SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded...

65
FRP FABRICATIONS DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-1 SECTION 13230 FIBERGLASS REINFORCED PLASTIC (FRP) FABRICATIONS PART 1 -- GENERAL 1.01 DESCRIPTION This section specifies general requirements for fiberglass reinforced plastic (FRP) fabrications. Equipment-specific requirements are detailed in other sections of the contract documents pertaining to specific equipment. This section is intended to be used in conjunction with the other related equipment specification sections and design drawings. It is intended to specify materials, describe methods of work, and provide for documentation of quality and acceptance. 1.02 QUALITY ASSURANCE Quality, as represented by raw materials used, manufacturing practices employed, and condition of the finished product, is of prime importance. Knowledge of new technology in the interest of improved quality and/or lower cost is welcomed. However, any change of raw materials, alteration of construction, or other deviations from the requirements of the Specification sections or design drawings must be submitted in detail and approved in writing by the Construction Manager. 1.03 REFERENCES A. REFERENCES: This section contains references to the following documents. They are a part of this section as specified and modified. In case of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail. Unless otherwise specified, references to the documents in this section shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid. If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, whether or not the document has been superseded by a version with a later date, discontinued or replaced. Reference Title AISC and Research Council for Riveted and Bolted Structural Joints (RCRBSJ) Specification for Structural Joints Using ASTM A325 or A490 Bolts

Transcript of SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded...

Page 1: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-1

SECTION 13230

FIBERGLASS REINFORCED PLASTIC (FRP) FABRICATIONS

PART 1 -- GENERAL

1.01 DESCRIPTION

This section specifies general requirements for fiberglass reinforced plastic (FRP)

fabrications. Equipment-specific requirements are detailed in other sections of the contract

documents pertaining to specific equipment. This section is intended to be used in conjunction

with the other related equipment specification sections and design drawings. It is intended to

specify materials, describe methods of work, and provide for documentation of quality and

acceptance.

1.02 QUALITY ASSURANCE

Quality, as represented by raw materials used, manufacturing practices employed, and

condition of the finished product, is of prime importance. Knowledge of new technology in the

interest of improved quality and/or lower cost is welcomed. However, any change of raw

materials, alteration of construction, or other deviations from the requirements of the

Specification sections or design drawings must be submitted in detail and approved in writing by

the Construction Manager.

1.03 REFERENCES

A. REFERENCES:

This section contains references to the following documents. They are a part of this

section as specified and modified. In case of conflict between the requirements of this section

and those of the listed documents, the requirements of this section shall prevail.

Unless otherwise specified, references to the documents in this section shall mean the

documents in effect at the time of Advertisement for Bids or Invitation to Bid. If referenced

documents have been discontinued by the issuing organization, references to those documents

shall mean the replacement documents issued or otherwise identified by that organization or, if

there are no replacement documents, the last version of the document before it was discontinued.

Where document dates are given in the following listing, references to those documents shall

mean the specific document version associated with that date, whether or not the document has

been superseded by a version with a later date, discontinued or replaced.

Reference Title

AISC and Research Council for

Riveted and Bolted Structural

Joints (RCRBSJ)

Specification for Structural Joints Using ASTM A325

or A490 Bolts

Page 2: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-2 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

Reference Title

American Institute of Steel

Construction (AISC)

Specification for the Design, Fabrication, and Erection

of Structural Steel for Buildings

AMCA 500 D Laboratory Methods of Testing Dampers for Rating

API 12P, American Petroleum

Institute (API)

Specification for Fiber Reinforced Plastic Tanks

ASME/ANSI RTP-1 Reinforced Thermoset Plastic Corrosion Resistant

Equipment

ASTM C582 Standard Specification for Contact Molded Reinforced

Thermosetting Plastic (RTP) Laminates for Corrosion-

Resistant Equipment

ASTM D883 Definitions of Terms Relating to Plastics

ASTM D2471 Gel Time and Peak Exothermic Temperature of

Reacting Thermoset Resins

ASTM D2563 Recommended Practice for Classifying Visual Defects

in Glass-Reinforced Plastic Laminate Parts

ASTM D2583 Test for Indentation Hardness of Rigid Plastics by

Means of a Barcol Impressor

ASTM D2584 Ignition Loss of Cured Reinforced Resins

ASTM D3299 Filament-Wound Glass Fiber Reinforced Polyester

Chemical-Resistant Tanks

ASTM D3567 Determining Dimensions of Reinforced Thermosetting

Resin Pipe and Fittings

ASTM D3982 Standard Specification for Contact Molded

“Fiberglass” (Glass Fiber Reinforced Thermosetting

Resin) Duct and Hood

ASTM D4097 Contact-Molded Glass Fiber Reinforced Thermoset

Resin Chemical-Resistant Tanks

ASTM E84 Standard Method of Test for Surface Burning

Characteristics of Building Materials

AWS D1.1, American Welding

Society (AWS)

Structural Welding Code

National Bureau of Standards

Voluntary Product Standard

PS 15-69

Custom Contact-Molded Reinforced-Polyester

Chemical Resistant Process Equipment

Iron and Steel Society Pocketbook of Standard Steels

IBC International Building Code

IMC International Mechanical Code

Page 3: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-3

1.04 DEFINITIONS

The terminology of this specification is consistent with ASTM D883. Fabricators are

responsible for correct interpretation. Further definitions are as follows:

1. EQUIPMENT: The FRP equipment, as listed in the pertinent equipment

section, including all ancillary equipment, work, and materials as described in this section and

related sections specification.

2. FABRICATOR: The primary party responsible for fabrication of the FRP

equipment.

3. FIELD JOINING CONTRACTOR: The party responsible for the field

joining of the equipment. This may be the same party as the Fabricator and/or the Contractor.

4. MAT: A fibrous material consisting of randomly oriented chopped or

swirled glass filaments loosely held together with a binder.

5. CHOPPED GLASS: A fibrous material consisting of randomly oriented

chopped filaments applied directly to a mold surface or laminate under construction by a chopper

gun.

6. FIBER PROMINENCE (JACKSTRAW): The distinct visibility of

individual glass strands causing a loss of translucency of the laminate.

1.05 SUBMITTALS

Submittals shall be provided in accordance with Specification Section 01300. Submittal

requirements for FRP fabrications are detailed in those specification sections pertaining to

specific equipment.

PART 2 -- PRODUCTS

2.01 GENERAL

All products shall be new, of current design, and produced by approved manufacturers

who specialized in the fabrication of such products.

Stainless steel hardware and fabricated parts (including anchor bolts, anchor lugs, lifting

lugs, hangers, etc.) shall be AISI Type 316.

Gaskets for use with FRP flanges shall be flat, full-faced, and drilled to match the drilling

of the mating flange(s). Gasket material shall be as specified in the pertinent equipment section.

Page 4: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-4 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

2.02 MATERIALS

A. RESIN:

The equipment shall be fabricated using the corrosion-resistant resin(s) specified in the

pertinent equipment section, or equal as approved by the Construction Manager. The resin shall

be used throughout all laminates.

Catalysts and promoters shall be of the type and amount recommended by the resin

manufacturer for use with their resin in the required service. The Construction Manager will

review the Fabricator's choice of resin/catalyst before fabrication begins to verify compliance to

the resin manufacturer's recommended procedures. Positive measurement control of catalysts,

promoters, and resins shall be maintained at all times.

No fillers, additives, or pigments shall be employed in the resin except as specified

below, and in the pertinent equipment section. A thixotropic agent for viscosity control may be

used in the proportion and type recommended by the resin manufacturer as approved by the

Construction Manager. No thixotropic agent is to be used in the corrosion liner or on surfaces to

be in contact with the corrosive environment.

Resin putty shall be made using the same resin as was used in the original fabrication of

the parts to be joined. Resin putty shall contain a minimum 15 percent by weight of milled glass

fibers. A fumed-silica additive such as Aerosil 200 or Cab-O-Sil TS-720 shall be added to

increase the viscosity of the putty. The use of silica flour, grinding dust, or other fillers is not

allowed.

When specified in the pertinent equipment section, antimony trioxide or antimony

pentoxide shall be added to the resin in the amount necessary to achieve the required fire

retardancy rating in the structural wall only. Resin manufacturer's recommendations shall be

followed. The corrosion liner shall not contain this additive.

B. REINFORCEMENT:

Type and sequence of reinforcement to be used shall be as designated in the pertinent

equipment section, the construction details, or on the design drawings.

Glass fiber reinforcement used shall be a commercial grade corrosion-resistant

borosilicate glass, except as otherwise noted.

All glass fiber reinforcing shall have an epoxy compatible silane type surface finish and

binder that is specifically recommended by the glass manufacturer for the particular resin system

to be used. This surface finish should allow the maximum possible chemical bonding between

the resin and glass.

Page 5: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-5

Surfacing veils shall be Type C (chemical grade) glass, 10 mil thickness, unless

otherwise specified. An apertured polyester surfacing veil, such as Nexus or approved equal,

shall be used only when indicated in the pertinent equipment section. The Construction Manager

is not aware of an equal product.

Mat shall be Type E (electrical grade) glass, 1-1/2 oz. or 3/4 oz. per sq. ft., as specified in

the pertinent equipment section, with nominal fiber length of 1.25 +0.75 inches.

Continuous glass roving used in chopper guns for spray-up shall be Type E chopper

roving.

Woven roving shall be 24 oz. per sq. yd. Type E glass and have a 5 x 4 plain weave.

Continuous roving used in filament wound construction shall be Type E glass winder

roving with a yield of 200 yards or more per pound.

Unidirectional reinforcement shall be weft unidirectional fabric, Type E glass, 15.7

oz./sq. yd., such as Hexcel Knytex, Brunswick Technologies, Inc., W-16, or equal.

2.03 FABRICATION

A. MOLDS:

Molds constructed of Masonite, wood, or other porous material must be completely

covered with mylar or other suitable material to produce a smooth and glossy inner surface on

the FRP equipment.

Molds and mandrels shall be hard-surfaced such that working the wet laminate will not

cause local displacement of the material or air entrapment. Covering of mandrels with cardboard

is not acceptable. If submitted, Contractor shall demonstrate that it produces an RTP-1 Level 2

liner quality before being approved by the Construction Manager prior to start of fabrication.

Certain construction details shown on the design drawings assume the availability of

specific tooling and/or molds. Alternate mold configurations may be considered by the

Construction Manager in the interest of cost savings or betterment. Any deviations from the

dimensions shown on the design drawings must be approved by the Construction Manager prior

to the start of fabrication.

B. VESSEL ASSEMBLY:

All cutouts from the equipment are to be marked, indicating their original location, and

retained. All cutouts become the property of the Construction Manager.

Centerlines marked on the equipment for use in assembly shall not be removed until after

inspection by the Construction Manager.

Page 6: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-6 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

Flanged nozzles shall be installed with boltholes straddling principle centerlines of the

vessel. For tank tops, nozzle boltholes straddle radial centerlines. Other layouts take precedence

when detailed on the design drawings.

When requested, Fabricator shall supply to the Contractor, at the earliest possible time, a

template which locates anchor bolt holes within +1/8-inch for each vessel.

When specified, or indicated on the design drawings or construction details of the

pertinent equipment section, a non-skid surface shall be provided on the exterior surface of

domed covers. Silica grit may be applied in conjunction with the final resin coat, or other

methods employed if approved by the Construction Manager.

The Fabricator shall furnish and overlay on the outside of the equipment a plastic

nameplate showing the following information:

1. Name of manufacturer

2. Date of manufacture

3. Construction Manager's purchase order number

4. Equipment name/number

5. Resin number and manufacturer

6. Design pressure and temperature

7. Vessel diameter, height, and weight

Butt joints or shell joints are to be in the number and location(s) as shown on the design

drawings. Additional joints are not allowed except as approved by the Construction Manager.

Slip joints, "mod joints," or other methods not conforming to the design drawings are not

allowed. If joint locations are not indicated on the design drawings, Fabricator shall propose

number and location for approval by Construction Manager.

Allowable tolerances shall be as listed in RTP-1, Fig. 4-1 and NM 7-1, except as

modified herein or on the design drawings.

When joining components, gaps at mating edges shall be limited to 1/4-inch maximum,

and misalignment of inside surfaces shall not exceed 1/3 of the lesser wall thickness.

The outside surface of vessel flat bottoms after assembly shall be flat within +1/2-inch.

In addition, localized indentations or protrusions shall not exceed +1/4-inch within two feet.

Nozzle cutout reinforcement shall be applied as specified on the design drawings.

When reinforcing materials are cut to facilitate placement around an installed nozzle or

opening, joints in successive reinforcing layers shall be staggered to avoid overlapping and shall

not be placed so that the joints are parallel to the axis of the tank. The principal fiber direction of

the woven roving reinforcement shall be parallel to the tank axis.

Page 7: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-7

C. DUCTWORK ASSEMBLY:

Centerlines marked on the equipment for use in assembly shall not be removed until after

inspection by the Construction Manager's representative.

