786 645336 694402 967589 1100586
Add for jointing
material 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Add for laying, jointing
labour10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Total 161583.00 164910.00 200046.00 278238.00 357866.00 396120.00 507786.00 685336.00 734402.00 1017589.00 1150586.00
Add 18% for GST 29084.94 29683.80 36008.28 50082.84 64415.88 71301.60 91401.48 123360.48 132192.36 183166.02 207105.48
Add 15% OH and CP 19066.79 19459.38 23605.43 32832.08 42228.19 46742.16 59918.75 80869.65 86659.44 120075.50 135769.15
Rate Including GST 209734.73 214053.18 259659.71 361152.92 464510.07 514163.76 659106.23 889566.13 953253.80 1320830.52 1493460.63
Particulars 80 mm dia 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including
transportation9543 12589 19822 32940 45622 68951 175000 213462 326923 476923
Add for jointing
material 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Add for laying, jointing
labour10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Total 29543.00 32589.00 39822.00 62940.00 75622.00 98951.00 40000.00 215000.00 253462.00 376923.00 526923.00
Add 18% for GST 5317.74 5866.02 7167.96 11329.20 13611.96 17811.18 7200.00 38700.00 45623.16 67846.14 94846.14
Add 15% OH and CP 3486.07 3845.50 4699.00 7426.92 8923.40 11676.22 4720.00 25370.00 29908.52 44476.91 62176.91
Rate Including GST 38346.81 42300.52 51688.96 81696.12 98157.36 128438.40 51920.00 279070.00 328993.68 489246.05 683946.05
Rate Analysis -33 for Isolation and Scour Valves
Rate Analysis -32 for FCV and PRV
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.99
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 25 mm dia 50 mm dia 80 mm dia 100 mm dia 150 mm dia Particulars Cost
Basic rate including
transportationNA 18991 25312 40474 56360
Basic rate
including
transportation
28651
Add for jointing
material 5000 5000 10000 10000 10000
Add for
jointing
material
2000
Add for laying, jointing
labour5000 5000 10000 10000 10000
Add for
laying, jointing
labour
3000
Total 10000.00 28991.00 45312.00 60474.00 76360.00 Total 33651.00
Add 18% for GST 1800.00 5218.38 8156.16 10885.32 13744.80Add 18% for
GST 6057.18
Add 15% OH and CP 1180.00 3420.94 5346.82 7135.93 9010.48Add 15% OH
and CP3970.82
Rate Including GST NA 37630.32 58814.98 78495.25 99115.28
Rate
Including
GST
43679.00
Rate Analysis -34 for Air ValvesRate Analysis -35 for
Pressure Transmitter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.100
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including
transportation98041 105692 125138 138297 158618 219362 249122 266894 310486 357802
Add for jointing
material
Add for laying, jointing
labour
Total 98041.00 105692.00 125138.00 138297.00 158618.00 219362.00 249122.00 266894.00 310486.00 357802.00
Add 18% for GST 17647.38 19024.56 22524.84 24893.46 28551.24 39485.16 44841.96 48040.92 55887.48 64404.36
Add 15% OH and CP 11568.84 12471.66 14766.28 16319.05 18716.92 25884.72 29396.40 31493.49 36637.35 42220.64
Rate Including GST 127257.22 137188.22 162429.12 179509.51 205886.16 284731.88 323360.36 346428.41 403010.83 464427.00
Rate Analysis -36 for Flow (Bulk) Meter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.101
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 15 mm dia 20 mm dia 25 mm dia Particulars 15 mm dia 20 mm dia 25 mm dia
Basic rate including
transportation7984 8708 10154
Basic rate
including
transportation
6487 9979 12973
Add for jointing
material
Add for
jointing
material
500 500 500
Add for laying, jointing
labour
Add for
laying, jointing
labour
500 500 500
Total 7984.00 8708.00 10154.00 Total 7487.00 10979.00 13973.00
Add 18% for GST 1437.12 1567.44 1827.72Add 18% for
GST 1347.66 1976.22 2515.14
Add 15% OH and CP 942.11 1027.54 1198.17Add 15% OH
and CP883.47 1295.52 1648.81
Rate Including GST 10363.23 11302.98 13179.89
Rate
Including
GST
9718.13 14250.74 18136.95
Rate Analysis - 37 for AMR Consumer Meter Rate Analysis - 38 for Direct Acting PRV
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.102
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description 15 mm 20 mm 25 mm
1
Providing and fixing brass ferrule with C.I. mouth cover
including boring and tapping the main CPWD DSR
18.20, P.N. 1200
243.6 280.65 363.7
2
Providing and fixing G.I. pipes complete with G.I. fittings
including trenching and refilling etc.CPWD DSR 18.12,
P.N. 1187
1602 1863 2058.5
3
Painting G.I. pipes and fittings with synthetic enamel
white paint with two coats over a ready mixed priming
coat, both of approved quality for new work :CPWD DSR
18.38, P.N. 1236
99.5 118 155
4
Providing and fixing G.I. Union in G.I. pipe including
cutting and threading the pipe and making long screws
etc. complete (New work) CPWD DSR 18.46, P.N. 1252
295.5 341.9 411.6
5
Providing and fixing ball valve (brass) of approved
quality, High or low pressure, with plastic floats complete
: CPWD DSR 18.46, P.N. 1252
287.25 327.05 331.95
6
Constructing masonry Chamber 30x30x50 cm inside, in
brick work in cement mortar 1:4 (1 cement :4 coarse
sand) for stop cock, with C. I. surface box 100x100 x75
mm (inside) with hinged cover fixed in cement concrete
slab 1:2:4
mix (1 cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size), i/c necessary
excavation, foundation concrete 1:5:10 ( 1 cement : 5
fine sand : 10 graded stone aggregate 40mm nominal
size ) and inside plastering with cement mortar 1:3 (1
cement : 3 coarse sand) 12mm thick, finished with a
floating coat of neat cement complete as per standard
design CPWD DSR 18.46, P.N. 1252
1195.35 1195.35 1195.35
Total 3723.2 4125.95 4516.1
Above rates are of CPWD DSR 2016, hence increase
35% for 2021. Hence Final Rate5026.32 5570.0325 6096.735
Rate Analysis - 39 for House Service Connection
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.103
Shimla Jal Prabandhan Nigam Limited M and R
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
1 2020 243250 21818159 17011771 5909500 22921271 2.88
2 2021 248264 23141800 18208128 6204975 24413103 2.89
3 2022 253279 24465441 19488636 6515224 26003860 2.91
4 2023 258293 25789082 20859588 6840985 27700573 2.94
5 2024 263308 27112724 22326276 7183034 29509310 2.98
6 2025 268322 28436365 23895660 7542186 31437846 3.03
7 2026 273337 29760006 25576476 7919295 33495771 3.08
8 2027 278351 31083647 27375720 8315260 35690980 3.15
9 2028 283366 32407288 29300496 8731023 38031519 3.22
10 2029 288380 33730929 31361244 9167574 40528818 3.29
11 2030 293395 35054571 33566772 9625953 43192725 3.38
12 2031 298409 36378212 35927592 10107250 46034842 3.47
13 2032 303424 37701853 38454252 10612613 49066865 3.57
O & M EXPENDITURE STATEMENT
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.104
Shimla Jal Prabandhan Nigam Limited M and R
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
14 2033 308438 39025494 41159040 11143244 52302284 3.67
15 2034 313453 40349135 44054244 11700406 55754650 3.79
16 2035 318467 41672776 47153928 12285426 59439354 3.91
17 2036 324814 43403489 50472156 12899697 63371853 4
18 2037 331161 45134202 54023064 13544682 67567746 4.1
19 2038 337508 46864915 57824232 14221916 72046148 4.21
20 2039 343856 48595628 61893276 14933012 76826288 4.33
21 2040 350203 50326341 66249516 15679663 81929179 4.46
22 2041 356550 52057054 70912452 16463646 87376098 4.6
23 2042 362897 53787767 75903252 17286828 93190080 4.75
24 2043 369244 55518480 81244860 18151170 99396030 4.9
25 2044 375591 57249193 86963700 19058728 106022428 5.07
26 2045 381938 58979906 93084600 20011665 113096265 5.25
27 2046 388285 60710619 99637536 21012248 120649784 5.44
28 2047 394633 62441332 106650924 22062860 128713784 5.65
29 2048 400980 64172045 114159996 23166003 137325999 5.86
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.105
Shimla Jal Prabandhan Nigam Limited M and R
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
30 2049 407327 65902758 122196792 24324303 146521095 6.09
31 2050 413674 67633471 130800204 25540518 156340722 6.33
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.106
Shimla Jal Prabandhan Nigam Limited M and R
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2020 3.0 14850 534600 0 12690 0 25 9878 2963520 114 9878 13513651 17011771
2021 3.0 16038 577368 0 13705 0 25 10570 3171000 114 10570 14459760 18208128
2022 3.0 17321 623556 0 14801 0 25 11310 3393000 114 11310 15472080 19488636
2023 3.0 18707 673452 0 15985 0 25 12102 3630600 114 12102 16555536 20859588
2024 3.0 20204 727344 0 17264 0 25 12949 3884700 114 12949 17714232 22326276
2025 3.0 21820 785520 0 18645 0 25 13855 4156500 114 13855 18953640 23895660
2026 3.0 23566 848376 0 20137 0 25 14825 4447500 114 14825 20280600 25576476
2027 3.0 25451 916236 0 21748 0 25 15863 4758900 114 15863 21700584 27375720
2028 3.0 27487 989532 0 23488 0 25 16973 5091900 114 16973 23219064 29300496
2029 3.0 29686 1068696 0 25367 0 25 18161 5448300 114 18161 24844248 31361244
2030 3.0 32061 1154196 0 27396 0 25 19432 5829600 114 19432 26582976 33566772
2031 3.0 34626 1246536 0 29588 0 25 20792 6237600 114 20792 28443456 35927592
2032 3.0 37396 1346256 0 31955 0 25 22247 6674100 114 22247 30433896 38454252
2033 3.0 40388 1453968 0 34511 0 25 23804 7141200 114 23804 32563872 41159040
2034 3.0 43619 1570284 0 37272 0 25 25470 7641000 114 25470 34842960 44054244
2035 3.0 47109 1695924 0 40254 0 25 27253 8175900 114 27253 37282104 47153928
ESTABLISHMENT CHARGES
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.107
Shimla Jal Prabandhan Nigam Limited M and R
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2036 3.0 50878 1831608 0 43474 0 25 29161 8748300 114 29161 39892248 50472156
2037 3.0 54948 1978128 0 46952 0 25 31202 9360600 114 31202 42684336 54023064
2038 3.0 59344 2136384 0 50708 0 25 33386 10015800 114 33386 45672048 57824232
2039 3.0 64092 2307312 0 54765 0 25 35723 10716900 114 35723 48869064 61893276
2040 3.0 69219 2491884 0 59146 0 25 38224 11467200 114 38224 52290432 66249516
2041 3.0 74757 2691252 0 63878 0 25 40900 12270000 114 40900 55951200 70912452
2042 3.0 80738 2906568 0 68988 0 25 43763 13128900 114 43763 59867784 75903252
2043 3.0 87197 3139092 0 74507 0 25 46826 14047800 114 46826 64057968 81244860
2044 3.0 94173 3390228 0 80468 0 25 50104 15031200 114 50104 68542272 86963700
2045 3.0 101707 3661452 0 86905 0 25 53611 16083300 114 53611 73339848 93084600
2046 3.0 109844 3954384 0 93857 0 25 57364 17209200 114 57364 78473952 99637536
2047 3.0 118632 4270752 0 101366 0 25 61379 18413700 114 61379 83966472 106650924
2048 3.0 128123 4612428 0 109475 0 25 65676 19702800 114 65676 89844768 114159996
2049 3.0 138373 4981428 0 118233 0 25 70273 21081900 114 70273 96133464 122196792
2050 3.0 149443 5379948 0 127692 0 25 75192 22557600 114 75192 102862656 130800204
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.108
Shimla Jal Prabandhan Nigam Limited M and R
Sr. No. SubworksNo of
Units
Superinte
ndent
Manager
(A.E.E.)
Supervisor
/Asstt.
Manager
(A.E.)
Assitant
Supervisor/
Junior
manager
Operators Fitters HelpersElectrician/
MechanicWatchman
1 Pump House 0.00 0 0 0 0 0 0 0 0
2 RWRM 0.00 0 0 0 0 0 0 0 0
3 WTP 0.00 0 0 0 0 0 0 0 0
4 PWRM 0.00 0 0 0 0 0 0 0 0
5 ESR/GSR 64.00 0 0 0 0 0 0 0 64
6 Gravity Main 0.00 0 0 0 0 0 0 0 0
7 D/System 25.00 0 0 0 0 25 50 0 0
Automation 1 0 3
0 3 0 0 25 50 0 64
Staff Pattern
Total
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.109
Shimla Jal Prabandhan Nigam Limited M and R
Annual M &
R Charges
Annual
Depreciation
(3x8) (5x7)
1 2 3 4 5 6 7 8 9 10
For Proposed Components
1
Providing and Laying of Pipes, Specials,
Valves, Meters for Distribution System
(GI Pipes (Heavy) 80 mm to 150 mm -
285.573 Km and MSERW Fe 410 Pipes
206.5 mm to 388.8 mm - 34.14 Km )
890000000 916700000 825030000 50 0.0076 0.25% 2225000 6270228
2
Civil Works for Distribution System (GI
Pipes (Heavy) 80 mm to 150 mm -
285.573 Km and MSERW Fe 410 Pipes
206.5 mm to 388.8 mm - 34.14 Km )
757800000 780534000 702480600 50 0.0076 0.25% 1894500 5338853
3
Construction of Reservoirs of various
capacities (Capacity Enhancement
capacity of 30 existing and 11 newly
proposed Reservoirs)
247400000 254822000 229339800 67 0.0039 0.50% 1237000 894425
4 Acquisition of Land for various Reservoirs 191000000 196730000 177057000 0 0
5 Plantation 20000000 20600000 18540000 0 0
6Staff Quarters at 11 Newly Pproposed
Reservoirs33600000 34608000 31147200 67 0.0039 0.50% 168000 121474
7 SCADA (Cloud Based) System 15400000 15862000 14275800 20 0.0354 2.50% 385000 505363
8House Service Connection, AMR
Consumer Meter and Direct Acting PRV1404400000 1446532000 1301878800 10 0.1000 5.00%
9Operation and Maintenance of the
Distribution System for 15 years592600000 610378000 549340200 0 0
4152200000 4276766000 5909500 13130343Total Rs.
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
STATMENT SHOWING ANNUAL M & R CHARGES
Sr.
No.Sub Work Net cost Gross cost
90% of
Gross Cost
Life in
Years
Depreciation
Factor% of M & R
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.110
PUMPING MAINS
ESTIMATE
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Cost (in Rs. Lakh)
1
Providing and Laying of Pipes, Specials, Valves, Meters for
Pumping Mains (GI Pipes (Heavy) 100 mm to 150 mm -
0.644 Km and MSERW Fe 410 Pipes 206.5 mm to 585 mm -
3.524 Km )
566.00
2
Civil Works for Pumping Mains (GI Pipes (Heavy) 100 mm to
150 mm - 0.644 Km and MSERW Fe 410 Pipes 206.5 mm to
585 mm - 3.524 Km )
125.00
3 Pumping Machinery 510.00
4 Construction of Pump House and staff quarter 580.00
5 Acquisition of Land for Pump House & Staff Quarter 225.00
6 Plantation 20.00
7 Express feeder, Substation and Transformer 695.00
8 SCADA (Cloud Based) System 23.00
9Operation and Maintenance of the Pumping Mains for 15
years2742.00
5486.00
165.00
5651.00Total Gross Cost
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Total Net Cost
Add 3% for Contingencies
Recapitulation Sheet for Pumping Mains
World Bank Project
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.111
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1Providing and Laying in trenches Galvanised mild steel pipe of following description
conforming to I.S 1239/2000 Heavy class, jointing all fitting , bends, Tees, Collars,
Tappers etc.including hydraullic testing of pipes as per direction of Engineer in
charge etc all complete
Galvanized Iron Pipes (Heavy class)
100 mm 621.70 Rmt 1402.08 871672.00
As per Rate Analysis -2
150 mm 22.80 Rmt 2079.89 47422.00
As per Rate Analysis -3
2 Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS:
3589-2001,steel grade Fe 410 with wall thickness , weight per meter, flanges as
described in analysis
206.5 mm dia 29.30 RMT 3676.43 107719.00
As per Rate Analysis -5
260.3 mm dia 373.10 RMT 4601.77 1716920.00
As per Rate Analysis -6
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Providing and Laying of Pipes, Specials, Valves, Meters for Pumping Mains (GI Pipes (Heavy) 100 mm to 150 mm - 0.644 Km and MSERW Fe
410 Pipes 206.5 mm to 585 mm - 3.524 Km )
Abstract
World Bank Project
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.112
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
309.7 mm dia 22.90 RMT 5977.04 136874.00
As per Rate Analysis -7
312.7 mm dia 90.50 RMT 6029.63 545682.00
As per Rate Analysis -8
341.5 mm dia 1424.40 RMT 7204.99 10262788.00
As per Rate Analysis -8
396.4 mm dia 464.70 RMT 13327.00 6193057.00
As per Rate Analysis -8
419 mm dia 1102.30 RMT 10733.37 11831394.00
As per Rate Analysis -8
585 mm dia 16.80 RMT 18109.88 304246.00
As per Rate Analysis -8
3 Providing, Suppying, fixing Specials such as Tee, Bend, Reducer, Tailpiece, etc.
GI Specials 20% Job 919094 183819.00
MS Specials 20% Job 31098680 6219736.00
4
Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic
controller, communication, data logger, standby battery. With inbuilt communication
the controller can send the data directly to SCADA system. No RTU,
Communication moden, external battery is required. for Flow Control Valves
As per rate anlysis- 32
100 1.00 No. 214053.18 214053.00
150 3.00 No. 259659.71 778979.00
200 4.00 No. 361152.92 1444612.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.113
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
250 1.00 No. 464510.07 464510.00
300 1.00 No. 514163.76 514164.00
600 1.00 No. 1493460.63 1493461.00
5
Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic
controller, communication, data logger, standby battery. With inbuilt communication
the controller can send the data directly to SCADA system. No RTU,
Communication moden, external battery is required. for Pressure Reducing Valves
As per rate anlysis- 32
100 1.00 No. 214053.18 214053.00
150 2.00 No. 259659.71 519319.00
200 4.00 No. 361152.92 1444612.00
250 1.00 No. 464510.07 464510.00
300 1.00 No. 514163.76 514164.00
600 1.00 No. 1493460.63 1493461.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.114
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
6 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated),
Glandless, Sluice Valve of Non Rising spindle type. The Valve will be WRAS
approved. Valve will be fully protected from corrosion by electro-statically applying
epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland sealing
& pocket less body passage for unobstructed flow and debris free bottom. Body,
Bonnet, Gland will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall
not be supplied. Spindle shall be of SS : 420/304. The gland ('O' Ring) section will
be of Ductile Iron, Tamper resistant and will be separate unit from bonnet housing.
Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be housed
separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The
valve shall have Dust/Ingression resistant washer at spindle top. The spindle,
spindle nut, O rings shall be interchangeable design. The flanges shall be drilled as
per IS: 1538 & the face to face shall confirm to IS: 14846. The Valve will be suitable
for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with
EPDM. for Isolation Valve
As per rate anlysis- 33
100 1.00 No. 42300.52 42301.00
150 3.00 No. 51688.96 155067.00
200 5.00 No. 81696.12 408481.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.115
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
250 1.00 No. 98157.36 98157.00
300 2.00 No. 128438.40 256877.00
500 1.00 No. 489246.05 489246.00
600 2.00 No. 683946.05 1367892.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.116
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
7 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated),
Glandless, Sluice Valve of Non Rising spindle type. The Valve will be WRAS
approved. Valve will be fully protected from corrosion by electro-statically applying
epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland sealing
& pocket less body passage for unobstructed flow and debris free bottom. Body,
Bonnet, Gland will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall
not be supplied. Spindle shall be of SS : 420/304. The gland ('O' Ring) section will
be of Ductile Iron, Tamper resistant and will be separate unit from bonnet housing.
Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be housed
separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The
valve shall have Dust/Ingression resistant washer at spindle top. The spindle,
spindle nut, O rings shall be interchangeable design. The flanges shall be drilled as
per IS: 1538 & the face to face shall confirm to IS: 14846. The Valve will be suitable
for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with
EPDM. for Scour Valve
As per rate anlysis- 33
400 1.00 No. 279070.00 279070.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.117
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
8
Manufacturing, Testing and Supplying Ductile Iron, Tamper Proof, Single chamber,
High Performance, Umbrella Sealing Arc design, Full port (Equal Size inlet &
outlets), Kinetic Air Release valve, for High Discharge, Venting, and Anti Vacuum
Function. The Inlet & Outlet parts of Air Valves should be equal to or larger than the
area of the nominal valve size to provide full flow area through the valve. The Valve
will be supplies with DI Resilient Seated Isolating Sluice Valve of PN 1.6 Rating.
The Valve shall be WRAS Approved. Body & top Cover will be in Ductile Iron Grade
GGG-50 or SGI 500/7. Lower grade shall not be supplied. The Ball, Ball Cage and
Umbrella sealing arc will be in SS: 304. The Valve will be suitable for PN 1.6
Pressure Ratings. All the top cover fasteners shall be of L & Key type with weather
proof PV cap, moisture & ingression resistant. The Sealing Arc shall be guided at
top and shall be capable of sealing at 0.2 kg/cm2. Valve will be fully protected from
corrosion by electro-statically applying epoxy coating of minimum 250 microns. The
flanges shall be drilled as per IS: 1538. The Cage, Ball, Arc, Gaskets, all will be
interchangeable.
AIR VALVE
Body, Bonnet - Ductile Iron DIN:1693 Gr. GGG - 50.
Float, Guide Barrel - Stainless Steel - ASTM A 276 Type - 304
Seat - Nitrile Rubber
Sealing Arc, Bolt, Small Nozzle - Stainless Steel - ASTM A 276 Type - 304
O-Ring - Rubber NBR/EPDM
Nozzle, Buffer - Rubber EPDM
ISOLATING SLUICE VALVE
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.118
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
As per rate anlysis- 34
25 (Rates not avialable Hence rates of 50 mm are taken, Valve shall also be of 50
mm)5.00 No.
37630.32188152.00
50 3.00 No. 37630.32 112891.00
9
Supply, install and commission Electromagnetic Flow Meter (EMF) As Per ISO
4064, for Raw/Pure water with accuracy +/-0.5% of measured value & protection as
per given specifications for size 100 mm-1000mm including sensor, transmitter
surge arrestor, cable suitable size for 25 mtrs built in GSM ( with Simcard and its
charges,valid for 36 months) including the pipe cutting, leveling and installation of
flow meter in the pipelines with necessary tool tackles, cranes including 36 months
guarantee etc complete, as may be required at site & based on technical
specifications
As per rate anlysis- 36
100 2.00 No. 127257.22 254514.00
150 3.00 No. 137188.22 411565.00
200 4.00 No. 162429.12 649716.00
250 4.00 No. 179509.51 718038.00
300 2.00 No. 205886.16 411772.00
450 1.00 No. 346428.41 346428.00
600 2.00 No. 464427.00 928854.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.119
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
10
Designing, Supplying, Installing, commissioning & testing of pressure transmitter
CE markd with following technical parameters at Raw Water Pump House and
Interfacing with PLC panel including Mounting arrangement.
Output 4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.1 % of full scale or better
Enclosure- IP 67
34.00 No. 43679.00 1485086.00
As per rate anlysis- 35
Total Net Cost 56585334.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.120
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Providing and Laying in trenches Galvanised mild steel pipe of following description conforming to I.S
1239/2000 Heavy class, jointing all fitting , bends, Tees, Collars, Tappers etc.including hydraullic testing
of pipes as per direction of Engineer in charge etc all complete
Galvanized Iron Pipes (Heavy class)
100 mm
pump house (PH_Kamnadevi) to the KamnadeviTemple 615.9 615.90 Rmt
North Oak 5.8 5.80 Rmt
150 mm
Dhingodevi Dalli 22.8 22.80 Rmt
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade
Fe 410 with wall thickness , weight per meter, flanges as described in analysis
206.5 mm dia
pump house (PH_Kamnadevi) to the KamnadeviTemple 0.8 0.80 Rmt
Kusumpti 28.5 28.50 Rmt
260.3 mm dia
Dhingodevi Dalli 300.8 300.80 Rmt
Jakhu 72.3 72.30 Rmt
309.7 mm dia
Dhingodevi Dalli 13.4 13.40 Rmt
Jakhu 9.5 9.50 Rmt
312.7 mm dia
Dhingodevi Dalli 90.5 90.50 Rmt
341.5 mm dia
Dhingodevi Dalli 794.1 794.10 Rmt
Jakhu 630.3 630.30 Rmt
396.4 mm dia
Sanjauli tank to the BPT1 464.7 464.70 Rmt
Unit
1
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Providing and Laying of Pipes, Specials, Valves, Meters for Pumping Mains (GI Pipes (Heavy) 100 mm to 150 mm - 0.644 Km and MSERW Fe 410 Pipes 206.5 mm to 585
mm - 3.524 Km )
Measurement Sheet
World Bank Project
2
Sr.
No.Description
MeasurementsQty.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.121
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
419 mm dia
Jakhu 1102.3 1102.30 Rmt
585 mm dia
Sanjauli tank to the BPT1 16.8 16.80 Rmt
3 Providing, Suppying, fixing Specials such as Tee, Bend, Reducer, Tailpiece, etc.
GI Specials 20% Job
MS Specials 20% Job
4Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller, communication,
data logger, standby battery. With inbuilt communication the controller can send the data directly to
SCADA system. No RTU, Communication moden, external battery is required. for Flow Control Valves
100 1 1.00 No.
150 3 3.00 No.
200 4 4.00 No.
250 1 1.00 No.
300 1 1.00 No.
600 1 1.00 No.
5 Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller, communication,
data logger, standby battery. With inbuilt communication the controller can send the data directly to
SCADA system. No RTU, Communication moden, external battery is required. for Pressure Reducing
Valves
100 1 1.00 No.
150 2 2.00 No.
200 4 4.00 No.
250 1 1.00 No.
300 1 1.00 No.
600 1 1.00 No.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.122
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
6 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of
Non Rising spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion
by electro-statically applying epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland
sealing & pocket less body passage for unobstructed flow and debris free bottom. Body, Bonnet, Gland
will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall not be supplied. Spindle shall be of
SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper resistant and will be separate
unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be housed
separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall have
Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be interchangeable
design. The flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS: 14846. The
Valve will be suitable for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Isolation
Valve
100 1 1.00 No.
150 3 3.00 No.
200 5 5.00 No.
250 1 1.00 No.
300 2 2.00 No.
500 1 1.00 No.
600 2 2.00 No.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.123
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
7 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of
Non Rising spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion
by electro-statically applying epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland
sealing & pocket less body passage for unobstructed flow and debris free bottom. Body, Bonnet, Gland
will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall not be supplied. Spindle shall be of
SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper resistant and will be separate
unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be housed
separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall have
Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be interchangeable
design. The flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS: 14846. The
Valve will be suitable for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Scour
Valve
400 1 1.00 No.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.124
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
8 Manufacturing, Testing and Supplying Ductile Iron, Tamper Proof, Single chamber, High Performance,
Umbrella Sealing Arc design, Full port (Equal Size inlet & outlets), Kinetic Air Release valve, for High
Discharge, Venting, and Anti Vacuum Function. The Inlet & Outlet parts of Air Valves should be equal to
or larger than the area of the nominal valve size to provide full flow area through the valve. The Valve will
be supplies with DI Resilient Seated Isolating Sluice Valve of PN 1.6 Rating. The Valve shall be WRAS
Approved. Body & top Cover will be in Ductile Iron Grade GGG-50 or SGI 500/7. Lower grade shall not be
supplied. The Ball, Ball Cage and Umbrella sealing arc will be in SS: 304. The Valve will be suitable for
PN 1.6 Pressure Ratings. All the top cover fasteners shall be of L & Key type with weather proof PV cap,
moisture & ingression resistant. The Sealing Arc shall be guided at top and shall be capable of sealing at
0.2 kg/cm2. Valve will be fully protected from corrosion by electro-statically applying epoxy coating of
minimum 250 microns. The flanges shall be drilled as per IS: 1538. The Cage, Ball, Arc, Gaskets, all will
be interchangeable.
AIR VALVE
Body, Bonnet - Ductile Iron DIN:1693 Gr. GGG - 50.
Float, Guide Barrel - Stainless Steel - ASTM A 276 Type - 304
Seat - Nitrile Rubber
Sealing Arc, Bolt, Small Nozzle - Stainless Steel - ASTM A 276 Type - 304
O-Ring - Rubber NBR/EPDM
Nozzle, Buffer - Rubber EPDM
ISOLATING SLUICE VALVE
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM.
25 (Rates not avialable Hence rates of 50 mm are taken, Valve shall also be of 50 mm) 5 5.00 No.
50 3 3.00 No.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.125
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DUnit
Sr.
No.Description
MeasurementsQty.
9 Supply, install and commission Electromagnetic Flow Meter (EMF) As Per ISO 4064, for Raw/Pure water
with accuracy +/-0.5% of measured value & protection as per given specifications for size 100 mm-
1000mm including sensor, transmitter surge arrestor, cable suitable size for 25 mtrs built in GSM ( with
Simcard and its charges,valid for 36 months) including the pipe cutting, leveling and installation of flow
meter in the pipelines with necessary tool tackles, cranes including 36 months guarantee etc complete, as
may be required at site & based on technical specifications
100 2 2.00 No.
150 3 3.00 No.
200 4 4.00 No.
250 4 4.00 No.
300 2 2.00 No.
450 1 1.00 No.
600 2 2.00 No.
10
Designing, Supplying, Installing, commissioning & testing of pressure transmitter CE markd with following
technical parameters at Raw Water Pump House and Interfacing with PLC panel including Mounting
arrangement.
Output 4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.1 % of full scale or better
Enclosure- IP 67
34.00 34.00 No.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.126
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m stacking the
soil not more than 3 meters clear from the edge of the excavation and then
returning the stacked soil in 15cm layers, when required into the plinths sides of
foundations etc., consolidating each deposited layer by ramming and watering
and then disposing of all surplus excavated earth as directed within a lead of 20
meters
3361.32 Cum 547.71 1841021.00
As per Rate Analysis -9
2Cutting in earth work and disposal of excavated earth upto a lead of 20mtr. In
pick jumper work. 50% each for laying of pipe line and civil structures.1680.66 Cum 409.27 687840.00
As per Rate Analysis -10
Constructing chambers with C.I surface box 100mm top dia & 180mm deep
(inside) with chained lid & RCC Walls and slab 1:1.5:3 (M20), 230mm thick and
100mm thick PCC 1:2:4 (M15) finished with a floating coat of neat cement
including curing complete
a) 600mmx600mmx750mm inside size with 200 mm thick RCC Wall 24.00 No. 18681.03 448345.00
As per Rate Analysis -11
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Civil Works for Pumping Mains (GI Pipes (Heavy) 100 mm to 150 mm - 0.644 Km and MSERW Fe 410 Pipes 206.5 mm to 585 mm - 3.524 Km )
Abstract
3
World Bank Project
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.127
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
b) 900mmx900mmx750mm inside size with 200 mm thick RCC Wall 24.00 No. 27116.61 650799.00
As per Rate Analysis -12
c) 1200mmx1200mmx750mm inside size with 200 mm thick RCC Wall 7.00 No. 36851.71 257962.00
As per Rate Analysis -13
d) 1500mmx1500mmx750mm inside size with 200 mm thick RCC Wall 8.00 No. 47886.35 383091.00
As per Rate Analysis -14
4Providing and constructing Anchor blocks/Thrust blocks for the pipeline
(Considering 30 blocks per km)125.00 No. 27077.27 3384659.00
As per Rate Analysis -15
5 Road Restoration 3334.80 Sqm 1400.00 4668720.00
As per Rate Analysis -16
6 Utility Shifting For pipe laying of given length in Km 4.17 Km 50397.60 210082.00
As per Rate Analysis -17
Total Net Cost 12532519.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.128
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
1
Excavation in foundations, trenches etc., in earth work, lift upto
1.5m stacking the soil not more than 3 meters clear from the edge
of the excavation and then returning the stacked soil in 15cm
layers, when required into the plinths sides of foundations etc.,
consolidating each deposited layer by ramming and watering and
then disposing of all surplus excavated earth as directed within a
lead of 20 meters
For Galvanized Iron Pipes (Heavy class)
100 mm 621.70 0.70 0.60 261.11 Cum
150 mm 22.80 0.75 0.60 10.26 Cum
For MSERW Pipes
206.5 mm dia 29.30 0.80 0.60 14.06 Cum
260.3 mm dia 373.10 0.85 0.60 190.28 Cum
309.7 mm dia 22.90 0.90 0.75 15.46 Cum
312.7 mm dia 90.50 0.90 0.75 61.09 Cum
341.5 mm dia 1424.40 0.95 0.90 1217.86 Cum
396.4 mm dia 464.70 1.00 1.00 464.70 Cum
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Civil Works for Pumping Mains (GI Pipes (Heavy) 100 mm to 150 mm - 0.644 Km and MSERW Fe 410 Pipes 206.5 mm to 585 mm - 3.524 Km )
Measurement Sheet
Sr. No. DescriptionMeasurements
Qty. Unit
World Bank Project
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.129
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DSr. No. Description
MeasurementsQty. Unit
419 mm dia 1102.30 1.00 1.00 1102.30 Cum
585 mm dia 16.80 1.20 1.20 24.19 Cum
2
Cutting in earth work and disposal of excavated earth upto a lead of
20mtr. In pick jumper work. 50% each for laying of pipe line and
civil structures.
1680.66 Cum
3
Constructing chambers with C.I surface box 100mm top dia &
180mm deep (inside) with chained lid & RCC Walls and slab
1:1.5:3 (M20), 230mm thick and 100mm thick PCC 1:2:4 (M15)
finished with a floating coat of neat cement including curing
complete
a) 600mmx600mmx750mm inside size with 200 mm thick RCC
Wall 24.00 24.00 No.
b) 900mmx900mmx750mm inside size with 200 mm thick RCC
Wall 24.00 24.00 No.
c) 1200mmx1200mmx750mm inside size with 200 mm thick RCC
Wall 7.00 7.00 No.
d) 1500mmx1500mmx750mm inside size with 200 mm thick RCC
Wall 8.00 8.00 No.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.130
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B DSr. No. Description
MeasurementsQty. Unit
4 Providing and constructing Anchor blocks/Thrust blocks for the
pipeline (Considering 30 blocks per km)125 125.00 No.
5 Road Restoration 1 3334.8 1 3334.80 Sqm
6 Utility Shifting For pipe laying of given length in Km 4.1685 4.1685 Km
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.131
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr.
