© 2008 Eventure Events. All rights reserved. Supply Chain Analytics Using Business Intelligence Elaina Ball – Director, Supply Chain Ralph Shay - Enterprise Application Delivery CPS Energy

Transcript of Sap Utilities Sca

Page 1: Sap Utilities   Sca

© 2008 Eventure Events. All rights reserved.

Supply Chain AnalyticsUsing Business Intelligence

Elaina Ball – Director, Supply Chain

Ralph Shay - Enterprise Application DeliveryCPS Energy

Page 2: Sap Utilities   Sca

• Business perspective– CPS Energy

– Supply Chain at CPS Energy

• IT perspective– SAP solutions at CPS Energy

– Supply Chain Analytics project

• Results and lessons learned

• Q & A

Presentation Outline

Page 3: Sap Utilities   Sca

• Nation’s largest municipally owned energy company (electric & gas)

• Assets approaching $9 billion• 680,000 electric customers• 319,000 gas customers• Highest financial ratings of any U.S.

electric system• Customers’ combined energy bills

rank among the lowest of the nation’s 20 largest cities

Company Profile

Page 4: Sap Utilities   Sca

• #1 in Customer Satisfaction– Provide reliable, low cost,

environmentally responsible energy to our customers

• Great place to work– Customer Commitment

– Performance

– Safety

– Respect

– Teamwork

– Trust

Vision

Page 5: Sap Utilities   Sca

• Business Objectives - support corporate objectives by striving for– Demand forecast accuracy– Perfect order fulfillment– Minimized costs

• Organizational Alignment– Organization based on customer fulfillment streams

(Materials, Contracts, Fleet)

• Performance Metrics– Transform supply chain operational transaction data

into performance metrics to identify improvement opportunities and track performance trends.

Supply Chain Strategy

Page 6: Sap Utilities   Sca

Business Objective: Reliability

Supply Chain enablement through:– Perfect order fulfillment through demand

forecast accuracy

– Services and materials available when needed, as specified

Seeking perfection in delivery is how we support reliability.

Business Perspective,Supply Chain alignment

Page 7: Sap Utilities   Sca

Business Objective: Low cost energy

Supply Chain Enablement through:– Reduced cost of supply

– Lower internal operating costs

– Strategic sourcing and spend management

Seeking lower cost of supply is how we support low cost energy for customers.

Business Perspective,Supply Chain Alignment

Page 8: Sap Utilities   Sca

Business Objective: Environmental responsibility

Supply Chain Enablement through:– Elimination of waste in business processes– Reduction of excess inventory– Reduction of errors

Seeking waste reduction is how we support environmental responsibility.

Business Perspective,Supply Chain Alignment

Page 9: Sap Utilities   Sca

Business Perspective,Supply Chain Context

How accurate is the plan compared to actual?How long does it take to process purchasing

documents?

What is the fill rate?

What opportunity exists for reducing inventory valuation while improving availability?

Page 10: Sap Utilities   Sca

1. Purchasing document cycle time

2. Inventory replenishment cycle time

3. Supply chain cycle time

4. Line count fill rate

5. Inventory accuracy

6. Inventory transfers between storage locations

7. Inventory usage

8. Inventory rationalization

Business Perspective,Supply Chain Scorecard

Page 11: Sap Utilities   Sca

9. Inventory consumption forecast vs. actual inventory consumption

10.Schedule forecast vs. actual start/complete

11.Volume of supply chain transactions

Business Perspective,Supply Chain Scorecard (cont’d)

Page 12: Sap Utilities   Sca

• SAP R/3 4.6c implemented late 2001

• Supply Chain use of SAP ERP primarily transactional with limited use of LIS

• SRM, SCM not implemented at this time

• BW 3.5 in place when Supply Chain presented need for analytics

• Commitment to upgrade to ECC 6.0 and BI 7.0 made after Supply Chain analytics project was launched

