Southwest Power Pool, Inc. SPP-ITO LG&E/KU Stakeholder Meeting Agenda
November 18, 2009 Hyatt Regency Louisville, 320 W Jefferson Louisville, KY 40202
• A G E N D A • 8:30 AM – 5:30 PM (Breakfast 7:30 – 8:30)
Relationship-Based • Member-Driven • Independence Through Diversity
Evolutionary vs. Revolutionary • Reliability & Economics Inseparable
Dial in Access: 1-866-760-3906 Participant Code: 4429588 7:30 - 8:30 Breakfast
Introductions & Overview Katherine Prewitt (Manager ITO Contract Services)
Action Items from Spring 2009 Stakeholders ………….….…………………………Katherine Prewitt (ITO)
ITO Operations …………………………………………………………………………..Jonathan Hayes(ITO)
• Operation Data
o Tariff Admin Statistics
o Scheduling Statistics
o TLR Statistics
• AFC/ATC
o Statistics/Metrics
ITO – OATI
• Implementation ..………………………………..……………….………Katherine Prewitt (ITO)
• OATI OASIS Navigation …………………………………………….…Jonathan Hayes (ITO)
ITO Tariff & LGI Studies ……………………………..………...………………………Jonathan Hayes (ITO)
• SIS Metrics
• GI Queue
ITO Review of 2008 TEP …………….………………………………………..………….David Kelley (ITO)
How the Flowgate Methodology Works …………………………………….………Nate Schweighart (TVA)
Open Forum – Stakeholder Feedback & Wrap-Up ……………………..……………Katherine Prewitt (ITO)
Adjourn/Break
Stakeholder Planning Committee (SPC) Meeting
- Review ATC between LGEE and MISO …………………..……Larry Monday (E.ON)
1
SPP Presentation -ITO
HELPING OUR MEMBERS WORK TOGETHERTO KEEP THE LIGHTS ON… TODAY AND IN THE FUTURE
Fall 2009 Stakeholders MeetingNovember 18, 2009
Prepared by:Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Katherine Prewitt
Introductions & Overview
2
November 18, 2009
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
2
Introductions & Overview
Logistics
Independent Transmission Organization
Logistics♦ Safety♦ Breaks/Lunch♦ Restrooms♦ Silence Cell Phones and Blackberries
3
♦ Name & Company when Speaking
Introductions
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Overview of MeetingAction Items from Spring 2009 Stakeholders
ITO Operations PresentationITO Operations Presentation
ITO - OATI Implementation & Navigation
Break
ITO Tariff & LGI Studies
ITO Review of 2008 TEPITO Review of 2008 TEP
Lunch in Belmont Room
4
3
Overview of MeetingHow the Flowgate Methodology Works
Open ForumOpen Forum
Adjourn/Break
Stakeholder Planning Committee (SPC) Meeting
5
Independent Transmission Organization
Katherine Prewitt
Open Action Items from Spring 2009 Stakeholder Meeting
6
November 18, 2009
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
4
Open Action ItemsSubmit requests for different statistics at future stakeholders meetings to Katherine Prewitt or Keith Yocum
Independent Transmission Organization
meetings to Katherine Prewitt or Keith Yocum
ITO will review the TLR data and the most frequently limited flowgates and report on parameters of how the data for the flowgates was retrieved
ITO will work with Larry Monday to ensure the data he needs for billing is available or work out an alternative plan
ITO will verify the format of the new ATC data postings due to th f t th t t i th i iti
7
the fact that some customers are using them in exiting processes
ITO will work with E.ON concerning how the data for the new OATI project will be retrieved
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Open Action ItemsE.ON stated that they would check into the major causes of the E.ON Rate increases for 2009 and report back to the group
Independent Transmission Organization
E.ON Rate increases for 2009 and report back to the group
ITO will review the proposed DNR\NITS process changes and NITS Application changes based on the feedback from the Stakeholders
ITO and E.ON committed to review the GI process to look for ways to better the process (what part(s) of the study are taking the longest)
ITO ill b tt d fi h t d i d d f th SGI
8
ITO will better define when a study is needed for the SGI process
ITO will conduct more research into the differences between the LGI and SGI studies
E.ON will facilitate the first SPC meeting per Attachment KRelationship-Based • Member-Driven • Independence Through Diversity
Evolutionary vs. Revolutionary • Reliability & Economics Inseparable
5
Independent Transmission Organization
Questions?