Fabricator shall apply and overlay an identification tag on each duct spool, straight duct

length or other equipment, showing the following information:

1. Name of manufacturer

2. Date of manufacture

3. Contractor’s purchase order number

4. Resin identification

5. Duct diameter

6. Laminate thickness

7. Unique spool identification number

Tolerances on spool assembly shall be as follows, except as otherwise noted on the

drawings:

1. Diametral, including out of roundness, shall be +1/8-inch or +1 percent,

whichever is greater.

2. Tolerance on overall length and location of tees and laterals shall be +1/4-

inch.

3. Plain ends shall be cut square with the duct axis +1/8-inch.

4. Flanges shall be perpendicular to the axis of the duct within 1/2 degree,

and shall be flat to +1/32-inch up to and including 16-inch diameter and

+1/16-inch for larger diameters.

5. Tolerance on the specified angle for tees, laterals, and miters shall be +1/2

degree.

All cutouts from the equipment are to be marked, indicating their original location, and

retained. All cutouts become the property of the Construction Manager.

1. CUT LENGTHS: Construction Manager prefers straight duct to be

supplied to required lengths with a minimum of shop butt joining of shorter lengths.

Recognizing that waste can be minimized by joining shorter sections, or that mandrels may be

limited to 20 ft., shop butt joints will be allowed within reason.

2. DUCT MARKING: All lengths of duct shall be identified in accordance

with the requirements of paragraph 13230-2.03 C2 above. If required by the Construction

Manager, Fabricator shall return a marked-up copy of the layout drawings, with Mark numbers

referenced.

Page 8: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-8 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

D. ALL LAMINATES:

Refer to the pertinent equipment section for reinforcement sequences. No deviations in

number or sequence of plies will be allowed without approval by the Construction Manager.

Positive methods shall be used to assure uniform total thickness of the laminate and

uniform glass-to-resin ratio without surplus resin or unsaturated glass.

All laminate thicknesses shown on the design drawings are construction minimums. It is

the responsibility of the Fabricator to verify that minimum thicknesses are obtained using the

laminate sequences specified.

The minimum allowable structural laminate thickness shall be the total laminate

thickness less the specified sacrificial corrosion liner thickness.

Interruptions in laminating sequence should only occur after exotherm plies (E or e), as

described in the pertinent equipment section. If an exotherm interruption becomes otherwise

necessary, it shall follow the application of a ply of mat and be succeeded by a ply of mat. This

may require an additional ply beyond that specified.

Laminating sequence interruptions shall not exceed 24 hours, and the in-process surface

must retain acetone sensitivity until laminating is resumed. Lack of compliance with these

procedures, or any indication that contamination of the surface has occurred, shall require that

surface preparation be accomplished before resuming. Before resuming lamination, any rough

areas or projections shall be touch-ground to allow full contact of the succeeding wet laminate.

An exotherm interruption is specifically prohibited within the corrosion liner. An

exotherm interruption between the corrosion liner and the structural layers is limited to a

maximum of twelve hours.

Chopped strand glass applied by chopper gun is allowed in lieu of mat layers in the

structural laminates only. Application must be mechanically controlled in order to assure

uniform thickness and glass-to-resin ratio. The specific methodology must be approved by the

Construction Manager prior to fabrication. Chopper gun application of the corrosion liner is not

allowed.

All non-mold surfaces shall be coated with resin containing wax additive in the amount

necessary to allow full cure of the surface. In the case of interior primary corrosion surfaces,

such as interior overlays, this wax coat shall be applied within 24 hours of original lamination.

In the case of exterior surfaces, this wax coat shall also contain a UV stabilizer in the type and

amount recommended by the resin manufacturer.

The exterior surface of all equipment shall be resin rich and reinforced with one layer c-

glass surfacing veil, except as otherwise specified.

Page 9: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-9

When specified in the pertinent equipment section, the exterior coat shall be an opaque

pigmented surface coat, applied only after Construction Manager's inspection. Color to be

selected by the Construction Manager.

Saturation of reinforcement prior to application to equipment shall not be performed on

waxed paper or other contaminated material. Saturation of reinforcement on clean paper or

cardboard is allowed.

All cut edges shall be thoroughly coated with resin so that no glass fibers are exposed.

Cut edges exposed to the corrosive service shall be sealed with a corrosion liner laminate. All

voids shall be filled with resin putty.

E. CORROSION LINER LAMINATES (inner surface and interior layers):

The inner (corrosion service) surface of all laminates shall be resin-rich and reinforced

with surfacing veil of the type and number of layers as described in the pertinent equipment

section.

The interior layer of the corrosion liner shall consist of 1-1/2 oz. per sq. ft. mat in the

number of layers specified in the pertinent equipment section. Each ply shall be rolled separately

to remove entrapped air.

Chopped glass applied by chopper gun is not allowed in the corrosion liner.

All plies of the inner surface and interior layer are to gel completely before proceeding

with the structural laminates, but in no case shall the interruption exceed twelve hours. The

surface must retain acetone sensitivity until the structural laminate is applied. Lack of

compliance to either of these aspects shall be cause for rejection of the corrosion liner.

Completed corrosion liner, as described above, shall contain not less than 20 percent nor

more than 30 percent glass (by weight). No thixotropic material shall be used in the liner resin

nor in the fabrication of any FRP components intended for direct contact with the process stream.

Completed liner shall be the minimum thickness specified in the pertinent equipment section.

Completed liner shall meet visual defects requirements of RTP-1, Table 6-1, Level 2.

All edges of surfacing veils in wet lay-up shall be lapped a minimum of one inch.

A separately cured unreinforced gel coat shall not be used.

Antimony shall not be used in the corrosion liner.

F. HAND-LAYUP STRUCTURAL LAMINATES:

The corrosion liner laminate shall be followed by structural laminates of varying

construction types, as specified in the pertinent equipment sections, or on the design drawings.

Page 10: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-10 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

For hand-layup structural laminates, reinforcement shall consist of mat and woven roving

in the sequence specified in the pertinent equipment section.

All woven roving shall have a ply of mat on each side. Two adjacent plies of woven

roving are not permitted.

All edges of woven roving material in wet lay-up shall be lapped a minimum of two

inches. Lapped edges of adjacent layers shall be staggered to obtain the maximum possible

strength.

Laminates containing primarily 1-1/2 oz. per sq. ft. mat layers in conjunction with woven

roving shall contain not less than 35 percent or more than 45 percent glass (by weight).

Laminates containing primarily 3/4 oz. per sq. ft. mat layers in conjunction with woven

roving are considered to be high strength laminates and shall contain not less than 45 percent or

more than 55 percent glass (by weight).

G. FILAMENT WOUND STRUCTURAL LAMINATES:

The corrosion liner laminate shall be followed by structural laminates of varying

construction types, as specified in the pertinent equipment section, or on the design drawings.

For filament wound structural laminates, reinforcement shall consist of continuous strand

fiberglass roving applied with a minimum of interruptions until the specified minimum thickness

is attained. This laminate shall contain the percentage of glass (by weight) specified in the

pertinent equipment sections.

Each complete cycle of filament winding shall form a closed pattern of winding bands

which completely covers the surface with two bi-directional layers. Each layer shall be a

maximum of one roving in thickness. Singular cycles shall not exceed a thickness of 0.06

inches, unless otherwise specified in the pertinent equipment sections. In laminates with helix

angles greater than 75 degrees, a minimum 10% of the structural wall thickness shall be oriented

at 0 degrees (longitudinal direction), plus or minus 5 degrees.

Upon request, Fabricator shall submit the following information:

1. Specific glass strand to be used and yield

2. Net thickness per cycle

3. Number of strands per inch in the winding band

4. Typical glass-to-resin ratio

Construction Manager retains the right to modify the laminate based on fabricator's

specific filament winding system.

Page 11: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-11

Spacing of filaments within the winding band shall be sufficiently close that bridging is

avoided and glass content is maintained within the specified limits. Spacing of the filaments

shall be uniform across the winding band without bunching or gapping.

The helix angle of winding shall be as specified in the pertinent equipment sections, as

measured from the centerline of revolution of the equipment shell.

Tolerance on helix angle is +2 degrees, -2 degrees, unless otherwise noted in the pertinent

equipment sections.

If layers of mat or chopped glass are needed to ensure proper bonding between the

corrosion liner and filament winding, or within the filament winding to accommodate the

fabricator's manufacturing methods, or to provide for laminates of acceptable quality, they may

be added at the Fabricator's option. These layers are considered to be extra material and will

result in a thickness greater than specified. The amount of filament winding and unidirectional

roving specified must still be applied.

If for any reason, winding is interrupted to the point where the outer surface is gelled or

exotherm temperatures are excessive, production shall stop and the laminate shall be allowed to

cure. Any prominent ridges left on the cured surface shall be ground to smooth the projections

and prevent bridging. Following the grinding, a bedding layer of 3/4 oz. per sq. ft. mat or

chopped glass shall be applied and thoroughly rolled to remove air. Winding with continuous

strand may be resumed before this layer gels. The additional mat layer is extra material and will

result in a wall thickness greater than that specified.

H. SURFACE PREPARATION:

1. SURFACE ABRASION:

a. Prior to starting secondary overlays, adequate surface abrasion

with no surface contamination is required. Every precaution shall

be taken to assure adequate surface preparation and a good bond of

the secondary overlays.

b. Prior to making all overlays, the cured or wax coated surfaces of

the area to be overlayed must be roughened thoroughly by

grinding. The roughened area shall extend 1-inch minimum

beyond the proposed overlay edge. The roughened area must be

completely coated with wax coat at the completion of the joint.

c. Grinding shall be sufficiently deep that all traces of glossy resin

coat are removed and that glass fiber is exposed over the entire

abraded surface.

d. The edges of the abraded surface shall be "feathered" out such that

no sharp discontinuities exist.

Page 12: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-12 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

e. For surface abrasion by grinding, grinding disks shall be new and

not contaminated, with a grit size of 16 to 24.

f. FRP joint application must begin within four hours of surface

abrasion, or else abrasion must be repeated.

2. FINAL SURFACE PREPARATION:

a. Within 15 minutes prior to beginning FRP joint application, dust

shall be removed from the abraded area by vacuuming or brushing

with clean non-metallic brushes, or wiping with clean dry rags.

b. Solvent wiping the abraded area is not allowed.

c. Air blowing the abraded area is not allowed.

d. If any indication of contamination is present after this final surface

preparation, the abraded area shall be scrubbed with solvent and

allowed to evaporate to verify removal of the contaminant. Repeat

this solvent wash if necessary. Surface abrasion must be repeated

after solvent washing.

I. JOINING LAMINATES:

FRP joining laminates are subject to all applicable requirements specified in other

sections for laminates.

FRP joints shall be reinforced with an overlay of glass reinforcement and resin which

extends equally within +1/2-inch on each side of the joint. A smooth contour is required.

Minimum thickness, ply sequence, and ply widths of FRP joints shall be as specified in the

pertinent equipment sections.

Tolerance on width of joint reinforcement plies is +1 inch, -0 inch. Woven roving plies

shall not exceed the width of the mat ply below them.

Parts to be joined shall be restrained to prevent movement until completion and cure of

the joint overlay.

Parts shall be fitup, and it shall be verified that all tolerances and assembly requirements

of sections are satisfied. The void between component parts shall be completely filled with resin

putty, taking care not to extrude an excessive amount of putty into the interior.

The puttied area shall be ground to a smooth contour and final surface preparation

repeated.

Page 13: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-13

The abraded area to be overlaid shall be resin coated immediately prior to applying glass

reinforcement, using a stiff brush to work resin into the rough surface. The resin coat shall be

applied only to an area as wide (+1 inch, -0 inch) as the next exotherm stage of the joint

sequence and shall be repeated prior to each exotherm stage. No thixotropic material shall be

used in this resin.

J. ENVIRONMENT:

It is the Fabricator's responsibility to maintain conditions in the FRP laminate work area

during all times when the final surface preparation and FRP laminate application are in process

in order to not jeopardize the reliability of the laminate or secondary bond. As a minimum,

controls shall include the following.

All surfaces to be overlaid and all materials are to be maintained within a range of 60 to

95 degrees F. This temperature must also be at least 5 degrees F greater than the dew point, as

measured with a sling psychrometer. During the exotherm stage(s) of each laminate sequence,

and during any unplanned exotherms, the temperature of the curing laminate will likely exceed

95 degrees F. No further lamination may proceed until the exotherm has completed and the

laminate has cooled to 95 degrees F or less. No attempt shall be made to cool the curing

laminate prematurely.

Prepared surfaces and materials shall be protected from blowing dust, moisture, and other

contaminants.

If any of the above conditions are violated while the final surface preparation or FRP

laminate application are in-process, work shall stop immediately and the process must begin

again with surface abrasion.

Materials shall be stored in a dry area and within the temperature and humidity limits

recommended by the manufacturers.