IT Perspective,Information Technology Context

Page 13: Sap Utilities   Sca

• Establish formal software development project

• Follow disciplines of PMO and SDLC

• During planning phase, prototype scorecard reports using data extracted from SAP R/3 tables

• Use prototypes to engage stakeholders and improve design through active use

• Prototyped reports serve as BI frontend design targets

IT Perspective,Project approach

Page 14: Sap Utilities   Sca

IT Perspective,Prototype example

Page 15: Sap Utilities   Sca

IT Perspective,Prototype example

Page 16: Sap Utilities   Sca

• Sapient Consulting engaged to provide professional services for BI 7.0 upgrade and Supply Chain Analytics development

• Consultants assigned to the engagement had extensive experience with:– Project management

– Utilities clients

– Supply Chain clients

– SAP BW and BI 7.0

IT Perspective,Professional services

Page 17: Sap Utilities   Sca

• Organize project execution phase into iterations to deliver “quick wins”

• Iteration 1 scoped to deliver scorecard reporting related to cycle time– Purchase Order Cycle Time

– Inventory Replenishment cycle time

– Supply Chain Cycle time

IT Perspective,Consultant’s recommendations

Page 18: Sap Utilities   Sca

IT Perspective,Consultant’s recommendations

Page 19: Sap Utilities   Sca

IT Perspective,Consultant’s recommendations

Page 20: Sap Utilities   Sca

IT Perspective,Consultant’s recommendations

Multiprovider for summary information

Page 21: Sap Utilities   Sca

IT Perspective,Consultant’s recommendations

Multiprovider from DSOs for jump queries

Page 22: Sap Utilities   Sca

IT Perspective,Sample results

Page 23: Sap Utilities   Sca

IT Perspective,Sample results

Page 24: Sap Utilities   Sca

IT Perspective,Sample results

Page 25: Sap Utilities   Sca

• Iteration 1 delivered January 2008– Purchasing document cycle time reporting

• Iteration 2 delivered July 2008– Demand forecast accuracy reporting

• Information delivered used to support continuous process improvement and operational efficiencies in the supply chain

Results,Project deliverables

Page 26: Sap Utilities   Sca

Example-Material Lead Time

Page 27: Sap Utilities   Sca

Business Explorer Sample Output. ..

Page 28: Sap Utilities   Sca

• Prototypes used to drive early business results– Identified excess inventory to drive decisions for

inventory reduction in excess of $5MM

– Identified opportunities for improved contract management to drive down inventory replenishment cycle time and reduce stock outs

– Prototypes of demand accuracy results supported cross-functional dialogue seeking improvement

• Process and transaction system “anomalies” exposed during data analysis and reconciliation

Results,Project “side benefits”

Page 29: Sap Utilities   Sca

• Knowledge transfer from consultants strengthened in-house BI team skills

• Supply Chain Information Team participation created foundational skills and knowledge for future extension of supply chain analytics in BI environment

• Experience with iteration 1 and iteration 2 project plans, budgets and results will serve to improve future BI project plans and cost estimates

Results,Project “side benefits”

Page 30: Sap Utilities   Sca

• Prototyping reports using data extracted from SAP tables helped stakeholders define reporting data sources and uses

• Professional services from an experienced consulting firm benefited both business and IT stakeholders

• Combining technical upgrades with a development project added complexities requiring a “program” approach to project management

Lessons Learned

Page 31: Sap Utilities   Sca

• BI projects are not simply about reporting– Security model

– Process chain reliability

– Information distribution choices

– End user training needs and considerations

• Development iterations deliver value earlier and allow the application of lessons learned to improve subsequent iterations

Lessons Learned

Page 32: Sap Utilities   Sca

Recap,Q & A

• Business perspective– CPS Energy

– Supply Chain at CPS Energy

• IT perspective– SAP solutions at CPS Energy

– Supply Chain Analytics project

• Results and lessons learned

• Q & A