ACKNOWLEDGEMENT
I first thank my Almighty God and my parents for their sustained blessings
and grace at all stages of my training.
I render my unfathomable gratitude and special institute to P.Saravanan,
Asst.Prof. (Sr.G) for his valuable guidance, remedial encouragement, timely
suggestions and his deference shown during the preparation of this dissertation.
I render my special thanks to our College Management and to our beloved Dean
Dr.Jayshree Suresh, for giving me this opportunity to carry out this Project.
Last but not the least, I thank my friends and well wisher for their good
cooperation while I am doing my project.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
3/193
BONAFIDE CERTIFICATE
Certified that this project report titled IMPLEMENTING SAP ERP IN ABP Ltd
is the bonafide work of Balasubramanian.L who carried out the research under my
supervision.
Certified further, that to the best of my knowledge the work reported here in doesnot form part of any other Project report or dissertation on the basis of which a
degree or award was conferred on an earlier occasion on this or any other
candidate.
Date:
Place: Student signature
PROJECT GUIDE HEAD OF THE MBA
P.Saravanan . Asst.Prof.(Sr.G) DR.JAYSHREE SURESH
. ..
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
4/193
SAP Implementation of
FI, CO, MM, PP
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
5/193
Table of Contents1. INTRODUCTION ............................................................................................................................................ 6
1.1SAPLANDSCAPE.............................................................................................................. 6
1.2SAPR/3OVERVIEW......................................................................................................... 8
1.3OBJECTIVE OF THE PROJECT......................................................................................... 10
2. ASAP METHODOLOGY .............................................................................................................................. 11
2.1PROJECT PREPARATION................................................................................................. 12
2.2BUSINESS BLUEPRINT..................................................................................................... 12
BUSINESS BLUEPRINT ................................................................................................................................... 13
2.2.1 Requirements ............................................................................................................................... 102.2.2 Existing Organisation Structure ................................................................................................ 112.2.3 Overview of Organizational Structure ...................................................................................... 12
REALIZATION .................................................................................................................................................. 18
2.3 REALIZATION.......................................................................................................... 142.3.1 Configuration of FI ..................................................................................................................... 152.3.2 CO ............................................................................................................................................... 163
2.3.3 MM ..................................................................................................................................................................................170
2.3.4 PP..................................................................................................................................................182
3.CONCLUSION...188
4.BIBLIOGRAPHY.189
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
6/193
1. Introduction
SAP Implementation is the whole of processes that defines a complete method to
implement the Enterprise Resource Planning SAP ERP software in an organization. The SAP
implementation method described in this entry is a generic method and not a specific
implementation method as such. It is based on best practices and case studies from various
literature sources and presents a collection of processes and products that make up a complete
implementation method to allow any organization to plan and execute the implementation of
SAP software
The Generic methods consist of the following steps:
Phases
Delivery Group
Activities
Task
The implementation of SAP software, such as SAP R/3 is almost always a massive operation that
brings a lot of changes in the organization. The whole process can take up to several years.
1.1 SAP Landscape
Landscape is like a server system or like a layout of the servers or some may even call it
the architecture of the servers viz. SAP is divided into three different landscapes Development,
Quality and Production.
- Development (DEV)is where the consultants do the customization as per the company's
requirement. It would have multiple clients for ex: 190- Sandbox, 100- Golden, and 180- Unit
Test.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
7/193
- Qualityis where the core team members and other members test the customization. Quality
may again have multiple clients for ex: 300- Integration Test, 700 to 710 Training.
- Productionis where the live data of the company is recorded. It may have something like a
200 Production.
These names and numbers are the implementer's discreet on how they want it or they
have been using in their previous implementations or how are the client's business scenario.
Now whatever we do in the Sandbox doesn't affect the other servers or clients. Whenever
we are satisfied with our configuration and we can use it moving forward, we RE-DO it in the
golden client (this is a very neat and clean client and we cannot use it for rough usage). As we re-
do everything that we thought was important and usable, we get a transport request pop up upon
saving every time. we save it under a transport request and give our description to it. Thus the
configuration is transported to the Unit Test client (180 in this example).
Now upon a successful transport by the Basis guy, we have the entire configuration in the
Testing client, just as it is in the Golden client. The configuration remains in sync between these
two clients.
But in the Testing client we can not even access SPRO (Display IMG) screen. It's a transaction
only client where you perform the unit test. Upon a satisfactory unit test, we can move the good
configuration to the next Server (DEV). The incorrect or unsatisfactory configuration is
corrected in Golden (may again as well be practiced in the sandbox prior to Golden) and
accordingly transported back to 180 (Unit Test) until the unit test affected by that particular
configuration is satisfactory.
The Golden client remains the 'database' or we may rather call it the 'ultimate' reference client forthe entire good, complete and final configuration that is being used in the implementation.
These three are landscape of any Company. They organized their office in these three ways.
Developer develops their program in Development server and then transports it to test server. In
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
8/193
testing server tester check/test the program and then transport it to Production Server. Later it
will deploy to client from production server.
1.2 SAP R/3 Overview
SAP R/3 is SAP's integrated software solution for client/server and distributed open
systems. SAP's R/3 is the world's most-used standard business software for client/server
computing. R/3 meets the needs of a customer from the small grocer with 3 users to the multi-
billion dollar companies The software is highly customizable using SAP's proprietary
programming language, ABAP/4. R/3 is scalable and highly suited for many types and sizes of
organizations.
R/3 stands for real-time three tier architecture. This is the kind of architecture SAP R/3 systemhas.
R/3 means three layers are installed in Different system/server and they are connected with each
other.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
9/193
Web-enabled
A p p l i c a t i o n
P r e s e n t a t i o n
I n t e r n e t
T r a n s a c t i o n
Se r v ic e / W e b
S e r v i c e
D a t a b a s e
Presentation Layer
The presentation server is actually a program named sapgui.exe. It is usually installed on
a user's workstation. To start it, the user double-clicks on an icon on the desktop or chooses a
menu path. When started, the presentation server displays the R/3 menus within a window. This
window is commonly known as the SAPGUI, or the user interface (or simply, the interface). The
interface accepts input from the user in the form of keystrokes, mouse-clicks, and function keys,
and sends these requests to the application server to be processed. The application server sends
the results back to the SAPGUI which then formats the output for display to the user.
Application Layer
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
10/193
An application server is a set of executables that collectively interpret the ABAP/4
programs and manage the input and output for them. When an application server is started, these
executables all start at the same time. When an application server is stopped, they all shut down
together. The number of processes that start up when you bring up the application server is
defined in a single configuration file called the application server profile. Each application server
has a profile that specifies its characteristics when it starts up and while it is running.
Database Layer
The database layer consists of a central database system containing all of the data in the
R/3 System. The database system has two components - the database management system
(DBMS), and the database itself. SAP does not manufacture its own database. Instead, the R/3
System supports the following database systems from other suppliers: ADABAS D, DB2/400
(on AS/400), DB2/Common Server, DB2/MVS, INFORMIX, Microsoft SQL Server, ORACLE,
and ORACLE Parallel Server.
1.3Objective of the project
Primary Objective
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
11/193
To explain about the end to end process of implementation of SAP
To do the configuration part in FI & CO for ABP Ltd
Secondary objective
To study the concepts of preparing business blueprint
To explain about phases of ASAP Methodology
To brief about step by step Realization part of FI , CO & SD
To discuss about the Testing methodologies
To explain about the requirements of ABP Ltd limited
2. ASAP Methodology
Project
preparation BlueprintingRealization
Final
preparation Go-live
Definition Requirements Design Build Test Implementclose-out
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
12/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
13/193
BUSINESS BLUEPRINT
2.2.1 Requirements
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
14/193
ABP Ltd manufactures and distributes Tyres and tubes. It has operations in India. The products
are sold throughout India. The company has four manufacturing plants located at Tamilnadu,Kerala,Karnataka, and Andhrapradesh in India.