K. FLANGES:

Except as otherwise specified on the design drawings, flanges shall be made by hand-

layup construction with nozzle neck and flange made integrally in one piece and fabricated in

accordance with the dimensions shown on the design drawings. All layers of reinforcement in

the nozzle neck and hub shall extend uninterrupted into the flange.

Unless otherwise noted on the design drawings, additional hub thickness shall be built-up

using alternating layers of 1-1/2 oz. per sq. ft. mat and 24 oz. per sq. yd. woven roving.

Additional thickness in the flange shall be built-up using "ring" cutouts of mat, evenly

distributed throughout the flange thickness.

Press molded or filament wound flanges are not allowed.

Page 14: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-14 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

To obtain proper seating, bolt holes shall be spotfaced for SAE size washers. Overall

machine facing of the back of flanges is not permitted. Bolt holes and all other cut surfaces shall

be resin coated. Spotfacing shall not produce a flange thickness less than that specified in the

pertinent equipment section.

Bolt holes in flanges are to straddle principal centerlines of the equipment. Tolerance in

bolt hole locations and in diameter of bolt circle shall be +1/16-inch.

Flange faces shall be flat to +1/32-inch up to and including 16-inch diameter and +1/16-

inch for larger diameters.

Resin coat all flange bolt holes so that no fibers are exposed.

2.04 FABRICATION QUALITY CONTROL

A. ALLOWABLE VISUAL DEFECTS:

Fabricator shall take care to minimize the amount of defects in all laminates. In no case

shall visual defects in any area of the equipment exceed the maximum allowable levels of visual

defects set forth in RTP-1, Table 6-1, Level 2.

Visual defects shall be as defined in ASTM D2563 and ASME/ANSI RTP-1, Table 6-1.

Presence of visual defects in excess of the allowable levels shall be grounds for rejection

of the equipment.

B. FRP FABRICATION:

Fabricator shall be responsible for implementation of a comprehensive quality assurance

procedure. The minimum requirements are described below.

Fabricator shall designate personnel to inspect equipment while in-process and after

completion to assure compliance to all aspects of the specification and design drawings.

Inspection shall include, as a minimum, checks for visual defects, laminate thickness and

sequence, glass content, Barcol hardness, dimensional tolerances, adherence to construction

details, surface preparation, and environmental conditions. Fabricator's inspector shall complete

a report of the findings including method of measurement for each separate assembly.

Prior to use of any resin, Fabricator shall test resin to establish cure characteristics and

verify that it meets the resin manufacturer's acceptance standards.

Resin testing shall be performed in accordance with ASTM D2471. Gel time to peak

exotherm and peak exotherm temperature shall be recorded.

Page 15: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-15

If the Fabricator in any way alters the resin after receipt, such as through the addition of

styrene, promoters, or other additives, one test shall be performed for each drum or portion

thereof mixed with additives.

Fabricator shall provide documentation for each test, including resin type, manufacturer,

batch and lot number, drum number, complete listing of all additives with amounts added, and

description and manufacturer of each additive.

Fabricator shall inspect all glass reinforcement prior to use in fabrication and shall not

use any glass that does not meet the manufacturer's acceptance standards. Glass material that is

wet or has been wet shall not be used. For each type of glass and lot number used, Fabricator

shall record the manufacturer, product description, binder type, product code, production date,

and lot number. For mat, woven roving, unidirectional roving, and cloth, records shall also

include actual measured weight per square yard of material.

Fabricator shall retain all nozzle cutouts and other excess laminate, clearly marking each

piece to identify its original location. These laminate samples become the property of the

Construction Manager. For areas where valid laminate samples are not available, sample plugs

shall be taken at the Construction Manager's request. Repair of subsequent holes will be

performed in a manner approved by the Construction Manager.

Fabricator shall verify glass content of corrosion liner and structural laminate on

available samples in accordance with ASTM D2584. This test shall be completed, and the

results reported for each major component where samples are available.

Prior to final shipment of the equipment, Fabricator shall provide the Construction

Manager with a complete quality control report, consisting of copies of all records maintained

for compliance with this section.

C. CONSTRUCTION MANAGER'S INSPECTION:

The Construction Manager shall be permitted access to the equipment during fabrication

and upon completion for the purpose of verifying compliance to the contract documents. The

Construction Manager's inspection is not intended to replace the Fabricator's own quality control

procedures.

In no respect does inspection of any equipment by the Construction Manager relieve the

Fabricator of compliance with the contract documents. A final inspection shall be performed by

the Construction Manager when the Fabricator certifies that all the terms and requirements of the

contract documents have been satisfied. At least five days notice shall be given the Construction

Manager prior to this inspection.

The Fabricator is required to notify the Construction Manager at the completion of

particular milestones during fabrication. The Fabricator shall give at least 48 hours notice prior

to occurrence of these milestones, as follows:

Page 16: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-16 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

1. View tooling prior to fabrication

2. Beginning application of corrosion liner for each part

3. Extraction of each part prior to beginning assembly

4. Upon completion of each separate assembly

Construction Manager reserves the right to include additional milestones.

In the event the equipment is not to the stage of completion designated for a milestone

inspection or is not complete as required for a final inspection at the time specified by the

Fabricator, the Fabricator agrees to assume the cost of the inspector's time and expenses and

further agrees that such charges be deducted from the cost of the equipment.

Construction Manager shall be allowed to photograph the equipment while in-process

and/or upon completion.

Construction Manager retains the right to employ the use of magnification or other

special viewing or measurement devices during inspection.

At the time of final inspection, the Fabricator shall assure that the equipment is cleaned of

all foreign material and workings which might block the view of the Construction Manager. The

equipment shall be in a position that allows for easy access and viewing and, at the request of the

Construction Manager, shall be moved to allow viewing of all parts of the equipment.

Evidence of poor workmanship or lack of compliance with any aspect of the contract

documents will be grounds for rejection of the equipment.

Subsequent repair of rejected equipment may, at the Construction Manager's option, be

undertaken in an attempt to bring the equipment to an acceptable state. Repair procedures must

be approved by the Construction Manager prior to implementation.

D. CONSTRUCTION MANAGER'S ACCEPTANCE:

The Construction Manager may employ destructive testing, such as ultimate tensile or

flexural strength tests or glass content ignition tests, on available samples or use other non-

destructive test methods, such as acoustic emission or ultrasonic polygauge thickness

measurement, on the completed equipment for verification of compliance to the contract

documents.

Testing performed by the Construction Manager shall be accomplished through use of

applicable ASTM test methods when appropriate.

Hardness tests shall be made for acceptance by the Construction Manager on the liner

surface using the Barcol impressor, Model GYZJ 934-1, calibrated at two points in accordance

with ASTM D2583. Ten readings will be taken in a localized area, deleting the two highest and

two lowest, and averaging the remaining six. Minimum acceptable Barcol hardness will be a

reading of 30, unless otherwise specified in the pertinent equipment section.

Page 17: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-17

An acetone sensitivity test shall also be performed by the Construction Manager as an

acceptance criterion. Evidence of a sticky or tacky surface following rubbing with an acetone-

saturated cloth shall be grounds for rejection of the equipment.

2.05 SHIPPING

A. VESSELS:

The Fabricator shall be responsible for proper packaging, loading, and protection of all

materials to prevent transit and handling damage.

All equipment which is shipped in a horizontal position shall be mounted on padded

cradles contacting at least 120 degrees of the vessel circumference. All end blocking used to

prevent shifting of equipment must be padded.

Equipment shall be loaded with a minimum clearance of two inches between pieces

(including external fittings, nozzles, or other projections) and the bed of the car or truck. When

two or more units are shipped together, sufficient clearance shall be provided between units to

prevent contact in transit.

Flange faces shall be protected by coverings of suitable plywood or hardboard, securely

fastened.

Loose parts such as fasteners, gaskets, and accessory fittings shall be packaged securely

to allow storage under field conditions.

All dry FRP field joining materials shall be precut in the shop and layered in order of

laminate sequence, then labeled and packaged in sealed, moisture-proof containers for shipment.

When a number of loose items or field joining materials are packed in larger shipping

crates, each crate will be individually marked or tagged as to its contents, clearly listing number

and type of each item contained therein.

B. DUCTWORK:

The Fabricator shall be responsible for proper packaging, loading, and protection of all

materials to prevent transit and handling damage.

All ducts shall be supported for shipment on cradles spaced no greater than 20 feet. Duct

lengths shall also be supported by cradles within two feet of the duct end.

Cradles used to support duct or other equipment during shall contact at least 120 degrees

of the circumference, be padded and match the outside diameter within +1/8-inch, -0 inch.

Page 18: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-18 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

If duct is stacked in layers, cradles shall be used which support each piece of duct

independently from the overlying and underlying equipment, such that no duct in a cradle carries

more than its own weight.

Duct ends and flange faces shall be protected by covering with suitable material which is

securely fastened.

If duct is gelcoated or painted, it shall be wrapped with foam or bubble wrap to protect

finish during shipment.

Equipment shall be loaded with a minimum clearance of two inches between pieces

(including external fittings, nozzles, or other projections) and the bed of the car or truck.

Loose parts such as fasteners, gaskets, and accessory fittings shall be packaged securely

to allow storage under field conditions.

When a number of loose items are packed in larger shipping containers, each container

will be individually marked or tagged as to its contents, clearly listing number and type of each

item contained therein.

2.06 HANDLING FRP EQUIPMENT

The equipment shall not be rolled, slid, dropped, allowed to swing into other objects, or

forced out of shape. Resulting impact and excessive distortions may cause cracking or crazing.

When working in or around FRP equipment, care should be exercised to prevent tools,

scaffolding, or other objects from striking or being dropped on or inside the equipment. Soft-

soled shoes should be worn by workers entering the equipment.

Proper rigging and hoisting practices shall be observed at all times.

The use of a crane is recommended both in lifting and positioning the equipment.

Ideally, the slings or cables attached to the equipment should lift as nearly vertical as possible,

and shall under no circumstances shall slings or cables lift more than 45 degrees from vertical. A

spreader bar (lifting fixture) may be necessary to keep the lifting angle within this range.

Lifting lugs in most cases are not designed to accommodate lifting vessels in or from the

horizontal position. Nylon slings encircling the tank should be used for this purpose and for

righting the vessel to the vertical position.

Unless otherwise specified, use all lifting lugs, loaded uniformly for lifting vessels in the

vertical position. The use of spreader bars is recommended to keep loads on lugs as nearly

vertical and uniform as possible.

Page 19: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13230-19

When lifting lugs are not provided, and it is necessary to use lifting slings in direct

contact with the FRP equipment, the slings shall be woven nylon or canvas at least 3 inches

wide. Care must be taken to assure that shackles, eyes, hooks, or other objects do not come into

contact with the FRP equipment.

Do not attach lifting slings or cables to (nor allow them to come in contact with) any

nozzles, flanges, gussets, or fittings other than lifting and/or anchor lugs.

PART 3 -- EXECUTION

3.01 GENERAL

FRP specialties shall be shipped, installed, joined and erected under the direction of

factory-trained specialists. Where jointing is required, workers employed for these efforts shall

have been trained in proper jointing techniques by the Fabricator. Fabricated equipment shall

have the warning, "Plastic Equipment Handle with Care" stenciled on two sides in letters a

minimum of 2 inches high.

3.02 ASSEMBLY AND ERECTION PLANS

Prior to assembly and erection of FRP towers, tanks, stacks and similar structures, the

Contractor shall provide assembly and erection plans prepared by the Fabricator. The plans shall

provide details on handling, field connections and final installation.

** END OF SECTION **

Page 20: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP FABRICATIONS

13230-20 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

THIS PAGE INTENTIONALLY LEFT BLANK

Page 21: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-1

SECTION 13234

FIBERGLASS REINFORCED PLASTIC (FRP) DUCTWORK

PART 1 -- GENERAL

1.01 SUMMARY

A. SCOPE:

This section specifies fiberglass reinforced plastic (FRP) ductwork. Unless specified

otherwise, all ductwork shall be filament wound construction.

B. STANDARDS:

The requirements of Section 13230 shall apply to all aspects of this specification section.

In cases of conflict, this section shall take precedence over Section 13230.

1.02 SERVICE REQUIREMENTS

A. AIR STREAM CONTENTS:

Saturated air streams at 40-120° F containing hydrogen sulfide in concentrations up to 50

ppm and droplets of sulfuric acid.

B. PRESSURE AND VACUUM:

Design conditions are 20 inches water column pressure and 12 inches water column

vacuum. A minimum structural safety factor of 10:1 shall be used in the design of ductwork for

tensile or flexural stress conditions. A minimum safety factor of 5:1 shall be used for conditions

of elastic stability, such as buckling under vacuum loads.

1.03 REFERENCES

References are described in Section 13230.

1.04 ENVIRONMENTAL CONDITIONS

Environmental conditions are as described in Section 01800.