No.Description No HP Unit Rate Amount
1 Supply & errection of pumping machinery alongwith its allied
accessories. complete with a provision of 100% stand by t each
pure water stage including surge control devices.
pump house (PH_Kamnadevi) to the KamnadeviTemple 2 55 BHP 30000 3300000.00
Sanjauli tank to the BPT1 2 75 BHP 30000 4500000.00
Sump_Digodevi_Rest to various tanks in this area 2 75 BHP 30000 4500000.00
Kusumpti tank to HP_PWD_Near_Kusumpti 2 495 BHP 25000 24750000.00
Sanjauli tank to Jakhu tanks 2 10 BHP 30000 600000.00
Sanjauli tank to North_Oak_1 2 180 BHP 28000 10080000.00
Head work to Ridge and Sanjauli tanks 2 55 BHP 30000 3300000.00
51030000.00
Hydraulic Design & Network Modelling for Shimla Water Supply
World Bank Project
ABSTRACT OF COST
Total Rs. In Lac.
Client : Shimla Jal Prabandhan Nigam Limited
Pumping Machinery
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.132
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty Rate Unit Amount
1 Construction of pump house cum attendant quarter 2 Nos. of 600
Sqm. Each for Kusumpti tank to HP_PWD_Near_Kusumpti and
Sanjauli tank to North_Oak_1
1200 30545 Per Sqm. 36654000.00
As per PWD, Himachal Pradesh rates for plinth area for buildings of
area more than 500 sqm is 24436 in 2014 and increased by 25% for
5years.
2 Construction of staff quarters Type-I,II & III. At New Reservoir 100
sqm x 7 pumping station
700 30545 Per Sqm. 21381500.00
As per PWD, Himachal Pradesh rates for plinth area for buildings of
area more than 500 sqm is 24436 in 2014 and increased by 25% for
5years.
58035500.00Total Rs. In Lac.
Hydraulic Design & Network Modelling for Shimla Water Supply
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Construction of Pump House and staff quarter
ABSTRACT OF COST
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.133
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1 Acquisition of land for Varoius Reservoirs in Shimla
For Pump House 1200
For Staff Quarter 700
Total area 1900 Sqm 11850.00 22515000.00
Net Amount 22515000.00
Acquisition of Land for Pump House & Staff Quarter
ABSTRACT OF COST
Hydraulic Design & Network Modelling for Shimla Water Supply
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.134
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1 Plantation in forest land/ cost of trees etc. L.S
LS 2000000.00
Net Amount 2000000.00
Plantation
ABSTRACT OF COST
Hydraulic Design & Network Modelling for Shimla Water Supply
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.135
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty Unit Rate Amount
1 Supply & errection of Transformer and Substation alongwith its
allied accessories.
pump house (PH_Kamnadevi) to the KamnadeviTemple 1 Job 1000000 1000000.00
Sanjauli tank to the BPT1 1 Job 1000000 1000000.00
Sump_Digodevi_Rest to various tanks in this area 1 Job 1000000 1000000.00
Kusumpti tank to HP_PWD_Near_Kusumpti 1 Job 10000000 10000000.00
Sanjauli tank to Jakhu tanks 1 Job 500000 500000.00
Sanjauli tank to North_Oak_1 1 Job 5000000 5000000.00
Head work to Ridge and Sanjauli tanks 1 Job 1000000 1000000.00
2 Supply & errection of Express feeder alongwith its allied
accessories at each pumping station. Quotation from HPEBL
1 Job 50000000 50000000.00
69500000.00Total Rs. In Lac.
Hydraulic Design & Network Modelling for Shimla Water Supply
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Express feeder, Substation and Transformer
ABSTRACT OF COST
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.136
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Supply, Installation, Commissioning, Testing, Terminating & Interfacing
Software Design to PLC and commissioning of SCADA software with required
hard tags plus 25% extra and with unlimited soft Tags & life time licence
Development version
1.00 Nos 450000 450000
2Developing/programming charges to install the software as per logic defined by
the dept.1.00 Nos 250000 250000
3
Supply, Installation, Testing, Terminating & Interfacing Centralised Historian
Server grade Historian PC with Window 7 or latest window operating system &
Historian software development cost etc. complete
1.00 Nos 85000 85000
4
Supply, Installation, Testing, Terminating & Interfacing Secondary Computer
Station Secondary computer station etc.
1.00 Nos 65000 65000
5Supply, Installation, Testing, Intgeration & Commissioning of 46" LCD monitor
at Conf. Room for display of total water system (Online) 1.00 Nos 98000 98000
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
SCADA (Cloud Based) System
Abstract
World Bank Project
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.137
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
6
Supplying and erecting window model mounted type room Air-Conditioner 3 star
230/250 V 50 cycles single phase A.C.supply 2 TRcapacity complete with gas
R410A/R32 at position in provided recess with wooden frame as per
specification No.AP-AC/WAC
1.00 Nos 45000 45000
7 Power Supply From Electrcity Department at each location of PRV and FCV 35.00 Job 10000.00 350000.00
8 Power Cable from Supply point to PRV/FCV and allied works 35.00 Job 5000.00 175000.00
9
Designing, Supplying, Installing, commissioning & testing of Ultrasonic level
transmitter CE marked with following technical parameters and Interfacing with
PLC panel including Mounting accessories.
14 Jobs 53125.842 743762.00
Total Net Cost 2261762.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.138
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1Providing staff for the operation and Maintenance of
Transmission lines
1 Fitter for 10 to 15 km as per CPHEEO manual
2 Helper for 10 to 15 km as per CPHEEO manual
Total length of network in three zone is 37 Km
Hence 2 fitter and 4 Helper per day will be required
For Years 2021 to 2035
2021 1.00 Job 7680408.00 7680408.00
2022 1.00 Job 8223876.00 8223876.00
2023 1.00 Job 8805996.00 8805996.00
2024 1.00 Job 9429072.00 9429072.00
2025 1.00 Job 10096080.00 10096080.00
2026 1.00 Job 10810776.00 10810776.00
2027 1.00 Job 11576172.00 11576172.00
2028 1.00 Job 12395388.00 12395388.00
2029 1.00 Job 13272888.00 13272888.00
2030 1.00 Job 14212500.00 14212500.00
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Operation and Maintenance of the Pumping Mains for 15 years
Abstract
World Bank Project
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.139
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
2031 1.00 Job 15218760.00 15218760.00
2032 1.00 Job 16296240.00 16296240.00
2033 1.00 Job 17450256.00 17450256.00
2034 1.00 Job 18686124.00 18686124.00
2035 1.00 Job 20009940.00 20009940.00
2Maintenance and repairs of transmission lines including all
material and labour required.
For Years 2021 to 2035
2021 1.00 Job 3709387.50 3709388.00
2022 1.00 Job 3894856.88 3894857.00
2023 1.00 Job 4089599.72 4089600.00
2024 1.00 Job 4294079.70 4294080.00
2025 1.00 Job 4508783.69 4508784.00
2026 1.00 Job 4734222.87 4734223.00
2027 1.00 Job 4970934.02 4970934.00
2028 1.00 Job 5219480.72 5219481.00
2029 1.00 Job 5480454.75 5480455.00
2030 1.00 Job 5754477.49 5754477.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.140
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
2031 1.00 Job 6042201.37 6042201.00
2032 1.00 Job 6344311.44 6344311.00
2033 1.00 Job 6661527.01 6661527.00
2034 1.00 Job 6994603.36 6994603.00
2035 1.00 Job 7344333.53 7344334.00
Total Net Cost 274207731.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.141
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Name of work :- Providing Water Supply for Shimla town.
Cement/Steel/G.I Pipe
Dhalli Store (IPH)
6 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Sand Deothi Solan
60 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Aggrigate below 40 mm size
115 K.M 0.5 K.M.
Punchakula By Mech Transport By Head load Site of work
Aggrigate above 40 mm size
115 K.M 0.5 K.M.
By Mech Transport By Head load Site of work
Steel/wood/Frame/Shuttering and Shutter
6 K.M 0.5 K.M.
Shimla By Mech Transport By Head load Site of work
Brick/MSERW Pipe/GI
130 K.M 0 K.M.
Chandigarh By Mech Transport By Head load Site of work
Flanges
6 K.M. 0.5 K.M.
Local By Mech Transport By Head load Site of work
Certified that lead is taken as per actual ,shortest and feasible as well as
economical route by all means.
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Lead Statement
LEAD CHART
World Bank Project
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.142
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1) Cement from IPH 2) STEEL:
LEAD : By Mech. 6 Km. LEAD : By Mech. 6 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.5 0.00 1 Km. 0 103.50 0.00
2 Km. 0 119.49 0.00 2 Km. 0 119.49 0.00
3 Km. 0 135.32 0.00 3 Km. 0 135.32 0.00
4 Km. 0 150.70 0.00 4 Km. 0 150.70 0.00
5 Km. 1 165.35 165.35 5 Km. 1 165.35 165.35
5- 10 Km. 1 13.56 13.56 5- 10 Km. 1 13.56 13.56
10-20 Km. 0 11.32 0.00 10-20 Km. 0 11.32 0.00
Beyond 20 Km. 0 9.51 0.00 Beyond 20 Km. 0 9.51 0.00
TOTAL : 178.91 TOTAL : 178.91
2 By Head load 2 By Head load
1st. 1 Km. 0 431.84 0.00 1st. 1 Km. 0 911.43 0.00
1st. 100 Mtr 1 68.60 68.60 1st. 100 Mtr 1 144.81 144.81
Bey:1 Km.Per 1/2Km. 0 215.92 0.00 Bey:1 Km.Per 1/2Km. 0 455.72 0.00
Bey:100 Mtr Per 50 Mtr 8 20.18 161.44 Bey:100 Mtr Per 50 Mtr 8 42.59 340.72
Total : 230.04 Total : 485.53
3) Sand: 4)
LEAD : By Mech. 60 Km. LEAD : By Mech. 115 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 155.25 0.00 1 Km. 0 155.25 0.00
2 Km. 0 179.24 0.00 2 Km. 0 179.24 0.00
3 Km. 0 202.98 0.00 3 Km. 0 202.98 0.00
4 Km. 0 226.05 0.00 4 Km. 0 226.05 0.00
5 Km. 1 248.03 248.03 5 Km. 1 248.03 248.03
5- 10 Km. 5 20.34 101.70 5- 10 Km. 5 20.34 101.70
10-20 Km. 10 16.98 169.80 10-20Km 10 16.98 169.80
Beyond 20 Km. 40 14.27 570.80 Beyond 20 Km. 95 14.27 1355.65
TOTAL : 1090.33 TOTAL : 1875.18
CARRIAGE OF MATERIALS
Stone aggregate below
40mm.:
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.143
Shimla Jal Prabandhan Nigam Limited Rate Analysis
2 By Head load 2 By Head load
1st. 1 Km. 0 732.74 0.00 1st. 1 Km. 0 732.74 0.00
1st. 100 Mtr 1 116.42 116.42 1st. 100 Mtr 1 116.42 116.42
Bey:1 Km.Per 1/2Km. 0 366.37 0.00 Bey:1 Km.Per 1/2Km. 0 366.37 0.00
Bey:100 Mtr Per 50 Mtr 8 34.24 273.92 Bey:100 Mtr Per 50 Mtr 8 34.24 273.92Total : 390.34 Total : 390.34
5) 6)
LEAD : By Mech. 115 Km. LEAD : By Mech. 6 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech.
1 Km. 0 168.02 0.00 1 Km. 0 155.25 0.00
2 Km. 0 193.98 0.00 2 Km. 0 179.24 0.00
3 Km. 0 219.67 0.00 3 Km. 0 202.98 0.00
4 Km. 0 244.64 0.00 4 Km. 0 226.05 0.00
5 Km. 1 268.43 268.43 5 Km. 1 248.03 248.03
5- 10 Km. 5 22.01 110.05 5- 10 Km. 1 20.34 20.34
10-20 Km. 10 18.38 183.80 10-20 Km. 0 16.98 0.00
Beyond 20 Km. 95 15.44 1466.80 Beyond 20 Km. 0 14.27 0.00
TOTAL : 2029.08 TOTAL : 268.37
2 By Head load 2 By Head load
1st. 1 Km. 0 792.22 0.00 1st. 1 Km. 0 585.93 0.00
1st. 100 Mtr 1 125.86 125.86 1st. 100 Mtr 1 93.09 93.09
Bey:1 Km.Per 1/2Km. 0 396.11 0.00 Bey:1 Km.Per 1/2Km. 0 292.97 0.00
Bey:100 Mtr Per 50 Mtr 8 37.02 296.16 Bey:100 Mtr Per 50 Mtr 8 27.38 219.04
Total : 422.02 Total : 312.13
7) 7.1)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.5 0.00 1 Km. 0 103.5 0.00
Stone aggregate 40mm
and above:
Timber(Local wood for
shuttering)and Shutter
GI Pipe below 100mm
dia :GI Pipe below 100mm dia :
LEAD From Chandigarh
:LEAD From IPH Store :
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.144
Shimla Jal Prabandhan Nigam Limited Rate Analysis
2 Km. 0 119.49 0.00 2 Km. 0 119.49 0.00
3 Km. 0 135.32 0.00 3 Km. 0 135.32 0.00
4 Km. 0 150.70 0.00 4 Km. 0 150.70 0.00
5 Km. 1 165.35 165.35 5 Km. 1 165.35 165.35
5- 10 Km. 5 13.56 67.80 5- 10 Km. 5 13.56 67.80
10-20 Km. 10 11.32 113.20 10-20 Km. 10 11.32 113.20
Beyond 20 Km. 116 9.51 1103.16 Beyond 20 Km. 116 9.51 1103.16
TOTAL : 1449.51 TOTAL : 1449.51
2 By Head load 2 By Head load
1st. 1 Km. 0 535.00 0.00 1st. 1 Km. 0 535.00 0.00
1st. 100 Mtr 1 85.00 85.00 1st. 100 Mtr 1 85.00 85.00
Bey:1 Km.Per 1/2Km. 0 267.50 0.00 Bey:1 Km.Per 1/2Km. 0 267.50 0.00
Bey:100 Mtr Per 50 Mtr 8 25.00 200.00 Bey:100 Mtr Per 50 Mtr 8 25.00 200.00
Total : 285.00 Total : 285.00
8) 9)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 706.97 0.00 1 Km. 0 964.05 0.00
2 Km. 0 816.21 0.00 2 Km. 0 1113.02 0.00
3 Km. 0 924.31 0.00 3 Km. 0 1260.42 0.00
4 Km. 0 1029.37 0.00 4 Km. 0 1403.69 0.00
5 Km. 1 1129.45 1129.45 5 Km. 1 1540.16 1540.16
5- 10 Km. 5 92.62 463.10 5- 10 Km. 5 126.30 631.50
10-20 Km. 10 77.34 773.40 10-20 Km. 10 105.46 1054.60
Beyond 20 Km. 116 64.96 7535.36 Beyond 20 Km. 116 88.59 10276.44
TOTAL : 9901.31 TOTAL : 13502.70
2 By Head load 2 By Head load
1st. 1 Km. 0 3057.20 0.00 1st. 1 Km. 0 5373.33 0.00
1st. 100 Mtr 1 485.72 485.72 1st. 100 Mtr 1 853.71 853.71
Bey:1 Km.Per 1/2Km. 0 1528.60 0.00 Bey:1 Km.Per 1/2Km. 0 2686.67 0.00
Bey:100 Mtr Per 50 Mtr 8 142.86 1142.88 Bey:100 Mtr Per 50 Mtr 8 251.09 2008.72
MSERW Pipe 200 mm dia :
MSERW Pipe 250 mm
dia :
LEAD (From Chandigarh
to IPH and IPH to Site) :
LEAD (From Chandigarh
to IPH and IPH to Site) :
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.145
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Total : 1628.60 Total : 2862.43
10) 11)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 1247.59 0.00 1 Km. 0 1767.42 0.00
2 Km. 0 1440.37 0.00 2 Km. 0 2040.53 0.00
3 Km. 0 1631.13 0.00 3 Km. 0 2310.77 0.00
4 Km. 0 1816.54 0.00 4 Km. 0 2573.43 0.00
5 Km. 1 1993.15 1993.15 5 Km. 1 2823.63 2823.63
5- 10 Km. 5 163.45 817.25 5- 10 Km. 5 231.56 1157.80
10-20 Km. 10 136.48 1364.80 10-20 Km. 10 193.35 1933.50
Beyond 20 Km. 116 114.64 13298.24 Beyond 20 Km. 116 162.41 18839.56
TOTAL : 17473.44 TOTAL : 24754.49
2 By Head load 2 By Head load
1st. 1 Km. 0 6724.09 0.00 1st. 1 Km. 0 9613.31 0.00
1st. 100 Mtr 1 1068.31 1068.31 1st. 100 Mtr 1 1527.35 1527.35
Bey:1 Km.Per 1/2Km. 0 3362.05 0.00 Bey:1 Km.Per 1/2Km. 0 4806.66 0.00
Bey:100 Mtr Per 50 Mtr 8 314.21 2513.68 Bey:100 Mtr Per 50 Mtr 8 449.22 3593.76
Total : 3581.99 Total : 5121.11
10) 11)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 2356.56 0.00 1 Km. 0 4241.80 0.00
2 Km. 0 2720.70 0.00 2 Km. 0 4897.27 0.00
3 Km. 0 3081.03 0.00 3 Km. 0 5545.85 0.00
4 Km. 0 3431.24 0.00 4 Km. 0 6176.23 0.00
MSERW Pipe 350 mm
dia :
LEAD (From Chandigarh
to IPH and IPH to Site) :
LEAD (From Chandigarh
to IPH and IPH to Site) :
MSERW Pipe 300 mm dia :
MSERW Pipe 400 mm dia :
MSERW Pipe 600 mm
dia :
LEAD (From Chandigarh
to IPH and IPH to Site) :
LEAD (From Chandigarh
to IPH and IPH to Site) :
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.146
Shimla Jal Prabandhan Nigam Limited Rate Analysis
5 Km. 1 3764.85 3764.85 5 Km. 1 6776.72 6776.72
5- 10 Km. 5 308.74 1543.70 5- 10 Km. 5 555.74 2778.70
10-20 Km. 10 257.80 2578.00 10-20 Km. 10 464.04 4640.40
Beyond 20 Km. 116 216.55 25119.80 Beyond 20 Km. 116 389.78 45214.48
TOTAL : 33006.35 TOTAL : 59410.30
2 By Head load 2 By Head load
1st. 1 Km. 0 11186.42 0.00 1st. 1 Km. 0 16406.73 0.00
1st. 100 Mtr 1 1777.28 1777.28 1st. 100 Mtr 1 2606.67 2606.67
Bey:1 Km.Per 1/2Km. 0 5593.21 0.00 Bey:1 Km.Per 1/2Km. 0 8203.37 0.00
Bey:100 Mtr Per 50 Mtr 8 522.73 4181.84 Bey:100 Mtr Per 50 Mtr 8 766.67 6133.36
Total : 5959.12 Total : 8740.03
12) Flange / Sluice Valve 13) Bricks: Per 1000.Nos.
By Mech. 136 LEAD : By Mech. 130 Km.
By Head : 0.5 By Head : 0 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.50 0.00 1 Km. 0 388.13 0.00
2 Km. 0 119.49 0.00 2 Km. 0 448.10 0.00
3 Km. 0 135.32 0.00 3 Km. 0 507.45 0.00
4 Km. 0 150.70 0.00 4 Km. 0 565.13 0.00
5 Km. 1 165.35 165.35 5 Km. 1 620.07 620.07
5- 10 Km. 5 13.56 67.80 5- 10 Km. 5 50.85 254.25
10-20 Km. 10 11.32 113.20 10-20 Km. 10 42.46 424.60
Beyond 20 Km. 116 9.51 1103.16 Beyond 20 Km. 110 35.67 3923.70
TOTAL : 346.35 TOTAL : 5222.62
2 By Head load 2 By Head load
1st. 1 Km. 0 911.43 0.00 1st. 1 Km. 0 1367.88 0.00
1st. 100 Mtr 1 144.81 144.81 1st. 100 Mtr 0 217.32 0.00
Bey:1 Km.Per 1/2Km. 0 455.72 0.00 Bey:1 Km.Per 1/2Km. 0 683.94 0.00
Bey:100 Mtr Per 50 Mtr 8 42.59 340.72 Bey:100 Mtr Per 50 Mtr 0 63.92 0.00
Total : 144.81 Total : 0.00
(Assumed as
locallyavailable) LEAD :
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.147
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr.
No.RATE UNIT
1 AGGREGATE 40 MM 550.00 /CUM
2 AGGREGATE 20 MM 725.00 /CUM
3 AGGREGATE 10 MM 725.00 /CUM
4 CEMENT 5120.00 /MT
5 SAND 650.00 /CUM
6 FINE SAND (FILTER MEDIA) 650.00 /CUM
7 M.R. TOR STEEL 4500.00 /QTL.
8 DRILLING EQUIPEMENT 3600.00 /DAY
9 SAFETY COILS 30.00 /COIL
10 DETONATORS 300.00 /100 Nos.
11 SPECIAL GELATINE 75.00 KG
12 STONE 500.00 /CUM
13 THROUGH BOUND STONE 1000.00 /100
14 MS ANGLE/ MS STRAPS 5000.00 /QTL.
15 WELDING CHARGES 4.00 /CMT.
16 WELDING CHARGES WITH GENERATOR SET 5.00 /CMT.
17 MS BOLTS 22 mm 5975.00 /QTL.
18 MS FLAT 5000.00 /QTL.
19 BOULDER/HARD STONE/PLUM 450.00 /CUM
20 CAST IRON M/H 90.00 /KG
21 BRICKS (I st Class) 4500.00 /1000
22 BRICKS II nd
Class) 4000.00 /1000
23 WHITE CEMENT 21500.00 /MT
24 Bitumen/Mexphalt 80/100 34500.00 /MT
25 KEROSENE OIL 14.00 /LTS.
26 DISEIL 56.00 /LTS.
27 M.OIL 285.00 /LTS.
28 FUEL WOOD 5.00 /KG
29 HIRING CHARGES OF TRUCK ( M.R.) 2500.00 /DAY
30 HIRE CHARGES OF PUMP 500.00 /DAY
31 HESSIAN CLOTH 25.00 /SQMT.
32 22mm RIVETS 6975.00 / QTL.
33 LIME(UNSLAKED) 1000.00 / QTL.
34 M.S.PLATES 4500.00 / QTL.
35 R.S.JOISTS 5000.00 / QTL.
36 C.I.RUNGS 40.00 /KG
37 ENAMELLED PAINT(OTHER THAN WHITE) 200.00 / LTS.
38 KAIL WOOD (Ist CLASS) 44500.00 /CUM
39 KAIL WOOD (IInd CLASS) 33830.00 /CUM
40 CHIL WOOD (Ist CLASS) 18100.00 /CUM
41 CHIL WOOD (IInd CLASS) 15800.00 /CUM
42 DEODAR WOOD 45200.00 /CUM
43 SAW CHARGES OF SLEEPERS TO PLANKS 700.00 /CUM
44 SAW CHARGES OF SLEEPERS TO BATTENS 500.00 /CUM
45 WOODEN BALLIES OF KAIL 125.00 /RMT.
46 WIRE GAUGE 250.00 /SQMT.
47 CI VENT PIPE 1.80 Mtr.Long 750.00 /EACH
** BASIC RATE **
Name of work:- Hydraulic Design & Network Modelling for Shimla Water Supply
DESCRIPTION OF ITEM
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.148
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr.
No.RATE UNITDESCRIPTION OF ITEM
48 Barbed Wire 56.68 Per Kg. (RC)
49 Ready Mixed Paint (other than white) 150.00 /ltr
50 Ready Mixed Paint (Pink Primer) 200.00 /ltr
51 Ready Mixed Red Mixed Paint 150.00 /ltr
52 Sliding Door Bolt (250 x 16 mm) 95.00 Each
53 Sliding Door Bolt (200X16 mm) 65.00 Each
54 Tower Bolt (Barrel Type 250 x 10 mm 35.00 Each
55 Tower Bolt (Barrel Type 200 x 10 mm 30.00 Each
56 Tower Bolt (Barrel Type 100 x 10 mm 25.00 Each
57 Tower Bolt (Barrel Type 150 x 10 mm 20.00 Each
58 Dry DisTamper 65.00 Kg
59 Oil Bound DisTamper 125.00 /ltr
60 Handles 100 mm 20.00 Each
61 Handles 125 mm 30.00 Each
62 SFRC Man Hole Cover 1700.00 Each
63 Terrazo Tiles 900.00 /SQMT.
64 Pink Makrana Marble 20 mm thick 1200.00 /SQMT.
64 Glass Strips 10.00 /Mtr.
65 Mild Steel Screws 40 mm 40.00 /Cent
66 Mild Steel Screws 25 mm 30.00 /10 nos
67 Mild Steel Screws 20 mm 25.00 /10 nos
68 Cement Paint 250.00 /ltr
69 Wood Perservative(Oil TYpe) 180.00 /ltr
70 Glass 2 mm to 3 mm 375.00 /Mtr
71 Iron Hinges ( 100 x 30 x 19 mm ) 25.00 /Cent
73 Iron Hinges ( 50 x 30 x 15 mm ) 15.00 /Cent
74 Ceramic Tile (153 x 152 x 6 mm) 750.00 /Sqm
82 C.G.I.SHEET 0.63 mm THICK 8000.00 /MT
83 P.G.I. SHEET 6000.00 /MT
84 800.00 /Cent
85 MS Flange of all tables 64.00 /KG
86 70.00 /KG
87 73.00 /KG
88 1373.00 /Meter
89 1703.00 /Meter
90 2318.00 /Meter
91 2880.00 /Meter
92 0.00 /Meter
93 4350.00 /Meter
94 0.00 /Meter
95 6140.00 /Meter
96 100 MM 105.00 EACH
97 150 MM 124.00 EACH
98 200 MM 171.00 EACH
99 250MM 295.00 EACH
100 300 MM 390.00 EACH
101 350 MM 703.00 EACH
Rubber Gasket EPDM
DI PIPE 400 MM DIA Including frieght charges Upto Kalka
DI PIPE 450 MM DIA Including frieght charges Upto Kalka
DI PIPE 500 MM DIA Including frieght charges Upto Kalka
DI PIPE 250 MM DIA Including frieght charges Upto Kalka
DI PIPE 300 MM DIA Including frieght charges Upto Kalka
DI PIPE 350 MM DIA Including frieght charges Upto Kalka
API Pipes (IS/ISO:3183-2007) Gr, X -
42 , 600 mm diaDI PIPE 150 MM DIA Including frieght charges Upto Kalka
DI PIPE 200 MM DIA Including frieght charges Upto Kalka
60 mm Thick Precast Interlocked Paver Blocks
API Pipes (IS/ISO:3183-2007) Gr, X -
42 450 mm dia
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.149
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr.
No.RATE UNITDESCRIPTION OF ITEM
102 400 MM 798.00 EACH
103 450 MM 1121.00 EACH
104 500 MM 1350.00 EACH
105 Plastic Steps 166.00 EACH
(B)
Rate i/c P/H Basic Rate Unit
88 FITTER (G-I) 292.00 252.00 /DAY
89 FITTER (G-II) 292.00 252.00 /DAY
90 MASON(G-1) 292.00 252.00 /DAY
91 MASON(G-II) 292.00 252.00 /DAY
92 PAINTER(G-I) 292.00 252.00 /DAY
93 PAINTER(G-II) 265.00 225.00 /DAY
94 BLACK SMITH (G-I) 292.00 252.00 /DAY
95 BLACK SMITH (G-II) 292.00 252.00 /DAY
96 CARPENTER G-I 292.00 252.00 /DAY
97 CARPENTER G-II 292.00 252.00 /DAY
98 BELDAR 250.00 210.00 /DAY
99 BHISTI 250.00 210.00 /DAY
100 MATE 250.00 210.00 /DAY
101 STONE DRESSER 250.00 210.00 /DAY
102 BHANDHANI 250.00 210.00 /DAY
103 DRILLER 250.00 210.00 /DAY
104 STONE CHISLER 250.00 210.00 /DAY
105 WHITE WASHER 265.00 210.00 /DAY
106 PUMP OPERATOR 262.00 252.00 /DAY
107 BLASTER 250.00 210.00 /DAY
108 Electrician 371.00 300.00 /DAY
109 BELDAR SKILLED 292.00 252.00 /DAY
RATE OF LABOUR AS APPLICABLE IN DEPTT. Vide Govt. notification No.FIN - ( PR ) B ( 7) -
33/2010 dt. 07-04-2017
Designation
Certified that above rates of materials are the lowest one pervailing markets rates & rates of
labour have been taken as applicable in this Department as per latest notification as issued by the Govt.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.150
Shimla Jal Prabandhan Nigam Limited Rate Analysis
56.00 285.00 250.00 2500.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 12.00 5.65 17.30 5.77 323.12 0.22 62.70 1500.00 2500.00 4385.82 776.25
2 12.75 5.12 26.48 8.83 494.48 0.33 94.05 1500.00 2500.00 4588.53 896.20 119.95
3 13.12 4.69 34.14 11.38 637.28 0.43 122.55 1500.00 2500.00 4759.83 1014.89 118.69
4 13.50 4.34 40.72 13.57 759.92 0.51 145.35 1500.00 2500.00 4905.27 1130.25 115.36
5 13.88 4.06 46.60 15.53 869.68 0.58 165.30 1500.00 2500.00 5034.98 1240.14 109.89
6 14.25 3.82 51.84 17.28 967.68 0.65 185.25 1500.00 2500.00 5152.93 1348.93 108.79
7 14.63 3.62 56.68 18.89 1057.84 0.71 202.35 1500.00 2500.00 5260.19 1453.09 104.16
8 15.10 3.46 61.36 20.45 1145.20 0.77 219.45 1500.00 2500.00 5364.65 1550.48 97.39
9 15.38 3.31 65.58 21.86 1224.16 0.82 233.70 1500.00 2500.00 5457.86 1648.90 98.42
10 15.75 3.17 69.40 23.13 1295.28 0.87 247.95 1500.00 2500.00 5543.23 1748.65 99.75 101.70
11 16.13 3.06 73.32 24.44 1368.64 0.92 262.20 1500.00 2500.00 5630.84 1840.14 91.49
12 16.50 2.96 77.04 25.68 1438.08 0.96 273.60 1500.00 2500.00 5711.68 1929.62 89.48
13 16.88 2.87 80.62 26.87 1504.72 1.01 287.85 1500.00 2500.00 5792.57 2018.32 88.70
14 17.25 2.78 83.84 27.95 1565.20 1.05 299.25 1500.00 2500.00 5864.45 2109.51 91.19
15 17.63 2.71 87.30 29.10 1629.60 1.09 310.65 1500.00 2500.00 5940.25 2191.97 82.46
16 18.00 2.64 90.48 30.16 1688.96 1.13 322.05 1500.00 2500.00 6011.01 2276.90 84.93
17 18.38 2.58 93.72 31.24 1749.44 1.18 336.30 1500.00 2500.00 6085.74 2358.81 81.91
18 18.75 2.52 96.72 32.24 1805.44 1.21 344.85 1500.00 2500.00 6150.29 2440.59 81.78
19 19.13 2.47 99.86 33.29 1864.24 1.25 356.25 1500.00 2500.00 6220.49 2518.42 77.83
20 19.50 2.42 102.80 34.27 1919.12 1.29 367.65 1500.00 2500.00 6286.77 2597.84 79.42 84.92
21 19.88 2.38 105.96 35.32 1977.92 1.32 376.20 1500.00 2500.00 6354.12 2669.80 71.96
22 20.25 2.34 108.96 36.32 2033.92 1.36 387.60 1500.00 2500.00 6421.52 2744.24 74.44
23 20.63 2.30 111.80 37.27 2087.12 1.40 399.00 1500.00 2500.00 6486.12 2820.05 75.81
24 21.00 2.26 114.48 38.16 2136.96 1.43 407.55 1500.00 2500.00 6544.51 2895.80 75.75
25 21.38 2.23 117.50 39.17 2193.52 1.48 421.80 1500.00 2500.00 6615.32 2966.51 70.71
26 21.75 2.20 120.40 40.13 2247.28 1.51 430.35 1500.00 2500.00 6677.63 3035.29 68.78
27 22.13 2.17 123.18 41.06 2299.36 1.54 438.90 1500.00 2500.00 6738.26 3105.19 69.90
28 22.50 2.14 125.84 41.95 2349.20 1.57 447.45 1500.00 2500.00 6796.65 3176.00 70.81
29 22.88 2.11 128.38 42.79 2396.24 1.60 456.00 1500.00 2500.00 6852.24 3247.51 71.51
30 23.25 2.09 131.40 43.80 2452.80 1.64 467.40 1500.00 2500.00 6920.20 3311.10 63.59 71.33
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT Sl.No.
Lead
inK.M
.(L)
Average speed Km/hour(s) No.of Trips
No.
No.of Km.
done
2NL+6
Litre of
diesel
consumed
Litre of
Diesel @
per Ltr.
Litres of
M.Oil
consumed
Cost of
M.Oil @
per litre
Cost of 6
Beldar @
per day
Hire
Charges
of Truck
@ per day
Total
cost
Col.No6+
8+9+10
Cost per
trip
Increas
e in
Cost per
Km over
previou
s Km.
Average
cost per
additional
Km.after
five Km.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.151
Shimla Jal Prabandhan Nigam Limited Rate Analysis
776.25 896.20 1014.89 1130.25 1240.14 101.70 84.92
1 2 3 4 5 6 7 8 9 10 11 12
1 Lime, moorum , building rubish. 6 cu.m 6.00 1 cu.m 129.38 149.37 169.15 188.38 206.69 16.95 14.15
2 Earth work. 6 cu.m 4.80 1 cu.m 161.72 186.71 211.44 235.47 258.36 21.19 17.69
3 Manure or sludge 6 cu.m 5.52 1 cu.m 140.63 162.36 183.86 204.76 224.66 18.42 15.38
4 Excavated rock. 6 cu.m 3.00 1 cu.m 258.75 298.73 338.30 376.75 413.38 33.90 28.31
5 Sand,stone agg. below 40mm 5 cu.m 5.00 1 cu.m 155.25 179.24 202.98 226.05 248.03 20.34 16.98
6 Stone agg.40mm & above,build.
Stones.
5 cu.m 4.62 1 cu.m 168.02 193.98 219.67 244.64 268.43 22.01 18.38
7 Soling stone, stone block & stone
for filling crates
5 cu.m 4.25 1 cu.m 182.65 210.87 238.80 265.94 291.80 23.93 19.98
8 Bricks. 2000Nos. 2000.00 1000 Nos. 388.13 448.10 507.45 565.13 620.07 50.85 42.46
9 Bricks tiles. 3200Nos. 3200.00 1000 Nos. 242.58 280.06 317.15 353.20 387.54 31.78 26.54
10 Slates. 14450Nos. 14450.00 1000 Nos. 53.72 62.02 70.23 78.22 85.82 7.04 5.88
11 Terrazzo Tiles. 2500Nos. 2500.00 1000 Nos. 310.50 358.48 405.96 452.10 496.06 40.68 33.97
12 Cement G.I. CI. AC. CC pipes
below 100mm dia & other heavy
materials.