Tamilnadu plant produces Three stone Tyres, Karnataka plant produces Tubes, Kerala Plant
produces Tubeless tyres, and AP plant produces Radial tyres.The purchasing organization at each plant looks after the material needs of the plants
respectively. Each purchasing organization is managed by their respective purchasing groups. 2
purchasing groups are assigned to each purchasing organization VG (Vendor ProcurementGroups) and LG (Local Procurement Groups).
Each plant has two types of storage locations (one for parts, semi-finished materials and the otherfor finished products). Each manufacturing plant has its own shipping point.
The company has one sales organization which is responsible for Pricing, Selling and other Sales
related activities in India. Therefore, price of the products provided through the sales
organization should be the same in all the different states in India. There are two Distributionchannels assigned to the sales organization, Retail and Wholesale. All the grinders are sold to
both retailers and wholesalers by the sales organization. The sales area is divided into 4 Salesdistricts based on geographical region TN, KL, KA and AP. The Sales districts could use
different marketing strategies and promotion methods. Each sales district has 2 sales offices in
their area and sales offices are divided into sales groups based on geographical region- EastSuburb, West Suburb, South Suburb, North Suburb and other regional areas.
Sales Representatives or Sales persons, the responsible persons for sales are belong to salesgroups and report to sales office about the sales activity of customers. Each Sales Personnel has
own Sales employee ID. These are maintained in Customer master data as partner function andused in sales orders in SAP ERP.
ABP Ltd uses 2 business areas one for Tilting grinders division and the other for Tabletop
division. Thus, the financial statements including Profit and loss statement are generatedseparately for each division. 2 cost centres are assigned to each business areas based on product.
As the company manufactures 4 different types of products, each cost centre calculates all the
related costs for each product. A work centre is assigned to each cost centre based on the type ofthe grinders.
2.2.2 Existing Organisation Structure
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
15/193
ABP Ltd.
TN
ABP Ltd.
KL
ABP Ltd.
KA
ABP Ltd.
AP
ABP Limited
2.2.3 Overview of Organizational Structure
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
16/193
2. 2.3.1 FI & CO
BA55
BA55
ABP Ltd
BA77
Tyres
BA88
Tubes
BA01
Tyres
Contr
ngArea
Compa
Cod
Busin
Area
Cos
Cent
BA11
Productionof radial tyres
BA02
Tubes
BA22
Tubeless Tyres
CONTROLLING AREA
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
17/193
A Controlling area structures the internal accounting operations of an organization within
Controlling. They represent closed units that are used to calculate costs. All internal allocationsrelate solely to objects that belong to the same controlling area. ABP Ltd is under a controlling
area of the following:
Controlling Area DescriptionBA55 Controlling Area for ABP Limited
COMPANY CODE
A company code is the smallest organizational unit for which a complete self-contained set ofaccounts can be drawn up for the purposes of external reporting. As shown in the above diagram,
the following company code will be defined for ABP Ltd:
Company Code DescriptionBA55 ABP Limited
BUSINESS AREA
Business areas provide an additional evaluation level for the purpose of segment reporting. InFinancial Accounting (FI), internal balance sheets and profit and loss statements area generated
on the basis ofbusiness areas. ABP Ltd has 2 business areas for each division.
Business Area DescriptionBA77 Tyres
BA88 Tubes
COST CENTRE
Cost centres are used to collects related costs. There are 4 cost centres used for DG Ltd:
Cost Centre DescriptionBA01 TYRES
BA11 RADIAL TYRES
BA02 TUBELESS TYRES
BA22 TUBES
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
18/193
REALIZATION
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
19/193
2.3
Realization
In this phase, configure the requirements contained in the Business Blueprint. Baseline
configuration (major scope) is followed by final configuration (remaining scope), which can
consist of up to four cycles. Other key focal areas of this phase are conducting integration tests
and drawing up end user documentation.
2.3.1 Configuration of FI
2.3.1.1 To create an IMG Project:
Tools -> Customizing ->IMG ->Project Administration
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
20/193
click on the Create Project icon at the top of the screen.
Move on to scope, which is the next tab
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
21/193
Save it. Click on project team member
Change the project name as Dinesh and move on to status vals and select status and move into
right as shown below
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
22/193
Save the project and come back to the following screen
Then select SAP reference IMG in the top of the screen to do the configuration part.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
23/193
2.3.1.2 Define a company
Enterprise Structure -> Definition -> Financial Accounting -> Define Company
Click on New Entries and Enter the following:
Company: BA55Company Name: BA55
City: CHENNAI
Country: INLanguage Key: EN
Currency: INR
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
24/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
25/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
26/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
27/193
2.3.1.4 Assign Company Code to Company
Enterprise Structure -> Assignment -> Financial Accounting -> Assign Company Code to
Company
Enter CC05 against the company code CC05
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
28/193
2.3.1.5 Define Business area
Enterprise Structure -> Definition -> Financial Accounting -> Define Business Area
Click on New entries icon and enter the followings:
BA77 Tilting GrindersBA88 Tabletop Grinders
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
29/193
2.3.1.6 Define functional area
Enterprise Structure> Definition> Financial Accounting> Define Functional Area
Click on New entries icon and enter the followings:
FA55 ABP Manufacturing
FA66 ABP Sales
FA77 ABP General AdminFA88 ABP Financial Expenses
FA33 ABP AUC
FA99 ABP Sales Revenue
FA44 ABP Cost of Goods Sold
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
30/193
2.3.1.7 Define credit control area
Enterprise Structure > Definition > Financial Accounting > Define credit control area
Click on New entries and enter the following:
Credit Control Area: BA55 Credit control area ABP Ltd
Currency: INRUpdate: 000012 (Open order value on time axis, delivery and bill.doct value)
Fiscal Year Variant: K4
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
31/193
2.3.1.8 Assign company code to credit control area
Enterprise Structure > Assignment > Financial Accounting > Assign company code to credit
control area
Assign company code BA55 to Credit Control area BA55.
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
32/193
2.3.1.9 Define Chart of Accounts
Financial Accounting > General Ledger Accounting > G/L Accounts > Master Data >Preparations > Edit Chart of Accounts List
Click on New entries icon.Enter the followings:
Chart of Accounts: BA56Description: Chart of Accounts_ABP Ltd
Controlling integration: as manual creation of cost elements
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
33/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
34/193
2.3.1.10 Assign Company Code to Chart of Accounts
Financial Accounting > General Ledger Accounting > G/L Accounts > Master Data >Preparations > Assign Company Code to Chart of Accounts
Find company code BA55 and assign chart of account BA56 for both chart of account field andcountry chart of account field.
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
35/193
2.3.1.11 Copy G/L Accounts
Financial Accounting > General Ledger Accounting > G/L Accounts > Master Data > G/LAccount Creation and Processing> Create G/L Accounts with Reference
Enter company code BA55 and reference company code 1000 which you want to copy from.Save.
Click on Details icon.
Click on Accounts from reference icon and enter the accounts you want to copy from.
Click on G/L accounts creation icon.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
36/193
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
37/193
2.3.1.12 FINANCIAL ACCOUNTING GLOBAL SETTINGS
Enter Global Parameters
Enter Global Parameters
Financial Accounting > Financial Accounting Global Settings > Company code > EnterGlobal Parameters
Enter as follows:
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
38/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
39/193
Active Cost of Sales Accounting
Financial Accounting > Financial Accounting Global Settings> Company Code> Cost of
Sales Accounting> Activate Cost of Sales Accounting
Find the company code BA55 and Set to Active.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
40/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
41/193
Set Up Ledger for Cost of Sales Accounting
Financial Accounting > Financial Accounting Global Settings> Company Code> Cost of
Sales Accounting>Set Up Ledger for Cost of Sales Accounting
Double click on Ledger 0F, Cost of Sales Accountng Ledger.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
42/193
Click on Assign company code/ Company.
On the bottom area, find the company code (BA55) and click on ASSIGN.