9
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Contact SPPITO
Independent Transmission Organization
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
p g
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
1
SPP Presentation -ITO
HELPING OUR MEMBERS WORK TOGETHERTO KEEP THE LIGHTS ON… TODAY AND IN THE FUTURE
Spring 2009 Stakeholders MeetingNovember 18, 2009
Prepared by:Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Jonathan Hayes
ITO – Operations
2
Jonathan Hayes
November 18, 2009
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
2
ITO Operations
Operational Data
Independent Transmission Organization
♦ Tariff Administration
♦ Scheduling
♦ TLR Statistics
Available Transfer Capacity
♦ Daily Firm Statistics
♦ Hourly Non-firm Statistics
3
Stakeholder Questions
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Tariff Administration
Reservations
Independent Transmission Organization
♦ 3227 Total Reservations processed
♦ 2847 TSRs Confirmed
♦ 6 TSRs in Study
♦ 149 TSRs Refused or Declined
225 TSR Withd R t t d A ll d I lid Di l d
4
♦ 225 TSRs Withdrawn, Retracted, Annulled, Invalid, Displaced or Superseded
Additional reservation statistics can be found at http://www.spp.org.
3
SchedulingThe ITO processed 4178 e-Tags from April 2009 through September 2009
Independent Transmission Organization
September 2009.
5
TLR StatisticsTLR(s) were called on LGEE flowgates over the 6 month period. Please refer to the charts below for more detailed information.
6
*Note the TLR information was provided by the Reliability Coordinator (TVA).
4
Daily Firm (Day Ahead) ATC MetricsBelow are the most frequently limited (ATC ≤ 0) flowgates for Daily
Independent Transmission Organization
Firm
♦ River Queen Tap-Earlington North 161 (flo) Green River-Corydon Tap 161
♦ Livingston-Earlington North 161 (flo) Livingston-Crittenden 161
♦ Albion - Crossville 138 (flo) Newton - Xenia 345
♦ Hardinsburg-Hardin County 138 (flo) Daviess Co-Hardin Co 345 kV
♦ Alcalde-Elihu 161
7
♦ Alcalde Elihu 161
Analysis of the Daily Firm ATC Metrics can be found at http://www.spp.org.
Hourly Non-Firm ATC Metrics
Below are the most frequently limited (ATC ≤ 0) flowgates for Hourly
Independent Transmission Organization
q y ( ) g yNon-Firm
♦ River Queen Tap-Earlington North 161 (flo) Green River-Corydon Tap 161
♦ Livingston-Earlington North 161 (flo) Livingston-Crittenden 161
♦ Hardinsburg-Hardin County 138 (flo) Daviess Co-Hardin Co 345 kV
♦ Albion - Crossville 138 (flo) Newton - Xenia 345
8
♦ Grahamville-S Paducah 161 kV (flo) Shawnee-Marshall 500 kV
Analysis of the HNF ATC Metrics can be found at http://www.spp.org.
5
Questions
Independent Transmission Organization
9
Contact SPPITO
Email: [email protected]
Independent Transmission Organization
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
p g
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
6
ITO – OATI
Independent Transmission Organization
Katherine Prewitt
•Implementation•OATI OASIS Navigation
11
Jonathan Hayes
November 18, 2009Relationship-Based • Member-Driven • Independence Through Diversity
Evolutionary vs. Revolutionary • Reliability & Economics Inseparable
OASIS Navigation Commonly Asked Questions
♦ How do I get to the ATC postings?
♦ How can I view the next day/next month ATC postings?
♦ How can I save AFC/ATC reports posted OASIS?
12
♦ How do I run scenarios to determine if ATC is available?
7
Available ATC (pre request)
13
14
8
15
Accessing the ATC postings
G t ti iGo to www.oatioasis.comLogin using your certificate/user ID/passwordClick on the LGE/KU logoClick on the reservations linkClick on AFC/Flowgate ReportsMake sure LGEE is selected from the drop downClick on Summary Reports (FG/Path Summary Page)Set your filter to: Provider: LGEE, Priority: ALL, Init. Date: Today, CalcType: EFFATC Horizon: Select a horizon (or choose all); click Enter to
16
CalcType: EFFATC, Horizon: Select a horizon (or choose all); click Enter to populate the reportsNote: The most recently created reports will populate at the bottom of the pageClick on the Report link to view the report. Priority 7 is for firm. Priority 0 is for non-firm.