7.50 Tonne 7.50 1 Tonne 103.50 119.49 135.32 150.70 165.35 13.56 11.32
13 Steam Coal 5.5 Tonne 5.50 1 Tonne 141.14 162.95 184.53 205.50 225.48 18.49 15.44
14 Steel i/c C.G.I & A.C.sheet. 7.50 Tonne 7.50 1 Tonne 103.50 119.49 135.32 150.70 165.35 13.56 11.32
15 Timber 5 cu.m 5.00 1 cu.m 155.25 179.24 202.98 226.05 248.03 20.34 16.98
16 Tar Bitumen etc. 4.50 Tonne 4.50 1 Tonne 172.50 199.16 225.53 251.17 275.59 22.60 18.87
17 R.C.C.,A.C. Hume, steel
C.I.Pipes:- 80 mm dia
329.40m 329.40 100m 235.66 272.07 308.10 343.12 376.48 30.87 25.78
14.27
15.85
21.65
4.94
28.53
9.51
12.97
9.51
14.27
15.44
16.78
35.67
22.29
13
11.89
14.86
12.92
23.78
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALSS.No MATERIALS CAPACITY NET QTY.TO
BE PAID
AFTER
DEDUCTION
OF VOIDS.
UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW
1 Km. 2Km. 3Km. 4Km. 5Km. BEYOND
5Km.UP TO
10 Km.
BEYOND
10Km.UP
TO 20 Km.
BEYOND 20Km
/Km.
71.33
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.152
Shimla Jal Prabandhan Nigam Limited Rate Analysis
776.25 896.20 1014.89 1130.25 1240.14 101.70 84.92
1 2 3 4 5 6 7 8 9 10 11 12 13
S.No MATERIALS CAPACITY NET QTY.TO
BE PAID
AFTER
DEDUCTION
OF VOIDS.
UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW
1 Km. 2Km. 3Km. 4Km. 5Km. BEYOND
5Km.UP TO
10 Km.
BEYOND
10Km.UP
TO 20 Km.
BEYOND 20Km
/Km.
71.33
18 100 mm dia 292.80m 292.80 100m 265.11 306.08 346.62 386.01 423.55 34.73 29.00
19 125 mm dia 219.6m 219.60 100m 353.48 408.11 462.15 514.69 564.73 46.31 38.67
20 150 mm dia 183m 183.00 100m 424.18 489.73 554.58 617.62 677.67 55.57 46.40
21 200 mm dia 109.80m 109.80 100m 706.97 816.21 924.31 1029.37 1129.45 92.62 77.34
22 250 mm dia 80.52m 80.52 100m 964.05 1113.02 1260.42 1403.69 1540.16 126.30 105.46
23 300 mm dia 62.22m 62.22 100m 1247.59 1440.37 1631.13 1816.54 1993.15 163.45 136.48
24 350 mm dia 43.92m 43.92 100m 1767.42 2040.53 2310.77 2573.43 2823.63 231.56 193.35
25 400 mm dia 32.94m 32.94 100m 2356.56 2720.70 3081.03 3431.24 3764.85 308.74 257.80
26 450 /500mmdia 25.62m 25.62 100m 3029.86 3498.05 3961.32 4411.59 4840.52 396.96 331.46
27 600, 700, 750 & 800 mm dia 18.30m 18.30 100m 4241.80 4897.27 5545.85 6176.23 6776.72 555.74 464.04
28 900,1000,1100 & 1200 mm dia. 11.00m 11.00 100m 7056.82 8147.27 9226.27 10275.00 11274.00 924.55 772.00
278.42
389.78
648.45
32.48
38.98
64.96
88.59
114.64
162.41
24.36
216.55
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.153
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
LIGHT MATERIALS A : 7.67 250.00 1917.50 2301.00
1 Lime, moorum and building rubish. 35 cu.m 35.00 1 cu.m 1917.50 65.74 27.39 93.13 586.15 293.08
2 .Earth work. 35 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
3 Manure or sludge 35cu.m 32.20 1 cu.m 1917.50 71.46 29.77 101.23 637.09 318.55
4 Excavated rock. 35 cu.m 17.50 1 cu.m 1917.50 131.49 54.79 186.28 1172.50 586.25
5 Sand,stone agg.below 40mm size. 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
6 Stone agg.40mm & above,build. Stones. 28 cu.m 25.90 1 cu.m 1917.50 88.84 37.02 125.86 792.22 396.11
7 Soling stone, stone block & stone for filling crates 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
8 Bricks. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
9 Bricks tiles. 24000
Nos.
24000.00 1000 Nos. 1917.50 95.88 39.95 135.83 854.93 427.47
10 Slates. 80000
Nos.
80000.00 1000 Nos. 1917.50 28.76 11.98 40.74 256.38 128.19
11 Terrazzo Tiles. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
HEAVY MATERIALS A : 9.20 250.00 2300.00 B : =(Col.No.7/2+Col.No.7*1.40/2) 2760.00
1 Stone blocks G.I,C.C. pipes below 100mm dia and
other heavy materials.
46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
2 cement 57 Tonne 57.00 1 Tonne 2300.00 48.42 20.18 68.60 431.84 215.92
3 Steel including C.G.I & asbestos sheet. 27 Tonne 27.00 1 Tonne 2300.00 102.22 42.59 144.81 911.43 455.72
4 Timber 42 cu.m 42.00 1 cu.m 2300.00 65.71 27.38 93.09 585.93 292.97
5 Tar Bitumen etc. 46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
6 Concrete, R.C.C. Hume, steel C.I.Pipes:- 100mm
dia
1702m 1702.00 100m 2300.00 162.16 67.57 229.73 1445.99 723.00
No's Beldar @ B : =(Col.No.7/2+Col.No.7*1.40/2)
No's Beldar @
CARRIAGE OF MATERIAL BY MANUAL LABOUR INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID A
FT
ER
DE
DU
CT
ION
OF
VO
IDS
.
UN
ITS
CO
ST
OF 8
HO
UR
S COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IRS
T 5
0
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF 5
0
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
0.5
0
FO
R 1
00
MT
R
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.154
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID A
FT
ER
DE
DU
CT
ION
OF
VO
IDS
.
UN
ITS
CO
ST
OF 8
HO
UR
S COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IRS
T 5
0
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF 5
0
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
0.5
0
FO
R 1
00
MT
R
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
7 Concrete, R.C.C. Hume, steel C.I.Pipes:- 125mm dia 1391m 1391.00 100m 2300.00 198.42 82.67 281.09 1769.15 884.58
8 Concrete, R.C.C. Hume, steel C.I.Pipes:- 150mm dia 1208m 1208.00 100m 2300.00 228.48 95.20 323.68 2037.28 1018.64
9 Concrete, R.C.C. Hume, steel C.I.Pipes:- 200mm dia 805m 805.00 100m 2300.00 342.86 142.86 485.72 3057.20 1528.60
10 Concrete, R.C.C. Hume, steel C.I.Pipes:- 250mm dia 458m 458.00 100m 2300.00 602.62 251.09 853.71 5373.33 2686.67
11 Concrete, R.C.C. Hume, steel C.I.Pipes:- 300mm dia 366m 366.00 100m 2300.00 754.10 314.21 1068.31 6724.09 3362.05
12 Concrete, R.C.C. Hume, steel C.I.Pipes:- 350mm dia 256m 256.00 100m 2300.00 1078.13 449.22 1527.35 9613.31 4806.66
13 Concrete, R.C.C. Hume, steel C.I.Pipes:- 400mm dia 220m 220.00 100m 2300.00 1254.55 522.73 1777.28 11186.42 5593.21
14 Concrete, R.C.C. Hume, steel C.I.Pipes:-
450mm,500mm dia
165m 165.00 100m 2300.00 1672.73 696.97 2369.70 14915.16 7457.58
15 Concrete, R.C.C. Hume, steel C.I.Pipes:- 600,700,750
& 800mm dia
150m 150.00 100m 2300.00 1840.00 766.67 2606.67 16406.73 8203.37
16 Concrete, R.C.C. Hume, steel C.I.Pipes:-
900,1000,1100&1200mm dia
125m 125.00 100m 2300.00 2208.00 920.00 3128.00 19688.00 9844.00
17 Asbestes cement pipes: - 50mm dia =5032 pipes
of 2m length 10064m
10064m 10064.00 100m 2300.00 27.42 11.43 38.85 244.59 122.30
18 As bestes cement pipes: - 80mm dia 1620 pipes of
2m length=3660
3660m 3660.00 100m 2300.00 75.41 31.42 106.83 672.39 336.20
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.155
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID A
FT
ER
DE
DU
CT
ION
OF
VO
IDS
.
UN
ITS
CO
ST
OF 8
HO
UR
S COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IRS
T 5
0
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF 5
0
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
0.5
0
FO
R 1
00
MT
R
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
19 As bestes cement pipes:- 100mm dia 1281 pipes of
2m length=2562m
2562m 2562.00 100m 2300.00 107.73 44.89 152.62 960.64 480.32
20 As bestes cement pipes:- 125mm dia 1100 pipes of
2m length= 2200m
2200m 2200.00 100m 2300.00 125.45 52.27 177.72 1118.58 559.29
21 As bestes cement pipes:- 150mm dia 915 pipes of
2m length =1830m
1830m 1830.00 100m 2300.00 150.82 62.84 213.66 1344.78 672.39
22 As bestes cement pipes:- 200mm dia 800 pipes of
2m length= 1600m
1600m 1600.00 100m 2300.00 172.50 71.88 244.38 1538.22 769.11
23 As bestes cement pipes:- 250mm dia 700 pipes of
2m length= 1400m
1400m 1400.00 100m 2300.00 197.14 82.14 279.28 1757.80 878.90
24 As bestes cement pipes:- 300mm dia 600 pipes of
2m length= 1200m
1200m 1200.00 100m 2300.00 230.00 95.83 325.83 2050.77 1025.39
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.156
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 1
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 80 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1Basic rates on F.O.R. destination
Chandigarh Mtr.10.00 691.8399 6918.40
Add 10% for Specials 0.10 691.84
Add 0.5% for inspection charges. 34.59
Add 3% for entry tax 207.55
White lead hemp oil etc., L.S. 35.00
Sub Total:- 7887.38 (A)
2 Carriage
130Km by Mech Transport Chandigarh to
ShimlaTonne 0.101 1449.51 146.40
6 Km by Mech. Transport from IPH.Store Tonne 0.101 1449.51 146.40
0.5 Km by Head Load Tonne 0.101 285.00 28.79
Sub total:- 321.59 (B)
3 Labour
1 Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total:- 414.30 (C)
Total (A+B+C) 8623.27
4 Other Additions
Add 10% C.P & 5 % O.H charges 8623.27 15.00% 1293.49
Add GST 0.00% 0.00
Add 1% Labour Cess 1.00% 86.23
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 1431.51 (D)
Cost for 10 Rmt. (A+B+C+D) 10054.78
Cost per running meter 1005.48
Cost of excavation 412.73
Cost per meter including excavation 1418.21
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.157
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 2
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 100 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1 Chandigarh Mtr. 10.00 996.6616 9966.62
Add 10% for Specials 0.10 996.66
Add 3 % Entry tex 299.00
Add 0.5% for inspection charges. 49.83
White lead hemp oil etc., L.S. 35.00
Sub Total:- 11347.11 (A)
2 Carriage
130Km by Mech Transport Chandigarh to
ShimlaTonne 0.148 1449.51 214.53
6 Km by Mech. Transport from IPH.Store Tonne 0.148 1449.51 214.53
0.5 Km by Head Load Tonne 0.148 285.00 42.18
Sub total:- 471.23 (B)
3 Labour
1 Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total:- 414.30 (C)
Total (A+B+C) 10852.15
4 Other Additions
Add 10% C.P & 5 % O.H charges 10852.15 15.00% 1627.82
Add GST 0.00% 0.00
Add 1% Labour Cess 1.00% 108.52
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 1788.13 (D)
Cost for 10 Rmt. (A+B+C+D) 14020.78
Cost per running meter 1402.08
Cost of excavation 412.73
Cost per meter including excavation 1814.81
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.158
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 3
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 150 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1 Basic rates on F.O.R. destination
Chandigarh Mtr. 10.00 1474.7898 14747.90 (A)
Add 10% for Specials 0.10 1474.79
Add 3 % Entry tex 442.44
Add 0.5% for inspection charges. 73.74
White lead hemp oil etc., L.S. 35.00
Sub total 16773.86 (A1)
2 Carriage
130 Km by Mech Transport Chandigarh to Shimla Tonne 0.219 1449.51 317.44
6 Km by Mech. Transport from IPH.Store Tonne 0.219 1449.51 317.44
0.5 Km by Head Load Tonne 0.219 285.00 62.42
Sub total 697.30 (B)
3 Labour
Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total 414.30 (C)
Total (A+B+C) 17885.46
4 Other Additions
Add 10% C.P & 5 % O.H charges 17885.46 15.00% 2682.82
Add GST 0.00% 0.00
Add 1% Labour Cess 1.00% 178.85
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 2913.46 (D)
Cost for 10 Rmt. (A+B+C+D) 20798.93
Cost per running meter 2079.89
Cost of excavation 412.73
Cost per meter including excavation 2492.63
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.159
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 206.50 mm dia
Diameter in mm 206.5
Thickness in mm 6.3
Density in Kg per Cum 7850
WT per Meter in Kg 33.06
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.21
Wt of pair of flange in Kg 4.41
No of Nut bolts 24
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 4.8
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 206.50 mm dia 3372.12 Kg 58.00 195582.96
Add GST 18.00% 35204.93
Cost of Pipe including GST 230787.89
Add entry tax 3.00% 6923.64
Add inspection Charges 0.50% 1153.94
Cost of pipe 238865.47
Carriage of pipes by mechanical transportation 1 Job 9901.31 9901.31
Carriage of pipes by head load 1 Job 1628.60 1628.60
Unloading and stacking 1 Job 1628.60 1628.60
Cost of Transportation of pipe 100 m length 13158.51
Cost of Pipe Welding 5231.25 cm 5.00 26156.25
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 3381.33 Kg 1.02 3448.96
RATE ANALYSIS - 4
Providing & laying in trenches MS ERW Pipelines of given 206.5 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.160
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 64.87
Outer side 68.83
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804133.7 Sqm 122.5 16378.25
Hasion cloth wraping
Clothe 0.69 Sqm 25.00 17.25
Bitumen 0.69 Sqm 40.00 27.60
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 141.78
Cost of wraping for 100 meters 14178.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.269948.31 % 15.00% 40492.25
Pair of Flange 4.41 Kg 64.00 282.24
Nut Blots 4.8 Kg 59.75 286.8
Add GST 12.00% 34.42
Cost of Flanges including GST 603.46
Add entry tax 3.00% 18.1
Add inspection Charges 0.50% 3.02
Cost of flange 624.58
Gasket 2 No 105.00 210.00
Length of welding from inside 129.75 cm 5.00 648.75
Length of welding from outside 275.33 cm 5.00 1376.65
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 2866.34
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.2810.7997 % 15.00% 421.62
Cost of pair of flange 3287.96
Add 1% Labour Cess 272759.11 % 1.00% 2727.59
Add EPF 12.5% on all Labour 63232.24 % 12.50% 7904.03
Cost of Piping including all for 100 meter 367642.65
Cost of Piping including all per meter 3676.43
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.161
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 260.4mm dia
Diameter in mm 260.4
Thickness in mm 6.3
Density in Kg per Cum 7850
WT per Meter in Kg 41.44
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.385
Wt of pair of flange in Kg 4.77
No of Nut bolts 36
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 7.2
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 260.4mm dia 4226.88 Kg 58.00 245159.04
Add GST 18.00% 44128.63
Cost of Pipe including GST 289287.67
Add entry tax 3.00% 8678.63
Add inspection Charges 0.50% 1446.44
Cost of pipe 299412.74
Carriage of pipes by mechanical transportation 1 Job 13502.70 13502.70
Carriage of pipes by head load 1 Job 2862.43 2862.43
Unloading and stacking 1 Job 2862.43 2862.43
Cost of Transportation of pipe 100 m length 19227.56
Cost of Pipe Welding 6518.18 cm 5.00 32590.90
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
RATE ANALYSIS - 5
Providing & laying in trenches MS ERW Pipelines of given 260.4 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.162
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 4238.85 Kg 1.02 4323.63
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 81.81
Outer side 85.77
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804167.58 Sqm 122.5 20528.55
Hasion cloth wraping
Clothe 0.86 Sqm 25.00 21.50
Bitumen 0.86 Sqm 40.00 34.40
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 152.83
Cost of wraping for 100 meters 15283.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.338158.06 % 15.00% 50723.71
Pair of Flange 4.77 Kg 64.00 305.28
Nut Blots 7.2 Kg 59.75 430.2
Add GST 12.00% 51.62
Cost of Flanges including GST 787.1
Add entry tax 3.00% 23.61
Add inspection Charges 0.50% 3.94
Cost of flange 814.65
Gasket 2 No 105.00 210.00
Length of welding from inside 163.61 cm 5.00 818.05
Length of welding from outside 343.06 cm 5.00 1715.30
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 3564.36
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.3485.1897 % 15.00% 522.78
Cost of pair of flange 4087.14
Add 1% Labour Cess 341643.25 % 1.00% 3416.43
Add EPF 12.5% on all Labour 76304.81 % 12.50% 9538.10
Cost of Piping including all for 100 meter 460177.14
Cost of Piping including all per meter 4601.77
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.163
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 309.70 mm dia
Diameter in mm 309.7
Thickness in mm 7.1
Density in Kg per Cum 7850
WT per Meter in Kg 55.47
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.485
Wt of pair of flange in Kg 4.97
No of Nut bolts 36
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 7.2
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 309.70 mm dia 5657.94 Kg 58.00 328160.52
Add GST 18.00% 59068.89
Cost of Pipe including GST 387229.41
Add entry tax 3.00% 11616.88
Add inspection Charges 0.50% 1936.15
Cost of pipe 400782.44
Carriage of pipes by mechanical transportation 1 Job 17473.44 17473.44
Carriage of pipes by head load 1 Job 3581.99 3581.99
Unloading and stacking 1 Job 3581.99 3581.99
Cost of Transportation of pipe 24637.42
Cost of Pipe Welding 7733.47 cm 5.00 38667.35
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 5670.11 Kg 1.02 5783.51
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 6
Providing & laying in trenches MS ERW Pipelines of given 309.7 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.164
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 97.3
Outer side 101.76
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804199.06 Sqm 122.5 24384.85
Hasion cloth wraping
Clothe 1.02 Sqm 25.00 25.50
Bitumen 1.02 Sqm 40.00 40.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 163.23
Cost of wraping for 100 meters 16323.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.439002.03 % 15.00% 65850.3
Pair of Flange 4.97 Kg 64.00 318.08
Nut Blots 7.2 Kg 59.75 430.2
Add GST 12.00% 51.62
Cost of Flanges including GST 799.9
Add entry tax 3.00% 24
Add inspection Charges 0.50% 4
Cost of flange 827.9
Gasket 2 No 105.00 210.00
Length of welding from inside 194.59 cm 5.00 972.95
Length of welding from outside 407.02 cm 5.00 2035.10
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 4052.31
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.3972.6897 % 15.00% 595.90
Cost of pair of flange 4648.21
Add 1% Labour Cess 442974.72 % 1.00% 4429.75
Add EPF 12.5% on all Labour 89212.14 % 12.50% 11151.52
Cost of Piping including all for 100 meter 597703.73
Cost of Piping including all per meter 5977.04
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.165
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 312.70 mm dia
Diameter in mm 312.7
Thickness in mm 7.1
Density in Kg per Cum 7850
WT per Meter in Kg 56
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.364
Wt of pair of flange in Kg 4.73
No of Nut bolts 36
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 7.2
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 312.70 mm dia 5712 Kg 58.00 331296
Add GST 18.00% 59633.28
Cost of Pipe including GST 390929.28
Add entry tax 3.00% 11727.88
Add inspection Charges 0.50% 1954.65
Cost of pipe 404611.81
Carriage of pipes by mechanical transportation 1 Job 17473.44 17473.44
Carriage of pipes by head load 1 Job 3581.99 3581.99
Unloading and stacking 1 Job 3581.99 3581.99
Cost of Transportation of pipe 100 m length 24637.42
Cost of Pipe Welding 7805.1 cm 5.00 39025.50
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 5723.93 Kg 1.02 5838.41
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 6
Providing & laying in trenches MS ERW Pipelines of given 312.7 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.166
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 98.24
Outer side 102.7
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804200.94 Sqm 122.5 24615.15
Hasion cloth wraping
Clothe 1.03 Sqm 25.00 25.75
Bitumen 1.03 Sqm 40.00 41.20
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 163.88
Cost of wraping for 100 meters 16388.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.442845.86 % 15.00% 66426.88
Pair of Flange 4.73 Kg 64.00 302.72
Nut Blots 7.2 Kg 59.75 430.2
Add GST 12.00% 51.62
Cost of Flanges including GST 784.54
Add entry tax 3.00% 23.54
Add inspection Charges 0.50% 3.92
Cost of flange 812
Gasket 2 No 105.00 210.00
Length of welding from inside 196.48 cm 5.00 982.40
Length of welding from outside 410.79 cm 5.00 2053.95
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 4064.71
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.3985.6297 % 15.00% 597.84
Cost of pair of flange 4662.55
Add 1% Labour Cess 446831.49 % 1.00% 4468.31
Add EPF 12.5% on all Labour 89948.79 % 12.50% 11243.60
Cost of Piping including all for 100 meter 602963.01
Cost of Piping including all per meter 6029.63
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.167
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 341.50 mm dia
Diameter in mm 341.5
Thickness in mm 8
Density in Kg per Cum 7850
WT per Meter in Kg 68.95
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 3.888
Wt of pair of flange in Kg 7.78
No of Nut bolts 48
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 9.6
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 341.50 mm dia 7032.9 Kg 58.00 407908.2
Add GST 18.00% 73423.48
Cost of Pipe including GST 481331.68
Add entry tax 3.00% 14439.95
Add inspection Charges 0.50% 2406.66
Cost of pipe 498178.29
Carriage of pipes by mechanical transportation 1 Job 24754.49 24754.49
Carriage of pipes by head load 1 Job 285.00 285.00
Unloading and stacking 1 Job 285.00 285.00
Cost of Transportation of pipe 25324.49
Cost of Pipe Welding 8535.71 cm 5.00 42678.55
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 7050.28 Kg 1.02 7191.29
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 7
Providing & laying in trenches MS ERW Pipelines of given 341.5 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.168
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 107.29
Outer side 112.31
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804219.6 Sqm 122.5 26901.00
Hasion cloth wraping
Clothe 1.12 Sqm 25.00 28.00
Bitumen 1.12 Sqm 40.00 44.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 169.73
Cost of wraping for 100 meters 16973.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.528021.91 % 15.00% 79203.29
Pair of Flange 7.78 Kg 64.00 497.92
Nut Blots 9.6 Kg 59.75 573.6
Add GST 12.00% 68.83
Cost of Flanges including GST 1140.35
Add entry tax 3.00% 34.21
Add inspection Charges 0.50% 5.7
Cost of flange 1180.26
Gasket 2 No 105.00 210.00
Length of welding from inside 214.57 cm 5.00 1072.85
Length of welding from outside 449.25 cm 5.00 2246.25
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 4722.08
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.4613.3394 % 15.00% 692.00
Cost of pair of flange 5414.08
Add 1% Labour Cess 532635.25 % 1.00% 5326.35
Add EPF 12.5% on all Labour 98108.32 % 12.50% 12263.54
Cost of Piping including all for 100 meter 720499.26
Cost of Piping including all per meter 7204.99
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.169
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 396.40 mm dia
Diameter in mm 396.4
Thickness in mm 8.8
Density in Kg per Cum 7850
WT per Meter in Kg 87.94
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 4.215
Wt of pair of flange in Kg 8.43
No of Nut bolts 48
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 9.6
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 396.40 mm dia 8969.88 Kg 58.00 520253.04
Add GST 18.00% 93645.55
Cost of Pipe including GST 613898.59
Add entry tax 3.00% 18416.96
Add inspection Charges 0.50% 3069.49
Cost of pipe 635385.04
Carriage of pipes by mechanical transportation 8.97 Ton 33006.35 296066.96
Carriage of pipes by head load 8.97 Ton 5959.12 53453.31
Unloading and stacking 8.97 Ton 5959.12 53453.31
Cost of Transportation of pipe 402973.57
Cost of Pipe Welding 9884.71 cm 5.00 49423.55
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 8987.91 Kg 1.02 9167.67
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 8
Providing & laying in trenches MS ERW Pipelines of given 396.4 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.170
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 124.53
Outer side 130.06
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804254.59 Sqm 122.5 31187.28
Hasion cloth wraping
Clothe 1.3 Sqm 25.00 32.50
Bitumen 1.3 Sqm 40.00 52.00
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 181.43
Cost of wraping for 100 meters 18143.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.1032193.49 % 15.00% 154829.02
Pair of Flange 8.43 Kg 64.00 539.52
Nut Blots 9.6 Kg 59.75 573.6
Add GST 12.00% 68.83
Cost of Flanges including GST 1181.95
Add entry tax 3.00% 35.46
Add inspection Charges 0.50% 5.91
Cost of flange 1223.32
Gasket 2 No 105.00 210.00
Length of welding from inside 249.07 cm 5.00 1245.35
Length of welding from outside 520.25 cm 5.00 2601.25
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 5292.64
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.5182.4394 % 15.00% 777.37
Cost of pair of flange 6070.01
Add 1% Labour Cess 1037375.93 % 1.00% 10373.76
Add EPF 12.5% on all Labour 112813.48 % 12.50% 14101.69
Cost of Piping including all for 100 meter 1332699.97
Cost of Piping including all per meter 13327
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.171
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 419 mm dia
Diameter in mm 419
Thickness in mm 10
Density in Kg per Cum 7850
WT per Meter in Kg 105.8
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 6.108
Wt of pair of flange in Kg 12.22
No of Nut bolts 60
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 12
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 419 mm dia 10791.6 Kg 58.00 625912.8
Add GST 18.00% 112664.3
Cost of Pipe including GST 738577.1
Add entry tax 3.00% 22157.31
Add inspection Charges 0.50% 3692.89
Cost of pipe 764427.30
Carriage of pipes by mechanical transportation 1 Job 33006.35 33006.35
Carriage of pipes by head load 1 Job 5959.12 5959.12
Unloading and stacking 1 Job 5959.12 5959.12
Cost of Transportation of pipe 100 m length 44924.59
Cost of Pipe Welding 10481.61 cm 5.00 52408.05
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 10815.82 Kg 1.02 11032.14
RATE ANALYSIS - 8
Providing & laying in trenches MS ERW Pipelines of given 419 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.172
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 131.63
Outer side 137.92
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804269.55 Sqm 122.5 33019.88
Hasion cloth wraping
Clothe 1.38 Sqm 25.00 34.50
Bitumen 1.38 Sqm 40.00 55.20
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 186.63
Cost of wraping for 100 meters 18663.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.787005.84 % 15.00% 118050.88
Pair of Flange 12.22 Kg 64.00 782.08
Nut Blots 12 Kg 59.75 717
Add GST 12.00% 86.04
Cost of Flanges including GST 1585.12
Add entry tax 3.00% 47.55
Add inspection Charges 0.50% 7.93
Cost of flange 1640.6
Gasket 2 No 105.00 210.00
Length of welding from inside 263.27 cm 5.00 1316.35
Length of welding from outside 551.66 cm 5.00 2758.30
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 5937.97
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.5796.4494 % 15.00% 869.47
Cost of pair of flange 6807.44
Add 1% Labour Cess 792802.29 % 1.00% 7928.02
Add EPF 12.5% on all Labour 120243.10 % 12.50% 15030.39
Cost of Piping including all for 100 meter 1073337.07
Cost of Piping including all per meter 10733.37
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.173
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 585 mm dia
Diameter in mm 585
Thickness in mm 12.5
Density in Kg per Cum 7850
WT per Meter in Kg 184.19
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 6.41
Wt of pair of flange in Kg 12.82
No of Nut bolts 60
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 12
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 585 mm dia 18787.38 Kg 58.00 1089668.04
Add GST 18.00% 196140.25
Cost of Pipe including GST 1285808.29
Add entry tax 3.00% 38574.25
Add inspection Charges 0.50% 6429.04
Cost of pipe 1330811.58
Carriage of pipes by mechanical transportation 1 Job 59410.30 59410.30
Carriage of pipes by head load 1 Job 8740.03 8740.03
Unloading and stacking 1 Job 8740.03 8740.03
Cost of Transportation of pipe 100 m length 76890.36
Cost of Pipe Welding 14564.42 cm 5.00 72822.10
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 18812.2 Kg 1.02 19188.44
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 4
Providing & laying in trenches MS ERW Pipelines of given 585 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.174
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 183.78
Outer side 191.64
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804375.42 Sqm 122.5 45988.95
Hasion cloth wraping
Clothe 1.92 Sqm 25.00 48.00
Bitumen 1.92 Sqm 40.00 76.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 221.73
Cost of wraping for 100 meters 22173.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.1327776.27 % 15.00% 199166.44
Pair of Flange 12.82 Kg 64.00 820.48
Nut Blots 12 Kg 59.75 717
Add GST 12.00% 86.04
Cost of Flanges including GST 1623.52
Add entry tax 3.00% 48.71
Add inspection Charges 0.50% 8.12
Cost of flange 1680.35
Gasket 2 No 105.00 210.00
Length of welding from inside 367.57 cm 5.00 1837.85
Length of welding from outside 766.55 cm 5.00 3832.75
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 7573.67
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.7430.7994 % 15.00% 1114.62
Cost of pair of flange 8688.29
Add 1% Labour Cess 1335207.07 % 1.00% 13352.07
Add EPF 12.5% on all Labour 166888.47 % 12.50% 20861.06
Cost of Piping including all for 100 meter 1810987.67
Cost of Piping including all per meter 18109.88
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.175
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Details of cost for 10 Cubic meters :
Sr.
No.Item Unit Qty. Rate Amount
1 Pick Work
1 Labour : Beldar Each 8.32 250.00 2080
Bhisti Each 0.28 250.00 70
Add for water charges @ 1.5% 32.25
Total Rs. 2182.25
Add 10% for Contractor profit 218.23
Add 5% for overhead charges 109.11
Cost of 10 cubic meters Rs. 2509.59
Cost per cum Rs. 250.96
2 Chiselling work in hard rock (Where blasting is prohibitted)1 Labour:
Beldar Each 11.71 250.00 2927.50
Stone Chiseller Each 23.43 250.00 5857.50
Black smith (G-II) Each 0.59 292.00 172.28
Total 8957.28
Add 10% Contractor profit 895.73
Add 5% Overhead Charges 447.86
Cost of 10 cubic meters Rs. 10300.87
Cost per cum Rs. 1030.09
Classification of soil Amount
Pick Work (70%) 250.96 70% 175.67
Chiselling Work (Hard work) (30%) 1030.09 30% 309.03
Average Rate 484.70
Add labour cess @ 1.00 % 484.70 1% 4.85
Add 12 % GST 12.0% 58.16
Total Cost Rs. Per Cum 547.71
Analysis of Rates - 9
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m stacking the soil not more than 3
meters clear from the edge of the excavation and then returning the stacked soil in 15cm layers, when
required into the plinths sides of foundations etc., consolidating each deposited layer by ramming and
watering and then disposing of all surplus excavated earth as directed within a lead of 20 meters.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.176
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Detail of cost for 10 cubic metre
1. Soft rock.
Sr. Item Unit Qty. Rate Amount.
Drilling equipment Day 0.18 3600.00 648.00
Material
Special gelatine (80%) kg. 2.520 75.00 189.00
Detonators ordinary 100 Nos 12.00 300.00 36.00
Safety fuse wire (coil 10 Mtrs length) Coil 1.00 75.00 75.00
Labour
Hole Driller each 0.54 250.00 135.00
Blaster each 0.36 250.00 90.00
Beldar each 6.67 250.00 1667.50
Total 2840.50
Add 10% Contractor profit 284.05
Add 5% Overhead Charges 142.03
Total 3266.58
Cost for 10 cum. 3266.58
Cost for 1 cum 326.66
Detail of cost for 10 cubic metre
2. Hard Rock
Drilling equipment Day 0.28 3600.00 1008.00
Material
Special gelatine (80 % ) Kg. 3.92 75.00 294.00
Detonators ordinary 100 Nos. 14.00 300.00 42.00
Safety fuse wire (coil 10 mtr. length ) Coil 1.25 75.00 93.75
Labour
Hole Driller Each 0.84 250.00 210.00
Blaster Each 0.56 250.00 140.00
Beldar Each 8.33 250.00 2082.50
Total 3870.25
Add 10% Contractor profit 387.025
Add 5% Overhead Charges 193.5125
Total 4450.79
Cost for 10 cum 4450.79
Cost of per cum 445.08
Classification of Rocks Amount
Soft Rock (70%) 326.66 70% 228.66
Hard Rock (30%) 445.08 30% 133.52
Average Rate 362.18
Add labour cess @ 1.00 % 362.18 1% 3.62
Add 12 % GST 12.0% 43.46
Total Cost Rs. Per Cum 409.27
Analysis of Rate - 10
Cutting in earth work and disposal of excavated earth upto a lead of 20 Mtrs soft rock.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.177
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded
stone aggregate 20 mm nominal size ) and curing complete
e/c the cost of form work and reinforcement in foundation &
plinth. (PCC M-150)
1 1.30 1.30 0.15 0.25 Cum 7957.06 2017.11
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in Bottom raft
slab
1 1 1 0.2 0.20 Cum 8,139.12 1627.82
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in Vertical
Walls
2 0.6 0.2 0.75 0.18 Cum 8,139.12 1465.04
2 1 0.2 0.75 0.30 Cum 8,139.12 2441.74
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in chamber top
cover
2 1 0.5 0.2 0.20 Cum 8,139.12 1627.82
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work including
bending binding and placing in position complete, @ 80 Kg
per Cum,
0.88 80 70.40 Kg 62.31 4386.82
Chamber of size 600 mm X 600 mm X 750 mm
Rate Analysis -11
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.178
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo (Ballies) in
Vertical Walls and Slab
For Foundation 1 1 1 1.00 Sqm 289.27 289.27
As per Rate Analysis - 18
Verical walls - inner face 4 0.6 0.75 1.80 Sqm 487.14 876.85
Verical walls - outer face 4 1 0.75 3.00 Sqm 487.14 1461.41
For Top Cover 1 1 1 1.00 Sqm 487.14 487.14
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 18681.03
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.179
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded
stone aggregate 20 mm nominal size ) and curing
complete e/c the cost of form work and reinforcement in
foundation & plinth. (PCC M-150)
1 1.60 1.60 0.15 0.38 Cum 7957.06 3055.51
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix of "
M - 20 " with 20 mm & down gauge nominal size graded
stone aggregate) & curing complete excluding the cost of
form work & reinforcement for reinforced concrete work in
Bottom raft slab
1 1.3 1.3 0.2 0.34 Cum 8,139.12 2751.02
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix of "
M - 20 " with 20 mm & down gauge nominal size graded
stone aggregate) & curing complete excluding the cost of
form work & reinforcement for reinforced concrete work in
Vertical Walls
2 0.9 0.2 0.75 0.27 Cum 8,139.12 2197.56
2 1.3 0.2 0.75 0.39 Cum 8,139.12 3174.26
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix of "
M - 20 " with 20 mm & down gauge nominal size graded
stone aggregate) & curing complete excluding the cost of
form work & reinforcement for reinforced concrete work in
chamber top cover
3 1.3 0.43 0.2 0.34 Cum 8,139.12 2751.02
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work including
bending binding and placing in position complete, @ 80 Kg
per Cum,
1.34 80 106.88 Kg 62.31 6659.99
Rate Analysis -12
Chamber of size 900 mm X 900 mm X 750 mm
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.180
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo (Ballies)
in Vertical Walls and Slab
For Foundation 1 1.3 1.3 1.69 Sqm 289.27 488.86
As per Rate Analysis - 18
Verical walls - inner face 4 0.9 0.75 2.70 Sqm 487.14 1315.27
Verical walls - outer face 4 1.3 0.75 3.90 Sqm 487.14 1899.84
For Top Cover 1 1.3 1.3 1.69 Sqm 487.14 823.26
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 27116.61
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.181
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand:
4graded stone aggregate 20 mm nominal size ) and
curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
1 1.90 1.90 0.15 0.54 Cum 7957.06 4308.75
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in Bottom raft slab
1 1.6 1.6 0.2 0.51 Cum 8,139.12 4167.23
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in Vertical Walls
2 1.2 0.2 0.75 0.36 Cum 8,139.12 2930.08
2 1.6 0.2 0.75 0.48 Cum 8,139.12 3906.78
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix
of " M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding
the cost of form work & reinforcement for reinforced
concrete work in chamber top cover
4 1.6 0.4 0.2 0.51 Cum 8,139.12 4167.23
Rate Analysis -13
Chamber of size 1200 mm X 1200 mm X 750 mm
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.182
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work
including bending binding and placing in position
complete, @ 80 Kg per Cum,
1.86 80 149.12 Kg 62.31 9292.09
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo
(Ballies) in Vertical Walls and Slab
For Foundation 1 1.6 1.6 2.56 Sqm 289.27 740.52
As per Rate Analysis - 18
Verical walls - inner face 4 1.2 0.75 3.60 Sqm 487.14 1753.70
Verical walls - outer face 4 1.6 0.75 4.80 Sqm 487.14 2338.26
For Top Cover 1 1.6 1.6 2.56 Sqm 487.14 1247.07
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 36851.71
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.183
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded
stone aggregate 20 mm nominal size ) and curing complete e/c
the cost of form work and reinforcement in foundation & plinth.