Click Continue to accept pop up message.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
43/193
Find the company code (BA55) on the upper side and click on Assign Activity.Click on Choose Activity
Copy all the activity and Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
44/193
Enable business area Balance Sheet
Financial Accounting > Financial Accounting Global Settings> Business area> Enable
business area balance sheet
Find company code and tick on the Company code (BA55)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
45/193
Fiscal Year
Maintain Fiscal Year Variant
Financial Accounting > Financial Accounting Global Settings > Fiscal Year > Maintain
Fiscal Year Variant (Maintain shortened Fisc. Year)
Click on new entries and create fiscal year variant Z1.
Make 12 as ordinary posting period and 4 as special period.
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
46/193
Assign Company code to a Fiscal Year Variant
Financial Accounting > Financial Accounting Global Settings > Fiscal Year > Assign
Company code to a Fiscal Year Variant
Assign the company code BA55 to the fiscal year variant Z1
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
47/193
Posting Periods
Define Variants for Open Posting Periods
Financial Accounting > Financial Accounting Global Settings > Document> Posting period>
Define Variants for Open Posting Periods
Click on New entries and enter the following:
BA00 Variant for ABP Ltd
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
48/193
Open and Close Posting Periods
Financial Accounting > Financial Accounting Global Settings > Document> Posting period >
Open and Close Posting Periods
Click on New entries and enter periods for each account type A, D, K, M, S.
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
49/193
Assign Variants to Company Code
Financial Accounting > Financial Accounting Global Settings > Document> Posting period >
Assign Variants to Company Code
Assign the variant BA00 to the company code CC05
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
50/193
Document Number Ranges
Define Document Number Ranges
Financial Accounting > Financial Accounting Global Settings > Document> Document
Number Ranges > Define Document Number Ranges
Enter the company code BA55 and Define number ranges.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
51/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
52/193
Document Header
Define Document types
Financial Accounting > Financial Accounting Global Settings > Document > Document
header > Define Document Types
As document types are pre-defined in SAP, just make sure that Document types are correctly
exist which will be used for the FI process
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
53/193
Document Item
Define Posting keys
Financial Accounting > Financial Accounting Global Settings > Document> Line Item>
Controls> Define Posting Keys
Check posting keys which will be used for the FI process
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
54/193
Maintain Field Status Variants
Financial Accounting > Financial Accounting Global Settings > Document> Line Item>
Controls> Define Field Status Variants
Click on New entries and name field status variant as BA00
Click on Field Status groups folder on the left side of the screen.
Check the followings as field status groups:
BPS1 Direct Postings for FI: REV, B/S inc WBS
BPS2 Direct Postings for FI: COSTS incl WBS
G001 General (with text, allocation)G003 Material consumption accounts
G004 Cost accounts
G005 Bank accounts (obligatory value date)
G006 Material accounts
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
55/193
G007 Asset accts (w/o accumulated depreciatn)
G008 Assets area clearing accountsG009 Bank accounts (obligatory due date)
G011 Clearing accounts (with settlement per.)
G012 Receivables/payables clearing
G013 General (obligatory text)G014 MM adjustment accounts
G017 Freight/customs provisions/clearing (MM)
G018 Scrapping (MM)G019 Other receivables/payables
G023 Plant maintenance accounts
G025 Inventory adjustment accountsG026 Accounts for down payments made
G029 Revenue accounts
G030 Change in stock accounts
G031 Accounts for down payments received
G032 Bank accounts (obligat.value/due dates)G033 Cost accounts for external services
G036 Revenue accts (with profit center)G039 Accts for pmnts on acct made for assets
G040 Personnel clearing accounts
G041 Tax office clearing accountsG045 Goods/invoice received clearing accounts
G049 Manufacturing costs accounts
G050 Customer commission clearing accountsG052 Accounts for fixed asset retirement
G056 Amortization accountsG059 Inventory accounting material stock acct
G062 Investment support accounts
G064 Other cost accounts (obligatory text)
G067 Reconciliation accountsG068 Reconciliatn accts (payables - Austria)
G069 Cost accounts (travel expenses)
G070 Clearing accounts (travel expenses)G071 Reconcil.accts (KIDNO/foreign payment)
ICCF CO FI reconciliation posting
Z001 Reserves subsequent settlementZ002 Balance Sheet w. Profit Centre
ZFUN Client Funds
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
56/193
Assign Company Code to Field Status Variants
Financial Accounting > Financial Accounting Global Settings > Document> Line Item>
Controls> Assign Company Code to Field Status Variants
Assign the company code BA55 to field status variant just created BA00
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
57/193
Define Screen Variants for Document Entry
Financial Accounting > Financial Accounting Global Settings > Document> Line Item>
Controls> Screen Variants for Document Entry
Find the company code and proper variants. If withholding tax is used for document entry, clickon 2. This removes withholding tax field when document is entered.
If not used, leave it to standard version.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
58/193
Define Tolerance Groups for Employees
Financial Accounting > Financial Accounting Global Settings > Document> Line Item >
Define Tolerance Groups for Employees
Click on new entry and enter the followings:
Tolerance group: BA55
Amount per document : 90000000000Amount per open item account: 90000000000
Cash discount per line item: 5%
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
59/193
Assign to the tolerance group just created BA55 to the company code BA55
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
60/193
Document default values
Enable Fiscal Year Default
Financial Accounting > Financial Accounting Global Settings > Document>Default Valuesfor Document Processing> Enable Fiscal Year Default
Choose the company code BA55 and tick on propose fiscal year
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
61/193
Default Value Date
Financial Accounting > Financial Accounting Global Settings > Document>Default Values
for Document Processing> Default Value Date
Choose the company code and tick on propose value date
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
62/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
63/193
Define Run dates
Financial Accounting > Financial Accounting Global Settings > Document>Recurring
Entries> Enter Run Dates
Choose Run Schedule BA55 and enter the dates
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
64/193
Tax
Check Calculation Procedure
Financial Accounting > Financial Accounting Global Settings> Tax on Sales/Purchases>
Basic Settings> Check Calculation Procedure
Choose Define process
Choose TAXIN
Double click Control data folder on the left side of the screen
Check Condition types. If not exists as followings, create new entries
BASB Base Amount
MWAS Output TaxMWVZ Non-deduct.Input Tax
MWVS Input Tax
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
65/193
Click on Go back icon.
Choose Define Condition types
Find the condition types defined above. Double click on MWVS
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
66/193
Check its Access Sequence whether it is MWST
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
67/193
Click on Go back icon.
Choose Access Sequences
Find the Access sequence checked above. Double click on MWST
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
68/193
Double click Field folder on the left side and check the fields.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
69/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
70/193
Assign Country to Calculation Procedure
Financial Accounting > Financial Accounting Global Settings> Tax on Sales/Purchases>
Basic Settings> Assign Country to Calculation Procedure
Find the country IN and assign TAXIN to IN
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
71/193
Define Tax Codes for Sales and Purchases
Financial Accounting > Financial Accounting Global Settings > Tax on Sales/Purchases >
Calculation > Define Tax Codes for Sales and Purchases
Find the country key IN and enter new entry D1- Input tax_ABP Ltd
Choose V for tax type which is input tax.
Press Enter.