Page 22: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-2 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

1.05 SUBMITTALS

The following submittal information shall be provided in accordance with Section 01300:

1. A copy of this specification section, with addendum updates included, and

all referenced and applicable sections, with addendum updates included,

with each paragraph check-marked to indicate specification compliance or

marked to indicate requested deviations from specification requirements.

A check mark shall denote full compliance with a paragraph as a whole. If

deviations from the specifications are indicated, and therefore requested by

the Contractor, each deviation shall be underlined and denoted by a

number in the margin to the right of the identified paragraph, referenced to

a detailed written explanation of the reasons for requesting the deviation.

The Construction Manager shall be the final authority for determining

acceptability of requested deviations. The remaining portions of the

paragraph not underlined will signify compliance on the part of the

Contractor with the specifications. Failure to include a copy of the

marked-up specification sections, along with justification(s) for any

requested deviations to the specification requirements, with the submittal

shall be sufficient cause for rejection of the entire submittal with no

further consideration.

2. Complete damper shop drawings illustrating component configuration,

dimensions, and materials list.

3. Certified damper leakage test results in accordance with AMCA 500

standards, pressure drop characteristics, and actuator torque requirements.

4. Proposed FRP ductwork plan, including hanger and support types and

locations, field joint locations, inspection plates, drains, blast gates,

dampers, expansion boots, etc.

5. Certification from the resin manufacturer that the selected resin and

catalyst systems are appropriate for the service conditions of the duct

systems, as specified in Sections 01800 and 13234.

6. Calculations and complete fabrication details of special system

components specified in paragraph 13234-2.01E. Approval of design is

required prior to the start of fabrication.

7. Qualifications of the Fabricator and Field Joining Contractor.

Page 23: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-3

PART 2 -- PRODUCTS

2.01 MANUFACTURERS

The Owner and Construction Manager believe the following candidate manufacturers are

capable of producing equipment and/or products that will satisfy the requirements of this Section.

This statement, however, shall not be construed as an endorsement of a particular manufacturer’s

products, nor shall it be construed that named manufacturers’ standard equipment or products

will comply with the requirements of this Section. Candidate manufacturers include Daniel

Mechanical, Spunstrand, ECS, or equal.

2.02 FRP DUCTWORK

A. DESIGN CRITERIA:

1. EQUIPMENT: FRP Ductwork.

2. RESIN: Resin shall be premium grade vinyl ester resin. Resin shall

achieve ASTM E84 Class I fire retardance without the use of antimony.

3. SPECIAL CATALYST: No additives that reduce the translucency shall

be included in the resin.

4. MINIMUM BARCOL HARDNESS: 30

5. SURFACING VEIL (INNER SURFACE): One (1) layer of 10 mil C-glass

surfacing veil.

6. INTERIOR LAYER: Two (2) layers of 1-1/2 oz./sq. ft. mat.

7. CORROSION LINER THICKNESS, MINIMUM: 100 mils.

8. FILAMENT WINDING HELIX ANGLE: 55° to 65°; Tolerance: ±2°

9. FILAMENT WINDING CYCLE THICKNESS, MAXIMUM: 0.06"

10. FILAMENT WOUND STRUCTURAL WALL GLASS CONTENT: 55

percent to 65 percent.

11. STRUCTURAL LAYERS: Natural color, no pigments allowed.

Exterior surface coat and 10 mil C-glass surfacing veil required; color to be

determined by the Construction Manager.

12. POSTCURE: Equipment to be postcured in accordance with the

recommendations of the resin manufacturer for the intended service.

Page 24: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-4 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

13. MARKING: In addition to the requirements of paragraph 13230-2.03.C,

all spool assemblies and pieces shall be identified with piece mark numbers using non-water-

soluble paint, easily removable with agents that will not attack the finish of the FRP Ductwork.

The exterior of all FRP duct to be located inside of any buildings shall be coated

with two (2) coats of PPG Speedhide Flat Latex paint No. 42-7, or equal, in accordance with the

manufacturer’s recommendations, for smoke rating and additional fire retardancy.

Any damage to this paint coat occurring during installation shall be repaired

promptly, restoring the paint coat to the original condition.

B. DETAILS:

As a minimum, FRP ductwork shall be constructed in accordance with the thicknesses,

laminate sequences and detail drawings that follow at the end of this section. If the design

requirements dictate that increased thickness or other changes are required, they shall be

submitted for approval of the Construction Manager. Details shall be used in conjunction with

contract drawings and Section 13230. Details are as follows:

Detail-1, FRP Duct and Fitting Thickness

Detail-2, FRP Flanges

Detail-3, Expansion Boot

Detail-4, 1-1/2" Dia. Drain Nozzle Installation

Detail-5, FRP Butt and Miter Joints

Detail-6, FRP Tee and Lateral Joints

Detail 7, Typical Round Blast Gate, All FRP Construction

Detail 8, FRP Zero Leak Damper

C. ELBOWS:

Elbows 30 inch diameter and smaller shall be one piece molded, smooth turn, hand lay-up

construction. Larger elbows may be fabricated from straight duct sections, using miter joints per

the drawing details in this section. Mitered elbows 45 degrees and less shall be two piece, one

miter joint. Mitered elbows 46 to 90 degrees shall be three piece with two miter joints. All

elbows shall be large radius (1.5 times the diameter) except as otherwise required.

D. LAMINATE SEQUENCE TABLES FOR FRP DUCTWORK:

Key for Tables 1 and 2:

C = 10 mil C-glass surfacing veil

M = 1-1/2 oz./sq. ft. mat

E = Exotherm ply, 1-1/2 oz./sq. ft. mat

R = 24 oz./sq. yd., 5x4 plain weave, woven roving

FW = Filament winding to the thickness specified.

Page 25: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-5

Table 1. Helix Wound Laminate Composition

Thk. C M E R Sequence of plies

0.21" 2 1 1 CME ⇒ 0.11" F.W. ⇒C

0.24" 2 1 1 CME ⇒ 0.14" F.W. ⇒C

0.27" 2 1 1 CME ⇒ 0.17" F.W. ⇒C

0.32" 2 1 1 CME ⇒ 0.22" F.W. ⇒C

0.35" 2 1 1 CME ⇒ 0.25" F.W. ⇒C

0.38" 2 1 1 CME ⇒ 0.28" F.W. ⇒C

0.41" 2 1 1 CME ⇒ 0.31" F.W. ⇒C

Table 2. Hand Lay-Up Laminate Composition

Thk. C M E R Sequence of plies

0.24" 2 4 1 1 CME MRMMC

0.33" 2 5 1 2 CME MRMRMMC

0.39" 2 6 1 3 CME MRMRMRMMC

0.46" 2 6 2 4 CME MRMRE MRMRMC

0.50" 2 7 2 4 CME MRMRMRE MRMMC

0.54" 2 7 2 5 CME MRMRMRE MRMRMC

0.57" 2 8 2 5 CME MRMRMRE MRMRMMC

0.64" 2 9 2 6 CME MRMRMRE MRMRMRMMC

E. SPECIAL SYSTEM COMPONENTS:

Fabricator shall be responsible for the design of rectangular duct, transitions, or any

special system components not specifically detailed in this section. Deflection of flat panels shall

be limited to 1 percent of the panel width at the system operating pressure. Rectangular duct and

flanges shall be fabricated in one piece with a minimum radius of 1/2" in all corners.

Rectangular duct shall not be assembled from multiple flat panels.

F. TURNING VANES:

Turning vanes shall be provided where indicated on the drawings and in accordance with

ASHRAE recommendations. All vanes shall have sufficient section and stiffness to operate

without flutter or vibration under the airflow conditions indicated. Turning vanes shall be airfoil

section with internal metal reinforcement and FRP laminate overlay or airfoil section, all Type

316 stainless steel. Duct fabricator shall propose and submit construction, location, and

installation details of vanes and splitters.

Page 26: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-6 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

2.03 FASTENERS

Bolts, nuts, and washers shall be stainless steel, AISI Type 316. Type 316 stainless steel

backing strips, drilled for the above bolting requirements, shall be employed for all connections

at fans, demisting sections, and wherever shear or moment loads may be encountered on duct

connections.

2.04 GASKETS

Gaskets shall be EPDM, Viton, or Buna-N.

2.05 EXPANSION BOOTS

Expansion boots shall be as shown on the detail drawings in this section, flanged one-

piece molded reinforced EPDM, a minimum thickness of 1/8-inch with stainless steel split

retaining rings. Expansion boots shall be Mercer Rubber Company, Duct Connector Model MI-

9, or equal. Provide a 1/2-inch diameter galvanized U-bolt to function as a guide at the closest

pipe support on each side of each expansion boot. Install U-bolt with approximately 1/8-inch

clearance between duct and U-bolt to allow axial movement of duct. For expansion/ flexible

connections at fans or blowers, refer to those equipment specifications.

For exterior ducts, Contractor shall size the expansion boots based on a minimum

temperature of -30°F and a maximum temperature of 105°F, using the coefficient of thermal

expansion for the particular duct work being provided by the Contractor.

2.06 SUPPORTS AND HANGERS

FRP ductwork shall be supported in accordance with Section 15050, and at intervals no

greater than those indicated in the table below. Supports and hangers shall transmit all ductwork

loads into the building structural frame through a system of intermediate beams and struts as

necessary to accommodate requirements of these specifications. The Contractor shall submit

construction details for supports and hangers and its proposed plan for location and type of

supports, including location of any required expansion joints. Acceptance of the proposed

locations and construction details by the Construction Manager is required prior to the start of

fabrication. Where supports and hangers are detailed on the Drawings, they shall be provided as

shown.

FRP ductwork allowable spans:

Inside Diameter - inches Maximum span, feet

<20 12

24-36 15

42 17

48-54 20

Page 27: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-7

Inside Diameter - inches Maximum span, feet

60 22

72 24

Hangers and supports shall be lined with 1/8-inch thick neoprene, bonded to the metal

hanger or support, to cushion the duct.

Hangers and supports shall fit the exterior of the duct closely and extend completely

around the duct. Minimum width shall be the larger of 4 inches or 1/8 of the duct diameter.

2.07 DAMPERS

A. GENERAL:

Dampers shall have FRP or Type 316 stainless steel blades, Type 316 stainless steel

shafts and hardware, and permanently lubricated bearings of material impervious to attack by

acids and caustics. Damper frames shall be fabricated to match connecting ductwork. Flanges

shall be pre-punched and shall match duct flanges and bolt patterns as specified in this section.

No shop fabricated or spooled in duct dampers will be allowed.

1. Stuffing boxes shall be provided for gas-tight seals to prevent leakage at

all shaft ductwork penetrations. Stuffing boxes shall be adjustable and

shall contain a minimum of two sets of packing glands. Bearings shall be

flange mounted, located outside the air stream. Bearings may be oil

impregnated sintered bronze or relubricable rolling element.

2. Damper linkage shall be capable of transmitting twice the maximum

torque required by the damper at 20 inches differential pressure. Linkage

lever arms shall be a minimum of 3 inches, and the lever arms shall be

welded to the axles. All linkage connections shall be supplied with oil

impregnated bronze bearings.

3. Actuators for dampers having torque requirements of 500 inch-pounds or

less shall have heavy-duty manual locking quadrants. Actuators for

dampers having torque requirements in excess of 500 inch-pounds shall

have manual worm gear actuators with hand wheel. Damper actuators not

readily accessible shall be provided with chain wheel actuators.

4. Damper supplier shall provide certified leakage, pressure drop, and torque

data for each damper type and size. Data shall result from prototype

testing conducted in accordance with AMCA 500 test standards, in an

AMCA certified test facility.

Page 28: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-8 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

B. RECTANGULAR DAMPERS:

Rectangular dampers shall be opposed blade dampers of the airfoil design. Rectangular

damper blades shall have a minimum thickness of 16 gauge and a maximum width of 9 inches.

Axles shall have a minimum diameter of 3/4-inch, shall be solid, and shall extend the full length

of the blade stuffing boxes and bearings. Blades shall be through-bolted to axles. Blade edge

and axle deflection produced by 20 inches differential pressure across the closed damper shall not

exceed 1/360th of the span or 1/8-inch, whichever is less.

Seals shall be provided on rectangular damper blade edges and jambs. Seal material shall

be closed cell elastomer material, and shall be applied with an adhesive which will provide a

bond strength greater than the tensile strength of the seal material. Seal material and adhesive

shall be impervious to attack by acids and caustics.

Leakage through the closed damper at 70° F and 10 inches water column differential

pressure shall not exceed 30 cfm per square foot of conduit cross-sectional area for rectangular

dampers.

Damper linkage shall be capable of transmitting twice the maximum torque required by

the damper at 20 inches differential pressure. Linkage lever arms shall be a minimum of 3

inches, and the lever arms shall be tack-welded to the axles.

C. STANDARD ROUND DAMPERS:

Round dampers shall be butterfly dampers suitable for balancing and shut-off. Dampers

shall be constructed between two flanges unless shown otherwise. Minimum damper blade

thickness shall be equal to flange thickness specified in this section. Share seal shall be Viton O-

ring. Leakage through the closed damper at 70° F and 10 inches water column differential

pressure shall not exceed 30 cfm per square foot of conduit cross-sectional area. Standard round

dampers shall be Spundstrand, Swartwout Model 914, or approved equal.