(PCC M-150)
1 2.20 2.20 0.15 0.73 Cum 7957.06 5776.82
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work &
reinforcement for reinforced concrete work in Bottom raft slab
1 1.9 1.9 0.2 0.72 Cum 8,139.12 5876.45
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work &
reinforcement for reinforced concrete work in Vertical Walls
2 1.5 0.2 0.75 0.45 Cum 8,139.12 3662.61
2 1.9 0.2 0.75 0.57 Cum 8,139.12 4639.30
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal mix of " M -
20 " with 20 mm & down gauge nominal size graded stone
aggregate) & curing complete excluding the cost of form work &
reinforcement for reinforced concrete work in chamber top
cover
5 1.9 0.38 0.2 0.72 Cum 8,139.12 5876.45
As per Rate Analysis - 25
Rate Analysis -14
Chamber of size 1500 mm X 1500 mm X 750 mm
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.184
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
5
Providing tor steel reinforcement for RCC work including
bending binding and placing in position complete, @ 80 Kg per
Cum,
2.46 80 197.12 Kg 62.31 12283.10
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo (Ballies) in
Vertical Walls and Slab
For Foundation 1 1.9 1.9 3.61 Sqm 289.27 1044.25
As per Rate Analysis - 18
Verical walls - inner face 4 1.5 0.75 4.50 Sqm 487.14 2192.12
Verical walls - outer face 4 1.9 0.75 5.70 Sqm 487.14 2776.69
For Top Cover 1 1.9 1.9 3.61 Sqm 487.14 1758.57
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 47886.35
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.185
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. No. Item of work No L W D Quantity Rate Unit Amount
1 Excavation in foundation trenches etc. in earth work lift
upto 1.5 mtr. stacking the excavated soil not more than 3
mtr. clear from the edge of excavation and then returning
the stacked soil in 15cm layers when required into plinths
sides of foundation etc. consolidating each deposited
layer by ramming and watering then disposing of all
surplus soil as directed within a lead of 20mtr. in soft &
hard rock.
1 1.35 1.65 1 2.23 547.71 Per cum. 1220.02
2 Prov. & laying cement
conc.1:2:4(1cement:2sand:4graded stone aggregate 20
mm nominal size ) and curing complete e/c the cost of
form work and reinforcement in foundation & plinth.1 1.35 1.65 0.15 0.33 7957.06 Per Cum. 2658.65
Providing & laying cement concrete using nominal mix of
" M - 20 " with 20 mm & down gauge nominal size
graded stone aggregate) & curing complete excluding the
cost of form work & reinforcement for reinforced concrete
work in Bottom raft slab
(a)foundation footintg basis of columns and like mass
concrete. 1 1.2 1.5 0.45 0.81 8,139.12 Per Cum. 6592.69
(b)Columns pillar posts and struts upto floor two level.1 0.3 0.9 2.15 0.58 8139.12 Per Cum 4724.76
4 Providing mild steel/Tor steel reinforcement for R.C.C.
work including bending, binding and placing in position
complete upto floor two level. Tor steel. 139.05 62.31 Per Kg. 8664.60
Rate Anlysis - 15 SH:-Construction of RCC Anchor Block size 0.3m*0.9m
ABSTRACT OF COST
3
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.186
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. No. Item of work No L W D Quantity Rate Unit Amount
Providing form work with steel plates 3.15mm thick
welded with angle iron in frame 30x30x5mm so as to give
a fair finish including centring shuttering strutting and
propping etc., with wooden battens and ballies, height of
propping and centring below supporting floor to ceiling not
exceeding 4 meters and removal of the same for in-situ-
reinforced concrete and plain concrete work in:-
a)Foundation, footing, basis of columns etc., and mass
concrete. 2.43 289.27 Per Sqmt. 702.92
b) Columns pillar posts and struts square, rectangular or
polygonal in plan. 5.16 487.14 Per Sqmt. 2513.63
27077.27Total Rs. In Lac.
5
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.187
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L W D Qty Unit Rate Amount
1
Providing and laying bituminous macadam using
crushed stone aggregates of specified grading premixed
with bituminous binder, transported to site by tippers, laid
over a previously prepared surface with paver finisher
equiped with electronic sensor to the required grade,
level and alignment and rolling with smooth wheeled,
vibratory and tandem rollers as per specifications to
achieve the desired compaction and density, complete
as per specificatons and directions of Engineer-in-
Charge. 50 to 100 mm average
compacted thickness with bitumen of grade VG-30 @
3.50% (percentage by weight of total mix) prepared in
Batch Type Hot Mix Plant of 100- 120 TPH capacity.
CPWD DSR Vol 2 16.55.1
1 1 1 0.075 0.075 Cum 5708.05 428.104
2
Construction of granular sub-base by providing close
graded Material conforming to specifications, mixing in a
mechanical mix plant at OMC, carriage of mixed material
by tippers to work site, for all leads & lifts, spreading in
uniform layers of specified thickness with motor grader
on prepared surface and compacting with vibratory
power roller to achieve the desired density, complete as
per specifications and directions of Engineer-in-Charge.
With material conforming to Grade-I (size range 75 mm
to 0.075 mm) having CBR Value-30 CPWD DSR Vol 2
16.78.1
1 1 1 0.2 0.2 Cum 2089.7 417.94
Rate Analysis -16 : Road Restoration
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.188
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L W D Qty Unit Rate Amount
3Providing and constructing WBM CPWD DSR Vol 2
16.13.21 1 1 0.175 0.175 Cum 1407.15 246.251
4
2.5 cm premix carpet surfacing with 2.25 cum and 1.12
cum of stone chippings of
13.2 mm and 11.2 mm size respectively per 100 sqm
and 52 kg and 56 kg of hot
bitumen per cum of stone chippings of 13.2 mm and
11.2 mm size respectively,
including a tack coat with hot straight run bitumen,
including consolidation with
road roller of 6 to 9 tonne capacity etc. complete (tack
coat to be paid for separately). With paving Asphalt
grade VG - 10 heated and then mixed with solvent at the
rate of 70 grams per kg of asphalt CPWD DSR Vol 2
16.33.1
1 1 1 1 Sqm 169.6 169.6
Total 1261.90
Add 12% for GST 151.43
Total 1413.32
Say 1400.00
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.189
Shimla Jal Prabandhan Nigam Limited Rate Analysis
A
B
C
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
A Water Supply Connections
ROVIDING & LAYING IN TRENCHES GALVANISED MILD STEEL
PIPE CONFORMING TO IS 1239/1990 (5th Revision) HEAVY
CLASS INCLUDING BENDS OF ALL DEGREES, TEES,
COLLARS, TAPERS, CROSSES, FLANGED SOCKET &
SPIGOTS AND JOINTING
As per RA
i) Residential Connections- 15 mm dia 29 5 145 Rmt 200.96 29139.61598
ii) Commercial Connections- 25mm dia 4 5 20 Rmt 243.58 4871.658522
34011.2745
B Electrical Lines & Poles
B-1 Electrical Poles - RA for 10 km
RATE ANALYSIS - 17
Utility Shifting:
1 nos of breakage per km occurred with required of cable length per breakage is assumed as 6 m. 3.0 mtr assumed as Optical cable and 3.0 metre Jelly filled
telephone cable
Amount A / 1 Km
Assumptions
Water Supply Connections
Total No. of properties in 1.00 Km length in city Area Consider property connection at 30 mtr distance is 1000/30 = 34 Nos, Assuming that out of 34 Nos 10% are
commercial connections and 90% are residential Connections. Commercial connections are of 25mm in size and Residential connections are 15 mm Size hence
Commercial connections are 4 Nos. and Residential Connections are 29 Nos Per Km. Connections Pipe length per connections are assumed as 2.5 mtr.
Electrical Lines & Poles
For RA purpose, shifting of one pole per 10 km length of network in city area , Hence RA is estimated for 10 km length. Electrical Cable joints required per km is
assumed as 2 nos
Communication Cable - Jelly Filled telephone lines and optical Fibre Cable
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.190
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
i)
Pole Foundation : providing cement concrete foundation including
excavation for the pole 60 cms x 60 cms x 1.5 mtr deep in1:3:6
cement concrete (20x 25 mm stone metal) and 45 cm x 45cm x45
cm / 45 cm x 45 cm height plinth duly plaster and with necessary
curing & finishing in above manner ( for 9 mtr pole)
1 1 Nos 3158.4 3158.4
PWD DSR 16-17 E&M, Item No. 16.3.2, Page No.306
ii)
Dismantling of existing poles above 6 mtr height with brackets.
Clamps, insulators stay from the cement concrete foundation and
making the site clear by refilling the pits with excavated materials
and bringing it to ground level
1 1 Nos 840 840
PWD DSR 16-17 E&M, Item No. 8.8.2, Page No. 191
i)
Re-Erecting: Supplying and erecting steel tubular swaged pole
165.1 X 139.7 X 114.3 mm dia with 4.5 X 4.5 X3.65 mm thick
(5+2+2m) length respectively and total 9 m long with pole cap,
base plate in provided foundation (weight 147 kg) as per
specifications.
1 1 Nos 13971.3 13971.3
PWD DSR 16-17 E&M, Item No. 8.1.3, Page No. 174
i)
Earthling : Providing pipe type earthing with 40mm. dia.G.l. pipe or
20 mm dia. G.l. Rod complete with all materials as per
specification No. EA-EP
1 1 Nos 1597.05 1597.05
i) PWD DSR 16-17 E&M, Item No. 9.1.4, Page No. 193
19566.75
1956.675
B-2 Electrical Cable - Providing and Jointing 391.335
CCommunication Cable - Jelly Filled telephone lines and optical
Fibre Cable
i)
Supply & Erecting of Jelly filled armoured telephone cable 10 pair
with 0.5 mm dia laid in provided trench as per specification no.
WG-TW
1 3 3 Rmt 114.45 343.35
PWD DSR 16-17 Item 1-10-10, Page No. 38
Amount B-1 /10 km
Amount B-1/ 1 Km
Amount B-2/ 1 Km
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.191
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
ii)
Supply & erecting of FR grade PVC armourd multi mode Optical
Fibre Cable with 6 fibres with core dia 50 µM, suitable for 1 GBps
Ethernet distance at 850 nm of wavelength on wall/ ceiling or laid
in provided pipe / trench as per specification no. WG- COC/ OFC
1 3 3 Rmt 236.25 708.75
PWD DSR 16-17 Item 1-12-8, Page No.41
iii)
Supply & fixing of wall /rack type 12 port light guide interconnection
unit for termination of optical fibre cable on wall /provided U rack
complete as per specification no. EG- NAS / LIU
1 1 Nos 4586.4 4586.4
PWD DSR 16-17 Item 1-14-5, Page No. 44 5638.5
41998.00
50397.60Total rate of utility Shifting per Km considering this project
Total rate of utility Shifting per Km for Maharashtra is
Amount C-1/ 1 Km
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.192
Shimla Jal Prabandhan Nigam Limited Rate Analysis
(a)Foundation footing basis of columns etc and mass concrete
Detail of cost for 10 Sqm.
Sr. Description. Unit Qty. Rate. Amount
Material
Rate as per above in Sub Analysis. Sqm. 10.15200 6174.44 62682.92
Battens IInd class kail wood
6 X 1 X 0.075 X 0.10m. = 0.045 cum.
Wastage @ 5% per kg. = 0.002 cum.
Total Qty:- = 0.047 cum.. Cum. 0.047 33,830.00 1590.01
Ballies 125mm dia Kail wood
6 X 1.50 = 9.00 Rmt.
Wastage @ 5% per kg. = 0.45Rmt.
Total Qty:- =9.45 Rmt. Rmt. 9.45 125.00 1181.25
Carriage of Timber :-
Ballies 125mm dia Kail wood
9.45 X 0.785 X (0.125)2 = 0.116 cum.
Battens IInd class kail wood =0.047 cum.
Total Qty:- = 0.163 cum..
50 K.M.by Mechanical Transport. Cum. 0.163 178.91 29.16
0.5 M.by head load. Cum. 0.163 485.53 79.14
Total Rs:- 2879.56
Carriage cost of wood i.e.1/16 Rs:- 6.77
Each. 0.01 62682.92 626.83
cent 0.01 62682.92 626.83
ANALYSIS OF RATES - 18
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Assuming that steel plates shall become unservicable after being used 100
times. Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning concrete
deposits & appling oiling and greasing etc.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.193
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cum. 0.0625 2879.56 179.97
cent 0.05 2879.56 143.98
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.52 292.00 151.84
Beldar. Each. 1.30 250.00 325
Total Rs:- 2054.45
Sundries @ 10% of labour cost. Rs:- 205.445
Total Rs:- 2259.895
Add 10% Contractor profit 225.99
Add 5% Overhead Charges 112.99
Add labour cess @ 1.00 % 22.60
Add 12 % GST 271.192892.67
289.27
Add 5% for using repeatedly including repair removal of dents cleaning concrete
deposits & appling
Cost for 10 Sq.m
Cost per Sqmt. Rs:-
Assuming that Timber shall become unservicable after being used 16
times.Hence cost for using once = 1/16
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.194
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
d)Columns,Pillar;Posts and struts Square Rectangular and Polygonal in Plan
Sr. Description. Unit Qty. Rate. Amount
Rate as per above in Sub Analysis. Sqm. 5.46 6174.44 33712.44
Ballies 125mm dia.(Kail wood 2nd class.) Meter 15.96 125.00 1995.00
50 Carriage of Timber :-K.M.by Mechanical Transport. Cum. 0.196 178.91 35.07
0.5 Carriage of Timber :-M.by head load. Cum. 0.196 485.53 95.16
Total Rs:- 2125.23
Carriage cost of wood i.e.1/16 Rs:- 8.14
Each. 0.01 33712.44 337.12
cent 0.01 33712.44 337.12
Cum. 0.0625 2125.23 132.83
cent 0.05 2125.23 106.26
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.59 292.00 172.28
Beldar. Each. 1.47 250.00 367.50
Total Rs:- 1453.11
Sundries @ 10% of labour cost. On Rs:- 539.78 Rs:- 145.311
Total Rs:- 1598.421
Add 10% Contractor profit 159.84
Add 5% Overhead Charges 79.92
Add labour cess @ 1.00 % 15.98
ANALYSIS OF RATES - 19
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Detail of cost for area in contact 4 X 0.30 X 3.50 = 4.20 Sqm.
Assuming that steel plates shall become unservicable after being used 100
times.Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning concrete
deposits & appling oiling and greasing etc.
Assuming that Timber shall become unservicable after being used 16
times.Hence cost for using once = 1/16
Add 5% for using repeatedly including repair removal of dents cleaning concrete
deposits & appling
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.195
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Add 12 % GST 191.812045.98
487.14Cost per Sqmt. Rs:-
Cost for 10 Sq.m
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.196
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Sr. Description. Unit Qty. Rate. Amount
Material:-
3.15 mm Thick M.S. Plate.
0.90 X 0.60 = 0.54 Sqm.
Weight @ 24.72kg per Sqm. =13.35kg.
Wastage @ 5% per kg. =0.66kg
Total Qty:- =14.01kg or 0.14 Qtl. Qtl. 0.14 4500.00 630.00
Angle iron in frame 30X30X5mm Size
2(0.90+0.60) = = 3.00 Rmt.
Weight @ 2.20kg per Rmt.. =13.35kg.
Wastage @ 5% per kg. =0.33kg
Total Qty:- =6.93kg or 0.0693 Qtl. Qtl. 0.0693 5,000.00 346.50
Sub Total Rs. 976.50 A
Carriage of M.S. Plate and angles.
M.S.Plate. = 0.140 Qtl
Angle iron =0.0693 Qtl.
Total Qty:- =0.2093 Qtl or 0.02093 Tonne.
50 K.M.by Mechanical Transport. Tonne 0.02093 178.91 3.74
0.5 M.by head load. Tonne 0.02093 485.53 10.16
Sub Total Rs. 13.90 B
Labour.
Black Smith Ist. Class. Each 0.066 292.00 19.27
Bandhani Each 0.066 250.00 16.50
Beldar Each 0.154 250.00 38.5
Sundries Each 10
Sub Total Rs. 84.27 C
ANALYSIS OF RATES - 20
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for
shuttering steel work welded in built up section I/c cutting fixing in positionin angles,plates etc. Detail of cost for 90cm X 60cm size of plates
complete 0.54 Sqm.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.197
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Welding charges by Electric Plant CM. 300.00 5.00 1500.00 D
Total Rs. (A+B+C+D) 2574.67
Add 1.5% water charges. Rs:- 38.62
Add 10% Contractor profit 257.47
Add 5% Overhead Charges 128.73
Add labour cess @ 1.00 % 25.75
Add 12 % GST 308.963334.20
6174.44
Cost for 0.54 Sqmt.Rs:-
Cost per Sqmt. Rs:-
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.198
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Discription Unit Qty. Rate Amount
Materials
Cement Tonne 0.32 5,120.00 1638.40
Sand Cum 0.445 650.00 289.25
10mm stone aggregate Cum 0.22 725.00 159.50
20mm stone aggregate Cum 0.67 725.00 485.75
Subtotal 2572.90 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.89 1875.18 1668.91
0 K.M. by Head Load Cum 0.89 390.34 347.40
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.45 1090.33 490.65
0 K.M. by Head Load Cum 0.45 390.34 175.65
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.32 178.91 57.25
0 K.M. by Head Load Tonne 0.32 230.04 73.61
Subtotal 2813.47 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
RATE ANALYSIS - 21
Providing & laying cement concrete 1:2:4, 20mm nominal size & curing complete for RCC work in: Suspended floor, roofs, landing and shelves and their
supports, balconies, beams, girders, bressumers and cantilever upto floor two level.
Details of Cost for 1 Cubic Meter
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.199
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 693.65 (C)
(A+B+C) 6080.02
Add for water charges @1.5% 6,080.02 1.50% 91.20
6171.22
Add 1% Labour cess 6,171.22 1.00% 61.71
Add GST 12.00% 740.55
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4532.82 15% 679.92
Rs:- 7,653.40
Total
Gross Total
Cost for one cubic meter
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.200
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.165 5,758.44 950.14
Subtotal 950.14 (A)
Labour :
Mason II nd class Each 0.80 294.00 235.20
Beldar Each 0.80 245.00 196.00
Bhishti Each 0.98 245.00 240.10
Sundries(Scaffolding etc.) L.S. 45.00
Subtotal 716.30 (B)
Total (A+B) 1666.44
Add for water charges @1.5% 1,666.44 1.50% 25.00
Gross Total 1691.44
Add 1% Labour cess 1,691.44 1.00% 16.91
Add GST 12.00% 202.97
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement741.30 15% 111.20
Cost for 10 square meter Rs:- 2,022.52
Cost of 1 Sqm. Rs:- 202.25
20 mm cement plaster in single coat on fair side f brick/stone masonry for interior plastering up to floor two level including arrises, internal rounded angles,
chamfers and/or rounded angles not exceeding 80mm in girth and finished even and smooth .
In cement mortar 1:4
Details of cost for 10 Sqm.
Desciption
RATE ANALYSIS - 22
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.201
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.224 6,592.42 1476.7
Sand & Gravel Crushed stone graded from 6 mm to 12mm Cum. 0.1 725.00 72.5
Grounded hydrated lime Kg 9.28 100.00 928
Subtotal 2477.2 (A)
Labour :
Mason II nd class Each 1.71 294.00 502.74
Beldar Each 1.58 245.00 387.10
Bhishti Each 1.7 245.00 416.50
Sundries(Scaffolding etc.) L.S. 45.00
Extra labour for coping
Mason II nd class Each 0.25 294.00 73.50
beldar Each 0.25 245.00 61.25
Extra labour for dashing of crushed stone
RATE ANALYSIS - 23
Rough side exterior cement plaster on wall up to a height of 10 mtr. above ground level with a mixture of sand and gravel or crushed stone graded from 6mm to
12 mm nominal size dashed over and including fresh plaster in two coats, backing coat 10 mm cement plaster 1:3 (1cement:3sand) and finishing coat 10 mm
cement mortor 1:3 (1cement:3sand) mixed with 10 % finely grounded hydrated lime by volume of cement including arrises, chamfersb and/or rounded angles
not exceeding 80 mm in girth. (natural cement finish using ordinary cement)
In cement mortar 1:3
Details of cost for 10 Sqm.
Desciption
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.202
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Mason II nd class Each 0.5 294.00 147.00
beldar Each 0.5 245.00 122.50
bhisti Each 0.1 245.00 24.50
sundries ( scaffolding etc.) 10.00
Subtotal 1790.09 (B)
Total (A+B) 4267.29
Add for water charges @1.5% 4,267.29 1.50% 64.01
Gross Total 4331.30
Add 1% Labour cess 4,331.30 1.00% 43.31
Add GST 12.00% 519.76
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2854.60 15% 428.19
Cost for 10 square meter Rs:- 5,322.56
Cost of 1 Sqm. Rs:- 532.26
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.203
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 1875.18 1593.90
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 1090.33 463.39
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 178.91 71.56
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 2718.55 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Discription
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 24
Prov.& laying c.conc. 1:2:4 (1cement:2 sand:4 graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work & reinforcement for RCC
work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.204
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 6361.03
Add for water charges @1.5% 6,361.03 1.50% 95.42
Gross Total 6456.45
Add 1% Labour cess 6,456.45 1.00% 64.56
Add GST 12.00% 774.77
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4408.45 15% 661.27
Cost for one cubic meter Rs:- 7,957.06
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.205
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 1875.18 1593.90
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 1090.33 463.39
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 178.91 71.56
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 2718.55 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
RATE ANALYSIS - 25
P/L cement concrete 1:1.5:3 (1cement:2sand:4graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work in suspended
floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level.
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.206
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 842.12 ( C)
Total (A+B+C) 6501.17
Add for water charges @1.5% 6,501.17 1.50% 97.52
Gross Total 6598.69
Add 1% Labour cess 6,598.69 1.00% 65.99
Add GST 12.00% 791.84
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4550.69 15% 682.60
Cost for one cubic meter Rs:- 8,139.12
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.207
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 1875.18 1425.14
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 1090.33 272.58
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 178.91 109.14
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 2341.43 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 294.00 79.38
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 245.00 12.25
Mate Each 0.04 245.00 9.80
RATE ANALYSIS - 26
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work in
suspended floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level. (Slab for For RCC GSR)
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.208
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Beldar for extra ramming Each 0.25 0.00 0.00
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 791.65 ( C)
Total (A+B+C) 6969.78
Add for water charges @1.5% 6,969.78 1.50% 104.55
Gross Total 7074.33
Add 1% Labour cess 7,074.33 1.00% 70.74
Add GST 12.00% 848.92
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement3951.13 15% 592.67
Cost for one cubic meter Rs:- 8,586.66
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.209
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 1875.18 1425.14
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 1090.33 272.58
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 178.91 109.14
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 2341.43 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Discription
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 27
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work &
reinforcement for RCC work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level. (Wall for For RCC
GSR)
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.210
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 6880.11
Add for water charges @1.5% 6,880.11 1.50% 103.20
Gross Total 6983.31
Add 1% Labour cess 6,983.31 1.00% 69.83
Add GST 12.00% 838.00
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement3860.11 15% 579.02
Cost for one cubic meter Rs:- 8,470.16
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.211
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty Rate Amount
Material:-
Mild Steel Bars Qtl. 1.00
Wastage @ 5% Qtl. 0.05
Total 1.05 Qtl. 1.05 4,500.00 4725.00 (A)
By Mech TransportK.M By Mechanical Transport Tonne 0.105 178.91 18.79
0 K.M ByHead load. Tonne 0.105 485.53 50.98
Subtotal 69.77 (B)
Labour:-
Black Smith Ist class Each 1.00 292.00 292.00
Beldar Each 1.00 245.00 245.00
Sundries LS 10.00
Subtotal 547.00 ( C)
Total (A+B+C) 5341.77
Add for water charges @1.5% 5,341.77 1.50% 80.13
Gross Total 5421.90
Add 1% Labour cess 5,421.90 1.00% 54.22
Add GST 12.00% 650.63
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Steel
696.90 15% 104.54
Cost per Qtl Rs:- 6,231.28
Cost per Kg Rs:- 62.31
RATE ANALYSIS - 28
Providing mild steel/tor steel reinforcement for RCC work includng bending binding and placing in position complete.
Detail of cost for 1 Qtl.
Description.
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.212
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:4 ( 1CEMENT : 4SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.38 5,120.00 1,945.60
Sand Cum 1.07 650.00 695.50
Subtotal 2,641.10 (A)
Carriage
Carriage of Sand
106 K.M. by Mechanical Transport Cum 1.07 1090.33 1,166.65
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.38 178.91 67.99
0 K.M. by Head Load Tonne 0.38 230.04 87.42
Subtotal 1,739.72 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 4,656.94
Add for water charges @1.5% 4,656.94 1.50% 69.85
Gross Total 4726.79
Add 1% Labour cess 4,726.79 1.00% 47.27
Add GST 12.00% 567.21
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2781.19 15% 417.18
Cost for one cubic meter Rs:- 5,758.44
Details of cost for 1cum
RATE ANALYSIS - 29
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.213
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:3 ( 1CEMENT : 3SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.51 5,120.00 2,611.20
Sand Cum 1.07 650.00 695.50
Subtotal 3,306.70 (A)
Carriage
Carriage of Sand
0 K.M. by Mechanical Transport Cum 1.07 1090.33 1,166.65
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.51 178.91 91.24
0 K.M. by Head Load Tonne 0.51 230.04 117.32
Subtotal 1,792.87 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 5,375.69
Add for water charges @1.5% 5,375.69 1.50% 80.64
Gross Total 5456.33
Add 1% Labour cess 5,456.33 1.00% 54.56
Add GST 12.00% 654.76
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2845.13 15% 426.77
Cost for one cubic meter Rs:- 6,592.42
RATE ANALYSIS - 30
Details of cost for 1cum
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.214
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 80 mm dia 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including
transportation141583 144910 180046 248238 327866 366120 467786 645336 694402 967589 1100586
Add for jointing
material 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Add for laying, jointing
labour10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Total 161583.00 164910.00 200046.00 278238.00 357866.00 396120.00 507786.00 685336.00 734402.00 1017589.00 1150586.00
Add 18% for GST 29084.94 29683.80 36008.28 50082.84 64415.88 71301.60 91401.48 123360.48 132192.36 183166.02 207105.48
Add 15% OH and CP 19066.79 19459.38 23605.43 32832.08 42228.19 46742.16 59918.75 80869.65 86659.44 120075.50 135769.15
Rate Including GST 209734.73 214053.18 259659.71 361152.92 464510.07 514163.76 659106.23 889566.13 953253.80 1320830.52 1493460.63
Particulars 80 mm dia 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including
transportation9543 12589 19822 32940 45622 68951 175000 213462 326923 476923
Add for jointing
material 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Add for laying, jointing
labour10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Total 29543.00 32589.00 39822.00 62940.00 75622.00 98951.00 40000.00 215000.00 253462.00 376923.00 526923.00
Add 18% for GST 5317.74 5866.02 7167.96 11329.20 13611.96 17811.18 7200.00 38700.00 45623.16 67846.14 94846.14
Add 15% OH and CP 3486.07 3845.50 4699.00 7426.92 8923.40 11676.22 4720.00 25370.00 29908.52 44476.91 62176.91
Rate Including GST 38346.81 42300.52 51688.96 81696.12 98157.36 128438.40 51920.00 279070.00 328993.68 489246.05 683946.05
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Rate Analysis -32 for FCV and PRV
Rate Analysis -33 for Isolation and Scour Valves
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.215
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 25 mm dia 50 mm dia 80 mm dia 100 mm dia 150 mm dia Particulars Cost
Basic rate including
transportationNA 18991 25312 40474 56360
Basic rate
including
transportation
28651
Add for jointing
material 5000 5000 10000 10000 10000
Add for
jointing
material
2000
Add for laying, jointing
labour5000 5000 10000 10000 10000
Add for laying,
jointing labour3000
Total 10000.00 28991.00 45312.00 60474.00 76360.00 Total 33651.00
Add 18% for GST 1800.00 5218.38 8156.16 10885.32 13744.80Add 18% for
GST 6057.18
Add 15% OH and CP 1180.00 3420.94 5346.82 7135.93 9010.48Add 15% OH
and CP3970.82
Rate Including GST NA 37630.32 58814.98 78495.25 99115.28
Rate
Including
GST
43679.00
Rate Analysis -34 for Air ValvesRate Analysis -35 for
Pressure Transmitter
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.216
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including
transportation98041 105692 125138 138297 158618 219362 249122 266894 310486 357802
Add for jointing
material
Add for laying, jointing
labour
Total 98041.00 105692.00 125138.00 138297.00 158618.00 219362.00 249122.00 266894.00 310486.00 357802.00
Add 18% for GST 17647.38 19024.56 22524.84 24893.46 28551.24 39485.16 44841.96 48040.92 55887.48 64404.36
Add 15% OH and CP 11568.84 12471.66 14766.28 16319.05 18716.92 25884.72 29396.40 31493.49 36637.35 42220.64
Rate Including GST 127257.22 137188.22 162429.12 179509.51 205886.16 284731.88 323360.36 346428.41 403010.83 464427.00
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Rate Analysis -36 for Flow (Bulk) Meter
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.217
Shimla Jal Prabandhan Nigam Limited M and R
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
1 2020 243250 21818159 7172885 3532750 10705635 1.34
2 2021 248264 23141800 7680408 3709388 11389796 1.35
3 2022 253279 24465441 8223876 3894857 12118733 1.36
4 2023 258293 25789082 8805996 4089600 12895596 1.37
5 2024 263308 27112724 9429072 4294080 13723152 1.39
6 2025 268322 28436365 10096080 4508784 14604864 1.41
7 2026 273337 29760006 10810776 4734223 15544999 1.43
8 2027 278351 31083647 11576172 4970934 16547106 1.46
9 2028 283366 32407288 12395388 5219481 17614869 1.49
10 2029 288380 33730929 13272888 5480455 18753343 1.52
11 2030 293395 35054571 14212500 5754477 19966977 1.56
12 2031 298409 36378212 15218760 6042201 21260961 1.6
13 2032 303424 37701853 16296240 6344311 22640551 1.65
O & M EXPENDITURE STATEMENT
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.218
Shimla Jal Prabandhan Nigam Limited M and R
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
14 2033 308438 39025494 17450256 6661527 24111783 1.69
15 2034 313453 40349135 18686124 6994603 25680727 1.74
16 2035 318467 41672776 20009940 7344334 27354274 1.8
17 2036 324814 43403489 21427800 7711550 29139350 1.84
18 2037 331161 45134202 22945872 8097128 31043000 1.88
19 2038 337508 46864915 24571776 8501984 33073760 1.93
20 2039 343856 48595628 26313168 8927083 35240251 1.99
21 2040 350203 50326341 28178412 9373437 37551849 2.04
22 2041 356550 52057054 30176052 9842109 40018161 2.11
23 2042 362897 53787767 32315304 10334215 42649519 2.17
24 2043 369244 55518480 34606164 10850926 45457090 2.24
25 2044 375591 57249193 37060116 11393472 48453588 2.32
26 2045 381938 58979906 39688044 11963145 51651189 2.4
27 2046 388285 60710619 42502992 12561303 55064295 2.48
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.219
Shimla Jal Prabandhan Nigam Limited M and R
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
28 2047 394633 62441332 45517440 13189368 58706808 2.58
29 2048 400980 64172045 48746700 13848836 62595536 2.67
30 2049 407327 65902758 52204884 14541278 66746162 2.77
31 2050 413674 67633471 55908972 15268342 71177314 2.88
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.220
Shimla Jal Prabandhan Nigam Limited M and R
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2020 3.0 14850 534600 0 12690 0 49 9878 5808499 7 9878 829786 7172885
2021 3.0 16038 577368 0 13705 0 49 10570 6215160 7 10570 887880 7680408
2022 3.0 17321 623556 0 14801 0 49 11310 6650280 7 11310 950040 8223876
2023 3.0 18707 673452 0 15985 0 49 12102 7115976 7 12102 1016568 8805996
2024 3.0 20204 727344 0 17264 0 49 12949 7614012 7 12949 1087716 9429072
2025 3.0 21820 785520 0 18645 0 49 13855 8146740 7 13855 1163820 10096080
2026 3.0 23566 848376 0 20137 0 49 14825 8717100 7 14825 1245300 10810776
2027 3.0 25451 916236 0 21748 0 49 15863 9327444 7 15863 1332492 11576172
2028 3.0 27487 989532 0 23488 0 49 16973 9980124 7 16973 1425732 12395388
2029 3.0 29686 1068696 0 25367 0 49 18161 10678668 7 18161 1525524 13272888
2030 3.0 32061 1154196 0 27396 0 49 19432 11426016 7 19432 1632288 14212500
2031 3.0 34626 1246536 0 29588 0 49 20792 12225696 7 20792 1746528 15218760
2032 3.0 37396 1346256 0 31955 0 49 22247 13081236 7 22247 1868748 16296240
2033 3.0 40388 1453968 0 34511 0 49 23804 13996752 7 23804 1999536 17450256
2034 3.0 43619 1570284 0 37272 0 49 25470 14976360 7 25470 2139480 18686124
2035 3.0 47109 1695924 0 40254 0 49 27253 16024764 7 27253 2289252 20009940
2036 3.0 50878 1831608 0 43474 0 49 29161 17146668 7 29161 2449524 21427800
ESTABLISHMENT CHARGES
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.221
Shimla Jal Prabandhan Nigam Limited M and R
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2037 3.0 54948 1978128 0 46952 0 49 31202 18346776 7 31202 2620968 22945872
2038 3.0 59344 2136384 0 50708 0 49 33386 19630968 7 33386 2804424 24571776
2039 3.0 64092 2307312 0 54765 0 49 35723 21005124 7 35723 3000732 26313168
2040 3.0 69219 2491884 0 59146 0 49 38224 22475712 7 38224 3210816 28178412
2041 3.0 74757 2691252 0 63878 0 49 40900 24049200 7 40900 3435600 30176052
2042 3.0 80738 2906568 0 68988 0 49 43763 25732644 7 43763 3676092 32315304
2043 3.0 87197 3139092 0 74507 0 49 46826 27533688 7 46826 3933384 34606164
2044 3.0 94173 3390228 0 80468 0 49 50104 29461152 7 50104 4208736 37060116
2045 3.0 101707 3661452 0 86905 0 49 53611 31523268 7 53611 4503324 39688044
2046 3.0 109844 3954384 0 93857 0 49 57364 33730032 7 57364 4818576 42502992
2047 3.0 118632 4270752 0 101366 0 49 61379 36090852 7 61379 5155836 45517440
2048 3.0 128123 4612428 0 109475 0 49 65676 38617488 7 65676 5516784 48746700
2049 3.0 138373 4981428 0 118233 0 49 70273 41320524 7 70273 5902932 52204884
2050 3.0 149443 5379948 0 127692 0 49 75192 44212896 7 75192 6316128 55908972
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.222
Shimla Jal Prabandhan Nigam Limited M and R
Sr. No. SubworksNo of
Units
Superinte
ndent
Manager
(A.E.E.)