Enter 10% for Input tax as tax percentage rate
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
72/193
Click on Tax accounts icon on the menu bar and choose Chart of accounts BA56
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
73/193
Assign G/L account 154000 (Input tax) to transaction VST
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
74/193
Define Tax Accounts
Financial Accounting > Financial Accounting Global Settings>Tax on Sales/Purchases>
Posting> Define Tax Accounts
Find VST (Input tax) and click on details
Enter chart of Account (BA56)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
75/193
Enter Input tax account 154000
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
76/193
Find MWS (Output tax) and click on details
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
77/193
Enter chart of Account (BA56)Enter Output tax account 175000
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
78/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
79/193
Enable Business Area Balance Sheet
Financial Accounting> Financial Accounting Global Settings> Business Area> Enable
Business Area Balance Sheet
Find the company code BA55 and tick on Business area FS
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
80/193
2.3.1.13 GENERAL LEDGER ACCOUNTING
G/L Master
Define Accounts Group
Financial Accounting > General Ledger Accounting > G/L Accounts > Master Data >
Preparations > Define Accounts Group
Find company code BA55 and define account groups as follows:
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
81/193
Financial Accounting > General Ledger Accounting > G/L Accounts > Master Records >Preparations > Define Retained Earnings Accounts
Under Chart of Account BA55, Transaction: BIL Balance Carry Forward, enter retained
earnings account from the chart of account
P&L Statement Account type Account
X 900000 (Inappropriate retained earnings from previous yr)
Y 10900000 (AR60/Unapp.retained earnings from previous yr)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
82/193
G/L Line items
Define Line Layout
Financial Accounting > General Ledger Accounting > G/L Accounts > Line Items > Display
Line Item > Define Line Layout
Double click on the line layout and click onInsert after. Choose needed fields and save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
83/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
84/193
Choose Additional fields
Financial Accounting > General Ledger Accounting > G/L Accounts > Line Items > Line
Item Display > Choose Additional Fields
Enter account type as D (Customer) and click onInsert after. Choose needed fields and save.Repeat the above step for K (Vendor) and S (G/L account) if needed.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
85/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
86/193
Adjustment Posting Reversal
Permit Negative Posting
Financial Accounting > General Ledger Accounting > Business Transactions > Adjustment
Posting/Reversal > Permit Negative Posting
Find company code BA55 and tick on Negative postings allowed
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
87/193
Define Reasons of Reversal
Financial Accounting > General Ledger Accounting > Business Transactions > AdjustmentPosting/Reversal > Define Reasons of Reversal
Check reason codes and add reasons if needed.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
88/193
G/L Closing
Prepare Automatic Postings for Foreign Currency Valuation
Financial Accounting > General Ledger Accounting > Business Transactions > Closing >Valuating > Foreign Currency Valuation > Prepare Automatic Posting for Foreign CurrencyValuation
Double click on Exch. Rate Diff. using Exch. Rate Key, Transaction KDB.
Enter the Chart of Account CA05 and enter the followings:
230000 280000DEM 230000 280000
FRF 230000 280000USD 230000 280000
230000: Foreign currency Revaluation losses
280000: Foreign Currency Revaluation Gains
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
89/193
Save.
Go back to the previous screen and double click on Exchange Rate Dif.: Open Items/GL Acct,Transaction KDF
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
90/193
Click on G/L Account 420000
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
91/193
Enter the followings:
Exchange Rate Difference Realised:
Loss: 230000 (Foreign currency revaluation losses)Gain: 280000 (Foreign currency revaluation gains)
Valuation:Val. Loss 1: 230010 (Expense from currency revaluation)
Val. Gain 1: 280010 (Income from currency revaluation)Bal. Sheet adj: 144099 (Accounts Receivable- other companies (adj acct.))
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
92/193
Repeat the above the steps for the following accounts:
44000 46000 86100 86200 86300 99000 100009 102009 110002 110005 110009 113101
Go back to the previous screen and double click on Payment difference for altern.currency,
Transaction KDW.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
93/193
Enter the followings:
Debit Credit
230030 (Translation differences - foreign currency) 280000(Foreign Currency RevaluationGains)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
94/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
95/193
Define Adjustment Accounts for GR/IR Clearing
Financial Accounting > General Ledger Accounting > Business Transactions > Closing >
Reclassify > Define Adjustment Accounts for GR/IR Clearing
Double click on Invoiced but not yet delivered (BNG) and enter the chart of account CA05.
Enter the followings:
Reconciliation account: 191000, 191100 (Goods Rcvd/Invoice Rcvd)Adjustment account: 191099 (Adjustment GR/IR clearing)
Target account: 191101 (GR/IR: Goods/services not yet delivered)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
96/193
Go back to the previous screen.
Double click on Delivered but not yet invoiced (GNB).
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
97/193
Enter the followings:
Reconciliation account: 191000, 191100 (Goods Rcvd/Invoice Rcvd)
Adjustment account: 191099 (Adjustment GR/IR clearing)Target account: 191102 (GR/IR: Goods and services not yet invoiced)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
98/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
99/193
Define Financial Statement Versions
Financial Accounting > General Ledger Accounting > Business Transactions > Closing >
Document > Define Financial Statement Versions
Click on New entries and enter the followings:
Financial Statement Version: BA55
Name: Balance sheet ABP LtdMaintain Language: EN
Chart of Account: BA56
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
100/193
G/L Integration
Define Accounts for Materials Management
Financial Accounting > General Ledger Accounting > Business Transactions > Integration >Materials Management > Define Accounts for Materials Management
Double click on Expense/revenue from consign.mat.consum.(Transaction: AKO)
Enter the followings:
Valuation Class Account
3000 236000 Losses - consumption for consignmentsale
3001 236000 Losses - consumption for consignmentsale3030 236000 Losses - consumption for consignment
sale
3040 236000 Losses - consumption for consignmentsale
3050 236000 Losses - consumption for consignment
sale
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
101/193
3100 236000 Losses - consumption for consignment
sale7900 236000 Losses - consumption for consignment
sale
7920 236000 Losses - consumption for consignment
sale
Double click on Expense/revenue from Expense/revenue from stock transfer (Transaction:AUM)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
102/193
Enter the followings:
Valuation Class Account
3000 235000 Losses - inventory transfer3001 235000 Losses - inventory transfer
3030 235000 Losses - inventory transfer
3040 235000 Losses - inventory transfer3050 235000 Losses - inventory transfer
3100 235000 Losses - inventory transfer
7900 235000 Losses - inventory transfer7920 235000 Losses - inventory transfer
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
103/193
Double click on Subsequent settlement of provisions (Transaction: B01)
Debit Credit
192700 Bonus provisions (MM) 192700 Bonus provisions (MM)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
104/193
Double click on Subsequent settlement of revenues (Transaction B02) and enter the accounts to
repeat the above steps.
Debit Credit
281200 Contribution bonus differences 281200 Contribution bonusdifferences
Double click on Change in stock account (Transaction BSV)
Valuation
class
Account
3000 400020 Material Consumed3001 400020 Material Consumed
3002 400020 Material Consumed3030 400020 Material Consumed3040 400020 Material Consumed
3050 400020 Material Consumed
3100 400020 Material Consumed7900 893010 Cost of goods sold without cost element
7920 893010 Cost of goods sold without cost element
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
105/193
Double click on Inventory posting (Transaction BSX)
Val.
Class Account
3000 300000 Inventory - Raw Material 13001 300010 Inventory - Raw Material 2
3002 300010 Inventory - Raw Material 2
3030 303000 Operating supplies3040 304000 Spare Parts
3050 305000 Packaging material
3100 310000 Trading Goods3200 300000 Inventory - Raw Material 1
7900 790000 Unfinished products
7910
790010 Work in process from external
procurement
7920 792000 Finished goods inventory7925 792500 Finished goods inventory
Double click on Revaluation of other consumables (Transaction COC)
Val.
Class Debit Credit
0001
231099 ML PRD
consumption
231099 ML PRD
consumption
Double click on Materials management small differences (Transaction DIF)
Debit Credit231900 Small price loss - invoice receipt
(MM)
281900 Small price gains - recepit of
invoice (MM)
Double click on Purchasing account (Transaction EIN)Val.
Modif
Valuation
class
Account
0001 3000 379998 Purchaseaccount
0001 3001 379998 Purchase
account0001 3030 379998 Purchase
account
0001 3040 379998 Purchaseaccount
0001 3050 379998 Purchase
account
0001 3100 379998 Purchaseaccount
0001 7910 379998 Purchase
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
106/193
account
Double click on Purchase offsetting account (Transaction EKG)
Val.
