3/27/2016 1 Crack filling/sealing Two types of crack treatment Crack Filling: Pavements that are in good condition Working cracks Crack Sealing: Filling non working cracks closely spaced Most cost effective treatment for preventive maintenance PLANNING & SCHEDULING

Transcript of Session 6 - Bauer and Quintana - RMACES

3/27/2016

1

Crack filling/sealing

Two types of crack treatment

Crack Filling: Pavements that are in good condition Working cracks

Crack Sealing: Filling non working cracks closely spaced

Most cost effective treatment for preventive maintenance

PLANNING & SCHEDULING

3/27/2016

2

OVERBANDING

CHIPSEALING

Blowing Cracks

3/27/2016

3

Lighting Heat Lance

3/27/2016

4

Using Heat Lance

3/27/2016

5

3/27/2016

6

3/27/2016

7

3/27/2016

8

3/27/2016

9

Router

CRACK SEALING CHECK LIST

□ Do site inspection/evaluation

□ Do traffic control plan to include speed reduction

□ Schedule equipment and people for job

□ Insure that quantity of crack filler material is on hand

□ Coordinate for Colorado State Patrol support for job

□ Coordinate for press release through Bob Wilson

□ Set out VMS boards to warn public of prior to job

□ Designate Traffic Supervisor and insure flagger certification

□ Schedule heating of material several hours prior to work

□ Schedule tail gate talk

3/27/2016

10

EQUIPMENT

•Tar pot

•Air compressor with heat lance

•2 VMS boards

•Tow vehicle/crack filler hauler

REPORTING

•Material class code

•Activity

•Material quantity reported = pounds

•Accomplishment = gallons

3/27/2016

11

QUESTIONS?

CHIP SEALS

3/27/2016

12

PROPER SHOT RATE

POUNDS PER SQUARE YARD

CLEAN SURFACE AND SHOULDERS

PUSHED BACK

3/27/2016

13

CHIP PILE AND STORAGE

Loading for Chip Seal

Traffic Control

3/27/2016

14

Shot rate even tack coat

Screen Maintenance

3/27/2016

15

Incorrect Nozzles or plugged Screen

Nozzle selection

Single

Double

Triple

Coverage

Spray bar height must be set exactly for proper coverage

3/27/2016

16

Calibrate equipment

• Spray bar height

• Nozzle angle

• Spray bar pressure

Nozzle Angle Setting = 15 - 30°

Spray bar Axis

Proper nozzle angle setting

SPRAY BAR

3/27/2016

17

Depth of asphalt binder just beforechip application

Depth of asphalt binder just afterchip application

Depth of asphalt binder just after rolling

Depth of asphalt binder afterconsiderabletraffic

Backing (GOAL)

3/27/2016

18

Stagger Trucks when backing to help with rolling.

Hookup

3/27/2016

19

Joints

Paper all Joints

Clean joint

3/27/2016

20

Overlap no paper

Keep correct distance from distributor

3/27/2016

21

Roll chips as soon as possible

Blot Truck

3/27/2016

22

Rolling

3/27/2016

23

CHIP CALCULATION GUIDE

DETERMINE:

1. Length of job in feet2. Width of job in feet3. Chip rate (28 lbs by normal estimate factor/starting point)

CALCULATE TONS :

• Length X Width divided by 9 = square yards

• Square yards X Pounds per square yard (28) = pounds

• Pounds divided by 2000 = tons of chips

LIQUID ASPHALT (HFMS2P) CALCULATION GUIDE

DETERMINE:

1. Length of job in feet

2. Width of job in feet

3. Desired shot rate of job (normally .38 to.46 depending on chip size)

CALCULATE GALLONS AND TONS :

• Length X Width divided by 9 = square yards

• Square yards X shot rate (.38) = gallons of oil

• Gallons divided by 238 = tons of oil

CHIP JOB CHECK LIST

□ Do site inspection to do materials estimate□ Do job estimate to insure commission limits are met□ Order and schedule chip deliver (PO)□ Order oil 4 days out (PO)□ Do traffic control plan to include speed reduction□ Schedule equipment and people for job□ Coordinate to sweep job site□ Order and plan tab placement□ Secure and put up job signs and VMS boards□ Coordinate for Colorado State Patrol support□ Coordinate with Bob Wilson for press release□ Identify traffic control supervisor/insure flagger cards□ Schedule to move equipment to job site□ Schedule tailgate talk□ Schedule briefing for traffic control personnel□ Schedule drivers meeting day prior/training talk□ Mark overhead wires□ Monitor weather/2 am call off if poor weather□ Pavement/air temperature: 70 degrees and rising□ Warning letter in mailboxes prior to job□ Arrange for post job sweeping□ Have blotting material on hand□ Have truck with MDSS on site□ Have rosin paper on hand□ Check chipper bar height on all tandems□ Check truck fit (bar and bed) to chipper day prior to job

3/27/2016

24

ORDERING FACTORS

• There are 25 tons per tanker load• One tanker load will normally cover 2 miles/one lane (15 ft)• Order oil 4 days in advance• Confirm order the day before• 1st tanker should be on site at 7 am• Order loads 1.5 hours apart• One tanker normally carries 25 tons/6000 gallons• Normally use 8 tandems with one spare• Oil is polymer modified emulsion CRS-2P• 2000 gallons distributor gets 3.25 pulls from tanker• Oil is 238 gallons per ton/8.4 lbs per gallon• Demurrage is paid 2 hour after scheduled delivery time. Pay attention to arrival

time. Call vendor if truck is late.• Have blotting material on site. Can be sand or crusher fines.• Have rosin paper on hand• Allow 25 minutes to load 2000 gallons• Tab every 4th stripe

EQUIPMENT NEEDED

• Chipper• Roller x 2• Distributor x 2• Dump trucks x 8• Tilt trailer• Broom/side sweep• Tandem with water tank• Loader

MATERIAL REPORTING

• Activity 160• Emulsion= class 13 in gallons• Chips= class 11 in tons

3/27/2016

25

QUESTIONS?