D. ZERO LEAK ROUND DAMPERS:

Zero leak dampers shall be suitable for air tight sealing, and leak free at 28 inches w.c.

pressure for one hour. Dampers shall be constructed between two flanges. Minimum damper

blade thickness shall be equal to flange thickness specified in this section. Share seal shall be

Viton O-ring. Zero leak dampers shall be provided similar to the detail drawing in this

specification section and installed at the locations shown on the contract drawings. Zero leak

dampers shall be Spundstrand ZL Series, Ershigs Type B, or approved equal. Unless shown

otherwise on drawings, all round dampers shall be zero leak.

Page 29: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-9

E. ACTUATORS:

All actuators for all dampers shall be independently supported.

2.08 INSPECTION PLATES

Removable inspection plates, covering 8 inch round access holes, shall be provided at all

fan inlet and discharge connections and upstream and downstream from all operable fittings such

as dampers, , screens, filters, and at all primary instrument locations. Inspection plates shall be

gasketed and shall make an airtight seal with the parent duct. Inspection plates shall be

fabricated of the same material as the parent duct.

Fabricator shall propose and submit construction, location, and installation details of

inspection plates.

2.09 BLAST GATES

Blast gates shall be provided in accordance with this specification section and installed at

the locations shown on the contract drawings.

2.10 DRAINS

Drains sumps shall be 1 1/2-inch flanged outlets fabricated and installed in accordance

with the detail drawings in this section. Each drain shall be fitted with a 316 stainless steel blind

flange with a 1 inch NPT PVC half-coupling mounted at its center.

In addition to drains shown on the drawings, drain sumps with 1 1/2-inch minimum

flanged outlets shall be provided at all low points. All drain sumps shall be fitted with a 1 1/2-

inch PVC ball valve. Drains shall be FRP or Schedule 80 PVC.

Fabricator shall propose and submit construction, location, and installation details of

drain sumps.

2.11 PRODUCT DATA

The following information shall be provided in accordance with Section 01300:

1. Installation certification Form 11000-A as specified in paragraph

13234-3.02.

Page 30: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-10 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

PART 3 -- EXECUTION

3.01 GENERAL

Refer to Section 13230. Unless otherwise specified, all ductwork shall be filament

wound construction.

3.02 INSTALLATION

A. GENERAL:

All material and equipment shall be installed as specified and as required by the

applicable state and local codes. All ductwork indicated on the drawings is schematic.

Therefore, changes in duct size, duct configuration, and location may be necessary to conform to

field conditions. All such changes shall be submitted to the Construction Manager for approval

prior to fabrication or construction.

B. FIELD JOINING MATERIALS:

FRP duct manufacturer shall supply all materials needed for any required FRP duct field

joining. Supply of these materials shall be in accordance with the requirements of this Section

and Section 13230.

C. FIELD JOINING:

Butt or flanged joints shall be provided as needed to allow installation of the duct as

shown. Number of joints shall be minimized.

Any required field joining shall be accomplished by the Field Joining Contractor in

accordance with the requirements of this section and Section 13230. The Field Joining

Contractor shall have a minimum five years experience in FRP ductwork.

D. INSTALLATION AND SUPPORT:

FRP ductwork shall be installed and supported in accordance with Chapter 11 of the

Uniform Mechanical Code. Ductwork shall be supported as described in Paragraph 13234-2.06.

Large elbows and terminal ends of ducts shall be supported independently. Flexible connections

as described in Paragraph 13234-2.05 shall be provided between fans and ductwork, and

elsewhere as indicated on the layout drawings.

E. CERTIFICATION:

The installation shall be certified on Form 11000-A, Section 01999.

Page 31: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-11

3.03 FIELD QUALITY CONTROL

A. TESTING:

All ductwork shall be leak-tested as described in Section 15050. All audible leaks shall

be sealed. All tests shall be scheduled with the Construction Manager by giving 24 hours notice.

The Contractor shall provide necessary fittings, blind flanges, etc. to isolate sections of duct and

to enable all sections of ductwork to be tested.

B. MANUFACTURER'S SERVICES:

The Fabricator shall provide a representative on-site at the start of the installation of the

ductwork to supervise installation of the FRP duct system. To ensure the Contractor is

employing the proper procedures, the Fabricator shall remain on-site to witness installation of all

ductwork. The Fabricator shall be on-site no less than two 8-hour days during the start of

installation.

The Fabricator shall instruct the Contractor on the proper installation procedures at any

time the Fabricator and/or the Construction Manager witnesses improper installation practices.

DUCT

I.D.

F.W. WALL THK.

( TABLE 1 )

H.L.U. WALL THK.

( TABLE 2 )

Up to 12" 0.21" 0.24"

14" 0.21" 0.24"

16" 0.21" 0.24"

18" 0.24" 0.33"

20” 0.24" 0.33"

24" 0.27" 0.33"

30" 0.32" 0.39"

36" 0.35" 0.46"

42" 0.38" 0.50"

48" 0.41" 0.54"

54” 0.41" 0.64”

60” 0.41" 0.64”

FRP DUCT AND FITTING THICKNESS

DETAIL-1

Page 32: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-12 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

FRP DRILLED FLANGE - DUCT DRILLING

NOZZLE

I.D.

NOZZLE

O.D

BOLT

CIRCLE

NO. OF

BOLT

HOLES

DIA. OF

BOLT

HOLES

A

B

(Table 2)

C

D

Up to 12" 16 3/8" 15" 12 1/2" 2" 0.24" 0.37" 0.50"

14" 18 3/8" 17" 12 1/2" 2" 0.24" 0.37" 0.50"

16" 20 3/8" 19" 16 1/2" 2 1/2" 0.24" 0.44" 0.63"

18" 22 3/8" 21" 16 1/2" 2 1/2" 0.33" 0.48" 0.63"

20" 24 3/8" 23" 20 1/2" 2 1/2" 0.33" 0.48" 0.63"

24" 28 3/8" 27" 20 1/2" 2 1/2" 0.33" 0.48" 0.63"

30" 34 3/8" 33" 28 1/2" 2 1/2" 0.39" 0.51" 0.63"

36” 40 3/8” 39” 32 1/2” 2 1/2" 0.46” 0.55” 0.63”

42” 46 3/8” 45” 36 1/2" 3” 0.50” 0.63” 0.75”

48” 54 3/8” 52” 44 5/8” 4” 0.54” 0.77” 1.00”

54” 66 3/8” 58” 44 5/8” 4” 0.64” 1.00” 1.00”

60” 66 3/8” 64” 52 5/8” 4” 0.64” 1.00” 1.00”

FRP DRILLED FLANGE – 125/150 PATTERN

NOZZLE

I.D.

NOZZLE

O.D

BOLT

CIRCLE

NO. OF

BOLT

HOLES

DIA. OF

BOLT

HOLES

A

B

(Table 2)

C

D

E

1-1/2" 5" 3-7/8" 4 5/8" 2" 0.24" 0.50" 0.50" 8"

FRP FLANGES

DETAIL-2

Page 33: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-13

EXPANSION BOOT

DETAIL-3

FLANGE

1/8" THICK REINFORCED

NEOPRENE BOOT, CONTINUOUS

Page 34: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-14 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

NOZZLE I.D.

EXTERNAL OVERLAY INTERNAL OVERLAY

THK. (TABLE 2) WIDTH THK. WIDTH.

1 1/2” 0.29” 10” (MMCC)” 4”

GENERAL NOTES: 1. Radius inside edge of nozzle, 1/8” min. to 1/4” max. 2. Fill voids with resin putty. Flare putty into a radius 1/4” min. to 3/8” max. 3. Locate vent hole as low as possible, resin coat edge of hole.

1 ½” DIA. DRAIN AND NOZZLE INSTALLATION

DETAIL-4

Page 35: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-15

FRP DUCT BUTT AND MITER JOINT OVERLAY

DUCT

EXTERNAL OVERLAY

( TABLE 2 )

I.D. THICKNESS WIDTH

Up to 12" 0.24" 8"

14" 0.24" 8"

16" 0.24" 8"

18" 0.33" 10"

20" 0.33" 10"

24" 0.33" 10"

30" 0.42" 12"

36" 0.46" 12"

42" 0.54" 12"

48” 0.54” 12”

54” 0.64” 14”

60” 0.64” 16”

NOTES:

1. See Section 13230 for assembly tolerances.

2. For 24" diameter and larger, and where accessible, apply an internal overlay (MMC)

6"wide.

FRP BUTT AND MITER JOINTS

DETAIL-5

Page 36: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-16 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

FRP DUCT TEE AND LATERAL JOINT OVERLAY

DUCT EXTERNAL OVERLAY

( TABLE 2 )

I.D. THICKNESS WIDTH

12" 0.33" 10"

14" 0.33" 10"

16" 0.33" 10"

18" 0.39" 12"

20" 0.39" 12"

24" 0.39" 12"

30" 0.46" 14"

36" 0.54" 14"

42" 0.57" 16"

48” 0.64" 16”

54” 0.64" 16”

60” 0.64" 16”

NOTES:

1. See Section 13230 for assembly tolerances.

2. Fill voids with resin putty as shown. Flare putty into a radius 1/4” min. to 3/8” max.

3. For header diameter 24" and larger, and where accessible, apply an internal overlay

(MMC) 6"wide.

FRP TEE AND LATERAL JOINTS

DETAIL-6

Page 37: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13234-17

VINYLESTER RESIN

NEOPRENE SEALS

CONSTRUCTION BLADE

THKNESS

HOLE

SIZE

BOLT

SIZE

4” THRU 16”

.187

7/16”

3/8”

18” THRU 24”

.250

7/16”

3/8”

26” THRU 36”

.320

7/16”

3/8”

42” THRU 72”

.375

9/16”

1/2”

TYPICAL ROUND BLAST GATE

ALL FRP CONSTRUCTION

DETAIL-7

Page 38: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

FRP DUCTWORK

13234-18 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

CONSTRUCTION BLADE

THKNESS

AXLE

DIM

BLADE

STIFFENERS

4” THRU 10” 0.125 0.75 --

12” THRU 16” 0.125 1.0 1

16” THRU 22” 0.187 1.0 2

24” THRU 28” 0.25 1.5 2

30” THRU 36” 0.375 1.5 3

ZERO LEAK ROUND DAMPER

DETAIL-8

** END OF SECTION **

Page 39: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

RTP GRATING

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13237-1

SECTION 13237

RTP GRATING

PART 1 -- GENERAL

1.01 THE REQUIREMENT

A. SCOPE:

This section specifies RTP grating and supports. All gratings to be provided shall be

resistant to degradation from the harsh environment normally found in wastewater treatment

plants, exposure to ultra-violet light, and shall meet the requirements of Section 13230,

Fiberglass Reinforced Plastic (FRP) Fabrications.

B. APPLICATION:

Provide grating to cover the walking surface above the influent gate and provide a non-

skid walking surface without the use of impregnated grit. Grating shall be configured to allow

for gate stem openings and supports.

Provide grating to cover the channels in the Grinder Facility. Provide non-skid walking

surface without the use of impregnated grit. Grating shall be configured to allow for the removal

of the gates and stop logs.

1.02 PERFORMANCE AND DESIGN REQUIREMENTS

A. DESIGN:

Manufacturer shall be responsible for designing and providing the grating and the

supports. Gratings shall be designed in accordance with the following:

1. SAFETY FACTOR: Minimum structural safety factor of 5.

2. DESIGN LOADS: Unless otherwise shown on the drawings, design loads

for gratings shall be as follows:

a. 1,000 pounds per square foot.

3. RESIN: Use fire retardant type resin specified in Section 13230-2.2 A.5

for all RTP gratings aand supports..

4. THICKNESS: The minimum thickness of all gratings shall be as

specified in Section 1.2C.

Page 40: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

RTP GRATING

13237-2 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

5. SIZES: Grating sheet sizes shall be compatible with the spans shown on

the drawings. A minimum amount of field cutting will be allowed on Type 1 grating only.

B. CORROSION RESISTANCE:

Grating shall be suitable for continuous service under the following conditions:

Condition Range

pH 4 to 11

Temperature 30 to 140 degrees F

Hydrogen sulfide, wet or dry 40 ppm

C. CHARACTERISTICS:

Item Type 1

Material RTP

Manufacturing type Molded

Grid Size, in x in 1 ½ x 1 ½

Min depth, in 1 ½

Percent Open, min 60

Nominal Panel Size, ft x ft 4 x 12

Max Unit Weight, lbs/sq. ft. 3.2

Number of bar/ft width, min 8

Min bar width, in 0.60

UV resistance Required

1.03 SUBMITTALS

The following submittals shall be provided in accordance with Section 01300:

1. Layout drawings

2. Support details

3. Manufacturer and method of fabrication

4. Installation details

5. Product sample

6. Material composition

7. Cut end sealing material information

Page 41: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

RTP GRATING

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13237-3

1.04 PRODUCT SHIPPING, STORAGE AND HANDLING

The Contractor shall be responsible for proper packaging and protection of all materials

to prevent damage during shipping, handling and storage. Store and handle all grating in

accordance with manufacturer’s recommendations.