Supervisor
/Asstt.
Manager
(A.E.)
Assitant
Supervisor/
Junior
manager
Operators Fitters HelpersElectrician/
MechanicWatchman
1 Pump House 7.00 0 0 0 21 28 0 0 7
2 RWRM 0.00 0 0 0 0 0 0 0 0
3 WTP 0.00 0 0 0 0 0 0 0 0
4 PWRM 0.00 0 0 0 0 0 0 0 0
5 ESR/GSR 0.00 0 0 0 0 0 0 0 0
6 Gravity Main 0.00 0 0 0 0 0 0 0 0
7 D/System 0.00 0 0 0 0 0 0 0 0
Automation 1 0 3
0 3 0 21 28 0 0 7
Staff Pattern
Total
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.223
Shimla Jal Prabandhan Nigam Limited M and R
Annual M &
R Charges
Annual
Depreciation
(3x8) (5x7)
1 2 3 4 5 6 7 8 9 10
For Proposed Components
1
Providing and Laying of Pipes, Specials,
Valves, Meters for Pumping Mains (GI
Pipes (Heavy) 100 mm to 150 mm -
0.644 Km and MSERW Fe 410 Pipes
56600000 58298000 52468200 50 0.0076 0.0025 141500 398758
2
Civil Works for Pumping Mains (GI Pipes
(Heavy) 100 mm to 150 mm - 0.644 Km
and MSERW Fe 410 Pipes 206.5 mm to
585 mm - 3.524 Km )
12500000 12875000 11587500 50 0.0076 0.0025 31250 88065
3 Pumping Machinery 51000000 52530000 47277000 20 0.0354 0.0250 1275000 1673606
4Construction of Pump House and staff
quarter58000000 59740000 53766000 67 0.0039 0.50% 290000 209687
5Acquisition of Land for Pump House &
Staff Quarter22500000 23175000 20857500 0 0
6 Plantation 2000000 2060000 1854000 0 0
7Express feeder, Substation and
Transformer69500000 71585000 64426500 20 0.0354 0.0250 1737500 2280698
8 SCADA (Cloud Based) System 2300000 2369000 2132100 20 0.0354 0.0250 57500 75476
9Operation and Maintenance of the
Pumping Mains for 15 years274200000 282426000 254183400 0 0
548600000 565058000 3532750 4726291
Hydraulic Design & Network modelling for Shimla Water Supply
World Bank Program
Client : Shimla Jal Prabandhan Nigam Limited
Total Rs.
STATMENT SHOWING ANNUAL M & R CHARGES
Sr.
No.Sub Work Net cost Gross cost
90% of
Gross Cost
Life in
Years
Depreciation
Factor
% of M &
R
Yash Innovative solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.224
TRANSMISSION MAINS
ESTIMATE
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Cost (in Rs. Lakh)
1
Providing and Laying of Pipes, Specials, Valves, Meters for
Transmission lines (GI Pipes (Heavy) 100 mm to 150 mm -
12.203 Km and MSERW Fe 410 Pipes 260.4 mm to 585 mm -
20.313 Km )
3692.00
2
Civil Works for Transmission lines (GI Pipes (Heavy) 100 mm
to 150 mm - 12.203 Km and MSERW Fe 410 Pipes 260.4
mm to 585 mm - 20.313 Km )
925.00
3 BPT (11 nos ) and Tanks (4 nos) 339.00
4 Acquisition of Land for various Reservoirs 384.00
5 Plantation 20.00
6 Staff Quarter at 11 BPT and 4 Tanks 458.00
7 SCADA (Cloud Based) System 42.00
8Operation and Maintenance of the Transmisson lines for 15
years1138.00
6998.00
210.00
7208.00Total Gross Cost
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Total Net Cost
Add 3% for Contingencies
Recapitulation Sheet for Transmission Mains
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.225
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Providing and Laying in trenches Galvanised mild steel pipe of following description
conforming to I.S 1239/2000 Heavy class, jointing all fitting , bends, Tees, Collars,
Tappers etc.including hydraullic testing of pipes as per direction of Engineer in
charge etc all complete
Galvanized Iron Pipes (Heavy class)
100 mm 1602.00 Rmt 1402.08 2246128.00
As per Rate Analysis -2
150 mm 10601.00 Rmt 2079.89 22048942.00
As per Rate Analysis -3
2 Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS:
3589-2001,steel grade Fe 410 with wall thickness , weight per meter, flanges as
described in analysis
260.4 mm dia 6.3 mm thk 5220.00 RMT 4618.47 24108413.00
As per Rate Analysis -5
309.7 mm dia 7.1 mm thk 1589.00 RMT 5977.04 9497517.00
As per Rate Analysis -6
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Providing and Laying of Pipes, Specials, Valves, Meters for Transmission lines (GI Pipes (Heavy) 100 mm to 150 mm - 12.203 Km and MSERW
Fe 410 Pipes 260.4 mm to 585 mm - 20.313 Km )
Abstract
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.226
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
339.6 mm dia 8 mm thk 5394.00 RMT 7281.60 39276950.00
As per Rate Analysis -7
388.8 mm dia 8.8 mm thk 3293.00 RMT 9015.51 29688074.00
As per Rate Analysis -8
437 mm dia 10 mm thk 506.00 RMT 11308.37 5722035.00
As per Rate Analysis -8
486 mm dia 11 mm thk 1161.00 RMT 13497.63 15670748.00
As per Rate Analysis -8
585 mm dia 15 mm thk 3067.00 RMT 18109.88 55543002.00
As per Rate Analysis -8
585 mm dia 15 mm thk 83.00 RMT 21256.82 1764316.00
As per Rate Analysis -8
3 Providing, Suppying, fixing Specials such as Tee, Bend, Reducer, Tailpiece, etc.
GI Specials 20% Job 24295070 4859014.00
MS Specials 20% Job 181271055 36254211.00
4
Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic
controller, communication, data logger, standby battery. With inbuilt communication
the controller can send the data directly to SCADA system. No RTU, Communication
moden, external battery is required. for Flow Control Valves
As per rate anlysis- 32
80 2.00 No. 209734.73 419469.00
100 7.00 No. 214053.18 1498372.00
150 29.00 No. 259659.71 7530132.00
200 14.00 No. 361152.92 5056141.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.227
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
250 2.00 No. 464510.07 929020.00
300 8.00 No. 514163.76 4113310.00
350 0.00 No. 659106.23 0.00
400 3.00 No. 889566.13 2668698.00
450 4.00 No. 953253.80 3813015.00
500 2.00 No. 1320830.52 2641661.00
600 1.00 No. 1493460.63 1493461.00
5
Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic
controller, communication, data logger, standby battery. With inbuilt communication
the controller can send the data directly to SCADA system. No RTU, Communication
moden, external battery is required. for Pressure Reducing Valves
As per rate anlysis- 32
80 2.00 No. 209734.73 419469.00
100 12.00 No. 214053.18 2568638.00
150 26.00 No. 259659.71 6751152.00
200 16.00 No. 361152.92 5778447.00
250 2.00 No. 464510.07 929020.00
300 13.00 No. 514163.76 6684129.00
350 0.00 No. 659106.23 0.00
400 3.00 No. 889566.13 2668698.00
450 4.00 No. 953253.80 3813015.00
500 2.00 No. 1320830.52 2641661.00
600 1.00 No. 1493460.63 1493461.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.228
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
6 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated),
Glandless, Sluice Valve of Non Rising spindle type. The Valve will be WRAS
approved. Valve will be fully protected from corrosion by electro-statically applying
epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland sealing &
pocket less body passage for unobstructed flow and debris free bottom. Body,
Bonnet, Gland will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall
not be supplied. Spindle shall be of SS : 420/304. The gland ('O' Ring) section will be
of Ductile Iron, Tamper resistant and will be separate unit from bonnet housing.
Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be housed
separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The
valve shall have Dust/Ingression resistant washer at spindle top. The spindle, spindle
nut, O rings shall be interchangeable design. The flanges shall be drilled as per IS:
1538 & the face to face shall confirm to IS: 14846. The Valve will be suitable for PN
1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with
EPDM. for Isolation Valve
As per rate anlysis- 33
80 2.00 No. 38346.81 76694.00
100 7.00 No. 42300.52 296104.00
150 28.00 No. 51688.96 1447291.00
200 21.00 No. 81696.12 1715619.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.229
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
250 4.00 No. 98157.36 392629.00
300 17.00 No. 128438.40 2183453.00
350 0.00 No. 51920.00 0.00
400 6.00 No. 279070.00 1674420.00
450 10.00 No. 328993.68 3289937.00
500 6.00 No. 489246.05 2935476.00
600 3.00 No. 683946.05 2051838.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.230
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
7 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated),
Glandless, Sluice Valve of Non Rising spindle type. The Valve will be WRAS
approved. Valve will be fully protected from corrosion by electro-statically applying
epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland sealing &
pocket less body passage for unobstructed flow and debris free bottom. Body,
Bonnet, Gland will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall
not be supplied. Spindle shall be of SS : 420/304. The gland ('O' Ring) section will be
of Ductile Iron, Tamper resistant and will be separate unit from bonnet housing.
Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be housed
separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The
valve shall have Dust/Ingression resistant washer at spindle top. The spindle, spindle
nut, O rings shall be interchangeable design. The flanges shall be drilled as per IS:
1538 & the face to face shall confirm to IS: 14846. The Valve will be suitable for PN
1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with
EPDM. for Scour Valve
As per rate anlysis- 33
80 2.00 No. 38346.81 76694.00
100 4.00 No. 42300.52 169202.00
150 27.00 No. 51688.96 1395602.00
200 14.00 No. 81696.12 1143746.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.231
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
250 4.00 No. 98157.36 392629.00
300 15.00 No. 128438.40 1926576.00
350 0.00 No. 51920.00 0.00
400 1.00 No. 279070.00 279070.00
450 12.00 No. 328993.68 3947924.00
500 3.00 No. 489246.05 1467738.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.232
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
8
Manufacturing, Testing and Supplying Ductile Iron, Tamper Proof, Single chamber,
High Performance, Umbrella Sealing Arc design, Full port (Equal Size inlet &
outlets), Kinetic Air Release valve, for High Discharge, Venting, and Anti Vacuum
Function. The Inlet & Outlet parts of Air Valves should be equal to or larger than the
area of the nominal valve size to provide full flow area through the valve. The Valve
will be supplies with DI Resilient Seated Isolating Sluice Valve of PN 1.6 Rating. The
Valve shall be WRAS Approved. Body & top Cover will be in Ductile Iron Grade GGG-
50 or SGI 500/7. Lower grade shall not be supplied. The Ball, Ball Cage and
Umbrella sealing arc will be in SS: 304. The Valve will be suitable for PN 1.6
Pressure Ratings. All the top cover fasteners shall be of L & Key type with weather
proof PV cap, moisture & ingression resistant. The Sealing Arc shall be guided at top
and shall be capable of sealing at 0.2 kg/cm2. Valve will be fully protected from
corrosion by electro-statically applying epoxy coating of minimum 250 microns. The
flanges shall be drilled as per IS: 1538. The Cage, Ball, Arc, Gaskets, all will be
interchangeable.
AIR VALVE
Body, Bonnet - Ductile Iron DIN:1693 Gr. GGG - 50.
Float, Guide Barrel - Stainless Steel - ASTM A 276 Type - 304
Seat - Nitrile Rubber
Sealing Arc, Bolt, Small Nozzle - Stainless Steel - ASTM A 276 Type - 304
O-Ring - Rubber NBR/EPDM
Nozzle, Buffer - Rubber EPDM
ISOLATING SLUICE VALVE
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon SteelAs per rate anlysis- 34
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.233
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
25 (Rates not avialable Hence rates of 50 mm are taken, Valve shall also be of 50
mm)41.00 No.
37630.321542843.00
50 51.00 No. 37630.32 1919146.00
80 10.00 No. 58814.98 588150.00
100 14.00 No. 78495.25 1098934.00
150 1.00 No. 99115.28 99115.00
9
Supply, install and commission Electromagnetic Flow Meter (EMF) As Per ISO 4064,
for Raw/Pure water with accuracy +/-0.5% of measured value & protection as per
given specifications for size 100 mm-1000mm including sensor, transmitter surge
arrestor, cable suitable size for 25 mtrs built in GSM ( with Simcard and its
charges,valid for 36 months) including the pipe cutting, leveling and installation of
flow meter in the pipelines with necessary tool tackles, cranes including 36 months
guarantee etc complete, as may be required at site & based on technical
specifications
As per rate anlysis- 36
80 (Rates not avialable Hence rates of 100 mm are taken, Valve shall also be of 100
mm)2.00 No. 127257.22 254514.00
100 7.00 No. 127257.22 890801.00
150 23.00 No. 137188.22 3155329.00
200 22.00 No. 162429.12 3573441.00
250 8.00 No. 179509.51 1436076.00
300 17.00 No. 205886.16 3500065.00
400 9.00 No. 323360.36 2910243.00
450 6.00 No. 346428.41 2078570.00
500 4.00 No. 403010.83 1612043.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.234
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
10
Designing, Supplying, Installing, commissioning & testing of pressure transmitter CE
markd with following technical parameters at Raw Water Pump House and
Interfacing with PLC panel including Mounting arrangement.
Output 4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.1 % of full scale or better
Enclosure- IP 67
162.00 No. 43679.00 7075998.00
As per rate anlysis- 35
Total Net Cost 369188229
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.235
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Providing and Laying in trenches Galvanised mild steel pipe of following description conforming to I.S
1239/2000 Heavy class, jointing all fitting , bends, Tees, Collars, Tappers etc.including hydraullic testing
of pipes as per direction of Engineer in charge etc all complete
Galvanized Iron Pipes (Heavy class)
100 mm 1602 1602.00 Rmt
150 mm 10601 10601.00 Rmt
Providing & laying in trenches MS ERW Pipelines of given dia conforming to IS: 3589-2001,steel grade
Fe 410 with wall thickness , weight per meter, flanges as described in analysis
260.4 mm dia 6.3 mm thk 5220 5220.00 Rmt
309.7 mm dia 7.1 mm thk 1589 1589.00 Rmt
339.6 mm dia 8 mm thk 5394 5394.00 Rmt
388.8 mm dia 8.8 mm thk 3293 3293.00 Rmt
437 mm dia 10 mm thk 506 506.00 Rmt
486 mm dia 11 mm thk 1161 1161.00 Rmt
585 mm dia 12.5 mm thk 3067 3067.00 Rmt
585 mm dia 15 mm thk 83 83.00 Rmt
3 Providing, Suppying, fixing Specials such as Tee, Bend, Reducer, Tailpiece, etc.
GI Specials 20% Job
MS Specials 20% Job
4 Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller,
communication, data logger, standby battery. With inbuilt communication the controller can send the data
directly to SCADA system. No RTU, Communication moden, external battery is required. for Flow
Control Valves
80 2 2.00 No.
100 7 7.00 No.
150 29 29.00 No.
200 14 14.00 No.
250 2 2.00 No.
2
Sr.
No.Description
MeasurementsQty. Unit
1
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Providing and Laying of Pipes, Specials, Valves, Meters for Transmission lines (GI Pipes (Heavy) 100 mm to 150 mm - 12.203 Km and MSERW Fe 410 Pipes 260.4 mm
to 585 mm - 20.313 Km )
Measurement Sheet
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.236
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Sr.
No.Description
MeasurementsQty. Unit
300 8 8.00 No.
350 0 0.00 No.
400 3 3.00 No.
450 4 4.00 No.
500 2 2.00 No.
600 1 1.00 No.
5 Providing, Suppying, fixing Electronically controlled valves with inbuilt hydraulic controller,
communication, data logger, standby battery. With inbuilt communication the controller can send the data
directly to SCADA system. No RTU, Communication moden, external battery is required. for Pressure
Reducing Valves
80 2 2.00 No.
100 12 12.00 No.
150 26 26.00 No.
200 16 16.00 No.
250 2 2.00 No.
300 13 13.00 No.
350 0 0.00 No.
400 3 3.00 No.
450 4 4.00 No.
500 2 2.00 No.
600 1 1.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.237
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Sr.
No.Description
MeasurementsQty. Unit
6 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of
Non Rising spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion
by electro-statically applying epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland
sealing & pocket less body passage for unobstructed flow and debris free bottom. Body, Bonnet, Gland
will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall not be supplied. Spindle shall be of
SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper resistant and will be separate
unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be
housed separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall
have Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be
interchangeable design. The flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS:
14846. The Valve will be suitable for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Isolation
Valve
80 2 2.00 No.
100 7 7.00 No.
150 28 28.00 No.
200 21 21.00 No.
250 4 4.00 No.
300 17 17.00 No.
350 0 0.00 No.
400 6 6.00 No.
450 10 10.00 No.
500 6 6.00 No.
600 3 3.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.238
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Sr.
No.Description
MeasurementsQty. Unit
7 Providing, fixing, testing, commissioning Ductile Iron, Resilient (Soft Seated), Glandless, Sluice Valve of
Non Rising spindle type. The Valve will be WRAS approved. Valve will be fully protected from corrosion
by electro-statically applying epoxy coating of minimum 250 microns. The Valve will have 'O' ring, gland
sealing & pocket less body passage for unobstructed flow and debris free bottom. Body, Bonnet, Gland
will be in Ductile Iron grade GGG50 / SGI 500-7, Lower grade shall not be supplied. Spindle shall be of
SS : 420/304. The gland ('O' Ring) section will be of Ductile Iron, Tamper resistant and will be separate
unit from bonnet housing. Brass/GM/Bronze Glands shall not be accepted. The spindle nut will be
housed separately in Wedge Groove and will not be encapsulated with EPDM Wedge. The valve shall
have Dust/Ingression resistant washer at spindle top. The spindle, spindle nut, O rings shall be
interchangeable design. The flanges shall be drilled as per IS: 1538 & the face to face shall confirm to IS:
14846. The Valve will be suitable for PN 1.6 Pressure Ratings.
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM. for Scour
Valve
80 2 2.00 No.
100 4 4.00 No.
150 27 27.00 No.
200 14 14.00 No.
250 4 4.00 No.
300 15 15.00 No.
350 0 0.00 No.
400 1 1.00 No.
450 12 12.00 No.
500 3 3.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.239
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Sr.
No.Description
MeasurementsQty. Unit
8 Manufacturing, Testing and Supplying Ductile Iron, Tamper Proof, Single chamber, High Performance,
Umbrella Sealing Arc design, Full port (Equal Size inlet & outlets), Kinetic Air Release valve, for High
Discharge, Venting, and Anti Vacuum Function. The Inlet & Outlet parts of Air Valves should be equal to
or larger than the area of the nominal valve size to provide full flow area through the valve. The Valve will
be supplies with DI Resilient Seated Isolating Sluice Valve of PN 1.6 Rating. The Valve shall be WRAS
Approved. Body & top Cover will be in Ductile Iron Grade GGG-50 or SGI 500/7. Lower grade shall not
be supplied. The Ball, Ball Cage and Umbrella sealing arc will be in SS: 304. The Valve will be suitable
for PN 1.6 Pressure Ratings. All the top cover fasteners shall be of L & Key type with weather proof PV
cap, moisture & ingression resistant. The Sealing Arc shall be guided at top and shall be capable of
sealing at 0.2 kg/cm2. Valve will be fully protected from corrosion by electro-statically applying epoxy
coating of minimum 250 microns. The flanges shall be drilled as per IS: 1538. The Cage, Ball, Arc,
Gaskets, all will be interchangeable.
AIR VALVE
Body, Bonnet - Ductile Iron DIN:1693 Gr. GGG - 50.
Float, Guide Barrel - Stainless Steel - ASTM A 276 Type - 304
Seat - Nitrile Rubber
Sealing Arc, Bolt, Small Nozzle - Stainless Steel - ASTM A 276 Type - 304
O-Ring - Rubber NBR/EPDM
Nozzle, Buffer - Rubber EPDM
ISOLATING SLUICE VALVE
Body, Bonnet, Gland - Ductile Iron DIN:1693 Gr. GGG - 50.
Wedge Nut - Brass BS:2874 Gr. CZ122
Stem - Stainless Steel AISI : 420/304
Gasket - Rubber EPDM
O-Ring - Rubber NBR
Dust Wiper - Rubber NBR
Hand Wheel - Carbon Steel
Hex Bolt, Washer, In Hex Bolt - Carbon Steel (Galvanized)
Wedge - Ductile Iron + Vulcanized Rubber DIN:1693 Gr. GGG - 50 Vulcanized with EPDM.
25 (Rates not avialable Hence rates of 50 mm are taken, Valve shall also be of 50 mm) 41 41.00 No.
50 51 51.00 No.
80 10 10.00 No.
100 14 14.00 No.
150 1 1.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.240
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Sr.
No.Description
MeasurementsQty. Unit
9 Supply, install and commission Electromagnetic Flow Meter (EMF) As Per ISO 4064, for Raw/Pure water
with accuracy +/-0.5% of measured value & protection as per given specifications for size 100 mm-
1000mm including sensor, transmitter surge arrestor, cable suitable size for 25 mtrs built in GSM ( with
Simcard and its charges,valid for 36 months) including the pipe cutting, leveling and installation of flow
meter in the pipelines with necessary tool tackles, cranes including 36 months guarantee etc complete,
as may be required at site & based on technical specifications
80 (Rates not avialable Hence rates of 100 mm are taken, Valve shall also be of 100 mm) 2 2.00 No.
100 7 7.00 No.
150 23 23.00 No.
200 22 22.00 No.
250 8 8.00 No.
300 17 17.00 No.
400 9 9.00 No.
450 6 6.00 No.
500 4 4.00 No.
10
Designing, Supplying, Installing, commissioning & testing of pressure transmitter CE markd with following
technical parameters at Raw Water Pump House and Interfacing with PLC panel including Mounting
arrangement.
Output 4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.1 % of full scale or better
Enclosure- IP 67
162.00 162.00 No.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.241
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m
stacking the soil not more than 3 meters clear from the edge of the
excavation and then returning the stacked soil in 15cm layers, when
required into the plinths sides of foundations etc., consolidating each
deposited layer by ramming and watering and then disposing of all
surplus excavated earth as directed within a lead of 20 meters
23636.01 Cum 546.74 12922794.00
As per Rate Analysis -9
Constructing chambers with C.I surface box 100mm top dia &
180mm deep (inside) with chained lid & RCC Walls and slab 1:1.5:3
(M20), 230mm thick and 100mm thick PCC 1:2:4 (M15) finished with
a floating coat of neat cement including curing complete
a) 600mmx600mmx750mm inside size with 200 mm thick RCC Wall 297.00 No. 18681.03 5548266.00
As per Rate Analysis -11
b) 900mmx900mmx750mm inside size with 200 mm thick RCC Wall 107.00 No. 27116.61 2901477.00
As per Rate Analysis -12
c) 1200mmx1200mmx750mm inside size with 200 mm thick RCC
Wall 70.00 No. 36851.71 2579620.00
As per Rate Analysis -13
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Civil Works for Transmission lines (GI Pipes (Heavy) 100 mm to 150 mm - 12.203 Km and MSERW Fe 410 Pipes 260.4 mm to
585 mm - 20.313 Km )
Abstract
2
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.242
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
d) 1500mmx1500mmx750mm inside size with 200 mm thick RCC
Wall 80.00 No. 47886.35 3830908.00
As per Rate Analysis -14
3Providing and constructing Anchor blocks/Thrust blocks for the
pipeline (Considering 30 blocks per km)975.00 No. 27075.12 26398238.00
As per Rate Analysis -15
4 Road Restoration 26012.80 Sqm 1400.00 36417920.00
As per Rate Analysis -16
5 Utility Shifting For pipe laying of given length in Km 32.52 Km 57134.40 1857782.00
As per Rate Analysis -17
Total Net Cost 92457005.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.243
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
1
Excavation in foundations, trenches etc., in earth work, lift upto
1.5m stacking the soil not more than 3 meters clear from the
edge of the excavation and then returning the stacked soil in
15cm layers, when required into the plinths sides of
foundations etc., consolidating each deposited layer by
ramming and watering and then disposing of all surplus
excavated earth as directed within a lead of 20 meters
For Galvanized Iron Pipes (Heavy class)
100 mm 1602 0.70 0.60 672.84 Cum
150 mm 10601 0.75 0.60 4770.45 Cum
For MSERW Pipes
260.4 mm dia 6.3 mm thk 5220 0.85 0.60 2662.20 Cum
309.7 mm dia 7.1 mm thk 1589 0.90 0.75 1072.58 Cum
339.6 mm dia 8 mm thk 5394 0.95 0.90 4611.87 Cum
388.8 mm dia 8.8 mm thk 3293 1.00 1.00 3293.00 Cum
437 mm dia 10 mm thk 506 1.10 1.10 612.26 Cum
486 mm dia 11 mm thk 1161 1.10 1.10 1404.81 Cum
585 mm dia 12.5 mm thk 3067 1.20 1.20 4416.48 Cum
585 mm dia 15 mm thk 83 1.20 1.20 119.52 Cum
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Civil Works for Transmission lines (GI Pipes (Heavy) 100 mm to 150 mm - 12.203 Km and MSERW Fe 410 Pipes 260.4 mm to
585 mm - 20.313 Km )
Measurement Sheet
Sr.
No.Description
MeasurementsQty. Unit
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.244
Shimla Jal Prabandhan Nigam Limited Cost Estimate
No. L B D
Sr.
No.Description
MeasurementsQty. Unit
2
Constructing chambers with C.I surface box 100mm top dia &
180mm deep (inside) with chained lid & RCC Walls and slab
1:1.5:3 (M20), 230mm thick and 100mm thick PCC 1:2:4 (M15)
finished with a floating coat of neat cement including curing
complete
a) 600mmx600mmx750mm inside size with 200 mm thick RCC
Wall 297 297.00 No.
b) 900mmx900mmx750mm inside size with 200 mm thick RCC
Wall 107 107.00 No.
c) 1200mmx1200mmx750mm inside size with 200 mm thick
RCC Wall 70 70.00 No.
d) 1500mmx1500mmx750mm inside size with 200 mm thick
RCC Wall 80 80.00 No.
3 Providing and constructing Anchor blocks/Thrust blocks for the
pipeline (Considering 30 blocks per km)975 975.00 No.
4 Road Restoration 1 26012.8 1 26012.80 Sqm
5 Utility Shifting For pipe laying of given length in Km 32.516 32.516 Km
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.245
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Designing, providing, constructing, testing and
commissioning of reservoirs of required capacity
including excavation, foundation, RCC works,
reinforcement, all type of acceessories, provding and
erecting all pipes and valves alongwith required specials ,
hydraulic testing , epoxy painting externally and
foodgrade epoxy painting internally, leveliing the plot,
backfilling, constrcution of compound wall in RCC framed
structure and Brickwork, plaster, painting, providing
erecting gate of required size, including all leads and lifts
at various places in Shimla as directed by Engineer-In-
Charge
BPT
1 667 Cum 10000.00 6670000.00
2 667 Cum 10000.00 6670000.00
3 430 Cum 10000.00 4300000.00
4 100 Cum 10000.00 1000000.00
5 325 Cum 10000.00 3250000.00
6 74 Cum 10000.00 740000.00
7 88 Cum 10000.00 880000.00
8 102 Cum 10000.00 1020000.00
9 102 Cum 10000.00 1020000.00
10 497 Cum 10000.00 4970000.00
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
BPT (11 nos ) and Tanks (4 nos)
Abstract
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.246
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
11 49 Cum 10000.00 490000.00
Tanks
1 17 Cum 10000.00 170000.00
2 4 Cum 10000.00 40000.00
3 192 Cum 10000.00 1920000.00
4 71 Cum 10000.00 710000.00
Total Net Cost 33850000.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.247
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1 Acquisition of land for Varoius Reservoirs in Shimla
BPT
1 441
2 441
3 324
4 144
6 256
7 144
8 144
9 144
10 400
11 144
Tanks
1 144
2 144
3 225
4 144
Total area 3239 Sqm 11850.00 38382150.00
Net Amount 38382150.00
Hydraulic Design & Network Modelling for Shimla Water Supply
Acquisition of Land for various Reservoirs
ABSTRACT OF COST
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.248
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1 Plantation in forest land/ cost of trees etc.
L.SLS 2000000.00
Net Amount 2000000.00
Hydraulic Design & Network Modelling for Shimla Water Supply
Plantation
ABSTRACT OF COST
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.249
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty Rate Unit Amount
1 Construction of staff quarters Type-I,II & III. At New Reservoir 100 sqm
x 15 reservoirs
1500 30545 Per Sqm. 45817500.00
As per PWD, Himachal Pradesh rates for plinth area for buildings of
area more than 500 sqm is 24436 in 2014 and increased by 25% for
5years.
45817500.00
Hydraulic Design & Network Modelling for Shimla Water Supply
Staff Quarter at 11 BPT and 4 Tanks
ABSTRACT OF COST
Total Rs. In Lac.
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.250
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1
Supply, Installation, Commissioning, Testing, Terminating &
Interfacing Software Design to PLC and commissioning of
SCADA software with required hard tags plus 25% extra and
with unlimited soft Tags & life time licence Development version
1.00 Nos 450000 450000
2Developing/programming charges to install the software as per
logic defined by the dept. 1.00 Nos 250000 250000
3
Supply, Installation, Testing, Terminating & Interfacing
Centralised Historian Server grade Historian PC with Window 7
or latest window operating system & Historian software
development cost etc. complete1.00 Nos 85000 85000
4
Supply, Installation, Testing, Terminating & Interfacing
Secondary Computer Station Secondary computer station etc.1.00 Nos 65000 65000
5
Supply, Installation, Testing, Intgeration & Commissioning of
46" LCD monitor at Conf. Room for display of total water
system (Online) 1.00 Nos 98000 98000
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
SCADA (Cloud Based) System
Abstract
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.251
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
6
Supplying and erecting window model mounted type room Air-
Conditioner 3 star 230/250 V 50 cycles single phase A.C.supply
2 TRcapacity complete with gas R410A/R32 at position in
provided recess with wooden frame as per specification No.AP-
AC/WAC 1.00 Nos 45000 45000
7Power Supply From Electrcity Department at each location of
PRV and FCV167.00 Job 10000.00 1670000.00
8 Power Cable from Supply point to PRV/FCV and allied works 167.00 Job 5000.00 835000.00
9
Designing, Supplying, Installing, commissioning & testing of
Ultrasonic level transmitter CE marked with following technical
parameters and Interfacing with PLC panel including Mounting
accessories.
14 Jobs 53125.842 743762.00
Total Net Cost 4241762.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.252
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
1Providing staff for the operation and Maintenance of distribution
system
1 Fitter for 10 to 15 km of Dist System as per CPHEEO manual
2 Helper for 10 to 15 km of Dist System as per CPHEEO manual
1 Watchman for each ESR as per CPHEEO manual
Total length of network in three zone is 320 Km
For Years 2021 to 2035
2021 1.00 Job 2987328.00 2987328.00
2022 1.00 Job 3202236.00 3202236.00
2023 1.00 Job 3432708.00 3432708.00
2024 1.00 Job 3679716.00 3679716.00
2025 1.00 Job 3944460.00 3944460.00
2026 1.00 Job 4228476.00 4228476.00
2027 1.00 Job 4533000.00 4533000.00
2028 1.00 Job 4859376.00 4859376.00
2029 1.00 Job 5209404.00 5209404.00
2030 1.00 Job 5584692.00 5584692.00
2031 1.00 Job 5987112.00 5987112.00
2032 1.00 Job 6418572.00 6418572.00
Hydraulic Design & Network Modelling for Shimla Water Supply
Client : Shimla Jal Prabandhan Nigam Limited
Operation and Maintenance of the Transmisson lines for 15 years
Abstract
World Bank Project
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.253
Shimla Jal Prabandhan Nigam Limited Cost Estimate
Sr. No. Description Qty. Unit Rate in Rs. Amount in Rs.
2033 1.00 Job 6881280.00 6881280.00
2034 1.00 Job 7377444.00 7377444.00
2035 1.00 Job 7909608.00 7909608.00
2Maintenance and repairs of transmission lines including all
material and labour required.
For Years 2021 to 2035
2021 1.00 Job 1740637.50 1740638.00
2022 1.00 Job 1827669.38 1827669.00
2023 1.00 Job 1919052.84 1919053.00
2024 1.00 Job 2015005.49 2015005.00
2025 1.00 Job 2115755.76 2115756.00
2026 1.00 Job 2221543.55 2221544.00
2027 1.00 Job 2332620.73 2332621.00
2028 1.00 Job 2449251.76 2449252.00
2029 1.00 Job 2571714.35 2571714.00
2030 1.00 Job 2700300.07 2700300.00
2031 1.00 Job 2835315.07 2835315.00
2032 1.00 Job 2977080.82 2977081.00
2033 1.00 Job 3125934.87 3125935.00
2034 1.00 Job 3282231.61 3282232.00
2035 1.00 Job 3446343.19 3446343.00
Total Net Cost 113795870.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.254
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Name of work :- Providing Water Supply for Shimla town.
Cement/Steel/G.I Pipe
Dhalli Store (IPH)
6 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Sand Deothi Solan
60 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Aggrigate below 40 mm size
115 K.M 0.5 K.M.
Punchakula By Mech Transport By Head load Site of work
Aggrigate above 40 mm size
115 K.M 0.5 K.M.
By Mech Transport By Head load Site of work
Steel/wood/Frame/Shuttering and Shutter
6 K.M 0.5 K.M.
Shimla By Mech Transport By Head load Site of work
Brick/MSERW Pipe/GI
130 K.M 0 K.M.
Chandigarh By Mech Transport By Head load Site of work
Flanges
6 K.M. 0.5 K.M.
Local By Mech Transport By Head load Site of work
Certified that lead is taken as per actual ,shortest and feasible as well as
economical route by all means.