Modif
Valuation
class
Account
0001 3000 379999 Purchase offset account0001 3001 379999 Purchase offset account
0001 3030 379999 Purchase offset account
0001 3040 379999 Purchase offset account0001 3050 379999 Purchase offset account
0001 3100 379999 Purchase offset account
0001 7910 379999 Purchase offset account
Double click on Freight clearing (Transaction FR1)
192100 Freight Clearing Account (MM)
Double click on Freight provisions (Transaction FR2)86100 Freight provision (MM)
Double click on Customs clearing (Transaction FR3)
192300 Customs Duty Clearing Account (MM)
Double click on Customs provisions (Transaction FR4)
86200 Customs provision (MM)
Double click on Purchasing freight account (Transaction FRE)379998 Purchase account
Double click on External activity (Transaction FRL)
Val.
Class Account1210 417001 Purchased services
3000 417001 Purchased services
3001 417001 Purchased services3002 417001 Purchased services
3003 417001 Purchased services
3030 417001 Purchased services3040 417001 Purchased services
3050 417001 Purchased services
3100 417001 Purchased services3200 417001 Purchased services
3300 417001 Purchased services
7900 417001 Purchased services
7910 417001 Purchased services7920 417001 Purchased services
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
107/193
Double click on Incidental costs of external activities (Transaction FRN)
415000 External procurement costs
Double click on Offsetting entry for inventory posting (Transaction GBB)
Val. Gen. Val.
Modif Modif Class Account0001 AUA 7900 895000 Factory output of production orders
0001 AUA 7910 895000
0001 AUA 7920 8950000001 AUF 3040 895000
0001 AUF 7900 895000
0001 AUF 7920 8950000001 AUF 7925 895000
0001 BSA 3100 799999 Inventory (own goods)
0001 BSA 7900 799999
0001 BSA 7920 799999
0001 BSA 7925 7999990001 INV 3000 233000 Losses - inventory variance
0001 INV 3001 2330000001 INV 3030 233000
0001 INV 3040 233000
0001 INV 3050 2330000001 INV 3100 233000
0001 INV 7900 233000
0001 INV 7920 2330000001 INV 7925 233000
0001 VAX 3000 400000 Consumption, raw material 10001 VAX 3001 400020 Materials consumed
0001 VAX 3030 400020
0001 VAX 3040 400020
0001 VAX 3050 4000200001 VAX 3100 893010 Cost of goods sold (without cost element)
0001 VAX 7900 893010
0001 VAX 7910 8930100001 VAX 7920 892000 Change in finished products inventory
0001 VAX 7925 892000
0001 VAY 3000 894025 Inventory change - foreign prod.sale w.cost elemnt0001 VAY 3001 894025
0001 VAY 3030 894025
0001 VAY 3040 8940250001 VAY 3050 894025
0001 VAY 3100 894025
0001 VAY 7900 894025
0001 VAY 7910 8940250001 VAY 7920 893015 Cost of goods sold (with cost element)
0001 VAY 7925 893015
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
108/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
109/193
0001 VNG 7920 890001
0001 VQP 3000 237000 Losses - consumption of quality control0001 VQP 3001 237000
0001 VQP 3030 237000
0001 VQP 3040 237000
0001 VQP 3050 2370000001 VQP 3100 237000
0001 VQP 7900 237000
0001 VQP 7910 2370000001 VQP 7920 237000
0001 VQP 7925 237000
0001 VQY 3000 400001 Raw materials scrapped0001 VQY 3001 400001
0001 VQY 3030 400001
0001 VQY 3040 400001
0001 VQY 3050 400001
0001 VQY 3100 4000010001 VQY 7900 890001 Scrapped material - own production
0001 VQY 7920 8900010001 VQY 7925 890001
0001 ZOB 3000 400020 Materials consumed
0001 ZOB 3001 4000200001 ZOB 3002 400020
0001 ZOB 3030 400020
0001 ZOB 3040 4000200001 ZOB 3050 400020
0001 ZOB 3100 4000200001 ZOB 7900 893025 Inventory change - additions to co. produced goods
0001 ZOB 7910 893025
0001 ZOB 7920 893025
0001 ZOF 3000 895000 Factory output of production orders0001 ZOF 7900 895000
0001 ZOF 7910 895000
0001 ZOF 7920 895000
Double click on Account-assigned purchase order (Transaction KBS)
Debit 81Credit 91
Double click on Materials management exch.rate diffs (Transaction KDM)Debit Credit
230000 280000
Double click on MM exchange rate rounding differences (Transaction KDR)Debit Credit
230000 280000
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
110/193
Double click on Material ledger frm low.levels E/R diff. (Transaction KDV)Debit Credit
230050 280050
Double click on Consignment payables KONGen.
Modif Account
PIP 169900 Accounts Payable - consigment sale
Double click on Accruals and defer.acct(material ledger) (Transaction LKW)
3000 231050
3001 231050
3030 231050
3040 231050
3050 2310503100 231050
7900 2310507920 231050 Reconciliation Material ledger
Double click on Price Differences from W/Off WIP (Transaction PRA)231001 Material ldg single-level price differences (loss)
Double click on Cost (price) differences (Transaction PRD)
General modification Valuation class Account3000 231000 Loss - price variances
3001 231000
3030 231000
3040 2310003050 231000
3100 231000
7900 231500 Expense from price difference of own goods7910 231500
7920 231500
PRA 3000 231000PRA 3001 231000
PRA 3030 231000
PRA 3040 231000PRA 3050 231000
PRA 3100 231000
PRA 7900 231500
PRA 7910 231500PRA 7920 231500
PRF 3000 231000
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
111/193
PRF 3001 231000
PRF 3030 231000PRF 3040 231000
PRF 3050 231000
PRF 3100 231000
PRF 7900 231500PRF 7910 231500
PRF 7920 231500
Double click on Price Diff. from WIP Written Off (Mat.) (Transaction PRM)
231002 Material ldg single-level price differences (loss)
Double click on Material ledger fr.low.levels price dif. PRV
231520 281520
Double click on Cost (price) differences (mater.ledger) (Transaction PRY)
0001 231520 2815200001 231099 231099 ML PRD consumption
Double click on Expense/revenue from revaluation (Transaction RAP)
231080 281080
Double click on Inv.reductions from log.inv.verification (Transaction RKA)
191120 Clearing-invoice reduction
Double click on Neutral provisions (Transaction RUE)
86300 Delivery costs provision (MM)
Double click on Unplanned delivery costs (Transaction UPF)
231600 Unplanned delivery costs
Double click on Input tax (Transaction VST)
154000 Input tax (See account assignment text)
Double click on WIP from Price Differences (Int. Acty) (Transaction WPA)
791000 Products being processed
Double click on WIP from Price Differences (Material) (Transaction WPM)
791000 Products being processed
Double click on GR/IR clearing account (Transaction WRX)
191100 Goods Rcvd/Invoice Rcvd (third party)
Double click on GR/IR clearing acct (mat. ledger) (old) (Transaction WRY)0001 191110
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
112/193
Integration Sales & Distribution and Financial Accounting (for billing)
Financial Accounting > General Ledger Accounting > Business Transaction > Integration >
Sales and Distribution > Prepare revenue account determination
Choose CustGrp/ MaterialGrp/ AcctKey
Enter the following in the table:
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
113/193
Save and go back to the previous screen.
Repeat the above steps for custgrp/account and matgrp/accout.Save.
Go back to the previous screen and choose general.
Define the following for sales organization BA01.Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
114/193
Go back to the previous screen.Choose Account key and enter the followings:
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
115/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
116/193
2.3.1.14 ACCOUNTS RECEIVABLE & ACCOUNTS PAYABLE
Customer Master
Define Account Groups with Screen Layout
Financial Accounting > Accounts Receivable and Accounts Payable > Customer Account >
Master Data >Preparation for creating customer master > Define Account Groups with
Screen Layout (Customers)
Click on New entries and enter the followings:
Account Group: BA01
Name: Wholesale customer
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
117/193
Maintain field status if needed by double clicking.