PART 2 – PRODUCTS

2.01 ACCEPTABLE MANUFACTURERS

A. GENERAL:

List of acceptable manufacturers or equal are listed in the following subsections.

1. Fibergrate Composite Structures, Inc. or Strongwell.

2.02 MATERIALS

RTP in accordance with Section 13230, Fiberglass Reinforced Pipe (FRP) Fabrications

and shall be fire-retardant, UV light resistant resin with glass reinforcement.

2.03 FABRICATION

Each grating shall be fabricated in panels sized per openings as indicated on the Contract

Drawings. Grating manufacturer shall coordinate with the Contractor to ensure properly sized

grating openings for gate stem and support specific to the gate being submitted. Fabricate

grating using molded construction. Construct each panel with concave type treads to provide a

non-skid walking surface. RTP grating shall have a UV-inhibitor to prevent UV degradation

during continuous exposure to sunlight.

2.04 ACCESSORIES

Provide all miscellaneous accessories required for a complete installation. Provide Type

316 stainless steel clips, bolts, nuts and washers, and anchors where required to obtain a tight and

secure fastened system.

PART 3 – EXECUTION

3.01 GENERAL

Install adequate gratings as shown in the drawings and per the manufacturer’s detailed

installation plan.

Page 42: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

RTP GRATING

13237-4 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

Minimal field cuts shall be allowed. All grating shall be shop fabricated, sealed and

tagged for installation. All grating shall be accurately aligned, level, and plumb. No wedges or

shimming devices shall be used.

Install RTP grating as recommended by the grating fabricator. Furnish RTP grating with

hold down attachments, end panel attachments, and appurtenances to make the work complete.

Secure grating panels end-to-end and side-to-side to form a continuous layer of grating

Grating shall be installed as a system with all accessories necessary to anchor adjoining

panels.

3.02 DAMAGED OR DEFECTIVE AREAS

Damaged or defective areas which are otherwise acceptable shall be repaired in a manner

satisfactory to the ENGINEER.

** END OF SECTION **

Page 43: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-1

SECTION 13565

PACKAGED BULK MEDIA BIOFILTER

PART 1 -- GENERAL

1.01 DESCRIPTION

A. SCOPE:

This section specifies material, labor, startup and performance testing services necessary

to provide a complete and properly functioning bulk media biofilter odor control system,

including the air plenum, humidification vessel, biofilter media, air header and distribution pipe,

media irrigation system, moisture sensing and controls, and all necessary appurtenances.

The biofilter will treat sewer headspace gases from a municipal wastewater lift station

located in Carlsbad, California. The biofilter will be constructed within concrete retention walls

and floor, provided by the Contractor. The biofilter will be open to the atmosphere and shall be

preceded by a humidification system designed to increase the relative humidity of the inlet air.

Fans shall be provided under specification Section 15828 and shall convey foul air to the

biofilter. At the Contractor’s option, the humidification vessel, foul air fans, and irrigation

system may be supplied under one subcontract to include the biofilter, fans, humidification

vessel, and all necessary control equipment.

The scope of supply shall also include the following services:

1. Laboratory analysis of the media being supplied

2. Oversight of biofilter and humidifier installation

3. Operator training and performance testing of the completed installation

B. DESIGN CONDITIONS:

Equipment furnished under this section shall be suitable for treating odorous air collected

from the Agua Hedionda Lift Station facility. Overall odorant concentrations are expected to

average 10 ppmv H2S, and minor concentration of organic sulfides (less than 0.5 ppmv). The

wastewater will have a temperature of 50 degrees Fahrenheit to 90 degrees Fahrenheit and will

have a pH that may range from 6 to 9. Outdoor temperature may range from 30° to 100°F.

Ambient conditions are further specified in Section 01800.

Page 44: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-2 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

C. EQUIPMENT LIST:

Schedule B

Item Equipment No.

Biofilter Media and Media Support System BIO-2250

Humidifier System MME-2230

D. OPERATING CONDITIONS AND PERFORMANCE REQUIREMENTS:

The performance requirements presented below specify the operating requirements for

the biofilter odor control system. Equipment furnished under this section shall be fully suitable

for continuous operation at the operating conditions specified:

1. REMOVAL EFFICIENCY: A 99 percent removal rate for H2S

concentrations above 10 ppmv and a 90 percent removal rate of mercaptans. A 100 ppbv

maximum discharge concentration at inlet concentrations less than 10 ppmv.

2. OLFACTORY PERFORMANCE: The biofilter shall have no detectable

odors at distance of fifty (50) feet from the bed.

3. MEDIA LIFE: Biofilter media shall be activated soil or inert synthetic

media, and the air plenum medium shall have a minimum useful life of ten (10) years. “Useful

life” shall be defined to mean operation under the following conditions: no detectable

degradation in the odor removal performance of the biofilter when operated within the specified

airflow and contaminant loading and maintained in accordance with the System Supplier’s

written operations and maintenance requirements.

E. DESIGN REQUIREMENTS:

1. GENERAL: The biofilter shall be specifically designed to continuously

treat odorous air collected from the influent interceptor and lift station wet well under the service

conditions specified in 13565-1.01 B and to meet the performance requirements listed in 13565-

1.01 D.

2. CHARACTERISTICS: Equipment provided under this section shall

conform to the following requirements:

a. The biofilter odor control system shall be installed as generally

shown on the Drawings. This arrangement is intended to represent

the minimum standard of quality and treatment capacity.

b. The biofilter system shall be designed to treat 8,300 cubic feet per

minute of odorous air continuously.

Page 45: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-3

c. This system shall be designed to eliminate odorous compounds

from the airstream typical of a municipal wastewater treatment

application. These compounds shall include, but not be limited to,

hydrogen sulfide, mercaptans, reduced sulfur compounds,

ammonia and volatile organic compounds typical of this type of

application.

d. The biofilter design shall utilize an activated soil bed type media or

other inert media. Compost, wood chips, and other types of

organic media will not be acceptable.

e. The total pressure drop through the humidifier, air plenum, air

header manifolds, air distribution laterals, and biofilter media shall

not exceed 8 inches of water column (WC).

1.02 QUALITY ASSURANCE

A. REFERENCES:

This section contains references to the following documents. They are a part of this section

as specified and modified. Where a referenced document contains references to other standards,

those documents are included as references under this section as if referenced directly. In the event

of conflict between the requirements of this section and those of the listed documents, the

requirements of this section shall prevail.

Unless otherwise specified, references to documents shall mean the documents in effect

at the time of Advertisement for Bids. If referenced documents have been discontinued by the

issuing organization, references to those documents shall mean the replacement documents

issued or otherwise identified by that organization or, if there are no replacement documents, the

last version of the document before it was discontinued. Where document dates are given in the

following listing, references to those documents shall mean the specific document version

associated with that date, regardless of whether the document has been superseded by a version

with a later date, discontinued or replaced.

Reference Title

ASTM D2563 Standard Practice for Classifying Visual Defects in Glass Reinforced

Plastic Laminate Parts

ASTM D2584 Standard Test Method for Ignition Loss of Cured Reinforced Resins

ASTM D3299 Standard Specifications for Filament Wound Glass Fiber Reinforced

Thermoset Resin Corrosion Resistant Tanks

ASTM D4097 Standard Specification for Contact Molded Glass Fiber Reinforced

Thermoset Resin Corrosion Resistant Tanks

NSB PS15 Custom Molded Reinforced Polyester for Chemical Resistant Process

Equipment

Page 46: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-4 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

As a minimum, references cited in the following specifications shall be used unless

otherwise indicated:

13230 FRP Fabrications

13234 FRP Ductwork

13237 RTP Grating

15064 Plastic Pressure Pipe

15065 High Density Polyethylene Pipe

B. SYSTEM SUPPLIER QUALIFICATIONS:

The System Supplier must have a minimum of ten (10) biofilter installations of similar

size, or larger, that have successfully operated to control the odors associated with hydrogen

sulfide, organic sulfur compounds, and other malodorous compounds associated with a

municipal wastewater collection system or treatment plant. These installations must have been

in operation for a minimum of three (3) years. Successful operation is defined as operation

within the original performance criteria for the life of the installation without requiring a media

replacement.

C. UNIT RESPONSIBILITY:

The Contractor shall assign unit responsibility, as specified in paragraph 11000-1.02 C, to

the manufacturer of the biofilter provided under this section. This manufacturer is the unit

responsibility manufacturer and has unit responsibility, as specified in paragraph 11000-1.02 C,

for both the equipment assembly specified in this section and for the foul air fans specified in

Section 15828: Centrifugal Fiberglass Reinforced Fans, and ductwork specified in Section

13234: Fiberglass Reinforced Plastic Ductwork, and all other equipment assembly components

specified elsewhere but referenced in this section. The fan performance criteria and operating

requirements in Section 15828 were based on a total of 8 inches of water column pressure drop

within the humidifier, air plenum, air header manifolds, air distribution laterals, and biofilter

media. If the pressure drop through the biofilter system differs from these conditions, the fan

performance or selection may change to accommodate the required pressure drop. This

manufacturer is responsible for the coordination of all interconnecting components. A

completed, signed, and notarized Certificate of Unit Responsibility (Form 11000-C, Section

01999) shall be provided.

1.03 SUBMITTALS

The Contractor shall provide the following submittals in accordance with Special

Provisions:

1. A copy of this specification section, with addendum updates included, and

all referenced and applicable sections, with addendum updates included,

with each paragraph check-marked to indicate specification compliance or

marked to indicate requested deviations from specification requirements.

Check marks shall denote full compliance with a paragraph as a whole. If

Page 47: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-5

deviations from the specifications are indicated, and therefore requested

by the Contractor, each deviation shall be underlined and denoted by a

number in the margin to the right of the identified paragraph, referenced to

a detailed written explanation of the reasons for requesting the deviation.

The Engineer shall be the final authority for determining acceptability of

requested deviations. The remaining portions of the paragraph not

underlined will signify compliance on the part of the Contractor with the

specifications. Failure to include a copy of the marked-up specification

sections, along with justification(s) for any requested deviations to the

specification requirements, with the submittal shall be sufficient cause for

rejection of the entire submittal with no further consideration.

2. A copy of the contract document control diagrams and process and

instrumentation diagrams relating to the submitted equipment, with

addendum updates that apply to the equipment in this section, marked to

show specific changes necessary for the equipment proposed in the

submittal. If no changes are required, the drawing or drawings shall be

marked "no changes required". Failure to include copies of the relevant

drawings with the submittal shall be cause for rejection of the entire

submittal with no further review.

3. Certificate of Unit Responsibility attesting that the Contractor has

assigned, and that the manufacturer accepts, unit responsibility in

accordance with the requirements of this Section and paragraph

11000-1.02 C. No other submittal material will be reviewed until the

certificate has been received and found to be in conformance with these

requirements.

4. Shop Drawings: Detailed pipe fabrication or spool drawings showing

special fittings and bends, dimensions, coating, field connection details,

and other pertinent information.

5. Control Diagrams: Wiring diagrams showing all components, flow rates

and unit requirements for the humidification system, moisture sensing and

control system, and irrigation sprinkler system.

6. Media Samples: Submit sample of media materials following delivery of

shipment.

7. Quality Control Submittals:

a. A letter from system supplier certifying that media has been placed

in accordance with the specifications and the System Supplier’s

requirements.

Page 48: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-6 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

b. Pipe Manufacturers’ Certificate of Compliance.

c. Submit functional and performance test certificates and reports.

8. Performance Test Submittals:

a. Submit a Detailed Performance Testing Plan which includes:

1) Test equipment and apparatus.

2) Calibration and setup procedures.

3) The specific testing methodology to be used. Flow

measurements shall not rely on blower curves but shall be a

direct measurement using flow or pressure instruments.

4) The sampling and analysis procedures.

5) Submit a final report that provides a narrative of the

sampling activities, a copy of the original sample logs,

photographs showing the locations of the velocity

measurements, tabular summary of the data, calculated

results, and conclusions of these results. The system

supplier shall witness the field tests and shall certify that:

• the equipment has been properly installed and aligned;

• is free from an undue stress imposed by connecting

piping and or anchor bolts;

• has operated under full load and reduced loads and that

the scrubber operates satisfactorily;

• the contractor has accurately recorded the data obtained

during the field test; and

• the system meets the criteria set forth in this

specification.

9. Warranty: The System Supplier shall guarantee the useful life of the

activated soil or synthetic biofilter medium for a period of at least 10 years

and shall also guarantee that there will be no nuisance odors detectable a

distance of 50 feet beyond the edge of the biofilter bed. If any defects or

malperformance occurs in that period, the System Supplier must make all

necessary alterations, repairs, or replacements free of charge.