9
Viewing Next Day/Next Month Postings
F ll th t t th FG/P th SFollow the same steps to access the FG/Path Summary pageFor Next Day Postings♦ Set your filter as previously recommended and choose Daily
Planning from the Horizon drop down; click Enter♦ The reports will populate; scroll to the bottom for the most
recent reports♦ Click on the report link corresponding to the next day
17
For next Month Postings♦ Set your filter the same but choose Monthly Study♦ Scroll to the bottom of the page and select the report link
corresponding to the next month
Saving Reports
O ATC b li ki h li kOpen up an ATC report by clicking on the report link
Select all of the data fields you wish to export; right click and select Copy
Open up an instance of Excel
Select the field A1. Paste the data into the Excel worksheet.
18
10
Scenario Analyzer
19
Scenario Analyzer
F th AFC/Fl t tFrom the AFC/Flowgate report page:♦ Click on the Scenario Analyzer link♦ Enter your scenario as you would create a TSR (select source/sink,
POR/POD, etc)♦ Select Enter Scenario♦ Make sure the queue position drop down selected is LAST♦ Select Check Capacity ♦ If all calculations pass Effective ATC is available for the scenario
entered
20
♦ Note: Yearly scenarios (or requests outside the 18 month operating window) would not provide a valid solution
11
Filtering for Requests
G t ti iGo to www.oatioasis.comLogin using your certificate/user ID/passwordClick on the LGE/KU logoClick on the reservations box
21
Questions
Independent Transmission Organization
22
1
SPP Presentation -ITO
HELPING OUR MEMBERS WORK TOGETHERTO KEEP THE LIGHTS ON… TODAY AND IN THE FUTURE
Spring 2009 Stakeholder MeetingNovember 18, 2009
Prepared by:Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Jonathan Hayes
ITO – Tariff Studies
2
November 18, 2009
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
2
Outline
SIS Metrics
Independent Transmission Organization
SIS MetricsFS MetricsStudy ContactsQuestions
3
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
SIS Metrics – 2009 Q2 and 2009 Q3
New SISA delivered 8
Independent Transmission Organization
New SISA delivered – 8New SISA executed – 4SIS Completed – 4SIS Completed Late – 0
4
SIS Avg. Completion time – 59
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
3
FS Metrics – 2009 Q2 and 2009 Q3
New FSA delivered 0
Independent Transmission Organization
New FSA delivered – 0New FSA executed – 0FS Withdrawn - 0FS Completed – 2
5
FS Completed Late – 1FS Avg. Completion time – 59
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Study Contacts
The ITO has revised it list of
Independent Transmission Organization
The ITO has revised it list of personnel to contact for the SIS Process. ♦ The new contact for the SIS
Studies is Chris MannPl CC B d Fit d B
6
♦ Please CC Brenda Fite and Bryce Bowie on all correspondence regarding the SIS Studies.
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
4
Independent Transmission Organization
Questions?
7
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Contact SPPITO
[email protected]@ pp g
Independent Transmission Organization
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
p g
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
1
SPP Presentation -ITO
HELPING OUR MEMBERS WORK TOGETHERTO KEEP THE LIGHTS ON… TODAY AND IN THE FUTURE
Fall 2009 Stakeholders MeetingNov 18, 2009
Prepared by:Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Nov 18, 2009
ITO – LGI Studies
2
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
2
Topics
Independent Transmission Organization
Update
Linear Queue
Achievements
3
Update / Coordination
♦ 7 Active requests (end of 3RD Quarter)
Independent Transmission Organization
q ( Q )
♦ Public info (Oasis)
New Location for study reports
4
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
3
Public Info Update Generation
Interconnectio Nearest Town State CA In-Service Date CAPACITY (MW) Type STATUS
Independent Transmission Organization
Interconnection Number or County State CA (proposed) CAPACITY (MW) Type STATUS
LGE-GIS-2007-004
Henderson County KY LGEE 3/31/2011 640.0
Combined Cycle
RESTUDY SET TO BEGIN
LGE-GIS-2008-001 Wise County VA LGEE 12/1/2011 150.0 Wind PENDING
LGE-GIS- 2008 – 002 Ohio County KY LGEE 8/01/2010 5.4 Small Gen
WAITING FOR QUEUE POSITION
LGE-GIS-2008-003 Sulphur KY LGEE 8/1/2010 9.0 Small Gen
WAITING FOR QUEUE POSITION
LGE-GIS-2008-004 Stanford KY LGEE 8/1/2010 5.4 Small Gen
WAITING FOR QUEUE POSITION004 Stanford KY LGEE 8/1/2010 5.4 Small Gen POSITION
LGE-GIS-2009-001 Paducah KY LGEE 5/1/2010 123.4
Pratt & Whitney
FT-8 Swift Pacs SIS REQUESTED
LGE-GIS-2009-002 Green River KY LGEE 560.0
Combined Cycle
REQUEST RECEIVED
5
Linear Queue
LGIP and SGIP one queue
Nature of linear queueRestudy
6
4
Achievements
Independent Transmission Organization
Will be executing power flow restudy for LGE-GIS-2007-004.