Lead Statement
LEAD CHART
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.255
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1) Cement from IPH 2) STEEL:
LEAD : By Mech. 6 Km. LEAD : By Mech. 6 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.5 0.00 1 Km. 0 103.50 0.00
2 Km. 0 119.49 0.00 2 Km. 0 119.49 0.00
3 Km. 0 135.32 0.00 3 Km. 0 135.32 0.00
4 Km. 0 150.70 0.00 4 Km. 0 150.70 0.00
5 Km. 1 165.35 165.35 5 Km. 1 165.35 165.35
5- 10 Km. 1 13.56 13.56 5- 10 Km. 1 13.56 13.56
10-20 Km. 0 11.32 0.00 10-20 Km. 0 11.32 0.00
Beyond 20 Km. 0 9.51 0.00 Beyond 20 Km. 0 9.51 0.00
TOTAL : 178.91 TOTAL : 178.91
2 By Head load 2 By Head load
1st. 1 Km. 0 431.84 0.00 1st. 1 Km. 0 911.43 0.00
1st. 100 Mtr 1 68.60 68.60 1st. 100 Mtr 1 144.81 144.81
Bey:1 Km.Per 1/2Km. 0 215.92 0.00 Bey:1 Km.Per 1/2Km. 0 455.72 0.00
Bey:100 Mtr Per 50 Mtr 8 20.18 161.44 Bey:100 Mtr Per 50 Mtr 8 42.59 340.72
Total : 230.04 Total : 485.53
3) Sand: 4)
LEAD : By Mech. 60 Km. LEAD : By Mech. 115 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 155.25 0.00 1 Km. 0 155.25 0.00
2 Km. 0 179.24 0.00 2 Km. 0 179.24 0.00
3 Km. 0 202.98 0.00 3 Km. 0 202.98 0.00
4 Km. 0 226.05 0.00 4 Km. 0 226.05 0.00
5 Km. 1 248.03 248.03 5 Km. 1 248.03 248.03
5- 10 Km. 5 20.34 101.70 5- 10 Km. 5 20.34 101.70
10-20 Km. 10 16.98 169.80 10-20Km 10 16.98 169.80
Beyond 20 Km. 40 14.27 570.80 Beyond 20 Km. 95 14.27 1355.65
TOTAL : 1090.33 TOTAL : 1875.18
2 By Head load 2 By Head load
1st. 1 Km. 0 732.74 0.00 1st. 1 Km. 0 732.74 0.00
CARRIAGE OF MATERIALS
Stone aggregate
below 40mm.:
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.256
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1st. 100 Mtr 1 116.42 116.42 1st. 100 Mtr 1 116.42 116.42
Bey:1 Km.Per 1/2Km. 0 366.37 0.00 Bey:1 Km.Per 1/2Km. 0 366.37 0.00
Bey:100 Mtr Per 50 Mtr 8 34.24 273.92 Bey:100 Mtr Per 50 Mtr 8 34.24 273.92Total : 390.34 Total : 390.34
5) 6)
LEAD : By Mech. 115 Km. LEAD : By Mech. 6 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech.
1 Km. 0 168.02 0.00 1 Km. 0 155.25 0.00
2 Km. 0 193.98 0.00 2 Km. 0 179.24 0.00
3 Km. 0 219.67 0.00 3 Km. 0 202.98 0.00
4 Km. 0 244.64 0.00 4 Km. 0 226.05 0.00
5 Km. 1 268.43 268.43 5 Km. 1 248.03 248.03
5- 10 Km. 5 22.01 110.05 5- 10 Km. 1 20.34 20.34
10-20 Km. 10 18.38 183.80 10-20 Km. 0 16.98 0.00
Beyond 20 Km. 95 15.44 1466.80 Beyond 20 Km. 0 14.27 0.00
TOTAL : 2029.08 TOTAL : 268.37
2 By Head load 2 By Head load
1st. 1 Km. 0 792.22 0.00 1st. 1 Km. 0 585.93 0.00
1st. 100 Mtr 1 125.86 125.86 1st. 100 Mtr 1 93.09 93.09
Bey:1 Km.Per 1/2Km. 0 396.11 0.00 Bey:1 Km.Per 1/2Km. 0 292.97 0.00
Bey:100 Mtr Per 50 Mtr 8 37.02 296.16 Bey:100 Mtr Per 50 Mtr 8 27.38 219.04
Total : 422.02 Total : 312.13
7) 7.1)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.5 0.00 1 Km. 0 103.5 0.00
2 Km. 0 119.49 0.00 2 Km. 0 119.49 0.00
3 Km. 0 135.32 0.00 3 Km. 0 135.32 0.00
4 Km. 0 150.70 0.00 4 Km. 0 150.70 0.00
5 Km. 1 165.35 165.35 5 Km. 1 165.35 165.35
5- 10 Km. 5 13.56 67.80 5- 10 Km. 5 13.56 67.80
GI Pipe below 100mm
dia :
LEAD From
Chandigarh :LEAD From IPH Store :
Stone aggregate 40mm
and above:
Timber(Local wood
for shuttering)and
Shutter
GI Pipe below 100mm
dia :
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.257
Shimla Jal Prabandhan Nigam Limited Rate Analysis
10-20 Km. 10 11.32 113.20 10-20 Km. 10 11.32 113.20
Beyond 20 Km. 116 9.51 1103.16 Beyond 20 Km. 116 9.51 1103.16
TOTAL : 1449.51 TOTAL : 1449.51
2 By Head load 2 By Head load
1st. 1 Km. 0 535.00 0.00 1st. 1 Km. 0 535.00 0.00
1st. 100 Mtr 1 85.00 85.00 1st. 100 Mtr 1 85.00 85.00
Bey:1 Km.Per 1/2Km. 0 267.50 0.00 Bey:1 Km.Per 1/2Km. 0 267.50 0.00
Bey:100 Mtr Per 50 Mtr 8 25.00 200.00 Bey:100 Mtr Per 50 Mtr 8 25.00 200.00
Total : 285.00 Total : 285.00
8) 9)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 964.05 0.00 1 Km. 0 1247.59 0.00
2 Km. 0 1113.02 0.00 2 Km. 0 1440.37 0.00
3 Km. 0 1260.42 0.00 3 Km. 0 1631.13 0.00
4 Km. 0 1403.69 0.00 4 Km. 0 1816.54 0.00
5 Km. 1 1540.16 1540.16 5 Km. 1 1993.15 1993.15
5- 10 Km. 5 126.30 631.50 5- 10 Km. 5 163.45 817.25
10-20 Km. 10 105.46 1054.60 10-20 Km. 10 136.48 1364.80
Beyond 20 Km. 116 88.59 10276.44 Beyond 20 Km. 116 114.64 13298.24
TOTAL : 13502.70 TOTAL : 17473.44
2 By Head load 2 By Head load
1st. 1 Km. 0 5373.33 0.00 1st. 1 Km. 0 6724.09 0.00
1st. 100 Mtr 1 853.71 853.71 1st. 100 Mtr 1 1068.31 1068.31
Bey:1 Km.Per 1/2Km. 0 2686.67 0.00 Bey:1 Km.Per 1/2Km. 0 3362.05 0.00
Bey:100 Mtr Per 50 Mtr 8 251.09 2008.72 Bey:100 Mtr Per 50 Mtr 8 314.21 2513.68
Total : 2862.43 Total : 3581.99
10) 11)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
MSERW Pipe 400 mm
dia :
LEAD (From
Chandigarh to IPH and
IPH to Site) :
LEAD (From Chandigarh
to IPH and IPH to Site) :
MSERW Pipe 350 mm
dia :
MSERW Pipe 250 mm
dia :
MSERW Pipe 300 mm
dia :
LEAD (From Chandigarh
to IPH and IPH to Site) :
LEAD (From
Chandigarh to IPH and
IPH to Site) :
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.258
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 By Mech. 1 By Mech.
1 Km. 0 1767.42 0.00 1 Km. 0 2356.56 0.00
2 Km. 0 2040.53 0.00 2 Km. 0 2720.70 0.00
3 Km. 0 2310.77 0.00 3 Km. 0 3081.03 0.00
4 Km. 0 2573.43 0.00 4 Km. 0 3431.24 0.00
5 Km. 1 2823.63 2823.63 5 Km. 1 3764.85 3764.85
5- 10 Km. 5 231.56 1157.80 5- 10 Km. 5 308.74 1543.70
10-20 Km. 10 193.35 1933.50 10-20 Km. 10 257.80 2578.00
Beyond 20 Km. 116 162.41 18839.56 Beyond 20 Km. 116 216.55 25119.80
TOTAL : 24754.49 TOTAL : 33006.35
2 By Head load 2 By Head load
1st. 1 Km. 0 9613.31 0.00 1st. 1 Km. 0 11186.42 0.00
1st. 100 Mtr 1 1527.35 1527.35 1st. 100 Mtr 1 1777.28 1777.28
Bey:1 Km.Per 1/2Km. 0 4806.66 0.00 Bey:1 Km.Per 1/2Km. 0 5593.21 0.00
Bey:100 Mtr Per 50 Mtr 8 449.22 3593.76 Bey:100 Mtr Per 50 Mtr 8 522.73 4181.84
Total : 5121.11 Total : 5959.12
10) 11)
By Mech. 136 Km. By Mech. 136 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 3029.86 0.00 1 Km. 0 4241.80 0.00
2 Km. 0 3498.05 0.00 2 Km. 0 4897.27 0.00
3 Km. 0 3961.32 0.00 3 Km. 0 5545.85 0.00
4 Km. 0 4411.59 0.00 4 Km. 0 6176.23 0.00
5 Km. 1 4840.52 4840.52 5 Km. 1 6776.72 6776.72
5- 10 Km. 5 396.96 1984.80 5- 10 Km. 5 555.74 2778.70
10-20 Km. 10 331.46 3314.60 10-20 Km. 10 464.04 4640.40
Beyond 20 Km. 116 278.42 32296.72 Beyond 20 Km. 116 389.78 45214.48
TOTAL : 42436.64 TOTAL : 59410.30
2 By Head load 2 By Head load
1st. 1 Km. 0 14915.16 0.00 1st. 1 Km. 0 16406.73 0.00
1st. 100 Mtr 1 2369.70 2369.70 1st. 100 Mtr 1 2606.67 2606.67
Bey:1 Km.Per 1/2Km. 0 7457.58 0.00 Bey:1 Km.Per 1/2Km. 0 8203.37 0.00
Bey:100 Mtr Per 50 Mtr 8 696.97 5575.76 Bey:100 Mtr Per 50 Mtr 8 766.67 6133.36
MSERW Pipe 450 mm
dia :
MSERW Pipe 600 mm
dia :
LEAD (From Chandigarh
to IPH and IPH to Site) :
LEAD (From
Chandigarh to IPH and
IPH to Site) :
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.259
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Total : 7945.46 Total : 8740.03
12) Flange / Sluice Valve 13) Bricks: Per 1000.Nos.
By Mech. 136 LEAD : By Mech. 130 Km.
By Head : 0.5 By Head : 0 Km.
1 By Mech. 1 By Mech.
1 Km. 0 103.50 0.00 1 Km. 0 388.13 0.00
2 Km. 0 119.49 0.00 2 Km. 0 448.10 0.00
3 Km. 0 135.32 0.00 3 Km. 0 507.45 0.00
4 Km. 0 150.70 0.00 4 Km. 0 565.13 0.00
5 Km. 1 165.35 165.35 5 Km. 1 620.07 620.07
5- 10 Km. 5 13.56 67.80 5- 10 Km. 5 50.85 254.25
10-20 Km. 10 11.32 113.20 10-20 Km. 10 42.46 424.60
Beyond 20 Km. 116 9.51 1103.16 Beyond 20 Km. 110 35.67 3923.70
TOTAL : 346.35 TOTAL : 5222.62
2 By Head load 2 By Head load
1st. 1 Km. 0 911.43 0.00 1st. 1 Km. 0 1367.88 0.00
1st. 100 Mtr 1 144.81 144.81 1st. 100 Mtr 0 217.32 0.00
Bey:1 Km.Per 1/2Km. 0 455.72 0.00 Bey:1 Km.Per 1/2Km. 0 683.94 0.00
Bey:100 Mtr Per 50 Mtr 8 42.59 340.72 Bey:100 Mtr Per 50 Mtr 0 63.92 0.00
Total : 144.81 Total : 0.00
(Assumed as
locallyavailable) LEAD :
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.260
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr.
No.
RATE UNIT
1 AGGREGATE 40 MM 550.00 /CUM
2 AGGREGATE 20 MM 725.00 /CUM
3 AGGREGATE 10 MM 725.00 /CUM
4 CEMENT 5120.00 /MT
5 SAND 650.00 /CUM
6 FINE SAND (FILTER MEDIA) 650.00 /CUM
7 M.R. TOR STEEL 4500.00 /QTL.
8 DRILLING EQUIPEMENT 3600.00 /DAY
9 SAFETY COILS 30.00 /COIL
10 DETONATORS 300.00 /100 Nos.
11 SPECIAL GELATINE 75.00 KG
12 STONE 500.00 /CUM
13 THROUGH BOUND STONE 1000.00 /100
14 MS ANGLE/ MS STRAPS 5000.00 /QTL.
15 WELDING CHARGES 4.00 /CMT.
16 WELDING CHARGES WITH GENERATOR SET 5.00 /CMT.
17 MS BOLTS 22 mm 5975.00 /QTL.
18 MS FLAT 5000.00 /QTL.
19 BOULDER/HARD STONE/PLUM 450.00 /CUM
20 CAST IRON M/H 90.00 /KG
21 BRICKS (I st Class) 4500.00 /1000
22 BRICKS II nd
Class) 4000.00 /1000
23 WHITE CEMENT 21500.00 /MT
24 Bitumen/Mexphalt 80/100 34500.00 /MT
25 KEROSENE OIL 14.00 /LTS.
26 DISEIL 56.00 /LTS.
27 M.OIL 285.00 /LTS.
28 FUEL WOOD 5.00 /KG
29 HIRING CHARGES OF TRUCK ( M.R.) 2500.00 /DAY
30 HIRE CHARGES OF PUMP 500.00 /DAY
31 HESSIAN CLOTH 25.00 /SQMT.
32 22mm RIVETS 6975.00 / QTL.
33 LIME(UNSLAKED) 1000.00 / QTL.
34 M.S.PLATES 4500.00 / QTL.
35 R.S.JOISTS 5000.00 / QTL.
36 C.I.RUNGS 40.00 /KG
37 ENAMELLED PAINT(OTHER THAN WHITE) 200.00 / LTS.
38 KAIL WOOD (Ist CLASS) 44500.00 /CUM
39 KAIL WOOD (IInd CLASS) 33830.00 /CUM
40 CHIL WOOD (Ist CLASS) 18100.00 /CUM
41 CHIL WOOD (IInd CLASS) 15800.00 /CUM
42 DEODAR WOOD 45200.00 /CUM
43 SAW CHARGES OF SLEEPERS TO PLANKS 700.00 /CUM
44 SAW CHARGES OF SLEEPERS TO BATTENS 500.00 /CUM
45 WOODEN BALLIES OF KAIL 125.00 /RMT.
46 WIRE GAUGE 250.00 /SQMT.
47 CI VENT PIPE 1.80 Mtr.Long 750.00 /EACH
48 Barbed Wire 56.68 Per Kg. (RC)
49 Ready Mixed Paint (other than white) 150.00 /ltr
50 Ready Mixed Paint (Pink Primer) 200.00 /ltr
51 Ready Mixed Red Mixed Paint 150.00 /ltr
52 Sliding Door Bolt (250 x 16 mm) 95.00 Each
53 Sliding Door Bolt (200X16 mm) 65.00 Each
** BASIC RATE **Name of work:- Hydraulic Design & Network Modelling for Shimla Water Supply
DESCRIPTION OF ITEM
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.261
Shimla Jal Prabandhan Nigam Limited Rate Analysis
54 Tower Bolt (Barrel Type 250 x 10 mm 35.00 Each
55 Tower Bolt (Barrel Type 200 x 10 mm 30.00 Each
56 Tower Bolt (Barrel Type 100 x 10 mm 25.00 Each
57 Tower Bolt (Barrel Type 150 x 10 mm 20.00 Each
58 Dry DisTamper 65.00 Kg
59 Oil Bound DisTamper 125.00 /ltr
60 Handles 100 mm 20.00 Each
61 Handles 125 mm 30.00 Each
62 SFRC Man Hole Cover 1700.00 Each
63 Terrazo Tiles 900.00 /SQMT.
64 Pink Makrana Marble 20 mm thick 1200.00 /SQMT.
64 Glass Strips 10.00 /Mtr.
65 Mild Steel Screws 40 mm 40.00 /Cent
66 Mild Steel Screws 25 mm 30.00 /10 nos
67 Mild Steel Screws 20 mm 25.00 /10 nos
68 Cement Paint 250.00 /ltr
69 Wood Perservative(Oil TYpe) 180.00 /ltr
70 Glass 2 mm to 3 mm 375.00 /Mtr
71 Iron Hinges ( 100 x 30 x 19 mm ) 25.00 /Cent
73 Iron Hinges ( 50 x 30 x 15 mm ) 15.00 /Cent
74 Ceramic Tile (153 x 152 x 6 mm) 750.00 /Sqm
82 C.G.I.SHEET 0.63 mm THICK 8000.00 /MT
83 P.G.I. SHEET 6000.00 /MT
84 800.00 /Cent
85 MS Flange of all tables 64.00 /KG
86 70.00 /KG
87 73.00 /KG
88 1373.00 /Meter
89 1703.00 /Meter
90 2318.00 /Meter
91 2880.00 /Meter
92 0.00 /Meter
93 4350.00 /Meter
94 0.00 /Meter
95 6140.00 /Meter
96 100 MM 105.00 EACH
97 150 MM 124.00 EACH
98 200 MM 171.00 EACH
99 250MM 295.00 EACH
100 300 MM 390.00 EACH
101 350 MM 703.00 EACH
102 400 MM 798.00 EACH
103 450 MM 1121.00 EACH
104 500 MM 1350.00 EACH
105 Plastic Steps 166.00 EACH
(B)
Rate i/c P/H Basic Rate Unit
88 FITTER (G-I) 292.00 252.00 /DAY
89 FITTER (G-II) 292.00 252.00 /DAY
90 MASON(G-1) 292.00 252.00 /DAY
91 MASON(G-II) 292.00 252.00 /DAY
60 mm Thick Precast Interlocked Paver Blocks
API Pipes (IS/ISO:3183-2007) Gr, X
- 42 450 mm diaAPI Pipes (IS/ISO:3183-2007) Gr, X
- 42 , 600 mm diaDI PIPE 150 MM DIA Including frieght charges Upto Kalka
DI PIPE 200 MM DIA Including frieght charges Upto Kalka
DI PIPE 250 MM DIA Including frieght charges Upto Kalka
DI PIPE 300 MM DIA Including frieght charges Upto Kalka
DI PIPE 350 MM DIA Including frieght charges Upto Kalka
DI PIPE 400 MM DIA Including frieght charges Upto Kalka
DI PIPE 450 MM DIA Including frieght charges Upto Kalka
DI PIPE 500 MM DIA Including frieght charges Upto Kalka
Rubber Gasket EPDM
RATE OF LABOUR AS APPLICABLE IN DEPTT. Vide Govt. notification No.FIN - ( PR ) B ( 7) -
33/2010 dt. 07-04-2017
Designation
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.262
Shimla Jal Prabandhan Nigam Limited Rate Analysis
92 PAINTER(G-I) 292.00 252.00 /DAY
93 PAINTER(G-II) 265.00 225.00 /DAY
94 BLACK SMITH (G-I) 292.00 252.00 /DAY
95 BLACK SMITH (G-II) 292.00 252.00 /DAY
96 CARPENTER G-I 292.00 252.00 /DAY
97 CARPENTER G-II 292.00 252.00 /DAY
98 BELDAR 250.00 210.00 /DAY
99 BHISTI 250.00 210.00 /DAY
100 MATE 250.00 210.00 /DAY
101 STONE DRESSER 250.00 210.00 /DAY
102 BHANDHANI 250.00 210.00 /DAY
103 DRILLER 250.00 210.00 /DAY
104 STONE CHISLER 250.00 210.00 /DAY
105 WHITE WASHER 265.00 210.00 /DAY
106 PUMP OPERATOR 262.00 252.00 /DAY
107 BLASTER 250.00 210.00 /DAY
108 Electrician 371.00 300.00 /DAY
109 BELDAR SKILLED 292.00 252.00 /DAY
Certified that above rates of materials are the lowest one pervailing markets rates & rates of
labour have been taken as applicable in this Department as per latest notification as issued by the Govt.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.263
Shimla Jal Prabandhan Nigam Limited Rate Analysis
56.00 285.00 250.00 2500.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 12.00 5.65 17.30 5.77 323.12 0.22 62.70 1500.00 2500.00 4385.82 776.25
2 12.75 5.12 26.48 8.83 494.48 0.33 94.05 1500.00 2500.00 4588.53 896.20 119.95
3 13.12 4.69 34.14 11.38 637.28 0.43 122.55 1500.00 2500.00 4759.83 1014.89 118.69
4 13.50 4.34 40.72 13.57 759.92 0.51 145.35 1500.00 2500.00 4905.27 1130.25 115.36
5 13.88 4.06 46.60 15.53 869.68 0.58 165.30 1500.00 2500.00 5034.98 1240.14 109.89
6 14.25 3.82 51.84 17.28 967.68 0.65 185.25 1500.00 2500.00 5152.93 1348.93 108.79
7 14.63 3.62 56.68 18.89 1057.84 0.71 202.35 1500.00 2500.00 5260.19 1453.09 104.16
8 15.10 3.46 61.36 20.45 1145.20 0.77 219.45 1500.00 2500.00 5364.65 1550.48 97.39
9 15.38 3.31 65.58 21.86 1224.16 0.82 233.70 1500.00 2500.00 5457.86 1648.90 98.42
10 15.75 3.17 69.40 23.13 1295.28 0.87 247.95 1500.00 2500.00 5543.23 1748.65 99.75 101.70
11 16.13 3.06 73.32 24.44 1368.64 0.92 262.20 1500.00 2500.00 5630.84 1840.14 91.49
12 16.50 2.96 77.04 25.68 1438.08 0.96 273.60 1500.00 2500.00 5711.68 1929.62 89.48
13 16.88 2.87 80.62 26.87 1504.72 1.01 287.85 1500.00 2500.00 5792.57 2018.32 88.70
14 17.25 2.78 83.84 27.95 1565.20 1.05 299.25 1500.00 2500.00 5864.45 2109.51 91.19
15 17.63 2.71 87.30 29.10 1629.60 1.09 310.65 1500.00 2500.00 5940.25 2191.97 82.46
16 18.00 2.64 90.48 30.16 1688.96 1.13 322.05 1500.00 2500.00 6011.01 2276.90 84.93
17 18.38 2.58 93.72 31.24 1749.44 1.18 336.30 1500.00 2500.00 6085.74 2358.81 81.91
18 18.75 2.52 96.72 32.24 1805.44 1.21 344.85 1500.00 2500.00 6150.29 2440.59 81.78
19 19.13 2.47 99.86 33.29 1864.24 1.25 356.25 1500.00 2500.00 6220.49 2518.42 77.83
20 19.50 2.42 102.80 34.27 1919.12 1.29 367.65 1500.00 2500.00 6286.77 2597.84 79.42 84.92
21 19.88 2.38 105.96 35.32 1977.92 1.32 376.20 1500.00 2500.00 6354.12 2669.80 71.96
22 20.25 2.34 108.96 36.32 2033.92 1.36 387.60 1500.00 2500.00 6421.52 2744.24 74.44
23 20.63 2.30 111.80 37.27 2087.12 1.40 399.00 1500.00 2500.00 6486.12 2820.05 75.81
24 21.00 2.26 114.48 38.16 2136.96 1.43 407.55 1500.00 2500.00 6544.51 2895.80 75.75
25 21.38 2.23 117.50 39.17 2193.52 1.48 421.80 1500.00 2500.00 6615.32 2966.51 70.71
26 21.75 2.20 120.40 40.13 2247.28 1.51 430.35 1500.00 2500.00 6677.63 3035.29 68.78
27 22.13 2.17 123.18 41.06 2299.36 1.54 438.90 1500.00 2500.00 6738.26 3105.19 69.90
28 22.50 2.14 125.84 41.95 2349.20 1.57 447.45 1500.00 2500.00 6796.65 3176.00 70.81
29 22.88 2.11 128.38 42.79 2396.24 1.60 456.00 1500.00 2500.00 6852.24 3247.51 71.51
30 23.25 2.09 131.40 43.80 2452.80 1.64 467.40 1500.00 2500.00 6920.20 3311.10 63.59 71.33
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT Sl.No.
Lead
inK.M
.(L)
Average speed Km/hour(s) No.of Trips
No.
No.of Km.
done
2NL+6
Litre of
diesel
consumed
Litre of
Diesel @
per Ltr.
Litres of
M.Oil
consumed
Cost of
M.Oil @
per litre
Cost of 6
Beldar @
per day
Hire
Charges
of Truck
@ per day
Total
cost
Col.No6+
8+9+10
Cost per
trip
Increas
e in
Cost per
Km over
previou
s Km.
Average
cost per
additional
Km.after
five Km.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.264
Shimla Jal Prabandhan Nigam Limited Rate Analysis
776.25 896.20 1014.89 1130.25 1240.14 101.70 84.92
1 2 3 4 5 6 7 8 9 10 11 12
1 Lime, moorum , building rubish. 6 cu.m 6.00 1 cu.m 129.38 149.37 169.15 188.38 206.69 16.95 14.15
2 Earth work. 6 cu.m 4.80 1 cu.m 161.72 186.71 211.44 235.47 258.36 21.19 17.69
3 Manure or sludge 6 cu.m 5.52 1 cu.m 140.63 162.36 183.86 204.76 224.66 18.42 15.38
4 Excavated rock. 6 cu.m 3.00 1 cu.m 258.75 298.73 338.30 376.75 413.38 33.90 28.31
5 Sand,stone agg. below 40mm 5 cu.m 5.00 1 cu.m 155.25 179.24 202.98 226.05 248.03 20.34 16.98
6 Stone agg.40mm & above,build.
Stones.
5 cu.m 4.62 1 cu.m 168.02 193.98 219.67 244.64 268.43 22.01 18.38
7 Soling stone, stone block & stone
for filling crates
5 cu.m 4.25 1 cu.m 182.65 210.87 238.80 265.94 291.80 23.93 19.98
8 Bricks. 2000Nos. 2000.00 1000 Nos. 388.13 448.10 507.45 565.13 620.07 50.85 42.46
9 Bricks tiles. 3200Nos. 3200.00 1000 Nos. 242.58 280.06 317.15 353.20 387.54 31.78 26.54
10 Slates. 14450Nos. 14450.00 1000 Nos. 53.72 62.02 70.23 78.22 85.82 7.04 5.88
11 Terrazzo Tiles. 2500Nos. 2500.00 1000 Nos. 310.50 358.48 405.96 452.10 496.06 40.68 33.97
12 Cement G.I. CI. AC. CC pipes
below 100mm dia & other heavy
materials.
7.50 Tonne 7.50 1 Tonne 103.50 119.49 135.32 150.70 165.35 13.56 11.32
13 Steam Coal 5.5 Tonne 5.50 1 Tonne 141.14 162.95 184.53 205.50 225.48 18.49 15.44
14 Steel i/c C.G.I & A.C.sheet. 7.50 Tonne 7.50 1 Tonne 103.50 119.49 135.32 150.70 165.35 13.56 11.32
15 Timber 5 cu.m 5.00 1 cu.m 155.25 179.24 202.98 226.05 248.03 20.34 16.98
16 Tar Bitumen etc. 4.50 Tonne 4.50 1 Tonne 172.50 199.16 225.53 251.17 275.59 22.60 18.87
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALSS.No MATERIALS CAPACITY NET QTY.TO
BE PAID
AFTER
DEDUCTION
OF VOIDS.
UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW
1 Km. 2Km. 3Km. 4Km. 5Km. BEYOND
5Km.UP TO
10 Km.
BEYOND
10Km.UP
TO 20 Km.
BEYOND 20Km
/Km.
71.33
13
11.89
14.86
12.92
23.78
14.27
15.44
16.78
35.67
22.29
4.94
28.53
9.51
12.97
9.51
14.27
15.85
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.265
Shimla Jal Prabandhan Nigam Limited Rate Analysis
17 R.C.C.,A.C. Hume, steel
C.I.Pipes:- 80 mm dia
332.40m 332.40 100m 233.53 269.61 305.32 340.03 373.09 30.60 25.55
18 100 mm dia 322.80m 322.80 100m 240.47 277.63 314.40 350.14 384.18 31.51 26.31
19 125 mm dia 219.6m 219.60 100m 353.48 408.11 462.15 514.69 564.73 46.31 38.67
20 150 mm dia 183m 183.00 100m 424.18 489.73 554.58 617.62 677.67 55.57 46.40
21 200 mm dia 109.80m 109.80 100m 706.97 816.21 924.31 1029.37 1129.45 92.62 77.34
22 250 mm dia 80.52m 80.52 100m 964.05 1113.02 1260.42 1403.69 1540.16 126.30 105.46
23 300 mm dia 62.22m 62.22 100m 1247.59 1440.37 1631.13 1816.54 1993.15 163.45 136.48
24 350 mm dia 43.92m 43.92 100m 1767.42 2040.53 2310.77 2573.43 2823.63 231.56 193.35
25 400 mm dia 32.94m 32.94 100m 2356.56 2720.70 3081.03 3431.24 3764.85 308.74 257.80
26 450 /500mmdia 25.62m 25.62 100m 3029.86 3498.05 3961.32 4411.59 4840.52 396.96 331.46
27 600, 700, 750 & 800 mm dia 18.30m 18.30 100m 4241.80 4897.27 5545.85 6176.23 6776.72 555.74 464.04
28 900,1000,1100 & 1200 mm dia. 11.00m 11.00 100m 7056.82 8147.27 9226.27 10275.00 11274.00 924.55 772.00
21.46
22.10
216.55
278.42
389.78
648.45
32.48
38.98
64.96
88.59
114.64
162.41
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.266
Shimla Jal Prabandhan Nigam Limited Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
LIGHT MATERIALS A : 7.67 250.00 1917.50 2301.00
1 Lime, moorum and building rubish. 35 cu.m 35.00 1 cu.m 1917.50 65.74 27.39 93.13 586.15 293.08
2 .Earth work. 35 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
3 Manure or sludge 35cu.m 32.20 1 cu.m 1917.50 71.46 29.77 101.23 637.09 318.55
4 Excavated rock. 35 cu.m 17.50 1 cu.m 1917.50 131.49 54.79 186.28 1172.50 586.25
5 Sand,stone agg.below 40mm size. 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
6 Stone agg.40mm & above,build. Stones. 28 cu.m 25.90 1 cu.m 1917.50 88.84 37.02 125.86 792.22 396.11
7 Soling stone, stone block & stone for filling crates 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
8 Bricks. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
9 Bricks tiles. 24000
Nos.
24000.00 1000 Nos. 1917.50 95.88 39.95 135.83 854.93 427.47
10 Slates. 80000
Nos.
80000.00 1000 Nos. 1917.50 28.76 11.98 40.74 256.38 128.19
11 Terrazzo Tiles. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
HEAVY MATERIALS A : 9.20 250.00 2300.00 B : =(Col.No.7/2+Col.No.7*1.40/2) 2760.00
1 Stone blocks G.I,C.C. pipes below 100mm dia and
other heavy materials.
46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
2 cement 57 Tonne 57.00 1 Tonne 2300.00 48.42 20.18 68.60 431.84 215.92
3 Steel including C.G.I & asbestos sheet. 27 Tonne 27.00 1 Tonne 2300.00 102.22 42.59 144.81 911.43 455.72
4 Timber 42 cu.m 42.00 1 cu.m 2300.00 65.71 27.38 93.09 585.93 292.97
5 Tar Bitumen etc. 46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
6 Concrete, R.C.C. Hume, steel C.I.Pipes:- 100mm
dia
1702m 1702.00 100m 2300.00 162.16 67.57 229.73 1445.99 723.00
7 Concrete, R.C.C. Hume, steel C.I.Pipes:- 125mm dia 1391m 1391.00 100m 2300.00 198.42 82.67 281.09 1769.15 884.58
No's Beldar @ B : =(Col.No.7/2+Col.No.7*1.40/2)
No's Beldar @
CARRIAGE OF MATERIAL BY MANUAL LABOUR INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID A
FT
ER
DE
DU
CT
ION
OF
VO
IDS
.