Page 49: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-7

10. Recommended sprinkler wetting rate and duration for both summer and

winter conditions.

B. PRODUCT DATA SUBMITTALS:

Operation and maintenance manuals including drawings, control diagrams, catalog

information, equipment cut sheets, performance data, and spare parts lists.

Submit a final report that provides a narrative of the sampling activities, a copy of the

original sample log, photographs showing the locations of the velocity measurements, tabular

summary of the data, calculated results, and conclusions of these results.

PART 2 -- PRODUCTS

2.01 ACCEPTABLE PRODUCTS

Bohn Biofilter Corporation, Tucson, Arizona

BIOREM Technologies, Guelph, ON, Canada

Or equal.

2.02 BIOFILTER MEDIA

Media shall be activated soil based inorganic media or inert synthetic media. Plenum

zone media where used shall be coarse gravel or other inert material provided by the biofilter

media manufacturer. Organic media consisting of compost, bark or similar components will not

be acceptable.

2.03 FOUL AIR PIPING

A. GENERAL:

Pipe lengths and fittings shall be supplied by the same manufacturer. Biofilter supplier

may propose alternative materials of equal or better quality and performance as the specified

materials.

B. PROTECTION:

Protection shall be provided against ultraviolet light degradation using carbon black, not

less than 2 percent, well dispersed in the resin.

Page 50: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-8 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

C. MAIN AIR HEADER MANIFOLD PIPES:

If used, main air header and manifold piping shall comply with the following:

1. Main air header manifold pipes shall be HDPE pipe meeting all

requirements of AASHTO M294, Type S.

2. Manufacturer shall weld stubs onto the air header manifold pipes for the

6-inch HDPE lateral connections.

a. Stubs shall consist of a short length of 6-inch SDR 32.5 HDPE

welded flush into the header manifold pipe .

b. Total length of the stub shall not exceed 12 inches.

c. No stubs shall be welded at a bell and spigot joint.

d. Stub spacing shall be approximately 2’-0” feet apart, or as per the

Biofilter System Supplier requirements.

3. JOINTS: HDPE water-tight bell and spigot couplings.

D. AIR DISTRIBUTION LATERALS:

Laterals, if required, shall be 6-inch-diameter corrugated and slotted HDPE pipe meeting

all requirements of AASHTO M252, Type CP. The standard dimension ratio of the pipe shall be

32.5.

Slot size and quantity shall be as recommended by the System Supplier.

1. JOINTS: HDPE snap couplings.

E. FITTINGS:

Snap type or factory welded with HDPE welds per manufacturer’s standard procedures

and requirements.

F. MANUFACTURER:

1. Advanced Drainage Systems (ADS), Inc.

2. Or equal.

Page 51: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-9

2.04 SPRINKLER SYSTEM

A. GENERAL:

The biofilter shall include an irrigation system for moisture control of the activated soil or

synthetic media. The sprinkler system shall include a sprinkler nozzle, sprinkler controller, and

automatic control valve.

B. LAYOUT:

The layout of the sprinkler system and the number of sprinkler system zones shall be

determined by the Biofilter System Supplier.

C. SPRINKLER NOZZLE:

The sprinkler nozzles shall be a full or part-circle low-trajectory sprinkler. The sprinkler

controller shall be a Rainbird, or equal.

D. CONTROL VALVE:

The sprinkler control valves shall be minimum 3/4-inch NPT, globe-type valve. Valve

shall be supplied with 24V AC coil and fail closed on a loss of power.

E. SPRINKLER CONTROL SYSTEM:

The sprinkler control system shall consist of a Rainbird sprinkler timer located within the

humidification system control panel. Electrical input required: 120 VAC ± 10%, 60 Hz.

Electrical output: 24-26.5 VAC.

1. SYSTEM OPERATION:

a. In power OFF, the moisture control system shall be inoperative.

b. In the AUTO bypass selector switch position, the system shall

actuate the zone control valve(s) for the amount of time

programmed.

c. In the ON bypass selector switch position, the system shall open

the zone control valve(s) regardless of the timer.

Page 52: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-10 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

2.05 HUMIDIFICATION SYSTEM

A. GENERAL:

The biofilter system shall include a humidification system for increasing the relative

humidity of the foul air. The humidification system shall be designed in accordance with the

biofilter manufacturer’s recommendations.

B. OPERATING REQUIREMENTS:

The humidification system shall be designed to achieve a minimum foul air relative

humidity of 70 percent at the design conditions described in Section 13565, 1.01 B.

C. MATERIALS:

The humidification system shall be designed to achieve a minimum foul air relative

humidity of 70 percent at the design conditions described in Section 13565, 1.01 B. Piping shall

comply with section 15050.

1. PACKED-TOWER HUMIDIFIERS:

a. Humidifier vessel fabrication and materials of construction shall

comply with Section 13230: Fiberglass Reinforced Plastic

Fabrications.

b. Packing material shall be structured polypropylene and shall not

shrink or swell under varying moisture and temperature conditions.

c. Humidifier package shall include all accessories such as lifting

lugs, recirculation pump, piping, control panels, and other

appurtenances necessary for proper operation.

2. MIST-BASED SYSTEMS:

a. Mist-based humidification systems shall provide at least three

misting nozzles on the pipe circumference, at 120 degrees angular

separation. All nozzles shall be oriented between 30 and 45

degrees from the pipe wall, and shall point towards the direction of

air flow. Nozzles shall be manufactured by BETE Fog Nozzle, Inc,

shall be constructed of Type 316 stainless steel, and shall have a

minimum spray angle of 90 degrees.

b. The nozzles shall be attached to the foul air duct or pipe wall by

means of a short spool piece with a flanged end to enable easy

removal of nozzles for inspection and maintenance. Flexible

Page 53: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-11

stainless steel braided hose shall be used for connecting supply

water piping to the nozzles at the flanged end.

c. Mist-based humidification systems shall be designed in a manner

that allows draining of water from the humidifier to the biofilter

sump.

2.06 PRODUCT DATA

The following information shall be provided in accordance with Section 01300:

1. Manufacturer’s installation Certificate Form 11000-A as specified in

Part 3.

2. Training Certification Form 11000-B as specified in Part 3.

3. Product literature to provide a complete description of the equipment.

4. Drawings, catalog information and cut sheets, and performance data.

5. Contract Closeout Submittals: Furnish Operations and Maintenance

PART 3 -- EXECUTION

3.01 BIOFILTER INSTALLATION

A. GENERAL:

Contractor shall provide for on-site installation, oversight and start-up services by a

qualified factory-trained equipment manufacturer's representative. As a condition precedent to

the final acceptance of the work, the manufacturer's representative shall demonstrate to the

Engineer that the equipment has been properly installed, aligned and tested and meets all

requirements for satisfactory performance under the conditions specified herein. Installation and

trial operation shall be certified on Form 11000-A as specified in Section 01999.

Do not permit workers to walk or stand directly on gravel or other materials that are less

than 1/2-inch in diameter. Use boards that will sustain workers’ weight without displacing gravel.

Elevations shall be surveyed at the biofilter floor, top of plenum zone, and top of soil

media to establish correct slope and correct thickness of each layer.

Do not compact materials per section 3.02.

Page 54: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-12 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

3.02 PLACING MEDIA

A. PLACEMENT INTO BED:

For activated soil media, remove debris from space to be occupied by soil filter bed.

Use placement devices, for example, chutes, pouring spouts, and conveyors or as

approved by System Supplier.

If applicable to the biofilter system, plenum zone gravel shall be placed in a manner that

will limit displacement of air distribution piping, if any. Plenum zone gravel shall be raked level

and undisturbed prior to placement of activated soil media.

B. HOT WEATHER:

Make provisions for windbreaks, shading, fog spraying, sprinkling, wet cover, or other

means to maintain media with a wet surface.

Addition of chemical wetting agents or other additives is not allowed.

C. BEDDING, PLENUM ZONE, AND SOIL FILTER MEDIA:

For activated soil based biofilters, place in layers as specified below:

Gravel Layer LAYER THICKNESS Size Limits

Air Distribution Layer 12 to 24 inches 1 inch followed by 3/8 inch

Soil Filter Media Up to 6 feet (place to prevent

aggregation)

Complete each layer before next layer above is started. Use only clean gravel.

3.03 ODOROUS AIR PIPING INSTALLATION

Where air distribution piping and headers are used, the following procedures shall be

followed:

A. EXAMINATION:

Verify size, material, joint types, elevation, horizontal location, and pipe service of

existing pipelines to be connected to new pipelines or new equipment.

B. PREPARATION:

Inspect pipe and fittings before installation, clean ends thoroughly, and remove foreign

matter and dirt from inside.

Page 55: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-13

C. INSTALLATION-GENERAL:

Joint pipe and fittings in accordance with manufacturer’s instructions, unless otherwise

shown or specified. Remove foreign objects prior to assembly and installation.

D. FLANGED JOINTS:

Install perpendicular to pipe centerline. HDPE flange with no bolt holes. Use torque-

limiting wrenches to ensure uniform bearing and proper bolt tightness.

Use flat-face flange when joining with flat-faced FRP flange. Use minimum 1/4” thick

neoprene gaskets.

3.04 SOIL FILTER PIPE INSTALLATION

A. PLACEMENT:

Keep trench dry until pipe laying and joining are completed. Exercise care when lowering

pipe into trench to prevent twisting or damage to pipe and stubs. Measure for grade at pipe

invert, not at crown.

Excavate trench bottom and sides of ample dimensions to permit visual inspection and

testing of entire flange, valve, or connection. Prevent foreign material from entering pipe during

placement.

Close and block open end of last laid pipe section when placement operations are not in

progress and at close of day’s work. Lay pipe upgrade with bell ends pointing in direction of

laying. After joint has been made, check pipe elevation at pipe ends and corners of soil filter

piping network.

3.05 BIOFILTER TESTING

A. FUNCTIONAL TESTING:

Test all system components for proper adjustment and operation in both the manual and

automatic operating modes. Air system testing, adjusting, and balancing shall be provided as

specified in Section 15990.

SPRINKLER SYSTEM: Allow the biofilter to operate for a 24-hour period with the

moisture control system in the AUTO mode and monitor moisture setpoint control and proper

sprinkler nozzle operation. Make adjustments as necessary for proper moisture system

operation.

Provide certification of functional acceptance prior to commencing performance testing.

Page 56: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-14 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

B. PERFORMANCE TESTING:

1. GENERAL:

a. To demonstrate that the biofilter system furnished hereunder is

installed and performs in accordance with the provisions of these

Specifications, the Contractor, under the supervision of the System

Supplier, shall conduct a performance test in accordance with an

approved testing protocol. The performance test shall not

commence until a test plan has been received and approved, and

the functional testing has been completed. Performance tests shall

last for a continuous period not less than 6 hours.

b. A sufficient quantity of bottled hydrogen sulfide gas shall be

introduced into the biofilter inlet ducting to raise the average

concentration of hydrogen sulfide gas in the influent airstream to

10 ppmv, excluding moisture, at the design air flow on a con-

tinuous basis for the test duration.

c. The System Supplier shall provide, install, and maintain, if

required, all temporary metering or analytical equipment necessary

to perform the tests and to measure the various performance

parameters.

d. The System Supplier shall inform the Engineer at least 14 days

prior to the start of any performance testing. The Engineer shall

have the right to observe, sample, and make any parallel

determinations during the performance test.

e. Within 10 days after the conclusion of the test period, the System

Supplier shall submit a Performance Test Report, including all

laboratory and field test data, stating the conclusions of the test

with regard to the performance criteria.

C. TEST CONDITIONS:

The biofilter shall have been fully functional and receiving odorous air from the facility

for a minimum of 14 consecutive days prior to commencing the testing.

Smoke tests shall be performed to confirm uniformity of airflow through the biofilter.

Smoke tests shall only be conducted on low-wind periods (wind-speed <2 knots). Tests shall be

conducted after installation of distribution piping, and after laying media. A smoke generating

stick shall be lit and placed in the ductwork. Smoke distribution at the piping outlets and at

biofilter surface shall be uniform.

All testing, adjusting, and balancing shall have been completed and approved.

Page 57: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-15

The actual sample day shall be chosen to limit weather interference.

D. SAMPLING AND DATA MEASUREMENT:

During the 6-hour test period, at a minimum, the following data and measurements shall

be taken at the frequency indicated:

1. SAMPLING PARAMETERS: Inlet air temperature, inlet air relative

humidity, inlet airflow rate, media temperature, media differential pressure, and other data as may be

appropriate: Initially

2. FAN AIRFLOW RATE: Initially. The airflow rate shall be as specified in

13565-1.01 E.

3. FAN DISCHARGE PRESSURE IN INCHES OF WC: Initially.

Discharge pressure shall be as specified in 15828.

4. UNIT AIRFLOWS (cfm/ft2): shall be taken at four (4) locations across

the biofilter; two corners and two equally spaced locations in the interior of the bed. These

measurements shall be taken at the beginning of the 6-hour test.