Choose Address and click on Details icon.Make necessary changes.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
118/193
Assign Number Ranges to Customer Account Groups
Financial Accounting > Accounts Receivable and Accounts Payable > Customer Account >
Master Record >Preparation for creating customer master > Assign Number Ranges toCustomer Account Groups
Acct
Group Name No Ranges
BA02 Wholesale customer ...XX
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
119/193
Vendor Master
Define Account Groups with Screen Layout
Financial Accounting > Accounts Receivable and Accounts Payable > Vendor Account >
Master Data> >Preparation for creating Vendor master > Define Account Groups with ScreenLayout (Vendors)
Click on New entries and enter the followings:
Account Group: BA02
Name: VendorMaintain field status if needed by double clicking.
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
120/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
121/193
Assign Number Ranges to Vendor Account Groups
Financial Accounting > Accounts Receivable and Accounts Payable > Vendor Account >
Master Data > >Preparation for creating Vendor master > Assign Number Ranges to VendorAccount Groups
Acct
Group Name No Ranges
BA02 Vendor XX
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
122/193
Outgoing Payment
Define Accounts for Overpayments/Underpayments
Financial Accounting > Accounts Receivable and Accounts Payable > Business Transactions> Outgoing Payment > Outgoing Payments Global Settings > Define Accounts forOverpayments/Underpayments
Enter the followings:
Chart of Accounts BA56 Chart of accounts_ABP LtdTransaction ZDI Payment differences by reason
Account 881000 (Unallowed customer discounts)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
123/193
Define Accounts for Exchange Rate Differences
Financial Accounting > Accounts Receivable and Accounts Payable > Business Transactions> Outgoing Payment > Outgoing Payments Global Settings > Define Accounts for Exchange
Rate Differences
Enter the Chart of Account BA56 and enter the accounts for exchange rate differences.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
124/193
Define Tolerances (Vendors)
Financial Accounting > Accounts Receivable and Accounts Payable > Business Transactions
> Outgoing Payment > Manual Outgoing Payments > Define Tolerances (Vendors)
Enter the company code BA55 and make new entries.
Tolerance Group: BA55
Assign the tolerance group to the company code.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
125/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
126/193
Define Accounts for Payment Differences (Manual OutgoingPayment)
Financial Accounting > Accounts Receivable and Accounts Payable > Business Transactions> Outgoing Payment > Manual Outgoing Payments > Overpayment/Underpayment > Define
Accounts for Payment Differences (Manual Outgoing Payment)
Chart of Accounts BA56 Chart of accounts ABP Ltd
Transaction ZDI Payment differences by reasonAccount 881000 Unallowed customer discounts
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
127/193
A/R & A/P Payment Program
Set Up All Company Codes for Payment Transactions
Financial Accounting > Accounts Receivable and Accounts Payable > Business Transactions
> Outgoing Payment > Automatic Outgoing Payments > Payment Method/Bank Selection forPayment Program > Set Up All Company Codes for Payment Transactions
Find the company code BA55 and set up cash discount and tolerance group.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
128/193
Set Up Paying Company Codes for Payment Transactions
Financial Accounting > Accounts Receivable and Accounts Payable > Business Transactions
> Outgoing Payment > Automatic Outgoing Payments > Payment Method/Bank Selection forPayment Program > Set Up Paying Company Codes for Payment Transactions
Find the company code BA55 and set up minimum amount for incoming /outgoing payments.
Decide how Bill of Exchange can be created choose one bill of exchange per due date option.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
129/193
Set Up Payment Methods per Country for Payment Transactions
Financial Accounting > Accounts Receivable and Accounts Payable > Business Transactions> Outing Payment > Automatic Outgoing Payments > Payment Method/Bank Selection for
Payment Program > Set Up Payment Methods per Country for Payment Transactions
Check payment methods for country code IN that it has C (Check), I (Bank transfer- incoming),
O (Overseas payments) and T (Bank transfer).
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
130/193
Set Up Payment Methods per Company Code for Payment Transactions
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >Outgoing Payment > Automatic Outgoing Payments > Payment Method/Bank Selection for
Payment Program > Set Up Payment Methods per Company Codes for Payment Transactions
Find the company code CC05 and check payment methods for the company code which has been
checked the above C, I, O and T.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
131/193
Set Up Bank Determination for Payment Transactions
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >Outgoing Payment > Automatic Outgoing Payments > Payment Method/Bank Selection for
Payment Program > Set Up Bank Determination for Payment Transactions
Find the paying company code CC05 and enter ranking order and bank accounts for payment
methods which are C, I, T and O.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
132/193
Incoming Payment
Define Accounts for Overpayments/Underpayments
Financial Accounting > Accounts Receivable and Accounts Payable >Business transactions >
Incoming Payment>Incoming Payments Global Settings > Define Accounts forOverpayments/Underpayments
Enter the chart of account CA05 and enter the followings:
Chart of Accounts BA56 Chart of accounts ABP Ltd
Transaction ZDI Payment differences by reasonAccount 881000 Unallowed customer discounts
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
133/193
Define Accounts for Exchange Rate Differences
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >
Incoming Payment > Incoming Payments Global Settings > Define Accounts for ExchangeRate Differences
Enter the chart of account BA56 and enter the accounts for exchange rate differences in the chart
of account.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
134/193
Define Tolerance Groups for Employees
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >
Incoming Payment > Manual Incoming Payments > Define Tolerance Groups for Employees
Check if the tolerance group is correctly assigned to the company code CC05 which is created inearlier stage of the implementation.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
135/193
Define Tolerances (Customers)
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >
Incoming Payment > Manual Incoming Payments > Define Tolerances (Customers)
Check if the tolerance group is correctly assigned to the company code BA55 which is createdpreviously. The company code should have 2 tolerance group assigned. One to the tolerance
group, which applies tolerance and the other which does not apply tolerance group.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
136/193
Down Payment
Define Reconciliation Account for Customer Down Payments
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >
Down Payment Received > Define Reconciliation Account for Customer Down Payments
Choose the chart of account BA55 and enter reconciliation accounts for down payment received
and down payment request.
Account type D (Customer)
Special G/L indicator F (Down payment Request)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
137/193
Click on Details icon.
Chart of Accounts BA56
Recon. SpecialAccount Account
140000(Trade Receivables-domestic) 196000 (Payment requests customers)
140010 (Trade Receivables - domestic one-time) 196000 (Payment requests customers)141000(Trade Receivables foreign) 196000 (Payment requests customers)
141010(Trade Receivables - foreign one-time) 196000 (Payment requests customers)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
138/193
Chart of Accounts BA56
Account type D (Customer)Special G/L indicator A (Down Payment)
Recon. Special
Account Account
140000(Trade Receivables-domestic) 170000 (Advanced Customer Payments)140010 (Trade Receivables - domestic one-time) 170000 (Advanced Customer Payments)
141000(Trade Receivables foreign) 170000 (Advanced Customer Payments)
141010(Trade Receivables - foreign one-time) 170000 (Advanced Customer Payments)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
139/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
140/193
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >Down Payment Made > Define Alternative Reconciliation Account for Down Payments
Choose the chart of account CA05 and enter reconciliation accounts for down payment made and
down payment request.