Will be executing power flow for LGE-GIS-2008-001
Running Enfuzion
Business Analysts
7
Questions/Comments
??8
5
Contact SPPITO
Email: [email protected]
Independent Transmission Organization
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
p g
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
1
SPP Presentation -ITO
HELPING OUR MEMBERS WORK TOGETHERTO KEEP THE LIGHTS ON… TODAY AND IN THE FUTURE
Fall 2009 Stakeholder MeetingNovember 18, 2009
Prepared by:Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
David Kelley
Transmission Expansion Planning
2
November 18, 2009
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
2
E.ON’s 2008 TEP
Independent Transmission Organization
2008 TEP based on summer and winter peak models for 2009 2013 and 2018
Projects in 2007 TEP 182Projects Completed -29
Projects Delayed or Eliminated -41
Projects Accelerated 24
models for 2009, 2013, and 2018
33
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
j
Projects Added 32
Projects in 2008 TEP 168
Powerflow Analysis
Contingency Analysis:
Independent Transmission Organization
N-1: Loss of a single generator, line, or transformerN-1-1: Loss of a generator AND line or generator AND transformerLoss of two generators
Results analyzed against criteria provided in planning guidelines
Thermal issues: Flow above 100 percent of applicable normal or contingency rating
4
or contingency ratingVoltage issues: Voltage below 94 percent or above 105 percent nominal during normal conditions and below 90 percent and above 105 percent nominal during contingency conditions
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
3
Issue Solutions
Switching Procedures
Independent Transmission Organization
Coordination
Problem Resolution
Expansion Plan ProjectsProject Timing
Modeling
5
Modeling
Mitigation Plans for Delayed Projects
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Powerflow Analysis Results
3 Thermal Issues
Independent Transmission Organization
69 kV system
Generally out-year issues
3 Voltage IssuesHigh Voltage
All di ti i
6
All are coordination issues
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
4
Powerflow Analysis Results
Cynthiana Sw Station – Renaker (69 kV)
Independent Transmission Organization
2018 Summer Thermal Violation (109%)
Due to loss of Paris 138/69 kV Transformer
Coordination with EKPC
7
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Powerflow Analysis Results
American Ave - Picadome (69 kV)
Independent Transmission Organization
2013 Summer Thermal Violation (101%)
Due to loss of Higby Mill 138/69 kV Transformer
2009 TEP Solution
8
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
5
Powerflow Analysis Results
Lakeshore – Bryant Rd Tap (69 kV)
Independent Transmission Organization
2018 Summer Thermal Violation (101%)
Due to loss of Loudon Ave – Avon 138 kV line
9
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Powerflow Analysis Results
Lebanon Jct (161 kV)
Independent Transmission Organization
Appears in each season except 2018-19 Winter
Voltage violation between 1.05 – 1.06 p.u.
Due to loss of both 138/161 kV transformers at Paddys Run
Isolates bus from E.ON
10
TVA Coordination
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
6
Powerflow Analysis Results
South Paducah (69 kV)
Independent Transmission Organization
2013-14 Winter Voltage Violation (1.051 p.u.)
Due to loss of Livingston Co. – S. Paducah 161 kV line
DOE Coordination
11
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Powerflow Analysis Results
Grahamville 161 kV and 69 kV
Independent Transmission Organization
2013-14 & 2018-19 Winter Voltage Violation (1.051 p.u.)
Due to loss of Westvaco – Wickliffe 69 kV line
DOE Coordination
12
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
7
TEP Coordination
RC Coordination
Independent Transmission Organization
♦ TEP presented to TVA as the RC in February 2009
Stakeholder Input♦ Any additional stakeholder questions or concerns
will be considered for the next 30 days♦ Final report will be prepared and posted by
December 31, 2009
1313
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Questions?
1414
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
8
Contact SPPITO
http://spp.issuetrak.com/Login.asp
Independent Transmission Organization
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
p g