5. HYDROGEN SULFIDE AND AMMONIA CONCENTRATIONS (PPB)

AT THE INLET TO THE BIOFILTER: Every hour.

6. HYDROGEN SULFIDE AND AMMONIA CONCENTRATIONS (PPB)

AT TWO LOCATIONS ON THE BIOFILTER BED USING A FLUX CHAMBER: Every

hour. The results will then be calculated by:

a. Percent Removal = (Average Inlet – Average Outlet)/Average Inlet

Note: percent Removal is only calculated when the biofilter inlet

sample concentrations of hydrogen sulfide and ammonia are

greater than 10 ppmv and 50 ppmv, respectively. For

concentrations less than 10 ppmv hydrogen sulfide and 50 ppmv

ammonia, all Average Biofilter Outlet samples must be less than

100 ppbv for hydrogen sulfide and less than 5 ppmv ammonia to

meet performance verification requirements.

7. TOTAL ODOR SAMPLING: After the second and fourth hours, foul air

samples shall be collected at two locations on the biofilter bed using a flux chamber and an air

sampling pump. Each sample shall be pumped into a 10-liter Tedlar bag. Each sample shall be

analyzed within 24 hours by a 10-member odor panel at a 20-liter per minute presentation rate

for determination of dilution to threshold (D/T) values. Testing shall be in accordance with the

laboratory’s published standards.

8. PHOTOGRAPHIC RECORD: A photographic record of the sampling

technique and bed sampling location will be completed for each type of sampling.

Page 58: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

13565-16 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

9. SAMPLING LOG: A sampling log shall be maintained that will include:

a. A hand-drawn map showing the approximate locations of all bed

sampling locations.

b. Date, time, location, sampler, and results of each sample.

c. A description of each photograph taken.

d. Weather conditions for the sampling day.

e. A description of any exceptions from the sampling plan.

10. HYDROGEN SULFIDE SAMPLING: Hydrogen sulfide sampling shall

be completed using a Jerome Analyzer with a detection limit of 1 ppbv. The analyzer shall be

operated in compliance with the manufacturer’s instructions. A copy of the instructions shall be

submitted with the final report. The results of the hydrogen sulfide sampling shall be recorded in

the sampling log.

11. AMMONIA SAMPLING: Ammonia sampling shall be completed with

detector sampling tubes. Tubes shall be used in compliance with the manufacturer’s written

instructions. A copy of the instructions shall be submitted with the final report. The results of

the ammonia sampling will be recorded in the sampling log.

After use, all tubes will be labeled and placed in a sealed plastic bag. They shall

be stored in a refrigerator for 2 weeks as a temporary record of the sampling. They shall be

destroyed after 2 weeks unless a specific request is made to deliver them to the Owner.

3.06 MANUFACTURER’S SERVICES

A representative for the System Supplier specified herein shall be present at the jobsite

for the minimum person-days listed for the services herein under, travel time excluded:

1. Five person-days for installation assistance, inspection, and certification of

the installation. Provide certificate.

2. Three person-days for functional testing, operator training, and

performance testing. In the event of unsatisfactory performance test,

additional time shall be required of the manufacturer to correct the

biofilter performance and retest the system.

3.07 MANUFACTURERS’ CERTIFICATE(S)

Provide manufacturers’ certificate(s) of proper installation.

Page 59: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

PACKAGED BULK MEDIA

BIOFILTER

DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13565-17

3.08 GUARANTEE

The System Supplier shall guarantee the useful life of the biofilter medium for a period of

at least 10 years and the System Supplier shall guarantee there will be no odors detectable a

distance of 50 feet beyond the edge of the biofilter bed. If any defects or faulty performance

occurs in that period, the System Supplier must make all necessary alterations, repairs, or

replacements free of charge. Requirements for monitoring, testing, recordkeeping, and frequency

of such activities pertinent to biofilter system components, including but not limited to the

media, shall be as directed by the System Supplier and shall be clearly outlined in the O&M

manual.

** END OF SECTION **

Page 60: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

MODIFICATIONS TO EXISTING STRUCTURES, PIPING, AND

EQUIPMENT DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13900-1

SECTION 13900

MODIFICATION TO EXISTING STRUCTURES, PIPING AND EQUIPMENT

PART 1 -- GENERAL

1.01 DESCRIPTION A. GENERAL: This Section specifies the modification of existing structures, piping, and equipment.

Modifications listed in this Section supplement work that is shown or specified elsewhere, however, the Contractor is cautioned that this is not a comprehensive list of all of the minor modifications and refurbishments required, specified or otherwise indicated in other locations in the Contract Documents.

The Contractor shall furnish all labor, material, equipment including any associated

electrical equipment and electrical supply, and incidentals required to modify the existing structures, piping, and equipment specified in this Section. Existing piping and equipment shall be dismantled and restored in accordance with the Contract Documents as necessary for the performance of the modifications to equipment, structures, and piping specified in this Section.

Throughout the execution of this project, the Contractor shall protect those portions of the

facilities being operated by plant staff from dust, debris, water, sludge or other damage, permanent or temporary, resulting from construction activities.

The Contract Documents reflect knowledge of conditions at the time of design and may

not reflect actual conditions to be encountered by the Contractor. The Contract Documents do not show or specify all features of the existing facilities that may impact the modification work. Other conditions may be hidden from view or may be otherwise inaccessible during the bid period. The Contractor shall evaluate the risk of each modification specified and shall incorporate into their bid price this risk such that change orders are not required. Additional funds above those bid will not be provided for the completion of the work specified in this Section except as specifically detailed in this Section.

Prior to initiating work, the Contractor shall field verify all pertinent features of existing facilities, including but not limited to the following: structures, including architectural features; piping, including all pipeline appurtenances and supports; mechanical equipment, including appurtenances and supports; electrical conduits, cables, trays, lights, panels, cabinets, circuits, and appurtenances and supports necessary to complete the work. The Contractor is responsible for identifying and resolving conflicts between modification work, existing facilities, and new construction. The proposed conflict resolution is subject to review and approval by the Engineer. The Contractor shall plan its work such that field verification, conflict identification, conflict resolution, and Engineer approval are accomplished prior to initiating modification work in the field.

Page 61: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

MODIFICATIONS TO EXISTING STRUCTURES, PIPING, AND EQUIPMENT 13900-2 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

Existing penetrations of floors, ceilings and walls, or holes resulting from removal of fasteners or other hardware, which are no longer required because of abandonment of piping or equipment, shall be sealed. Pipe penetrations required as part of this work shall be sealed in a professional and workmanlike manner.

Locations of all existing equipment, piping and appurtenances shall be field verified by

the Contractor. The Contractor shall dispose of all equipment, piping, conduit, wiring, and appurtenances removed, except items specifically designated in the Contract Documents. PART 2 -- PRODUCTS (NOT USED)

PART 3 -- EXECUTION

3.01 GENERAL STRUCTURAL MODIFICATIONS

The Contractor shall cut, repair, reuse, excavate, demolish, or otherwise remove parts of the existing structures, piping, and appurtenances, as indicated on the Contract Drawings, herein specified, or necessary to permit completion of the work under this Contract. The above work shall include drilling of holes into existing concrete for the purpose of setting dowel rods, anchor bolts, or other appurtenances and cutting of holes in concrete and/or masonry for the installation of pipe, conduits, and other appurtenances. The work shall include all necessary cutting and bending of reinforcing steel, structural steel, or miscellaneous metal work found embedded in the existing structures.

Anchor bolts for equipment and structural steel removed together with exposed

reinforcement steel shall be cut off 1 inch below the concrete surface. When removing materials or portions of existing structures and when making openings in

walls and partitions, the Contractor shall take all precautions and use all necessary barriers and other protective devices so as not to damage the structures beyond the limits necessary for the new work, nor to damage the structures or contents by falling or flying debris.

All work for altering existing structures shall comply with the approved construction

schedule. Holes in existing concrete or masonry resulting from modification work shall be sealed

with concrete or cement mortar. The sides of the openings shall be provided with keyed joints and shall be suitably roughened to furnish a good bond and make a watertight joint. All loose or unsound material adjacent to the opening shall be removed and, if necessary, replaced with new material. The method for placement of the concrete or grout seal shall provide a suitable means of releasing entrapped air.

Surfaces of seals visible in the completed work shall be made to match as nearly as

possible the adjacent surfaces.

Page 62: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

MODIFICATIONS TO EXISTING STRUCTURES, PIPING, AND

EQUIPMENT DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13900-3

3.02 GENERAL EQUIPMENT AND PIPING MODIFICATIONS

The Contractor shall modify or dismantle and remove all existing equipment, piping and other appurtenances required for the completion of the work. Where called for or required, existing pipelines shall be cut for the purpose of making connections thereto or providing both temporary and permanent blind flanges. Removal of equipment shall include all appurtenances and connections, including electrical. Removal of electrical connections shall include all conductors back to source unless otherwise specified, together with unused conduit.

Modification and/or relocation of work shall include all process, auxiliary, drainage,

supply, structural, electrical, and control connections as specified and as necessary to yield a complete operational installation.

Where necessary or required for the purpose of making connections, the Contractor shall

cut existing pipelines in a manner to provide an approved joint. Where required, the Contractor shall weld beads, flanges or provide couplings, as required. Pipe ends shall be capped using groove-end fittings, welded flange or cap, standard blind flanges, or other method approved by the Engineer. Coatings, linings and insulation on existing pipelines modified by the work shall be repaired to new condition, or to the maximum extent practical, as directed by the Engineer.

All temporary piping used in the construction of the work of this contract shall conform

to the requirements of Section 15050, except as otherwise authorized by the Engineer. 3.03 GENERAL MODIFICATIONS

The floor slabs or walls may contain buried and undocumented electrical conduit and

mechanical piping systems. Prior to saw cutting or core drilling, locate encased rebar, conduits, piping, etc. Floor areas surveyed shall be marked and labeled identifying obstructions found when available.

Prior to installation of equipment, the following information shall be provided in

accordance to Section 01300 submittal:

1. A copy of this specification section, with addendum updates included, and all referenced and applicable sections, with addendum updates included, with each paragraph check-marked to indicate specification compliance or marked to indicate requested deviations from specification requirements or those parts which are to be provided by the Contractor or others. Check marks (√) shall denote full compliance with a paragraph as a whole. If deviations from the specifications are indicated, and therefore requested by the Contractor, each deviation shall be underlined and denoted by a number in the margin to the right of the identified paragraph, referenced to a detailed written explanation of the reasons for requesting the deviation. The Engineer shall be the final authority for determining acceptability of requested deviations. The remaining portions of the paragraph not underlined will signify compliance on the part of the Contractor with the

Page 63: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

MODIFICATIONS TO EXISTING STRUCTURES, PIPING, AND EQUIPMENT 13900-4 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

specifications. Failure to include a copy of the marked-up specification sections, along with justification(s) for any requested deviations to the specification requirements shall be cause for rejection of the entire submittal and no further submittal material will be reviewed.

2. A copy of the contract document control diagrams, process and

instrumentation diagrams and mechanical layout drawings relating to the submitted equipment, with addendum updates that apply to the equipment in this section, marked to show specific changes necessary for the equipment proposed in the submittal. If no changes are required, the drawing or drawings shall be marked “no changes required”. Failure to include copies of the relevant drawings with the submittal shall be cause for rejection of the entire submittal with no further review.

3. Certificate of Unit Responsibility attesting that the Contractor has

assigned unit responsibility in accordance with the requirements of this section and paragraph 11000-1.02. No other submittal material will be reviewed until the certificate has been received and found to be in conformance with these requirements.

4. Applicable operations and maintenance information as specified in

specification Section 01730. 5. Equipment control wiring diagram identifying internal and face mounted

components and connections to remote equipment. 6. Shop drawings indicating construction and installation details, a complete

detailing of the materials construction and equipment number, unit capacity and weights.

7. Factory testing information either as standard from the manufacturer or as

specifically required in this section. 8. Dimensioned drawings of all equipment and accessories as a complete

system including cross-section views. 9. Warranty information.

10. Dimensional drawings, showing required access and clearances, including

any layout and installation requirements of the equipment. 11. Manufacturer’s catalog and/or other data confirming conformance to the

specified design, material, and equipment requirements.

Page 64: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

MODIFICATIONS TO EXISTING STRUCTURES, PIPING, AND

EQUIPMENT DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 13900-5

12. Predicted performance data confirming conformance to the specified performance requirements.

** END OF SECTION **

Page 65: SECTION 13230 FIBERGLASS REINFORCED PLASTIC ...ASTM D3982 Standard Specification for Contact Molded “Fiberglass” (Glass Fiber Reinforced Thermosetting Resin) Duct and Hood ASTM

MODIFICATIONS TO EXISTING STRUCTURES, PIPING, AND EQUIPMENT 13900-6 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014

THIS PAGE INTENTIONALLY LEFT BLANK