Chart of Accounts BA56
Account type K (Vendor)
Special G/L indicator F (Down payment Request)
Recon. Special
Account Account
160000(Trade Payable-domestic) 196300 (Payment requests Vendors)
160010 (Trade Payable -domestic one-time) 196300 (Payment requests Vendors)161000(Trade Payable- foreign) 196300 (Payment requests Vendors)
161010(Trade Payable- foreign one-time) 196300 (Payment requests Vendors)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
141/193
Repeat the above step for down payment current asset, tangible, intangible assets
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
142/193
Reconciliation Account
Define Alternative Reconciliation Account for Customers
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >
Postings with Alternative Reconciliation account > Other Special G/L Transactions > DefineAlternative Reconciliation Account for Customers
Account type D (Customer)Special G/L indicator E (Reserve for bad debt)
Click on details icon
Chart of Accounts BA56
Recon. Special
Account Account140000(Trade Receivables-domestic) 142000 (Allowance for doubtful accounts)140010 (Trade Receivables - domestic one-time) 142000 (Allowance for doubtful accounts)
141000(Trade Receivables foreign) 142000 (Allowance for doubtful accounts)
141010(Trade Receivables - foreign one-time) 142000 (Allowance for doubtful accounts)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
143/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
144/193
Account type D (Customer)
Special G/L indicator H (Security Deposit)
Chart of Accounts BA56
Recon. Special
Account Account140000(Trade Receivables-domestic) 197000 (Accounts Receivable - payment
withheld)
140010 (Trade Receivables - domestic one-time) 197000 (Accounts Receivable - paymentwithheld)
141000(Trade Receivables foreign) 197000 (Accounts Receivable - payment
withheld)
141010(Trade Receivables - foreign one-time) 197000 (Accounts Receivable - paymentwithheld)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
145/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
146/193
Define Alternative Reconciliation Account for Vendors
Financial Accounting > Accounts Receivable and Accounts Payable > Business transactions >
Postings with Alternative Reconciliation account > Other Special G/L Transactions > DefineAlternative Reconciliation Account for Vendors
Account type K (Vendor)
Special G/L indicator G (Guarantee Received)
Click on details icon.Chart of Accounts BA56
Recon. Special
Account Account160000(Trade Payable-domestic) 196400 (Guarantees vendors)
160010 (Trade Payable -domestic one-time) 196400 (Guarantees vendors)161000(Trade Payable- foreign) 196400 (Guarantees vendors)161010(Trade Payable- foreign one-time) 196400 (Guarantees vendors)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
147/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
148/193
Chart of Accounts BA56
Account type D (Customer)Special G/L indicator H (Security Deposit)
160000(Trade Payable-domestic) 197100 (Accounts Payable - payment withheld)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
149/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
150/193
2.3.1.15 BANK ACCOUNTING
House Bank
Define Housebank
Financial Accounting > Bank Accounting > Bank Accounts > Define House Banks
Define/ Check House banks and its accounts. If needed, add new entries.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
151/193
Bill of Exchange
Define Alternative Reconcil. Acct Bills/Exch. Receivable
Financial Accounting > Bank Accounting > Business transactions > Bill of Exchange
Transactions > Bill of Exchange Receivable > Post Bill of Exchange Receivable > DefineAlternative Reconcil. Acct Bills/Exch. Receivable
Account type D (Customer)Special G/L ind. B (Bill of exchange received)
Chart of Accounts BA56
Recon. SpecialAccount Account140000(Trade Receivables-domestic) 126000 (Bills of exchange receivable)
140010 (Trade Receivables - domestic one-time) 126000 (Bills of exchange receivable)
141000(Trade Receivables foreign) 126000 (Bills of exchange receivable)141010(Trade Receivables - foreign one-time) 126000 (Bills of exchange receivable)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
152/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
153/193
Account type D (Customer)
Special G/L ind. S (Check/ Bill of exchang)
Chart of Accounts BA56
Recon. Special
Account Account140000(Trade Receivables-domestic) 196200 (Contingent claim for bills of
exchange)
140010 (Trade Receivables - domestic one-time) 196200(Contingent claim for bills of exchange)141000(Trade Receivables foreign) 196200 (Contingent claim for bills of
exchange)
141010(Trade Receivables - foreign one-time) 196200(Contingent claim for bills of exchange)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
154/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
155/193
Define Alternative Reconciliation. Account Bills of Exchange Payable
Financial Accounting > Bank Accounting > Business transactions > Bill of Exchange
Transactions > Bill of Exchange Payable > Create Bill of Exchange Payable > DefineAlternative Reconcil. Acct Bills/Exch. Receivable
Account type K (Vendor)
Special G/L ind. S (Check/ Bill of exchange)
Chart of Accounts BA56
Recon. Special
Account Account
160000(Trade Payable-domestic) 196200 (Contingent claim for bills of exchange)160010 (Trade Payable -domestic one-time) 196200 (Contingent claim for bills of exchange)
161000(Trade Payable- foreign) 196200 (Contingent claim for bills of exchange)161010(Trade Payable- foreign one-time) 196200 (Contingent claim for bills ofexchange)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
156/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
157/193
Define Alternative Reconcil. Account for Reverse Bill/Exch
Financial Accounting > Bank Accounting > Business transactions > Bill of Exchange
Transactions > Check/Bill of Exchange > Check/Bill of Exchange Transactions Issued >Define Alternative Reconcil. Account for Reverse Bill/Exch.
Account type K (Vendor)
Special G/L ind. S (Check/ Bill of exchange)
Chart of Accounts BA56
Recon. Special
Account Account
160000(Trade Payable-domestic) 196200 (Contingent claim for bills of exchange)160010 (Trade Payable -domestic one-time) 196200 (Contingent claim for bills of exchange)
161000(Trade Payable- foreign) 196200 (Contingent claim for bills of exchange)161010(Trade Payable- foreign one-time) 196200 (Contingent claim for bills ofexchange)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
158/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
159/193
Define Alternative Reconcil. Account for Reverse Bill/Exch
Financial Accounting > Bank Accounting > Business transactions > Bill of ExchangeTransactions > Check/Bill of Exchange > Check/Bill of Exchange Transactions Received >
Define Alternative Reconcil. Account for Reverse Bill/Exch.
Account type D (Customer)
Special G/L ind. B (Bill of exchange receivable)
Chart of Accounts BA56
Recon. Special
Account Account140000(Trade Receivables-domestic) 126000 (Bills of exchange receivable)
140010 (Trade Receivables - domestic one-time) 126000 (Bills of exchange receivable)141000(Trade Receivables foreign) 126000 (Bills of exchange receivable)141010(Trade Receivables - foreign one-time) 126000 (Bills of exchange receivable)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
160/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
161/193
Account type D (Customer)
Special G/L ind. S (Check/ Bill of exchange)
Chart of Accounts BA56
Recon. Special
Account Account140000(Trade Receivables-domestic) 196200 (Contingent claim for bills of
exchange)
140010 (Trade Receivables - domestic one-time) 196200(Contingent claim for bills of exchange)141000(Trade Receivables foreign) 196200 (Contingent claim for bills of
exchange)
141010(Trade Receivables - foreign one-time) 196200(Contingent claim for bills of exchange)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
162/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
163/193
2.3.2 CO
2.3.2.1 CONTROLLING AREA
Maintain controlling area.
Create controlling area to establish cost centre standard hierarchy
Enterprise Structure -> Definition-> Controlling-> Maintain controlling area-> MaintainControlling Area
Click onNew Entries:
Controlling Area: BA55(CO Area = CCode)Name:ABP Ltd
Assignment Control: Controlling area same as company code
Currency type: 10Currency:INR
Chart of Accounts:BA56
Fiscal Year Variant:Z1
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
164/193
Assign company code to controlling area
Enterprise Structure -> Assignment -> Controlling-> Assign company code to controlling area
Highlight oncontrolling area BA55. Click onAssignment of company code BA55. Click on
New entries. EnterBA55.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
165/193
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
166/193
2.3.2.2 COST CENTRE ACCOUNTING
Activate cost centre accounting in controlling area
Controlling -> Cost centre accounting -> Activate cost centre accounting in controlling area
Highlight oncontrolling area CC05. Click onActivate components/control indicators. Click
onNew entries. Enter the following:
Fiscal year:2010Cost centres: Component active
Order Mgt: Component active
Commit Mgt: Component activeActivity Based costing: Component active for parallel and integrated calculation
Insert tick (activate) onall components
Insert tick onAll currencies and Variances
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
167/193
2.3.2.3 STANDARD HIERARCHY
Enter Standard Hierarchy
Controlling -> Cost centre accounting -> Activate cost centre accounting in controlling area
Highlight oncontrolling area BA55. Click onDetails
You will notice an additional item called CCtr Std Hierarchy under other settings. Insert the
valueBA55and enter. Click on Yesto a message Should system CC05 be created as a standardhierarchy?