UN
ITS
CO
ST
OF 8
HO
UR
S COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IRS
T 5
0
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF 5
0
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
0.5
0
FO
R 1
00
MT
R
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.267
Shimla Jal Prabandhan Nigam Limited Rate Analysis
8 Concrete, R.C.C. Hume, steel C.I.Pipes:- 150mm dia 1208m 1208.00 100m 2300.00 228.48 95.20 323.68 2037.28 1018.64
9 Concrete, R.C.C. Hume, steel C.I.Pipes:- 200mm dia 805m 805.00 100m 2300.00 342.86 142.86 485.72 3057.20 1528.60
10 Concrete, R.C.C. Hume, steel C.I.Pipes:- 250mm dia 458m 458.00 100m 2300.00 602.62 251.09 853.71 5373.33 2686.67
11 Concrete, R.C.C. Hume, steel C.I.Pipes:- 300mm dia 366m 366.00 100m 2300.00 754.10 314.21 1068.31 6724.09 3362.05
12 Concrete, R.C.C. Hume, steel C.I.Pipes:- 350mm dia 256m 256.00 100m 2300.00 1078.13 449.22 1527.35 9613.31 4806.66
13 Concrete, R.C.C. Hume, steel C.I.Pipes:- 400mm dia 220m 220.00 100m 2300.00 1254.55 522.73 1777.28 11186.42 5593.21
14 Concrete, R.C.C. Hume, steel C.I.Pipes:-
450mm,500mm dia
165m 165.00 100m 2300.00 1672.73 696.97 2369.70 14915.16 7457.58
15 Concrete, R.C.C. Hume, steel C.I.Pipes:- 600,700,750
& 800mm dia
150m 150.00 100m 2300.00 1840.00 766.67 2606.67 16406.73 8203.37
16 Concrete, R.C.C. Hume, steel C.I.Pipes:-
900,1000,1100&1200mm dia
125m 125.00 100m 2300.00 2208.00 920.00 3128.00 19688.00 9844.00
17 Asbestes cement pipes: - 50mm dia =5032 pipes
of 2m length 10064m
10064m 10064.00 100m 2300.00 27.42 11.43 38.85 244.59 122.30
18 As bestes cement pipes: - 80mm dia 1620 pipes of
2m length=3660
3660m 3660.00 100m 2300.00 75.41 31.42 106.83 672.39 336.20
19 As bestes cement pipes:- 100mm dia 1281 pipes of
2m length=2562m
2562m 2562.00 100m 2300.00 107.73 44.89 152.62 960.64 480.32
20 As bestes cement pipes:- 125mm dia 1100 pipes of
2m length= 2200m
2200m 2200.00 100m 2300.00 125.45 52.27 177.72 1118.58 559.29
21 As bestes cement pipes:- 150mm dia 915 pipes of
2m length =1830m
1830m 1830.00 100m 2300.00 150.82 62.84 213.66 1344.78 672.39
22 As bestes cement pipes:- 200mm dia 800 pipes of
2m length= 1600m
1600m 1600.00 100m 2300.00 172.50 71.88 244.38 1538.22 769.11
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.268
Shimla Jal Prabandhan Nigam Limited Rate Analysis
23 As bestes cement pipes:- 250mm dia 700 pipes of
2m length= 1400m
1400m 1400.00 100m 2300.00 197.14 82.14 279.28 1757.80 878.90
24 As bestes cement pipes:- 300mm dia 600 pipes of
2m length= 1200m
1200m 1200.00 100m 2300.00 230.00 95.83 325.83 2050.77 1025.39
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.269
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 1
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 80 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1Basic rates on F.O.R. destination
Chandigarh Mtr.10.00 691.8399 6918.40
Add 10% for Specials 0.10 691.84
Add 0.5% for inspection charges. 34.59
Add 3% for entry tax 207.55
White lead hemp oil etc., L.S. 35.00
Sub Total:- 7887.38 (A)
2 Carriage
130Km by Mech Transport Chandigarh to
ShimlaTonne 0.101 1449.51 146.40
6 Km by Mech. Transport from IPH.Store Tonne 0.101 1449.51 146.40
0.5 Km by Head Load Tonne 0.101 285.00 28.79
Sub total:- 321.59 (B)
3 Labour
1 Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total:- 414.30 (C)
Total (A+B+C) 8623.27
4 Other additions
Add 10% C.P & 5 % O.H charges 8623.27 15.00% 1293.49
Add 12% GST 0.00% 0.00
Add 1% Labour Cess 1.00% 86.23
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 1431.51 (D)
Cost for 10 Rmt. (A1+B+C+D) 10054.78
Cost per running meter 1005.48
Cost of excavation 412.73
Cost per meter including excavation 1418.21
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.270
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 2
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 100 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1 Chandigarh Mtr. 10.00 996.6616 9966.62
Add 10% for Specials 0.10 996.66
Add 3 % Entry tex 299.00
Add 0.5% for inspection charges. 49.83
White lead hemp oil etc., L.S. 35.00
Sub Total:- 11347.11 (A)
2 Carriage
130Km by Mech Transport Chandigarh to
ShimlaTonne 0.148 1449.51 214.53
6 Km by Mech. Transport from IPH.Store Tonne 0.148 1449.51 214.53
0.5 Km by Head Load Tonne 0.148 285.00 42.18
Sub total:- 471.23 (B)
3 Labour
1 Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total:- 414.30 (C)
Total (A+B+C) 10852.15
4 Other additions
Add 10% C.P & 5 % O.H charges 10852.15 15.00% 1627.82
Add 12% GST 0.00% 0.00
Add 1% Labour Cess 1.00% 108.52
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 1788.13 (D)
Cost for 10 Rmt. (A1+B+C+D) 14020.78
Cost per running meter 1402.08
Cost of excavation 412.73
Cost per meter including excavation 1814.81
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.271
Shimla Jal Prabandhan Nigam Limited Rate Analysis
RATE ANALYSIS - 3
(Earth work in trenches & jointing of pipes to be measured and paid seperately)
DETAILS OF 10 RMT. LENGTH OF 150 MM DIAMETER G.I. PIPE
Sr. Item Unit Qty. Rate Amount
A Material
1 Basic rates on F.O.R. destination
Chandigarh Mtr. 10.00 1474.7898 14747.90
Add 10% for Specials 0.10 1474.79
Add 3 % Entry tex 442.44
Add 0.5% for inspection charges. 73.74
White lead hemp oil etc., L.S. 35.00
Sub total 16773.86 (A)
2 Carriage
130 Km by Mech Transport Chandigarh to Shimla Tonne 0.219 1449.51 317.44
6 Km by Mech. Transport from IPH.Store Tonne 0.219 1449.51 317.44
0.5 Km by Head Load Tonne 0.219 285.00 62.42
Sub total 697.30 (B)
3 Labour
Labour for laying 10 m pipe
* Plumber (fitter) Each 0.40 292.00 116.80
* Beldar Each 1.19 250.00 297.50
Sub total 414.30 (C)
Total (A+B+C) 17885.46
4 Other additions
Add 10% C.P & 5 % O.H charges 17885.46 15.00% 2682.82
Add GST 0.00% 0.00
Add 1% Labour Cess 1.00% 178.85
Add 12.5% EPF on Labour 414.30 12.50% 51.79
Sub Total:- 2913.46 (D)
Cost for 10 Rmt. (A+B+C+D) 20798.93
Cost per running meter 2079.89
Cost of excavation 412.73
Cost per meter including excavation 2492.63
Providing & laying in trenches galvanised mild steel pipe conforming to IS 1239/1990 (5th revision) heavy class
including bends of all degrees, tees, collars, tapers, crosses, flanged socket & spigots and jointing
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.272
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 260.40 MM Dia
Diameter in mm 260.4
Thickness in mm 6.3
Density in Kg per Cum 7850
WT per Meter in Kg 41.44
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.385
Wt of pair of flange in Kg 4.77
No of Nut bolts 36
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 7.2
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 260.40 MM Dia 4226.88 Kg 58.00 245159.04
Add GST 18.00% 44128.63
Cost of Pipe including GST 289287.67
Add entry tax 3.00% 8678.63
Add inspection Charges 0.50% 1446.44
Cost of pipe 299412.74
Carriage of pipes by mechanical transportation 1 Job 13502.70 13502.70
Carriage of pipes by head load 1 Job 3581.99 3581.99
Unloading and stacking 1 Job 3581.99 3581.99
Cost of Transportation of pipe 100 m length 20666.68
Cost of Pipe Welding 6518.18 cm 5.00 32590.90
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 4238.85 Kg 1.02 4323.63
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
RATE ANALYSIS - 5
Providing & laying in trenches MS ERW Pipelines of given 260.4 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.273
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 81.81
Outer side 85.77
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804167.58 Sqm 122.5 20528.55
Hasion cloth wraping
Clothe 0.86 Sqm 25.00 21.50
Bitumen 0.86 Sqm 40.00 34.40
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 152.83
Cost of wraping for 100 meters 15283.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.339597.18 % 15.00% 50939.58
Pair of Flange 4.77 Kg 64.00 305.28
Nut Blots 7.2 Kg 59.75 430.2
Add GST 12.00% 51.62
Cost of Flanges including GST 787.1
Add entry tax 3.00% 23.61
Add inspection Charges 0.50% 3.94
Cost of flange 814.65
Gasket 2 No 105.00 210.00
Length of welding from inside 163.61 cm 5.00 818.05
Length of welding from outside 343.06 cm 5.00 1715.30
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 3564.36
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.3485.1897 % 15.00% 522.78
Cost of pair of flange 4087.14
Add 1% Labour Cess 343082.37 % 1.00% 3430.82
Add EPF 12.5% on all Labour 76304.81 % 12.50% 9538.10
Cost of Piping including all for 100 meter 461846.52
Cost of Piping including all per meter 4618.47
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.274
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 250MM Dia
Diameter in mm 309.7
Thickness in mm 7.1
Density in Kg per Cum 7850
WT per Meter in Kg 55.47
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 2.485
Wt of pair of flange in Kg 4.97
No of Nut bolts 36
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 7.2
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 250MM Dia 5657.94 Kg 58.00 328160.52
Add GST 18.00% 59068.89
Cost of Pipe including GST 387229.41
Add entry tax 3.00% 11616.88
Add inspection Charges 0.50% 1936.15
Cost of pipe 400782.44
Carriage of pipes by mechanical transportation 1 Job 17473.44 17473.44
Carriage of pipes by head load 1 Job 3581.99 3581.99
Unloading and stacking 1 Job 3581.99 3581.99
Cost of Transportation of pipe 100 m length 24637.42
Cost of Pipe Welding 7733.47 cm 5.00 38667.35
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 5670.11 Kg 1.02 5783.51
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 6
Providing & laying in trenches MS ERW Pipelines of given 309.7 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.275
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 97.3
Outer side 101.76
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804199.06 Sqm 122.5 24384.85
Hasion cloth wraping
Clothe 1.02 Sqm 25.00 25.50
Bitumen 1.02 Sqm 40.00 40.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 163.23
Cost of wraping for 100 meters 16323.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.439002.03 % 15.00% 65850.3
Pair of Flange 4.97 Kg 64.00 318.08
Nut Blots 7.2 Kg 59.75 430.2
Add GST 12.00% 51.62
Cost of Flanges including GST 799.9
Add entry tax 3.00% 24
Add inspection Charges 0.50% 4
Cost of flange 827.9
Gasket 2 No 105.00 210.00
Length of welding from inside 194.59 cm 5.00 972.95
Length of welding from outside 407.02 cm 5.00 2035.10
Carriage of flanges by mechanical transportation 0.01 Ton 346.35 3.46
Carriage of flanges by head load 0.01 Ton 144.81 1.45
Unloading and stacking 0.01 Ton 144.81 1.45
Cost of pair of flange 4052.31
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.3972.6897 % 15.00% 595.90
Cost of pair of flange 4648.21
Add 1% Labour Cess 442974.72 % 1.00% 4429.75
Add EPF 12.5% on all Labour 89212.14 % 12.50% 11151.52
Cost of Piping including all for 100 meter 597703.73
Cost of Piping including all per meter 5977.04
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.276
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 250MM Dia
Diameter in mm 339.6
Thickness in mm 8
Density in Kg per Cum 7850
WT per Meter in Kg 68.58
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 3.989
Wt of pair of flange in Kg 7.98
No of Nut bolts 48
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 9.6
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 250MM Dia 6995.16 Kg 58.00 405719.28
Add GST 18.00% 73029.47
Cost of Pipe including GST 478748.75
Add entry tax 3.00% 14362.46
Add inspection Charges 0.50% 2393.74
Cost of pipe 495504.95
Carriage of pipes by mechanical transportation 1 job 24754.49 24754.49
Carriage of pipes by head load 1 job 5121.11 5121.11
Unloading and stacking 1 job 5121.11 5121.11
Cost of Transportation of pipe 100 m length 34996.71
Cost of Pipe Welding 8490.34 cm 5.00 42451.70
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 7012.74 Kg 1.02 7152.99
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
RATE ANALYSIS - 7
Providing & laying in trenches MS ERW Pipelines of given 339.6 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.277
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 106.69
Outer side 111.72
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804218.41 Sqm 122.5 26755.23
Hasion cloth wraping
Clothe 1.12 Sqm 25.00 28.00
Bitumen 1.12 Sqm 40.00 44.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 169.73
Cost of wraping for 100 meters 16973.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.535094.29 % 15.00% 80264.14
Pair of Flange 7.98 Kg 64.00 510.72
Nut Blots 9.6 Kg 59.75 573.6
Add GST 12.00% 68.83
Cost of Flanges including GST 1153.15
Add entry tax 3.00% 34.59
Add inspection Charges 0.50% 5.77
Cost of flange 1193.51
Gasket 2 No 105.00 210.00
Length of welding from inside 213.38 cm 5.00 1066.90
Length of welding from outside 446.86 cm 5.00 2234.30
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 4717.43
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.4608.2394 % 15.00% 691.24
Cost of pair of flange 5408.67
Add 1% Labour Cess 539702.53 % 1.00% 5397.03
Add EPF 12.5% on all Labour 97679.50 % 12.50% 12209.94
Cost of Piping including all for 100 meter 728159.74
Cost of Piping including all per meter 7281.6
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.278
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 250MM Dia
Diameter in mm 388.8
Thickness in mm 8.8
Density in Kg per Cum 7850
WT per Meter in Kg 86.29
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 4.650
Wt of pair of flange in Kg 9.3
No of Nut bolts 48
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 9.6
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 250MM Dia 8801.58 Kg 58.00 510491.64
Add GST 18.00% 91888.5
Cost of Pipe including GST 602380.14
Add entry tax 3.00% 18071.4
Add inspection Charges 0.50% 3011.9
Cost of pipe 623463.44
Carriage of pipes by mechanical transportation 1 job 33006.35 33006.35
Carriage of pipes by head load 1 job 5959.12 5959.12
Unloading and stacking 1 job 5959.12 5959.12
Cost of Transportation of pipe 100 m length 44924.59
Cost of Pipe Welding 9703.25 cm 5.00 48516.25
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 8820.48 Kg 1.02 8996.89
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
RATE ANALYSIS - 8
Providing & laying in trenches MS ERW Pipelines of given 388.8 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.279
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 122.15
Outer side 127.67
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804249.82 Sqm 122.5 30602.95
Hasion cloth wraping
Clothe 1.28 Sqm 25.00 32.00
Bitumen 1.28 Sqm 40.00 51.20
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 180.13
Cost of wraping for 100 meters 18013.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.662590.70 % 15.00% 99388.61
Pair of Flange 9.3 Kg 64.00 595.2
Nut Blots 9.6 Kg 59.75 573.6
Add GST 12.00% 68.83
Cost of Flanges including GST 1237.63
Add entry tax 3.00% 37.13
Add inspection Charges 0.50% 6.19
Cost of flange 1280.95
Gasket 2 No 105.00 210.00
Length of welding from inside 244.29 cm 5.00 1221.45
Length of welding from outside 510.7 cm 5.00 2553.50
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 5278.62
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.5166.4694 % 15.00% 774.97
Cost of pair of flange 6053.59
Add 1% Labour Cess 667757.17 % 1.00% 6677.57
Add EPF 12.5% on all Labour 110949.42 % 12.50% 13868.68
Cost of Piping including all for 100 meter 901550.95
Cost of Piping including all per meter 9015.51
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.280
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 250MM Dia
Diameter in mm 437
Thickness in mm 10
Density in Kg per Cum 7850
WT per Meter in Kg 110.24
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 4.923
Wt of pair of flange in Kg 9.85
No of Nut bolts 60
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 12
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 250MM Dia 11244.48 Kg 58.00 652179.84
Add GST 18.00% 117392.37
Cost of Pipe including GST 769572.21
Add entry tax 3.00% 23087.17
Add inspection Charges 0.50% 3847.86
Cost of pipe 796507.24
Carriage of pipes by mechanical transportation 1 job 42436.64 42436.64
Carriage of pipes by head load 1 job 7945.46 7945.46
Unloading and stacking 1 job 7945.46 7945.46
Cost of Transportation of pipe 100 m length 58327.56
Cost of Pipe Welding 10911.38 cm 5.00 54556.90
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 11266.33 Kg 1.02 11491.66
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
RATE ANALYSIS - 8
Providing & laying in trenches MS ERW Pipelines of given 437 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.281
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 137.29
Outer side 143.57
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804280.86 Sqm 122.5 34405.35
Hasion cloth wraping
Clothe 1.44 Sqm 25.00 36.00
Bitumen 1.44 Sqm 40.00 57.60
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 190.53
Cost of wraping for 100 meters 19053.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.831059.69 % 15.00% 124658.95
Pair of Flange 9.85 Kg 64.00 630.4
Nut Blots 12 Kg 59.75 717
Add GST 12.00% 86.04
Cost of Flanges including GST 1433.44
Add entry tax 3.00% 43
Add inspection Charges 0.50% 7.17
Cost of flange 1483.61
Gasket 2 No 105.00 210.00
Length of welding from inside 274.58 cm 5.00 1372.90
Length of welding from outside 574.28 cm 5.00 2871.40
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 5950.63
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.5814.4194 % 15.00% 872.16
Cost of pair of flange 6822.79
Add 1% Labour Cess 836874.11 % 1.00% 8368.74
Add EPF 12.5% on all Labour 124796.59 % 12.50% 15599.57
Cost of Piping including all for 100 meter 1130837.14
Cost of Piping including all per meter 11308.37
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.282
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 250MM Dia
Diameter in mm 486
Thickness in mm 11
Density in Kg per Cum 7850
WT per Meter in Kg 134.82
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 5.337
Wt of pair of flange in Kg 10.67
No of Nut bolts 60
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 12
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 250MM Dia 13751.64 Kg 58.00 797595.12
Add GST 18.00% 143567.12
Cost of Pipe including GST 941162.24
Add entry tax 3.00% 28234.87
Add inspection Charges 0.50% 4705.81
Cost of pipe 974102.92
Carriage of pipes by mechanical transportation 1 job 42436.64 42436.64
Carriage of pipes by head load 1 job 7945.46 7945.46
Unloading and stacking 1 job 7945.46 7945.46
Cost of Transportation of pipe 100 m length 58327.56
Cost of Pipe Welding 12129.06 cm 5.00 60645.30
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 13774.31 Kg 1.02 14049.80
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
RATE ANALYSIS - 8
Providing & laying in trenches MS ERW Pipelines of given 486 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.283
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 152.68
Outer side 159.59
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804312.27 Sqm 122.5 38253.08
Hasion cloth wraping
Clothe 1.6 Sqm 25.00 40.00
Bitumen 1.6 Sqm 40.00 64.00
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 200.93
Cost of wraping for 100 meters 20093.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.990009.24 % 15.00% 148501.39
Pair of Flange 10.67 Kg 64.00 682.88
Nut Blots 12 Kg 59.75 717
Add GST 12.00% 86.04
Cost of Flanges including GST 1485.92
Add entry tax 3.00% 44.58
Add inspection Charges 0.50% 7.43
Cost of flange 1537.93
Gasket 2 No 105.00 210.00
Length of welding from inside 305.36 cm 5.00 1526.80
Length of welding from outside 638.37 cm 5.00 3191.85
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 6479.30
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.6341.2494 % 15.00% 951.19
Cost of pair of flange 7430.49
Add 1% Labour Cess 996350.49 % 1.00% 9963.50
Add EPF 12.5% on all Labour 138805.21 % 12.50% 17350.65
Cost of Piping including all for 100 meter 1349763.07
Cost of Piping including all per meter 13497.63
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.284
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 100MM Dia
Diameter in mm 585
Thickness in mm 12.5
Density in Kg per Cum 7850
WT per Meter in Kg 184.19
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 6.41
Wt of pair of flange in Kg 12.82
No of Nut bolts 60
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 12
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 100MM Dia 18787.38 Kg 58.00 1089668.04
Add GST 18.00% 196140.25
Cost of Pipe including GST 1285808.29
Add entry tax 3.00% 38574.25
Add inspection Charges 0.50% 6429.04
Cost of pipe 1330811.58
Carriage of pipes by mechanical transportation 1 job 59410.30 59410.30
Carriage of pipes by head load 1 job 8740.03 8740.03
Unloading and stacking 1 job 8740.03 8740.03
Cost of Transportation of pipe 100 m length 76890.36
Cost of Pipe Welding 14564.42 cm 5.00 72822.10
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 18812.2 Kg 1.02 19188.44
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
RATE ANALYSIS - 4
Providing & laying in trenches MS ERW Pipelines of given 585 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.285
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 183.78
Outer side 191.64
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804375.42 Sqm 122.5 45988.95
Hasion cloth wraping
Clothe 1.92 Sqm 25.00 48.00
Bitumen 1.92 Sqm 40.00 76.80
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 221.73
Cost of wraping for 100 meters 22173.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.1327776.27 % 15.00% 199166.44
Pair of Flange 12.82 Kg 64.00 820.48
Nut Blots 12 Kg 59.75 717
Add GST 12.00% 86.04
Cost of Flanges including GST 1623.52
Add entry tax 3.00% 48.71
Add inspection Charges 0.50% 8.12
Cost of flange 1680.35
Gasket 2 No 105.00 210.00
Length of welding from inside 367.57 cm 5.00 1837.85
Length of welding from outside 766.55 cm 5.00 3832.75
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 7573.67
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.7430.7994 % 15.00% 1114.62
Cost of pair of flange 8688.29
Add 1% Labour Cess 1335207.07 % 1.00% 13352.07
Add EPF 12.5% on all Labour 166888.47 % 12.50% 20861.06
Cost of Piping including all for 100 meter 1810987.67
Cost of Piping including all per meter 18109.88
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.286
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Data
Pipe: MS ERW - 100MM Dia
Diameter in mm 585
Thickness in mm 15
Density in Kg per Cum 7850
WT per Meter in Kg 221.95
Length of pipe in meter 100
Add for bends 2%
Total length in Meter 102
Welding
Average Length of pipe 5.5
No of Welds 19
Flanges
Wt of flange as per table in Kg 6.04
Wt of pair of flange in Kg 12.08
No of Nut bolts 60
% for Wt of nut bolt in Kg 20%
Wt of Nut bolts in Kg 12
No of runs of welding to inside 1
No of runs of welding to outside 2
Analysis of Rate:
Description Qty Unit Rate Amount
Pipe: MS ERW - 100MM Dia 22638.9 Kg 58.00 1313056.2
Add GST 18.00% 236350.12
Cost of Pipe including GST 1549406.32
Add entry tax 3.00% 46482.19
Add inspection Charges 0.50% 7747.03
Cost of pipe 1603635.54
Carriage of pipes by mechanical transportation 1 job 59410.30 59410.30
Carriage of pipes by head load 1 job 8740.03 8740.03
Unloading and stacking 1 job 8740.03 8740.03
Cost of Transportation of pipe 100 m length 76890.36
Cost of Pipe Welding 14683.8 cm 5.00 73419.00
Labour for laying (Detail of cost for 514 kg)
Fitter 0.20 Nos 292.00 58.40
Assistant Fitter. 0.20 Nos 292.00 58.40
Beldar. 1.60 Nos 250.00 400.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 514 Kg 526.80
Cost of laying per Kg 1.02
Cost of laying of 100 m pipeline 22662.98 Kg 1.02 23116.24
Labour for jointing (Detail for 10 Joints.)
Plumber 0.36 Nos 292.00 105.12
Assistant plumber 0.36 Nos 292.00 105.12
Beldar. 1.32 Nos 250.00 330.00
Sundries. 1 LS 10.00 10.00
Cost of laying for 10 joints 550.24
RATE ANALYSIS - 4
Providing & laying in trenches MS ERW Pipelines of given 585 mm dia conforming to IS: 3589-2001,steel grade Fe 410 with
wall thickness, weight per meter, flanges as described in analysis
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.287
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Description Qty Unit Rate Amount
Cost of laying per joint 55.02
Cost of Jointing of 100 m pipeline 19 Joints 55.02 1045.38
Painting two or more coat in and out side of the pipe.
Innner side 183.78
Outer side 193.21
Cost of Painting of 100 m pipeline (rate as per CPWD DSR 2016-
I.N. 13.52.1 P.N. 804376.99 Sqm 122.5 46181.28
Hasion cloth wraping
Clothe 1.93 Sqm 25.00 48.25
Bitumen 1.93 Sqm 40.00 77.20
Fuel wood 5.57 Sqm 5.00 27.85
Sundries. 0.00
Painter 0.072 265.00 19.08
Beldar. 0.2 250.00 50.00
Rate of wraping per meter 222.38
Cost of wraping for 100 meters 22238.00
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.1555946.46 % 15.00% 233391.97
Pair of Flange 12.08 Kg 64.00 773.12
Nut Blots 12 Kg 59.75 717
Add GST 12.00% 86.04
Cost of Flanges including GST 1576.16
Add entry tax 3.00% 47.28
Add inspection Charges 0.50% 7.88
Cost of flange 1631.32
Gasket 2 No 105.00 210.00
Length of welding from inside 367.57 cm 5.00 1837.85
Length of welding from outside 772.83 cm 5.00 3864.15
Carriage of flanges by mechanical transportation 0.02 Ton 346.35 6.93
Carriage of flanges by head load 0.02 Ton 144.81 2.90
Unloading and stacking 0.02 Ton 144.81 2.90
Cost of pair of flange 7556.04
Add 10% C.P.& 5% O.H.Charges on amount excluding cost of
taxes.7414.8394 % 15.00% 1112.23
Cost of pair of flange 8668.27
Add 1% Labour Cess 1563361.30 % 1.00% 15633.61
Add EPF 12.5% on all Labour 171701.90 % 12.50% 21462.74
Cost of Piping including all for 100 meter 2125682.39
Cost of Piping including all per meter 21256.82
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.288
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Details of cost for 10 Cubic meters :
Sr. Item Unit Qty. Rate Amount
1 Pick Work
1 Labour : Beldar Each 8.32 250.00 2080
Bhisti Each 0.28 250.00 70
Add for water charges @ 1.5% 32.25
Total Rs. 2182.25
Add 10% for Contractor profit 218.23
Add 5% for overhead charges 109.11
Cost of 10 cubic meters Rs. 2509.59
Cost per cum Rs. 250.96
2 Chiselling work in hard rock (Where blasting is prohibitted)1 Labour:
Beldar Each 11.71 250.00 2927.50
Stone Chiseller Each 23.43 250.00 5857.50
Black smith (G-II) Each 0.59 250.00 147.50
Total 8932.50
Add 10% Contractor profit 893.25
Add 5% Overhead Charges 446.63
Cost of 10 cubic meters Rs. 10272.38
Cost per cum Rs. 1027.24
Classification of soil Amount
Pick Work (70%) 250.96 70% 175.67
Chiselling Work (Hard work) (30%) 1027.24 30% 308.17
Average Rate 483.84
Add labour cess @ 1.00 % 483.84 1% 4.84
Add 12 % GST 12.0% 58.06
Total Cost Rs. Per Cum 546.74
Detail of cost for 10 cubic metre
1. Soft rock.
Sr. Item Unit Qty. Rate Amount.
Drilling equipment Day 0.18 75.00 13.50
Material
Special gelatine (80%) kg. 2.520 5000.00 12600.00
Detonators ordinary 100 Nos 12.00 1000.00 120.00
Safety fuse wire (coil 10 Mtrs length) Coil 1.00 5000.00 5000.00
Labour
Hole Driller each 0.54 262.00 141.48
Blaster each 0.36 0.00 0.00
Beldar each 6.67 250.00 1667.50
Total 19542.48
Add 10% Contractor profit 1954.25
Add 5% Overhead Charges 977.12
Total 22473.85
Cost for 10 cum. 22473.85
Cost for 1 cum 2247.39
Detail of cost for 10 cubic metre
2. Hard Rock
Drilling equipment Day 0.28 75.00 21.00
Material
Analysis of Rate - 10
Cutting in earth work and disposal of excavated earth upto a lead of 20 Mtrs soft rock.
Analysis of Rates - 9
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m stacking the soil not more than 3 meters clear from
the edge of the excavation and then returning the stacked soil in 15cm layers, when required into the plinths sides of
foundations etc., consolidating each deposited layer by ramming and watering and then disposing of all surplus excavated
earth as directed within a lead of 20 meters.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.289
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Item Unit Qty. Rate Amount.
Special gelatine (80 % ) Kg. 3.92 5000.00 19600.00
Detonators ordinary 100 Nos. 14.00 1000.00 140.00
Safety fuse wire (coil 10 mtr. length ) Coil 1.25 5000.00 6250.00
Labour
Hole Driller Each 0.84 262.00 220.08
Blaster Each 0.56 0.00 0.00
Beldar Each 8.33 250.00 2082.50
Total 28313.58
Add 10% Contractor profit 2831.358
Add 5% Overhead Charges 1415.679
Total 32560.62
Cost for 10 cum 32560.62
Cost of per cum 3256.06
Classification of Rocks Amount
Soft Rock (70%) 2247.39 70% 1573.17
Hard Rock (30%) 3256.06 30% 976.82
Average Rate 2549.99
Add labour cess @ 1.00 % 2549.99 1% 25.50
Add 12 % GST 12.0% 306.00
Total Cost Rs. Per Cum 2881.49
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.290
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand:
4graded stone aggregate 20 mm nominal size )
and curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
1 1.30 1.30 0.15 0.25 Cum 7957.06 2017.11
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge
nominal size graded stone aggregate) & curing
complete excluding the cost of form work &
reinforcement for reinforced concrete work in
Bottom raft slab
1 1 1 0.2 0.20 Cum 8,139.12 1627.82
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge
nominal size graded stone aggregate) & curing
complete excluding the cost of form work &
reinforcement for reinforced concrete work in
Vertical Walls
2 0.6 0.2 0.75 0.18 Cum 8,139.12 1465.04
2 1 0.2 0.75 0.30 Cum 8,139.12 2441.74
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge
nominal size graded stone aggregate) & curing
complete excluding the cost of form work &
reinforcement for reinforced concrete work in
chamber top cover
2 1 0.5 0.2 0.20 Cum 8,139.12 1627.82
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work
including bending binding and placing in position
complete, @ 80 Kg per Cum,
0.88 80 70.40 Kg 62.31 4386.82
Chamber of size 600 mm X 600 mm X 750 mm
Rate Analysis -11
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.291
Shimla Jal Prabandhan Nigam Limited Rate Analysis
As per Rate Analysis - 28
6Providing form work with steel plates and Bamboo
(Ballies) in Vertical Walls and Slab
For Foundation 1 1 1 1.00 Sqm 289.27 289.27
As per Rate Analysis - 18
Verical walls - inner face 4 0.6 0.75 1.80 Sqm 487.14 876.85
Verical walls - outer face 4 1 0.75 3.00 Sqm 487.14 1461.41
For Top Cover 1 1 1 1.00 Sqm 487.14 487.14
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 18681.03
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.292
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand:
4graded stone aggregate 20 mm nominal size ) and
curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
1 1.60 1.60 0.15 0.38 Cum 7957.06 3055.51
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge nominal
size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for
reinforced concrete work in Bottom raft slab
1 1.3 1.3 0.2 0.34 Cum 8,139.12 2751.02
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge nominal
size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for
reinforced concrete work in Vertical Walls
2 0.9 0.2 0.75 0.27 Cum 8,139.12 2197.56
2 1.3 0.2 0.75 0.39 Cum 8,139.12 3174.26
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge nominal
size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for
reinforced concrete work in chamber top cover
3 1.3 0.43 0.2 0.34 Cum 8,139.12 2751.02
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work
including bending binding and placing in position
complete, @ 80 Kg per Cum,
1.34 80 106.88 Kg 62.31 6659.99
As per Rate Analysis - 28
Rate Analysis -12
Chamber of size 900 mm X 900 mm X 750 mm
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.293
Shimla Jal Prabandhan Nigam Limited Rate Analysis
6Providing form work with steel plates and Bamboo
(Ballies) in Vertical Walls and Slab
For Foundation 1 1.3 1.3 1.69 Sqm 289.27 488.86
As per Rate Analysis - 18
Verical walls - inner face 4 0.9 0.75 2.70 Sqm 487.14 1315.27
Verical walls - outer face 4 1.3 0.75 3.90 Sqm 487.14 1899.84
For Top Cover 1 1.3 1.3 1.69 Sqm 487.14 823.26
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 27116.61
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.294
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement
:2sand: 4graded stone aggregate 20 mm
nominal size ) and curing complete e/c the cost of
form work and reinforcement in foundation &
plinth. (PCC M-150)
1 1.90 1.90 0.15 0.54 Cum 7957.06 4308.75
As per Rate Analysis - 24
2
Providing & laying cement concrete using
nominal mix of " M - 20 " with 20 mm & down
gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in
Bottom raft slab
1 1.6 1.6 0.2 0.51 Cum 8,139.12 4167.23
As per Rate Analysis - 25
3
Providing & laying cement concrete using
nominal mix of " M - 20 " with 20 mm & down
gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in
Vertical Walls
2 1.2 0.2 0.75 0.36 Cum 8,139.12 2930.08
2 1.6 0.2 0.75 0.48 Cum 8,139.12 3906.78
As per Rate Analysis - 25
4
Providing & laying cement concrete using
nominal mix of " M - 20 " with 20 mm & down
gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work
& reinforcement for reinforced concrete work in
chamber top cover
4 1.6 0.4 0.2 0.51 Cum 8,139.12 4167.23
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work
including bending binding and placing in position
complete, @ 80 Kg per Cum,
1.86 80 149.12 Kg 62.31 9292.09
Rate Analysis -13
Chamber of size 1200 mm X 1200 mm X 750 mm
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.295
Shimla Jal Prabandhan Nigam Limited Rate Analysis
As per Rate Analysis - 28
6Providing form work with steel plates and
Bamboo (Ballies) in Vertical Walls and Slab
For Foundation 1 1.6 1.6 2.56 Sqm 289.27 740.52
As per Rate Analysis - 18
Verical walls - inner face 4 1.2 0.75 3.60 Sqm 487.14 1753.70
Verical walls - outer face 4 1.6 0.75 4.80 Sqm 487.14 2338.26
For Top Cover 1 1.6 1.6 2.56 Sqm 487.14 1247.07
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 36851.71
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.296
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L B H Qty. Unit. Rate. Amount
1
Prov. & laying cement conc.1:2:4 (1cement :2sand:
4graded stone aggregate 20 mm nominal size ) and
curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
1 2.20 2.20 0.15 0.73 Cum 7957.06 5776.82
As per Rate Analysis - 24
2
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge nominal
size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for
reinforced concrete work in Bottom raft slab
1 1.9 1.9 0.2 0.72 Cum 8,139.12 5876.45
As per Rate Analysis - 25
3
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge nominal
size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for
reinforced concrete work in Vertical Walls
2 1.5 0.2 0.75 0.45 Cum 8,139.12 3662.61
2 1.9 0.2 0.75 0.57 Cum 8,139.12 4639.30
As per Rate Analysis - 25
4
Providing & laying cement concrete using nominal
mix of " M - 20 " with 20 mm & down gauge nominal
size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for
reinforced concrete work in chamber top cover
5 1.9 0.38 0.2 0.72 Cum 8,139.12 5876.45
As per Rate Analysis - 25
5
Providing tor steel reinforcement for RCC work
including bending binding and placing in position
complete, @ 80 Kg per Cum,
2.46 80 197.12 Kg 62.31 12283.10
As per Rate Analysis - 28
Rate Analysis -14
Chamber of size 1500 mm X 1500 mm X 750 mm
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.297
Shimla Jal Prabandhan Nigam Limited Rate Analysis
6Providing form work with steel plates and Bamboo
(Ballies) in Vertical Walls and Slab
For Foundation 1 1.9 1.9 3.61 Sqm 289.27 1044.25
As per Rate Analysis - 18
Verical walls - inner face 4 1.5 0.75 4.50 Sqm 487.14 2192.12
Verical walls - outer face 4 1.9 0.75 5.70 Sqm 487.14 2776.69
For Top Cover 1 1.9 1.9 3.61 Sqm 487.14 1758.57
As per Rate Analysis - 19
7 Providing and fixing Surface box 1 1.00 Nos 2000 2000.00
Total 47886.35
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.298
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. No. Item of work No L W D Quantity Rate Unit Amount
1 Excavation in foundation trenches etc. in earth work lift upto 1.5 mtr.
stacking the excavated soil not more than 3 mtr. clear from the edge
of excavation and then returning the stacked soil in 15cm layers
when required into plinths sides of foundation etc. consolidating
each deposited layer by ramming and watering then disposing of all
surplus soil as directed within a lead of 20mtr. in soft & hard rock.