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
168/193
2.3.2.4 COST CENTRE
Create cost centre standard hierarchy
Controlling -> Cost center accounting-> Master Data-> Cost center-> Define standardhierarchy.
Normally your standard hierarchy is selected by default. If it is different, to choose your standard
hierarchy for the controlling area BA55, use the following menu path:
Extras => Transport standard Hierarchy
Enter thecontrolling area BA55. Enter.
In your standard hierarchy/controlling Area, choose CreateCost centre. Enter basic data.
Cost Centre:BA01
Name:Production Centre 1
Description: Tyres
Person Responsible:51038-01
Cost Centre Category: 1 (Production)
In the next screen, Enter
Business Area:BA01Functional Area:BA55 (ABP Ltd Manufacturing)
Currency:INR
Repeat the above steps for other Cost Centres and Make 4 cost centres BM01, BM02, BM11,
BM22
Cost Centre:BA11Name:Production Centre 2
Description:Productioncentre for radial tyres
Person Responsible:51038-01
Cost Centre Category: 1(Production)Business Area:BA01
Functional Area:BA55 (ABP Ltd Manufacturing)Currency:INR
Cost Centre:BA02Name:Production Centre 1
Description: Tubes
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
169/193
Person Responsible:51038-01
Cost Centre Category: 1 (Production)
Business Area:BA02
Functional Area:BA55 (ABP Ltd Manufacturing)
Currency:INR
Cost Centre:BA22
Name:Production Centre 1
Description: Tubeless tyres
Person Responsible:51038-01
Cost Centre Category: 1 (Production)
Business Area:BA02Functional Area:BA55ABP Ltd Manufacturing)
Currency:INR
Save to activate the cost centres created. If you still see the status as red, move back and come
back to see the standard hierarchy. You will notice the status being active (green).
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
170/193
2.3.2.5 COST ELEMENTS
Define Cost Elements
Controlling -> Cost Element accounting-> Master Data-> Cost Elements -> Create CostElements
Choose Create Primary Cost Element
Enter Controlling Are BA55
Enter
Enter Cost Element 890000 and validate date.
Choose Cost Element Category > Choose 1 (Primary costs/Cost-reducing Revenues)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
171/193
Save.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
172/193
2.3.2.6 NUMBER RANGES FOR CO DOCUMENTS
Set Number Ranges for CO documents
Controlling -> General Controlling -> Organization -> Maintain Number Ranges forControlling Documents
Enter Controlling Area BA55 and click Copy icon.Copy from Co Area 1000 to BA55.
Accept a message. Enter.
Click Display Interval to check the number ranges
Your screen will be the following:
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
173/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
174/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
175/193
CopyFrom plant: 1000To plant: BA01
The above process is repeated for the second plant (BA02), the third plant (BA03) and the fourth
plant (BM04).
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
176/193
Maintain Storage Location
Enterprise Structure -> Definition -> Materials Management -> Maintain Storage Location
Enter Work Area:BA01
All storage locations will have been copied from plant 1000 to plant BM01. Select all and then
deselect the first 2 storage locations. Delete the selected storage locations.
Modify as follows:
0011 Semi Finished
0012 Finished
Repeat the above process for maintaining storage locations (Semi-Finished and Finished) forWork Area: Plant BA02, BA03, BA04.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
177/193
Maintain Purchasing Organization
Enterprise Structure -> Definition -> Materials Management -> Maintain PurchasingOrganization
New Entries defined for Purchasing Organisations:
BA01 CN Purchasing OrganisationBA02 KL Purchasing Organisation
BA03 KA Purchasing Organisation
BA04 AP Purchasing Organisation
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
178/193
Assign Plant to Company Code
Enterprise Structure -> Assignment -> Logistics General -> Assign Plant to Company Code
Click on Assign to assign the plants BA01, BA02, BA03, BA04 to the company code BM02.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
179/193
Create Purchasing Groups
Materials Management -> Purchasing -> Create Purchasing Groups
Create purchasing groups:
VPG: Vendor Proc Grp
LPG: Local Proc Grp
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
180/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
181/193
Maintain company code for Materials Management
Logistics-General -> Material Master -> Basic Settings -> Maintain Company Codes for
Materials Management
Against the company code BA55, change the period to current period (current year and currentmonth) i.e. June, 2010.
Note: Before you start creating any material master in your plant/company code, you need to
perform the above step to initialize the accounting period to the current period. Otherwise, once
material master is created, and if the accounting period is in the past, then you need to close all
the periods by closing one month at a time to move forward to the current period. To close one
month at a time, you can use the following menu path:
(To know the current period of your material master (MM), you need to check the Accounting
view of your material master and note down the period.)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
182/193
To close the period:
Logistics -> Materials Management -> Material Master -> Other -> Close Period (Transaction
Code: MMPV)
From Company Code:BA55To Company Code:BA55Period:Next monthFiscal Year: Suitable year
Execute.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
183/193
1.5.2 ACCOUNT GROUP-VENDOR
Logistic-General ->Business Partner ->Vendor ->Control ->Define Account Groups and Field
Selection(Vendor)
If this is done in FI module, the account groups should exist.Check the followings.
BA01 VendorsBA02 Vendors-others
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
184/193
1.5.3 PARTNER FUNCTION
Material Management -> Purchasing->Partner Determination->Partner Roles->Define
Permissible Partner Roles per Account Group
Enter the followings:
VN Vendor BA01 Vendors
VN Vendor BA02 Vendors-others
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
185/193
1.5.4 VALUATION AREA
Materials Management> Valuation and Account Assignment> Account Determination>
Account Determination Without Wizard> Group Together Valuation Areas
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
186/193
2.
1. 6 PP
2.6.1 ENTERPRISE STURCTURE
Create work centre
Logistics => Production => Master Data => work centre => work centre => Create
(transaction Code: CR01)
Plant: BA55
Work centre: BA01
Work centre category: 0003 (labour)
Enter
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
187/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
188/193
2.6.2 MASTER DATA
Create a standard routing for the finished product A-IPBW
Logistics => Production => Master Data => Routings => Routings => Standard Routings =>
Create (transaction Code: CA01)
Material: A-IPBW_01
Plant: BA01
In the next screen, enter:
Usage: 1 (Production)
Status: 4 (General Released)
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
189/193
Create a Bill of Material (BOM) for A-IPBW_01
Logistics => Production => Master Data => Bills of Materials => Bill of Material =>
Material BOM => Create (transaction Code: CS01)
Material: Tyres & Tubes
Plant: BA01
BOM usage: 3
Alternative BOM: 1
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
190/193
Activate MRP
Material Requirements Planning> Planning File Entries> Activate MRP and Set Up Planning
File
Click on MRP
Find plants BA01, BA02, BA03 and BA04 and tick on Activate Requirements planning.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
191/193
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
192/193
Conclusion
Thus The Implementation of SAP ERP for ABP Limited has been done through
various phases of ASAP Methodologies and it is configured based upon the
companys requirements. Also the requirements could be satisfied with reference to
testing Sales and distribution processes. Unit Testing has been done for various
business transactions.
-
7/25/2019 Sap Implementation of Fi Co Reallife Project
193/193
BIBLIOGRAPHY
WWW.SAPHELP.COM
WWW.SAPLIBRARY.COM
WWW.UAC.SAP.COM
WWW.WIKIPEDIA.COM
WWW.ONESTOPSAP.COM
http://www.saphelp.com/http://www.saphelp.com/http://www.saplibrary.com/http://www.saplibrary.com/http://www.uac.sap.com/http://www.uac.sap.com/http://www.wikipedia.com/http://www.wikipedia.com/http://www.onestopsap.com/http://www.onestopsap.com/http://www.onestopsap.com/http://www.wikipedia.com/http://www.uac.sap.com/http://www.saplibrary.com/http://www.saphelp.com/