1 1.35 1.65 1 2.23 546.74 Per cum. 1217.87
2 Prov. & laying cement conc.1:2:4(1cement:2sand:4graded stone
aggregate 20 mm nominal size ) and curing complete e/c the cost of
form work and reinforcement in foundation & plinth. 1 1.35 1.65 0.15 0.33 7957.06 Per Cum. 2658.65
Providing & laying cement concrete using nominal mix of " M - 20 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work in Bottom raft slab
(a)foundation footintg basis of columns and like mass concrete. 1 1.2 1.5 0.45 0.81 8,139.12 Per Cum. 6592.69
(b)Columns pillar posts and struts upto floor two level. 1 0.3 0.9 2.15 0.58 8139.12 Per Cum 4724.76
4 Providing mild steel/Tor steel reinforcement for R.C.C. work
including bending, binding and placing in position complete upto
floor two level. Tor steel.139.05 62.31 Per Kg. 8664.60
Providing form work with steel plates 3.15mm thick welded with
angle iron in frame 30x30x5mm so as to give a fair finish including
centring shuttering strutting and propping etc., with wooden battens
and ballies, height of propping and centring below supporting floor
to ceiling not exceeding 4 meters and removal of the same for in-
situ-reinforced concrete and plain concrete work in:-
a)Foundation, footing, basis of columns etc., and mass concrete.2.43 289.27 Per Sqmt. 702.92
b) Columns pillar posts and struts square, rectangular or polygonal
in plan. 5.16 487.14 Per Sqmt. 2513.63
27075.12Total Rs. In Lac.
Hydraulic Design & Network Modelling for Shimla Water Supply
Rate Anlysis - 15 SH:-Construction of RCC Anchor Block size 0.3m*0.9m
ABSTRACT OF COST
3
5
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.299
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L W D Qty Unit Rate Amount
1
Providing and laying bituminous macadam using
crushed stone aggregates of specified grading
premixed with bituminous binder, transported to site
by tippers, laid over a previously prepared surface
with paver finisher equiped with electronic sensor to
the required grade, level and alignment and rolling
with smooth wheeled, vibratory and tandem rollers as
per specifications to achieve the desired compaction
and density, complete as per specificatons and
directions of Engineer-in-Charge.
50 to 100 mm average compacted thickness with
bitumen of grade VG-30 @ 3.50% (percentage by
weight of total mix) prepared in Batch Type Hot Mix
Plant of 100- 120 TPH capacity. CPWD DSR Vol 2
16.55.1
1 1 1 0.075 0.075 Cum 5708.05 428.10375
2
Construction of granular sub-base by providing close
graded Material conforming to specifications, mixing
in a mechanical mix plant at OMC, carriage of mixed
material by tippers to work site, for all leads & lifts,
spreading in uniform layers of specified thickness
with motor grader on prepared surface and
compacting with vibratory power roller to achieve the
desired density, complete as per specifications and
directions of Engineer-in-Charge.
With material conforming to Grade-I (size range 75
mm to 0.075 mm) having CBR Value-30 CPWD DSR
Vol 2 16.78.1
1 1 1 0.2 0.2 Cum 2089.7 417.94
3Providing and constructing WBM CPWD DSR Vol 2
16.13.21 1 1 0.175 0.175 Cum 1407.15 246.25125
Rate Analysis -16 : Road Restoration
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.300
Shimla Jal Prabandhan Nigam Limited Rate Analysis
S.N. Description No L W D Qty Unit Rate Amount
4
2.5 cm premix carpet surfacing with 2.25 cum and
1.12 cum of stone chippings of
13.2 mm and 11.2 mm size respectively per 100 sqm
and 52 kg and 56 kg of hot
bitumen per cum of stone chippings of 13.2 mm and
11.2 mm size respectively,
including a tack coat with hot straight run bitumen,
including consolidation with
road roller of 6 to 9 tonne capacity etc. complete
(tack coat to be paid for separately). With paving
Asphalt grade VG - 10 heated and then mixed with
solvent at the rate of 70 grams per kg of asphalt
CPWD DSR Vol 2 16.33.1
1 1 1 1 Sqm 169.6 169.6
Total 1261.90
Add 12% for GST 151.43
Total 1413.32
Say 1400.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.301
Shimla Jal Prabandhan Nigam Limited Rate Analysis
A
B
C
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
A Water Supply Connections
ROVIDING & LAYING IN TRENCHES
GALVANISED MILD STEEL PIPE CONFORMING
TO IS 1239/1990 (5th Revision) HEAVY CLASS
INCLUDING BENDS OF ALL DEGREES, TEES,
COLLARS, TAPERS, CROSSES, FLANGED
SOCKET & SPIGOTS AND JOINTING
As per RA
i) Residential Connections- 15 mm dia 29 5 145 Rmt 234.99 34073.10835
ii) Commercial Connections- 25mm dia 4 5 20 Rmt 277.61 5552.140228
39625.24858
B Electrical Lines & Poles
B-1 Electrical Poles - RA for 10 km
i)
Pole Foundation : providing cement concrete
foundation including excavation for the pole 60 cms
x 60 cms x 1.5 mtr deep in1:3:6 cement concrete
(20x 25 mm stone metal) and 45 cm x 45cm x45
cm / 45 cm x 45 cm height plinth duly plaster and
with necessary curing & finishing in above manner
( for 9 mtr pole)
1 1 Nos 3158.4 3158.4
PWD DSR 16-17 E&M, Item No. 16.3.2, Page
No.306
ii)
Dismantling of existing poles above 6 mtr height
with brackets. Clamps, insulators stay from the
cement concrete foundation and making the site
clear by refilling the pits with excavated materials
and bringing it to ground level
1 1 Nos 840 840
PWD DSR 16-17 E&M, Item No. 8.8.2, Page No.
191
i)
Re-Erecting: Supplying and erecting steel tubular
swaged pole 165.1 X 139.7 X 114.3 mm dia with
4.5 X 4.5 X3.65 mm thick (5+2+2m) length
respectively and total 9 m long with pole cap, base
plate in provided foundation (weight 147 kg) as per
specifications.
1 1 Nos 13971.3 13971.3
PWD DSR 16-17 E&M, Item No. 8.1.3, Page No.
174
i)
Earthling : Providing pipe type earthing with 40mm.
dia.G.l. pipe or 20 mm dia. G.l. Rod complete with
all materials as per specification No. EA-EP
1 1 Nos 1597.05 1597.05
i)PWD DSR 16-17 E&M, Item No. 9.1.4, Page No.
193
19566.75
1956.675
B-2 Electrical Cable - Providing and Jointing 391.335
CCommunication Cable - Jelly Filled telephone lines
and optical Fibre Cable
i)
Supply & Erecting of Jelly filled armoured
telephone cable 10 pair with 0.5 mm dia laid in
provided trench as per specification no. WG-TW
1 3 3 Rmt 114.45 343.35
PWD DSR 16-17 Item 1-10-10, Page No. 38
RATE ANALYSIS - 17
Utility Shifting:
1 nos of breakage per km occurred with required of cable length per breakage is assumed as 6 m. 3.0 mtr assumed as Optical cable and 3.0
metre Jelly filled telephone cable
Amount A / 1 Km
Amount B-1 /10 km
Amount B-1/ 1 Km
Amount B-2/ 1 Km
Assumptions
Water Supply Connections
Total No. of properties in 1.00 Km length in city Area Consider property connection at 30 mtr distance is 1000/30 = 34 Nos, Assuming that out of 34
Nos 10% are commercial connections and 90% are residential Connections. Commercial connections are of 25mm in size and Residential
connections are 15 mm Size hence Commercial connections are 4 Nos. and Residential Connections are 29 Nos Per Km. Connections Pipe length
per connections are assumed as 2.5 mtr.
Electrical Lines & Poles
For RA purpose, shifting of one pole per 10 km length of network in city area , Hence RA is estimated for 10 km length. Electrical Cable joints
required per km is assumed as 2 nos
Communication Cable - Jelly Filled telephone lines and optical Fibre Cable
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.302
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Nos Item Description Nos Length Breadth Depth Qty Unit Rate Amount
ii)
Supply & erecting of FR grade PVC armourd multi
mode Optical Fibre Cable with 6 fibres with core
dia 50 µM, suitable for 1 GBps Ethernet distance at
850 nm of wavelength on wall/ ceiling or laid in
provided pipe / trench as per specification no. WG-
COC/ OFC
1 3 3 Rmt 236.25 708.75
PWD DSR 16-17 Item 1-12-8, Page No.41
iii)
Supply & fixing of wall /rack type 12 port light guide
interconnection unit for termination of optical fibre
cable on wall /provided U rack complete as per
specification no. EG- NAS / LIU
1 1 Nos 4586.4 4586.4
PWD DSR 16-17 Item 1-14-5, Page No. 44 5638.5
47612.00
57134.40Total rate of utility Shifting per Km considering this project
Total rate of utility Shifting per Km for Maharashtra is
Amount C-1/ 1 Km
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.303
Shimla Jal Prabandhan Nigam Limited Rate Analysis
(a)Foundation footing basis of columns etc and mass concrete
Detail of cost for 10 Sqm.
Sr. Description. Unit Qty. Rate. Amount
Material
Rate as per above in Sub Analysis. Sqm. 10.15200 6174.44 62682.92
Battens IInd class kail wood
6 X 1 X 0.075 X 0.10m. = 0.045 cum.
Wastage @ 5% per kg. = 0.002 cum.
Total Qty:- = 0.047 cum.. Cum. 0.047 33,830.00 1590.01
Ballies 125mm dia Kail wood
6 X 1.50 = 9.00 Rmt.
Wastage @ 5% per kg. = 0.45Rmt.
Total Qty:- =9.45 Rmt. Rmt. 9.45 125.00 1181.25
Carriage of Timber :-
Ballies 125mm dia Kail wood
9.45 X 0.785 X (0.125)2 = 0.116 cum.
Battens IInd class kail wood =0.047 cum.
Total Qty:- = 0.163 cum..
50 K.M.by Mechanical Transport. Cum. 0.163 178.91 29.16
0.5 M.by head load. Cum. 0.163 485.53 79.14
Total Rs:- 2879.56
Carriage cost of wood i.e.1/16 Rs:- 6.77
Each. 0.01 62682.92 626.83
cent 0.01 62682.92 626.83
Cum. 0.0625 2879.56 179.97
Assuming that Timber shall become unservicable after being used 16
times.Hence cost for using once = 1/16
ANALYSIS OF RATES - 18
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Assuming that steel plates shall become unservicable after being used 100
times. Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling oiling and greasing etc.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.304
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
cent 0.05 2879.56 143.98
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.52 292.00 151.84
Beldar. Each. 1.30 250.00 325
Total Rs:- 2054.45
Sundries @ 10% of labour cost. Rs:- 205.445
Total Rs:- 2259.895
Add 10% Contractor profit 225.99
Add 5% Overhead Charges 112.99
Add labour cess @ 1.00 % 22.60
Add 12 % GST 271.192892.67
289.27
d)Columns,Pillar;Posts and struts Square Rectangular and Polygonal in Plan
Sr. Description. Unit Qty. Rate. Amount
Rate as per above in Sub Analysis. Sqm. 5.46 6174.44 33712.44
Ballies 125mm dia.(Kail wood 2nd class.) Meter 15.96 125.00 1995.00
50 Carriage of Timber :-K.M.by Mechanical Transport. Cum. 0.196 178.91 35.07
0.5 Carriage of Timber :-M.by head load. Cum. 0.196 485.53 95.16
Total Rs:- 2125.23
Carriage cost of wood i.e.1/16 Rs:- 8.14
Each. 0.01 33712.44 337.12
cent 0.01 33712.44 337.12
Add 5% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling
Cost for 10 Sq.m
Cost per Sqmt. Rs:-
ANALYSIS OF RATES - 19
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Detail of cost for area in contact 4 X 0.30 X 3.50 = 4.20 Sqm.
Assuming that steel plates shall become unservicable after being used 100
times.Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling oiling and greasing etc.
Assuming that Timber shall become unservicable after being used 16
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.305
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cum. 0.0625 2125.23 132.83
cent 0.05 2125.23 106.26
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.59 292.00 172.28
Beldar. Each. 1.47 250.00 367.50
Total Rs:- 1453.11
Sundries @ 10% of labour cost. On Rs:- 539.78 Rs:- 145.311
Total Rs:- 1598.421
Add 10% Contractor profit 159.84
Add 5% Overhead Charges 79.92
Add labour cess @ 1.00 % 15.98
Add 12 % GST 191.812045.98
487.14
Sr. Description. Unit Qty. Rate. Amount
Material:-
3.15 mm Thick M.S. Plate.
0.90 X 0.60 = 0.54 Sqm.
Weight @ 24.72kg per Sqm. =13.35kg.
Wastage @ 5% per kg. =0.66kg
Total Qty:- =14.01kg or 0.14 Qtl. Qtl. 0.14 4500.00 630.00
Angle iron in frame 30X30X5mm Size
2(0.90+0.60) = = 3.00 Rmt.
Weight @ 2.20kg per Rmt.. =13.35kg.
Wastage @ 5% per kg. =0.33kg
Total Qty:- =6.93kg or 0.0693 Qtl. Qtl. 0.0693 5,000.00 346.50
Cost per Sqmt. Rs:-
times.Hence cost for using once = 1/16
Add 5% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling
Cost for 10 Sq.m
ANALYSIS OF RATES - 20
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for
shuttering steel work welded in built up section I/c cutting fixing in positionin angles,plates etc. Detail of cost for 90cm X 60cm size of plates
complete 0.54 Sqm.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.306
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Sub Total Rs. 976.50 A
Carriage of M.S. Plate and angles.
M.S.Plate. = 0.140 Qtl
Angle iron =0.0693 Qtl.
Total Qty:- =0.2093 Qtl or 0.02093 Tonne.
50 K.M.by Mechanical Transport. Tonne 0.02093 178.91 3.74
0.5 M.by head load. Tonne 0.02093 485.53 10.16
Sub Total Rs. 13.90 B
Labour.
Black Smith Ist. Class. Each 0.066 292.00 19.27
Bandhani Each 0.066 250.00 16.50
Beldar Each 0.154 250.00 38.5
Sundries Each 10
Sub Total Rs. 84.27 C
Welding charges by Electric Plant CM. 300.00 5.00 1500.00 D
Total Rs. (A+B+C+D) 2574.67
Add 1.5% water charges. Rs:- 38.62
Add 10% Contractor profit 257.47
Add 5% Overhead Charges 128.73
Add labour cess @ 1.00 % 25.75
Add 12 % GST 308.963334.20
6174.44
Discription Unit Qty. Rate Amount
Materials
Cost for 0.54 Sqmt.Rs:-
Cost per Sqmt. Rs:-
RATE ANALYSIS - 21
Providing & laying cement concrete 1:2:4, 20mm nominal size & curing complete for RCC work in: Suspended floor, roofs, landing and shelves and their
supports, balconies, beams, girders, bressumers and cantilever upto floor two level.
Details of Cost for 1 Cubic Meter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.307
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Tonne 0.32 5,120.00 1638.40
Sand Cum 0.445 650.00 289.25
10mm stone aggregate Cum 0.22 725.00 159.50
20mm stone aggregate Cum 0.67 725.00 485.75
Subtotal 2572.90 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.89 1875.18 1668.91
0 K.M. by Head Load Cum 0.89 390.34 347.40
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.45 1090.33 490.65
0 K.M. by Head Load Cum 0.45 390.34 175.65
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.32 178.91 57.25
0 K.M. by Head Load Tonne 0.32 230.04 73.61
Subtotal 2813.47 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 693.65 (C)
(A+B+C) 6080.02
Add for water charges @1.5% 6,080.02 1.50% 91.20
6171.22
Add 1% Labour cess 6,171.22 1.00% 61.71
Add GST 12.00% 740.55
Total
Gross Total
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.308
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4532.82 15% 679.92
Rs:- 7,653.40
Unit Qty. Rate Amount
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.165 5,758.44 950.14
Subtotal 950.14 (A)
Labour :
Mason II nd class Each 0.80 294.00 235.20
Beldar Each 0.80 245.00 196.00
Bhishti Each 0.98 245.00 240.10
Sundries(Scaffolding etc.) L.S. 45.00
Subtotal 716.30 (B)
Total (A+B) 1666.44
Add for water charges @1.5% 1,666.44 1.50% 25.00
Gross Total 1691.44
Add 1% Labour cess 1,691.44 1.00% 16.91
Add GST 12.00% 202.97
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement741.30 15% 111.20
Cost for 10 square meter Rs:- 2,022.52
Cost of 1 Sqm. Rs:- 202.25
RATE ANALYSIS - 22
Cost for one cubic meter
20 mm cement plaster in single coat on fair side f brick/stone masonry for interior plastering up to floor two level including arrises, internal rounded angles,
chamfers and/or rounded angles not exceeding 80mm in girth and finished even and smooth .
In cement mortar 1:4
Details of cost for 10 Sqm.
Desciption
RATE ANALYSIS - 23
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.309
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.224 6,592.42 1476.7
Sand & Gravel Crushed stone graded from 6 mm to 12mm Cum. 0.1 725.00 72.5
Grounded hydrated lime Kg 9.28 100.00 928
Subtotal 2477.2 (A)
Labour :
Mason II nd class Each 1.71 294.00 502.74
Beldar Each 1.58 245.00 387.10
Bhishti Each 1.7 245.00 416.50
Sundries(Scaffolding etc.) L.S. 45.00
Extra labour for coping
Mason II nd class Each 0.25 294.00 73.50
beldar Each 0.25 245.00 61.25
Extra labour for dashing of crushed stone
Mason II nd class Each 0.5 294.00 147.00
beldar Each 0.5 245.00 122.50
bhisti Each 0.1 245.00 24.50
Rough side exterior cement plaster on wall up to a height of 10 mtr. above ground level with a mixture of sand and gravel or crushed stone graded from 6mm
to 12 mm nominal size dashed over and including fresh plaster in two coats, backing coat 10 mm cement plaster 1:3 (1cement:3sand) and finishing coat 10
mm cement mortor 1:3 (1cement:3sand) mixed with 10 % finely grounded hydrated lime by volume of cement including arrises, chamfersb and/or rounded
angles not exceeding 80 mm in girth. (natural cement finish using ordinary cement)
In cement mortar 1:3
Details of cost for 10 Sqm.
Desciption
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.310
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
sundries ( scaffolding etc.) 10.00
Subtotal 1790.09 (B)
Total (A+B) 4267.29
Add for water charges @1.5% 4,267.29 1.50% 64.01
Gross Total 4331.30
Add 1% Labour cess 4,331.30 1.00% 43.31
Add GST 12.00% 519.76
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2854.60 15% 428.19
Cost for 10 square meter Rs:- 5,322.56
Cost of 1 Sqm. Rs:- 532.26
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 1875.18 1593.90
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 24
Prov.& laying c.conc. 1:2:4 (1cement:2 sand:4 graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work & reinforcement for
RCC work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level.
Discription
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.311
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 1090.33 463.39
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 178.91 71.56
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 2718.55 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 6361.03
Add for water charges @1.5% 6,361.03 1.50% 95.42
Gross Total 6456.45
Add 1% Labour cess 6,456.45 1.00% 64.56
Add GST 12.00% 774.77
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4408.45 15% 661.27
Cost for one cubic meter Rs:- 7,957.06
Unit Qty. Rate Amount
RATE ANALYSIS - 25
P/L cement concrete 1:1.5:3 (1cement:2sand:4graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work in
suspended floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level.
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.312
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 1875.18 1593.90
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 1090.33 463.39
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 178.91 71.56
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 2718.55 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.313
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 842.12 ( C)
Total (A+B+C) 6501.17
Add for water charges @1.5% 6,501.17 1.50% 97.52
Gross Total 6598.69
Add 1% Labour cess 6,598.69 1.00% 65.99
Add GST 12.00% 791.84
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4550.69 15% 682.60
Cost for one cubic meter Rs:- 8,139.12
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 1875.18 1425.14
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 1090.33 272.58
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 178.91 109.14
RATE ANALYSIS - 26
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work
in suspended floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level. (Slab for For RCC GSR)
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.314
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 2341.43 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 294.00 79.38
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 245.00 12.25
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 0.00 0.00
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 791.65 ( C)
Total (A+B+C) 6969.78
Add for water charges @1.5% 6,969.78 1.50% 104.55
Gross Total 7074.33
Add 1% Labour cess 7,074.33 1.00% 70.74
Add GST 12.00% 848.92
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement3951.13 15% 592.67
Cost for one cubic meter Rs:- 8,586.66
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 27
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work &
reinforcement for RCC work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level. (Wall for For
RCC GSR)
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.315
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 1875.18 1425.14
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 1090.33 272.58
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 178.91 109.14
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 2341.43 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 6880.11
Add for water charges @1.5% 6,880.11 1.50% 103.20
Gross Total 6983.31
Add 1% Labour cess 6,983.31 1.00% 69.83
Add GST 12.00% 838.00
Discription
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.316
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement3860.11 15% 579.02
Cost for one cubic meter Rs:- 8,470.16
Unit Qty Rate Amount
Material:-
Mild Steel Bars Qtl. 1.00
Wastage @ 5% Qtl. 0.05
Total 1.05 Qtl. 1.05 4,500.00 4725.00 (A)
By Mech TransportK.M By Mechanical Transport Tonne 0.105 178.91 18.79
0 K.M ByHead load. Tonne 0.105 485.53 50.98
Subtotal 69.77 (B)
Labour:-
Black Smith Ist class Each 1.00 292.00 292.00
Beldar Each 1.00 245.00 245.00
Sundries LS 10.00
Subtotal 547.00 ( C)
Total (A+B+C) 5341.77
Add for water charges @1.5% 5,341.77 1.50% 80.13
Gross Total 5421.90
Add 1% Labour cess 5,421.90 1.00% 54.22
Add GST 12.00% 650.63
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Steel
696.90 15% 104.54
Cost per Qtl Rs:- 6,231.28
Cost per Kg Rs:- 62.31
RATE ANALYSIS - 28
Providing mild steel/tor steel reinforcement for RCC work includng bending binding and placing in position complete.
Detail of cost for 1 Qtl.
Description.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.317
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:4 ( 1CEMENT : 4SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.38 5,120.00 1,945.60
Sand Cum 1.07 650.00 695.50
Subtotal 2,641.10 (A)
Carriage
Carriage of Sand
106 K.M. by Mechanical Transport Cum 1.07 1090.33 1,166.65
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.38 178.91 67.99
0 K.M. by Head Load Tonne 0.38 230.04 87.42
Subtotal 1,739.72 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 4,656.94
Add for water charges @1.5% 4,656.94 1.50% 69.85
Gross Total 4726.79
Add 1% Labour cess 4,726.79 1.00% 47.27
Add GST 12.00% 567.21
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2781.19 15% 417.18
Cost for one cubic meter Rs:- 5,758.44
Details of cost for 1cum
RATE ANALYSIS - 29
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.318
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:3 ( 1CEMENT : 3SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.51 5,120.00 2,611.20
Sand Cum 1.07 650.00 695.50
Subtotal 3,306.70 (A)
Carriage
Carriage of Sand
0 K.M. by Mechanical Transport Cum 1.07 1090.33 1,166.65
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.51 178.91 91.24
0 K.M. by Head Load Tonne 0.51 230.04 117.32
Subtotal 1,792.87 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 5,375.69
Add for water charges @1.5% 5,375.69 1.50% 80.64
Gross Total 5456.33
Add 1% Labour cess 5,456.33 1.00% 54.56
Add GST 12.00% 654.76
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2845.13 15% 426.77
Cost for one cubic meter Rs:- 6,592.42
RATE ANALYSIS - 30
Details of cost for 1cum
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.319
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 80 mm dia 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including transportation 141583 144910 180046 248238 327866 366120 467786 645336 694402 967589 1100586
Add for jointing material 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Add for laying, jointing labour 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Total 161583.00 164910.00 200046.00 278238.00 357866.00 396120.00 507786.00 685336.00 734402.00 1017589.00 1150586.00
Add 18% for GST 29084.94 29683.80 36008.28 50082.84 64415.88 71301.60 91401.48 123360.48 132192.36 183166.02 207105.48
Add 15% OH and CP 19066.79 19459.38 23605.43 32832.08 42228.19 46742.16 59918.75 80869.65 86659.44 120075.50 135769.15
Rate Including GST 209734.73 214053.18 259659.71 361152.92 464510.07 514163.76 659106.23 889566.13 953253.80 1320830.52 1493460.63
Particulars 80 mm dia 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including transportation 9543 12589 19822 32940 45622 68951 175000 213462 326923 476923
Add for jointing material 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Add for laying, jointing labour 10000 10000 10000 15000 15000 15000 20000 20000 20000 25000 25000
Total 29543.00 32589.00 39822.00 62940.00 75622.00 98951.00 40000.00 215000.00 253462.00 376923.00 526923.00
Add 18% for GST 5317.74 5866.02 7167.96 11329.20 13611.96 17811.18 7200.00 38700.00 45623.16 67846.14 94846.14
Add 15% OH and CP 3486.07 3845.50 4699.00 7426.92 8923.40 11676.22 4720.00 25370.00 29908.52 44476.91 62176.91
Rate Including GST 38346.81 42300.52 51688.96 81696.12 98157.36 128438.40 51920.00 279070.00 328993.68 489246.05 683946.05
Particulars 25 mm dia 50 mm dia 80 mm dia 100 mm dia 150 mm dia Particulars Cost
Basic rate including transportation NA 18991 25312 40474 56360
Basic rate
including
transportation
28651
Add for jointing material 5000 5000 10000 10000 10000
Add for
jointing
material
2000
Add for laying, jointing labour 5000 5000 10000 10000 10000
Add for
laying, jointing
labour
3000
Total 10000.00 28991.00 45312.00 60474.00 76360.00 Total 33651.00
Add 18% for GST 1800.00 5218.38 8156.16 10885.32 13744.80Add 18% for
GST 6057.18
Add 15% OH and CP 1180.00 3420.94 5346.82 7135.93 9010.48Add 15% OH
and CP3970.82
Rate Including GST NA 37630.32 58814.98 78495.25 99115.28
Rate
Including
GST
43679.00
Rate Analysis -34 for Air ValvesRate Analysis -35 for
Pressure Transmitter
Rate Analysis -32 for FCV and PRV
Rate Analysis -33 for Isolation and Scour Valves
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.320
Shimla Jal Prabandhan Nigam Limited Rate Analysis
Particulars 100 mm dia 150 mm dia 200 mm dia 250 mm dia 300 mm dia 350 mm dia 400 mm dia 450 mm dia 500 mm dia 600 mm dia
Basic rate including
transportation98041 105692 125138 138297 158618 219362 249122 266894 310486 357802
Add for jointing
material
Add for laying, jointing
labour
Total 98041.00 105692.00 125138.00 138297.00 158618.00 219362.00 249122.00 266894.00 310486.00 357802.00
Add 18% for GST 17647.38 19024.56 22524.84 24893.46 28551.24 39485.16 44841.96 48040.92 55887.48 64404.36
Add 15% OH and CP 11568.84 12471.66 14766.28 16319.05 18716.92 25884.72 29396.40 31493.49 36637.35 42220.64
Rate Including GST 127257.22 137188.22 162429.12 179509.51 205886.16 284731.88 323360.36 346428.41 403010.83 464427.00
Rate Analysis -36 for Flow (Bulk) Meter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.321
Shimla Jal Prabandhan Nigam Limited M and R
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
1 2020 243250 21818159 2786875 1657750 4444625 0.56
2 2021 248264 23141800 2987328 1740638 4727966 0.56
3 2022 253279 24465441 3202236 1827669 5029905 0.56
4 2023 258293 25789082 3432708 1919053 5351761 0.57
5 2024 263308 27112724 3679716 2015005 5694721 0.58
6 2025 268322 28436365 3944460 2115756 6060216 0.58
7 2026 273337 29760006 4228476 2221544 6450020 0.59
8 2027 278351 31083647 4533000 2332621 6865621 0.61
9 2028 283366 32407288 4859376 2449252 7308628 0.62
10 2029 288380 33730929 5209404 2571714 7781118 0.63
11 2030 293395 35054571 5584692 2700300 8284992 0.65
12 2031 298409 36378212 5987112 2835315 8822427 0.66
13 2032 303424 37701853 6418572 2977081 9395653 0.68
14 2033 308438 39025494 6881280 3125935 10007215 0.7
15 2034 313453 40349135 7377444 3282232 10659676 0.72
16 2035 318467 41672776 7909608 3446343 11355951 0.75
17 2036 324814 43403489 8480316 3618660 12098976 0.76
18 2037 331161 45134202 9092184 3799593 12891777 0.78
19 2038 337508 46864915 9748392 3989573 13737965 0.8
20 2039 343856 48595628 10452156 4189052 14641208 0.83
21 2040 350203 50326341 11206956 4398504 15605460 0.85
22 2041 356550 52057054 12016452 4618429 16634881 0.88
23 2042 362897 53787767 12884532 4849351 17733883 0.9
24 2043 369244 55518480 13815420 5091819 18907239 0.93
25 2044 375591 57249193 14813940 5346409 20160349 0.96
26 2045 381938 58979906 15884760 5613730 21498490 1
27 2046 388285 60710619 17033376 5894416 22927792 1.03
28 2047 394633 62441332 18265164 6189137 24454301 1.07
29 2048 400980 64172045 19586556 6498594 26085150 1.11
30 2049 407327 65902758 21003672 6823524 27827196 1.16
31 2050 413674 67633471 22523724 7164700 29688424 1.2
Hydraulic Design & Network Modelling for Shimla Water Supply
O & M EXPENDITURE STATEMENT
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.322
Shimla Jal Prabandhan Nigam Limited M and R
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2020 3.0 14850 534600 0 12690 0 0 9878 0 19 9878 2252275 2786875
2021 3.0 16038 577368 0 13705 0 0 10570 0 19 10570 2409960 2987328
2022 3.0 17321 623556 0 14801 0 0 11310 0 19 11310 2578680 3202236
2023 3.0 18707 673452 0 15985 0 0 12102 0 19 12102 2759256 3432708
2024 3.0 20204 727344 0 17264 0 0 12949 0 19 12949 2952372 3679716
2025 3.0 21820 785520 0 18645 0 0 13855 0 19 13855 3158940 3944460
2026 3.0 23566 848376 0 20137 0 0 14825 0 19 14825 3380100 4228476
2027 3.0 25451 916236 0 21748 0 0 15863 0 19 15863 3616764 4533000
2028 3.0 27487 989532 0 23488 0 0 16973 0 19 16973 3869844 4859376
2029 3.0 29686 1068696 0 25367 0 0 18161 0 19 18161 4140708 5209404
2030 3.0 32061 1154196 0 27396 0 0 19432 0 19 19432 4430496 5584692
2031 3.0 34626 1246536 0 29588 0 0 20792 0 19 20792 4740576 5987112
2032 3.0 37396 1346256 0 31955 0 0 22247 0 19 22247 5072316 6418572
2033 3.0 40388 1453968 0 34511 0 0 23804 0 19 23804 5427312 6881280
2034 3.0 43619 1570284 0 37272 0 0 25470 0 19 25470 5807160 7377444
2035 3.0 47109 1695924 0 40254 0 0 27253 0 19 27253 6213684 7909608
Hydraulic Design & Network Modelling for Shimla Water Supply
ESTABLISHMENT CHARGES
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.323
Shimla Jal Prabandhan Nigam Limited M and R
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2036 3.0 50878 1831608 0 43474 0 0 29161 0 19 29161 6648708 8480316
2037 3.0 54948 1978128 0 46952 0 0 31202 0 19 31202 7114056 9092184
2038 3.0 59344 2136384 0 50708 0 0 33386 0 19 33386 7612008 9748392
2039 3.0 64092 2307312 0 54765 0 0 35723 0 19 35723 8144844 10452156
2040 3.0 69219 2491884 0 59146 0 0 38224 0 19 38224 8715072 11206956
2041 3.0 74757 2691252 0 63878 0 0 40900 0 19 40900 9325200 12016452
2042 3.0 80738 2906568 0 68988 0 0 43763 0 19 43763 9977964 12884532
2043 3.0 87197 3139092 0 74507 0 0 46826 0 19 46826 10676328 13815420
2044 3.0 94173 3390228 0 80468 0 0 50104 0 19 50104 11423712 14813940
2045 3.0 101707 3661452 0 86905 0 0 53611 0 19 53611 12223308 15884760
2046 3.0 109844 3954384 0 93857 0 0 57364 0 19 57364 13078992 17033376
2047 3.0 118632 4270752 0 101366 0 0 61379 0 19 61379 13994412 18265164
2048 3.0 128123 4612428 0 109475 0 0 65676 0 19 65676 14974128 19586556
2049 3.0 138373 4981428 0 118233 0 0 70273 0 19 70273 16022244 21003672
2050 3.0 149443 5379948 0 127692 0 0 75192 0 19 75192 17143776 22523724
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.324
Shimla Jal Prabandhan Nigam Limited M and R
Sr. No. SubworksNo of
Units
Superinte
ndent
Manager
(A.E.E.)
Supervisor
/Asstt.
Manager
(A.E.)
Assitant
Supervisor/
Junior
manager
Operators Fitters HelpersElectrician/
MechanicWatchman
1 Pump House 0.00 0 0 0 0 0 0 0 0
2 RWRM 0.00 0 0 0 0 0 0 0 0
3 WTP 0.00 0 0 0 0 0 0 0 0
4 PWRM 0.00 0 0 0 0 0 0 0 0
5 ESR/GSR 15.00 0 0 0 0 0 0 0 15
6 Gravity Main 4.00 0 0 0 0 0 0 0 4
7 D/System 0.00 0 0 0 0 0 0 0 0
Automation 1 0 3
0 3 0 0 0 0 0 19
Hydraulic Design & Network Modelling for Shimla Water Supply
Staff Pattern
Total
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.325
Shimla Jal Prabandhan Nigam Limited M and R
Annual M &
R Charges
Annual
Depreciation
(3x8) (5x7)
1 2 3 4 5 6 7 8 9 10
For Proposed Components
1
Providing and Laying of Pipes, Specials,
Valves, Meters for Transmission lines (GI
Pipes (Heavy) 100 mm to 150 mm -
12.203 Km and MSERW Fe 410 Pipes
260.4 mm to 585 mm - 20.313 Km )
369200000 380276000 342248400 50 0.0076 0.0025 923000 2601088
2
Civil Works for Transmission lines (GI
Pipes (Heavy) 100 mm to 150 mm -
12.203 Km and MSERW Fe 410 Pipes
260.4 mm to 585 mm - 20.313 Km )
92500000 95275000 85747500 50 0.0076 0.0025 231250 651681
3 BPT (11 nos ) and Tanks (4 nos) 33900000 34917000 31425300 67 0.0039 0.50% 169500 122559
4Acquisition of Land for various
Reservoirs38400000 39552000 35596800 0 0
5 Plantation 2000000 2060000 1854000 0 0
6 Staff Quarter at 11 BPT and 4 Tanks 45800000 47174000 42456600 67 0.0039 0.50% 229000 165581
7 SCADA (Cloud Based) System 4200000 4326000 3893400 20 0.0354 0.0250 105000 137826
8Operation and Maintenance of the
Transmisson lines for 15 years113800000 117214000 105492600
699800000 720794000 1657750 3678735Total Rs.
Hydraulic Design & Network Modelling for Shimla Water Supply
STATMENT SHOWING ANNUAL M & R CHARGES
Sr.
No.Sub Work Net cost Gross cost
90% of
Gross Cost
Life in
Years
Depreciation
Factor% of M & R
World Bank Project
Client : Shimla Jal Prabandhan Nigam Limited
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.326